MV Cable Pulling and Installation Method Statement

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 8

NINXIA

Document Title: Document No. EMG-LAS-


Method Statement for Cable Pulling & Termination of MV&LV Cables MS-BGxxx-xx-015
Project Title: Date: Rev. No. 00

JIGCC POWER BLOCK PROJECT (PACKAGE4) 19 DEC Page 1 of 8


SEPCO ELCTRIC POWER CONSTRUCTION COPORATION 2019

PROJECT TITLE
JIGCC POWER BLOCK PROJECT (PACKAGE4)
SEPCO ELCTRIC POWER CONSTRUCTION COPORATION

Document Title

Method Of Statement for Cable


Pulling & Termination of MV&LV
Cables

Revision and Approval History


CONTRACTOR EMPLOYER
Rev. Description Approval
Date Reviewe
No. / Remarks Prepared Approved Approved Status
d

M.NOUZAL
NINXIA

Document Title: Document No. EMG-LAS-


Method Statement for Cable Pulling & Termination of MV&LV Cables MS-BGxxx-xx-015
Project Title: Date: Rev. No. 00

JIGCC POWER BLOCK PROJECT (PACKAGE4) 19 DEC Page 2 of 8


SEPCO ELCTRIC POWER CONSTRUCTION COPORATION 2019

1.0 PURPOSE

2.0 SCOPE

3.0 REFERENCES

4.0 DEFINITIONS

5.0 RESPONSIBILITIES

6.0 EQUIPMENT

7.0 HEALTH AND SAFETY ARRANGEMENTS

8.0 PROCEDURE

8.3 CABLE TERMINATION & INSTALLATION

8.4 TESTING & COMMISSIONING

9.0 DOCUMENTATION
NINXIA

Document Title: Document No. EMG-LAS-


Method Statement for Cable Pulling & Termination of MV&LV Cables MS-BGxxx-xx-015
Project Title: Date: Rev. No. 00

JIGCC POWER BLOCK PROJECT (PACKAGE4) 19 DEC Page 3 of 8


SEPCO ELCTRIC POWER CONSTRUCTION COPORATION 2019

1.0 PURPOSE

This method statement is applicable for laying & termination of MV&LV Cables for
NINGXIA COMPANY, client of SEPCO ARABIA CO. in accordance with the specified
standards and regulations in project specifications.

2.0 SCOPE

The Scope of works includes the delivery to site, installation, pre-commissioning, testing,
commissioning and guarantee of the system as described in the specification/contract
documents and drawings.

3.0 REFERENCES

3.1 Project Contract Specifications


3.2 Approved Project Quality Plan: SEPCO-PQP-01 Rev.01
3.3 Approved Project HSE Plan: SEPCO-HSE-01 Rev.00
3.4 SEPCO HSE Procedures
3.5 Approved AFC Drawings
3.6 Approved Materials

4.0 DEFINITIONS

Employer/ Client : SEPCO ARABIA CO.

Customer : NINXIA
NINXIA

Document Title: Document No. EMG-LAS-


Method Statement for Cable Pulling & Termination of MV&LV Cables MS-BGxxx-xx-015
Project Title: Date: Rev. No. 00

JIGCC POWER BLOCK PROJECT (PACKAGE4) 19 DEC Page 4 of 8


SEPCO ELCTRIC POWER CONSTRUCTION COPORATION 2019

Operating Company :
SEPCO ARABIA
Contractor/Contractor :

Subcontractor/Sub-tiers : Organization employed by Contractor for executing part of


the works

Supplier : Organization used by Contractor and /or subcontractors


for supply of approved Materials.

IR : Inspection Request

HSE : Health, Safety and Environment

5.0 RESPONSIBILITIES

5.1 The Project Manager is over all responsible for implementation of this Method
Statement and to ensure that his site team of Engineers and Foremen are aware of
this Method Statement and all resources, manpower, material and equipment are
available to carry out the work as planned and without any delay.

5.2 The Construction Manager/Site Engineer will co-ordinate with the MEP Sub
contractors and the Safety Officer, Foreman for a safe and proper execution of
works.

5.3 The Site Supervisor/General Foreman along with Foreman will ensure that, the
installation is carried out according to the Specifications/Drawings and the Method
Statement.

5.4 Lead QA/QC Engineer, in close interaction with MEP Site personnel, will ensure
that, the works are carried out as per the project requirements. He is also responsible
for the implementation of QA/QC related to works as detailed in this procedure and
for completing Quality Documents for the Installation works.

5.5 Lead Safety Engineer will ensure implementation of all safety procedures, Safety
measures related to the nature of works being carried out in accordance with Project
HSE Plan “ EMG-HSE-01 Rev.00

6.0 EQUIPMENT

 Cable Rollers
NINXIA

Document Title: Document No. EMG-LAS-


Method Statement for Cable Pulling & Termination of MV&LV Cables MS-BGxxx-xx-015
Project Title: Date: Rev. No. 00

JIGCC POWER BLOCK PROJECT (PACKAGE4) 19 DEC Page 5 of 8


SEPCO ELCTRIC POWER CONSTRUCTION COPORATION 2019

 Cable Pulling Grip


 Hand Cable cutter
 Manual Cable Crimpers
 Hacksaw blade
 Power Tools
 Tool Box
 Measuring Tape
 Ladders / Scaffoldings/Platform
 Hand tools Hilti Drill Machine
 Hilti Concrete Bit (6mm to 16 mm)
 Anchor Bolt/Screw
 Screw Driver
 Adjustable Spanner
 Hammer
 Electrician’s Knife
 Multi Meter
 1 KV / 5 KV IR Test Kit
 Continuity Tester
 Torque wrench
 VLF – Test Kit

7.0 HEALTH AND SAFETY ARRANGEMENTS

The hazards associated with the Cable Pulling & Termination of MV Cables have
documented (Ref: Job Hazard analysis Doc. No. HSE/RA/__. Control measures
as identified in the documents will be complied with the approved Project HSE
Plan.

8.0 PROCEDURE

8.1 Preparation

8.1.1 Excavation

 Permit to Work (PTW) shall be raised for the excavation clearly mentioning the
location of work, size of excavation and levels.
 Excavations area shall be surveyed and marked to the lines and levels as shown on
the drawings.
 The area of excavation will be cordoned off using safety devices.
NINXIA

Document Title: Document No. EMG-LAS-


Method Statement for Cable Pulling & Termination of MV&LV Cables MS-BGxxx-xx-015
Project Title: Date: Rev. No. 00

JIGCC POWER BLOCK PROJECT (PACKAGE4) 19 DEC Page 6 of 8


SEPCO ELCTRIC POWER CONSTRUCTION COPORATION 2019

 Ensure the working area at any confined space is free from any Hazardous Gas by
proper Gas testing using the Gas testing instrument.

8.1.2 Materials

 Not necessary for the construction shall be removed carefully and stored neatly for
reinstating after the construction works.
 The material received from the client shall be stored in designated area of store.
 Arrangements shall be made to protect against effects of weather and environment.

8.2 Cable Pulling

 Insulation resistance of the cables shall be checked before laying cables.


 After the test, the end of the cable shall be sealed to prevent the ingress of
moisture.
 Location of the panels / equipment shall be identified.
 Cables shall be lubricated if bends in conduits are encountered in a run to facilitate
drawing in.
 Cables must not be bent to a radius of less than 12 times the overall diameter of
the cable.
 Rollers must be used where cables are installed in an open trench using a pulling
rope and eye; cable rollers are to be used at frequent intervals to support the cables
and must never be more than 3 meters apart.
 The rollers are to be placed securely to prevent movement.
 The pulling rope must be equipped with a swivel and be attached to the cable by
a stocking grip with pulling eye.
 The cable drum intended for cable pulling shall be identified as per that indicated
in the drum schedule.
 The cable drums shall be un-packed and placed on a cable roller, as required.
 Cable laying will generally start from one end of the route length or at any suitable
point, as necessary.
NINXIA

Document Title: Document No. EMG-LAS-


Method Statement for Cable Pulling & Termination of MV&LV Cables MS-BGxxx-xx-015
Project Title: Date: Rev. No. 00

JIGCC POWER BLOCK PROJECT (PACKAGE4) 19 DEC Page 7 of 8


SEPCO ELCTRIC POWER CONSTRUCTION COPORATION 2019

 Depending on the weight and size of the drum, suitable size of the cable rolling
shaft (Spindle) shall be placed inside the central axis of the drum.
 Suitable jacks shall be placed firmly on the ground and jacked-up to allow
clearance from the ground depending on the size of the cable drum.
 The drum shall be lifted by required equipment and placed on the jacks.
 The cable drum will be correctly positioned and the direction of cable pulling as
indicated by arrow on the drum shall be complied.
 The cable shall be drawn into the trench smoothly with a minimum of stops and
at an average speed of between 9-12 meters per minute, to avoid irregular
movement.

8.3 Cable Termination & Installation

 Termination point inside the panels / equipment shall be considered for suitable
spare length to be left available during pulling of cable termination.
 After cutting the cable to the required length the termination work will be
conducted as per ADDC Standard.
 Jointing and Termination will be carried out as per ADDC standards. All jointing
and termination work will be carried out by trained technicians, experienced in
such work for the operating voltage concerned.
 Proper crimping tools shall be used compression type lugs. All cables are to be
terminated used glands of proper type and size as per area classification.
 The gland shall be assembled strictly in accordance with manufacturer’s
instruction, particular attention being paid to ensure good mechanical and
electrical contact between parts without excessive strain or distortion of cable.
 The entire body of the cable must enter the gland. The cable shall be on a straight
axis from a point at least six diameter before entering the gland. Seals shall be
checked for correct size at the point of application.
 Unused cable entries shall be closed with plug suitable for the degree of protection
classification.
 After completion of indoor and outdoor termination the cable is ready for Testing.
NINXIA

Document Title: Document No. EMG-LAS-


Method Statement for Cable Pulling & Termination of MV&LV Cables MS-BGxxx-xx-015
Project Title: Date: Rev. No. 00

JIGCC POWER BLOCK PROJECT (PACKAGE4) 19 DEC Page 8 of 8


SEPCO ELCTRIC POWER CONSTRUCTION COPORATION 2019

8.4 Testing & Commissioning

 The following calibrated testing instruments will be used:


 1 KV / 5 KV IR Test Kit - 1 no.
 Multi Meter - 1 no.
 Continuity Tester - 1 no.
 Continuity Tester - 1 no.
 Torque wrench - 1 no.
 VLF - Test Kit

 Before starting the test, the corresponding Circuit Breakers at both ends of the
cables are racked out and earthed properly.

 Test will be conducted at the MV panel end. The opposite end of the cable
termination will be secured & protected. Testing engineer will be at the end where
high voltage is applied and another Engineer to monitor at the opposite end of the
cable.
 Insulation Resistance will be done first: (a) between termination lugs; (b) Phase,
Neutral and Earth termination lug; (c) conductor to termination lug. This will be
done one minute each at 5kV, and the results are noted as per approved test report
format.

Note: The cables and conductors must discharged per test.


 The continuity test and phase sequence tests would be carried out and results
would be recorded for records and future reference.

9.0 DOCUMENTATION

9.1 Request of Inspections will be issued for all hold and witness points as indicated on
the Quality Control Plans
9.2 QC Forms will be jointly completed and signed off at the end of Inspection.
9.3 Attachment:
 Quality Checklist - Cable Pulling & Termination of MV Cables
Inspection
 Risk Assessment