Wind Turbine Generator System Power Quality Test Report For The Gaia Wind 11-kW Wind Turbine
Wind Turbine Generator System Power Quality Test Report For The Gaia Wind 11-kW Wind Turbine
Wind Turbine Generator System Power Quality Test Report For The Gaia Wind 11-kW Wind Turbine
Technical Report
NREL/TP-5000-51477
July 2011
This report was prepared as an account of work sponsored by an agency of the United States government.
Neither the United States government nor any agency thereof, nor any of their employees, makes any warranty,
express or implied, or assumes any legal liability or responsibility for the accuracy, completeness, or usefulness of
any information, apparatus, product, or process disclosed, or represents that its use would not infringe privately
owned rights. Reference herein to any specific commercial product, process, or service by trade name,
trademark, manufacturer, or otherwise does not necessarily constitute or imply its endorsement, recommendation,
or favoring by the United States government or any agency thereof. The views and opinions of authors
expressed herein do not necessarily state or reflect those of the United States government or any agency thereof.
P.O. Box 62
Oak Ridge, TN 37831-0062
phone: 865.576.8401
fax: 865.576.5728
email: mailto:reports@adonis.osti.gov
Cover Photos: (left to right) PIX 16416, PIX 17423, PIX 16560, PIX 17613, PIX 17436, PIX 17721
Printed on paper containing at least 50% wastepaper, including 10% post consumer waste.
Wind Turbine Generator System
Power Quality Test Report
for the
Boulder, CO
Conducted for
Conducted by
Page 1 of 35
Table of Contents
1.0 Background ................................................................................................................... 5
2.0 Test Summary ............................................................................................................... 5
3.0 Continuous Operation Test Results .............................................................................. 6
3.1 Wind Turbine Data .................................................................................................... 6
3.2 Active Power, Reactive Power and Power Factor..................................................... 7
3.3 Line Voltage Distortions ......................................................................................... 10
3.4 Current Harmonics .................................................................................................. 11
3.5 Current Interharmonics ........................................................................................... 13
3.6 Current Distortions .................................................................................................. 14
3.7 Current and Voltage Imbalance............................................................................... 15
3.8 Continuous Operation Flicker ................................................................................. 16
4.0 Switching Operation Tests Results ............................................................................. 18
4.1 Turbine starts and stops ........................................................................................... 18
5.0 Exceptions ................................................................................................................... 28
Appendix A. Test Matrix .................................................................................................. 29
Appendix B. Post Calibration Report ............................................................................... 30
Page 3 of 35
List of Tables
Table 1: Gaia Wind 11-kW wind turbine general data ....................................................... 6
Table 2: Wind turbine rated data ........................................................................................ 6
Table 3: Maximum permitted power .................................................................................. 6
Table 4: Number of data points per 1 m/s wind speed bins ................................................ 7
Table 5: Data binned by real power .................................................................................. 10
Table 6: Maximum instantaneous real and reactive power .............................................. 10
Table 7: Maximum Current Harmonics (10 min averages) .............................................. 11
Table 8: Current Interharmonics ....................................................................................... 13
Table 9: Current Distortions (2 - 9 kHz range) ................................................................. 14
Table 10: Resulting flicker coefficients in continuous operation ..................................... 18
Table 11: Table of Figures for transient waveforms ......................................................... 18
Table 12. Characteristics of start at cut-in wind speed ..................................................... 27
Table 13. Characteristics of stop at cut-in wind speed ..................................................... 27
Table 14. Characteristics of start at rated wind speed ...................................................... 27
Table 15. Characteristics of stop at rated wind speed ....................................................... 28
List of Figures
Figure 1: Turbulence intensity vs. wind speed ................................................................... 7
Figure 2: Active and reactive power vs. wind speed .......................................................... 8
Figure 3: Power factor vs. active power ............................................................................. 9
Figure 4: Reactive Vs. Active Power.................................................................................. 9
Figure 5: Current TDD Vs. Power .................................................................................... 12
Figure 6: Voltage Imbalance Vs. Power ........................................................................... 15
Figure 7: Current imbalance Vs. Power ............................................................................ 15
Figure 8: Pst vs. power for 30° network impedance angle................................................. 16
Figure 9: Pst vs. power for 50° network impedance angle ................................................ 16
Figure 10: Pst vs. power for 70° network impedance angle............................................... 17
Figure 11: Pst vs. power for 85° network impedance angle............................................... 17
Figure 12: Cut-in wind (4.8 m/s) start: current waveforms (August 19, 2009) ................ 19
Figure 13: Cut-in wind (4.8 m/s) start: power and RMS voltage (August 19, 2009) ....... 20
Figure 14: Rated wind (10.5 m/s) start, current waveforms (December 31, 2009) .......... 21
Figure 15: Rated wind (10.5 m/s) start, power, and RMS voltage (December 31, 2009) 22
Figure 16: Cut-in wind (3.4 m/s) stop, current waveforms (August 19, 2009) ................ 23
Figure 17: Cut-in wind (3.4 m/s) stop, power, and RMS voltage (August 19, 2009) ...... 24
Figure 18: Rated wind (10.0 m/s) stop: current waveforms (December 31, 2009) .......... 25
Figure 19: Rated wind (10.0 m/s) stop: power and RMS voltage (December 31, 2009) . 26
1
Page 4 of 35
1.0 Background
This test is being conducted as part of the U.S. Department of Energy’s (DOE)
Independent Testing project. This project was established to help reduce the barriers of
wind energy expansion by providing independent testing results for small turbines. In
total, five turbines are being tested at the NWTC as a part of this project. Power quality
testing is one of up to five tests that may be performed on the turbines, including power
performance, safety and function, noise, and duration tests. The results of the testing will
provide the manufacturers with reports that may be used for small wind turbine
certification.
The power quality test for the Gaia Wind 11-kW wind turbine began on July 23, 2009
and ended on January 15, 2010. About 9,995 10-min intervals of data were collected
while the turbine was available. The IEC 61400-21 Power Quality Standard requires at
least five 10-min average data points for each 1 m/s wind speed bin for the wind
turbulence intensity between 8 and 16%. This condition reduced the valid data to 1,021
10-min intervals. The highest bin filled (with no wind speed normalization) was the 14
m/s bin. When the data is binned by percent of rated power, more than five data points
were recorded for each bin. According to the IEC 61400-21, not enough data was
collected to fill the 15 m/s bin due to high turbulence intensity for the data points
collected in the 15 m/s bin. The test matrix is given in Appendix A.
The test was conducted in accordance IEC 61400-21 Power Quality Standard and
MEASNET procedures, and the following are the test results required by the standard and
are included in this report:
Page 5 of 35
3.0 Continuous Operation Test Results
3.1 Wind Turbine Data
Number of blades 2
Page 6 of 35
3.2 Active Power, Reactive Power and Power Factor
The relationship between active and reactive power was measured at the wind turbine
low voltage (480 VAC) terminals. Only 10-min data points, with turbulence intensity
within 8-16% range, were used for this analysis (Figure 1). Power measurements were
sampled during continuous operation only, and taken so that at least five 10-min time
series of power were collected for each 1 m/s wind speed (according to IEC 61400-21).
The sampled data was transferred to 10-minute average data by applying block averaging
for each 10-min period (Table 4 and Figure 2). The power factor (Figure 3) was
calculated using active and reactive power values. The reactive power demand is shown
in Figure 4.
18
16
14
Turbulence Intensity
12
10
0
0 2 4 6 8 10 12 14 16 18
0 to 1 0
1 to 2 0
2 to 3 0
3 to 4 142
4 to 5 346
5 to 6 220
6 to 7 112
Page 7 of 35
7 to 8 61
8 to 9 54
9 to 10 29
10 to 11 15
11 to 12 17
12 to 13 16
13 to 14 6
14 to 15 1
Power Curve
15
10
5
Power (kW)
-5
-10
-15
Wind Speed (m/s)
Page 8 of 35
1.0
0.9
0.8
0.7
Power Factor
0.6
0.5
0.4
0.3
0.2
0.1
0.0
0 2 4 6 8 10 12 14 16
0
0 2 4 6 8 10 12 14 16
-2
Reactive Power (kVAR)
-4
-6
-8
-10
-12
The 10-min average data was sorted according to the method of bins so that the reactive
power could be specified for 0, 10, …., 90, 100% of rated power (Table 5). The
maximum active power was measured both as 60-sec (P60) and 0.2-sec average (P0.2)
Page 9 of 35
values. The reactive power at Pmc , P60, and P0.2 was determined by extrapolation of the
measured relation between the active and reactive power (Table 6).
Note 2: The active power curve shown in Figure 2 may not be used for the Gaia Wind 11-
kW wind turbine power performance evaluation. The official power curve will be
published in the Gaia Wind 11-kW Power Performance Test Report.
The average voltage Total Harmonic Distortions (THD) measured during the test are
shown below for each phase:
Phase A – 2.028 %
Phase B – 1.798 %
Phase C – 1.734 %
Page 10 of 35
The maximum voltage THDs measured during the test are shown below for each phase:
Phase A – 4.163 %
Phase B – 4.028 %
Phase C – 3.595 %
All voltage THDs were calculated from harmonic voltages. The harmonic voltages were
subgrouped according to Section 5.6 of IEC 61000-4-7/CDV. The window width used
during measurements Tw=12.
The individual harmonic currents during continuous operation were measured as 10-min
average data for each harmonic order (up to 50th) at the output power giving the
maximum individual harmonic current. The harmonic data and the maximum current
Total Demand Distortion (TDD) values as a percentage of nominal current In are shown
in Table 7. Figure 5 shows the plots of 10-min average data for maximum current TDD
(% of In) as a function of output power.
Page 11 of 35
29 4.310 2.444 4.310 2.054 4.310 1.937
30 4.310 1.775 4.310 1.494 4.310 1.518
31 4.310 1.634 4.310 1.344 4.310 1.361
32 4.310 1.488 4.310 1.188 4.310 1.239
33 4.310 1.378 4.310 0.998 4.310 1.083
34 4.310 1.255 4.310 0.901 4.310 1.010
35 4.310 1.354 0.189 1.195 4.310 1.023
36 4.310 0.920 4.310 0.674 4.310 0.755
37 4.310 0.758 4.310 0.596 4.310 0.654
38 4.310 0.636 4.310 0.508 4.310 0.531
39 4.310 0.500 4.310 0.441 4.310 0.389
40 4.310 0.441 4.310 0.379 4.310 0.373
41 7.771 0.555 4.447 0.454 4.447 0.536
42 4.310 0.303 4.310 0.273 4.310 0.251
43 12.112 0.288 12.112 0.288 4.310 0.212
44 4.310 0.216 4.310 0.198 4.310 0.179
45 12.112 0.207 12.112 0.201 4.310 0.137
46 4.310 0.157 4.310 0.145 4.310 0.128
47 4.447 0.232 1.627 0.199 0.845 0.252
48 4.310 0.114 4.310 0.109 4.310 0.091
49 11.579 0.126 11.579 0.149 4.622 0.112
50 4.310 0.086 4.310 0.082 6.731 0.079
Max. phase A current TDD (% of In): 16.823 Output power at max current THD (kW): 12.780
Max. phase B current TDD (% of In): 15.113 Output power at max current THD (kW): 12.780
Max. phase C current TDD (% of In): 15.316 Output power at max current THD (kW): 12.780
The harmonic currents were subgrouped according to Section 5.6 of IEC 61000-4-
7/CDV. The window width used during measurements was Tw=12.
20
18
16
14
Current TDD (%)
12 CURRENT A
10 CURRENT B
CURRENT C
8
0
0 2 4 6 8 10 12 14 16
Power (kW))
Page 12 of 35
3.5 Current Interharmonics
The individual interharmonic currents below 2 kHz are given in Table 8 as 10-min
average values for each frequency at the output power giving the maximum individual
interharmonic current.
Page 13 of 35
2850 6.127 0.146 6.127 0.135 6.127 0.153
2910 6.127 0.141 6.127 0.131 6.127 0.149
2970 6.127 0.138 6.127 0.128 6.127 0.145
3030 12.778 0.817 12.778 0.734 12.778 0.700
The individual current distortions in the range 2 kHz up to 9 kHz are given in Table 9 as
10-min average values for each frequency at the output power giving the maximum
individual current distortion.
Page 14 of 35
8.7 2.149 0.064 2.149 0.063 2.149 0.055
8.9 2.149 0.053 2.149 0.054 1.231 0.047
The current distortions were measured and evaluated according to Annex B of IEC
61000-4-7/CDV. The window width used during measurements Tw=12.
1.2
1.0
Voltage Imbalance (%)
0.8
0.6
0.4
0.2
0.0
0 2 4 6 8 10 12 14 16
80
70
Current Imbalance (%)
60
50
40
30
20
10
0
0 2 4 6 8 10 12 14 16
Page 15 of 35
3.8 Continuous Operation Flicker
The flicker coefficients C(Ψk ,Va) were determined according to procedures listed in
IEC61400-21. The flicker measuring and analysis methods are described in the standard.
Total number of 10-min interval data collected for this test: Nbin=1021.
Figure 8, Figure 9, Figure 10, and Figure 11 show the graphs of fictitious grid flicker
coefficients as a function of 10-min average active power for four different impedance
phase angles (30°, 50°, 70° and 85°). The resulting flicker coefficients for continuous
operation are shown in Table 10. The ratio between three-phase short circuit apparent
power of the fictitious grid Sk,fic and turbine rated apparent power Sn used for the analysis
is 50. During the power quality test there was a nearby dynamometer test and a
neighboring turbine test that were both known to affect the power quality on the grid.
These tests may have contributed to the variations in Pst.
6
5
4
3
Pst
2
1
0
-5 0 5 10 15
POWER (kW)
6
5
4
3
Pst
2
1
0
-5 0 5 10 15
POWER (kW)
Page 16 of 35
6
5
4
3
Pst
2
1
0
-5 0 5 10 15
POWER (kW)
Figure 10: Pst vs. power for 70° network impedance angle
6
5
4
3
Pst
2
1
0
-5 0 5 10 15
POWER (kW)
Figure 11: Pst vs. power for 85° network impedance angle
The simulated flicker values Pst depend on Sk.fic and the grid impedance angle. To reduce
this dependence, IEC 61400-21 defines flicker coefficients C(Ψk ,Va) which are
calculated as a normalized quantity according to Equation 6 of the standard (Ψk - network
impedance phase angle, Va – annual average wind speed). The flicker coefficient of the
wind turbine for the actual Ψk and Va at the site, may be found from the Table 10 by
applying linear interpolation.
Page 17 of 35
Table 10: Resulting flicker coefficients in continuous operation
Normal start tests were conducted at cut-in, moderate, and rated wind speeds. The wind
speed was recorded during the tests along with voltage and current waveforms, and 10-
min average wind speed during the switching operation was within ± 2 m/s of the
required wind speed. The measurements were taken for a period long enough to ensure
that the transient of the switching operation was abated, though limited to exclude
possible power fluctuations due to turbulence. Table 11 lists the figure numbers for the
current waveforms for all starting and stopping cases.
The active and reactive powers were calculated for each start and stop case. The time
series RMS voltage for Phase A also are shown for each case to illustrate voltage
fluctuations during switching operations.
Page 18 of 35
The voltage and current time series were combined in Equation 1 of the standard to
simulate fictitious voltage time series ufic(t) for four different network impedance angles.
The flicker step factors and voltage change factors were determined for each switching
operation for four impedance angles (Table 12-15).
Figure 12: Cut-in wind (4.8 m/s) start: current waveforms (August 19, 2009)
Page 19 of 35
Figure 13: Cut-in wind (4.8 m/s) start: power and RMS voltage (August 19, 2009)
Page 20 of 35
Figure 14: Rated wind (10.5 m/s) start, current waveforms (December 31, 2009)
Page 21 of 35
Figure 15: Rated wind (10.5 m/s) start, power, and RMS voltage (December 31, 2009)
Page 22 of 35
Figure 16: Cut-in wind (3.4 m/s) stop, current waveforms (August 19, 2009)
Page 23 of 35
Figure 17: Cut-in wind (3.4 m/s) stop, power, and RMS voltage (August 19, 2009)
Page 24 of 35
Figure 18: Rated wind (10.0 m/s) stop: current waveforms (December 31, 2009)
Page 25 of 35
Figure 19: Rated wind (10.0 m/s) stop: power and RMS voltage (December 31, 2009)
Page 26 of 35
The maximum number of switching operations for 10-min and 120-min intervals (N10 and
N120) for each type of switching operation was not provided by the turbine manufacturer.
So, the N10 and N120 values were assumed based on the method given by IEC61400-21.
The flicker step factor and voltage change factors were determined as the average results
of five values are shown in the tables below.
Page 27 of 35
Table 15. Characteristics of stop at rated wind speed
The flicker step factor and voltage change factor of the wind turbine for the actual Ψk at
the site can be found from the above tables by applying linear interpolation.
5.0 Exceptions
Exceptions to IEC61400-21:
• The current and voltage sensors used for this testing do not meet the Standard
requirements for compliance with the IEC 60044-1 and IEC 60186 respectively, but
they do exceed the minimum accuracy required by the Standard. This should have no
effect on results or uncertainty.
• The 15 m/s wind speed bin was not filled because it is difficult for our site to have
high wind speed within the 8% to 16% turbulence intensity required in the standard
due to our diverse terrain.
Page 28 of 35
Appendix A. Test Matrix
Continuous operation:
number of 10 min intervals 5 for each bin, At least 5 for each 1 m/s wind speed
except 15 m/s bin
bin
Switching operation:
Switching operation:
Switching operation:
Switching operation:
Page 29 of 35
Appendix B. Post Calibration Report
Page 30 of 35
Page 31 of 35
Page 32 of 35
Page 33 of 35
Page 34 of 35
Page 35 of 35