EOT Is Granted To A Contractor As A Compensation For A Delay'
EOT Is Granted To A Contractor As A Compensation For A Delay'
EOT Is Granted To A Contractor As A Compensation For A Delay'
Time for Completion is calculated FROM the Commencement Date (i.e. EXCLUDING
THE THICKNESS of the Commencement Date)
The date of ‘Substantial Completion’ is mentioned in the “Taking Over Certificate:
issued to the Contractor (by the Engineer)
Substantial Completion
Not the full completion. But as the name suggests it is the level of completion achieved
that permits the intended use of the building (or infrastructure).
E.g. – A hotel building completed except for the painting of ceiling of staff accommodation – the hotel can be functioned
without the ceiling painting of the staff accommodation.
7. The Engineer must look into depths of the relevant delaying event(s) to
check whether the Contractor is GENUINLY entitled (or not entitled) for the
EOT.
8. Amount of EOT can be ‘zero’ (0) - If the Engineer finds that the Contractor is
NOT entitled for the EOT.
Delaying categories
The Contractor has always been burdened with the responsibility of taking “mitigation
action” against any delay that occur.
It does not matter whether the delay is caused by the Contractor or the Employer.
The Contractor cannot simply sit there and is doing nothing to minimise the effects of
delay…
When considering an EOT claim raised by the Contractor, the Engineer will essentially
look into the matter to check if the Contractor has taken mitigation action(s) in order
to minimise the loses due to delay. If the Contractor has not taken any such actions,
there is a great chance that the Engineer will state that “you Mr. Contractor, are not
fairly entitled to be granted with an extension of time, ultimately rejecting his claim for
EOT.
The Contractor in proving himself will need to put up two separate “delay analyses”.
1. General Analyses of delay on “As Planned Programme”
The impact of the delay is depicted on the “As Panned Programme”, which is
the “base line” programme. Total delay is shown…
2. Final Delay Impact Analysis
The Contractor will take a copy of the above, and will superimpose the mitigation
action(s) that he has taken in order to mitigate the effects of the delay. Then the
recovery of time due to such mitigation actions is clearly visible to the Engineer.
However, there could be a “residual delay” for which he could not recover via
the mitigation action(s). For that bit of the delay, the Engineer will provide
the Contractor with an extension of time.
Even though someone can see that the Contractor has been given
solid chances in claiming for EOTs, the discretion has been given
to the Engineer in deciding whether the Contractor is fairly entitled
for the EOT.
Definition of Nominated
59.1 (d)
Sub Contractors
Damage to Works by Special
65.3 (a)
Risks
Contractor’s Entitlement
69.4 (b)
to Suspend Work
Easiest of clauses against which the determination of entitlement and the additional
payment are highlighted in the Green above. Because the entitlement naturally comes
under Sub-clause 44.1 (b). The type of additional payment also clearly provided within
the clause itself.
If the Contract does not clearly state that the Contractor is entitled for extension of
time and/or additional payment, it is a bit difficult to determine…
TESTS SHALL BE APPLIED…Tests is to check if a particular delay event could
be “fitted into” any of the 5 categories mentioned under Sub-Clause 44.1, i.e. a,
b, c, d & e
The delaying effect of variations shall be taken into account by the Contractor and
the Engineer and should be claimed for EOTs, additional payments accordingly.
Clauses giving rise to variations / varied works (so for the associated delays) are
highlighted in Pink/Orange above.
A delay caused by a variation / varied work…The entitlement for the Extension of time
comes under Clause 44.1 (a). The additional payment shall be determined as a part
of the valuation of the variation under Sub-Clause 52.1 (Direct Valuation) and Sub-
Clause 52.2 (Indirect Valuation)
Almost all cases of delays / prolongation, the affects work items are “Time-related”
items. Considering the original ‘Time for Completion’ (duration), the Contractor prices
his overheads, especially the Site Overhead, i.e. Supervision / Staff Salaries, Site
Office Maintenance, Tower Crane…and the like. He includes rates & prices taking
into account the total original duration of the project / or the original duration for which
the resource is required.
When a delay induced by a variation prolongs the project duration, the Contractor
would say that…
the nature and/or amount (i.e. the quantum but not the commercial value) of the
variation that the Engineer has instructed rendered his rates & prices
inappropriate or inapplicable to value the variation…
In such a case, he would issue a notice to the Engineer within 14 days from the
instructions to the variation asking for varied rates and/or prices to value the variation
pursuant to Sub Clause 52.2 (a).
In a case where there is NO preliminaries bill section available in the Contract,
generally the cost of preliminaries has been distributed across the direct work items.
If a variation issued delays the project, the Contractor would say that all if not most of
rates & prices have become inapplicable or inappropriate. He would require a fixed
mark-up on all or several rates as the compensation. His claims would be made
pursuant to Sub-clause 52.1 (a).
However, regardless of having a Preliminaries bill or not, the ideal approach
would be to claim for an “extra payment” pursuant to Sub-clause 52.1 (a),
properly calculated based on contemporary site records that the Contractor
maintains.
An interesting scenario…
The Employer creates a delay…assume that the Employer makes a delayed
appointment of a Nominated Sub-Contractor or a third-party contractor appointed by
the Employer delays the progress on site, the Contractor can claim for extension of
time pursuant to Clause 44.1 (d). But what if there is no provision in the Contract to
claim prolongation cost?
The Contract includes the “Expressed terms” that regulates the performance of the contract.
The “LAW” governing the Contract includes the “implied terms” that regulates the performance
of the contract. If in any case, the Contract does not include a necessary provision (as an
expressed term), the governing LAW comes in to play in order to fill the gap…
In many jurisdictions around the world, provides that a party to a contract shall NOT
prevent the other party from performing the obligations under the Contract.
In the above case, by appointing a Nominated Sub-contractor late or delaying the
Contractor’s progress, the Employer has ‘prevented’ the Contractor from performing
his obligations under the contract. By doing so, the Employer is in “breach of the
contract”. The Contractor can claim damages! Damages are what, the ‘prolongation
costs’ in this case…
However, there is something which is not quite right…isn’t it?
The contract was being performed…everything was going as intended until the
unfortunate incident about the Nominated Sub-contractor. Shall the Employer be sued
by the Contractor always to get the prolongation costs in all of this kind of events that
happen always? No…!
The FIDIC includes the necessary provision in place…
A blanket clause wrapping up Contractor’s all other entitlements to cost and also the
Contractor’s entitlements which are NOT expressly written in the contract but exist in
the governing law which the Engineer is DUTY BOUND to look at when determining
Contractor’s entitlement to the costs…
“Notwithstanding any other provision of the contract, if the Contractor intends to claim
any additional payment pursuant to any clause of these conditions OR OTHERWISE,
he shall give a notice of his intention to the Engineer with a copy to the Employer
within 28 days after the event giving rise to the claim has first arisen.”
IMPORTANT!!!
The Governing law applies only when a party to the
contract is in breach of the contract
1st Test:
To check if the entitlement for cost is mentioned in the clause it self
2nd Test:
To check if any other clause gives the entitlement for cost in the Contract.
3rd Test:
To check if the sub-clause 52.2 (a) provides the entitlement as varied rate / prices or
extra payment.
4th Test:
To check if the whole Contract is silent? The provision in the Law or customs in use
in the country? [Only applies when a party is in breach of the contract].
TIME AT LARGE
It is very important that the Contractor is given Extension of Time (following a fair
evaluation) …
It protects the interest of the Employer…
If extension of time is not granted, the Employer would lose his right to apply
Liquidated Damages (LDs) / Penalties on the Contractor for any future/ further delays
occur after…
BECAUSE THE TIME BECOMES AT LARGE…
It’s like a Prisoner breaks away from his cell. Until the prisoner is re-captured and put
in his cell, the PRISONER IS AT LARGE. Similarly applies to time as well.
If there is no Date for Completion (i.e. if there is no any Time for Completion) defined,
there is no confinement of time…
Or in case where “Time for Completion is in place”, BUT if there is
1. no EOT clause mentioned in the Contract;
2. very badly drafted EOT clause which is good for nothing;
3. or the Employer (thru the Engineer) does not give EOT compensating a delay
occurred,
the ‘old’ confinement voids. Again, there is NO confinement for time…Time becomes
at large…
Special Note:
There is no way that a Contractor is penalised first and then granted an EOT.
In a scenario where the Contractor has delayed the project and then the Employer
makes another delay by himself.
What could happen???
Assume that the contractor has caused delay of 6 weeks and the Employer’s has
caused a delay of 3 weeks.
Please refer to the image in the next page showing the ‘dotting-on’ of time Employer’s
delay after the original Date for Completion. The resultant period for which the
Contractor will be held liable and LDs will apply is 6 – 3 = 3 weeks only.