As T2t3ewrs
As T2t3ewrs
As T2t3ewrs
Redevelopment
Architetural Specification
T2 and T3 External Wall
and Rooflight Systems
Tender
27 July 2007
CENTRAL MARKET DEVELOPMENT
ABU DHABI
Foster + Partners
Riverside Three
22 Hester Road
London SW11 4AN
CONTENTS
A GENERAL REQUIREMENTS ..............................................................................4
A GENERAL REQUIREMENTS
A.1000 FORMAT, DEFINITIONS AND USE OF THE SPECIFICATION
[NOTE: The A Section includes requirements for the final full Specification].
a) Refer to the requirements of the following drawings, reports and supplemental information as
relevant:
i) Planning permission and conditions.
ii) Project Common Tolerance and Movement Document.
iii) Wind Loading Report/Wind Tunnel Test Report.
iv) Acoustic Report.
v) Fire Strategy Report.
vi) Façade Access and Maintenance Report.
vii) Design Drawings.
viii) Structural/Services Engineer’s Drawings.
b) The Design Drawings include a ‘Technical Reference Sheet’ (TRS), which is a directory of
references for elements and systems. This directory shall be used to correlate the Design
Drawings with the Specification. The TRS provides a link between the Specification and the
Design Drawings.
A.1004 Definitions
The following definitions apply to the Specification:
a) "Specification": This document, comprising Sections A - Z inclusive.
b) "Contractor’s Proposals": Drawings, detailed technical specifications, method statements,
calculations and any other relevant information prepared by the Contractor and submitted with
the Tender response, maintaining the design and visual intent, functional, performance criteria
and technical requirements as stated in the Tender documents.
c) "Design": The visual intent prepared by the CA for Tender purposes, represented by the Design
Drawings and Specification.
d) "Detailed Design": That prepared either by the Contractor (for Descriptive works) represented
by the Shop Drawings and Contractor’s specifications or by the CA (for
Prescriptive works) showing the full design.
e) "Design Drawings":
i) For Descriptive works: Drawings issued by the CA, representing the Design for Tender
purposes showing the visual and design intent, scope, layout, principal dimensions,
arrangement of services and structure, technical, function, visual and aesthetic
requirements and where the Detailed Design is carried out by the Contractor.
ii) For Prescriptive works: Drawings issued by the CA, representing the Design for Tender
purposes showing the Detailed Design, scope, layout, principal dimensions, arrangement
of services and structure, technical, function, visual and aesthetic requirements where the
Detailed Design is carried out by the CA.
f) "Shop Drawings": Drawings representing the Detailed Design, prepared by the Contractor (or
his specialist sub-contractor) based upon the Design Drawings, showing plans, elevations,
sections and full size details of fabrication, assembly, installation and fixings of the works,
submitted to the CA for examination prior to manufacture, showing all necessary information
required to fabricate, manufacture and install/construct all elements of the works, maintaining
the design intent.
g) "As-built Drawings": Drawings produced by the Contractor, where required, which show the
works as finally constructed as represented by the Shop Drawings unless otherwise agreed.
h) "Contract Drawings": The drawings listed in the Contract, comprising Design Drawings and
Contractor’s Tender response Drawings agreed with the CA with which all Shop Drawings shall
comply.
i) "Evaluation": Reviews carried out by the CA and Contractor between Tender return and
Contract award to agree materials, typical details and critical interfaces to establish
specifications and drawings for Contract purposes.
j) "Inspection": Inspection carried out by the CA of materials, components, equipment and
installation of the works. Such inspection shall be limited to an inspection of the visual
appearance only and not to the selection of materials or the Detailed Design or construction of
components and equipment, which shall remain the sole responsibility of the Contractor. Such
inspections by the CA shall not relieve the Contractor from compliance with the Contract
Documents.
k) "A(a)ccepted, A(a)cceptance or A(a)cceptable": Materials, components, equipment and
installations accepted by the CA shall be based upon Inspections (as defined above).
l) "Contractor’s Supplemental Information": Documentation produced after Contract award, by the
Contractor, demonstrating that the Detailed Design complies with the Contract Documents.
m) "Inspecting Authority": Competent independent body or association, which verifies compliance
with the Specification.
n) “Testing Authority”: Competent accredited independent testing body or association, which
provides appropriate testing equipment, testing environment and independent testing results
which will be used to verify conformance with the CA. The Testing Authority shall be subject to
acceptance by the CA.
o) "works": The scope of work covered by the Specification.
p) "Detailed Design Programme": Submitted by the Contractor, prior to Contract award, showing
the Detailed Design drawing submission dates, sample submissions, prototyping and testing
activities prior to manufacture.
A.1006 Disclosure
The nature of the design and construction work performed and any information belonging to the CA,
with which the Contractor may become familiar, will be treated as confidential and may not be
disclosed without the written consent of the CA. Do not publish any drawings, sketches or
photographs of the works or building or its construction without the prior written consent of the CA.
f) The design and visual character of the project is important and shall be maintained. Hence,
there shall be no variation in the final surface finish of similar materials, which shall remain
visually consistent, including colour and texture, regardless of orientation or natural grain within
agreed tolerances and agreed samples.
g) Provide submittals outlined within A.4000 and 1300 of each particular work section.
h) Provide Shop Drawings and technical information to demonstrate compliance with the Design
Drawings and Specification and to complete the detailing as necessary and comply with the
approvals process specified. The Contractor’s final Detailed Design shall be based on the
Design Drawings which indicate generic solutions and may not cover all conditions.
i) Where proprietary products are to be installed, be responsible for providing any modification,
additional bracing, reinforcing, suitable fixings, etc. to ensure that the products meet the
requirements of the Specification for the circumstances and situation in which they shall be
expected to perform. Be responsible for conveying any concerns that the manufacturers may
have expressed regarding the suitability of products for the purpose intended.
j) No portion of the works shall commence without acceptance of the required submittals by the
CA.
k) Comply with all relevant National Health and Safety requirements including the production and
submission of system Risk Assessment analysis reports.
l) Be responsible for ensuring that items specified are installed correctly such that the
performance requirements specified are fully satisfied for the service life required. All fixings and
other aspects not fully detailed or specified shall be regarded as the Contractor’s responsibility.
m) Be responsible for the final selection of products and associated components, which shall be
used solely for the purpose intended by the manufacturer; which shall satisfy the requirements
of the Specification.
n) Be responsible for the carrying out of all testing as specified.
o) Co-ordinate with the work of others including all interfacing as required.
p) Provide warranties as required.
q) Submit relevant documents to Building Control as required to comply with the Particular
Requirements sections.
r) Comply with the requirements of Planning Approval.
s) Submit relevant documents to the Local Planning Authority.
t) Set out the works and accurately co-ordinate all related works.
u) Provide details, calculations and any other relevant information to the CA for submission to and
approval by the local authorities. Make any adjustments required by the local authorities,
following submissions, to the satisfaction of the CA.
v) In addition to submissions for the Local Authority, be responsible for submitting structural,
deflection and other calculations and technical information, where required (as requested in the
Specification) for review by the CA. Such submissions shall demonstrate compliance with the
Specification.
v) Samples of proposed materials as required and as listed in the relevant work sections.
vi) Full details of systems, materials and suppliers where different from those specified.
vii) Drawings as listed herein or as deemed necessary to explain the Contractor’s Proposals.
viii) Comprehensive technical specifications of the Contractor’s Proposals.
ix) Relevant supplementary information.
x) Drawings as required by the Particular Requirement Sections or as deemed necessary to
explain the Contractor’s Proposals.
xi) Technical statements confirming performance compliance.
xii) Details of guarantees and warranties including details of predicted service lives for
primary and secondary components.
xiii) Summary of deviations from the Design Drawings and Specification.
xiv) Commissioning information as relevant.
d) Submit all relevant information sufficient to demonstrate compliance with the Specification to
the Relevant Authorities.
are relevant to the design and construction of the works, wish to make proposals for changes in
any details, dimensions or materials shown in the Design Drawings or referred to in the
Specification, then such proposals shall be provided as separate alternative options and
returned with the Tender. In no way shall any proposal fail to meet the minimum performance
requirements herein specified.
b) A request for a substitution shall be deemed to be a warranty by the Contractor to the client
that such substitutions meet the requirements of the Specification and as such must be
confirmed in writing as equal by the Contractor and accepted in writing by the CA. Admissibility
of any request for substitution after Tender shall be at the sole discretion of the CA and may be
rejected without reason given.
c) In the case that any substitution alters the specified requirements, submit sufficient information
on substituted materials to allow evaluation by the CA on any deviations from the Specification.
A.4000 SUBMITTALS
A.4001 Procedure
a) No portion of the works shall commence without acceptance of the required submittals by the
CA.
b) A schedule of submittals shall be provided for agreement with the CA. Schedule to indicate the
dates on which the CA shall receive the required submittals. The schedule shall be correlated
with the master programme and allow a reasonable amount of time for the review of each
submittal. Critical decision dates shall be indicated for selection of finishes and colours. The
schedule of submittals shall be revised and resubmitted as necessary.
c) Provide submittals in accordance with the following:
i) Addressing of Submittals: Submittals shall be delivered to the premises identified by the
CA.
ii) Identification of Submittals: Each submittal shall be individually identified with the project
name, respective specification reference, supplier's/manufacturer's name and product
reference as appropriate. Each submittal shall be accompanied by a transmittal form
containing similar information; together with the purpose for which the submittal is being
made. Space shall be provided on each item submitted for stamping by the CA.
iii) Numbering of Submittals: Submittals shall be numbered consecutively and that
numbering system shall be retained throughout all revisions and resubmittals.
iv) Completeness of Submittals: All relevant information shall be included within each
submittal to define completely and explain each separate system of work. Submittals may
be combined from various sections as necessary and furnished at one time as a single
submission.
v) Variations and Substitutions: Submittals that differ from the requirements of the Design
Drawings and Specification shall be so identified.
d) Submission and Return of Shop Drawings/Documents:
i) Allow for the required period between the first submission of a Drawing/document and
receipt of comments. Allow for resubmissions for each item to achieve a Category A or B
Status.
ii) Provide a list of Shop Drawings proposed.
iii) Information specifically requested for each element of the works shall be provided.
Additional information may be required by the CA on inspection of the Contractor’s
submittals to allow for accurate comments to be made.
e) The Contractor’s submittals shall be reviewed by the CA during the evaluation period, and any
alteration and/or agreements reached shall be incorporated into the Contract Drawings and
Contract Specification.
After Contract award provide Shop Drawings, samples, mock-ups, prototypes, quality benchmarks,
calculations, test reports and other relevant data.
A.4007 Mock-ups
a) During the Shop Drawings preparation phase (in due time to permit adjustments to the design)
and where described in the particular Works Sections, the Contractor shall provide full size
mock-ups for inspection by the CA.
b) Mock-ups shall be erected either on or off Site, not necessarily using actual materials to be
incorporated in the works but representing the design solutions.
c) The mock-up shall be constructed to confirm the general visual intent including colour, size and
co-ordination.
A.4008 Prototypes
a) Prior to manufacture of elements of the works, construct off Site (or on Site if specifically
requested by the CA) full scale three-dimensional sections where described in the particular
Works Sections and/or shown on the Design Drawings utilising final specified materials but not
necessarily final production techniques.
b) The prototypes shall be tested fully to ensure that the systems meet the performance
requirements of the Specification and/or be used as a Quality Assurance/Quality Control “Hold
Point”. Manufacture of materials/products for inclusion in the works shall not commence until
the CA’s written acceptance of the prototypes has been received.
c) Shop Drawings for the prototypes shall be submitted in accordance with the requirements of
the Specification.
d) Any modifications required to the prototypes shall be recorded to show their final construction.
e) Programme tests to enable any necessary adjustments without delay to the works programme.
b) Installations shall not commence in other areas of that particular trade until the CA has
examined and accepted the quality benchmark. Carry out immediately any alterations or
adjustments required by the CA in order to achieve the quality of installation required.
c) Upon receipt of the CA’s acceptance, fully protect the quality benchmark. It shall be used, from
time to time, by the CA to check and monitor quality of materials and workmanship incorporated
in the remaining areas of the works, or where specifically stated for the purpose of further
testing. Remove and replace all protection when requested by the CA for such purposes.
i) If, before commencing or during the preparation of the Shop Drawings the design intent of the
Design Drawings and/or Specification may be affected, or where other elements of the works
may be affected, notify the CA immediately.
j) Where applicable, the Shop Drawings may utilise the manufacturer’s standard details provided
that they comply with the design intent.
k) The CA shall have the right at all reasonable times to visit the Contractor’s (or his specialist
sub-contractors) design office to check on progress.
l) The Shop Drawings shall be annotated in English and titled in the manner determined for the
Contract, with the title block fully indicating the part of the works to which they apply.
m) Information contained in any of the Design Drawings shall be treated as confidential and shall
not be utilised for any purpose other than for the works. Such information shall not be
communicated to third parties for other purposes without the specific acceptance of the CA.
n) Maintain on Site a full set of Design Drawings, Shop Drawings and technical specifications.
o) Upon completion of the design, manufacture and installation phases, provide the CA with the
appropriate number of As-built Drawings, in accordance with the Conditions of Contract.
p) No Shop Drawings shall be accepted if produced to a reduced size.
q) The Shop Drawings shall be fully co-ordinated with interfacing trades.
h) Guarantees and warranties: Provide certified copies of all relevant guarantees and warranties
available for installed materials and products.
i) All submittals provided shall be written in the English language.
A.5100 General
c) Secondary components are all components with a predicted service life of the element being
specified, assuming regular cleaning and maintenance in accordance with information supplied
by the manufacturer. Secondary components shall be capable of easy replacement without
compromising the structural or weatherproof integrity of the element being specified.
Secondary components shall be capable of replacement without progressive dismantling of
adjacent elements.
d) Confirm the predicted service life (i.e. the service life predicted from recorded performance or
accelerated tests) and maintenance requirements of the components of the building as defined
in BS 7543 and BS ISO 15686 for the review by the CA and provide detailed information at
Tender Stage.
e) Materials shall be used solely for the purpose intended by the manufacturer and which satisfy
the requirements of the Specification.
f) Premature deterioration shall not be acceptable.
A.5300 Structural
Refer to the Structural Specification by others for particular requirements.
a) The works shall be capable of accommodating the following live loads without any reduction in
performance:
i) All loads resulting from movements of the building structure and support structure.
ii) Impact loads, or transferred impact loads, that occur during the service life of the works,
without deterioration in performance and without sustaining non-repairable damage.
iii) Loads imposed during replacement of components.
b) When calculating loads the worst combination shall be considered.
A.5304 Deflections
a) The works when carrying full design loads shall not exceed the deflection limits specified within
the relevant Particular Work Section.
b) The works shall not deflect under loading in any way that is detrimental to any component or
adjacent structural or building elements.
c) All components, couplings and fixings shall be capable of accommodating deflections without
permanent distortion, deformation or failure.
d) The works shall accommodate differential structural movements arising from any loads imposed
by adjacent structures.
e) The magnitude of the allowable deflections shall be reduced if they are detrimental to any part
of the works, its support structure or internal finishes.
A.5305 Wind Loads
a) The works shall withstand without permanent deformation, the effects of wind loads where
appropriate (e.g. external conditions or internal areas subject to external wind pressure).
b) Design Wind Pressures: Refer to the Wind tunnel test Report.
c) When assessing the wind pressure allowances, account shall be taken of the shape of the
building and its location in relation to the layout of the adjacent structures.
d) Particular attention is to be paid to areas subject to increased pressures as defined by BS
6399: Part 2, i.e. eaves, canopies and external corners. Special care shall also be taken to
identify and design for any situation not clearly defined in BS 6399: Part 2 where it is believed
that the geometry of the building shall cause increased pressure due to vortex or eddy
conditions. Maximum gust wind pressure shall be calculated in accordance with BS 6399: Part
2. Refer to the Wind Tunnel Test Report.
e) When calculating loads it shall be ensured that the worst combination of load cases have been
considered and in particular, that the governing wind pressure coefficients may be determined
by more than one wind regime. Refer to the Wind Tunnel Test Report.
A.5307 Vibration
Ensure that the works withstand all vibration caused by traffic, aircraft, equipment effects or any other
shocks, slamming, strains, stresses and movement imposed, thus avoiding deterioration or fracture of
any element, both during construction and after installation.
Table 2. Minimum Horizontal and Vertical Flanking Sound Insulation Rating Values:
Building Reference and Adjacency Weighted
Normalized Flanking
Level Difference
(Dnf,w)
Tower T2 – Residential
Apartment at Apartment 50dB
Amenity Space at Apartment 55dB
Plant Room at Apartment 60dB
Tower T3 – Office
Office Tenant at Office Tenant 45dB
Amenity Space at Office Tenant 50dB
Plant Room at Office Tenant 55dB
A.5401 Generally
a) Ensure that the works conform to all aspects of the Specification, taking into account all local
environmental conditions prevailing at Site.
b) Refer to the Particular Requirement Sections for specific performance data.
c) Obtain any additional meteorological and climate data considered necessary in order to fulfil
contractual obligations.
d) Allow for the fact that the works will be erected in all extremes of weather conditions throughout
the year and that the building may not be climatically controlled during construction. Damage to
materials as a result of Site conditions shall be the Contractor’s responsibility.
e) All material grades, manufacturing methods and standards, corrosion protection, etc. shall be
selected so that they are fully suited to the internal and external environmental conditions as set
out below (to meet the relevant British Standards and all other relevant standards) and as
contained in the relevant parts of the Mechanical & Electrical Engineer’s specifications and
drawings. Refer to Mechanical & Electrical Engineer’s specifications and drawings for relevant
data.
fire resistance to elements of structure which form a junction with adjacent components, ensure
that the junction is fire stopped to the same degree as the elements.
A.5601 General
a) Ensure that protective measures are taken to avoid any corrosion or any deleterious effects
caused by manufacturing, finishing, transportation, storage and installation of materials.
b) Ensure full resistance to any corrosion for components that are secured or bolted to each other,
paying particular attention to the surface damage caused by such bolting or securing.
c) Ensure full resistance in repair of corrosion protection to cope with the Site cutting of
components, especially at boundary and external conditions.
d) The minimum requirements for the corrosion protection system for secondary structural
steelwork shall conform to BS 5493, BS EN ISO 12944: Parts 1-8 and BS EN ISO 14713 as
appropriate. For primary structural steelwork refer to the Structural Engineer’s specification. The
environmental category under BS EN ISO 12944: Part 2 shall be:
i) External corrosion category:
• Category C5-M including resistance to the effects of high salinity, wind blown sand
including sand storms: Refer also to clause A.5402.
ii) Interior corrosion category:
• Category C1: Refer also to clause A.5402.
e) Allow for protection against all corrosion arising from exposure to seawater, non-saline water,
soil, high humidity, low or high temperatures, chemical acids and alkalis, abrasion and impact,
fungi and bacteria.
f) Particular care shall be taken with delivery and storage on Site, particularly if storage is
prolonged. On no account shall materials or components be stored or used beyond the
manufacturer’s expiry date.
A.5602 Galvanising Corrosion Protection
The interval to first maintenance shall be no less than the following period as defined in BS EN ISO
14713: Very long (equal to or greater than 20 years).
A.5701 General
a) All extraneous conductive parts of the works shall be effectively bonded to earth. An extraneous
conductive part is defined as being that part which is liable to transmit a potential, including
earth potential, and not forming part of the electrical installation. Each component shall
constitute an extraneous conductive part.
b) The works shall be electrically continuous as required by the latest edition of the IEE (Institution
of Electrical Engineers) Regulations.
c) Equipotential bonding shall be provided to ensure that the various exposed conductive parts
and extraneous conductive parts as defined by the IEE Regulations shall be at a substantially
equal potential.
d) Earthing connecting shall comply with BS 6651 and BS 7430. Copies of the final testing
A.6101 General
a) Establish, document and maintain a quality assurance and quality control system capable of
verifying to the satisfaction of the CA that all materials and workmanship, whatever their
sources, conform to the requirements of the Specification. Should the Contractor or any of his
sub-contractors be certified to the BS EN ISO 9000 family of standards then these works shall
be monitored accordingly.
b) The quality programme shall be defined in a quality control manual or similar document in which
the organisation systems, inspection and test plan procedures are fully described to ensure that
all essential inspection requirements are determined and satisfied throughout all phases of the
works.
c) Establish a tolerance quality control manual to cover all aspects of tolerance compliance
relating to the works. A quality control proposal shall be prepared for submission to the CA for
acceptance. This shall describe, in detail, the various types of quality control checks that shall
be carried out during each stage of the works; what means and methods shall be used; which
personnel shall be employed, together with their qualifications, and how each type of tolerance
check shall be recorded and kept for future reference.
d) The Contractor’s proposals for the quality control manual shall meet the requirements of this
section as a minimum and be submitted to the CA. Provide facilities in the event that the CA
wishes to examine these proposals at the works. Include details of any formal approvals held for
the Contractor’s or any sub-contractor’s quality system or any evaluations or assessments
carried out by independent third parties.
e) Within 30 days of the written order to commence the works, submit a comprehensive quality
control manual to the CA for review, amendment where appropriate and acceptance.
f) Include with the quality control manual an inspection and test plan for each major item of work
or type of fabrication which shall detail, in sequential order:
i) The principal activities to be carried out.
ii) The type, method and frequency of inspections and tests to be carried out.
iii) The inspecting authority.
iv) The acceptance criteria.
v) The records to be kept.
g) The inspection and test plan shall contain sufficient space for the CA to indicate on it the
activities he wishes to inspect as either "hold" or "witness" points.
h) A "hold" point is defined as a point on the inspection and test plan beyond which the process
may not continue until it has been accepted by the CA.
i) A "witness" point is defined as a point on the inspection and test plan where the Contractor
shall give reasonable notice that a particular part of the process has been reached although the
process may continue without acceptance being notified by the CA.
j) The inspection and test plan shall provide the basis of inspection for the item of work and shall
be accepted prior to commencement of the work.
k) At all times during the Contract period, make available at the works all necessary resources and
facilities and implement any reviews and amendments of the quality control manual deemed
necessary or desirable by the CA.
l) As a minimum the quality control manual shall include information and procedures as defined
below:
i) Organisation and Management.
ii) Facilities, Measuring and Test Equipment.
iii) Personnel Training and Certification.
iv) Documentation.
A.6201 Standards
a) British Standards and Local Building Regulations and Codes shall be the governing standards
for the works.
b) Only where expressly stated in the Specification shall other National Standards be applicable to
the works.
c) All reference to British and other standards, regulations and requirements of statutory bodies
shall mean the latest published editions at the time of Contract award. Where such standards,
regulations and requirements are amended after Contract award and affect the Contractor’s
responsibilities during the course of the works, immediately inform the CA in writing.
d) If unable to comply with the governing standards or regulations and proposing to substitute
other National Standards, inform the CA within the summary of deviations from the
Specification. Provide fully detailed reasons for being unable to comply, together with any
design and/or technical implications. Failure to provide such notification prior to Contract award
shall be deemed to be acceptance of the governing standards or regulations and later
notification shall be a nullity.
A.6401 General
a) Replaceable materials/components shall be maximised.
b) Materials shall be capable of simple maintenance/repair and integration with other maintenance
systems.
by the Specification.
d) Maintenance Procedures: The Maintenance Manual shall include fully comprehensive details in
respect of:
i) Cleaning procedures for all elements of the works.
ii) Replacement procedures.
iii) Regular cyclical maintenance procedures (avoiding damage).
iv) Repair procedures in the event of damage.
v) Washing methods, including the frequency and method of washing required to maintain
performance and appearance. Details shall be provided in respect of the maximum time
during which performance of components can be maintained, together with the frequency
and method of washing required to achieve this.
A.6510 Materials
i) Paints and coatings shall have a low VOC content, the limits of which are established in
the following:
• -Green Seal standard GS-11 paints first edition May 20 1993.
• -Green Seal standard GC-03 anti-corrosive paints, second edition Jan 07 1997.
• -(SCAQMD) rule #1113, Architectural Coatings.
A.6550 Workmanship
A.6555 Compatibility
Ensure that all materials and processes employed in the works are compatible with each other and
meet the current requirements of the relevant British Standards and Codes of Practice.
A.6557 Suppliers
Be responsible for all materials, components and equipment supplied or manufactured by sub-
contractors or suppliers, until the end of the warranty period defined in the Contract.
A.6558 Covering Up
No work shall be covered up without agreement by the CA. Afford reasonable notice and full
opportunity for the examination and measurement of any work that is about to be covered up.
A.6560 Deterioration
a) All materials shall be treated/selected to prevent any damage from all possible combinations of
atmospheric deterioration, corrosion, wet rot, dry rot, fungi, mould and all other deleterious
effects including atmospheric pollution and pH factor of the adjacent elements.
b) Ensure that no chemical or electrolytic action takes place where dissimilar metals and/or
materials are used together.
c) No materials shall discolour, crack or otherwise be damaged by the worst possible combination
of environmental conditions identified herein.
d) With materials subject to surface treatment, special attention shall be given to the substrate to
ensure that the preparation is compatible with the surface treatment.
e) Ensure that all superficial dust and friable materials are removed and that adequate protection is
provided during the process of the surface treatment and finishes to prevent contamination by
dust and other debris.
f) Materials used in the manufacture of the works shall not be liable to infestation attack by micro-
organisms, fungi, insects or other vermin, nor provide harbourage for same.
End of Section
Contents
E50.1304 Mock-ups
Refer to Section H11 for Mock-up requirements.
E50.1305 Prototypes
The following prototypes shall be provided in accordance with Section A.4000:
Make allowance for the construction of a prototype as required. Refer to Section H11 for prototype
requirements.
E50.1401 General
For structural performance requirements, refer to Section H11 and Structural Engineers Report.
iii) Type C finish: This finish is obtained by first producing a Type B finish. The surface shall
then be improved by carefully removing all fins and other projections, thoroughly washing
it down and then filling the most noticeable surface blemishes with a cement and fine
aggregate paste to match the colour of the original concrete. The release agent shall be
carefully chosen to ensure that the concrete surface does not become stained or
discoloured. After the concrete has been properly cured, the face shall be rubbed down,
where necessary, to produce a smooth and even surface.
b) Moulds shall be maintained in clean, sound condition and inspected carefully for defects before
each reuse. Damaged moulds shall not be repaired and reused if this would impair the surface
appearance of the units.
c) Moulds shall be designed to permit demoulding without damage to the units.
d) Where applicable, moulds shall be coated evenly with a suitable release agent, which shall not
be allowed to touch the reinforcement. Application shall be such as to prevent puddling or
concentrations in corners, etc.
e) Moulds shall be constructed of mould lining that is an impervious material suitable to provide
the consistency of finish required and selected to provide crisp edge details as indicated on the
Design Drawings. The mould linings shall not be of steel unless agreed with the CA. Materials
for fillets, etc. required to achieve features shall be chosen to provide a finish identical to the
finish to the body of the unit.
f) Any joints and fixings in mould linings shall be sealed to prevent grout loss defects and shall be
such as to result in no visible change in plane of the concrete and no change in the finish
whatsoever.
g) The mould linings shall have no variations in stiffness that may produce differences in vibration
across the mould surface.
h) The mould linings shall be replaced after the agreed maximum number of casts, or upon
discovery of damage or defects whichever is the sooner.
i) Before casting, ensure that moulds have been checked to be free of all dust, reinforcement
clippings or other debris.
j) Moulds inspection: Inform the CA when each mould is complete and not less than 10 days
before commencing manufacture of units.
k) Moulds for features, etc. shall not have any splits, cracks or other defects.
l) Moulds that have been previously used shall be repaired and the edges resealed before they
are assembled. Moulds, which in the opinion of the Contractor have deteriorated to an extent
such that they shall not produce the specified finish, shall not be used for that class or a higher
class of finish.
m) Moulds shall be cut in such a manner that reinforcement and built-in components passing
through the moulds are maintained in position; the joint shall be tight and shall not permit grout
loss.
n) Formers for profiled work, chamfers, splays, rebates, curved troughs and other features shall be
rigidly and evenly fixed to the formwork along the complete length and shall not permit grout
loss.
o) Moulds shall be designed to be consistent with the geometry and as indicated on the Design
Drawings, subject to the acceptance of the CA. The lines of joints between units shall form
smooth curved lines consistent with the geometry and as indicated on the Design Drawings,
subject to the acceptance of the CA. The number of make-up pieces shall be kept to a
minimum.
p) Holes left by ties and components in concrete surfaces shall be in line horizontally and vertically
and shall form a regular pattern, to the acceptance of the CA.
q) Unless otherwise indicated on the Design Drawings, chamfers shall be provided for all external
angles of 90° or less in concrete surfaces with plain or fine finishes.
r) Moulds for curved concrete surfaces shall not be made up of a series of facets, unless
indicated on the Design Drawings.
concreting. Unless permitted by the CA, void formers and box-outs shall not be used instead of
built-in components. Polystyrene shall not be used for void formers and box-outs unless
permitted by the CA.
b) Do not cut hardened concrete to provide holes or chases.
c) Correctly locate and secure pipe sleeves, inserts and ducts in place. Formwork for all openings,
chases and holes in columns and units shall be constructed in such a way that it does not
interfere with the reinforcement.
d) Formwork moulds shall be rigid and free from movement that shall affect their performance with
regard to tolerances or colour of concrete. Allow for all necessary mid-rib reinforcement of the
moulds.
E50.2109 Aggregates
Aggregates shall be selected in accordance with the recommendations of BS EN 12620, of
consistent colour, free from absorbent particles that may cause pop-outs and other particles such as
coal and iron sulphide that may be unsightly or cause unacceptable staining. Obtain from one source,
and ensure that adequate supplies can be maintained throughout the contract. Submit evidence to
demonstrate compliance in respect of compressive strength and free water/cement ratio.
E50.2111 Dowels/Fixings
a) All dowels and fixings shall be concealed when fixed in position in the works.
b) Dowels/fixings shall be stainless steel grade 1.4401 to BS EN 10088 and the relevant precast
concrete standards.
c) Consideration shall be given to the use of a dedicated main mixing and batching plant to avoid
contamination of the mix. A stand-by back-up plant shall also be available that is capable of
providing equivalent mix and batching facilities. The use or otherwise of such a plant shall be
stated in the Contract documentation.
E50.2203 Generally
Conform to the procedures of BS 8110, BS 8297, the requirements of Section H11 as applicable
and the requirements of all relevant National Standards. Provide Shop Drawings for all precast
concrete for review by the CA.
E50.2207 Inspection
Carefully inspect and check all completed units for match with accepted sample(s) or control unit(s)
and compliance with the Specification before dispatch to Site. Make arrangements with the CA for
him to inspect the completed units in the factory.
E50.2208 Records
a) Keep complete records for each unit including the following information:
i) Unique identification number.
ii) Correlation with records of mixes, including batch numbers.
iii) Date of each stage of manufacture.
iv) Dates and results of all tests, checks and inspections.
v) Dimensions related to specified levels of accuracy.
vi) Specific location in the finished work.
vii) Details of any damage.
viii) Any other pertinent data, e.g. if the unit is an accepted production control unit.
b) Records shall be available for inspection on request.
samples of precast concrete units which have been submitted and accepted by the CA shall be
used as reference samples for all precast units prior to being passed for inclusion into the
works, to the satisfaction of the CA. Precast units may be rejected for the following reasons:
i) Exceeding specified construction tolerances for units.
ii) Chipped, spalled or cracked units or other damage incurred during transport or
construction operations.
iii) Exposed-to-view surfaces that develop surface finish deficiencies.
iv) Other defects as listed including:
• Ragged or irregular edges.
• Finish quality below standard set by samples or mock-up.
• Excessive air voids/blowholes on exposed surfaces.
• Casting lines evident from different placements.
• Visible form joints or irregular surfaces.
• Stains on unit surfaces.
• Non-uniformity of colour and texture.
• Effects of grout seepage.
• Areas of any back-up concrete bleeding through facing concrete.
• Foreign material embedded in face.
• Visible repairs.
• Reinforcement shadow lines.
• Visible cracks.
• Any damage due to erection methods, propping panels, etc.
d) Provide a method statement demonstrating how damage will be avoided during all stages of
manufacture, installation and transportation.
and shall not be in the visible faces of the unit without prior agreement.
E50.3106 Cleaning
a) Clean dirt or blemishes from exposed surfaces.
b) Wash and rinse in accordance with the precast concrete manufacturer’s recommendations.
c) Protect adjacent surfaces from damage caused by cleaning operations.
d) Do not use cleaning materials or processes that could alter the character of exposed finishes.
E50.3200 PROTECTION
E50.3201 Protection of the Works
a) Provide full and adequate protection for the works against the effects of weather, until the
building is watertight, during storage, handling, and transport and during and after installation.
b) Provide full and adequate protection for the works, until Practical Completion of the project,
against damage or accidental spillage of liquids that may discolour the concrete finishes.
c) The protective measures used shall not in any way permanently mark or damage the concrete
finishes.
Contents
G10 PAINTED VISIBLE AND STRUCTURAL STEEL FRAMING
(ARCHITECTURAL REQUIREMENTS) ...........................................................................3
G10.1200 DESCRIPTIONS/TYPES................................................................................................... 3
Paint to Internal Exposed Mild Steel.......................................................................................................................................... 3
G10.1201 Paint to Exposed Secondary Steelwork for Types EWS-14, EWS-40C, EWS-20G and EWS-40E....................3
G10.1200 DESCRIPTIONS/TYPES
Paint to Internal Exposed Mild Steel.
G10.1201 Paint to Exposed Secondary Steelwork for Types EWS-14, EWS-40C, EWS-20G and EWS-40E.
a) Location: External exposed secondary steelwork incorporated into Types EWS-14, EWS-40C,
EWS-20G and EWS-40E in Section H11.
b) Painting:
i) Surface preparation shall remove all rust, scale and surface contamination to leave a
G10.1304 Mock-ups
Not required.
G10.1305 Prototypes
Not required.
G10.1307 Inspection
Permit the CA, and/or an appointed independent inspection authority, to inspect the work at all
reasonable times and at all places where it is being carried out. Provide all facilities, hand tools,
lighting, etc. as necessary to ensure adequate inspection.
G10.1308 Testing
Arrange for testing to be carried out as directed by the CA. Prepare any necessary test pieces.
Submit copies of all test and examination results to the CA as soon as they are available.
G10.1311 Products
When requested by the CA, submit a copy of test certificates for finishes to steelwork.
G10.1402 General
The work shall maintain the specified appearance and performance for the specified period to first
maintenance period without failure resulting from inappropriate material selection or defects in either
materials or workmanship. Failure shall be defined as excessive fading, excessive non-uniformity of
colour or shade, discolouration, yellowing, cracking, peeling, pitting or other defects identified in BS
2015 and BS EN ISO 4618 within the following limits:
a) Excessive fading: A change in appearance which is perceptible and unacceptable, as
determined by the CA, when visually compared with the original range samples from a distance
of 2m (under the agreed lighting conditions).
b) Cracking, peeling, pitting or other defects that are discernible (by the CA) when viewed from a
distance of 1m, or which result in any corrosion or impairment to the substrate.
c) All finished surfaces shall be subject to visual inspection and be accepted by the CA. No areas
of unfinished material shall be visible in the finished work.
d) Visual requirements shall be based upon samples submitted and agreed.
G10.1403 Appearance
a) All finishes shall be stable, fade resistant and not affected by ultraviolet light. Provide data and
samples for review by the CA.
b) All finishes shall be durable, of uniform texture and colour and be resilient to all known and/ or
specified environmental and pollution effects. This shall include scratching and cigarette smoke
and burns, etc. Submit data and samples for review by the CA.
c) Minor scratches and blemishes shall be repaired using the coating manufacturer's
recommended products and system, matching original finish for colour, texture and gloss.
Repair coatings shall be visually acceptable to the CA. Confirmation shall be provided that the
damaged finish complies in all respects to the requirements of the Specification. Guarantee in
writing that the damaged or defective coating is satisfactory for the proposed remedial paint
system. Employ an independent finishing consultant to carry out an inspection and any
necessary tests and supply a full report to the CA.
d) All finishes shall be within the limits of the agreed samples and without irregularities or
distortions. Fixings, stiffeners, etc. which are not intended to be visible shall be treated so that
there is no discontinuity in the finished surface appearance.
G10.1408 Inspection
a) Together with the applicator, where Site coats are to be applied, alert the paint manufacturer
seven days prior to the start of the application programme and permit the paint manufacturer to
inspect the work in progress and prepare inspection reports in accordance with the standard
conditions of Contract. The paint manufacturer shall forward a copy of any inspection report
direct to the CA.
b) Technical support from the paint manufacturer shall not relieve the Contractor of his contractual
responsibility to ensure that the coatings are applied in accordance with the Specification.
Where the paint manufacturer does not have an inspection/quality control support system, then
employ an independent testing authority to verify compliance of the coating systems with the
Specification.
G10.2202 Two Pack Zinc Rich Primer, Isocyanate Free Acrylic Polysiloxane, Compliant Coating
a) Location: Internal exposed steelwork.
b) Shop primer:
i) Dry film thickness: 75 microns minimum.
ii) Colour: Grey.
iii) Special requirements: Maximum V.O.C. 189gms/litre. Volume solids: 73%.
c) Shop topcoat:
i) Dry film thickness: 100 microns minimum.
ii) Colour: As required by the CA.
iii) Special requirements: Maximum V.O.C. 165gms/litre. Volume solids: 76%.
d) Refer to the manufacturer’s recommended working procedures to be read in conjunction with
the technical data sheet and material safety data sheet. Provided information to be strictly
adhered to.
G10.3202 Finishes
a) Once applied the finish shall not in any way slump, flow, crack, flake, split, sag, pit, bubble,
blister, float, effloresce, craze, shrink, break, wrinkle, crinkle, yellow, chalk, fade, discolour,
powder, stain, bleed or lose its finish or gloss in any way, taking full account of the extremes of
all atmospheric and environmental conditions for the service life specified and during
construction.
b) Paints shall not be overthinned so as to change in any way the surface colour, gloss, opacity or
finish and nothing shall be added to paints to change in any way the consistency or constitution.
Thinning shall be strictly in accordance with the manufacturer's written recommendations and
the express agreement of the CA.
c) All necessary controls shall be undertaken to ensure uniformity in manufacture and to maintain
G10.3204 Inspection
a) Applicator to alert the paint manufacturer where their paint system is being applied to inspect
works in progress and prepare inspection reports in accordance with their standard conditions
of contract. The manufacturer to forward copies of any inspection reports direct to the CA.
Technical support from the manufacturer does not relieve the applicator of his contractual
responsibility to ensure that the coatings are applied in accordance with the Specification.
b) Notify the CA of projected dates for start of surface preparation and coating.
c) Give the CA at least 7 days' notice before coated members or components leave the works.
G10.3206 Protection
a) Adequately protect freshly applied surface coatings from damage.
b) Exhibit `Wet Paint' signs and provide protective barriers where necessary.
c) Adequately protect surfaces adjacent to those being covered.
a) Ensure that the surface preparation is sufficient to meet the Design and service life expectancy
of the Specification and is carried out strictly in accordance with the manufacturer's
recommendations.
b) Comply with BS 6150 and BS 8000: Part 12, Section 2 and additional requirements in the
Specification.
c) When removing or partially removing coatings, use methods that will not damage the substrate
or adjacent surfaces, nor adversely affect subsequent coatings.
d) Materials used in preparation to be types recommended by their manufacturers and the coating
manufacturer for the situation and surfaces being prepared.
e) Prevent or control exposure of operatives to dust, vapour and fumes exceeding occupational
exposure standards set in the current Health and Safety Executive (HSE) document EH40.
f) Substrates shall be sufficiently dry in depth to suit the coating to be applied.
g) Remove efflorescence salts from surfaces. Repeat removal if efflorescence recurs.
h) Clean off dirt, grease and oil from surfaces. If contamination of surfaces/ substrates has
occurred, obtain instructions before proceeding.
i) Unless otherwise specified or agreed, cleaning shall be carried out with an anti-silicone solution
with lint free cloths, the solution shall have a neutral pH to ensure that it is not detrimental,
should any spillage occur.
j) Remove dust and particles from dry abrasive preparation of surfaces.
k) Remove residues from wet preparation of surfaces by rinsing with clean water, wiping and
allowing to dry.
l) Where the preparation of the metal exposes bare steel or zinc galvanising, either chromate
passivation, phosphate treatment, mordant (zinc only), as applicable or an appropriate etch
primer shall be applied before the chosen paint/ protective coating system is used.
G10.3400 PAINTING
G10.3401 Suitability of Conditions
a) Do not apply coatings:
i) To surfaces affected by moisture or frost.
ii) Unless the steel temperature is at least 3°C above the dew point with conditions stable or
improving.
iii) Unless the relative humidity is below 85%.
iv) When heat is likely to cause blistering or wrinkling.
b) Take all necessary precautions including restrictions on working hours, providing temporary
protection and allowing extra drying time, to ensure that coatings are not adversely affected by
climatic conditions before, during and after application.
c) Take responsibility for the application of coatings and ensure the suitability of surfaces and
conditions within any given area.
smooth steel reference plate, the number and position of measurements to be as directed by
the CA. Carry out all measurements in the presence of the CA, unless otherwise directed.
c) Over any square metre of coating ensure that the average accumulated dry film thickness is
equal to or exceeds the specified thickness, with no reading less than 75% of the specified
thickness. Where a minimum dry film thickness has been specified, any areas found to be below
the specified figure shall be made good at no extra cost to the Client.
d) If at any stage the accumulated dry film thickness is deficient, apply additional coats at no extra
cost.
e) The dry film thickness of the topcoat shall be sufficient to give an even, solid, opaque
appearance, irrespective of the number of applied topcoats necessary to achieve cosmetic
obliteration of the undercoat. The full specified topcoat dry film thickness shall be maintained
notwithstanding any greater than specified undercoat dry film thickness.
End of Section
Contents
H11 ROOF AND WALL SYSTEMS............................................................................5
H11.1103 Interfaces
a) Complete the Detailed Design of all interfaces with adjoining trades prior to commencement of
manufacture.
b) Ensure that all interfaces are fully co-ordinated prior to commencement.
f) The system to incorporate insulated spandrel panels within ceiling void as shown on the Design
Drawings comprising aluminium faced composite panels integrated into the curtain walling
system.
g) The system to include precast concrete channel profile at floor levels as shown on the Design
Drawings as specified. Refer to section E50 for precast concrete. Provide insulation, fire
separation and seals behind to seal junctions with floor slabs as shown on the Design Drawings
including provision for expansion and all bracketry, fixings and closure pieces as required.
h) Open screen system with various patterns to screens. Screens to be fixed to framing
comprising solid fabricated stainless steel profiles with concealed fixings/bracketry.
i) Finishes:
i) All aluminium to be colour anodised externally. All internal aluminium to be PVDF coated.
Anodising and RAL colours to be confirmed.
ii) GRC to be self coloured with smooth finished to accepted samples. Colour to be
confirmed.
iii) Refer to section E50 for finish to precast concrete mullion cappings.
j) Pattern variations to screens to be as shown on the Design Drawings.
k) Panels to be set out in a facetted manner as shown on the Design Drawings.
l) Bird mesh/spikes to be discreetly integrated as indicated on design drawings.
vi) Thermal tubes: Thermal tube panels integrated into the curtain walling system. Refer to
the M&E Specification for details of the performance requirements, interfacing etc.
Thermal tubes to be mounted to brackets to inside of mullion profiles and hinged for
maintenance as shown on the Design Drawings.
b) Panels to be set out in a facetted manner as shown on the Design Drawings.
c) Provide aluminium set back spandrel panel with fully formed return edges and welded corners.
Folds with internal ‘V’ cut to reduce bending radius. All fixings concealed. Aluminium shall be
colour anodised to match PVDF coating to frame.
d) Incorporate pressure valve with filter to prevent sand/dust ingress into top transom to allow
cavity to breathe in response to thermal expansion of the air. As shown on the design drawings.
e) All external metalwork to be colour anodised. All internal metalwork to be PVDF coated.
Aluminium surfaces facing the inside of the cavity to be colour anodised to match PVDF coating
to frame. Non-visible framing to be corrosion protected.
f) Contractor to coordinate with Interior Works Package Contractor and provide fixing point for
internal finishes by others.
H11.1211 Type EWS-20E Cladding System with Fixed Stainless Steel Louvre
a) Vertical stainless steel louvers incorporating sand-trap and insect mesh. Stainless steel to be
grade 1.4401 with mirror polished finish. Profiles to comply with the design intent and as
indicated on the Design Drawings. Refer to Section L10 for performance requirements for
louvres.
fitted onto fabricated profiles as shown on the Design Drawings. To include seals and gaskets.
b) System is to include local dead load glazing support and mechanical back-up restraints to
horizontal edges which also accommodate vertical movement. Refer to the Design Drawings.
c) To include vertical and horizontal stack joints between aluminium and steel framing to connect
‘stick built’ system with unitised system. Stack joints are to be concealed behind internal
partition walls. Vertical stack joints consisting of male/female half mullions which clip together
as shown on the Design Drawings.
d) External visual appearance of both ‘stick built’ and unitised systems are to be the same as
EWS-20A including joints and glazing.
maintenance and cleaning purposes. Panel to be sealed at junction with floor slab to provide
continuity of fire separation between floors. Refer to the Fire Strategy Report.
d) Panel at ceiling level is to allow air flow over full height of glass as shown on the design
drawings.
e) Provide a ventilation passage at ceiling void (hot air out) and at low level (cool air in) to facilitate
ventilation of cavity as shown on the Design Drawings. Provide air filter at bottom to prevent
dust entering cavity. To be coordinated with M&E and A/C contractor.
f) All external metalwork to be colour anodised. All internal metalwork to be PVDF coated. Non-
visible framing to be corrosion protected.
f) The rooflight system to be double glazed with photovoltaic panels (glass Type GL-30) as
specified. The system is to include wiring, junction boxes and is to be coordinated with the M&E
specification.
g) Panels to comprise fixed panels including flashings, drips, seals and associated gaskets, fixings
and bracketry as required to complete the installation.
h) Framing profiles are to be aluminium capped internally as shown on the Design Drawings.
i) Ring beam and columns are to be clad with aluminium panels internally as shown on the Design
Drawings.
j) All external metalwork to be colour anodised. All internal metalwork to be PVDF coated. Non-
visible framing to be corrosion protected.
k) All necessary wiring to be concealed.
Shading Devices
deemed to be satisfactory by the CA, laboratory tests shall be carried out to satisfy the
requirements of the Specification.
c) Test certificates do not relieve the Contractor of his responsibilities regarding the performance
and service life requirements of the cladding works.
a) The joint between the façade cladding and the structural slab at each floor level shall be sealed
such that air shall leak through the façade floor joint at no more than 0.1 litres/sec. per linear
metre of façade at 50N/m².
b) The façade floor joint air leakage testing shall be carried out on Site by a specialist laboratory
such as CERAM, Taywood or BSRIA.
c) Allow for the testing of up to 10 sections of façade, each section comprising the building
module of façade. The test sections shall be selected by the CA. If the test fails, locate the leak,
seal it and retest the section until the test is passed. If more than two tests fail, a further 10
sections of façade shall be re-tested.
H11.1401 General
a) Comply with the general performance of Section A.5000 and the following specific
performance requirements.
b) The works generally shall be designed, constructed and installed to BS 8200 and the
recommendations of the CWCT Standard for Systemised Building Envelopes.
c) Inclined overhead glazing shall comply with the requirements of the CWCT Standard for
Systemised Building Envelopes.
Structural Performance
H11.1403 Deflections
a) The allowable deflection of any glazed element of the works, when carrying full design loads,
shall comply with BS 6262 as applicable.
b) Unless otherwise specified, the maximum allowable deflection for any general framing members,
panels, glass components shall be in accordance with the requirements of the CWCT Standard
for Systemised Building Envelopes and all relevant standards as applicable.
c) The allowable deflection of any element of the inclined overhead glazing assemblies, when
carrying full design loads, shall be in accordance with the recommendations of BS 6262, BS
5516: Parts 1 and 2 and the Centre for Window Cladding Technology (CWCT) Standard for
Systemised Building Envelopes as applicable.
d) The works shall not deflect under loading in any way that is detrimental to any element of the
works or adjacent structural or building elements.
e) All components, couplings and fixings shall be capable of accommodating all of the above
deflection without permanent distortion, deformation or failure.
f) The works shall accommodate defined differential structural movements arising from any loads
imposed by adjacent structures.
g) The magnitude of the allowable deflections shall be reduced if they are detrimental to any part
of the works, their support structure or internal finishes.
h) Calculations of deflections for structural aluminium shall recognise criteria contained in BS
8118: Part 1 limiting deflections.
d) The Glazed Curtain Walling/ Cladding Systems shall be designed so that failure of any one
local element (e.g. bolt, anchor, of fixing component) will not result in progressive failure of the
curtain wall/ cladding.
e) Cast-in Inserts: Design to resist worst load combinations. For proprietary inserts, design to
manufacturers requirements.
d) The loads created by wind loading as specified shall be accommodated safely, without
detriment to the overall design, structural integrity and performance of the works.
e) Make necessary provisions as required to eliminate vibration, noise and metal fatigue caused by
airflow to the screen cladding.
d) Ensure that the maximum opening pressures required to open fire rated or non-fire rated doors
on disabled access routes are in accordance with the requirements of BS 8300.
Environmental Performance
iii) 3.0m³/hr/per metre length of opening for framed and rebated doors.
d) Items i), ii) above shall be tested at a minimum pressure of 600 Pa when tested generally in
accordance with the CWCT Standard for Systemised Building Envelopes.
e) Air leakage shall be distributed and not concentrated at any one location.
f) Provide actual air leakage results from tests for acceptance.
g) Where appropriate, analyse details of pressure equalisation proposals for all areas of rainscreen
cladding taking into account variable external pressure gradient for acceptance by the CA.
H11.1418 Condensation
a) Except under extreme conditions where the relative humidity is in excess of that specified in
clause A.5402, condensation shall not form, either on internal or external surfaces of framing
members, glazing, solid panels or louvres, or interstitially within the construction of infill panels
forming a part of the works, such that it may lead to degradation of performance, damage or
staining under the psychrometric conditions specified.
b) Condensation shall be permitted in non-visible drained and ventilated rebates subject to
condensation not having a deleterious effect on performance or durability.
c) Provide a condensation risk assessment with the Tender return based upon the psychrometric
conditions specified, for review by the CA.
d) In conditions outside of the ranges given in A.5400, design the system so that the condensate
either:
i) Drains to the outside or;
ii) Sits in a collection point designed for this purpose, which allows the condensate to
evaporate harmlessly.
H11.1419 Capillarity
The Detailed Design, gaskets, seals, etc. shall take into account and eliminate any possibility of water
migration to the inside of the building due to capillarity.
H11.1424 General
a) All elements of the works shall be either non-combustible or not easily ignitable with low flame
spread characteristics, and shall not produce excessive quantities of smoke or toxic gases.
Comply with NFPA 5000 and the Fire Strategy Report.
b) All materials and products used shall comply with Abu Dhabi Civil Defence local requirements.
Joints made within or between fire resistance-rated assemblies shall be protected with a joint system
that is designed and tested to prevent the spread of fire for a time period equal to that of the
assembly in which the joint is located. Such materials, systems, or devices shall be tested as part of
the assembly in accordance with the requirements of ASTM E 1966, Standard Test Method for Fire-
Resistive Joint Systems, or ANSI/ UL 2079, Standard for tests for Fire Resistance of Building Joint
Systems.
H11.1430 General
The performance criteria shall be satisfied for the full service life of the works, as stated in the
Specification, provided always that the maintenance has been carried out as specified.
H11.1432 Demountability
a) Elements of the works shall be individually and independently removable ensuring access for
maintenance and/or replacement of glazed units in the event of breakage.
b) The removal of glazed units shall not affect the performance or safety of adjacent or any other
part of the works. Provide a method statement for removal and replacement of glass panels for
acceptance.
Components
H11.1437 General
a) Blinds shall operate with minimal noise, smoothly and consistently for the service life as
specified.
b) All blinds shall be easily operated by a single person using the intended operating mechanism.
H11.2100 SYSTEMS
Wall Cladding Systems
H11.2105 Glass Types (Refer to section Z25 for general glass clauses)
a) GL-01: Neutral body tinted double glazed unit (solar control) with low reflectivity and good light
transmittance.
b) GL-20 Reflective solar control double glazed unit. Spacers to be aluminium and black in colour
(plastic not acceptable). Silicone black. Outer pane laminated annealed glass (2 sheets). Inner
pane to be heat strengthened glass. Reflective coating to face 2.
c) GL-21: Single glazing. Clear laminated low iron safety glass.
d) GL-22: Reflective solar control double glazed unit. Laminated heat strengthened glass (2
sheets). Inner pane to be heat strengthened glass. Reflective coating to cavity side to reflect
light/UV back on tubes. To have a high performance coating on face 2 and a low E coating on
face 3
e) GL-25: Single glazing. Laminated heat strengthened safety glass.
f) GL-30: Photo-voltaic double glazed units (overhead glazing). Laminated heat strengthened
glass to underside. Reflective coating to face 2, to be confirmed by the architect. Photovoltaic
cells placed within interlayer within outer pane.
g) GL-31 As GL-30 but safety glass with photovoltaic cells within laminated interlayer.
Blinds
g) Guidess. To operate without the need for guide cords. To be confirmed following testing.
h) Lifting Strips: Specially coated polyester strip, or acceptable equivalent, UV resistant, low
expansion and low shrinkage, unbreakable and kink-proof.
i) Lower Rail: Extruded aluminium profile, powder-coated with plastic end-caps.
j) Drive: Concealed built-in, maintenance-free electrical central motor (230V, 50Hz) with built-in
limit switches and thermal protection switches. The motor is switched off at the lower end
position by means of a geared cam limit switch and at the upper end position by means of a
limit switch sensor.
k) The drive is required to be fitted with a suitable incremental transducer to suit.
l) Operation: Lifting and lowering of the light-guiding blinds to rest position by use of the up-down
switch. Turning of the blades with suitable mechanism indicating the respective direction. The
switch to be provided with direction arrows. If the upper or lower limit position is reached, the
limit switches built into the motor cause the automatic switching-off of the drive.
m) All switches shall be stainless steel with brushed 240 grit finish (grade 1.4401).
n) Switches to be integrated into the cladding mullions/framing as required. All wiring shall be
concealed.
o) Rope Guides: Transparently sheathed steel wire core or acceptable equivalent. The cords to be
fastened in the upper rail, and run through all the lamellae and the lower rail. Bottom fixing detail
to be fully concealed. Assembly of internal threaded end stop fixed to transom with dual thread
screw.
p) Corner blinds to be mitred.
q) Refer to the M&E documentation for the specification of controls.
r) All visible metal elements shall be new and free from visible defects or performance defects.
Finishes shal be free from any blemishes, tool or die marks, striations or defects of any kind.
s) Mechanisms shall incorporate overload devices to prevent damage from excessive operating
forces.
t) The works shall provide a robust, smoothly operating installation that meets the performance
requirements, irrespective of the blind's dimensions and shall, with routine maintenance, retain
its original appearance and performance throughout its design life.
u) All moving parts shall move freely and shall be self-lubricating.
v) The following information shall be supplied for every item component and/ or system:
i) Certified manufacturing certificate.
ii) A full description of operating requirements, giving any special features.
iii) A full breakdown of the parts and the catalogue number of the constituent parts.
w) Provide all associated bracketry/ cleats and fixings to fix blinds to the primary structure/cladding
as required.
x) No product names, manufacturer's names or reference numbers or identifying marks shall
appear on the finished surface of any component.
y) Profiles shall be true to line, angle and curvature as indicated on the Design Drawings.
z) Refer to Section Z11 for aluminium and stainless steel generally.
e) Blind Slats:
i) Dimensions and profiles as shown on the Design drawings.
ii) Material: Aluminium/Steel.
iii) Finish:
• External: PVDF finish. Colour to be as the accepted sample.
• Internal: To be coordinated with interior design.
f) Drive: Concealed built-in, maintenance-free electrical central motor (230V, 50Hz) with built-in
limit switches and thermal protection switches.
g) The drive is required to be fitted with a suitable incremental transducer to suit.
h) All switches shall be stainless steel with brushed 240 grit finish (grade 1.4401).
i) Switches to be integrated into the cladding mullions/framing as required. All wiring shall be
concealed.
j) Refer to the M&E documentation for the specification of controls.
k) All visible metal elements shall be new and free from visible defects or performance defects.
Finishes shal be free from any blemishes, tool or die marks, striations or defects of any kind.
l) Mechanisms shall incorporate overload devices to prevent damage from excessive operating
forces.
m) The works shall provide a robust, smoothly operating installation that meets the performance
requirements, irrespective of the blind's dimensions and shall, with routine maintenance, retain
its original appearance and performance throughout its design life.
n) All moving parts shall move freely and shall be self-lubricating.
o) The following information shall be supplied for every item component and/ or system:
i) Certified manufacturing certificate.
ii) A full description of operating requirements, giving any special features.
iii) A full breakdown of the parts and the catalogue number of the constituent parts.
p) Provide all associated bracketry/ cleats and fixings to fix blinds to the primary structure/cladding
as required.
q) No product names, manufacturer's names or reference numbers or identifying marks shall
appear on the finished surface of any component.
r) Profiles shall be true to line, angle and curvature as indicated on the Design Drawings.
s) Refer to Section Z11 for aluminium and stainless steel generally.
H11.2200 MATERIALS
General
be installed on the warm side of the thermal insulation to provide a continuous air and vapour
tight seal at all interfacing joints and intersections between the units and the building structure.
k) All framing shall be detailed in order that any necessary replacement of damaged glazing units,
as well as doors, windows and structural silicone glazed components, can be carried out from
outside the building with minimum disturbance to occupants, except for any internal glazing
systems.
the glass sealed unit manufacturer or, in the absence of such specific recommendation, with the
provisions of BS 6262. The sealed unit manufacturer’s fabricating tolerances shall be
accommodated. Frames shall be sufficient to restrain the glass under maximum positive and
negative wind pressures.
g) Include for all framing members of the opening casements to comprise two separate metal
profiles, to comply with all structural and surface treatment requirements. The framing to
comprise composite framing profiles with a proven continuous thermal break. The thermal break
system shall minimise the thermal transmittance noise transfer and shall inhibit condensation on
any of the internal surfaces of the framing members.
h) Where opening sections and curtain wall framing sections are required to align, the external
dimensions and appearance of the framing for the opening casements shall correspond exactly
to the perimeter sub-frames for the fixed light glazing so that no visual distinction between these
components can be made. The framing of the opening casements shall be fixed into the
supporting window frames by means of heavy-duty aluminium or stainless steel hinges and
concealed opening restrictor stays. The interfacing joint between the opening casements and
the window frames shall be provided with a minimum of two perimeter sealing gaskets inserted
into corresponding grooves in the aluminium profiles, creating an external rain barrier and the
internal airtight vapour barrier required for a pressure equalised window system. The space
between these gaskets shall be ventilated and drained to the outside of the assembly.
i) Special aluminium/stainless steel extrusions shall be installed into corresponding grooves in the
external side of the framing profiles of the opening casements to provide the loadbearing
bonding surfaces between structural silicone joint and the supporting framework.
j) Special aluminium/stainless steel extrusions shall be installed into corresponding grooves in the
external side of the glazing sub-frame profiles to provide the dead loadbearing support for the
cured silicone glass setting blocks.
k) Special aluminium/stainless steel extrusions shall be installed from the outside to the perimeter
glazing sub-frames to provide a slim perimeter mechanical safety restraint for the structural
silicone glazed double glazing units. This continuous external perimeter glass restraint framing
shall be detailed to provide minimal metal visible externally. The external surface of these
perimeter safety restraints shall be flush with the external surface of the double glazing units.
l) The extrusions for the framing of the opening casements shall be detailed to allow for the
secure installation of continuous sealing gaskets, vapour and air seals, gaskets within the
glazing rebates as well as connections for thermal break strips and provision for seals, corner
cleats, clip-in aluminium profiles, such as the special natural anodised aluminium extrusions for
the bonding of the structural silicone and the continuous perimeter aluminium safety rails for the
four-sided structural silicone glazing, heavy-duty aluminium or stainless steel hinges, concealed
stainless steel opening restraints, concealed multi-point locking devices with budget locks, etc.
All of this under due consideration of the structural requirements, the specified type of surface
treatment and to achieve the specified thermal transmittance and sound reduction values.
m) The thermally broken aluminium or separated profiles shall be factory assembled into opening
casement unit frames by means of mitred corners, mechanically jointed with cleats and the
appropriate additional sealant. The entire opening casement assemblies shall be structurally
sound to fully comply with all applicable and specified wind and dead load forces. They shall be
sufficiently rigid to safely withstand any additional forces that may act onto these assemblies, in
particular during transport and erection on Site. The opening casements shall be detailed to
accommodate, without distortion, water leakage, noise or other adverse effects and/or any
differential structural and thermal movements.
n) All opening casements shall be detailed in order that they may be removed from outside the
building in the event of replacement of damaged double glazing units, so as to create minimum
disturbance to the occupants of the building.
o) The heavy-duty hinges shall be manufactured from aluminium or austenitic stainless steel to fully
comply with all applicable and specified wind and dead load forces. They shall be sufficiently
rigid to safely withstand any additional forces which may act onto the opening casements whilst
being operated or when they are in their closed or open position.
p) Opening casements shall incorporate two fully concealed mechanical opening angle restrictors
with a built-in mechanism to hold the opening casement rigidly in its open position under the full
specified design wind load until the locking latch is manually released.
Doors
H11.2210 General
a) Refer to the Door and Ironmongery Schedule for ironmongery requirements. Interface with the
M&E requirements regarding all security access requirements.
b) Refer to the Fire Strategy Report for fire resistant requirements.
c) Generally all doors to be of a robust nature to conform with DD171, BS 8300 and PAS 24.
Where fire rated doors are required, these shall incorporate fire rated glazing and glazing
methods including fire rated seals.
d) All doors shall prevent unauthorised entry by removing hinges or locking devices.
e) The client shall advise on the mastering requirements.
f) Comply with the requirements of BS 8300.
g) All cables/ conduits to be integrated and concealed in door frames. Draw wires to be provided
for connections by others.
h) Manifestation for all doors to be as referred to in Section Z25.
i) All doors opening outwards unless otherwise shown on the Tender Drawings.
j) Door frames and associated glazing to achieve the required maximum air leakage rates,
weathertightness, acoustic performance and U-values as specified.
m) For security the door shall be able to be locked with key operated concealed lock to comprise
of patch lock to the bottom outer edge of two door leaves, locking into the floor, accessible and
operable only from the interior of the building.
n) Stainless steel matwell frame formed from profiles to be set to the radius of the door
incorporating recessed linear pattern 'brush off' matting. Matwell material to be extruded
aluminium or stainless steel strips (impact resisting and heavy duty) with inlaid coarse fibre
(coir) inlaid strips to match the matting system to be used in the entrance area.
o) All moving parts requiring lubrication shall have grease caps, which can easily be maintained
and shall not cause oil drips during operation.
p) All specified items for casting-in shall be designed, fabricated and delivered to Site in sufficient
time to cast-in to meet the programme. Check also that they are set out and placed to the
required tolerances, having due regard for concrete tolerances and deflections.
q) In addition, include, inter alia, the following:
i) All copings, sill caps and cappings.
ii) All metal and neoprene flashings inclusive of all necessary supports.
iii) All sealants, coating and seals required to provide both first and second line of protection.
iv) All weepholes, drainer channels and ways to provide a fully drained system.
v) Any steelwork and any other supporting system required.
vi) All miscellaneous steel and aluminium required by the revolving door system, including all
relevant shims, relieving angles, back angles, attachment clips, cramps, corbels, bolts and
other required devices as necessary for the proper support and attachment of the system
to the cladding and having due regard for normal in situ concrete tolerances at the base.
vii) Cutting chases, recesses, mortices, notches, drilling holes and perforations for fixing
devices and the like, securing in position fixing brackets for casting-in concrete, by others,
grouting-in and making good as necessary.
viii) All screws, fixings, bolts, nuts, washers, rivets, distance pieces, etc.
ix) All waterbars, flashing and all other seals at the junction with adjacent work, including all
due allowance for returning to the works to complete the installation of seals after the
adjacent works have been completed.
x) Weather-sealing at interfaces with any adjoining or abutting elements and structures.
g) All ironmongery shall be satin stainless steel, pull handles, locks, etc. to be agreed with the CA.
See also Section P21.
H11.2213 Ironmongery
a) Allow for co-ordination of all ironmongery with the security Contractor and provide ironmongery
and wireways as required. Doors shall include concealed door contact magnets to be
integrated into the design of the door for connection to the B.M.S. Provide Access Control as
required (refer to the M&E Specification for requirements). Conceal all wiring within framework.
Mount all access control equipment recessed flush into door frames as side panels. Develop
details with M&E and Security Sub-Contractors and agree with the CA.
b) External swing doors shall incorporate the following:
i) Concealed head mounted overhead door closers to minimum class C to BS EN 1154
with fully adjustable spring power and backcheck facility.
ii) D line satin stainless steel pull handles both inside and outside, 19mm diameter, as
scheduled in lengths as indicated on the Tender Drawings and Door/ Ironmongery
Schedules, using satin stainless steel (Allgood Ltd 'D line' or acceptable equivalent).
iii) Keyed locks of the pin tumbler, cylinder high security (anti-pick) type, with a minimum of 6
pins. Double cross cut or side-pin cylinders shall be removable when the door is open but
shall not be removable when the door is closed.
iv) Locking and latching devices shall be suited to the door design and shall comply with the
requirements of BS EN 12209 category B locks and latches.
v) Automatic power operated doors shall comply with BS 7036.
vi) Suiteing to be co-ordinated with suiteing requirements for the building as a whole. Refer
to Section P21.
c) Where required, make provision for doors to remain in defaulted 'open position' in the event of a
fire emergency.
Glazing
• Provide a range of samples defining the upper and lower limits of variations in
colour.
• Sample range shall demonstrate that even distribution of aggregate can be
achieved to prevent settlement during curing.
• Sample range shall demonstrate that control of colour and colour shading can be
achieved to reduce colour and colour shading fluctuations.
x) Surface coatings: Provide proposals for acceptance by the CA.
xi) Panels to be sufficiently thick sheets as required to satisfy the design intent and the
performance criteria.
xii) All surfaces to have eased corners.
xiii) GRC to have acid etched finish texture and colour to be selected from the range of
proposed samples by the Architect.
h) Fixings:
i) All fixings shall be concealed. Fixing methods to be selected to suit the expected thermal
and moisture movement, shrinkage, hydration and the nature of materials to be fixed to as
well as the performance criteria to be satisfied. Provide suitable stainless steel bracketry
as required.
ii) All dissimilar metals to be separated to prevent bi-metallic corrosion.
i) All screens to be demountable.
j) Curing:
i) Curing methods are to ensure sufficient strength is achieved to meet the design intent
and structural requirements.
ii) Panels must be kept continually moist during curing or the use of an acrylic thermoplastic
copolymer dispersion with the agreement of the CA.. Duration of curing times to be as per
the manufacturers instructions and suitable for the local conditions.
All reinforcement to be provided to GRC profiles as required to meet the performance requirements.
Provide continuous stainless steel edge framing (picture frame) to GRC panels for support purposes
cast flush into GRC as shown on the design drawings, unless it can be demonstrated to the CA that
this is not required.
Copings
i) Make provision for BMU track connection into primary structure and coordinate with BMU
contractor and structural contractor for all interfaces. Refer to the structural engineers report
and the façade/access maintenance equipment works package for loadings and interfaces etc.
Flashings
H11.2218 Flashings
a) As indicated on the Design Drawings, aluminium flashings shall be provided. They shall be
treated with anti-drumming insulation on the protected face if required.
b) Flashings shall be PVDF coated to match the cladding.
c) Externally exposed flashings shall have continuation and interconnecting joints fully complying
with the sealant manufacturer’s written recommendations for movement joints; simple butt
straps shall not be accepted.
Fixings
H11.2222 Sealants
a) Sealant shall not leak or bleed causing any discolouration and runoff staining below or above
horizontal joints shall be avoided either on stone facing or on elements.
b) Structural Silicone Sealants:
i) All glazing requiring structural silicone bonding shall be glazed under controlled factory
conditions without any need for Site applied structural bonding sealant, unless accepted
otherwise by the CA.
ii) Structural sealant glazing design shall limit the design tensile stress of sealants to
138kPa.
H11.2223 Gaskets
a) Gaskets shall be made of either Ethylene Propylene material (EPDM/EP) or of Silicone. The
colour of all gaskets shall be black.
b) All visible room side glazing gaskets shall have factory vulcanised corners. All other gaskets
shall have overlapping joints with appropriate sealant in between. It is a condition that the
internal sealant of the entire envelope system has a continuous vapour and air seal. This also
includes all interfacing connections.
Miscellaneous Materials
Specification.
c) Framing to be designed to accommodate fixings related to any face fixed cladding systems.
Where fixings penetrate the breather membrane ensure that a water and vapour tight seal is
achieved.
d) Provide windposts as required, designed to meet the wind loading criteria specified.
e) Refer to Section Z11 of the Specification for steel generally.
H11.2228 Insulation
a) The insulation shall be inert, durable, rot-proof and vermin-proof and not be degradable by
moisture, extreme temperatures or water vapour.
b) The insulation shall not bulge, sag, delaminate or detach during its installation or in situ during
the life of the works.
c) Insulation shall be LPCB certified to LPS 1181.
d) Insulation shall have zero Ozone Depleting Potential (ODP), be CFC and HFC free and have a
Global Warming Potential (GWP) of less than five. Refer also to Section A.6000 of the
Specification.
e) Insulation shall be selected to meet the recommendations of ‘The Green Guide to Specification’
and shall have a minimal environmental impact when assessed using BREEAM/L.E.A.D
International criteria.
f) The selected insulation shall comply with all relevant British Standards and be BBA certified.
decoration and tapered edges for smooth seamless jointing. Board to be moisture resistant where
required.
H11.2300 FABRICATION
H11.2301 Fabrication of Curtain Walling Systems
a) Unless otherwise specified or agreed, curtain walling shall be fabricated as a unitised system.
b) Fabricate sections to accommodate and interface with work of other adjacent works by means
of rabbets, interlocks, miscellaneous angles, trim and filler sections, as required.
c) Component fastenings shall be concealed throughout, shall be of adequate strength, fabricated
from aluminium or stainless steel and shall be fusion welded where required. Jointing and
intersections of the metal shall be accurately cut and fitted to a tolerance of 1mm in true planes
with adequate concealed fastenings and sealed. Welds shall be ground smooth and flush,
buffed and polished so that they are indistinguishable from surrounding metal.
d) Reinforce mullions with aluminium or stainless steel sections as required. Secure aluminium
sections with adequate anchors to structure.
e) All gaskets shall be free from all contact and migration stain and compatible with all substrates,
sealants and finishes with which they have contact. Refer to Section Z36.
f) Provide inconspicuous, baffled weepholes to properly vent, and drain system cavities to exterior.
g) Fabricate glazing recess of sufficient depth to cover glass edge-seal. Refer to Section Z25.
d) Refer to Sections Z22 and Z25 and fabricate in accordance with Guideline for European
Technical Approved for Structural Sealant Glazing Systems (SSGS) ETAG No. 002.
a) Deviations in panel length, width and diagonal dimensions shall not exceed ±1mm.
b) The twist and warping shall not cause any point of the panel shall be more than 0.5mm out of
plane. The twist and warping shall not cause any point of the structural frame to be more than
2mm out of plane.
c) Alignment of joints between panels shall not exceed ±2mm.
d) Alignment of the faces between panels shall not exceed ±1mm.
H11.2400 FINISHES
H11.2401 Colours
a) Colours to be to RAL colours or anodising colours and specified by the CA. PVDF and
polyester powder coatings (30% gloss/70% matt). Colours to be determined on the basis of
samples provided for acceptance by the CA.
b) All finishes shall be of sufficiently durable quality to suit the prevailing environmental conditions
including wind-blown sand. Refer to Section Z31 for polyester powder coatings, Section Z33
for anodising and Section Z32 for PVDF coatings.
H11.2500 ANCILLARIES
Lightning Protection and Earth Bonding
H11.2501 General
a) Bonding is required between individual sections of cladding, in accordance with BS 6651 and
BS EN 62305: Parts 1-4, to ensure continuity between adjacent sections, both vertically and
horizontally over the whole façade. Bonding between sections shall have a minimum cross
section of 50mm².
b) Bonding between the cladding and structural steelwork shall be carried out at intervals at no
greater than 10m horizontally and 20m vertically. The first level of bonding to the structural
steelwork shall be at the highest floor level of each part of the building.
c) Provide studs/bolts on the cladding for subsequent connections to be made by the lightning
protection contractor.
d) All straps/connections shall be concealed.
e) No straps shall be fixed along copings.
Fixing Brackets for Blinds
H11.2502 General
a) Fixing brackets shall be provided fixed to the framework as indicated on the Design Drawings.
b) Brackets shall be compatible with the blinds proposed for incorporation.
Cradle Restraints
H11.3100 WORKMANSHIP
H11.3101 Generally
a) All works shall be true to detail with continuous profiles, free from marks, defects, flaws, steps,
waves, or damage of any nature.
b) Dimensions and levels of the structure shall be verified.
c) The glazing works shall be set out such that all framing members are installed in the correct
position, within tolerance, and in the correct relationship to the building structure.
d) All fixing bolts and anchors shall be installed in accordance with the manufacturer's
recommended procedures.
e) Materials shall be kept dry until fixed.
f) Acceptance shall be obtained from the CA before drilling or cutting parts of the structure, other
than where shown on the Working Drawings.
g) Isolating tape, plastic washers or other suitable means shall be used to prevent bi-metallic
corrosion between dissimilar metals.
h) Bars shall be set out at evenly spaced centres, straight, parallel and truly aligned with other
features where shown on the Working Drawings.
i) The finished work shall be square, regular, true to line, level and plane with a satisfactory fit at all
junctions.
j) Ensure that all interfacing requirements relating to fixings are provided. Liaise with the primary
structural steelwork/ concrete sub-contractor in due time prior to fabrication of structural
steelwork/ concrete to ensure that fixing holes, brackets, lugs, etc. are provided in correct
locations to agreed tolerances suitable for fixing curtain walling system as required.
k) Ensure that any remedial works are carried out where damage to structural steelwork finishes or
corrosion protection occurs.
l) Ensure that all interface requirements are provided relating to lightning protection and earth
bonding.
m) Ensure that all interfaces with roof covering systems and associated flashings are
accommodated as indicated on the Design Drawings.
n) Ensure that interfaces with internal bulkhead ceiling linings are accommodated.
o) Ensure that all interfaces with internal partitions and floor slabs are accommodated including
requirements for providing continuity of fire and acoustic separation as required.
a) The panel finishes shall be uniform in colour, texture and appearance, unless specified
otherwise.
b) Panel finish shall match the agreed Control Samples. Disregard and replace any units that do
not appear identical to the accepted samples.
H11.3200 TOLERANCES
H11.3201 Installation
a) The works shall be installed to meet the tolerances as specified below. These tolerances shall
be adhered to for the works in its completed installed condition. Make due allowance for any
structural movements and deviations including deformations caused by the installation itself
due, for example, to the effect of the self-weight of the cladding on its supporting structure. In
this respect, refer to the Project Common Movement and Tolerances Report document. In the
case of any doubt seek further advice from the Project Structural Engineer regarding the
deformations which shall be allowed for in the Detailed Design and installation.
b) Level: Set out following horizontal bands, each corner of the panel shall be placed to within
2mm of the design dimension to the corresponding Horizontal Location Reference Plane.
Further, the bottom edge of each cladding panel, based on the mean level of the respective
bottom corners, shall be placed to within ±1mm of the design dimensions from the
corresponding Location Reference Plane. Unless otherwise stated, the Location Reference
Plane shall be defined as the horizontal plane through the mean level of the tops of the primary
edge beam elements or slab edge to which each horizontal cladding panel band is
placed/suspended.
c) Plumbness: Each panel’s reference face (exterior face for external cladding, visible face for
single side exposure panels) shall be installed such that the respective offset distances of the
top and bottom edges of the panel to an adjacent true vertical line (plumbline) do not differ by
more than 2mm or 0.1% of the height of the panel, whichever is less.
d) Panel Plan Alignment: The panels shall be installed such that the distances of the respective
corners of the reference face to the cladding Location Reference Plane are within 3mm of the
Design Dimension and do not differ from each other by more than 2mm. This applies both to the
top and bottom edges of each panel. Unless otherwise stated, the Vertical Location Reference
Plane shall be defined as the mean plane of the edges of the primary edge beams or slab
edges corresponding to top and bottom widths of each cladding panel.
e) Transom alignment: The misalignment between the edge of a cladding panel and its supporting
transom shall not exceed 1mm.
f) Joints: Where adjacent elements are designed to have edges, lines or surfaces which line
through their common joint, the maximum allowed step across the joint is the lesser of ±2mm or
±10% of the joint width in any direction.
g) The works shall be erected plumb and in proper alignment and relation to established lines and
grades as shown on the Working Drawings. The erected system shall present true and accurate
lines and flat planes. Deviations from lines, planes and verticality shall be limited to long wave
formations of minimum wave length of 20m length with a rate of exchange not exceeding
1:1000 and a maximum amplitude of 3mm. All the above shall be measured from an optical or
laser reference line.
h) All tolerances stated shall be measured and monitored at a mean temperature to be agreed with
the CA. Before work begins on Site the proposed method of dimensional setting-out and cross-
checking with adjacent trades and elements, to satisfy the accuracy requirements, shall be
submitted to the CA. The checking of any setting-out or of any line or level by the CA, or his
representative, shall not in any way relieve the Contractor of his responsibility for the
correctness thereof.
i) Alternative tolerances to those specified may be permitted at the CA's discretion, provided they
are agreed in advance of the manufacture of components.
j) Tolerances shall not be cumulative.
deviation of the horizontal distance between any two adjacent elements is ±2mm from the
corresponding Design Dimension.
c) Verticality: For any element connecting two or more reference levels, the maximum allowed
deviation of the relative plan position in any direction of that element at any two successive
levels is ±2mm from the corresponding Design Dimension.
d) Planarity: Any element or group of elements whose position is defined from a reference plane
shall not deviate from the Design Dimension of the reference plane by more than ±2mm
measuring perpendicular to the defined plane.
End of Section
APPENDIX A
Testing of EWS-40a
Introduction
A performance test is proposed for the Office Tower EWS-40a to verify performance predictions and tune physical
parameters. The performance test is not intended to verify aesthetic properties of the façade system and shall be
entirely separate from any specified requirements for aesthetic mock ups and tests. It should be noted that the
performance tests will need to be carried out in advance of the visual mock-ups.
− an external double glazed unit (DGU) with high performance reflective solar coating and low E coating
− a blind in the cavity between the DGU and back up wall – it is likely that the blind will normally be fully lowered
and occupants will be given ‘tilt’ control only.
− the cavity is internally ventilated using exhaust air from the adjoining office space
− Maximum views
− Limit solar gain with the reflective coating and ventilated cavity which removes heat at source
− Reduce peak cooling load in perimeter office areas and reduce energy required for cooling
− Maximize comfort at the perimeter by cutting down direct solar gain and reducing surface temperatures of the
room facing glass
− Verify thermal performance predictions under design conditions, particularly overall heat gain (SHGF and G-
Value)
− Optimise mounting position of the blind in the cavity and its impact on thermal transmittance and comfort
− Ensure proposed ventilation inlet and outlet positions and sizes avoid blind ‘flutter’ and confirm there is no
requirement for blind guides
Whilst the test could also be used to confirm the required performance in terms of avoidance of condensation on
mullions and glass, this would require actual mullion sections and the added complication of replicating external
humidity as well as temperature. For the time being condensation checks will therefore NOT form part of this test
programme.
The Tenderer shall include in his Tender for laboratory testing in a facility that can provide the facilities and testing
described below and in particular can faithfully create the design conditions. The Tenderer may propose alternative
methodologies for the physical testing, such as field testing. However, a laboratory test is preferred for its ability to
control all parameters consistently during the test programme.
− The test shall be conducted in a climate chamber where the design internal and external conditions can be
created either side of the Abluftfenster. The key is to re-create near-design conditions without too many
compromises. The internal temperature shall be maintained by a recirculating fan coil with supply diffusers
located so as not to influence the test results. The design conditions to be created are:
− Simulated solar energy with similar short wave radiation spectrum at variable altitude and a
radiation flux up to 1,000 W/m²
− The section of façade for testing shall faithfully replicate all physical features that could impact on the tests and
results. Ideally, this would be a true mock up with correct framing and mullion details but the development
programme may not allow this. Key physical components shall include:
− Actual glass configuration for DGU and inner back up wall – glass thicknesses, solar
coating, low E coating, spacing, etc
− Framing with equivalent dimensions and thermal properties to the final frame
− Blind matching the architect’s preferred blind – material, finish/reflectance, perforation and
position relative to the DGU/back up wall. Position of the blind within the cavity to be
adjustable.
− Ventilation inlets and outlets shall match the design proposals in terms of numbers, size,
location, etc.
− Ventilation flow rates through the cavity shall be capable of being varied in the range 4-20 l/s per linear metre
of façade. An extract fan and ductwork connected via a plenum to the top of cavity shall draw air into the
cavity from the ‘internal’ room. A separate supply ventilation system shall provide make-up air. The make-up
air will need to be cooled and supplied to the internal room so as not to influence the test results.
Testing of EWS-20c
Introduction
A performance test is proposed for the T1 Hotel and T2 Residential thermal tube panels to verify performance
predictions and tune physical parameters. The performance test is not intended to verify aesthetic properties of the
façade system and shall be entirely separate from any specified requirements for aesthetic mock ups and tests. It
should be noted that the performance tests will need to be carried out in advance of the visual mock-ups.
The test shall be carried out by the Cladding Contractor in conjunction with the preferred supplier of the solar thermal
tubes. The experience of the supplier with regard to thermal tube performance shall be used in finalising the details
and running of the tests.
Façade Panels
− an external ‘clear’ single glazed unit – minimum Solar Transmittance 75% - refer to Specification for full
performance data
− an internal ‘reflective’ double glazed back up wall which is openable to facilitate cleaning and maintenance –
refer to Specification for glass performance
− Panels are oriented as close as possible to ESE (-66.5°) and WSW (+66.5°) to achieve homogenous solar
collection ability over the year
Performance Requirements
− Minimum specific collector output for ESE orientation – 725kWh per annum per m² panel aperture area (ie
excluding headers and fixings), excluding circulation line losses.
Testing
− Verify thermal performance of the panel under design conditions, particularly overall heat gain (SHGF and G-
Value)
− Prove solar energy collection capability and demonstrate by testing and calculation that the specified
performance requirements will be achieved – for ESE orientation
− Extend the testing and calculations to provide an overall annual energy collection profile for the entire system
of solar collectors.
− Verify all glass surface temperatures under peak thermal design conditions with and without thermal tubes
operational
The Tenderer shall include in his Tender for laboratory testing in a facility that can provide the facilities and testing
described below and in particular can faithfully create the design conditions. The Tenderer may propose alternative
methodologies for the physical testing, such as field testing. However, a laboratory test is preferred for its ability to
control all parameters consistently during the test programme. The Tenderer shall provide a full method statement for
testing and calculations for approval.
− The test shall be conducted in a climate chamber where the design internal and external conditions can be
created either side of the façade panel. The key is to re-create near-design conditions without too many
compromises. The internal temperature shall be maintained by a recirculating fan coil with supply diffusers
located so as not to influence the test results. The design conditions to be created are:
− Simulated solar energy with similar short wave radiation spectrum at variable altitude and a
radiation flux up to 1,000 W/m²
− The laboratory shall accommodate a minimum 3m length of façade and a panel one storey high
− The section of façade for testing shall faithfully replicate all physical features that could impact on the tests and
results. Ideally, this would be a true mock up with correct framing and mullion details but the development
programme may not allow this. Key physical components shall include:
− Framing with equivalent dimensions and thermal properties to the final frame
− Thermal tubes configured with pipework connections and pumping/water flow arrangement
to recommendations of thermal tube supplier.
Contents
H31 METAL PROFILED SHEET CLADDING/COVERING/SIDING ......................3
H31.2400 FINISHES/COLOURS....................................................................................................... 8
H31.2401 Colours..............................................................................................................................................................................................8
H31.2403 Anodising................................................................................................................................... Error! Bookmark not defined.
H31.2500 SUNDRIES.......................................................................................................................... 8
Lightning Protection and Earth Bonding .................................................................................................................................. 8
H31.2501 General .............................................................................................................................................................................................8
H31.1304 Mock-ups
A mock-up shall be provided in accordance with Section A.4000 as follows:
Single column of the works including all interfaces..
H31.1305 Prototypes
A prototype shall be provided in accordance with Section A.4000 as follows:
Single column of the works including all interfaces.
H31.1401 General
The Contractor shall have a full understanding of the structural behaviour of the building and how it
affects the works.
H31.1410 Condensation
No condensation shall take place either on internal or external surfaces under the temperature and
humidity conditions specified.
H31.1411 Capillarity
Water migration caused by capillarity shall be prevented to areas that are designed to remain dry.
H31.1415 General
a) The performance criteria shall be satisfied for the full design life of the works, provided always
that the maintenance has been carried out as specified.
b) Metal sheets shall not suffer bowing, dimpling, oil canning, sagging, pillowing, rippling, warp,
abrupt transitions and other visual deformation or irregularity.
H31.1417 Demountability
a) Elements of the works shall be individually and independently removable for maintenance and/or
replacement of panels in the event of damage.
b) The removal of panels shall not affect the performance or safety of any other part of the works.
H31.2100 SYSTEMS
External Wall Cladding
a) Aluminium panelling system forming vertical cladding of aluminium profiles bonded onto suitable
moisture resistant backing boards and fixed to a secondary support structure forming a façade
to the concrete columns, aluminium panels as shown on the Design Drawings.
b) Aluminium to be colour anodised.
c) Provide concealed/secret supports/bracketry as required and as shown on the Design
Drawings.
d) To be fixed to the concrete columns as indicated on the Structural Engineer’s drawings.
H31.2200 MATERIALS
H31.2203 Profile Fillers
Type(s) supplied by the manufacturer accurately matching sheet profile and perforated for ventilation
and drainage of condensation at centres of crowns/troughs as appropriate.
H31.2208 General
Refer to Section Z20 of the Specification.
H31.2300 FABRICATION
Tolerances
a) The following tolerances apply to each individual panel manufactured, assembled and ready for
installation:
i) Length/ Width: Maximum allowed deviation of side length shall be 1.5mm up to 3000mm
and 3.0mm above 3000mm of design dimension.
ii) Panel Thickness/ Depth: Maximum allowed deviation is ±0.5mm.
H31.2400 FINISHES/COLOURS
H31.2401 Colours
a) Anodised aluminium shall be from the RAL range. CA to confirm.
b) Refer to section Z33 for anodising.
H31.2500 SUNDRIES
Lightning Protection and Earth Bonding
H31.2501 General
a) Provide bonding between individual sections of cladding, in accordance with BS 6651 and BS
EN 62305: Parts 1-4, to ensure continuity between adjacent sections, both vertically and
horizontally over the whole façade. Bonding between sections shall have a minimum cross
section of 50mm². Any bolts used for bonding shall be of a minimum size of M10.
b) Bonding between the cladding and structural steelwork shall be carried out at intervals at no
greater than 10m horizontally and 20m vertically. The first level of bonding to the structural
steelwork shall be at the highest floor level of each part of the building.
c) Provide studs/bolts on the cladding for subsequent connections to be made by the Lightning
Protection contractor.
d) All straps/connections shall be concealed.
H31.3100 WORKMANSHIP
H31.3101 Generally
a) All works shall be true to detail with continuous profiles, which shall be free from marks, defects,
flaws, steps, waves, or damage of any nature.
b) All elements of framework and components shall be stored on Site such that they shall not be
damaged, distorted or weathered unevenly.
c) All finished components shall be carefully packed in stillages or crates such that they are
suitably separated and protected to prevent scratching, scuffing or other surface damage.
d) Dimensions and levels of the structure shall be verified.
e) Setting out shall be such that all panels are installed in the correct position, within tolerance,
and in the correct relationship to the building structure.
f) All fixing bolts and anchors shall be installed in accordance with the manufacturer's
recommended procedures.
g) Materials shall be dry until fixed.
h) Acceptance shall be obtained from the CA before drilling or cutting parts of the structure, other
than where shown on the Shop Drawings.
i) Isolating tape, plastic washers or other suitable means to prevent bi-metallic corrosion between
dissimilar metals shall be used.
j) The finished work shall be square, regular, true to line, level and plane, with a satisfactory fit at
all junctions.
Assembly of Components
H31.3107 Structure
Check that the structure is in a suitable state to receive cladding before commencing fixing and
obtain acceptance from the CA.
H31.3110 Abutments
Ensure a weathertight junction with flashings, which shall be correctly located and neatly dressed
down.
H31.3112 Insulation
a) The insulation board shall be attached to or supported within the works so as not to bulge, sag,
delaminate or detach during installation or in situ during the life of the works.
b) Install and secure as the work proceeds ensuring continuity between
supports/purlins/rails/spacers and leaving no gaps. Keep dry and do not compress.
c) Cut back or debond the minimum necessary and to a clean straight line ensuring there are no
gaps in insulation after fixing.
H31.3200 TOLERANCES
H31.3201 Installation Tolerances
a) Horizontal Plan Position: For any element at any level whose position is defined in relation to a
primary reference grid, the maximum allowed deviation from the Design Dimension to that
reference grid is ±2mm.
b) Where a series of elements are arranged in an array of two or more, the maximum allowed
deviation of the horizontal distance between any two adjacent elements is ±2mm from the
corresponding Design Dimension.
c) Verticality: For any element connecting two or more reference levels, the maximum allowed
deviation of the relative plan position in any direction of that element at any two successive
levels is ±2mm from the corresponding Design Dimension.
d) Planarity: Any element or group of elements whose position is defined from a reference plane
shall not deviate from the Design Dimension of the reference plane by more than ±2mm
measuring perpendicular to the defined plane.
e) Deviations from lines, planes and verticality shall be limited to long wave formations of minimum
wave length of 20m length with a rate of exchange not exceeding 1:1000, and a maximum
amplitude of 3mm. All the above shall be measured from an optical or laser reference line.
f) The width of any joint shall not deviate from the nominal width by more than ±1mm of the joint
width, whichever is the lesser. Any variation shall be equally distributed with no sudden
changes. The misalignment between joints shall not exceed 1mm.
g) Line and level shall be within ±2mm of the specified level. The cumulative slope between the
same locations on any panel shall not exceed 1 in 1000.
h) The works shall be erected such that no point on any panel is more than 1mm from its
theoretical plane. The cumulative slope between the same locations on any panel shall not
exceed 1 in 1000.
i) The dimensional and detailed provisions intended to accommodate the construction tolerances
of surrounding elements in order to ensure that all aspects of the works relate satisfactorily to
the works as a whole shall be stated and shown on the Shop Drawings.
j) All tolerances stated shall be measured and monitored at a mean temperature to be agreed with
the CA.
k) Before work begins on Site the proposed method of dimensional setting-out and cross-
checking with adjacent trades and elements, to satisfy the accuracy requirements, shall be
submitted to the CA. The checking of any setting-out or of any line or level by the CA, or his
representative, shall not in any way relieve the Contractor of his responsibility for the
correctness thereof.
l) Alternative tolerances to those specified may be permitted at the CA’s discretion, provided they
are agreed in advance of the manufacture of components.
m) The works, when installed, shall not be subject to warping or twisting, shall be strictly rigid, firm,
free from vibration, knocking, rattles, squeaks and other noises when subject to the worst
combination of environmental conditions and wind loads.
n) Tolerances shall not be cumulative.
End of Section
Contents
H42 PRECAST CONCRETE CLADDING .................................................................3
iv) The method statement to include details of proposals for repair of any damage to panels
including cleaning of installed panels which may be envisaged during all stages of
production and installation including all proposals for temporary protection and
transportation methods.
v) Samples where specified.
vi) List of Tests included.
vii) QA/QC programme.
viii) List of proposed Shop Drawings.
ix) Summary of deviations from the Specification.
x) Outline technical specifications reflecting proposed materials/systems.
xi) A list of proposed suppliers and sub-contractors intended to be used.
Samples, Mock-ups, Prototypes and Quality Benchmarks
H42.1304 Mock-ups
Refer to Section H11 for mock up requirements.
H42.1305 Prototypes
A prototype in accordance with Section A.4000 shall be provided as follows:
To be confirmed.
H42.1401 General
a) The external works elements shall be designed, constructed and installed to meet the
requirements of BS 8200 and BS 8297.
b) The supporting framework for precast concrete units shall be fixed back to the primary
structure, details of which are to be found in the Structural Engineer's specification and
drawings.
c) Requirements specified in this section apply to the entire works (unless otherwise noted),
including flashings and junctions with adjacent parts of the building. Full allowance must be
made for deflections and other movements.
d) The design shall take account of all structural criteria and ensure that the works take account of
all movements and tolerances, in both permanent and temporary conditions, in order to avoid
stress, deformation and failure.
e) Ensure that the structure to which the works is being installed, including tolerances and
deflections, are suitable to receive the works. This shall be monitored and verified throughout
the contract period.
f) Provide structural calculations, prior to manufacture, supporting design integrity and justifying
the selection of materials, fixings, etc.
g) All structural calculations prepared shall be submitted for checking to the CA. Such checking
shall not relieve the Contractor of his obligations in respect of the final detailed design.
h) Tolerances: To BS 5606, BS 8298, BS 8297 and as specified herein.
Structural
H42.1402 General
a) Refer to Section A, clause series A.5300.
b) The works shall be designed in accordance with BS 8110 to resist all dead and live loads and
in accordance with the Structural Engineer’s specification and drawings for the frame and
cladding.
c) Be responsible for ascertaining all dead and live loads imposed as relevant to the precast
concrete cladding system and its supports.
d) The design and detail of the Precast Concrete Cladding system shall accommodate all the
various tolerances and movements of the building structure. Movements of the building
structure will occur from the application of dead, live and wind loads plus moisture, shrinkage,
creep and thermal effects.
e) Provide structural calculations, prior to manufacture, supporting design integrity and justifying:
i) The selection of concrete mix and any reinforcing including compressive strength of
concrete.
ii) Methods of fixing and support bracketry.
iii) Fixing devices including pull out loading.
f) The Precast Concrete Cladding system shall resist all specified static and dynamic design
loads likely to be encountered without causing permanent deformation of components or the
failure of fixings, panels or seals and shall transmit such loads safely to the points of support.
H42.1406 Deflections
a) See the Structural Engineer's specification for deflections associated with the primary structure.
b) The precast concrete cladding shall not deflect under loading in any way that is detrimental to
any element of the Precast Concrete Cladding or the adjacent structural or building elements.
c) Co-ordinate the Detailed Design with that for all related works and accommodate the specified
movements, tolerances and deflections for structural elements as specified in the Structural
Engineering specifications and 'Tolerance Movement and Deflection Schedule'.
d) Deflection of works shall be limited to 0.003 x span at test pressure level calculated in
accordance with BS 6399: Part 2 (minimum 1200 Pa) combined with dead and imposed loads.
e) All components, couplings and fixings shall be capable of accommodating all of the above
deflection without permanent distortion, deformation or failure.
f) The works shall accommodate differential structural movements arising from any loads imposed
by adjacent structures.
g) The magnitude of the allowable deflections shall be reduced if they are detrimental to any part
of the works, their support structure or internal finishes.
H42.1413 Capillarity
Water migration caused by capillarity shall be prevented. Vertical joints to be designed to eliminate
capillarity. Joints to be open but designed so the substrate behind the concrete cladding is not
visible. Refer to Design Drawings for indicative design of open joints.
Provide details of all interfaces allowing sufficient time for the CA to comment, and to allow such
comments to be implemented.
H42.1420 General
a) The works shall achieve 120 minutes fire rating unless otherwise specified on the Design
Drawings.
b) The panel surfaces shall have Class 0 surface spread of flame, in accordance with BS 476:
Part 7.
Durability
H42.1421 General
The performance criteria shall be satisfied for the full design life of the works, as stated in the
Specification, provided always that the maintenance has been carried out as specified.
H42.1422 Demountability
a) Elements of the works shall be individually and independently removable.
b) The removal of works units shall not affect the performance or safety of adjacent or any other
part of the works.
Primary and Secondary Components
columns.
f) Cover to reinforcement: The Contractor shall determine the minimum cover to meet the relevant
standards.
g) Joints between panels shall be open as required to satisfy the performance requirements. Open
joints shall be nominal 20mm unless otherwise agreed.
h) Joints requiring to have mortar joints shall have lime mortar joints. The mortar shall be not less
than a 3:1 sand/ hydraulic lime Mix 'H' in accordance with Section Z21.
i) Sands shall be well graded crushed stone or similar with colour match to accepted samples to
suit joint thickness(es) of between 2-4mm and shall be washed and free from salts.
j) Refer to Section Z22 for sealants generally.
k) Fixings/ cramps and dowels shall be austenitic stainless steel grade 1.4401 (316) to BS EN
10088 and in compliance with BS 8298. Refer to Section Z11. To be fixed as Section Z20.
The Contractor shall be responsible for designing all fixings and support systems in accordance
with the design intent as indicated on the Design Drawings and in accordance with the
Structural Engineer's specification and drawings.
l) Sizes of panels shall be as indicated on the Design Drawings.
H42.2200 MATERIALS
Concrete
H42.2201 Moulds
a) Casting deviations shall be readily controlled to comply with the Specification.
b) Maintain in clean, sound condition and inspect carefully for defects before each reuse.
Damaged moulds shall not be repaired and reused if this would impair the surface appearance
of the units.
c) Construct to prevent loss of grout.
d) Permit demoulding without damage to units.
e) Coat evenly with a suitable release agent, which shall not be allowed to touch the
reinforcement.
f) Moulds inspection: Inform the CA when each mould is complete and not less than 5 days
before commencing manufacture of units.
H42.2203 Reinforcement
a) Deformed bars shall be to BS 4449.
b) Galvanised finish shall be to BS EN ISO 1461 zinc coating applied before manufacturing.
c) Prestressing steel strands shall be to BS 4486.
d) Welded wire fabric shall be:
i) To BS 4483, fabricated of plain cold-drawn steel wire conforming to BS 4482.
ii) Furnished in flat sheets.
iii) Galvanised to BS EN ISO 1461 when fabric is within 38mm of panel face.
e) Steel wire shall be to BS 4482 and galvanised to BS EN ISO 1461.
iii) Adjust the design mix to obtain the required colour, texture and grade of the surface
aggregate.
iv) Maximum water absorption for normal weight concrete not to exceed 5% by weight.
c) Batching and Mixing:
i) Plant shall conform to the requirements of BS 8500: Parts 1 and 2 and BS EN 206: Part
1.
ii) Volumetric batching of concrete is not permitted.
iii) Accurately measure the concrete components by weight within the tolerance limits of BS
8500: Parts 1 and 2 and BS EN 206: Part 1.
iv) The concrete temperature at the time of placement shall not exceed 29°C.
Miscellaneous Materials
H42.2207 Insulation
a) The insulation shall be inert, durable, rot-proof and vermin-proof and not be degradable by
moisture, extreme temperatures or water vapour.
b) The insulation shall not bulge, sag, delaminate or detach during its installation or in situ during
the life of the works.
c) Insulation shall be LPCB certified to LPS 1181.
d) Insulation shall have zero Ozone Depleting Potential (ODP), be CFC and HFC free and have a
Global Warming Potential (GWP) of less than five. Refer also to Section A.6000 of the
Specification.
e) Insulation shall be selected to meet the recommendations of ‘The Green Guide to Specification’
and shall have a minimal environmental impact when assessed using BREEAM/L.E.A.D
International criteria.
f) The selected insulation shall comply with all relevant British Standards and be BBA certified.
Metalwork
H42.2300 FABRICATION
H42.2301 Sizes Generally
The works units shall be worked to sizes indicated on the Design Drawings and be within the
recommended deviations. They shall hold out reasonably square at the back, i.e. without corners
broken away whereby the strength of the fixings system may be impaired.
herein.
b) Check the overall dimensions, straightness, squareness, twist and flatness of the mould(s)
immediately before each reuse and of each unit as soon as possible after demoulding. Make
adjustments to the moulds as necessary.
H42.2304 Casting
a) Provide face mix for full panel depth when more than one major face or edge is exposed.
b) Cast ‘U’ and ‘L’ shaped panels in a single casting so as not to have a visible casting joint.
c) Where only one face of the precast component is exposed, use a single facing mix throughout
the entire thickness of the unit or place the facing mix and back-up mix consecutively in forms
as follows:
i) Use Portland cement and aggregate specified for the facing mix and use Portland cement
and aggregate mix to meet the design performance criteria for the back-up mix.
ii) Place and consolidate the facing and back-up mixes to achieve a monolithic panel
construction.
iii) Depth of facing: 44mm minimum.
d) Cast units in an enclosure to maintain a controlled ambient temperature. Mix concrete to
distribute fine and coarse aggregate evenly.
e) Place to prevent concrete segregation in forms.
f) Manufacture units to required profiles and size. Execute work accurately to specified tolerances
and free of broken edges. Manufacture edges straight and with clean accurate arrises.
g) Ensure that exposed edges and ends match the finish and texture of the face of the panel.
h) Identification: Mark each panel with an identification mark corresponding to the Shop Drawings
and date cast.
H42.2307 Inspection
Carefully inspect all completed units and check for match with accepted sample(s) or control unit(s)
and for compliance with the Specification before dispatch to Site. Make arrangements with the CA
for the inspection of completed units in the factory.
H42.2308 Records
a) Keep complete records for each unit including the following information:
i) Unique identification number.
ii) Correlation with records of mixes, including batch numbers.
iii) Date of each stage of manufacture.
iv) Dates and results of all tests, checks and inspections.
v) Dimensions related to specified levels of accuracy.
vi) Specific location in the finished work.
vii) Details of any damage and making good.
viii) Any other pertinent data, e.g. if the unit is an accepted production control unit.
b) Records shall be available for inspection on request.
H42.3100 WORKMANSHIP
H42.3101 Construction Generally
Conform to the procedures of the British Precast Concrete Federation and BS 8297.
H42.3103 Storage
Store precast concrete units clear of the ground, protect from inclement weather and keep dry.
Prevent soiling, chipping and contamination by salts and other deleterious substances.
H42.3107 Cleaning
a) Clean any dirt or blemishes from exposed surfaces.
b) Wash and rinse in accordance with the precast manufacturer’s recommendations.
c) Protect adjacent surfaces from damage due to cleaning operations.
d) Do not use cleaning materials or processes that could alter the character of exposed finishes.
End of Section
Metalwork ......................................................................................................................................................................................... 8
L10.2201 Aluminium .........................................................................................................................................................................................8
L10.2202 Mild Steel..........................................................................................................................................................................................8
Sealants and Gaskets ................................................................................................................................................................... 8
L10.2203 Sealants ............................................................................................................................................................................................8
L10.2204 Gaskets.............................................................................................................................................................................................8
Support Structure/ Fixings........................................................................................................................................................... 8
L10.2205 Support Structure ..........................................................................................................................................................................8
L10.2206 Fixings................................................................................................................................................................................................8
L10.1201 General
a) Single bank shallow section louvre system integrated into the cladding system as required as
shown on the Design Drawings. Louvres to comprise extruded aluminium profiles to satisfy the
design intent as shown on the Design Drawings with PVDF finish externally. Refer to Section
Z11.
b) Louvres to provide class A rain defence to comply with the HEVAC standard and to incorporate
sand traps and insect mesh.
c) Aluminium louvre blades shall comprise single piece extrusions of profile depth/pitch to meet
the performance requirements with aluminium framing, end capping pieces, connectors and
support bracketry as required for fixing back to the curtain wall mullions.
d) The aluminium extrusions shall be to BS EN 573: Parts 1-3, BS EN 515 and BS EN 755: Parts
1-9.
e) Refer to the M&E specification for requirements for blanking panels, dynamic performance,
pressure drop and free area requirements for all louvres.
f) Provide blanking plates to all non-active louvres. Blanking plates to be PVDF finished matt
black. Refer to the M&E specification and drawings for requirements for blanking panels.
Custom made aluminium louvred wall system and framing with sand traps and incorporating louvred
door EDR-05. Provide blanking panels as required. Refer to the M&E specification for details of
ventilation requirements/blanking panels. The external louvres to comprise extruded aluminium blades
at 45 degree angle including insect/vermin mesh behind. Finish to louvres to be colour anodised.
Anodising colour to be advised.
L10.1304 Mock-ups
Architectural Specification – Tower 2 and L10/4 Foster + Partners
Tower 3- Wall and Rooflight System
Tender Issue
27/07/07
Central Market Development, Abu Dhabi
L10.1305 Prototypes
Subject to previous testing results being provided. Provides prototypes for testing if required.
L10.1306 Benchmarks
The following quality benchmark shall be provided in accordance with Section A.4000:
The first fully installed and completed part of the works.
Testing
L10.1401 General
When calculating loads the worst combinations shall be considered, taking account of the fact that
the pressure coefficients at various locations may determine more than one design criterion.
L10.1402 Deflections
The maximum in-plane deflection of any main framing member due to dead and live loads shall not
exceed 1/500 of the span or 3mm, whichever is the lesser.
L10.1416 General
All elements of the works shall be either non-combustible or not easily ignitable with low flame spread
characteristics and shall not produce excessive quantities of smoke or toxic gases.
L10.1419 General
The performance criteria shall be satisfied for the full design life of the works, as stated in the
Specification, provided always that the maintenance has been carried out as specified.
L10.1422 Demountability
a) Elements of the works shall be individually and independently removable ensuring access for
maintenance.
b) The removal of units shall not affect the performance or safety of any other part of these, or
adjacent, works.
L10.2100 SYSTEMS
Louvres
L20.3107 Ironmongery
Assemble and fix carefully and accurately using fastenings with a matching finish supplied by the
ironmongery manufacturer. Prevent damage to ironmongery and adjacent surfaces. At completion
check, adjust and lubricate as necessary to ensure correct functioning.
L10.2200 MATERIALS
Metalwork
L10.2201 Aluminium
a) Aluminium sheeting to be of thickness to suit performance criteria. Unless specified otherwise,
aluminium sheeting shall be a minimum of 3mm thick and satisfy the requirements of BS EN
485: Parts 1-4, BS EN 515 and BS EN 573: Parts 1-4.
b) Refer also to Section Z11.
L10.2203 Sealants
Refer to Section Z22.
L10.2204 Gaskets
a) Gaskets shall be made of either Ethylene Propylene material (EPDM/ EP) or of Silicone. The
colour of all gaskets shall be black.
b) Refer to Section Z36.
Support Structure/ Fixings
L10.2206 Fixings
Fixing components shall comply with all statutory requirements (and be to the acceptance of the
District Surveyor/ Building Control Officer/Structural Engineer) both as to strength and type and shall
be designed to carry all dead, live and wind loading under due consideration of any applicable
thermal movements. Select suitable components and fixings in accordance with the following:
a) Fixing components for the works shall comprise stainless steel components of high grade
austenitic stainless steel exterior quality to BS EN 10088, BS EN 10084, BS EN 10087, BS
EN 10095, BS EN 10048, BS EN 10051, BS EN 10250: Part 4 and BS EN ISO 9445 and BS
8298.
b) Any sheet mild steel, cleats, angles, fixing brackets, etc. used in the fixing assemblies shall
comply with BS 7668, BS EN 10029, BS EN 10210 and BS EN 10025: Parts 1-4 and 6 and
rolled sections shall be used wherever practicable or appropriate. Steel sections used shall be
hot-dip galvanised to the requirements of BS EN ISO 1461 after all cutting, drilling of holes and
welding has been completed.
c) All non-visible supporting aluminium sub-constructions shall be corrosion protected. Mill
finished aluminium shall not be used. Aluminium sub-constructions shall be separated from
concrete by bitumen paint or similar acceptable method. Austenitic stainless steel to BS EN
10088 may be used in lieu of aluminium for any supporting sub-constructions.
d) Fixing bolts, nuts, screws, washers, etc. shall be manufactured from austenitic stainless steel
complying with BS EN ISO 3506: Parts 1 and 2. All screw fixings and attachments shall be
secured against vibrating loose.
L10.2300 FABRICATION
L10.2301 Tolerances for Manufacture
a) Assembly: The physical fitting together of any assembly of sub-elements shall be properly
allowed for in the Detailed Design of the corresponding sub-elements.
b) The following tolerances apply to each individual component:
i) Length/Width: Maximum allowed deviation is the lesser of 1.5mm up to 3000mm and
3.0mm above 3000mm of design dimension.
ii) Thickness/Depth (extrusion tolerances nominally): Maximum allowed deviation is ±0.5mm.
L10.3100 WORKMANSHIP
L10.3101 General Requirements
a) The works shall be erected plumb (or at the angles prescribed) and true in proper alignment
and relation to established lines and grids as shown on the Shop Drawings. The erected system
shall present true and accurate lines and flat planes. Deviations from lines, planes and verticality
shall be limited to long wave formations of minimum wave length of 20m length with a rate of
exchange not exceeding 1:1000, and a maximum amplitude of 3mm. All the above shall be
measured from a laser reference line.
b) Joints between panels: The actual width of any joint shall not deviate from the nominal width by
more than ±2mm or 10% of the joint width whichever is the lesser. Any variation shall be
equally distributed with no sudden changes. The misalignment between joints shall not exceed
2mm.
c) Level: The works shall be within ±2mm of the specified level. The cumulative slope between the
same locations on any panel shall not exceed 1 in 1000.
d) Plumbness: The works shall be erected such that no point on any panel is more than 3mm from
its theoretical vertical/diagonal plane. The cumulative slope between the same locations on any
panel shall not exceed 1 in 1000. The vertical plane shall be within ±2mm of the theoretical
plane position.
e) A method statement detailing proposals to achieve the specified tolerances shall be submitted
with the Tender. This shall demonstrate a clear understanding of the construction programme,
the effects of the building structure and construction method and the fabrication method of the
panels.
f) Sufficient analysis of the erection sequence shall be undertaken to ensure that the installation
tolerances stated above shall be met to the acceptance of the CA.
g) Dimensional Checking: Before work begins on Site the proposed method of dimensional
setting-out and crosschecking with adjacent trades and elements to satisfy the accuracy
requirements shall be submitted to the CA. The checking of any setting-out or of any line or
level by the CA, or his representative, shall not in any way relieve the Contractor of his
responsibility for the correctness thereof.
h) Alternative Tolerances: Alternative tolerances to those specified may be permitted at the CA's
discretion, provided they are agreed in advance of manufacture of components.
i) The Shop Drawings shall provide for sufficient tolerance in manufacture of the works in order to
accommodate manufacturing tolerances of interfacing elements.
j) The tolerances stated herein shall be adhered to. No revisions to the tolerances to cater for
inadequate control shall be permitted.
k) Full details shall be submitted to the CA for review of the proposed methods for achieving and
constantly monitoring the fabrication tolerances during all stages of the work. Detailed records
of the constant control and tolerances achieved shall be submitted to the CA.
l) The works, when installed, shall not be subject to warping or twisting and shall be strictly rigid,
firm, free from vibration, knocking, rattles, squeaks and other noises when subject to the worst
combination of environmental conditions and wind loads.
m) All tolerances stated shall be measured and monitored at a mean temperature to be agreed with
Architectural Specification – Tower 2 and L10/10 Foster + Partners
Tower 3- Wall and Rooflight System
Tender Issue
27/07/07
Central Market Development, Abu Dhabi
the CA.
n) No rainwater ponding shall be permitted on any element of the works.
End of Section
Contents
Z11 METALWORK........................................................................................................2
Z11 METALWORK
To be read in conjunction with Section A and other related sections of the Specification, Preliminaries
and Contract Conditions.
Z11.2100 MATERIALS
Z11.2101 Metal Components
a) The Detailed Design of sections, material thicknesses and the dimensions shown on the Design
Drawings shall be maintained within specified tolerances.
b) All materials and components shall be durable and to the minimum standards set out in the
Specification, together with the relevant British Standards.
c) For each material or component, the total quantity shall be obtained from the same supplier or
manufacturer unless otherwise agreed with the CA.
d) All inaccessible steel shall be properly protected against corrosion for the design life of the
Works.
e) All support systems shall be of adequate thickness and strength, to meet the structural
requirements and eliminate risk of distortion in finished surfaces.
f) Protection shall be provided until handover to avoid any blemishes on the finished elements.
g) All exposed metalwork shall be finished in accordance with the relevant British Standards.
Unless otherwise specified, concealed items shall be mill finished aluminium in internal
conditions only, or hot dip galvanised steel in accordance with BS EN ISO 1461. Any cut
edges shall be treated to ensure that the level of protection is maintained.
h) Adequate measures shall be taken to prevent bi-metallic corrosion between dissimilar metals
and to isolate aluminium components from cementitious surfaces. To this end attention is drawn
to publication PD 6484 'Commentary on corrosion at bi-metallic contacts and its alleviation'.
Z11.2103 Aluminium
a) All extruded aluminium alloy members shall be fabricated from the appropriate grade of
aluminium alloy complying with BS EN 754: Parts 3-5 and BS EN 755: Parts 1-9 unless
otherwise specified.
b) Unless specified otherwise, aluminium sheeting shall be a minimum of 3mm thick and satisfy the
requirements of BS EN 485: Parts 1-4, BS EN 515 and BS EN 573: Parts 1-4.
c) Only appropriate grades, strengths and thicknesses of aluminium shall be used to ensure that
all structural and finishing requirements of the Specification are met. The wall thicknesses of
aluminium extrusions shall be sufficient to ensure their rigidity in the lengths required in the final
installation.
d) All aluminium fixing brackets and cleats shall be manufactured from the appropriate grade of
alloy to the requirements of BS EN 515, BS EN 573: Parts 3 and 4, and BS EN 755: Parts 1-9.
If visible, they shall be finished to match the metal panels and framing members.
e) All exposed aluminium shall be protected with low tack adhesive film during construction and
prior to handover.
f) Where aluminium is to be anodised, aluminium sheeting and flat panels shall be manufactured
using alloy grade J57S, or acceptable equivalent, and aluminium extrusions shall be
manufactured using alloy grade 6063, or acceptable equivalent.
g) Aluminium panels shall be manufactured such that the grain on each runs in the same direction.
h) Issue “Die Drawings” to the CA for review. These shall be considered as Shop Drawings. The
“Die Drawings” shall indicate polished surfaces and shape.
i) Aluminium extrusions containing score lines resulting from poorly polished surfaces shall not be
acceptable.
j) Aluminium sheets shall not suffer bowing, dimpling, oil canning, sagging, pillowing, rippling,
warp, abrupt transitions or other visible deformation or irregularity.
iii) Shall be manufactured using the lost wax process or such other process as may be
proposed by the Contractor and accepted by the CA.
iv) Exposed feeder ports and die lines shall not be acceptable in the finished castings.
v) The surface finish of the castings shall be determined by the submission of samples for
review and acceptance by the CA. Samples once accepted should be the standard
required for all subsequent castings to be used in the works.
vi) The surface roughness of the casting surface prior to any subsequent finishing process
shall be SCRATA A2 (Steel Castings Research and Trade Association) or better.
vii) Make allowance for two post production finishing processes to be utilised. The processes
shall be agreed with the CA and shall include blast finishes (including bead blasting) and
electropolishing or acid pickling.
h) Stainless steel fixings and support brackets for natural stone cladding shall comply with BS
8298.
i) Stainless steel wire, cold-forged fasteners and similar components shall comply with BS EN
10263: Part 5.
j) Stainless steel for wall ties and other components associated with masonry construction shall
comply with BS 5628: Part 3 and BS EN 845: Part 1.
k) Stainless steel shall be protected where possible using appropriate adhesive film, to the film
manufacturer’s written recommendations.
l) If stainless steel has not been protected by adhesive film, thoroughly clean prior to presentation
to the CA for acceptance.
Z11.2106 Zinc
Zinc-copper-titanium alloy shall be in accordance with BS EN 988. The use of Zinc in fully-supported
roofing shall be in accordance with BS EN 501.
Z11.2200 WORKMANSHIP
Z11.2201 Fabrication Generally
a) Fabricate components carefully and accurately to ensure compliance with the Design and the
Specification.
b) Do not permit contact between dissimilar metals in components that are to be fixed where
moisture may be present or occur.
c) Finished components shall be rigid and free from distortion, cracks, burrs and sharp arrises.
Moving parts shall move freely and without binding.
d) Unless specified otherwise, mitre corner junctions of identical sections.
d) Prevent weld spatter falling on surfaces of materials that will be self-finished and visible in
completed work.
e) Remove all traces of flux residue, slag and weld spatter.
f) Metal arc welding shall be to BS EN 1011: Parts 1 and 2, or other methods subject to review
by the CA.
Z11.2206 Brazing
To BS EN 14324.
End of Section
Contents
Z20 FIXINGS/ADHESIVES..........................................................................................2
Z20 FIXINGS/ADHESIVES
To be read in conjunction with Section A and other related sections of the Specification, Preliminaries
and Contract Conditions.
Z20.2100 MATERIALS
Z20.2101 Fixing Generally
a) All fixings shall be of sufficient strength, appropriate to their location, and are provided at
adequate positions so as to ensure the performance of the elements being attached. The fixings
shall be suitable and used solely for the purposes intended by the manufacturer in order to
satisfy the requirements of the Specification.
b) Unless otherwise specified, observe the following requirements:
i) Durability - fixings shall be selected such that adequate protection against any corrosion
likely to occur in their position of use is provided for the service life specified.
ii) Rigidity - fixings shall be used which are suited to the likely stresses, movements and
vibrations in use.
iii) Appearance - unless otherwise specified, fixings shall not be visible; where fixings are
visible these shall match or suit the items being fixed or comply with the Design Drawings.
iv) Removable items that require accessibility or removal shall be fixed with hidden screws
and/or bolts, unless otherwise specified.
c) Use fixings that are suitable for their intended purpose and adequate to comply with the
requirements stated in the Specification.
d) All visible bolts, screws, nuts, anchors and other fixings shall be of adequate strength for their
designed purpose and shall, unless specified otherwise, be manufactured from the most
appropriate grade of austenitic stainless steel or other materials as specified. Where specified,
structural steel fixings shall comply with the grades specified.
e) Supply all necessary and appropriate fasteners, fixings, bearings, brackets, etc. necessary for
the safe and proper installation plus associated flashings and closures.
f) All fixings shall conform to all statutory requirements in respect of strength and type.
g) Adequate measures shall be taken to prevent bi-metallic corrosion between dissimilar metals
and to isolate aluminium components from cementitious surfaces. To this end attention is drawn
to publication PD 6484 'Commentary on corrosion at bi-metallic contacts and its alleviation'.
h) Generally, fixings within aluminium framing components shall not be visible, with the exception
of capping pieces fixed to vertical mullions.
i) Visible fixings shall be restricted to the assembly of non-visible elements to support steelwork,
using round-headed Allen bolts into a proprietary system.
j) Any steel sub-frame assemblies shall be galvanised and effectively weatherproofed to avoid
exposure to the external environment.
k) Provide cast-in channel fixings in concrete and fixings directly made to structural steelwork.
l) All fixings shall be tested in accordance with BS 5080: Parts 1 and 2 by an independent
Testing Authority acceptable to the CA.
Z20.3100 APPLICATION
Z20.3101 Adhesives
a) Surfaces to receive adhesive shall be sound, unfrozen and free from dust, grease and any other
contamination likely to affect bond. Where necessary, clean surfaces using methods and
materials recommended by the adhesive manufacturer.
b) Surfaces shall be sufficiently smooth and even to suit the gap-filling and bonding characteristics
of the adhesive. Prepare as necessary.
c) Operatives shall observe both the manufacturers’ and statutory requirements for storage and
safe usage of adhesives.
d) No adhesives shall be used in unsuitable environmental conditions or beyond the
manufacturer’s recommended maximum shelf life or open-pot time periods.
e) Adhesives shall be applied using recommended spreaders/applicators to ensure correct
coverage. Bring surfaces together within the recommended time period and apply pressure
evenly over the full area of contact surfaces to ensure full bonding.
f) Surplus adhesive shall be removed using methods and materials recommended by the adhesive
manufacturer and without damage to affected surfaces.
g) Adhesives and sealants with a low VOC content in line with (SCAQMD) rule #1168.
Z20.3102 Fixings
a) Carry out all necessary preparation work such as drilling, plugging, screwing, bolting, cutting for
anchor bolts or sockets to be cast-in and for making good, including grouting-in of anchor bolts
and fixings where necessary.
b) The method of fixing shall not damage anything being fixed or anything receiving fixings.
c) Welding shall not be permitted, unless accepted by the CA.
d) Fasteners shall be installed with a co-ordinated purpose design tooling system that
incorporates a mechanical depth locator to ensure consistent depth setting and facilitates
perpendicular installation. The fastener manufacturer shall be capable of providing on-Site
instruction in the use of the fastener installation tooling system.
e) All fixings shall comply with Section 2 of Approved Document A of the Building Regulations and
any subsequent amendments thereto.
f) Submit QA/QC procedures for inspection of fixings to the CA to include, but not be limited to,
checking each fixing for correct torques, depth of mortices, alignment, etc.
g) Ensure that no lock-up stresses are generated.
c) Remove all unspent cartridges from the Site when no longer required.
d) Apply zinc rich primer to heads of fasteners used externally in external walls or in other locations
subject to dampness.
e) Use top hat section plastic washers to isolate cartridge-fired nails from stainless steel
components fixed externally, in external walls or in other locations subject to dampness.
End of Section
Contents
Z22 SEALANTS.............................................................................................................2
Z22.2000 MATERIALS/PRODUCTS..................................................................................... 2
Z22 SEALANTS
To be read in conjunction with Section A and other related sections of the Specification, Preliminaries
and Contract Conditions.
Z22.2000 MATERIALS/PRODUCTS
Z22.2100 MATERIALS
Z22.2101 Types and Method
a) Sealant shall be suitable for the purpose intended, and used strictly in accordance with the
manufacturer's instructions.
b) Sealants shall not be in any way a potential health hazard. Maintain full up-to-date records of all
current published research and legislation in this respect. Obtain information from the sealant
manufacturer regarding storage, handling, use and disposal of sealants.
c) Wet applied sealants shall only be used in the locations shown on the Design Drawings or
Shop Drawings or as and where agreed with the CA, provided that all the requirements of the
Specification are satisfied.
d) Sealants shall be the most appropriate type and grade suitable for the intended application.
e) Written confirmation from the sealant manufacturer shall be obtained and submitted to the CA
for consideration as to the suitability of the sealant for the application intended.
f) Submit proposals and reference samples to the CA of the type and colour of the sealant prior
to ordering.
g) Sealant colour shall be agreed with the CA. State the period during which the sealant shall not
change in appearance or colour. Any discolouration of sealant during this time shall not be
acceptable.
h) The chemical composition of the sealant and primers, where any, shall be compatible with the
joint substrate, and with adjacent surface treatments or building components with which they
may come into contact.
i) Determine the appropriate hardness, compressibility or consistency of sealants in consultation
with the manufacturer, considering the joint movement and exposure for the size of joint. Upon
request, furnish information concerning theoretical joint movement related to the anticipated
temperatures at which sealants shall be installed and cured.
j) Demonstrate to the satisfaction of the CA that the sealant joints can accommodate and are
compatible with any movements to which they may be subjected.
k) Sealants shall have the lowest modulus of elasticity which is consistent with the degree of
exposure to wear, abrasion and vandalism. Any sealant exposed to traffic shall have strength
and modulus sufficiently high to resist damage by traffic, including indentation.
l) Sealants that are likely to stain, discolour or bleed into adjacent building materials shall not be
used. Provide independent testing evidence to this effect.
m) Where the sealant location involves special requirements, comply with the following:
i) Where the sealant is used in trafficked surfaces and/or requires to be fuel resistant, it
shall comply with BS EN 14188: Part 1 for hot applied sealants and BS EN 14188: Part
2 and BS 5212 for cold applied sealants.
ii) Where the sealant is required to achieve a period of fire resistance, provide independent
UK performance certification of the proposed sealants to show the sealant satisfies the
required fire resistance requirement.
iii) Where sealants are in contact with drinking water, provide evidence of compliance with
UK water quality standards.
iv) Resistance to permanently wet service environments.
n) Sealant performance shall be verified by provision of current independent test certificates.
o) Manufacturers’ product descriptions shall confirm compliance with performance standards
including the BS EN ISO 11600 coding and be confirmed on the package labels, in the
technical data sheets and on any certificates demonstrating performance capability.
Z22.3100 WORKMANSHIP
Z22.3101 Application
a) Carefully prepare surfaces to receive sealant, using correct de-greasing solvents, primers and
bonding agents as necessary.
b) Where sealants are applied, either on or off Site, they shall be in accordance with BS 6213, BS
6093 or BS 8000: Part 16 and BS EN ISO 11600 as appropriate.
c) The application of sealants shall be in accordance with the supplier's/manufacturer's written
preparatory and application procedures and the Code of Practice prepared by the British
Adhesives and Sealant Association Manual of Good Practice or acceptable equivalent
organisation.
d) Excess sealant shall be removed and all joints shall be neat and clean. Only liquids approved by
the sealant manufacturer shall be used to tool freshly applied sealants.
e) Sealant shall be evenly applied without bubbles in joints.
f) Sealants shall be adequately protected during the curing process to avoid contamination or
damage from other activities or conditions on Site.
g) Joint fillers, when placed in the joint, shall provide a gap consistent with the required depth of
sealant. The cross section of sealant in the joint shall be of 2:1 width to depth unless otherwise
accepted. Joint fillers shall be as follows:
i) Compatible with the sealant used and surrounding construction elements.
ii) Formed from closed cell foam.
iii) Non-adhering to cured sealant.
h) Applicators shall operate within an approved BS EN ISO 9002 scheme.
i) Only materials meeting the Specification requirements and stored under appropriate conditions
shall be used for installation.
End of Section
Contents
Z25 GLASS AND COATINGS....................................................................................2
Z25.2100 MATERIALS
Z25.2110 Types of Glass
of anisotropy at the time of manufacture. Glass shall be rejected if it does not fall within the
range of agreed samples.
g) The maximum allowed deviation of the top and bottom edges (i.e. the curved edges) measured
on the face of the glass and perpendicularly to the curvature shall be ±3mm.
installation with the double glazed unit and all handling of glass shall be carried out using
protective cotton or surgical gloves so as not to damage the surface of the coating with
fingerprints. After protection is removed from the coated glass panes the panes must be
installed into the double glazed units and sealed within the recommended time by the coating
manufacturer, to avoid any atmospheric deformation of the surface.
f) Provide samples minimum 1200mm x 1200mm in size of any coated glass types for review by
the CA.
b) Edge zone - area around edge with width (w)/10 or height (h)/10 respectively:
i) Inclusions, bubbles, spots, stains, etc.:
• Pane area not less than or equal to 1m²: Maximum 4 cases, each not less than or
equal to 3mm diameter.
• Pane area greater than 1m²: Maximum 1 case, each not less than or equal to 3mm
diameter per metre of perimeter.
ii) Residues (spots) in the gas-filled cavity:
• Pane area not less than or equal to 1m²: Maximum 4 cases, each not less than or
equal to 3mm diameter.
• Pane area greater than 1m²: Maximum 1 case, each not less than or equal to 3mm
diameter per metre of perimeter.
iii) Residues (patches) in the gas-filled cavity: Whitish grey or transparent – maximum 1 case
not less than or equal to 3cm².
iv) Scratches: Total of individual lengths; maximum 90mm. Individual length; maximum 30mm.
v) Hair-line cracks: Not allowed in higher concentration.
c) Main zone (remainder of unit inside the edge zone):
i) Inclusions, bubbles, spots, stains, etc.:
• Pane area not less than or equal to 1m²: Maximum 2 cases, each not less than or
equal to 2mm diameter.
• Pane area greater than 1m² but not less than or equal to 2m²: Maximum 3 cases,
each not less than or equal to 2mm diameter.
• Pane area greater than 2m²: Maximum 5 cases, each not less than or equal to 2mm
diameter.
ii) Scratches: Total of individual lengths; maximum 45mm. Individual length; maximum 15mm.
iii) Hair-line cracks: Not allowed in higher concentration.
d) Main and edge zone combined:
i) Maximum number of allowable discrepancies as in edge zone.
ii) Inclusions, bubbles, spots, stains, etc. of dimensions 0.5 – 1.0mm are allowable without
any area-related limitation, except when they appear in higher concentration. “ Higher
concentration” means that at least 4 inclusions, bubbles, points, patches, etc. are located
within a circle with a diameter of not less than or equal to 20cm.
e) Visual inspection of the glass edges, edge seals and spacers shall be unhindered, prior to
glazing.
v) Structural sealant glazing shall be suited to local conditions including blown sand. The
grade of sealant/silicone shall be suited to the local temperature and solar exposure and
at least capable of withstanding temperatures of at least 100 degrees.
b) Materials:
i) Provide structural sealant adhesive, which shall be obtained from a single source
manufacturer and applied strictly in accordance with the manufacturer’s written
recommendations.
ii) For marine, or similar environments, the structural silicone shall be resistant to damage
from algae or attack by birds.
c) Installation/Fabrication:
i) Structural silicone glazing application shall not be carried out on Site unless agreed
otherwise with the CA.
ii) Provide documentation of the sealant manufacturer’s requirements for the particular
substrate of the construction including joint sizes, limitations and requirements for mixing,
cleaning, surface preparation, priming and application.
iii) Provide evidence that the sealant has been selected taking into account the sealant
manufacturer’s recommendations as to use and compatibility with the contact surfaces.
iv) Joint design shall be in accordance with the sealant manufacturer’s written
recommendations for glue-line and bite to glue-line ratio, taking into consideration the
design wind pressures and panel sizes.
v) Provide details of tensometer and any other testing equipment as required.
vi) Glazing procedures shall include frame assembly, cleaning, priming (if necessary),
gunning, tooling and frame handling after glazing and curing. Sealants shall not be applied
when the temperature is below 4°C and units shall not be moved until the silicone has
achieved a level of cure recommended by the silicone supplier.
vii) Adopt sealant batching logging procedures to record all batches used, including batch
manufacture date and arrival date of each batch at the fabrication works. The location of
each structural silicone glazed panel shall be individually located on As-built Drawings of
the building, recording date and batch of structural silicone, with details of tests carried
out to ensure that the highest quality of silicone is being used.
viii) The structural silicone glazing shall be recorded at the time of assembly and shall include
identification marks of every panel by a unique number, readable from the inside of the
building for the life of the building. Provide glazing records with information on each panel
including silicone type, batch, date of application, glazier’s name and temperature and
humidity measured inside the factory on the day of assembly.
ix) Recommend a periodical maintenance regime for agreement with the CA. This shall be
incorporated in the O&M manuals. Acceptance criteria shall be consistent with the
requirements of the testing criteria, which as a minimum shall be:
• A standard ‘peel test’ on any broken panels that require replacement.
• A close visual inspection, to be carried out externally from the cleaning apparatus,
including application of hand pressure to verify continued adhesion. This exercise
shall be carried out for 1% of the cladding, at a yearly frequency for the first 3 years,
then at a frequency of 5 years following. The panels shall be randomly selected
around the elevations at varying heights.
• The tests shall be carried out by the sealant supplier, or other qualified body.
i) All defined loads resulting from specified movements of the main structural frame during
building use.
ii) Point loads imposed on the glass framing members of 695N inwardly acting based upon
BS 5516. Maintenance loads shall not be carried by the glass infill panels.
iii) Wind loads as defined by BS 6399: Part 2 and BS 5516.
iv) Loads imposed by snow as determined by BS 6399: Part 3 and BS 5516.
v) Minimum working pressures on infill panels for hand cleaning operations as defined in BS
5516.
vi) The impact load of two persons falling on it during maintenance, cleaning and inspection
operations in accordance with the requirements of the Specification. The glazing system
to maintain its structural integrity and the glass and edge covering to have adequate
thickness so that units do not ‘pop out’ of the frame under such impact. Should the outer
layer of glass break, then the inner sheet glass shall stay in place and support the
operatives.
vii) Large body impact tests by an accredited test organisation with certification produced to
demonstrate compliance to an energy level of 1200J, when tested to prEN 1873.
c) When calculating loads on the glazing and structure, the worst combination of the above shall
be considered, taking into account of the fact that the pressure coefficients at various locations
may determine more than one design criterion.
End of Section
Contents
Z30 METALWORK FINISHES ....................................................................................2
Z30.2100 MATERIALS
Z30.2101 Appearance
a) All finishes shall be stable, fade resistant and not affected by ultraviolet light. Provide data and
samples for review by the CA.
b) All finishes shall be durable, of uniform texture and colour and be resilient to all known and/or
specified environmental and pollution effects. This shall include scratching and cigarette smoke
and burns, etc. Submit data and samples for review by the CA.
c) Minor scratches and blemishes shall be repaired using the coating manufacturer’s
recommended products and system, matching original finish for colour, texture and gloss.
Repair coatings shall be visually acceptable to the CA. Confirmation shall be provided that the
repair to the damaged finish complies in all respects to the requirements of the Specification.
Guarantee in writing that the damaged or defective coating is satisfactory for the proposed
remedial paint system. Employ an independent finishing consultant to carry out an inspection
and any necessary tests and supply a full report to the CA.
d) All finishes shall be within the limits of the agreed samples and without irregularities or
distortions. Fixings, stiffeners, etc. which are not intended to be visible shall be treated so that
there is no discontinuity in the finished surface appearance.
Z30.2200 FINISHES
Z30.2201 Liquid Organic Coating
For aluminium alloy components to BS 4842.
Z30.2202 Plating of Surfaces
a) Cadmium/zinc plating of iron and steel surfaces shall comply with BS EN 12329 and BS EN
12330.
b) Chromium plating shall comply with BS EN 12540.
welds as required and fill pits and other surface imperfections that may cause the premature
failure of the coating system.
c) Galvanising: The steelwork shall be supplied to the galvaniser in a suitable condition to be acid
pickled in dilute hydrochloric acid, passivated and then hot dip galvanised in accordance with
the provisions of BS EN ISO 1461.
d) Uniformity: The galvanising shall be carried out in such a way as to maximise the smoothness
and uniformity of the deposited coating. Only use double dipping where no alternative exists.
e) Touching-up is not allowed unless agreement is given by the CA. In which case it shall be in
accordance with Annex C of BS EN ISO 1461.
i) Where acceptance is given, use the Zilt-Stick system in accordance with the
manufacturer’s current recommendations. Zilt-Stick is a self-fluxing and galvanising
system, which is applied by hand. The stick is made up of a galvanising compound, which
has a “foil” wrapping, and is rubbed over the affected area until completely covered. The
black flux residue can be removed using a damp cloth.
ii) The maximum size of an area of touch-up is to be determined by locating the point on the
damaged surface that is furthest from an intact galvanised coating. If the distance from
this point to the galvanising is in excess of 10mm, then the member shall be re-galvanised
or rejected.
iii) Galvafroid or paint applied finishes are not permitted under any circumstances.
f) Refer to the recommendations of the Zinc Development Association for galvanising and zinc
metal-spraying.
g) Immersion process: This shall be discussed and agreed with the CA and submitted for formal
comment. This is to ensure that during the galvanising process drips are not allowed to run off
fair-faced surfaces and thus disfigure them. Fair-faced surfaces are all those surfaces that will
be visible in the completed Works. Agree location of all fair-faced surfaces with the CA before
application.
h) Breathing Holes: Locate in unobtrusive places. Agree the location of these holes with the CA
and mark clearly on the Shop Drawings.
i) Distortion: Ensure that no distortion of fabricated elements occurs during galvanising. Advise
the CA on the possibility for distortion of the steelwork elements during the galvanising process
to enable design modifications of components to be made before fabrication of these
components.
End of Section
Contents
Z31 POWDER COATINGS.........................................................................................2
Z31.2102 Materials
a) Colour: The colour shall be selected by the CA from the BS/RAL ranges.
b) Colour Consistency: Colour consistency shall be assured from batch to batch for the Works, in
accordance with the conditions described in BS 950: Part 1.
c) Colour Uniformity: Limits for acceptable colour variations in production shall be established and
accepted by the CA from samples provided by the Contractor prior to production. When
metallic colours are used, top and bottom limits of colour variation and appearance shall be
established and agreed prior to coating commencement. All colour samples shall be submitted
and accepted by the CA before coating commences.
d) The minimum and maximum local dry film thickness on adjacent panels shall not vary by more
than 20%. If this is not achievable, submit samples to the CA for review showing the maximum
variation in coating thickness.
e) The powder coating shall be consistent throughout in all respects within the upper and lower
levels agreed which shall be based on samples provided and agreed with the CA.
f) Protective Tapes/Films: Adhesive/protective tapes/films shall be low tack type applied at room
temperature, remaining in contact with the surface for a maximum period of 6 months. Should
longer periods be required, then the tape/film shall be removed and replaced. Where
adhesive/protective tapes/films are used, then the colour shall be white or lighter in tone than
the powder coating.
Z31.2103 Workmanship
a) The selected coating shall carry a current British Board of Agrément Approval Certificate or
acceptable equivalent. A copy, signed by the Managing Director of the coating applicator
company, shall be made available to the CA, prior to commencement of coating.
b) Applicator Requirements: The powder coating application and stoving shall be carried out in
accordance with BS 6496 and/or BS 6497. Only one coating plant shall be used for the
Works along with one batch of powder, unless otherwise accepted by the CA.
c) Guarantees: Make available to the CA, fully documented and signed copies of the coating
guarantees. The duration of the guarantees shall be 25 years or as otherwise agreed with the
CA.
d) Cleaning Frequency: The normal cleaning frequency associated with the guarantees detailed
above shall be 12 months unless agreed otherwise by the CA.
e) Repair of Damage: Damage shall be repaired immediately. Site rectification of damage shall
generally not be acceptable and only be carried out with the CA’s agreement carrying a
guarantee for colour retention, gloss retention and adhesion for the remaining period of the
guarantee.
f) In addition to the requirements of BS 6496 the pretreatment shall use a chromate process.
Z31.2104 Testing
Demonstrate compliance with the following test requirements:
a) Artificial Weathering: There shall be no chalking in excess of the minimum illustrated in the
photographic reference standards of ASTM D 4214 when tested in accordance with BS 6496,
Clause 4.10 (a) or BS 6497, Clause 4.8 (a). In addition, the coating shall show no cracking,
checking or flaking and any change in colour shall not exceed one step in hue, value or chroma
in the Munsell atlas from the original colour.
b) Natural Weathering: There shall be no chalking in excess of the minimum illustrated in the
photographic reference standards of ASTM D 4214 when tested for three years in accordance
with BS 6496, Clause 4.10 (a) or BS 6497, Clause 4.8 (b). In addition, the coating shall show
no checking, cracking or flaking and any change in colour shall not exceed one step in hue,
value or chroma in the Munsell atlas from the original colour.
c) Exterior Exposure: When viewed from a distance of 1m, there shall be no blisters, dirt,
entrapped particles, craters, pinholes, porosity, scratches or other visual defects on significant
surfaces when measured in accordance with BS 6496, Clause 10.2.
d) Impact Resistance: There shall be no sign of cracking or detachment of film, when measured in
accordance with BS 6496, Clause 4.7.
e) Cupping Test: There shall be no sign of detachment when measured in accordance with BS
6496, Clause 4.5.
f) Scratch Test: There shall be no penetration to the substrate when tested in accordance with
BS 6496, Clause 4.6.
g) Adhesion: The coating shall have a classification of Class 0 and there shall be no removal of the
coating when tested in accordance with BS 6496, Clause 4.4.
h) Flexibility: There shall be no cracking, flaking or film deformation above 6mm when tested in
accordance with BS EN ISO 6860.
i) Salt Spray Resistance: No blistering, softening or detachment of the coating shall occur when
tested for 1000 hours on aluminium to BS 6496, Clause 4.9 or for 500 hours on galvanised
steel to BS 6497, Clause 4.7.
j) Humidity Resistance: No blistering, softening or detachment of the film shall occur when tested
in accordance with BS 6496, Clause 4.11.
k) Permeability: The coating, when tested in accordance with BS 6496, Clause 4.13, shall show
no blistering of the coating, except within 3mm of any edge.
l) Mortar Resistance: There shall be no blistering, softening or detachment of the coating, etc.
when tested in accordance with BS 6496, Clause 4.8.
m) Film Thickness: The minimum film thickness at any point shall be 40 microns for aluminium and
60 microns for galvanised steel. (Note 1: - Where hazardous environments are involved, the
minimum shall be increased to 60 microns and 80 microns respectively.) (Note 2: - Some
colours also require the minimum film thickness to be increased to 60 microns to develop the
correct intensity of colour.) No seeding or double coating of work shall be accepted.
n) Gloss Levels: The gloss level, when measured using a 60 degree Gardiner head, shall read: -
25% ±5% for matts, 70% ±5% for satins and 85% ±5% for gloss.
o) Spread of Flame: The Powder Coating, when tested to BS 476: Part 7, shall have a Class 1
rating.
p) Building Regulations: The Powder Coating shall have a Class 0 rating as defined under the
Building Regulations.
q) Product tests shall meet all the requirements of the Specification.
r) Test pieces shall consist of finished panels or extrusions representative of product-coated
aluminium. Test pieces shall be at least 150mm long and 75mm wide with a flat
coated/significant surface, as defined in BS EN ISO 2064, on which to conduct instrumental
measurements. The Shop Drawings shall indicate exposed/significant surfaces.
s) Tests shall be performed on exposed/significant surfaces as defined in BS EN ISO 2064 as
indicated, and shall meet the requirements of BS 6496 or BS 6497.
t) Test reports shall be produced at the time of coating and made available to the CA. These
reports shall include:
i) Date when tests were performed and date of issue of report.
ii) Identification of the coating system tested, including product supplier, colour reference,
product code and batch reference.
iii) Statement indicating that the coating system tested passed all tests, or failed one or
more.
iv) In the case of failure, which test(s) and description of failure(s).
v) Statement that all tests were conducted in accordance with the Specification.
vi) Name and address of the laboratory which conducted the tests and issued the reports.
vii) The CA shall commission an independent testing authority, with the Contractor being
responsible for all costs incurred. To gain acceptance of the finished products for use,
carry out a minimum of three independent acceptance inspections, sampling procedures
and plans as set out in BS 6001: Part 1 for general inspection level 2. AQL (Acceptable
Quality Level) = 1% on each colour and finish used in the Works. These inspections shall
be carried out at the finishing plant prior to fabrication by an independent, consultant or
acceptance laboratory.
viii) In addition, the Contractor shall make allowance for Site inspections where, due to
damage or non-supply of the production test reports, the CA may require independent
investigation of all finishes on Site-fixed units. This investigation shall be carried out within
the guidelines of BS 6001: Part 2, LQ (Limited Quality) (Pa = 10%) + 5%. For the
purpose of this inspection, each section in the window curtain wall or other fabrication
shall be taken as an individual component in assessing the overall batch number to allow
the acceptance inspection laboratory to certify that the Works comply with the
Specification. For units that are finished in fewer than three production runs, acceptance
inspections shall also be made using BS 6001: Part 2 to the same LQ.
ix) Certificates of Practical Completion or any other document of authority accepting
responsibility may not be signed by the CA until he has received these reports.
End of Section
Contents
Z32 PVDF COATINGS.................................................................................................2
Z32.2101 General
a) PVDF coating shall be carried out using materials suitable for the intended purpose. Aluminium
alloys shall be selected to ensure that the finished visual appearance of all components is
constant and identical. The alloy for extrusions shall be grade 6063, 6060 or acceptable
equivalent, complying with BS EN 515, BS EN 573: Parts 3 and 4, and BS EN 755: Parts 1-9
and for sheet material grade 1200/3103, complying with BS EN 485: Parts 1-4, BS EN 515
and BS EN 573: Parts 1-4. All aluminium shall be in a condition suitable for the application of
the coating process. The sheet shall be of a suitable and agreed thickness and of suitable
temper to withstand the stoving process.
b) In conjunction with the CA, ensure that the application complies with all the relevant parts of the
COSHH Regulations 1988, the Environmental Protection Act 1990 Part 1, the Management of
Health and Safety at Work Regulations 1992 and the Construction (Design and Management)
Regulations 1994.
Z32.2102 Materials
a) Colour: The colour shall be selected by the CA from the BS/RAL ranges.
b) Colour Consistency: Colour consistency shall be maintained between batches, in accordance
with BS 950: Part 1.
c) Colour Uniformity: Limits for acceptable colour variations in production shall be established and
agreed by the CA from samples provided, prior to production. When metallic colours are to be
used, the top and bottom limits of colour variation and appearance shall be accepted by the CA
prior to coating commencement. The grain on PVDF coated materials shall be identified in order
to ensure that they are fixed in the same direction in their finished position.
d) The PVDF coating minimum and maximum local dry film thickness on adjacent panels shall not
vary by more than 20%. Submitted samples shall confirm compliance.
e) The PVDF coating finish shall be identical in all respects subject to the criterion specified, on all
components similarly finished, and hung in the same direction.
f) Protective Tapes/Films: When adhesive/protective tapes/films are proposed to protect finished
products, tapes/films of a low tack nature shall be used. They shall be applied at room
temperature, after the coating is fully stoved, and remain in contact with the surface for a
maximum period of six months. Should longer periods be required, then the tape/film shall be
removed and replaced. Care shall be taken when removing adhesive/protective tapes/films. No
sharp instruments or abrasive materials shall be used to remove the tape/film. No solvents or
cleaning solutions shall be used to remove residues, without the prior permission of the CA.
Where adhesive/protective tapes/films are used, then the colour shall be white or lighter in tone
than the finish it is protecting.
d) Repair of Damage: If during installation, or later, damage occurs, this shall be rectified
immediately and not left to the end of the installation. Site rectification of damage shall only be
carried out with the CA’s acceptance and shall carry a guarantee for colour retention, gloss
retention and adhesion for the remaining period of the original guarantee.
Z32.2104 Testing
a) Carry out the following tests or provide data demonstrating that the following tests have been
carried out. All PVDF coatings applied to aluminium shall comply with the requirements of
AAMA 2605 including:
i) Gloss Retention: The residual gloss shall be at least 50%, after 10 years' exposure in
Florida, in accordance with AAMA 2605, Clause 7.9.1.4.
ii) Colour Retention: A maximum colour change of Delta E5, after 10 years' exposure in
Florida, in accordance with AAMA 2605, Clause 7.9.1.2.
iii) Exterior Exposure: When viewed from a distance of 3m, no visible blisters, scratches, flow
lines, streaks or other visual defects shall be allowed, in accordance with AAMA 2605,
Clause 4.2.
iv) Impact Resistance: There shall be no removal of film, when measured in accordance with
AAMA 2605, Clause 7.5.
v) Abrasion Test: The coating shall demonstrate a minimum value of 40 for the abrasion
coefficient, when tested in accordance with AAMA 2605, Clause 7.6.2.
vi) Adhesion: There shall be no removal of film or blistering, when measured in accordance
with AAMA 2605, Clause 7.4.
vii) Dry Film Hardness: A minimum pencil hardness of grade F (Berol Eagle Turquoise Pencil)
shall be obtained when the coating is tested in accordance with AAMA 2605, Clause 7.3.
viii) Salt Spray Resistance: The coating shall pass the requirements of AAMA 2605, Clause
7.8.2 after an exposure period of 4000 hours.
ix) Humidity Resistance: The coating shall pass the requirements of AAMA 2605, Clause
7.8.1 after an exposure period of 4,000 hours.
x) Mortar Resistance: Easy removal of mortar shall be obtained after 24 hours when tested
in accordance with AAMA 2605, Clause 7.7.2. In addition, there shall be no loss of film
adhesion or visual change in appearance.
xi) Muriatic Acid Resistance: The coating shall show no signs of attack when tested in
accordance with AAMA 2605, Clause 7.7.1.
xii) Film Thickness: The minimum dry film thickness shall be 30 microns for solid colours and
40 microns for metallic colours, when measured in accordance with AAMA 2605, Clause
4.3. The minimum local dry film thickness shall be increased to be consistent with colour
selection and type of coating as recommended by the coating manufacturer. Additionally,
the local dry film thickness shall be increased consistent with durability requirements and
environmental conditions, as recommended by the coating manufacturer.
xiii) Gloss Levels: The gloss level, when measured using a 60 degree Gardiner head shall
read 19% or less for ‘low gloss’, 20-79% for ‘medium gloss’ and 80% and over for ‘high
gloss’, in accordance with AAMA 2605, Clause 7.2.
xiv) Spread of Flame: The PVDF coating, when tested to BS 476: Part 7 shall have a Class 1
rating.
xv) Building Regulations: The PVDF coating shall have a Class 0 rating as defined under the
Building Regulations.
d) Test reports shall be produced at the time of coating and made available to the CA. These
reports shall include:
i) Date when tests were performed and date of issue of report.
ii) Identification of the PVDF coating/system tested, including product supplier, colour
reference, product code and batch reference.
iii) Statement indicating that the PVDF coating/system tested passed all tests, or failed one
or more.
iv) In the case of failure, which test(s) and description of failure(s).
v) Statement that all tests were conducted in accordance with the Specification.
vi) Name and address of the laboratory which conducted the tests and issued the reports.
vii) The CA shall commission an independent inspecting authority with the Contractor
responsible for all costs incurred. To gain acceptance of the finished products for use,
carry out a minimum of three independent acceptance inspections, sampling procedures
and plans as set out in BS 6001: Part 1 for general inspection level 2. AQL (Acceptable
Quality Level) = 1% on each colour and finish used in the Works. These inspections shall
be carried out at the finishing plant prior to fabrication by an independent consultant or
acceptance laboratory.
viii) Carry out a Site inspection since, due to damage or non-supply of the production test
reports, the CA shall commission an independent investigation of all finishes on Site-fixed
units. This investigation shall be carried out within the guidelines of BS 6001: Part 2, LQ
(Limited Quality) (Pa = 10%) = 5%. For the purpose of this inspection each section in the
window curtain wall or other fabrication shall be taken as an individual component in
assessing the overall batch number to allow the acceptance inspection laboratory to
certify that the Works comply with the Specification. For units that are finished in fewer
than three production runs, acceptance inspections shall also be made using BS 6001:
Part 2 to the same LQ. The acceptance inspection laboratory shall be accepted by the
CA and instructed by the commissioning authority to submit all reports simultaneously to
the Contractor and the CA. These reports shall cover factory production materials and
Site-fixed units.
ix) Certificates of Practical Completion or any other document of authority accepting
responsibility may not be signed by the CA until he has received these reports.
End of Section
Contents
Z33 ANODISING ..........................................................................................................2
Z33 ANODISING
To be read in conjunction with Section A and other related sections of the Specification, Preliminaries
and Contract Conditions.
Z33.2102 Workmanship
a) Anodic oxidation coating shall be carried out at a single place of manufacture. All critical visible
areas shall be anodised in a single batch.
b) Anodising shall commence after fabrication/machining is complete wherever possible.
c) Any fabrication of pre-finished lengths shall be previously agreed with the CA. Uncoated edges
shall not be visible in assemblies or exposed to the atmosphere. Fabricated pieces shall meet
the thickness requirements of BS 3987.
d) The processes adopted shall be compatible, offering weather resistance, abrasion resistance,
impact resistance and protection against chemical attacks as follows:
i) Corrosion resistance shall be equal to or greater than that of an anodised aluminium finish
thickness of minimum average 25 microns and sealing in accordance with BS 3987 and
the Specification.
ii) For production control the abrasion resistance of the anodising shall be determined in
accordance with BS 6161: Part 18. Films, which when tested by this method continue to
be scratched by glass coated abrasive paper do not conform to the Specification. In the
event of a dispute, the referee test described in BS EN 12373: Part 9 shall be carried out
on test pieces cut from eight components whose results from the abrasive paper test
indicate that they have suspect low abrasion resistance. The wear index obtained from the
referee test shall be no greater than 1.4, for acceptance.
iii) For production control the sealing value of the anodising shall be determined in
accordance with BS EN 12373: Part 5. In the event of a dispute, the referee test
described in BS EN 12373: Part 7 shall be carried out. The maximum weight loss from
the referee test shall be no greater than 30mg/dm², for acceptance. Impregnated cold
sealing processes shall not be used.
iv) For production control the film thickness of the anodising shall be determined in
accordance with BS EN ISO 2360. In the event of a dispute the referee test described in
BS EN ISO 1463 shall be carried out. The minimum local film thickness shall be 20
microns with a maximum of 35 microns.
v) Anodic oxidation coating shall be carried out by the sulphuric acid bath process. The
temperatures of the anodising bath and chemical content shall be set and maintained to
achieve good quality control of the finished product in accordance with BS 3987.
vi) Notwithstanding BS 3987 visible surfaces shall be free from coating or metallurgical
defects when viewed from 1 metre.
e) The temperatures of the anodising bath and chemical content shall be set and maintained to
achieve good quality control of the finished product in accordance with BS 3987.
f) A quality control system for cleaning extrusion dies shall be adopted such that no lines appear
on the face of the extrusions. As a minimum check every 5th extrusion.
g) Rejected anodised extrusions shall only be reprocessed once.
h) Anodised finishes shall be within the control limits (established from range samples) or
standards accepted by the CA.
i) The finish shall be agreed with the CA from the range samples provided.
j) The finish shall be sealed in accordance with BS 3987.
k) Finishes shall be tested to BS EN 12373: Part 8.
l) Variation of final surface finish shall be limited to tolerances agreed with the CA prior to
commencement. If such variations do occur then such components that, in the opinion of the
CA, fail to achieve a uniform final surface finish shall be replaced by the Contractor at his own
expense.
m) Lines produced at the location of die connection points shall only occur on non-visible surfaces
in the installed Works. The contact marks on sections resulting from electrical connection shall
not be on visible surfaces of the installed Works.
n) Cleaning Frequency: The normal cleaning frequency associated with the guarantees shall be
not less than 18 months, unless advised otherwise at the time of Tender.
o) Repair of damage: Surface areas likely to be damaged during handling, fixing or by other
building trades shall be fully protected until completion of all other work in the area of the
installation. If during fixing or glazing any damage does occur, this shall be rectified immediately
and not left until the end of the installation. Site rectification of damage shall only be carried out
with the CA’s acceptance and shall carry a 25 year guarantee for colour retention, avoidance of
discolouration and corrosion resistance.
Z33.2103 Testing
a) The CA shall commission an independent testing authority with the Contractor responsible for
all costs incurred. To gain acceptance of the finished products for use, carry out a minimum of
three independent acceptance inspections, sampling procedures and plans, as set out in BS
6001: Part 1, for general inspection level 2. AQL (Acceptable Quality Level) = 1% on each
colour and finish used in the Works. These inspections shall be carried out at the finishing plant
prior to fabrication by a competent independent inspector from one of the approved
laboratories listed in the AASC technical information sheet No. 8.
b) Where there is damage or the production test reports have not been provided, the CA shall
commission an independent investigation of all finishes on Site-fixed units with the Contractor
being responsible for all costs in connection with such Site inspections. This investigation shall
be carried out within the guidelines of BS 6001: Part 2, LQ (Limited Quality) (Pa = 10%) =
5%. For the purpose of this inspection each section in the window curtain wall or other
fabrication shall be taken as an individual component in assessing the overall batch number to
allow the consultant to certify that the completed Contract complies with the Specification. For
units that are finished in fewer than three production runs, acceptance inspections shall also be
made using BS 6001: Part 2 to the same LQ.
c) Certificates of Practical Completion or any other document of authority accepting responsibility
may not be signed by the CA until he has received these reports.
End of Section
Contents
Z36 GASKETS ..............................................................................................................2
Z36 GASKETS
To be read in conjunction with Section A and other related sections of the Specification, Preliminaries
and Contract Conditions.
End of Section