METHOD STATEMENT Issue Date 02 October 2013
Rev. Date NA
Method statement for testing and commissioning of fire hose reel.
Pages 1 of 7
TABLE OF CONTENTS
1. REVISION RECORD.............................................................................................................................3
2. PURPOSE...........................................................................................................................................4
TECHNICAL DEPARTMENT-CIVIL (Replace by the Project Doc. No.
TEC-211200-MET-DoR-002
Name) (Rev No.)
METHOD STATEMENT Issue Date 02 October 2013
Rev. Date NA
Method statement for testing and commissioning of fire hose reel.
Pages 2 of 7
3. SCOPE................................................................................................................................................4
4. REFERENCES......................................................................................................................................4
4.1. Contract documents......................................................................................................................4
4.2. Contractors Submittal...................................................................................................................4
5. DEFINITIONS / ABBREVIATIONS........................................................................................................4
5.1. Definition.......................................................................................................................................4
5.2. Abbreviations................................................................................................................................4
6. RESPONSIBILITY.................................................................................................................................5
7. EQUIPMENTS/ TOOLS / MANPOWER/MATERIALS...........................................................................5
8. PRE COMMISSIONING PROCEDURE..................................................................................................5
8.1. Definition.......................................................................................................................................5
8.2. Visual Inspection...........................................................................................................................5
8.3. Hydrostatic Test............................................................................................................................5
8.4. Flushing.........................................................................................................................................6
9. COMMISSIONING PROCEDURE.........................................................................................................6
9.1. Equipment/Instruments to be used..............................................................................................6
10. HEALTH, SAFETY AND ENVIRONMENT..........................................................................................6
11. ATTACHMENTS..............................................................................................................................6
11.1. Inspection Checklists.................................................................................................................6
11.2. Inspection Test Plan..................................................................................................................6
11.3. Risk Assessment........................................................................................................................6
1. REVISION RECORD
This page is a record of all revisions of the document identified below by number and title. All
previous revisions are hereby superseded and are to be destroyed.
TECHNICAL DEPARTMENT-CIVIL (Replace by the Project Doc. No.
TEC-211200-MET-DoR-002
Name) (Rev No.)
METHOD STATEMENT Issue Date 02 October 2013
Rev. Date NA
Method statement for testing and commissioning of fire hose reel.
Pages 3 of 7
Signature field
Revision
Revision
Number
Date
Prepared by Checked by
Reviewed
By Construction Technical QA/QC MEP Co- Sub-
Manager Manager Engineer HSE Officer ordinator contractor
Approved
By Project
Manager
2. PURPOSE
3. SCOPE
4. REFERENCES
4.1. Contract documents
1. Project Specification :- Division 21, Section 211200
2. Contract Drawings :-
TECHNICAL DEPARTMENT-CIVIL (Replace by the Project Doc. No.
TEC-211200-MET-DoR-002
Name) (Rev No.)
METHOD STATEMENT Issue Date 02 October 2013
Rev. Date NA
Method statement for testing and commissioning of fire hose reel.
Pages 4 of 7
6. Shop Drawings
Sr.
Description Shop Drawings Rev No. Date Remarks
No.
1
2
3
5. DEFINITIONS / ABBREVIATIONS
5.1. Definition
1. Project -(Replace with project name)
2. Client -(Replace with clients name)
3. Developer -(Replace with developers name)
4. Consultant -(Replace with consultants name)
5. PMC -(Replace with PMC name)
6. Contractor -(Replace with contractors name)
7. Sub-contractor -(Replace with sub-contractors name)
8. Supplier -(Replace with suppliers name)
5.2. Abbreviations
1. Engineer - Representative of “Name of engineering consultancy”
2. ICL - Inspection Check List
3. IR - Inspection Request
4. ITL -Independent Testing Laboratory
5. ITP - Inspection and Test Plan
6. ITR -Inspection & Test Requests
7. MAT - Material Submittal
TECHNICAL DEPARTMENT-CIVIL (Replace by the Project Doc. No.
TEC-211200-MET-DoR-002
Name) (Rev No.)
METHOD STATEMENT Issue Date 02 October 2013
Rev. Date NA
Method statement for testing and commissioning of fire hose reel.
Pages 5 of 7
3. Fill complete pipeline with water avoiding any air column. (For this purpose keep the drain valve at the
highest elevation slightly open, while filling water when line is completely filled with water close the
valve)
4. By a pressure pump pressurize the line to an intermediate pressure, say 100 psi. Wait for 5 minutes;
check all major joints for any visible leak.
5. If the system is OK as per point No. 4 again pressurize the system to 150 psi and wait for 10 minutes
for any drop in pressure or leakage.
6. If the system is found to be leak proof as per item No. 5 pressurizes the line to 200 psi and keep for 2
hrs.
8.4. Flushing
1. Prior to perform the final Test of the internal fire hose reel and Fire Hose system a flush test shall be
conducted as follows,
2. Pull the hose reel or fire hose outside the building or inside the toilet area
3. Direct the hose to a free direction.
4. Open the valve.
5. Keeps water going for 2-3 minutes?
6. Continue the flushing till all debris is removed and clean water is coming out.
7. Close the valve.
8. Repeat the same procedure for all others.
9. COMMISSIONING PROCEDURE
9.1. Equipment/Instruments to be used
1. Adjustable Spanner.
2. Pressure Gauges.
3. Pipe Wrench.
The following are to be checked prior to handover of the Fire Hose / Hose reel System to the Clients/ End
Users.
1. All Fire Hose System Network and attached appurtenances subjected to system working pressure shall
be hydrostatically tested at 200 psi. (13.8 bars) and shall maintain that pressure without loss for 2
hours. Loss shall be determined by a drop in gauge pressure.
2. The piping system shall be flush tested to ensure thorough cleaning of the network piping. The
minimum flow rate shall be at least that necessary to provide a velocity of 3 m/ sec.
3. Ensure all the components of the fire cabinets are installed properly (landing valves, hose reels,
extinguishers & fire hoses).
4. Check pressure in all the floors by using special adapter with calibrated pressure gauge and note the
readings.
5. Open the lock shield valve of each hose reel and adjust its pressure to 3 - 4 bars through 1" PRV. The
water throw should be 6 metre. (Hose reel should be opened inside toilets or outside the building to
avoid any damages to other services).
6. Check all the fire extinguishers for its certification (inside pressure & hose connections also to be
checked).
7. A system functional test may be conducted as given below once the entire Fire protection system is
completed.
TECHNICAL DEPARTMENT-CIVIL (Replace by the Project Doc. No.
TEC-211200-MET-DoR-002
Name) (Rev No.)
METHOD STATEMENT Issue Date 02 October 2013
Rev. Date NA
Method statement for testing and commissioning of fire hose reel.
Pages 7 of 7