Method Statement: Waste Water Treatment Project

Download as pdf or txt
Download as pdf or txt
You are on page 1of 13

METHOD STATEMENT

0 Aug 03rd, 19 Octchiara Cho M. Dhefanda B. M. Bham NS Issued for Approval


Rev. Rev. Date Created by Checked by Approved by Description

WASTE WATER TREATMENT PROJECT

CONTRACT NO: 00i-4E-0008807654A

TITLE:
CIVIL POND WORK

DRAWING / DOCUMENT. No.WWTP-0w00A00199 REV : 2

CONTRACTOR:

Responsible Dept. Created by Checked by Approved by Format:


Construction Octachiara Cho M. Dhefanda B M. Bham NS A4 size

Issue. Type : □For


√ Approval □For Information □Other
Doc. Status: □Approved □Approved Excepted as Noted
□Returned for Correction and Re-submission

Dwg/Doc. No. WWTP-0w00A00199 Rev. 02


TotalPage (14)
WASTE WATER TREATMENT PROJECT

Doc. No : 00i-4E-0008807654A
CIVIL POND WORK Job No : 223354
Rev. No.: 2 Page 2 of 13

REVISION CONTROL SHEET

REV. NO DATE DESCRIPTION


rd
00 Aug 03 , 19 Issued for Approval

001 Oct 4st, 19

002 Dec 03rd, 19


WASTE WATER TREATMENT PROJECT

Doc. No : 00i-4E-0008807654A
CIVIL POND WORK Job No : 223354
Rev. No.: 2 Page 3 of 13

TABLE OF CONTENTS

1) Introduction ........................................................................................................ 4

2) Definition ............................................................................................................ 4

3) Scope of Works .................................................................................................. 4

4) Materials ............................................................................................................. 4

5) Schedule and Organization Chart .................................................................... 5

6) Construction Equipment ................................................................................... 5

7) Manpower ........................................................................................................... 6

8) Method of Works ................................................................................................ 6

9) Health, Safety &Environmental ........................................................................ 13

Attachment:

- Attachment-1………………………………………………………Permit of Work Form


- Attachment-2………………………………………………………ERP Notification
- Attachment-3……………………………………………………… ITP
WASTE WATER TREATMENT PROJECT

Doc. No : 00i-4E-0008807654A
CIVIL POND WORK Job No : 223354
Rev. No.: 2 Page 4 of 13

1) INTRODUCTION
This civil Method Statement defines the procedure to carry out the pond work as per
requirement in WWT project to ensure the safety and quality of the work.

2) DEFINITION
Definition Within the contents of this specification shall be as follow:
 The “OWNER” shall mean Amperro De Achoz Corporation.
 The “CONTRACTOR” shall mean DdNyca, PTE Ltd.

3) SCOPE OF WORKS
This procedure describe that for excavation activity, rebar installation, formworks, concrete
pouring, curing of concrete, formwork dismantling, finishing, and other civil work base on civil
work item list.

4) MATERIALS
The material should be use in the activity;
Figure 4.1: Materials
No Item Class Specification
SNI07-2052-
1 Rebar D 13 for dowel
2002/BJTS40
JIS G 3551 with grade
2 wiremesh M10 for reinforcement
WFR
3 Anchor bolt with template setting (By Contractor)
Polyethylene sheet & geomembrane
4 GRI GM 13,
HDPE 2mm for waterproofing

5 Embedded steel (By Contractor)


SIKA WATERBAR
Waterstop & Bitumen for construction FLEXIBLE PVC WATER
6
joint STOP
SIKA BITUSEAL T-130 SG

7 Plywood 12 mm & support for formwork KELAS-1


Lean concrete fc’150 Kg/cm2 and
8
structure concrete fc’ 250 Kg/cm2
WASTE WATER TREATMENT PROJECT

Doc. No : 00i-4E-0008807654A
CIVIL POND WORK Job No : 223354
Rev. No.: 2 Page 5 of 13

SNI07-2052-
9 BRC for fence
2002/BJTS40
10 Embedded parts & pipe By Other

5) SCHEDULE AND ORGANIZATION CHART

Bikinlah bagan organisasi disini bro!!!

Figure 5.1: Organization Chart

Figure 5.2: MasterSchedule

6) CONSTRUCTION EQUIPMENT
Pond work consist of general excavation backfilling and Concrete work, general excavation and
backfilling equipment will provided as mention in doc. No ……………… and concrete work will
be used as mention below:
- Concrete work equipment (Refer to Doc. ………………..)
WASTE WATER TREATMENT PROJECT

Doc. No : 00i-4E-0008807654A
CIVIL POND WORK Job No : 223354
Rev. No.: 2 Page 6 of 13

- Truck mixer and concrete pump


- Crane and truck
- Scaffoldings and accessories,
- Formwork and accessories,
- Lighting in situational (If needed),
- Hand tools
- Hand Cutter, HDPE Weld machine

7) MANPOWER
Direct manpower shall be allocated as following:
1. Foreman
2. Concrete worker
3. Carpenter
4. Batching plant Operator & Crew
5. Truck mixer operator
6. Concrete pump operator
7. General Labour
8. Masson
9. Rebar men
10. Surveyor
11. Mechanic & electrician
12. HDPE Welder

8) METHOD OF WORKS
The general activity to construct the pond describe on chart below, at cluster #9 the pond area
positioned on existing pond, there are water, HDPE geo membrane, and also wider than the
design,
Over all the existing pond will reconditioning and reshape to design parameter and the water will
free with construct open drainage, connecting the both pond and to existing drainage, because
of elevation deviation the water will flow by self and the geo membrane will cut piece by piece
and remove it to other place.
WASTE WATER TREATMENT PROJECT

Doc. No : 00i-4E-0008807654A
CIVIL POND WORK Job No : 223354
Rev. No.: 2 Page 7 of 13

And before earth work activity, the remaining water will pump by excavator and mud, sediment
material will transfer nearby area to make it dry by self, and it will reuse and/or mixing with good
soil as filling material.

General Flow chart to construct Pond on cluster


General Flow chart to construct Pond on Cluster 9
CL1, CL6 and CLA

JOINT SURVEY, to check original ground level CLEANING EXISTING POND

EXCAVATION, monitored by surveyor team to


FILLING EXISTING POND
avoid over cut, done by layer per layer

POLIETILINE INSTALLATION, be done by POLIETILINE INSTALLATION, be done by


general worker general worker

REBAR, EMBEDDED ITEMS REBAR, EMBEDDED ITEMS


INSTALLATION INSTALLATION

REQUEST FOR INSPECTION REQUEST FOR INSPECTION

POURING/CASTING CONCRETE POURING/CASTING CONCRETE

CURING CONCRETE CURING CONCRETE

HDPE GEOMEMBRANE INSTALLATION HDPE GEOMEMBRANE INSTALLATION

CLEANING/ HOUSE KEEPING; CLEANING/ HOUSE KEEPING;

Figure 8.1: Method of Work

8.1 Excavation
The surveyor will perform joint survey to get the original ground level; afterwards will mark the
area to allow the excavation.
The excavation will perform as per layer (not designed depth layer). Excavation work is
finished when the bottom of the excavation has reached the elevation as shown in the
drawings.
The excavation will start after the subcontractor receive the drawing with for construction
WASTE WATER TREATMENT PROJECT

Doc. No : 00i-4E-0008807654A
CIVIL POND WORK Job No : 223354
Rev. No.: 2 Page 8 of 13

status and the treatment general earth work at cluster #9, and other cluster will continue with
general excavation.
Temporary sum pit will construct to collect the water (if rainy season), and the sum pit will
complete with temporary drainage entire the edge to sum pit area, and the water (if any) will
pump outside and the sum pit will keep until all polyethylene installed finish. And the sum pit
will close with concrete as describe in the drawing below.

Figure 8.2. Excavation phase

8.2 Polyethylene &Rebar Installation


Polyethylene will be installed after excavation has reached design elevation, to lift, load and
mobilize during installation will perform by crane (If needed).
Rebar and or wire-mesh will mobilize to design area from stockpile area/ bar bending area
and it will install by worker (tightened by hand tool).
The formwork will replace by chicken mesh to perform rough surface to next joint pouring
and or to next joint construction.
WASTE WATER TREATMENT PROJECT

Doc. No : 00i-4E-0008807654A
CIVIL POND WORK Job No : 223354
Rev. No.: 2 Page 9 of 13

8.3 Formwork Installation


Plywood

Supports

Water Stop Plywood


Chicken mesh
Supports
Wire mesh

Tag to soil

Figure 8.3: Formwork Installation

The edge of pedestrian pond will install formwork as well describe drawing above,
construction joint will perform with fold the waterstop and combine with chicken mesh.
Forms shall be constructed from sound materials of plywood with supporting accessories
(Wood, Steel hollow, tie rod etc), shall be fixed in perfect alignment and securely braced to
with stand displacements and deflections due to construction loads, such as vertical,
horizontal and impact construction loads. Such as to produce a smooth surface free from
irregularities. The formwork shall be of sufficient strength, properly rigid throughout the placing
and compacting of the concrete without visible deflection. Forms shall be so constructed that
they can be removed without shock or vibration to the concrete.
WASTE WATER TREATMENT PROJECT

Doc. No : 00i-4E-0008807654A
CIVIL POND WORK Job No : 223354
Rev. No.: 2 Page 10 of 13

Before concreting is commenced the forms shall be thoroughly cleaned and free from dust,
dirt and other debris. Temporary openings shall be provided where necessary to drain away
water and rubbish.
Wooden formwork (plywood), thickness shall not be less than 12 mm.
Forms shall be removed in such manner as to ensure the complete safety of the structure, and
similar sort vertical forms may be removed after a lapse of 3 days during all form surfaces
shall be cleaned before re use.

8.4 Concrete Pouring

Portable roller
Top of Concrete

Temporary guide elevation


Supports

Figure 8.4: Concrete Pouring

Concrete shall be sprayed to the poring area by equipment (concrete pump or other)
ensuring it’s required. Concrete shall be deposited directly in it, final position/elevation and
shall not be caused to flow in a manner to permit or cause segregation. And the fresh
concrete will be smoothed by construct temporary rail as guidance, the support of
guidance/rail below of top concrete, and during the pouring time the guidance/rail will
remove and all the top concrete will be smoothed by hand trowel.
When pouring of concrete has started, it shall be carried on as a continuous operation until
the placing of the block complete.
The pond will pour with phase to phase (area by area), refer to joint construction item, as
shown below.
Where joints are to be made the surface of the hard concrete shall be cleaned thoroughly,
roughened, and all laitance shall be removed by chipping and treated with a thin layer of
neat cement before additional fresh concrete is placed.
WASTE WATER TREATMENT PROJECT

Doc. No : 00i-4E-0008807654A
CIVIL POND WORK Job No : 223354
Rev. No.: 2 Page 11 of 13

Figure 8.5: Phase of Pouring Concrete

8.5 Curing & Concrete Protection

All concrete surfaces shall be kept wet at least 7 days after placing except that high early
strength concrete shall be so maintained for at least 3 days and method approved by the
EMPLOYER.
The covering material shall remain in place during the full curing period. The covering
material may be removed when the concrete has hardened sufficiently.

8.6 Surface Treatment of Structural Concrete

Top surfaces of structural concrete slabs shall be levelled unless otherwise indicated.
Hand tool trowel finish; The same requirements apply as for monolithic finish, except that
the consistency of concrete shall be as used for the portion of work for which steel troweled
finish is specified.

8.7 Geo membrane Installation

After material/geo membrane stock nearby pond area, it will spray/install per sheet to mark
area, installation will conduct by excavator and tidy by general worker, and some of them
WASTE WATER TREATMENT PROJECT

Doc. No : 00i-4E-0008807654A
CIVIL POND WORK Job No : 223354
Rev. No.: 2 Page 12 of 13

will cut as connection (as drawing below), the geo membrane will be connected with fusion
welding, before installation perform, the pond will be pumped from water (if any).

Figure 8.6: Geomembrane Installation

8.8 Fence installation and concrete paving work

The foundation of fence and concrete paving will perform with precast, and then it will be
installed by excavator and guided by surveyor for alignment and excavation will perform
manually with general worker.
WASTE WATER TREATMENT PROJECT

Doc. No : 00i-4E-0008807654A
CIVIL POND WORK Job No : 223354
Rev. No.: 2 Page 13 of 13

Figure 8.7: Fence Installation & Concrete Paving

9) HEALTH, SAFETY & ENVIRONMENTAL


9.1 Sub-Contractor will follow Project Health & Safety Plan …………………………
9.2 Safety concern during the excavation work as a mention below:
 Ensure Permit To Work and JSA ready
 Assign a safety supervisor frequently on site to ensure work is being conducted in
accordance with the Permit to Work and JSA
 Conduct truck mixer when loading & unloading
 Provide all mandatory PPE
 Conduct toolbox talk before commencement of works
 Ensure all personnel beware with all safety signs, barricades and other type of safety
controls of hazard identification
 All personnel should maintain awareness of potential hazards before beginning each
shift
 Establish effective communication system between operators, supervisors and other
parties.