Nothing Special   »   [go: up one dir, main page]

Pert-Cpm - S-Curve PDF

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

Ireenel Construction and Supply Inc. (ICS Inc.

)
297C Sto. Rosario St. Plainview Subd., Mandaluyong City T:(02) 534 9348
ireenelconstandsupply@gmail.com

PERT/CPM & S-CURVE


Project Title 2019 Repair and Rehabilitation of Classroom -Lot 2 Bid Amount PHP 2,693,973.02 No. Buildings 7 Number of Workers 10
School/s San Andres ES, San Vicente ES, Francia ES School Division SCHOOLS DIVISION OFFICE - CITY OF IRIGA No. of Classroom 10
1st Quarter 2nd Quarter 3th Quarter 4th Quarter
Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10 Week 11 Week 12 Week 13 Week 14 Week 14
/ Days
Duration

Site/Activity/Work M T W Th F Sa Su M T W Th F Sa Su M T W Th F Sa Su M T W Th F Sa Su M T W Th F Sa Su M T W Th F Sa Su M T W Th F Sa Su M T W Th F Sa Su M T W Th F Sa Su M T W Th F Sa Su M T W Th F Sa Su M T W Th F Sa Su M T W Th F Sa Su M T W Th F Sa Su M T W Th F Sa Su

A DECS 1CL-San Andres


Roofing Works 7 1 1 1 1 1 1 1
Steel Works 11 1 1 1 1 1 1 1 1 1 1 1
Carpentry Works 11 1 1 1 1 1 1 1 1 1 1 1
Electrical Works 2 1 1
Doors & Windows 5 1 1 1 1 1
Painting Works 23 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
B BLSB 2CL-San Andres 88.249
Roofing Works 7 1 1 1 1 1 1 1
Truss Works 11 1 1 1 1 1 1 1 1 1 1 1
Carpentry Works 11 1 1 1 1 1 1 1 1 1 1 1
Electrical Works 2 1 1
Doors & Windows 4 1 1 1 1
Painting Works 23 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
C MARCOS TYPE 2CL -San Andres
Roofing Works 10 1 1 1 1 1 1 1 1 1 1
Steel Works 7 1 1 1 1 1 1 1
Carpentry Works 16 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Electrical Works 2 1 1
Doors & Windows 8 1 1 1 1 1 1 1 1
Painting Works 24 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
D BLSB 2CL-San Andres
Roofing Works 7 1 1 1 1 1 1 1
Truss Works 11 1 1 1 1 1 1 1 1 1 1 1
Carpentry Works 11 1 1 1 1 1 1 1 1 1 1 1
Electrical Works 2 1 1
Doors & Windows 4 1 1 1 1
Painting Works 23 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
E DECS 1CL-San Vicente 47.002
Roofing Works 7 1 1 1 1 1 1 1
Steel Works 11 1 1 1 1 1 1 1 1 1 1 1
Carpentry Works 11 1 1 1 1 1 1 1 1 1 1 1
Electrical Works 2 1 1
Doors & Windows 4 1 1 1 1
Painting Works 22 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
F DECS 1CL-San Vicente
Roofing Works 7 1 1 1 1 1 1 1
Steel Works 11 1 1 1 1 1 1 1 1 1 1 1
Carpentry Works 11 1 1 1 1 1 1 1 1 1 1 1
Electrical Works 2 1 1
Doors & Windows 6 1 1 1 1 1 1
Painting Works 23 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
G DECS 1CL-Francia 17.266
Roofing Works 7 1 1 1 1 1 1 1
Steel Works 11 1 1 1 1 1 1 1 1 1 1 1
Carpentry Works 11 1 1 1 1 1 1 1 1 1 1 1
Electrical Works 2 1 1
Doors & Windows 4 1 1 1 1
Painting Works 23 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
0 417 2 3 2 2 2 2 2 4 3 4 4 3 3 3 2 2 2 2 1 1 1 3 4 3 3 3 3 3 5 4 4 4 2 3 3 2 2 2 2 1 1 1 5 6 7 6 7 7 7 9 8 6 7 4 4 5 5 5 5 5 4 2 2 4 5 4 4 4 4 4 # # 9 9 7 7 7 9 7 # # 5 7 7 5 5 5 5 3 3 3 3 3 2 2 2 2 2 2 2 0 0 0 0 0
### # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # #
% Work per Week 3.597 5.755 2.638 5.276 5.995 2.638 10.791 10.312 6.715 6.954 14.388 13.189 6.954 3.837 0.959
% Work per Quarter 17.266 29.736 41.247 11.751
Commulative % Work 0 17.266 47.002 88.249 100.000
Amount per Week 96,905.50 155,048.81 71,064.04 142,128.07 161,509.17 71,064.04 290,716.51 277,795.78 180,890.27 187,350.64 387,622.02 355,320.18 187,350.64 103,365.87 25,841.47
Amount per Quarter 465,146.42 801,085.50 1,111,183.12 316,557.98
Commulative Amount PHP 465,146.42 PHP 1,266,231.92 PHP 2,377,415.04 PHP 2,693,973.02

Prepared by:
PATRICK SARMIENTO
Contractor