Nothing Special   »   [go: up one dir, main page]

Power System Operation and Control

Download as pptx, pdf, or txt
Download as pptx, pdf, or txt
You are on page 1of 14

Power System Operation

and Control
Load Variations and Load Characteristics,
Load Curves, Load Duration Curves, Reserves,
Load Forecasting and Unit Commitment
Introduction
 Power Station delivers power to large number
of customers
 Customer’s need (or load) is never constant
 Electric Power cannot be stored and must be
consumed upon production
 At the same time, alternators give maximum
efficiency at their rated capacity
 Proper Load prediction and calculations are
key to efficient design of power Station
Topics Covered
Load Curve.
Daily Load Curve Interpretation.
Few important terms and factors.
Load Duration Curves.
Base Loads, Peak loads.
Reserves.
Load Forecasting.
Unit Commitment.
Variable Load
 Definition: The load on a power station
varies from time to time due to uncertain
demands of customers. This is known as
Variable load on power station

 Effects of Variable Load:


Need for additional Equipment 
◦ Eg: Equipment to handle raw materials during
varying load conditions in thermal power
station.
Increase in Production Cost 
◦ Eg: Alternators of different capacities must
be installed to get maximum efficiency by
operating at rated capacity.
Load Curves
 Definition: The curve
showing variation of load
on a power station w. ref.
to time
 Daily Load Curve  Variation of load on
a day plotted on an hourly basis
 Monthly Load Curve Variations of load
in a month – Plotted using daily load
curves  used to fix rates of
energy
 Yearly Load Cur ve  Extrapolated using
monthly load curves  used to
determine annual Load Factor
Daily Load Curve
Interpretation
Shows variation of load on power station on a day
 Units generated in a day = Area (in kWh) under the
daily load curve
 Highest point on curve  Maximum demand on the
station for the day Area (in kWh) under daily curve
 Average Load on the station =
24 hrs

Average Load
 Load Factor =
 Helps in Max Demand
◦ Selecting Size and number of generating units
◦ Preparing operating schedule of the station

Important Terms and
Factors
 Connected Load : Sum of continuous rating of all equipments
connected to supply system
 Maximum Demand : Greatest demand of Load on the power station
during a given time
 Maximum Demand
Demand Factor =
◦ usually <1 Connected Load
◦ vital in determining capacity of plant equipment
 Average load or Average Demand: Average of loads
occurring on a power station in a given period


 No of units (kWh ) generated in a day
Daily avg Load =

24 hrs
No of units (kWh ) generated in a month
Monthly avg Load =
Hours in a month
No of units (kWh ) generated in a year
Yearly avg Load =
8760
Important Terms and Factors –
contd.. Avg Load units generated in T hrs

Load always =<1
◦ Factor =
Max Demand Max demand × T
◦ Used for determining overall cost/unit generation
◦ Higher the load factor  lesser the cost / unit

◦ always > 1
◦ Greater Sum diversity factor  lesser cost of
of individual max demands
generation
Diversity Factor = of power
max demand on power station

 Actual Energy produced


Capacity Factor =
◦ Indicativemaxofenergy that could
reserve ' ve been produced
capacity of the plant
Total Demand (Units generated in T hrs )
=
Plant Capacity in T hrs
Annual kWh output
Annual Capacity Factor =
Plant Capacity ×8760
Important Terms and Factors
– contd..
Reserve Capacity = Plant Capacity – Max
Demand.
◦ Difference between L.F and C.F is indicative
of reserve capacity
◦ If max demand = plant capacity, then L.F =
C.F  no reserve capacity
 Station Output in kWh
Plant Use Factor =
Plant Capacity × hours of use
Unit Generated/Annum
Avg Load
Load Factor =
Max Demand
Avg Load = Max Demand × L.F
unit gen / annum = Avg load × hours in a year
= Max Demand × L.F . × 8760
Load Duration Curve
 Definition: When load elements of load curve are
arranged in order of descending magnitudes, the
resulting curve is Load duration curve
◦ Input is the load curve
◦ Max load is at left and decreasing loads are at right
in descending order
◦ Area under load curve = Area under load duration
curve
Base Load and Peak Load
The unvarying
load which
occurs almost
the whole day 
Base Load

The varying peak
demands of load
over and above
the base load 
Peak Load
Reserve
 Installed reserve  is the amount of existing generation that is
higher than that needed to reliably meet a forecasted peak load
 Spinning reserve  is the unused capacity that can be activated by
the system operator and which is provided by generators
synchronized to the network
 Hot Reserve  the reserve capacity that is synchronized to the grid
system and should be capable of meeting the demand within 10
minutes of a dispatch instruction. It is useful during emergency
conditions and unexpected load swings.
 Cold or Non - Spinning Reserve  capacity of generators not
running at present that can be ramped to capacity and synchronized
to the grid within 10 minutes of a dispatch instruction and should
be capable of maintaining that output for at least two hours. Non-
Spinning Reserve is useful during emergency conditions
Unit Commitment
Fd
Fd

You might also like