JMS For Drainage & Sewage Works
JMS For Drainage & Sewage Works
JMS For Drainage & Sewage Works
TEC-221300-MET-DoR-002
Name) (Rev No.)
METHOD STATEMENT Issue Date 02 October 2013
Rev. Date NA
Method statement for drainage & Sewage works
Pages 1 of 16
Signature field
Revision
Revision
Number
Date
Prepared by Checked by
Reviewed
By Construction Technical QA/QC MEP Co- Sub-
Manager Manager Engineer HSE Officer ordinator contractor
Approved
By Project
Manager
2. PURPOSE
The purpose of this Method Statement is to define the procedure for the preparation and construction of
Gravity Sewer lines with GRP pipes with associated inspection chambers, manholes in accordance with the
requirements specified in the relevant specifications specification 220000considering safety and quality of
the work activities.
3. SCOPE
1. Gravity sewer lines of about 2.1 Kms with 36 manholes 1500mm dia. Associated with house connection
chambers to facilitate the project.
2. The G.R.P pipes 150mm dia. 1173 Mts, 200mm dia. 191 Mts and 300mm dia. 241 mts. Laid in a trench
width of 600mm + pipe diameter in a stable soil and 5 times pipe diameter in unstable soil.
3. The limit of contract is gravity feed connection to the pumping station constructed by others adjacent to
project boundary.
4. REFERENCES
4.1. Contract documents
1. Project Specification :- Division 22, Section 221300
2. Contract Drawings :-
6. Material approvals
Sr. No. Description Material Sub. No. Rev No. Date Remarks
1
2
3
7. Shop Drawings
Sr. No. Description Shop Drawings Rev No. Date Remarks
1
2
3
5. DEFINITIONS / ABBREVIATIONS
5.1. Definition
1. Project -(Replace with project name)
2. Client -(Replace with clients name)
3. Developer -(Replace with developers name)
4. Consultant -(Replace with consultants name)
5. PMC -(Replace with PMC name)
6. Contractor -(Replace with contractors name)
7. Sub-contractor -(Replace with sub-contractors name)
8. Supplier -(Replace with suppliers name)
5.2. Abbreviations
1. Engineer - Representative of “Name of engineering consultancy”
2. ADSSC -Abu Dhabi Sewage Services Company
3. ICL - Inspection Check List
4. IR - Inspection Request
5. ITL -Independent Testing Laboratory
6. ITP - Inspection and Test Plan
7. ITR -Inspection & Test Requests
8. MAT - Material Submittal
9. MEP - Mechanical Electrical Plumbing
10.MET - Method Statement
11.MIR - Material Inspection Request
12.MSDS - Material Safety Data Sheet
13.PPE -Personal Protective Equipment
14.PQP -Project Quality Plan
15.PTW -Permit To Work ( Working at Height or enclosed spaces)
16.RA -Hazard Identification and Risk Assessment
17.RFIA - Request for Inspection and Approval
18.SPD - Shop Drawing
19.TBM - Temporary Bench Mark
6. RESPONSIBILITIES
6.1. Project Manager
1. Ensuring that the subject works in coordination with other works with the requirements of Quality
Plan & programme.
2. Ensuring the full compliance of subcontractors with Company Quality policies and with the
requirements of this method statement.
3. To ensure that all the equipment required to execute the works according to the construction
programme are available, in good condition, and provide any additional equipment that might be
required.
4. To co-ordinate with the Construction Manager, Project Engineer, Safety Engineer, Foreman and
Surveyor for a safe and proper execution of the works.
5. To guide specific attention to all measures in coordination with the safety Officer/Engineer.
6.5. Surveyor
1. To establish benchmarks from agreed reference points, provide required setting out and level
markings and follow up with regular checks.
2. Co-ordinate with the Site Engineer / Foreman and ensure the approved shop drawings/construction
drawings will be implemented properly.
3. Maintain survey details and reports, periodically check the progressing works and advise the Project
Manager of any deviation from the drawings.
8.1. Dewatering
1. Where formation levels are below the ground water table, we propose to dewater our excavation
utilizing well point dewatering system.
2. We shall pre-drill the wells using Drill head fitted to the boom of a wheeled or chain excavator.
3. The well-points of 6 m. in length will be installed into the pre-drilled holes using jetting pumps.
4. The slotted filter heads of the well-points will be surrounded with sharp filter sand while jetting.
5. 50 mm dia. UPVC well-points will be connected to 150 mm dia. Header pipes via 50 mm dia. Flexible
hoses. The header pipes will be linked to 150 mm dia. Vacuum pumps which will pump the
groundwater via 150 mm dia. Lay flat discharge lines, connected to 10” discharge lines laid up to
approved discharge points. (Through a setting tank) to avoid sand going to the existing system.