MSRA Installation of Firefighting System
MSRA Installation of Firefighting System
MSRA Installation of Firefighting System
Date: 13-04-2020
Method Statement
Installation of firefighting system
1
Ref.
Date: 13-04-2020
This Method of Statement covers the onsite procedures which explain and covers the installation of firefighting system and requirements of checks to be carried
out.
The purpose of this method of statement is to ensure that the works are conducted at site as per the approved shop drawings and approved materials. To ensure
that safety measures are maintained at site. To ensure that the testing and inspections are carried as per the specifications.
2. REFERENCE DOCUMENTS
1. Project specifications
2. Approved shop drawings (latest reversion)
3. Approved materials submittals
3. GENERAL
2
Ref.
Date: 13-04-2020
6 LPO Local Purchase Order
5. EQUIPMENT
1. Threading Machine with Accessories.
2. Grooved Machine with Accessories.
3. Welding Machine with accessories.
4. Pressure Pump for Pressure Test.
5. Hole Saw Machine.
6. Pipe wrench (Different Sizes)
7. Spanner tool
8. Adjustable spanner
9. Hammer (1.5 kg max.)
10. Hacksaw
11. Screw Driver (Positive & Negative)
12. Spirit Level
13. Round file / Flat file
14. Measuring Tape
15. Hack Saw blade
6. RESPONSIBLE PERSONNEL
a. Project Manager
b. The Project Manager is responsible for overall implementation of contract specification and requirement of the project, including assignment of personnel to
implement procedure requirements and for approval of special receiving procedures.
c. Make sure all submittals are given to Main Contractor/Authority for MEP works as per scheduled date.
d. Make sure that all MEP works follow the progress of civil works at site and no complaints arise from Main Contractor/Client/Consultant as per program of work.
3
Ref.
Date: 13-04-2020
e. Responsible for all permit concerned, control measures, plant and labor needed to execute the works according to the scope/program are available and
workable.
f. To Co-ordinate with the Project & Site Engineer, Safety Officer, Foreman for safe and proper execution of the works.
g. To guide specific attention to all safety measures in co-ordination with Safety Officer.
2. Project Engineer
1. Handle the submission of submittals like Material Submittal, Shop Drawings, and RFI in coordination with full team.
2. Handle and follow-up suppliers for receipt of materials at Stores/Site as per LPO’s issued.
3. Coordination to all site team and to the project manager for any issues arises at site.
4. Responsible for outsourcing activities as per approved vendor’s list.
5. Attend meetings with the consultant, main contractor & sub-contractor.
6. Ensure to execute and monitor site progress and condition as per approved baseline program.
3. Site Engineer
1. Lead person for site work as per the approved material, shop drawings and Method of Statement.
2. Handle WIR for all installation works and submit to consultant for inspection.
3. Carry out the work at site & monitor manpower’s work as per approved shop drawing and as per specifications to the quality required, for approval by the Main
Contractor/Consultant.
4. Allocate labor for various activities in consultation with the Supervisor as per requirements at site on a daily basis.
5. Coordination to all site team and to the project Engineer for any issues arises at site.
6. Responsible for preparation of Hot Work Permit/Over-night permit from Safety Officer prior to start work.
4. Foreman
1. Responsible for preparation of Hot Work Permit/Over-night permit from Safety Officer prior to start work.
2. Ensure that tool box meetings in coordination with Safety Officer/Supervisor every day prior to start the work.
4
Ref.
Date: 13-04-2020
3. Daily works assignment of technician and charge-hand. Assuring also that all technician and charge-hand follows the HSE regulations at site in monitoring of the
foreman.
5. Safety Officer
1. To ensure that all persons are wearing their PPE at site and in hazardous locations.
2. To ensure implementation of all safety measures related to the nature of the works.
3. Production of the risk assessment in conjunction with Project Manager and presentation to the site team in form of a tool box talk.
4. To ensure that all personnel are aware of their responsibilities, alert and safe.
5. To coordinate with the Project Manager to ensure that all the implemented safety measures are effective enough to maintain safe working on site.
6. To give special concern to housekeeping and ensure the area of work is kept clean and tidy.
7. To ensure access to the area of work is maintained and clear and safe for both vehicles and personnel. Ensure all requires signs for the safe execution of the job
are in place and regularly monitored.
8. Check and approve all hot works permit, plant certification etc.
6. Store Keeper
1. To ensure implementation of all safety measures related to the nature of the works.
2. Production of the risk assessment in conjunction with Project Manager and presentation to the site team in form of a tool box talk.
3. To ensure that all personnel are aware of their responsibilities, alert and safe.
4. To coordinate with the Project Manager to ensure that all the implemented safety measures are effective enough to maintain safe working on site.
5. To give special concern to housekeeping and ensure the area of work is kept clean and tidy.
6. To ensure access to the area of work is maintained and clear and safe for both vehicles and personnel. Ensure all requires signs for the safe execution of the job
are in place and regularly monitored.
7. Check and approve all hot works permit, plant certification etc.
8. Responsible for keeping all materials received in organized manner as per approved method statement and ensure that all materials are inspected and
approved by Consulting Engineer.
5
Ref.
Date: 13-04-2020
9. Responsible for tracking all materials and keeping count of all items (in and out register) and provide daily weekly reports.
10. Monitor materials which having an expiration date (provide shelf-life register) to avoid usage of expired materials.
7. HANDLING AND STORAGE
1. All the materials received as site shall be handled and stored as per the manufacturer’s recommendation.
2. All received material will be checked by storekeeper and site engineer for the confirmation to the project specification and approved material.
3. MIR shall be raised on every lot of delivery by attaching the deliver note and country of origin certificate (If applicable).
8. PROCEDURE
PRE-INSTALLATION PROCEDURE
1. Ensure that Piping Material received are inspected and found acceptable as per approved materials submittal, are available to carry out the work.
2. Proper Material including pipes and fittings are to be selected and used in accordance with approved shop drawings.
3. Ensure that all related material of approved make is available before carrying out any work.
4. Prior to Commencement of work, areas and access will be inspected by safety officer to confirm that site is ready to commence the work and all relevant shop
drawing dully approved for construction.
5. All relevant documentation (Drawings) and Material applicable to particular section of work will be checked by Site Supervisor prior to commencement of work.
6. The Site Engineer/ Site Supervisor will give necessary instructions to foreman and provided necessary approved construction/ shop drawings of latest revision
along with coordinated lay outs.
7. Ensure that location of grid lines, reference levels are marked by main contractor.
INSTALLATION PROCEDURE
INSTALLATION OF SPRINKLERS
6
Ref.
Date: 13-04-2020
2. The sprinkler points are checked at site locations as per approved layout/coordinated drawings.
3. Before installing the sprinklers, check whether the sprinkler bulb has any damage.
4. Reference gridlines shall be established to determine exact location of sprinkler heads as per Reflected ceiling plan
5. Install correct type of sprinkler heads as per approved drawings and manufacturer’s instruction.
6. Wrap with Teflon Tape to respective Sprinklers.
7. Tightened the sprinklers into the provided fittings.
8. Remove the safety cap on the sprinklers before DCD inspection.
9. For sidewall and recessed pendent escutcheon plate is provided after the ceiling, ceiling to be holed as per the escutcheon plate size requirements
10. Zone control valve set (butterfly valve, flow switch, pressure gauge test & drain valve) to be installed as per the DCD requirements
a. Minimum distance should be provided between flow switch and the butterfly valves per the manufacture guide lines
b. Drain should be provided at lowest point of the pipe to ensure 100% drain
7
Ref.
Date: 13-04-2020
1. Installation as per NFPA 14.
2. Confirm the cabinet location on the approved drawing and provided cabinet are appropriate for the location and ensure no damage.
3. Ensure the provided space by civil with opening are sufficient to install the cabinet.
4. Make necessary holes in the cabinet for piping (2 ½” and 1”).
5. Locate the cabinet above the up stand (300mm from FFL) and fix the bolt and check the stability.
6. As per DCD requirement the remotest landing valve pressure at 6.9 bar
7. Install the 2 ½” landing valve on the pipe taped from the wet riser in the lower compartment of the cabinet.
8. Tap the 1” piping from the landing valve line or from riser for hose reel connection along with PRV and LSV.
9. Connect the fire hose of 2 ½ “along with necessary adapter and nozzle.
10. Provide the extinguisher inside the fire hose cabinet as per the approved material submittal.
TESTING:
Description Observation
8
Ref.
Date: 13-04-2020
9. QUALITY CONTROL
1. Project Engineer along with Site Engineer and Site Supervisor will monitor that all components are installed as per the contract specifications and approval
submittals.
2. Inspection Request (IR) shall be submitted to the Main Contractor/Consultant after completion of installation of riser pipes along with testing.
9
Ref.
Date: 13-04-2020
General Requirements:
All site team to strictly follow the recommendations/instructions given in attached risk assessment. Site Engineer and Safety Officer to ensure that all people are
wearing appropriate PPE’s in relation to the type of works/activities being carried out and following the recommendations. In addition:
a. Work will commence as per regulations laid down in the contract specification and project safety plan.
b. Risk Assessment will be established detailing the hazards involved and control measures that will be taken to eliminate/reduce the impact of those hazards.
c. All Personal Protective Equipment shall be used as appropriate according to the nature of the job.
d. Only competent workers are allowed to use the power tools.
e. All working areas shall be isolated encircled with warning tapes, and warning sign boards before commencement of works where practicable.
f. Full body Safety Harness must be used on Working at Heights.
g. Ensure that proper Scaffolding & Ladders are available at site without any defect.
h. Access and Exit routes to be un-obstructed, labelled and known to all employees at site.
i. Ensure that shafts are adequate blocked above and below the working level, so that no fall of debris/materials takes place.
j. Ensure the mandatory requirement of Five points PPE
k. Ensure the Task briefing will be performed by Blackhat trained supervisor. The task briefing should be performed at the location of work.
l. Hazard hunt should be performed before start any activity and required action must be taken prior to start
m. MSRA to be communicated to all workers prior to start any activity
10
Ref.
Date: 13-04-2020
RISK ASSESSMENT
MAIN ACTIVITY: Installation of firefighting system RA No
LOCATION: PROJECT: Australian Pavilion
EQUIPMENT TO BE USED SUBSTANCES TO BE USED REVISION STATUS
Spirit Level, Measuring Loctite Super Glue REVISION NUMBER REVISED DATE
Tape, Nylon Twine, Pipe
Cutter, Hack Saw, Files
Threading,grooving 00
machine, Hammers,
WORKING FROM ELECTRICITY HAND TOOLS MATERIAL HANDLING CONFINED □EXCAVATION/BACK FILLING EMPLOYEES PUBLIC
HEIGHT SPACE
MANUAL HANDLING FATIGUE
SUBCONTRACTORS
PEDESTRIAN HAZARDOUS SUBSTANCES VISITORS
11
Ref.
Date: 13-04-2020
FALLING MATERIALS NOISE &
SLIPS / TRIPPING SITE VEHICLE SECURITY VIBRATION
MACHINERY/EQUIPMET
ADVERSE WEATHER ACCESS/EGRESS LIFTING OPERATION HEAT STAKE HOLDERS OTHERS
FIRE RISK MATERIAL STORAGE EXHAUSTION ENVIRONMENTAL
(Use Environmental Impact- Severity
Rating Section for these HAZARDS)
MANDATORY HSE REQUIREMENTS (TICK BOX)
SAFETY INDUCTION ADEQUATE WORK PERMIT PROPER TOOLS / EQUIPMENT
SUPERVISION
VENTILATION
TOOL BOX TALK
DUST CONTROL TASK LIGHTING
TASK SPECIFIC PPE BARRICADES, WARNING SIGN IN THE AFFECTED AREA
PERSONAL PROTECTIVE EQUIPMENT (PPE) REQUIREMENT (TICK BOX)
SAFETY HELMET GOGGLES / SAFETY GLASSES RESPIRATORY PROTECTION / BREATHING GLOVES OVERALLS
SAFETY BOOTS EAR PLUGS / DEFENDER APPARATUS
FULL BODY SAFETY HARNESS HIGH VIZ SAFETY JACKET WELDING/METAL CUTTING PPE
TO REFER TO OTHER RISK ASSESSMENTS
1.
12
Ref.
Date: 13-04-2020
Area congestion Falling of materials Workers 4 3 12 M No any person is allowed to stand near to the unloading area. 3 3 9 M
Manual handling Stuck by materials Co-workers Tool box talk to be conducted before work may commence.
Insufficient adequate of Mechanical failure Visitors Route will be plan and inspected.
lightning Back injury Remove all possible obstructed materials and any source of slip
Unauthorized workers Hands injury and trip (ex. Concrete block, Cable wire, wet ground, grease
nearby Slip and trip surface, etc.).
Obstruction Safe access / egress to be maintained at all time.
Heavy load Adequate lighting in the area to be provided.
Entanglement Mandatory PPE’s to be worn by all operatives at all time.
Pre inspection for the mechanical lifter
Maintain proper housekeeping in the area.
Manual lifting should be in proper procedure.
Close supervision shall be implemented.
Notify other workers for the transportation of material to avoid
crossing or conducting of their activity in the said access.
Only highly experienced worker shall be involved in the material
shifting activity.
In cased of any unwanted lightning off. Activity must be stop.
Avoid any improvised lifter.
Methods statement must be follow.
Severity (S) Values: 1-5 Likelihood (L) Values: 1-5 Note: Use the RAM when determining the values of S and L Risk (R) = S x L
Risk Ranking: 1 – 4 = Low (L) 5 – 12 = Medium (M) 15 – 25: High (H)
Activity 2: SHIFTING OF FIRE CABINET BOX AND FIRE EXTINGUISHERS TO WORK LOCATION
Who / what? Initial Risk (with Control Measures Residual Risk
is at risk existing
Hazards Risk controls)
13
Ref.
Date: 13-04-2020
Risk Risk
S L R Level S L R Level
Area congestion Falling of materials Workers 4 3 12 M No any person is allowed to stand near to the unloading area. 3 3 9 M
Manual handling Stuck by materials Co-workers Tool box talk to be conducted before work may commence.
Insufficient adequate of Mechanical failure Visitors Route will be plan and inspected.
lightning Back injury Remove all possible obstructed materials and any source of slip
Unauthorized workers Hands injury and trip (ex. Concrete block, Cable wire, wet ground, grease
nearby Slip and trip surface, etc.).
Obstruction Safe access / egress to be maintained at all time.
Heavy load Adequate lighting in the area to be provided.
Entanglement Mandatory PPE’s to be worn by all operatives at all time.
Pre inspection for the mechanical lifter
Maintain proper housekeeping in the area.
Manual lifting should be in proper procedure.
Close supervision shall be implemented.
Notify other workers for the transportation of material to avoid
crossing or conducting of their activity in the said access.
Only highly experienced worker shall be involved in the material
shifting activity.
In cased of any unwanted lightning off. Activity must be stop.
Avoid any improvised lifter.
Methods statement must be followed.
Severity (S) Values: 1-5 Likelihood (L) Values: 1-5 Note: Use the RAM when determining the values of S and LRisk (R) = S x L
Risk Ranking: 1 – 4 = Low (L) 5 – 12 = Medium (M) 15 – 25: High (H)
14
Ref.
Date: 13-04-2020
4 3 12 M 4 1 4 L
Painting at heights Eye Injury Workers Operative should be wearing an appropriate PPE (Google,
Poor housekeeping Inhalation of chemical paint Co-workers filtered mask, Rubber Gloves, Helmet, safety shoes)
Chemical paint Absorption Visitors Painting at heights should be wear a full body harness and the
Ergonomics Ingestion of chemical paint Environment appropriate PPE for painting.
Skin allergy Scaffolding should be complete and inspected.
Back and shoulder pain MSDS must be discussed to the operatives.
Slip and trip Proper posture for prolong painting.
Flammable Firefighting equipment like fire extinguisher must be available
in painting area.
All combustible material should be removed.
Painting can/ container should be place in a spill try.
Supervision of foreman should be maintained
COSHH assessment to be prepared and must be address to
operatives.
All empty paint cans/ container and used paint brush must be
disposed in proper waste disposal.
All paints must be store in chemical storage room.
Operatives should be having a knowledge and experience to
handle the chemical paint.
Severity (S) Values: 1-5 Likelihood (L) Values: 1-5 Note: Use the RAM when determining the values of S and L
Risk (R) = S x L Risk Ranking: 1 – 4 = Low (L) 5 – 12 = Medium (M) 15 – 25: High (H)
15
Ref.
Date: 13-04-2020
Poor housekeeping Slip and trip Machine operator 4 4 16 H Operator must be competent and trained. 4 2 8 M
manual handling Electric shock Co-worker Pre checking of machines before it use.
sharp edge Machine failure Visitors All cable wire must be properly check and properly place.
High voltage Physical injury Environment Machine should be place in a spill try for any leakage of
excessive noise caught in moving parts oil.
Entanglement Pinch points Operator must be wearing an appropriate dress.
Oil leak Falling of pipes Operator should be using an appropriate PPE such as Ear
Poor management of cable plug, gloves, goggles, helmet and safety shoes.
Incompetent operator Use a proper pipe stand while fabricating the pipe.
Fabrication area should be barricaded when work piece
extends beyond the machines.
Proper supervision should be maintained.
Unauthorized operator is not allowed to operate the
machines.
Good housekeeping should be maintained anytime.
Manual lifting should be proper lift procedure.
All mechanical lift like pulley or chain block must be
certified and good condition.
Fire extinguisher should be available in machine area.
Fabrication area should be barricaded when work piece
extends beyond the machines.
Keep dry always the floor of fabrication area.
Severity (S) Values: 1-5 Likelihood (L) Values: 1-5 Note: Use the RAM when determining the values of S and L
Risk (R) = S x L Risk Ranking: 1 – 4 = Low (L) 5 – 12 = Medium (M) 15 – 25: High (H)
16
Ref.
Date: 13-04-2020
Risk Risk
S L R Level S L R Level
Poor housekeeping Slip and trip Machine operator 4 4 16 H Operator must be competent and trained. 4 2 8 M
manual handling Electric shock Co-worker Pre checking of machines before it use.
sharp edge Machine failure Visitors All cable wire must be properly check and properly place.
High voltage Physical injury Environment Machine should be place in a spill try for any leakage of
excessive noise caught in moving parts oil.
Entanglement Pinch points Operator must be wearing an appropriate dress.
Heavy pipes Falling of pipes Operator should be use an appropriate PPE such as Ear
Poor management of cable plug, gloves, goggles, helmet and safety shoes.
Incompetent operator Use a proper pipe stand while fabricating the pipe.
Fabrication area should be barricaded when work piece
extends beyond the machines.
Proper supervision should be maintained.
Unauthorized operator is not allowed to operate the
machines.
Good housekeeping should be maintained anytime.
Manual lifting should be proper lift procedure.
All mechanical lift like pulley or chain block must be
certified and good condition.
Fire extinguisher should be available in machine area.
Fabrication area should be barricaded when work piece
extends beyond the machines.
Keep dry always the floor of fabrication area.
Severity (S) Values: 1-5 Likelihood (L) Values: 1-5 Note: Use the RAM when determining the values of S and LRisk (R) = S x L
Risk Ranking: 1 – 4 = Low (L) 5 – 12 = Medium (M) 15 – 25: High (H)
17
Ref.
Date: 13-04-2020
Risk Risk
S L R Level S L R Level
Excessive dust Slip and trip Workers 4 3 12 M Close supervision must be maintained. 4 1 4 L
Entanglement Physical injury Co-workers Toolbox talk should be conducted prior to commence the
High voltage Stuck by material Visitors activity.
Poor housekeeping Damage to the property Workers should be wearing the mandatory PPE anytime such as
Insufficient adequate of Falling of material helmet, goggles, gloves, mask and safety shoes.
lightning Cable wire should be place properly. Never used damaged cable
Poor management of cable wire.
Manual handling Scaffolding should be complete and inspected.
Manual lifting should be in proper procedure. Never carry over
load.
All hand tools should be in good condition. Never used defective
hand tools.
All electrical tools must be inspected before it use. Never used
defective electrical tools.
Proper housekeeping should be maintained in work place.
In cased of any unwanted lightning off. Activity must be stop.
Proper access should be available.
Body system should be maintained while working.
Severity (S) Values: 1-5 Likelihood (L) Values: 1-5 Note: Use the RAM when determining the values of S and L
Risk (R) = S x L Risk Ranking: 1 – 4 = Low (L) 5 – 12 = Medium (M) 15 – 25: High (H)
18
Ref.
Date: 13-04-2020
Risk Risk
S L R Level S L R Level
Excessive dust Slip and trip Workers 4 3 12 M Toolbox talk should be conducted prior to commence the 4 1 4 L
Heavy loads Physical injury Co-workers activity.
Entanglement Stuck by material Visitors Close supervision must be maintained.
High voltage Falling of materials Workers should be wearing the mandatory PPE anytime such as
Poor housekeeping Damage to the property helmet, goggles, gloves, mask and safety shoes.
Insufficient adequate of Wound cutting Cable wire should be place properly. Never used damaged cable
lightning wire.
Poor cable management Scaffolding should be complete and inspected.
Manual handling Working at heights should be wear a full body harness anytime
while working at heights.
Manual lifting should be in proper procedure. Never carry over
load.
All hand tools should be in good condition. Never used defective
hand tools.
All electrical tools must be inspected before it uses. Never used
defective electrical tools.
Proper housekeeping should be maintained in work place.
In cased of any unwanted lightning off. Activity must be stop.
Proper access should be available.
Body system should be maintained while working.
Severity (S) Values: 1-5 Likelihood (L) Values: 1-5 Note: Use the RAM when determining the values of S and LRisk (R) = S x L
Risk Ranking: 1 – 4 = Low (L) 5 – 12 = Medium (M) 15 – 25: High (H)
19
Ref.
Date: 13-04-2020
Risk Risk
S L R Level S L R Level
Excessive dust Slip and trip Workers 4 4 16 H Toolbox talk should be conducted prior to commence the 4 2 8 M
Heavy loads Mechanical failure Co-workers activity.
Entanglement Physical injury Visitors Close supervision must be maintained.
High voltage Stuck by material Workers should be wear the mandatory PPE anytime such as
Poor housekeeping Falling of materials helmet, goggles, gloves, mask and safety shoes.
Insufficient adequate of Damage to the property Cable wire should be place properly. Never used damaged cable
lightning Wound cutting wire.
Poor cable management Scaffolding should be complete and inspected.
Sharp edges Working at heights should be wear a full body harness anytime
Manual handling while working at heights.
Manual lifting should be in proper procedure. Never carry over
load.
All hand tools should be in good condition. Never used defective
hand tools.
All electrical tools must be inspected before it use. Never used
defective electrical tools.
Proper housekeeping should be maintained in work place.
In cased of any unwanted lightning off. Activity must be stop.
Proper access should be available.
Mechanical lifting such as jack pallet, pulley or chain block
should be certified and good condition.
Body system should be maintained while working.
Severity (S) Values: 1-5 Likelihood (L) Values: 1-5 Note: Use the RAM when determining the values of S and LRisk (R) = S x L
Risk Ranking: 1 – 4 = Low (L) 5 – 12 = Medium (M) 15 – 25: High (H)
20
Ref.
Date: 13-04-2020
Risk Risk
S L R Level S L R Level
Sparks/fire Electrocution Welder 4 4 16 H Hot work permit should be completed prior to start the activity. 4 2 8 M
Toxic Fumes Slip and trip Co-worker Toolbox talk should be conducted prior to start the activity.
Excessive noise Flammable Visitor All combustible material should be removed in hot work area.
Sharp edge Machine failure All firefighting equipment should be available like fire
Hot surface extinguisher, fire blanket, water and etc.
High voltage All machines and cable wires must be in good condition and
Poor housekeeping inspected prior to start the work.
Access should be clear in any obstruction.
Welder should be wearing appropriate PPE such as welding
mask, welding gloves, welding apron, face shields, ear plug and
safety shoes.
Proper supervision must be maintained.
Welder must be a certified and trained.
Fire watcher must be available in hot area.
Welding machines must be a certified and tested.
Cutting wheel and grinding wheel should be inspected before it
uses.
Do not by pass any guards for grinder and cut off saw machine.
Maintain proper housekeeping before and after the activity.
Never use any machines if find out any unwanted sounds.
Lock out tag out must be observed in working area.
Severity (S) Values: 1-5 Likelihood (L) Values: 1-5 Note: Use the RAM when determining the values of S and LRisk (R) = S x L
Risk Ranking: 1 – 4 = Low (L) 5 – 12 = Medium (M) 15 – 25: High (H)
Activity 10: PRESSURE TESTING FOR GI ERW PIPES
21
Ref.
Date: 13-04-2020
Initial Risk (with
Who / what? existing Residual Risk
Hazards Risk controls) Control Measures
is at risk
Risk Risk
S L R Level S L R Level
Workers 4 3 1 M Toolbox talk should be conducted prior to commence the 4 2 8 M
• Exceeding Maximum Allowable •Severe injury Co-workers activity.
Pressure •Damage to materials/equipment. Visitors Close supervision must be maintained.
• Unsafe Depressurization Workers should be wear the mandatory PPE anytime such
• Injury to Workers as helmet, goggles, gloves, mask and safety shoes.
Proper housekeeping should be maintained in work place.
In cased of any unwanted lightning off. Activity must be
stop.
Proper access should be available.
Body system should be maintained while working.
Competent worker should perform the job.
Check for all pipe joints for proper coupling/plugs.
Barricade the pump area and provide adequate signages.
Proper co-ordination between supervisor and workers.
Check for any leakages throughout the testing time.
Ensure the safe depressurization by opening the drain valve
slowly.
Calibrated pressure gauges and Pressure safety valves only shall
be used
Supervisors shall be present at work location during hydro
testing activities are done
Pressure should be raised gradually under control to allow time
for pipes to strain and time for personnel to check for leaks.
Ensure air vent provided at the highest elevation
Severity (S) Values: 1-5 Likelihood (L) Values: 1-5 Note: Use the RAM when determining the values of S and LRisk (R) = S x L
Risk Ranking: 1 – 4 = Low (L) 5 – 12 = Medium (M) 15 – 25: High (H)
22
Ref.
Date: 13-04-2020
Initial Risk (with
Who / what? existing Residual Risk
Hazards Risk controls) Control Measures
is at risk
Risk Risk
S L R Level S L R Level
Dust Slip and trip Workers 3 3 9 M Toolbox talk should be conducted prior to commence the 3 2 6 M
Combustible material Physical injury Co-workers activity.
Scrap material Falling Visitors Close supervision must be maintained.
Poor cable management Damage to the property Workers should be wearing the mandatory PPE anytime
Lost material such as helmet, goggles, gloves, mask and safety shoes.
All waste material should be put on proper disposal area.
All lost material that needs to use for the activity should be
put in a box.
Proper cable management should be follow.
Proper housekeeping should be maintained in work place.
In cased of any unwanted lightning off. Activity must be
stop.
Proper access should be available.
Body system should be maintained while working.
Severity (S) Values: 1-5 Likelihood (L) Values: 1-5 Note: Use the RAM when determining the values of S and LRisk (R) = S x L
Risk Ranking: 1 – 4 = Low (L) 5 – 12 = Medium (M) 15 – 25: High (H)
23
Ref.
Date: 13-04-2020
Initial Risk (with
Who / what? existing Residual Risk
Hazards Risk controls) Control Measures
is at risk
Risk Risk
S L R Level S L R Level
Fall of material on the Serious body injury. Workers 4 4 16 H Activity briefing will be conducted for the entire crew. 4 2 8 M
person standing below. Property damage. Co-worker Ensure all scaffolding components are in good condition.
Fall of person. Fatality Visitor Erection, modification & Dismantling will be carryout by
Material falling from height. trained & certified competent scaffolding team.
Failure of scaffold/ ladder. Aluminum scaffold will be placed on a level, compact and
unobstructed ground.
Aluminum scaffolds will be use away from all electrical units.
Aluminum scaffold access will be provided from inside to
prevent topping.
Out riggers will be extended according to the work and area.
Will follow manufactures instruction during erection,
alternation and dismantling.
Aluminum scaffold platforms will not be overloaded
Scaffolding erection and dismantling will be done only with
the close supervision.
One third of the total height of the scaffold will be
demarcated as exclusion zone.
Should be ensure all wheels are locked.
Dropping/throwing of scaffold material will not be permitted.
Materials to be lifted/lowered using rope and tools bag.
Sequence of dismantling will be opposite to erection.
Scaffold will only be allowed to use after inspection from a
competent person and green tagged,
All involved in the process of erection, usage and dismantling will
be equipped with full body double lanyard with 100%
anchorage.
Beneath area will be barricaded.
Appropriate signage will be displayed
Do not move the mobile scaffold when person on the platform.
Severity (S) Values: 1-5 Likelihood (L) Values: 1-5 Note: Use the RAM when determining the values of S and LRisk (R) = S x L
Risk Ranking: 1 – 4 = Low (L) 5 – 12 = Medium (M) 15 – 25: High (H)
24
Ref.
Date: 13-04-2020
Severity (S) Values: 1-5 Likelihood (L) Values: 1-5 Note: Use the RAM when determining the values of S and LRisk (R) = S x L
Risk Ranking: 1 – 4 = Low (L) 5 – 12 = Medium (M) 15 – 25: High (H)
25
Ref.
Date: 13-04-2020
1 2 3 4 5
LIKELIHOOD
Never heard of in Heard of in industry/ Incident has Happens Happens several
industry/ company company occurred in several times times per year in a
Activity is taking Activity is taking industry/ per year in location
place rarely place occasionally company industry/ Activity is taking
PEOPLE ENVIRONMENT Activity is taking company place continuously
place frequently Activity is taking
place regularly
26
Ref.
Date: 13-04-2020
WRITTEN SAFE WORK PROCEDURE
1. OBJECTIVE
2. PROCEDURE
1. Do pre-use inspection of all equipment to be used and replace or repair faulty items.
2. Use trained competent employees only.
3. Use appropriate Personal Protective Equipment i.e.:
3.1. Hardhat.
3.2. Safety boots.
3.3. Overalls.
3.4. Ear Protection.
3.5. Masks
3.6. Safety Gloves
3.7. Hand gloves
3.8. Full body safety harness
2.1. Appropriate PPE must be worn by all workers on site & special PPE should be provided for those who are directly involved in this activity.
2.2. Site Induction and toolbox talks should be given prior to start job.
2.3. Equipment to be used should be inspected and must be safe for use.
2.4. Materials be properly secured while being transported and during offloading.
2.5. Permit to work system should be followed by all supervisors and engineers.
2.6. Daily, weekly and monthly inspection to be done regularly any defect found must be reported immediately.
2.7. Physical barricade to installed and maintained with entry and exit points.
2.8. Only personnel involve in the activities are allowed inside the barricaded area.
2.9. Enforce the use of competent persons only.
2.10. All hand and power tools must be inspected before use
2.11. All type of power tools must be colour coded and tagged as safe for use also must be entered in register.
27
Ref.
Date: 13-04-2020
2.12. Permit to work system should be in place.
2.13. PPE should be worn by all operators as per the job nature.
2.14. Maintain work area isolated with means of barricade and appropriate signage should be in place.
2.15. Remind personnel through toolbox talk to observe proper positioning when working
2.16. All the work should be done under the competent supervision.
28