S-000-5131-301 - 0 Project Excution Plan
S-000-5131-301 - 0 Project Excution Plan
S-000-5131-301 - 0 Project Excution Plan
TABLE OF CONTENTS
1. SCOPE
2. GENERAL
2.1 OWNER
2.2 PROJECT GOALS, OBJECTIVES AND KEY SUCCESS FACTORS
2.3 PROJECT SCHEDULE REQUIREMENTS
2.4 CONTRACTUAL REQUIREMENTS
2.5 ORGANISATION AND MULTI-OFFICE ORGANISATION
2.6 INFORMATION TECHNOLOGY (IT) REQUIREMENT AND TOOL
2.7 APPLICABLE CODES AND STANDARDS
2 OF 35
Oman Refineries and Petrochemicals
Project Execution Plan
Company LLC.
S-000-5131-301
Sohar Refinery Improvement Project
Rev.0
Sultanate of Oman
Contract No. 21297
Job No : 120476 / JI-02022
1. SCOPE
This Project Execution Plan describes the methods and activities required to be executed by
CONTRACTOR, as the lump sum Engineering, Procurement, Construction, Testing,
Commissioning, Performance Testing and Completion Contractor, for the Sohar Refinery
Improvement Project of Oman Refineries and Petrochemicals Company LLC, Sultanate of
Oman.
Definitions
JV Joint Venture
Subcontractor Any agency or organization executing any part of the Works under a
contract with the JV Members, individually or as part of the JV
Works All services and works required to be carried out by the Contractor to
meet the Owner’s requirements, and may include temporary works for
the Contractor’s sole use
References
3 OF 35
Oman Refineries and Petrochemicals
Project Execution Plan
Company LLC.
S-000-5131-301
Sohar Refinery Improvement Project
Rev.0
Sultanate of Oman
Contract No. 21297
Job No : 120476 / JI-02022
2.1 OWNER
Oman Refineries and Petrochemicals Company LLC (Owner) in the Sultanate of Oman
has entered into a Contract with a JV of Daelim Industrial Co. Ltd. (based in Seoul,
Republic of Korea) and Petrofac International Limited (based in Sharjah, United Arab
Emirates) for expansion of facilities at the existing Sohar Refinery in Oman, for the
production of various downstream products.
As part of the overall project, ORPC has separately entered into a number of licensor
documents with the following technology providers for the units mentioned against each
name:
a) Reactor Package – ordered on ATB Riva Calzoni: include three (3) high pressure
reactors as well as two (2) hot high pressure separator vessels
b) Centrifugal Pumps Package (High Pressure Pumps) – ordered on Flowserve BV:
include ten (10) High Pressure Pumps with drives and auxiliaries
c) Centrifugal Compressor Package – ordered on Nuovo Pignone S.p.a (Oil & Gas
Business of GE Company): includes one steam turbine driven Recycle Gas
Compressor along with auxiliaries and sub-systems
d) Reciprocating Compressor Package – ordered on Howden Thomassen Compressors
BV: include three (3) motor driven Make-up Hydrogen Compressors along with
auxiliaries and sub-systems
4 OF 35
Oman Refineries and Petrochemicals
Project Execution Plan
Company LLC.
S-000-5131-301
Sohar Refinery Improvement Project
Rev.0
Sultanate of Oman
Contract No. 21297
Job No : 120476 / JI-02022
Contractor to work with the above mentioned technology providers and novated Sellers,
as well as various other Sellers and sub-Contractors, to achieve the required completion
of the Contract requirements.
Owner has contracted scope of work in a greenfield area which will encompass new
process units, utility and offsites units, and storage, as well as a brownfield area within the
existing Sohar Refinery, for revamp of existing units and tie-ins to existing facilities.
Contractor is fully committed to work with the Owner as a team to meet project objectives.
These include,
• work for the greenfield as well as brownfield aspects of the work; in the brownfield
areas work with the Owner’s permit-to-work system
• drive the concept of Health, Safety and Environment (HSE) management throughout
all phases of the project and ensure that all targets, measured by key performance
indicators, are fully met
• Comply with all the local and Omani laws and regulations
• achieve all Contract milestones, which reflect a construction driven engineering and
procurement schedule
• take a pro-active approach and fully co-operate with and support the Owner
regarding all project interfaces and ensure efficient interface co-ordination with other
project parties by timely resolution of interface issues and close-out of interface
actions
• achieve In Country Value (ICV) in line with the agreed ICV Plan
5 OF 35
Oman Refineries and Petrochemicals
Project Execution Plan
Company LLC.
S-000-5131-301
Sohar Refinery Improvement Project
Rev.0
Sultanate of Oman
Contract No. 21297
Job No : 120476 / JI-02022
• develop and maintain a good working relationship with Subcontractors and Sellers
and other stakeholders by conducting business in an ethical, professional, fair and
reasonable manner
• provide a complete set of ‘as-built’ documentation to the Owner required for taking
over the facilities
• accomplish the entire project works within the target schedule and contract price
The Contract requires that Initial Acceptance of the facilities should happen within thirty
six (36) months after 25-Nov-2013, the Effective Date of Contract.
Contract also requires that Final Acceptance of the facility should happen after completion
of the Defects Liability Period or twelve (12) months after Initial Acceptance.
To meet the above, Contractor will submit the Level III schedule for Owner’s approval
which affects a 34 months working schedule.
The contractual requirements between the Owner and the Contractor are spelt out in the
Contract dated 25-Nov-2013.
The Contract also has the following Appendices which form part of the Contract:
• Appendix A – Owner’s Requirement [this includes seven (7) Addendums and twenty
eight (28) Circulars]
• Appendix B – Payment Schedule & Terms
• Appendix C – Schedule of Permissions to be obtained by the Owner
• Appendix D – Work Programme and Key Milestones
• Appendix E – Completion Tests, Performance Guarantees and LDs
• Appendix F – Safety Targets
• Appendix G – Form of Direct Payment
• Appendix H – Form of Performance Bond
• Appendix I – Form of Advance Payment Bond
• Appendix J – Key Personnel
• Appendix K – Minimum Insurances
• Appendix L – Form of Novation Agreement
• Appendix M – Form of Parent Company Guarantee
• Appendix N – Training of Owner’s Personnel
6 OF 35
Oman Refineries and Petrochemicals
Project Execution Plan
Company LLC.
S-000-5131-301
Sohar Refinery Improvement Project
Rev.0
Sultanate of Oman
Contract No. 21297
Job No : 120476 / JI-02022
Contractor is a Joint Venture (JV) between Daelim Industrial Co. Ltd. (‘Daelim’) and
Petrofac International Ltd. (‘Petrofac’). Daelim is the JV Leader.
The scope of work has been split appropriately by the JV Members. To the Owner
however, the JV will work as a single, united entity.
Engineering for the units/plant areas in each JV Member’s scope will be carried out in one
of each Member’s Engineering offices – in Seoul, South Korea, for JV Leader Daelim, and
Mumbai, India, for JV Member Petrofac. A dedicated office area will be provided for the
Owner’s team in Seoul as well as the JV teams in Seoul and Mumbai. Contractor will
assign competent resources to execute the project. It is envisioned that at least for the
initial phase of the Engineering part of the project, JV Member Petrofac’s lead engineers
for each Engineering discipline will be stationed at JV Leader Daelim’s office in Seoul to
have direct interface with and liase more effectively between the two Engineering teams,
as well as act as a part of the JV Engineering interface with the Owner’s Engineering team
which is expected to be stationed there.
Smartplant (SP) 3-D 30%, 60% and 90% model reviews are planned to be done at JV
Leader Daelim’s office in Seoul along with Owner.
Procurement will be done either using Daelim’s ‘Ensemble’ procurement software for the
Daelim procured items, and Petrofac’s ‘Vision’ software for the Petrofac procured items, or
will be done exclusively using one of these two systems for procurement by both JV
partners.
Inspection and testing [including factory acceptance testing (FATs)] will be done as
required at the Seller manufacturing locations.
7 OF 35
Oman Refineries and Petrochemicals
Project Execution Plan
Company LLC.
S-000-5131-301
Sohar Refinery Improvement Project
Rev.0
Sultanate of Oman
Contract No. 21297
Job No : 120476 / JI-02022
documentation, to/from the Owner’s document system, will happen from a JV platform
residing in Daelim’s office in Seoul or Petrofac’s office in Sharjah.
The project will be executed in line with the SRIP Project specifications utilizing the
Contractor’s established engineering standards, procedures, guidelines covering design,
engineering, procurement, testing/inspection and construction phases of the work, all in
accordance to a Quality System conforming to ISO 9001.
The following approach will be used for IT usage for the project:
Engineering software
a) SP3D will be used for 3-D modeling of the plant, and extraction of 2-D drawings, for
Piping, Civil, Electrical, Instrumentation and Telecommunication layouts. This will
work on global workshare concept, with mirrored databases functioning at both
Daelim Seoul and Petrofac Mumbai offices.
b) SPPID will be used for P&ID generation.
c) SPI will be used for Instrumentation engineering deliverables like data sheets, wiring
drawings, termination drawings. The Daelim and Petrofac databases will be separate,
and will be merged on necessary occasions like when deliverables to Owner need to
be provided, or if required to be provided merged to the Integrated Control and Safety
System (ICSS) Seller.
d) SPEL will be used for Electrical Engineering final as-built stage deliverables. SPEL
will be hosted at one location, either at Daelim or at Petrofac office.
e) 2-D drawings will be generated and presented in AUTOCAD format.
Procurement software
Procurement record and tracking will be done either using Daelim’s ‘Ensemble’
procurement software.
Documentation
Petrocept DC at Petrofac’s side, and Daelim’s EDMS at Daelim’s side will be used as a
depository/tracking mechanism/reporting mechanism for Engineering and Seller
deliverables.
8 OF 35
Oman Refineries and Petrochemicals
Project Execution Plan
Company LLC.
S-000-5131-301
Sohar Refinery Improvement Project
Rev.0
Sultanate of Oman
Contract No. 21297
Job No : 120476 / JI-02022
All international and national codes, standards and recommended practices referred in the
Contract as applicable shall be followed by the Contractor. The edition/version/revision
current as on the Effective Date shall be considered relevant.
Contractor has a HSSE Management System (HSSEMS) which provides the framework to
enable the implementation of the specified standards, procedures, and practices in a
consistent manner. The HSSEMS defines the application of HSSE into the work practices,
processes, and systems for Engineering / Design, Procurement, Construction, and
Commissioning involving Project execution and delivery. Contractor’s HSSEMS identifies
the requirements relating to HSSE and provides the baseline for application and Project
execution in compliance with the Health, Safety, and Environmental Management Systems
requirements prescribes in OHSAS 18001:2007 and ISO 14001:2004 respectively.
Contractor’s HSSEMS shall meet the requirements and be compatible with Owner’s HSSE
Management System and shall demonstrate alignment with the Contract requirements.
Contractor shall develop a Project HSSE Plan (Doc. No. S-000-5242-001) which is the
highest level Project HSSE document and, as such, defines the execution strategy, HSSE
Management and methodologies for implementation. It is designed to complement the
Project Execution Plan and provide a disciplined framework for management of HSSE
aspects for the Project. It is the link document for Contractor HSSE Management System
for the Project application.
The approach to HSSE for design and in the field is “risk-based” , and as such, the Project
HSE Philosophy identifies the assessments and studies to be undertaken to certify that all
the necessary measures and safeguards can be identifed and catered for to ensure an
inherent safe design, safe execution, and risk reduction to ALARP. In addition to the risk-
based approach, Contractor shall also fully meet the requirements, specifications, and
standards of the Owner.
The Project HSSE Plan has been developed based on the Owner’s requirements and the
HSSE Management systems of the Contractor to:
9 OF 35
Oman Refineries and Petrochemicals
Project Execution Plan
Company LLC.
S-000-5131-301
Sohar Refinery Improvement Project
Rev.0
Sultanate of Oman
Contract No. 21297
Job No : 120476 / JI-02022
• Describe the arrangements in place for the management of HSSE during the execution
of the Project.
• Identify hazards and provide safeguards / measures to prevent, control, or mitigate the
hazards to ensure that risk is reduced to ALARP.
• Construct and complete the plant without harm or injury to anyone or damage the
environment by adopting the principles of zero tolerance
• Develop mechanisms such that all personnel understand the hazards and the
safeguards in place.
• Set performance targets such that the expectations of the Project are known and
understood by all.
• Specify the mechanisms in place for the review and monitoring of the HSSE
performance to ensure that the objectives and targets are achieved and to identify
where opportunities for improvement are available.
Contractor shall implement an effective Hazard and Effects Management process
throughout all the phases of the project. Equipment integrity is assured through design,
construction, and procurement in accordance with recognized Codes, Standards, and
Practices. Potential hazards in new and existing plants shall be identified systematically.
The risks shall be evaluated using qualitative and quantitative techniques, and reduced to
levels as low as reasonably practical (ALARP) by appropriate engineering and managerial
methods.
Hazard Identification Risk Assessment (HAZID) shall be conducted prior to commencement
of major permanent works. Temporary works, including camps and offices, shall be
controlled through JSAs specific for the activity. HAZID shall consider potential risk
exposures of the Project and where additional controls, workshops, training etc… are
required to review and manage the risks. HSSE workshops shall be held to cover the
mobilisation Phase and construction phases, and these workshops will be conducted prior
to the start of the relevant activity.
10 OF 35
Oman Refineries and Petrochemicals
Project Execution Plan
Company LLC.
S-000-5131-301
Sohar Refinery Improvement Project
Rev.0
Sultanate of Oman
Contract No. 21297
Job No : 120476 / JI-02022
11 OF 35
Oman Refineries and Petrochemicals
Project Execution Plan
Company LLC.
S-000-5131-301
Sohar Refinery Improvement Project
Rev.0
Sultanate of Oman
Contract No. 21297
Job No : 120476 / JI-02022
Contractor shall ensure that Fitness to work process, Health Risk Assessments, Drug &
Alcohol policy, and general health requirements are implemented throughout the execution
of the Project.
Contractor shall develop Security Management Plan (Doc. No. S-000-5242-006) and
Emeregency Response Plan (Doc. No. S-000-5242-005) to implement an effective
HSSEMS.
Contractor places prime importance on Environmental issues, and as such, Contractor shall
develop and Environmental Management Plan (Doc. No. S-000-5242-003) and Waste
Management Plan (Doc. No. S-000-5242-004). An Environmental,Aspects and Impacts
Register shall be developed in order to identify and manage the environmental
risks/aspects associated with CONTRACTOR project activities. The register shall also
include details of management and mitigation measures to be implemented throughout the
execution of the Project.
Contractor will undertake to implement a quality management system for the Project with
the following objectives:
The project will be executed in accordance with Contractor’s established engineering and
quality standards and procedures covering design, engineering, procurement, inspection
and testing, and construction phases of the work, all in accordance with Quality systems
conforming to ISO 9001-2000. Subcontractor work procedures will be reviewed and
approved by CONTRACTOR. Key procedures shall be submitted to Owner for review and
approval. The Project Quality Plan will be implemented for all phases of the project.
Compliance with the plan will be confirmed by planned project audits. The Project Quality
Plan is put in place to assure conformance with the Contract in every respect.
The Project Quality Manager reports to the Project Director for ensuring that the Project
Quality Plan is being implemented and the required quality is being achieved.
12 OF 35
Oman Refineries and Petrochemicals
Project Execution Plan
Company LLC.
S-000-5131-301
Sohar Refinery Improvement Project
Rev.0
Sultanate of Oman
Contract No. 21297
Job No : 120476 / JI-02022
The level of inspection intervention and visit frequencies will depend on the criticality of
equipment, defined in the quality section of each requisition/Subcontract.
CONTRACTOR will lead all site quality management and control activities. CONTRACTOR
will assign a Site Quality Manager, QC Coordinators, welding engineer, QC engineers and
discipline inspectors. Subcontractor quality control personnel will be integrated in the site
Quality team under the direction of the Site Quality Manager.
The project implementation process required for performing, monitoring and measuring all
significant activities and their sequence, interactions are determined for this project in order
to achieve error/defect free deliverables and facilities.
Contractor shall nominate two Project Sponsors (one from each JV partner) to serve as an
active link between the Owner and Contractor’s Senior Management.
Contractor shall identify and appoint a Contractor’s Representative who will lead the JV
Directorate. He shall be knowledgeable in all aspects of the Contract and the Work, and
shall be responsible for all aspects of the work, from the commencement until final
acceptance. This responsibility shall include the provision of all services necessary to
ensure that the Project proceeds in an orderly and timely manner in accordance with the
Contract.
Contractor’s JV shall comprise a dedicated full-time project execution team, under the
responsibility of the Project Director. The Project Director is responsible for all the phases of
the project and discipline activities, including HSSE, Project Controls, Quality, Engineering,
Procurement, Quality Assurance and Quality Control, Inspection and Testing, Construction,
Pre-commissioning and Commissioning. The Project Director’s responsibilities also include
co-ordination/liaison with Owner and Subcontractors.
The Project Director shall be supported by the following key project task force personnel
who each in turn will be supported by staff and discipline specialists:
13 OF 35
Oman Refineries and Petrochemicals
Project Execution Plan
Company LLC.
S-000-5131-301
Sohar Refinery Improvement Project
Rev.0
Sultanate of Oman
Contract No. 21297
Job No : 120476 / JI-02022
• Project Manager
• Interface Co-ordinator
• QA/QC Manager
• Project Controls Manager
• Project Contracts Manager
• Engineering Manager
• Project Procurement Manager
• Home Office Construction Support Manager
• Site Manager
• Commissioning Support Manager
Deputy Project Director (DPD) reports to Project Director and deputizes for him during his
absence. The DPD focuses on ensuring that CONTRACTOR offices comply with the
requirements of the Contract by achieving the targets, ensuring adherence to the Project
Quality Plan, and allocation of adequate resources for the performance of the execution
teams.
IT Manager reports to the PD and is responsible for setting up and maintaining the IT
network between the various JV offices and the Owner’s systems, hosting the various
software used for the project, ensuring adequate licenses for all users, co-ordinating with
the project and engineering teams, and ensuring a trouble-free seamless IT system for the
project.
Project Manager reports to the PD and is responsible for internal & external coordination for
all pre-order & post order activities for all Purchase Orders placed for the project, including
equipment, bulk materials and services. Also, he has overall responsibility for interfacing
and enabling the construction, pre-commissioning and commissioning teams. Project
Manager is supported by a dedicated team of Project Engineers.
Interface Co-ordinator reports to the PD and is responsible for ensuring effective interfacing,
exchange of information, and seamless work flows between the JV partners.
QA/QC Manager is responsible for developing the Project Quality Plan for all the Quality
Assurance & Quality Control aspects of the project, ensuring adequate QA/QC and
inspection coverage for the project, and handling of NCRs. The Project Quality Plan will
outline the overall framework of the project Quality Assurance program.
14 OF 35
Oman Refineries and Petrochemicals
Project Execution Plan
Company LLC.
S-000-5131-301
Sohar Refinery Improvement Project
Rev.0
Sultanate of Oman
Contract No. 21297
Job No : 120476 / JI-02022
Project Controls Manager reports to the PD and his responsibilities include Project Controls,
Cost control, Project Administration, Document Control, etc. The project controls team led
by the Project Control Manager and is responsible for preparing schedules, reports,
monitoring progress, etc. The Project Controls Manager will coordinate all Project Controls
activities throughout the Project and will be the point of contact for the Owner’s
Representatives on all matters relating to scheduling, progress control, cost control, and
invoicing.
Engineering Manager reports to the PD and is responsible for leading the engineering task
force and coordinating all engineering activities throughout the Project. He will be the point
of contact for the Owner’s representatives on all matters relating to design and engineering
activities. He shall be responsible for the engineering activities carried out in the JV leader’s
office as well as the overall JV engineering activities and in addition liason with the Field
Engineering team. He shall supervise the development of a comprehensive set of
engineering specifications, which provide the parameters and requirements for all aspects
of the engineering, and design of the facilities. He shall ensure that a system is in place to
issue technical documentation in sufficient copies for Owner’s review, approval and
information. The Engineering Manager shall be supported by the Deputy Engineering
Manager who is responsible for the JV partner engineering and co-ordinating with the JV
leader’s engineering team.
Project Procurement Manager (PPM) reports to PD and will be responsible for all
purchasing/buying activities including floating of Request for Quotations, expediting
quotations, preparing Letter of Award and Purchase Orders, and directing the procurement
task force. The Deputy Procurement Manager reports to the Procurement Manager and
carries out the daily procurement activities with the help of the team of buyers and
expeditors.
Home office Construction Support Manager reports to the PD and is responsible for
providing construction inputs and interfacing with engineering and procurement during
preparation of subcontract ITB, constructability study, review of layout and other
construction drawings, preparation of Project schedule etc. He also supports site manager
in building up site infrastructure and enabling facilities and resource mobilisation.
Site manager reports to PD and is responsible for overall construction management and
field construction work including implementation of project HSSE and Quality systems at
site, Subcontract administration, field materials management, and field project controls. He
is supported by Construction managers and respective Field managers responsible for
HSSE, QA/QC, Project planning and controls, Field Engineering, Project Support services,
15 OF 35
Oman Refineries and Petrochemicals
Project Execution Plan
Company LLC.
S-000-5131-301
Sohar Refinery Improvement Project
Rev.0
Sultanate of Oman
Contract No. 21297
Job No : 120476 / JI-02022
Reference can be made to the project organisation charts in subsequent sections in this
Project Execution Plan document.
Contractor’s JV office in Seoul shall host the initial interfaces among the Owner’s and JV
project execution teams. The starting phase of the project will need the Owner and
Contractor’s execution teams interacting and discussing with each other the project
setups including IT awareness, and execution methodologies. The interactions will then
continue throughout the Project cycle in a mutually beneficial and co-operative manner.
Contractor shall undertake a Contract review immediately starting after the Effective date.
The issues brought out as part of the Contract review shall be discussed between
Contractor and Owner for mutual techno-commercial resolution.
Contractor is responsible for overall management and execution of the Project. The
Contractor’s goals in this regard will be driven by
16 OF 35
Oman Refineries and Petrochemicals
Project Execution Plan
Company LLC.
S-000-5131-301
Sohar Refinery Improvement Project
Rev.0
Sultanate of Oman
Contract No. 21297
Job No : 120476 / JI-02022
• establishing a system for acquiring security pass for site mobilization/site visits
• close interaction involving Owner for negotiations and further work on novated Sellers
and their products
• regular meetings, in liaison with Owner, and wherever required with other agencies to
sort out interface issues
• effective use of electronic media, especially e-mails/Internet etc. for better co-
ordination with Owner, Sellers, Subcontractors & site teams
• working closely with Owner to ensure that Commissioning & Performance Tests
follow immediately after Pre-commissioning
• fast track follow up of novated Long Lead Items engineering and drawing/document
reviews/approvals
• early deputation of the engineering team to site for collecting all the relevant data
• leveraging the market situation to lock in vendors to meet budget and to book
capacity
• establishing clarity early in the Project regarding Owner’s involvement in quality and
inspection/testing aspects
17 OF 35
Oman Refineries and Petrochemicals
Project Execution Plan
Company LLC.
S-000-5131-301
Sohar Refinery Improvement Project
Rev.0
Sultanate of Oman
Contract No. 21297
Job No : 120476 / JI-02022
The key activities which are planned to achieve the Project goals are -
• Early mobilization: In order to gain early momentum and to gain from the extensive
tendering / ITT review / pre-award engineering work carried out, there will be a
comprehensive hand over of the project details from the bidding stage proposal task
force to the Project execution teams. This includes internal kick-off meetings carried
out very early in the proposal and post-award stage. Also, key project execution team
personnel are identified early and assigned to the job towards the end of tendering
phase.
• Design review: Technical aspects of the project are reviewed as per the project
procedure and action items are recorded and continuously tracked till close-out.
• Risk review (technical, execution, schedule and commercial) & mitigation plan: A
detailed risk review is carried out (sometimes separate sessions for separate aspects)
and mitigation plans are proposed.
• Kick-off meeting with Owner: Kick-off meeting with Owner carried out to apprise
Owner of the Project execution philosophy and plans, teams involved, strategies
planned, communication channels defined and way forward outlined, based on the
expectations of the Owner.
18 OF 35
Oman Refineries and Petrochemicals
Project Execution Plan
Company LLC.
S-000-5131-301
Sohar Refinery Improvement Project
Rev.0
Sultanate of Oman
Contract No. 21297
Job No : 120476 / JI-02022
The following sections constitute major project execution activities and outline the
Project execution strategy.
Risk management in the Project will aim to minimize the impact of potential Project
exposures and to take advantage of the opportunity for improvement. Contractor will
organize workshops on a regular basis to identify risks. The frequency of these
workshops is dependent on the need. Contractor will identify main areas of attention and
risk issues and these will be discussed with Owner on a regular basis. These issues will
be captured in an action register with possible solution options.
The risk register shall be prepared and submitted at the early stage of the engineering
phase and shall be updated on a monthly basis and circulated to Orpic for information.
The risks beyond acceptable limits will be identified in a structured manner and, based
on historical experience, be listed. The risk identification relates to costs time and
deliverables, as well as issues related to security, liabilities, information, technology,
safety, health, environment and new technologies involved. Also interaction between
risks needs to be considered.
Solutions to eliminate, mitigate or transfer risks, decisions to accept risks and plans to
take advantage of opportunities, should be based on known procedures to avoid
introduction of new risks. When a risk is identified it needs a contingency plan to identify
the undesirable effects and response actions necessary. When deemed necessary
provisions in terms of time float/monetary risk budgets
should be made. Alternatively the risk can be mitigated through subcontracting,
insurance or simply accepted. Risk responses will be clearly documented.
3.8. INSURANCE
Contractor shall provide the applicable insurance covers specified in Appendix K and
satisfying the conditions of Clause 20 in the Contract. These insurances will be provided
jointly or individually by JV Members, as applicable. Contractor will ensure necessary
insurances are provided by Subcontractors and Sellers.
Contractor will make sure that all the insurances are renewed whenever they are due.
Construction All Risks and Third Party Liability Insurance shall be arranged by Owner in
accordance with Appendix K of the Contract.
19 OF 35
Oman Refineries and Petrochemicals
Project Execution Plan
Company LLC.
S-000-5131-301
Sohar Refinery Improvement Project
Rev.0
Sultanate of Oman
Contract No. 21297
Job No : 120476 / JI-02022
• Contractor shall ensure to spend 20% of the Contract value for local spend.
• Contractor shall make provision for employing specialized sub- contractors and
Omani labour recruited in the region.
• Contractor and Subcontractor shall make provision for recruiting thirty percent (30%)
of Omani staff and labour for all job categories, which include on job training.
Contractor will maximize the Omanization and local content as much as possible in
limitation of available Sub-contractors in Oman based on the Approved Vendor List and
also based on the minimum quality and schedule requirements in Contract.
The project control plans will be based on Contractor’s standard project control systems
and procedures, reflecting Owner’s minimum requirements.
20 OF 35
Oman Refineries and Petrochemicals
Project Execution Plan
Company LLC.
S-000-5131-301
Sohar Refinery Improvement Project
Rev.0
Sultanate of Oman
Contract No. 21297
Job No : 120476 / JI-02022
Contractor’s project control plans will identify the specific procedures, methods, forms
and techniques for effective project control during the execution of the Work. This will
address the Contractor’s formation of a JV and will cover all the offices where the Project
is executed. This will also address and comprehend any planning and scheduling
activities performed by its SubContractors. In addition, Contractor’s schedules will
incorporate all schedules prepared by its Seller’s and Subcontractors; and such
schedules shall highlight the interdependencies between the Seller and Subcontractor
schedules and those of Contractor.
The time schedule hierarchy of the project that Contractor will develop and maintain will
comprise as a minimum four levels in which each successively lower schedule level
depicts the project activities in more detail. The structure and detail of the schedules will
be such that the schedule status can be
summarized from the detailed level.
The schedule levels are –
• Early Work Schedule
This will reflect all activities to be performed during the first 3 months of the Project
including all project mobilization and project set-up requirements.
21 OF 35
Oman Refineries and Petrochemicals
Project Execution Plan
Company LLC.
S-000-5131-301
Sohar Refinery Improvement Project
Rev.0
Sultanate of Oman
Contract No. 21297
Job No : 120476 / JI-02022
The Logic Network Schedule (LNS) shall be a precedence based critical path
method network using Primavera software.
3.12. ENGINEERING
Key strategy:
a) Priorities based upon the path of construction
b) Data collection given priority
c) Involvement of construction, commissioning personnel in engineering
Refer the Engineering Execution Plan (Doc. No. S-000-5141-001) for more details.
The design review by the Owner shall be the review/approval/keep for information
activities pertaining to Contractor’s and Seller’s drawings/documents, as well as formal
participation in the workshops for
PFD screenings
Plot plan review
22 OF 35
Oman Refineries and Petrochemicals
Project Execution Plan
Company LLC.
S-000-5131-301
Sohar Refinery Improvement Project
Rev.0
Sultanate of Oman
Contract No. 21297
Job No : 120476 / JI-02022
Constructability reviews
P&ID screenings
HAZOP reviews
SIL classification
3D model reviews
Ergonomic reviews
RBM/RBI reviews
Prestart-up safety assessment
HSSE reviews
The 3D model reviews by Owner and Contractor’s engineering team shall be held at
30%, 60% and 90% model completion.
Contractor will provide individual equipment criticality rating and shall identify the
equipment inspection and maintenance needs (with the assistance of Seller inputs). It
will identify and qualify all preventative and condition monitoring needs and intervals and
thus provide a basis for determining manning levels, potential subcontracted services,
spare part requirements and operational budget estimates.
23 OF 35
Oman Refineries and Petrochemicals
Project Execution Plan
Company LLC.
S-000-5131-301
Sohar Refinery Improvement Project
Rev.0
Sultanate of Oman
Contract No. 21297
Job No : 120476 / JI-02022
• uniform and well defined documentation management system followed across the
project.
The single focal point for the implementation of the document control procedures shall
be the document controller in JV Leader Daelim’s Seoul office during the engineering/
procurement/inspection and testing phase. He will have extensive links and
communication with JV Member Petrofac’s offices in Mumbai and Sharjah, and will be
focal point for the Owner’s document controllers. During the construction phase, JV
Member Petrofac’s Sharjah office or the Contractor’s JV site office shall have prime
responsibility and will be the focal point for the Owner.
The project management, engineering management and QA/QC teams will ensure that
the documents generated for the Project comply with established procedures and project
Contractual specifications. At all levels the teams will ensure that the drawings and
documents generated by the Sellers Vendors comply with the relevant Company
procedures.
Seller documents management:
The drawings and documentation requirements from each Seller will be listed on the
required documentation sheet which forms a part of the Inquiry/Purchase Requisition.
This ‘Supplier Document Requirement List’ (SDRL) will identify the
and so on.
24 OF 35
Oman Refineries and Petrochemicals
Project Execution Plan
Company LLC.
S-000-5131-301
Sohar Refinery Improvement Project
Rev.0
Sultanate of Oman
Contract No. 21297
Job No : 120476 / JI-02022
Seller is required to translate the requirements of the SDRL into a register of individual
documents known as the Vendor Document register (VDR).
The VDR shall list all drawings/documents and ancillary information .Once agreed, the
VDR effectively replaces the SDRL. The VDR in itself is not used to record the status of
documents, but to provide the basic information for loading into the Seller documentation
registers in the finally used Seller documentation handling software. The VDR shall be
considered to be a “live” document for the duration of the Purchase Order.
All drawings and data including Seller’s standard drawings shall be checked for accuracy,
clarity, completeness and conformance with the applicable codes specifications etc.
before submitting to Owner.
Seller shall ensure each document carries either the Document Decal or a Seller
Document A4 Cover Sheet. These shall be given to the Seller along with the Purchase
Requisition.
After the Purchase Order (P.O.) placement, the Expeditor/ Project Engineer will follow-up
with the Seller for submission of data/document indicated in SDRL/ VDR.
The document controllers will check the quality, drawing/document number, revision and
legibility and record the Seller document within the Vendor Document Register (VDR)
module and forward a of the same to the concerned discipline Lead Engineer as per the
Seller document review flowchart. Seller documents shall be reviewed internally by the
Requisition originating discipline and shall be subject to interdisciplinary checks (IDC) as
required. On receipt of internal discipline comments the originating discipline will then
compile all the comments on the Seller drawings/documents and return the same to the
Seller via the Document Controller with appropriate review code.
Review of selected Seller documents by Owner will be carried after review and coding of
Seller documents by Contractor. Parallel reviews if required will be done as necessary in
the interest of Project performance as a whole.
All document controllers will maintain a document register for relevant documentation.
The key strategies to be taken up during procurement to meet Project goals are
a) early procurement of equipment & materials, in line with project specifications and
Approved Project Vendor List.
25 OF 35
Oman Refineries and Petrochemicals
Project Execution Plan
Company LLC.
S-000-5131-301
Sohar Refinery Improvement Project
Rev.0
Sultanate of Oman
Contract No. 21297
Job No : 120476 / JI-02022
Contractor will develop and implement a project specific Project Procurement Plan which
will detail procurement objectives, strategy, Seller management, purchasing, expediting
and transportation.
In view of the current market conditions, availability of Seller shops may be problematic
and long deliveries have to be anticipated for certain package/ specialty items. In line
with the construction driven approach early procurement is a key aspect for ‘on time’
successful implementation of the Project.
To mitigate this risk Contractor will adopt the following early procurement approach:
• early preparation and issue of Inquiry Requisitions for long lead Items/ critical
items.
Contractor’s Procurement team will plan and execute activities to ensure that the
procurement of equipment, materials and services is in compliance to the technical and
quality requirements, budget and overall Project schedule.
The Procurement and Project teams will seek to strike the correct balance between cost
and recognition of the need to ensure timely delivery. The focus will be on areas of
critical delivery, quality and compliance with both Owner and Contractor standards and
requirements.
The Procurement Team will focus on the selection of quality Vendors having high degree
of conformity to Project specifications, satisfactory performance track record and
reasonable after sales support services.
Besides the Project Procurement task force, dedicated expeditors and project engineers
will be assigned with the responsibility for Seller management. This team will be
responsible for all pre and post award coordination with the Owner, Engineering
disciplines, QA/QC, inspectors, and logistics in-charges. Expediting task force will
26 OF 35
Oman Refineries and Petrochemicals
Project Execution Plan
Company LLC.
S-000-5131-301
Sohar Refinery Improvement Project
Rev.0
Sultanate of Oman
Contract No. 21297
Job No : 120476 / JI-02022
comprise of desk expeditors, field expeditors, and shop expeditors (mobilized at specific
Seller shops). Towards maintaining an effective strategy for expediting, continuous in-
field monitoring of the Sellers and supporting expeditious movement of inspection and
expediting personnel will be supported.
The logistics team shall be responsible for safe and timely movement of all material from
Seller shops around the world to the Site including customs and port clearances and
material storage at site storage areas.
The materials controls team in coordination with Project Procurement Manager will be
responsible for the implementation and overall monitoring of the materials management
system and plan.
Contractor will be using an integrated material management system, which will be linked
to the procurement management software modules used in the Project.
3.16. SUBCONTRACTING
The Subcontracting team will be responsible to finalize subcontracts with support of the
Contractor’s offices in Sharjah and Seoul.
The Project Quality Manager and Site Quality Manager will confirm compliance of
Subcontractors with the Project Quality Plan by routine audits.
Subcontractors will use the single Contract HSSE management plan. The project and
site HSSE managers will confirm compliance by routine audits and key performance
indicators.
3.17. CONSTRUCTION
27 OF 35
Oman Refineries and Petrochemicals
Project Execution Plan
Company LLC.
S-000-5131-301
Sohar Refinery Improvement Project
Rev.0
Sultanate of Oman
Contract No. 21297
Job No : 120476 / JI-02022
The overall construction of the facilities will be planned meticulously and executed
smartly by a strong and committed construction management team from the Contractor’s
side, backed up with robust systems and procedures in place and proven experienced in
the construction management and execution of mega projects.
Construction Management:
The Construction management team’s organizational structure will be designed to
support main working areas exclusively i.e process areas, utilities/off-sites areas and
work inside the existing Sohar Refinery.
Each of these areas will have a dedicated construction management team under a
Construction Manager/Construction Superintendent reporting to the Site Manager.
Linked across this organization are functional groups with distinct responsibilities.
These functions provide the work processes, procedures, monitoring/control and
expertise to deliver efficient, responsible, and safe construction that meets or exceeds
acceptable level of performance in all aspects – quality, cost, schedule and
sustainability while completing all the work with no harm to person, asset and the
surrounding environment.
All Construction work will be subcontracted to competent & experienced
Subcontractors after due diligence and adequate evaluation. The construction
management team will be commensurate with the nature and scope of the Project with
responsibility for management of subcontracts and hands-on supervision of
Subcontractor’s work, covering all aspects of work (HSSE, Quality, and Schedule)
through experienced & dedicated multi-disciplinary team.
28 OF 35
Oman Refineries and Petrochemicals
Project Execution Plan
Company LLC.
S-000-5131-301
Sohar Refinery Improvement Project
Rev.0
Sultanate of Oman
Contract No. 21297
Job No : 120476 / JI-02022
Construction Strategy:
• identification of key senior construction personnel early with a clear corporate
commitment to maintain the identified personnel throughout the required construction
phases of the project
• mobilization of Site Manager and experienced construction specialists to the
Contractor’s engineering offices to participate in review of layout during early
engineering phase and to provide inputs for Constructability
• mobilization of work crews in a progressive manner in accordance with the
schedule requirements and workload projection. Construction manpower is provided by
subcontractors & normal working hours are 10 hours/day, 6 days/week.
• identification and execution of Early Works - topographic and geotechnical survey,
site preparation and temporary facilities installation as per an engineered and approved
plan starting early upon availability of access to the site and required clearance for
commencement of work.
• Alignment of construction sequence/path of construction with the overall project
schedule and embedding the same in the construction schedule. Finalisation of the
programme of work for all areas in advance taking into consideration the schedule and
achieved progress. In general, the following sequence of work will be followed:
- mobilisation
- site surveys
- site preparation /temporary facilities including construction of traffic
island and construction gates
- piling work
- construction of main Substations
- construction of other buildings
- underground facilities
- foundations
- pre-cast pipe racks
29 OF 35
Oman Refineries and Petrochemicals
Project Execution Plan
Company LLC.
S-000-5131-301
Sohar Refinery Improvement Project
Rev.0
Sultanate of Oman
Contract No. 21297
Job No : 120476 / JI-02022
After major commodity progress, the overall execution program will be oriented and
aligned with the commissioning requirement, with aim to assure availability of
permanent utilities for commissioning and start-up of the plant.
Constructability:
The Project constructability program will be initiated from an early stage of the
Project. Constructability aspects will be captured normally as part of 30%, 60% and
90% 3-D model review. The strategy of constructability is to proactively engage
construction expertise from the beginning of the design process, so that when
design is completed specific attributes related to constructability and preassembly
are incorporated.
Examples of the elements within these programs include:
a) determining the optimum path of construction
b) incorporating best practices while reducing construction complexity.
c) integrating HSSE considerations and requirements into the design and
purchasing cycles
d) optimizing workplace efficiency
e) identifying opportunities to preassemble work offsite
f) evaluating capabilities of remote preassembly at shops and yards
g) performing technical studies for heavy haul and heavy lifts
h) supporting procurement through evaluation of traffic and logistics
i) facilitating management integration and continuity in project deliverables.
Suggestions, ideas and opportunities related to constructability and preassembly will
be processed in accordance with the respective plans, with approvals by the
Managers of Engineering, Procurement and Construction as appropriate.
The basis for successful Pre-commissioning, Commissioning and Start-up resides in the
paperwork and the planning, and thus these activities should commence early in the
30 OF 35
Oman Refineries and Petrochemicals
Project Execution Plan
Company LLC.
S-000-5131-301
Sohar Refinery Improvement Project
Rev.0
Sultanate of Oman
Contract No. 21297
Job No : 120476 / JI-02022
project. Key Commissioning personnel as required will be mobilized along with the
Project Management and Engineering discipline teams and will be integrated with the
Project task force during the early stages. They will closely interact with the Owner’s
Commissioning personnel to understand the requirements, operating philosophies,
sequences etc. As the project progresses through the engineering and construction
phases, key personnel from the Engineering and Construction groups will also be
progressively moved to work with the Commissioning team to maximise knowledge
transfer and continuity. Early involvement of the Commissioning team and early
movement of Engineering personnel in particular the Process and Instrumentation
disciplines will ensure that plant design and associated databases and documentation
etc. are developed in a manner which will facilitate a safe and efficient start-up.
The plans and procedures etc. developed by the Commissioning team will clearly
document the progressive and hierarchical discipline, subsystem/area, system and multi-
system work scope required to satisfy the overall Project execution schedule.
Mechanical Completion, Commissioning, start-up and turnover activities will be
progressed and recorded through an extensive system of check sheets, inspection and
test records, procedures and reports, which will also recognize and satisfy certification
requirements.
It is also envisaged that experienced members of the Owner’s project and operations
groups will be integrated into the team to take on an active role.
The work scope will be planned in a logical manner reflecting the progressive
development from discipline to system to multi-system activities, phased as necessary to
integrate with construction activities and existing plant shutdown schedules. Safety will
be of primary importance and the plan will recognize all Permit To Work (PTW) issues,
particularly isolation of ‘live’ systems from adjacent/simultaneous construction activities.
Indeed it is precisely this type of issue, which necessitates early involvement of the
Commissioning team during the design phase. Licensor support will be obtained by
Contractor wherever required. Any additional support if the Contractor feels necessary
shall also be obtained from the respected Licensor
The key Commissioning staff will be integrated into the Construction team and will do
the Commissioning, start-up and initial operation in a seamless fashion in order to
31 OF 35
Oman Refineries and Petrochemicals
Project Execution Plan
Company LLC.
S-000-5131-301
Sohar Refinery Improvement Project
Rev.0
Sultanate of Oman
Contract No. 21297
Job No : 120476 / JI-02022
ensure the most effective learning process are achieved. The transition from bulk
completion to system/sub-system completion will be closely monitored/ driven to achieve
scheduled milestones. The technicians involved in the initial operations may be used
during Pre-commissioning, Commissioning, start-up, and initial operations to achieve
minimal disruption between the phases of completion.
A Pre-Commissioning and Commissioning Execution Plan and associated Pre
commissioning, Commissioning and start-up manuals will be developed during the
engineering phase of the project, which take into account the Commissioning logic, start-
up and operational requirements.
Contractor will utilize a specific software for the Pre-commissioning and Commissioning
activities. This will be the Project electronic Completions and certification system. The
pre-Commissioning/Commissioning team will manage the verification and testing scope
of work from construction through to Commissioning.
As the construction, Commissioning and operations team use the same database, then
systems and sub-systems can be verified for functional performance and during
handover the requisite documentation and acceptance certification can be generated.
The final documentation from Commissioning will be the Ready For Start-Up (RFSU)
Dossiers. Contractor will compile documentation pertaining to the commissioning
activities in a RFSU dossier arranged by system/subsystem. The RFSU dossier will
contain all information required to demonstrate that the Subsystem has reached the
RFSU stage.
3.19. TRAINING
Contractor will develop detailed training plans for the classroom based sessions and on-
job at Site. On-job training at site will be more of a practical nature and be aimed at
maintenance and operational staff. This training will be conducted largely by Seller
specialists and supplemented by Contractor personnel where appropriate. The scope will
be targeted towards complex equipment and packaged units, for example the
DCS/SIS/FGS/VMS, analyzers, compressors, special valves etc.
Contractor shall include Owner’s requirements for training by Suppliers in all relevant
requisitions, as optional scope.
The purpose of the training is that Owner acquires the ability to operate and maintain the
plant while achieving optimum performance, availability and reliability of the facilities.
The employees of maintenance, production and process engineering sections, including
32 OF 35
Oman Refineries and Petrochemicals
Project Execution Plan
Company LLC.
S-000-5131-301
Sohar Refinery Improvement Project
Rev.0
Sultanate of Oman
Contract No. 21297
Job No : 120476 / JI-02022
In general the trainer can assume an audience with adequate proficiency and experience
in refineries or the process industry.
There are some common elements that shall be part of each Seller provided training:
- the lecture and material shall be in English.
- the trainer shall ensure proper interpretation of the drawings by the trainees.
- any service agreements shall be discussed with the maintenance employees.
Training shall be given at the premises of Owner. If the location is not suitable the Seller
shall find alternative accommodation. Training at Seller’s premises will require prior
approval from Owner.
The As-Built Drawings will be prepared as per the Owner requirements defined in the
‘AB’ column in the ‘Specification for EPC Documents requiring CLIENT’s Review’ (Doc.
No. S-000-5140-104 Rev. 1) in the Contract.
The Contractor’s Site team will keep a true and up-to-date mark up of drawings and
documents to reflect site comments/modifications and forward these to the engineering
offices after successful Commissioning of the system. The engineering office will
incorporate site modifications and issue necessary copies of as-built drawings and
documents as per Contract for COMPANY reference and record.
General Remark: Documentation and data shall be provided in the formats requested by
the owner as per the project specs and the data shall be compatible with the IT system
as per the Contract. It is considered that such IT requirements are covered elsewhere in
Contract.
Contrcator will issue a formal project close out report at the end of the project,
incorporating details from all relevant discipline and groups.
General Remark: Lessons learnt session shall be conducted to capture project lessons
33 OF 35
Oman Refineries and Petrochemicals
Project Execution Plan
Company LLC.
S-000-5131-301
Sohar Refinery Improvement Project
Rev.0
Sultanate of Oman
Contract No. 21297
Job No : 120476 / JI-02022
learnt
4. CONTRACTOR’S ORGANISATION
The Contractor will have a comprehensive Project execution organisation which will see
through the complete Project cycle till hand over/Final Acceptance.
Any change in the key personnel as identified in Appendix J of the Contract will be with the
approval of the Owner.
Project nominated personnel including key personnel are shown in the table below. Also
refer the Organograms attached to this Project Execution Plan document.
34 OF 35
Oman Refineries and Petrochemicals
Project Execution Plan
Company LLC.
S-000-5131-301
Sohar Refinery Improvement Project
Rev.0
Sultanate of Oman
Contract No. 21297
Job No : 120476 / JI-02022
35 OF 35