Bridge Design
Bridge Design
Bridge Design
INTRODUCTION
1.1 INTRODUCTION
SEQUENCE OF WORKS
2. SPECIFICATIONS
2.1 EXCAVATION
The soil present beneath the surface was too clayey so it was dumped and
was not used for back filling.
The filling is done in layer not exceeding 20 cm layer and than its
compacted. Depth of excavation was 6’6” from Ground Level.
2.2 FOUNDATION
In foundation the details and the specifications are taught to me by the site
engineer the below are the details of foundations and specifications.
A foundation occupies space between the main floor of the house and the
ground below.
There is access to the foundation from the main floor or from outside.
The “floor” of the foundation can be dirt or stone with a vapor barrier, or it
may be capped with concrete.
At our site, Raft foundations are used to spread the load from a structure
over a large area, normally the entire area of the structure.
They are often needed on soft or loose soils with low bearing capacity as
they can spread the loads over a larger area.
At our site, Raft foundations are used to spread the load from a structure
over a large area, normally the entire area of the structure.
They are often needed on soft or loose soils with low bearing capacity as
they can spread the loads over a larger area.
Brickwork is said to be one brick thick if it has a total width equal to the
length of one of its regular component bricks.
At these more modest wall thicknesses, distinct patterns have emerged allowing
for a structurally sound layout of bricks internal to each particular specified
thickness of wall.
2. Mix of motor.
3. Size and shape of masonry construction.
The strength of brick masonry depends upon the strength of bricks used in
the masonry construction.
The strength of bricks depends upon the nature of soil used for making and
the method adopted for moulding and burning of brick . since the nature of soil
varies from region to region
Bricks should be soaked in water for adequate period so that the water
penetrates to its full thickness. Normally 6 to 8 hours of wetting is sufficient.
All bricks should be placed on their bed with frogs on top (depression on
top of the brick for providing bond with mortar).
Thread, plumb bob and spirit level should be used for alignment, verticality
and horizontality of construction.
Joints should be raked and properly finished with trowel or float, to provide
good bond.
2.6 LINTELS
Lintel is a structural component of a building. It is made above door and
window opening. Its main function is to support the masonry wall above openings
and transfer its load to side walls.
Lintel can be made from various materials. Such as steel, wood, stone,
RCC, etc.,
The most used material for lintel is RCC. Normally used concrete ratio for
RCC lintel is 1:2:4.
Lintel can be classified into two types Pre-cast RCC lintel Cast-in-place RCC
lintel
However, you should follow the construction manual for lintel extension-
length into wall, concrete strength and also for reinforcement details
Flight are the diagonal 2x12s that carry the weight of the people walking
up the stairs.
Treads are the top baseboards onto which you step, and risers are placed
perpendicularly under each tread.
With this information, you're ready to begin building. See Step 1 below
for a detailed guide on how to bring a set of stairs from concept to execution.
Steel reinforcements are used generally in the form of bars of circular cross
section in concrete structure.
This has limited the use of plain mild steel bars because of higher yield
stress and bond strength resulting in saving of steel quantity.
They not only take care of structural requirements but also help main
reinforcements to remain in desired position.
Cover blocks are placed to prevent the steel rods from touching the
shuttering plates and there by providing a minimum cover and fix the
reinforcements as per the design drawings.
Sometimes it is commonly seen that the cover gets misplaced during the
concreting activity.
To prevent this, tying of cover with steel bars using thin steel wires called
binding wires (projected from cover surface and placed during making or casting
of cover blocks) is recommended.
Forms are generally made of the materials like timber, plywood, steel, etc.
Generally camber is provided in the formwork for horizontal members to
counteract the effect of deflection caused due to the weight of reinforcement and
concrete placed over that.
The steel form work was designed and constructed to the shapes, lines and
dimensions shown on the drawings.
All forms were sufficiently water tight to prevent leakage of mortar. Forms
were so constructed as to be removable in sections. One side of the column forms
were left open and the open side filled in board by board successively as the
concrete is placed and compacted except when vibrators are used.
For flooring ceramic verified tiles are used. These are of varies sizes, the
sizes used are as shown below
30 cm x 30 cm in toilets
The tiles is used in wash area and original granite is used in balcony. Lift
lobby and fascia wall and floor are made using composite marble and vitrified
tiles. Staircases are using vitrified tile flooring.
Placing tiles at the bottom of floor and wall is known as skirting. Bending
the edge of tiles and granite is known as bending. The tiles and granites placed
on the wall is known as doing. The parking area surrounding the building is made
by vacuum dewatered flooring. Inter lock are used in main entrance ground.
2.14 PLASTERING
Perfect slaking of the calcined lime before being used is very important as,
if used in a partially slaked condition, it will "blow" when in position and blister
the work. Lime should therefore be run as soon as the building is begun, and at
least three weeks should elapse between the operation of running the lime and its
use. The first coat or rendering is from 1/2 to 3/4 inches thick, and
mixed in the proportions of from one part of cement to two of sand to one
part to five of sand. The finishing or setting coat is about 3/16 inches thick, and
is worked with a hand float on the surface of the rendering, which must first be
well wetted.Roughcast or pebbledash plastering is a rough form of external
plaster
Painting is the final work of a building which gives a fantastic and fabulous
look to the building. Painting a wall requires a bit of planning, but when done
right, can give a room a completely different feel. Mostly of two coatings of paint
were used for the smooth surface. Roller brushes were used instead of normal
brushes to get smooth surface. The undulation in the wall is noted. Based upon in
it the painting thickness varied.
Mostly of white color painting was painted inside and outside the hall.
Painting works were done using constructing scaffoldings outside the wall.
etc.,
Fig .2.16(a) INTERIOR PAINTING
GROUND FLOOR
Fig: 3.1.1
Fig: 3.1.2
Fig: 3.1.3
Name Of Lay out : Merina City
DESIGN OF COLUMN
CONCLUSION