US932565A - Anticipatory riprap-dikes. - Google Patents
Anticipatory riprap-dikes. Download PDFInfo
- Publication number
- US932565A US932565A US47529109A US1909475291A US932565A US 932565 A US932565 A US 932565A US 47529109 A US47529109 A US 47529109A US 1909475291 A US1909475291 A US 1909475291A US 932565 A US932565 A US 932565A
- Authority
- US
- United States
- Prior art keywords
- dike
- riprap
- poles
- cells
- stream
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02B—HYDRAULIC ENGINEERING
- E02B3/00—Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
- E02B3/04—Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
Definitions
- My invention relates to improvements in anticipatory riprip dikes in which eellulated vertically disposed structures and laterally extended mattress structures of logs, poles, brush and fibrous materials, suchv as cane, weeds7 straw, hay, corn and cotton stalksa-nd bagasse, framed spiked and wired together and bound and Vanchored by cables, sunken ground-anchors and piles are disposed in a manner to arrest erosion, straighten and control streams and protect the banks thereof; and the objects of my improvement are, first, to keep out of the channel of the stream while doing such work and thus avoid obstructi-ng navigation; second, to produce facilities lto vbreakout new straight channels across the.
- eellulated vertically disposed structures and laterally extended mattress structures of logs, poles, brush and fibrous materials suchv as cane, weeds7 straw, hay, corn and cotton stalksa-nd bagasse, framed spiked and wired together and bound and Vanchored by cables, sunken ground-anchors and pile
- FIG. 4l is a perspective sectional detail on the broken lilies n, at A,B and E, 'of Figs.' 1 and 6;
- Fig. 5 isan enlargedV detail plan of same bank, as indicated at 74:.
- j increases the serpentining of the course until avulsion takes place by the stream breaking through some old bed-now a long the construction, particularly of the part G in Figs. 6 and 7, of part V in Figs. 10 and 11 ⁇ and of part T in Figs. 14 and 15;
- Fig. 6, is a plan ofthe construction -and work at B, of Fig. 1;
- Fig. 7, is a vertical section of stream, bank and work at the broken line O on Figs.
- FIG. 11 is a vertical section on the broken line i, of Fig. 10;
- Fig. 12 is a vertical section showing separately the binding cables with the angle poles theyengage and the vertical anchor-cables of ⁇ Figs. 10 and 11;
- Fig.v 13 is a modified structure used where poles vand tine fibrous materials are plentiful and ordinary brush scarce;
- Fig. 14 is aV plan ofthe work as disposed at D in Fig. 1, parts cut away to disclose the construction which is appropriate for all the low land work F, 3, 3, 3 and 3;
- Fig. 15, is a vertical'section on the broken line s of Figs. T14 and 16; and
- Fig. 1,6, is a plan of the angle portion L, of Figs. 14 and 15.
- FIG. 1 A topography that is very common along erosive streams,l I have illustrated by Figs. '1, 2 and 3 and show thereon the application of myinvention to reclaim the river-bottom lands by correcting and controlling the course of the stream deepening its channel and protecting its banks.
- the nearly levelplateau F lying between the river 10 and the Vold river-bed 12, is generally the result of accretion, having often been worked over, back and forth, by the l ever changing course of the stream cutting away the Vbanks in its outward bends, as at B', and accreting bars to downstream off the This often curved lake-so located that it spans the narrow neck of land between two bends far 'l apart on the course of the stream, and hence,
- V56 of the cut which may be sloped Y downward toward the stream at low water periods, is. straightened to startthe work on to the vertical as they will safely stand to work oyer.V
- a large portion of the excavated earth is pushed out over the bank into the current,ras shown at 36 Fig. 3, serving as a temporary check to the erosion while the other part of the work is carried forward.
- a centrally disposed row of pits 28 are'sunk in the bottom from end to end of the work as shown in plan of part T in 14.
- a row of heavy upright posts or piles 14 is driven along each side of the bottom of the cut at its junction with the sloped sides. These piles are spaced in the row about equal to the width of the bottom, as the structure here shown illustrates al single tier of superimposed rectangular cells. For much heavier work a double tier of superimposed cells as shown at V in Figs.
- l() and 11 are employed; generally the size of cells and spacing of posts or piles being controlled by the length of the brush used in building up lioors and ceilings 25, 2G etc., and the longitudinal walls 27 and cross or partition walls 28; these spans being best made of single lengths of brush.
- the heavy longitudinal poles 17 are placed, and centrally parallel therewith the poles 19 are stretched. along the bottom; each line of poles being made continuous by fastening them end to end together with wires or cables.
- the cross-poles 30 are lplaced across the longitudinal poles with their ends agai .et opposite piles and all the members bound firmly together by the wire lashing 2S at every place of eontactwith each other.
- rFhe short diagonal poles 21 are placed on top across the angle between the cross-poles 30 and the longitudinal poles 17; they are spaced away from the piles 14, as shown in Fig. 5, so that with the short posts 15 set centrally against the diagonal pole the space between the post and pile is just suiiicient to contain the longitudinal walls 27 and the cross walls 28 where the brush of which they are composed interlap in forming the angles of the cells.
- the diagonal poles are fastened to the longitudinal and crosspoles as shown at 29, the short posts are fastened to the diagonal poles and to further secure the corners the binding wires 33 are inserted l often, tightly wound around the posts and piles and twisted together as shown.
- the posts 15 are applied in short lengths of sufficient height only for each cell-story, at the floors of which they are spliced together by the wire lashing 1G; this leaves their tops low enough so that in working from the inside the brish composing the walls and partitions is conveniently passed over them.
- the cen tral binding pole 1S is placed.
- the anchorcables 22, previously fastened around both the central bottom-pole 19 and the crosspole, is brought up through and fastened around said binding pole to retain the Iioor material firmly compacted together so as to hold the accumulated mud or filling.
- the walls and. iioors are pressed tightly by any suitable means and strongly bound together that they may be tight enough to retain the added or accumulated lling.
- the brush at hand are too coarse to afford the requisite tightness liner fibrous material as hay straw or bagasse is added, mixed in with said coarse brush of walls and floors, near or yat their inner surfaces.
- the central part must be entirely independent of the triangular side parts which abut against it and not wider at its top than at its bottom; preferably a little narrower at the top so that if undermined by ,the eroding current it will slide downward,
- these dikes are placed from 800 to 1,000 feet apart; ordinarily from sixty to eighty feet wide and from 100 to 200 feet long; modified in position, plan and depth to meet the vary ing requirements of anticipatory riprapping.
- the outer angle K is started out on the ice 39, as shown in Figs.A 6, 7 and 8, to assist in lilling ⁇ out this bend to bring it in line with the work below across the plateau F.
- Excavation is started at 38 making the temporary earth fill 3G shown directly under in Fig. 3.
- the holes 40 are cut and the anchorboxes 24 with the anchor' cables 22 attached are deposited into the till.
- Other holes 41 are cut through the ice and the long posts orpiles 42 are set agreeing in arrangement withthe shorter posts 43 set in the bottom of the excavation for thepart H on the bank.
- the two longitudinal rows of cells lying in the started excavation 38 and on the ice toward the stream, are first built up and filled with the earth excavated forth@ next two longitudinal rows and so on including the ksection G.
- the section G is let down to ⁇ greater depth if possible to form a downward projecting flange or lip along the land or shore edge of the structure to assist to anchor the Whole and is continued back into thebank with triangular side lilling 85 as at A.
- the part H built up on the bottom 55 of theexcavation is usually placed about level, but is better sloped toward the stream; if placed at a period of low water it is given such inclination; and in ordinary work it is only made one cell-story high.
- the small short posts 15 are used at the cell angles with the piles'42 of part K, posts 43 of part H and posts 14 in the part G.
- This structure is built in double longitudinal rows of cells'accommodating long brush for the cross partitions floors and ceilings. And the central longitudinal walls above each longitudinal row of sunken anchor-boxes 24,.-including walls '66 in part G and part V in Figs. l0 and 11,-are secured with the cross walls by the posts 31 'and 32 and the wire lashings 34, as shown in Figs. 5,6 and 7.
- base cross poles 53 are made continuous by splicing the same as the longitudinal poles.
- the lateral encompassingv binding cables 46, 47, 48 and 49 arranged as shown in Figs. 9 and 6 and more particularly shown on Fig. 14, are placed with the starting of each double row of cells; they are continued around all the double rows added, ending around the part Gr; using for every third or fourth the larger cable 46 encompassing the whole as shown.
- the dike at C is fully illustrated in construction, disposition and manner of placing by Figs. 10, 11 and 12. Located at the highest part of plateau F where there is a dense growth of willows, these are employed directly, without cuttinof them, to construct one important feature o the dike:- First, the long row of posts 54, spaced to -serve like the regular posts 43 in forming the cells, is set as a guide for the length and position of the work. This row also marksthe division line between the level portion built above the natural surface of the ground and the inclined part lying on the bottom of an excavation cut between the level part and the deep vertically disposed independent part V. This inclined part pitches downward toward said ⁇ part V and toward the stream, as shown in Fig. 11. The level and inclined portions of the work are carried forward in three sections each consisting of three longitudinal rows of cells: The level section contained within the encompassing binding cables 49,-see Figs. 10 and 12,--- ⁇
- the upper inclined section is bound therewith by the binding cables 48 and the lower inclined section subjaeent to the part V is encompassed with the other two sections by the larger binding cables 4G.
- the excavation for the inclined part may be started and theV removed earth used for the filling 50 in the finished or partly finished cells.
- the inclination is made as steep as convenient to work on, if the water level is not encountered; in which case the part V may not be carried to greater depth than the lowest part of the incline.
- the last section of the incline is generally made two stories in height as shown, the top of the whole finished at a less inclination to give heavier work toward the stream.
- the part V is entirely detached from the subjacent in clined section which abuts against it so that itwill settle vertically and independently if undermined, like the center at A; like which it is constructed except that it is two cells wide and has the central longitudinal partition 6G as heretofore described.
- V'Vhen all is filled, roofed and the anchor cables 5 attached and secured to the piles 4, the earth covering 51 is applied.
- the angle between the part V and the bank cutting 37 may be filled with fascines or cell-work as in A, or have the earth filling'GT, as here shown.
- the large long cellulated fascine G is placed as shown. It is anchored longitudinally by the cable 5, and laterally at a number of points in its length, by the inclined anchor posts 59 and G0 set deep in the ground crossed and bound together against the fascine by a wire lashing 62 at.
- the dike D, lower end of E and those of 3, 3, 3 and 3, are all substantially the same in ⁇ construction and are positioned to protect the banks of and control this newly opened channel.
- the ground floor 58 is constructed of these, uncut, as described above and also shown in Figs. 10 and 1l. On this the excavated earth from T may be piled, as shown at 72, until the cells of this part are made, when the earth is ⁇ thrown back into said cells.
- FIGs. 1, 14 and 15 Another feature, that can also be combined with the other dikes, is illustrated in Figs. 1, 14 and 15: the superimposed cellulated fascine 7, which is anchored by a single cable attached vto its upstream end. This is constructed where it is shown, toward the river edge of the dike. It may be of large diameter and preferably longerthan the dike.
- AtE the dikes are repeated in a line of direction agreeing with the angled position of that one at the end of the line on the bank ofthe new channel; extending the work across the plateau F to and across the lake 12 and into the bench-bank 9.
- This operates conjointly with D, C and B to still the high-water current and cause a heavy flood deposit in the lake and raise the rtliil ie dikes in this line of dikes are separated end from end leaving the embrasures or open spaces 13 between; these serve as driveways in delivering materials on the work during construction and are left open to allow a part of the current to pass through; thus avoiding a too strong deflection of the whole current, an undermining fall over the dike or a destructive eddy below.
- I claimh i A riprap cell filled withweighting material and a supplemental weight-anchor attached to said cell. 12. A riprap cell disposed above the surface 'of the ground and a weight-anchor attachedV and sunk beneath said cell.
- a permeably walled riprap cell connected by a cable to a dependent weightanchor.
- yAiriprap dike comprising two abutted structures adapted to slide upon each other at their? contact surfaces and settle independently.
- A'riprap dike comprising two abutted structures adapted to support and slide against each otherand settle independently.
- riprap dike comprisinga Vvvertically disposed vstructure7 a structure, abutted against VAsaid vertically disposed structure, and said vertically disposed structure adapted to slide' along said abutting structure and settle independently thereagainst.
- riprap dike comprising a weighted structure, a structure abutted against said weightedstructure, and said weighted structure adapted to slide along the contact surdependently thereof.
- a riprap dike comprising two independentlyconstructed weighted structures abutted together and'adapted to slide upon Y face of said vabutting structure and settle ineach other and settle independently.
- Ariprap dike comprising a structure weighted by heavy anchors sunk beneath 1t, a structure abutted against. said weighted i structure, and said weighted structure adapted to settle ⁇ independently of said abutting structure.
- a riprapdike comprising an inclinedly extended structure, and a contiguous vertical structure adapted to settle independently against the edge of said inclined structure.
- a riprap dike comprising a cellulated structure built up from the ground surface and anchored by weight-anchors sunk in the ground beneatl 14.
- a riprap dike comprising a cellulated structure, weight-anchors attached and sunk beneath said cellulated structure, and an independent structure abutted against said cellulated anchored structure.
- a riprap dike comprising a cellulated structure, weighting materials 1n the cells of said structure, and weight-anchors sunk beneath and attached to said structure.
- a riprap dike comprising a Verti cally disposed structure, and a subjacent laterally extended mattress structure having one edge abutted against to support said vertical y disposed structure.
- a riprap dike comprising a vertically disposed cellulated structure, weighting materials in the cells of said structure, and an inclined cellular structure abutted against said vertical structure but not attached thereto.
- a riprap dike comprising a cellula-ted structure having weighting materials in the cells thereof and a subjacent structure abutted against said cellulated structure.
- a riprap dike comprising a vertically disposed structure, and a subjacent inclined laterally extended mattress structure abutted against said vertically disposed structure.
- a riprap dike comprising a laterally extended structure having an integral downwardly extended smaller portion embedded in. the earth below to anchor said structure.
- a riprap dike comprising a structure having a downward extension embedded in the earth below said structure, and an attached weight-anchor suspended in a pit beneath said extension.
- a riprap dike comprising a structure having an integral downwardly extended flange or lip along one edge to anchor said structure in the ground and against lateral movement.
- a riprap dike comprising a fiat cellulated structure having anintegral downwardly projected cell built in a pit. below the general structure and filled with earth or other weighting material to anchor said dike.
- a riprap dike comprising a cellulated structure having an integral portion containing an additional lower story embedded in the ground to anchor said dike.
- a retaining frame comprising longitudinal side-poles, cross-poles fastened across said side-poles, tall posts fastened in anglesbetween crosspolesand side-poles, diagonal poles fastened o-n said cross-poles and side-poles across the angles opposite to said tall posts, and short posts fastened centrally to said diagonal poles.
- a cellular riprap dike bottom comprising side bottom-poles and a central bottom-pole, cross-poles fastened on said central and ⁇ side bottom-poles, posts fastened y in angles between cross-poles and.. side bottompoles, diagonal poles fastened ⁇ to said side bottom-poles and cross-poles across the angle opposite to said posts, other posts fastened centrally to said diagonal poles, a layer of fibrousmaterial laid across said central and side bottom-poles, and a central binding-pole disposed on said layer ofiibrous material and fastened therethroughto said central bottom-pole.
- top and bottom pole members In a riprap dike, the combination of top and bottom pole members, a cable disposed vertically through the dike and made fast to said top and bottom members, and a ⁇ weight-anchor disposed beneath the dike and made fast to the lower end of said cable.
- a sub-anchor for riprap dikes comprising a heavy body disposed in an excavation beneath the dike and connected by a cable fastened to said heavy body and to the structure of the dike.
- a dike having an anchored edge, a binding cable disposed to laterally embrace the whole dike including said anchored edge, and a binding cable to laterally embrace only a part ofthe dike including said anchored edge.
- a dike having binding cables of different lengths disposed to secure together different quantities ofthe dike and all of said binding cables disposed to embrace a selected portion of said dike.
- An anchorage to secure a fascine lying above the surface of the ground consisting of an inclined post having its base fastened to a buried cross-log and its top above the fascine crossed with and fastened to a post set on the opposite side of said fascine.
- a long Acontinuous dike constructed ⁇ partly above and partly below the surface of the ground, the portion above the ground transversely cut to leave narrow7 embrasures between merlons of greater length.
- a method of anticipatory riprapping consisting in forming and protecting new banks along a predetermined course for a stream by building riprap dikes in excavations made in the high land to arrest the erosions and form and protect the new banks therein, and building riprap dikes above the surface of the low land to raise said new banks thereon by flood deposits.
- a method of anticipatory riprapping consisting in forming and protecting new banks along a predetermined course for a stream by building riprap dikes in excavations made in the high land to arrest the erosions and form and protect the new banks therein and building ripr'ap dikes above the surface of the low land to raise new banks thereon by flood deposits and to protect said new banks and extending said low -land dikes out from said predetermined course across contiguous low land to raise the surface thereof by flood deposits.
Landscapes
- Engineering & Computer Science (AREA)
- General Engineering & Computer Science (AREA)
- Environmental & Geological Engineering (AREA)
- Ocean & Marine Engineering (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Revetment (AREA)
Description
D. NBALE.. ANTIGIPATORY BIPRAP DIKE. APPLICATION FILED JAN. 30, 1,909.
Armen/5r.
PatentedAug. 31, 1909.
8 SHEETS-SHEET 1` l D. NBALB. ANTIOIPATOBY BIPBAP DIKE.
APPLIUATIORII'BBD JAN Patented Aug. 31, 1909.
8 SHEETS-SHEET Z.
Mrk
WITNESSES D. NEALE.
ANTIGIPATORY RIPRAP DIKE.
APPLIoATloN HL2 un. ao, loos.
Patented Aug. 31, 1909.
e sums-SHEET a.
@THT WIT/VESSEFS.'
ATTORNEY.
D. NEALB.
.llN'lIOIPATORY RIPRAP DIKE. APPLIOATION FILED JAN. so, 1909.
Patented Aug. 31, 1909.
6 SHEETS-SHEET 4.
Tron/vn.
v D. NEALB. ANTIGIPATORY RIPRAP DIKE.
APPLIGATION FILED JAN. ao, 1909.
l Patented Allg. 31, 1909.
6 SHEETS-SHEET 5.
www s. GRAHAM uo, mmouwoumwnins wAsumeroN` u. L
D. NEALE.
ANTIGIPATORY RIPRAP DIKE.
APPLIOATION FILED JAN. so, 1909.
932,565. l Patented Aug. 31, 1909.
6 SHEETS-SHEET DAvID NEALE, OF FORT CALHOUN, NEBRASKA.
ANTICIPATORY MrRAP-DIKES.
Specification of Letters Patent. Patented Aug. 31, 1909.
Application filed January 30, 1909. Serial No. 475,291.
To all whom it may concern:
Be it known that I, DAVID NEALE, a citizen of the United States, residing at Fort Calhoun, in the county of Vashington and State of Nebraska, have invented vcertain new and useful Improvements in Anticipatory Riprap-Dikes, of which the following is a specification.
My invention relates to improvements in anticipatory riprip dikes in which eellulated vertically disposed structures and laterally extended mattress structures of logs, poles, brush and fibrous materials, suchv as cane, weeds7 straw, hay, corn and cotton stalksa-nd bagasse, framed spiked and wired together and bound and Vanchored by cables, sunken ground-anchors and piles are disposed in a manner to arrest erosion, straighten and control streams and protect the banks thereof; and the objects of my improvement are, first, to keep out of the channel of the stream while doing such work and thus avoid obstructi-ng navigation; second, to produce facilities lto vbreakout new straight channels across the.
low lands between `bends of a stream and protect the new banks athwart such new channels by previously placed riprap; third, to provide a surface riprap` and eilicient anchorage to sustain it to raise the surface of low lands during the high water floods; fourth, to prevent a river from approaching and regaining an `ancient channel now eX- isting as an elongated lake or sloughatthe base of bench lands or bluffs; and` fifth to arrest the erosions and protect the banks at places where the stream hasalready reached the old high banksypr is cutting against high y land. These and other minor objects de'- veloped in the prosecution of the work and more fully hereinafter set forth are` attained by mechanism and in a manner as illustrated in the accompanyino' drawings,'in which- Figure 1 is a small scale map of a tract `of river bottom fland and adjacent bench land and bluffs, showing plans and disposition of the works to build up the bottom land, straighten the stream-and control and pro#` tect its banks; Fig. 2, isa profile on the broken line m, of Fig. 1; F ig. 3,\is aA profile on the broken line y), of Fig. 1, looking toward the bench bank 9 and adjacent bluifs; Fig. 4l, is a perspective sectional detail on the broken lilies n, at A,B and E, 'of Figs.' 1 and 6; Fig. 5, isan enlargedV detail plan of same bank, as indicated at 74:. j increases the serpentining of the course until avulsion takes place by the stream breaking through some old bed-now a long the construction, particularly of the part G in Figs. 6 and 7, of part V in Figs. 10 and 11`and of part T in Figs. 14 and 15; Fig. 6, is a plan ofthe construction -and work at B, of Fig. 1; Fig. 7, is a vertical section of stream, bank and work at the broken line O on Figs. 6 and 8, looking atan angle downstruction; F ig. 11, is a vertical section on the broken line i, of Fig. 10; Fig. 12, is a vertical section showing separately the binding cables with the angle poles theyengage and the vertical anchor-cables of `Figs. 10 and 11; Fig.v 13, is a modified structure used where poles vand tine fibrous materials are plentiful and ordinary brush scarce; Fig.
14, is aV plan ofthe work as disposed at D in Fig. 1, parts cut away to disclose the construction which is appropriate for all the low land work F, 3, 3, 3 and 3; Fig. 15, is a vertical'section on the broken line s of Figs. T14 and 16; and Fig. 1,6, is a plan of the angle portion L, of Figs. 14 and 15.
` Similar reference characters refer toY simi- `lar parts throughout the several views and the arrows 11 always indicate the direction of the water current.
A topography that is very common along erosive streams,l I have illustrated by Figs. '1, 2 and 3 and show thereon the application of myinvention to reclaim the river-bottom lands by correcting and controlling the course of the stream deepening its channel and protecting its banks.
The nearly levelplateau F, lying between the river 10 and the Vold river-bed 12, is generally the result of accretion, having often been worked over, back and forth, by the l ever changing course of the stream cutting away the Vbanks in its outward bends, as at B', and accreting bars to downstream off the This often curved lake-so located that it spans the narrow neck of land between two bends far 'l apart on the course of the stream, and hence,
4e Y and the'sides 37 retained at a slope as near the downstream bend at a much lower level. A similar action is imminent at B, in connection with the old river-bed 12 which is now a slough or long curved lake lying along the base of the bench-bank 9. If the erosion at B is not arrested it will soon reach the adjacent head of the old bed 12, when a pe- Y riod vof high water would open out the old channel and the tract F be avulsed to the opposite bank. The surface water-line 78 in Fig. 3 shows that the dow/'nstream end of the tract F is much lower, there being much less soil above the water-line at this end. Also the high water line 2 in F ig. 2 shows a general descent from the old river-bed toward the stream; although intervening portions left undisturbed by avulsions, rather than formed by accretion, are often more elevated. On these higher places timber often attains considerable age and' size and the whole surface, aside from lakes left by avulsions, produces a rank rapid growth of willows, all of which as hereinafterset forth are utilized among the most important features of my invention.
To at once arrest the encroachment of the stream cutting into a high bank, as at A lFigs. 1 and 8, I employ the construction illustrated by Fig. e, of plan and disposition shown in Fig. 1. All ofthe work, which is generally of much greater length than width, is placed longitudinally at an angleV of from 30to 45 toward the river and downstream as shown. The excavation to receive this structure is made to aV desired depth, controlled by the rapidity of the erosion, mag
nitude and quality of bank and stream. The bottom V56 of the cut, which may be sloped Y downward toward the stream at low water periods, is. straightened to startthe work on to the vertical as they will safely stand to work oyer.V A large portion of the excavated earth is pushed out over the bank into the current,ras shown at 36 Fig. 3, serving as a temporary check to the erosion while the other part of the work is carried forward. To complete the excavation a centrally disposed row of pits 28 are'sunk in the bottom from end to end of the work as shown in plan of part T in 14. Strong anchorboxes-'24,- lled with heavy material, as earth, rocks or sand and having a large cable 22 attached, are deposited in said pits; the cable being out to sufficient length to reach up through the whole work and attach around the various members from bottomV to top,
and anchoring them down. When the bot:- tom 56 is down close to or below the water line thesev pits may be sunk to any desired depth by a large well-auger. And a large rock may be substituted for the iilled an- Chor-.box to form the desired weight-anchors. A row of heavy upright posts or piles 14 is driven along each side of the bottom of the cut at its junction with the sloped sides. These piles are spaced in the row about equal to the width of the bottom, as the structure here shown illustrates al single tier of superimposed rectangular cells. For much heavier work a double tier of superimposed cells as shown at V in Figs. l() and 11 are employed; generally the size of cells and spacing of posts or piles being controlled by the length of the brush used in building up lioors and ceilings 25, 2G etc., and the longitudinal walls 27 and cross or partition walls 28; these spans being best made of single lengths of brush. Along the bottoni against the inside of cach row of piles the heavy longitudinal poles 17 are placed, and centrally parallel therewith the poles 19 are stretched. along the bottom; each line of poles being made continuous by fastening them end to end together with wires or cables. The cross-poles 30 are lplaced across the longitudinal poles with their ends agai .et opposite piles and all the members bound firmly together by the wire lashing 2S at every place of eontactwith each other.
rFhe short diagonal poles 21 are placed on top across the angle between the cross-poles 30 and the longitudinal poles 17; they are spaced away from the piles 14, as shown in Fig. 5, so that with the short posts 15 set centrally against the diagonal pole the space between the post and pile is just suiiicient to contain the longitudinal walls 27 and the cross walls 28 where the brush of which they are composed interlap in forming the angles of the cells. The diagonal poles are fastened to the longitudinal and crosspoles as shown at 29, the short posts are fastened to the diagonal poles and to further secure the corners the binding wires 33 are inserted l often, tightly wound around the posts and piles and twisted together as shown.
The posts 15 are applied in short lengths of sufficient height only for each cell-story, at the floors of which they are spliced together by the wire lashing 1G; this leaves their tops low enough so that in working from the inside the brish composing the walls and partitions is conveniently passed over them.
After the ioor 25 has been laid the cen tral binding pole 1S is placed. The anchorcables 22, previously fastened around both the central bottom-pole 19 and the crosspole, is brought up through and fastened around said binding pole to retain the Iioor material firmly compacted together so as to hold the accumulated mud or filling. In this work at A it is expedient to iill the cells with the excavated earth conveniently at hand. The walls and. iioors are pressed tightly by any suitable means and strongly bound together that they may be tight enough to retain the added or accumulated lling. And if the brush at hand are too coarse to afford the requisite tightness liner fibrous material as hay straw or bagasse is added, mixed in with said coarse brush of walls and floors, near or yat their inner surfaces.
On the linished "floor 25 the walls are started and built up of like materials inter.`
lapped at all angles and inthese angles the binding wires 33 are inserted often. When the walls are up to the top of the first story of cells the cells are lled' withthe ex' cavated earth rammed in compactly. Here a ceiling or second ioor 26 is laid on of the same materials, thoroughly interlapped and bound into the Walls which are `continued up for the next story; and. so on finishing the top, as shown on part V, of Figs. 10 and 11, with a ceiling and roof 57 of brush, like other ceilings and floors, and the binding poles 63. The free ends of the cables are drawn up taut and made `fast to the central' i built up like the central part could be used.
In either case the central part must be entirely independent of the triangular side parts which abut against it and not wider at its top than at its bottom; preferably a little narrower at the top so that if undermined by ,the eroding current it will slide downward,
carried by its own weight and assisted by the weighted anchor-boxes beneath. These anchor-boxes and the pile points preventthe base from being swept out laterally. As it settles the fascines 35, or other filling of the triangles, close in above and follow it down and protect the top if the water raises to high-water-mark, as indicated by the broken lines 2 in Figs. 2 and 3. All the parts are thoroughly anchored by the anchor-cables 5 disposed upstream and out from the river bank and fastened to piles`4 or other suitable anchorages all as shown in Fig. 1 and indicated on other views.
In the general management of long stretches of a stream or the breaking through of a new channel, as across the plateau F, these dikes are placed from 800 to 1,000 feet apart; ordinarily from sixty to eighty feet wide and from 100 to 200 feet long; modified in position, plan and depth to meet the vary ing requirements of anticipatory riprapping.
At B and C the dikes are placed closer together and in them my invention is applied in a manner to meet the most serious conditions and demands for rlver riprappmg.
If the dike B can be placed 1n the winter,
the outer angle K is started out on the ice 39, as shown in Figs.A 6, 7 and 8, to assist in lilling` out this bend to bring it in line with the work below across the plateau F. Excavation is started at 38 making the temporary earth fill 3G shown directly under in Fig. 3. As soon as the ice is sufficiently thick to sup port, the holes 40 are cut and the anchorboxes 24 with the anchor' cables 22 attached are deposited into the till. Other holes 41 are cut through the ice and the long posts orpiles 42 are set agreeing in arrangement withthe shorter posts 43 set in the bottom of the excavation for thepart H on the bank.
The two longitudinal rows of cells lying in the started excavation 38 and on the ice toward the stream, are first built up and filled with the earth excavated forth@ next two longitudinal rows and so on including the ksection G. The section G is let down to `greater depth if possible to form a downward projecting flange or lip along the land or shore edge of the structure to assist to anchor the Whole and is continued back into thebank with triangular side lilling 85 as at A. The part H built up on the bottom 55 of theexcavation is usually placed about level, but is better sloped toward the stream; if placed at a period of low water it is given such inclination; and in ordinary work it is only made one cell-story high. In all cases these structures are pliant readily litted to any irregularity during construction and will bend to meet any undermining erosion. The part K, when the cells are illed, as at 50, with the excavated earth from H, will break 'the ice and settle down; cutting the ice along the margin of the dike is sometimes necessary to facilitate this settlement. That it may go down evenlyT and gradually, so that. additional stories of cells can be added and filled on this part, certain of the long piles 42, selected in regular arrangement, are left loose in the structure so that it will slide down on them; and heavy cables fastened in the structure are snubbed to the tops of these selected piles in a manner to be eased olf and control said settlement.
The small short posts 15 are used at the cell angles with the piles'42 of part K, posts 43 of part H and posts 14 in the part G. This structure is built in double longitudinal rows of cells'accommodating long brush for the cross partitions floors and ceilings. And the central longitudinal walls above each longitudinal row of sunken anchor-boxes 24,.-including walls '66 in part G and part V in Figs. l0 and 11,-are secured with the cross walls by the posts 31 'and 32 and the wire lashings 34, as shown in Figs. 5,6 and 7. In parts `H and K, base cross poles 53 are made continuous by splicing the same as the longitudinal poles. The lateral encompassingv binding cables 46, 47, 48 and 49 arranged as shown in Figs. 9 and 6 and more particularly shown on Fig. 14, are placed with the starting of each double row of cells; they are continued around all the double rows added, ending around the part Gr; using for every third or fourth the larger cable 46 encompassing the whole as shown.
.Y When the cells are allv filled-50-with the excavated earth, the top covering 52 of brush f fender poles are very securely fastened down to all the lower work including the top ends of the anchor cables 22 which are fastened around them, and such other vertical bilidings as may be employed. As there isrgenerally a large excess of excavated earth where this dike isplaced a full top dressing 51 is piled over the whole.
The dike at C is fully illustrated in construction, disposition and manner of placing by Figs. 10, 11 and 12. Located at the highest part of plateau F where there is a dense growth of willows, these are employed directly, without cuttinof them, to construct one important feature o the dike:- First, the long row of posts 54, spaced to -serve like the regular posts 43 in forming the cells, is set as a guide for the length and position of the work. This row also marksthe division line between the level portion built above the natural surface of the ground and the inclined part lying on the bottom of an excavation cut between the level part and the deep vertically disposed independent part V. This inclined part pitches downward toward said` part V and toward the stream, as shown in Fig. 11. The level and inclined portions of the work are carried forward in three sections each consisting of three longitudinal rows of cells: The level section contained within the encompassing binding cables 49,-see Figs. 10 and 12,---`
the upper inclined section is bound therewith by the binding cables 48 and the lower inclined section subjaeent to the part V is encompassed with the other two sections by the larger binding cables 4G.
From the line of posts 54 vtoward the stream the land ,is cleared of timber and brush which are prepared for use in constructing the cells. The encompassing binding cables'are then placed on ther ground among the standing willows and the longitudinal floor poles 17 and 19 placed on said cables; the pits 28 having been previously dug and the weighted anchor-boxeswith the attached cables 22 deposited therein. Then the standing willows and other brush are the growth of brush is sparce or too coarse loose brush or finer fibrous material is added to give the bottom the requisite tightness. The longitudinal central binding poles 18 are now laid and fastened to the poles 19 by the cables 22 disposed through the compacted fioor and the cell structure carried forward as shown, and heretofore described.
Vhen the cells or any part of them in this level section are completed, the excavation for the inclined part may be started and theV removed earth used for the filling 50 in the finished or partly finished cells. The inclination is made as steep as convenient to work on, if the water level is not encountered; in which case the part V may not be carried to greater depth than the lowest part of the incline. The last section of the incline is generally made two stories in height as shown, the top of the whole finished at a less inclination to give heavier work toward the stream. The part V is entirely detached from the subjacent in clined section which abuts against it so that itwill settle vertically and independently if undermined, like the center at A; like which it is constructed except that it is two cells wide and has the central longitudinal partition 6G as heretofore described. V'Vhen all is filled, roofed and the anchor cables 5 attached and secured to the piles 4, the earth covering 51 is applied. The angle between the part V and the bank cutting 37 may be filled with fascines or cell-work as in A, or have the earth filling'GT, as here shown.
To reinforce this dike against the action of a sudden rise of the stream, carrying a heavy ice floe and drift, and to increase the inclined face filling (i7 rather than to allow it and the top of part V to be carried away by the fiood current, the large long cellulated fascine G is placed as shown. It is anchored longitudinally by the cable 5, and laterally at a number of points in its length, by the inclined anchor posts 59 and G0 set deep in the ground crossed and bound together against the fascine by a wire lashing 62 at.
the crossing of the posts. The ground ends of the post-s disposed toward the expected current are lashed securely to a buried cross-log G1 see Fig.- 10. This cellulated fascine resists the first flood action becoming more secure as itself and the space between it and the top of part V rapidly fills with the insinuating mud silt and sand.
The points 8 in Fig. 1 represent eXf ploded mines of some powerful explosive,
placed close enough together to act unitedly and discharged simultaneously to open out a new straight channel through the plateau F as indicated. The dike D, lower end of E and those of 3, 3, 3 and 3, are all substantially the same in `construction and are positioned to protect the banks of and control this newly opened channel.
The dike as applied at D,.E, 3,`etc., is
fully illustrated in detailin Figs. 14E, 15 and 1G, showing most of the construction features heretofore set forth.. As it is applied where the ground water-line is very near the surface, excavations are reduced to the minimum; in some cases only what is required to sink the weighted anchorfboxes 24: generally limited to the single longitudinal row of two-story cells T, on the shore or land edge in like manner as atGr in Figs; 6 and 7 let down as low as possible to form a downward projecting flange or lip to better anchor this edge; andan excavation for the single upstream corner cell L; .and
possibly in some cases for` an intervening end cell, to vassist in anchoring "down the upper end of the dike. And in some cases it is expedient to excavate only half, making the row of cells T alternately one and two stories. Usually only to the extent of this excavation do the parts constructed therein receive the earth `filling A50; Vother-` wise the cells are left to ill with mud silt and sand throughtheir permeable walls `and coverings; unless the conditions require and afford some other weighty filling. Often aA large area of this work is started by laying and linishing the ground fioorduring the summer and fall and covering it with a light dressing of earth to protect` it from fire; during the subsequent winter the work is carried forward to completion before the spring high water period. y
As far as the growth of `willows is ample, the ground floor 58 is constructed of these, uncut, as described above and also shown in Figs. 10 and 1l. On this the excavated earth from T may be piled, as shown at 72, until the cells of this part are made, when the earth is `thrown back into said cells.
Another feature, that can also be combined with the other dikes, is illustrated in Figs. 1, 14 and 15: the superimposed cellulated fascine 7, which is anchored by a single cable attached vto its upstream end. This is constructed where it is shown, toward the river edge of the dike. It may be of large diameter and preferably longerthan the dike.
In serious cases a numberof these are built on, each one independently, in arpile forming a magazine of fascinesthat will rolloiiI into the stream and assist to arrest the erosion immediately the edge of the vcellular structure beneath .them is undermined and sinks down. i
`surface over theadjoining plateau.
In some instances where ordinary suitablel brush are not at hand and the supply of poles and finer materials as corn and cotton stalks, hay, straw, bagasse etc., are'plentiful themoditication illustrated in Fig. 13 is resorted to A line of narrow cells around the outside of the dike are built up on a floor of crosspoles 71.laid close on the longitudinal ground poles 17 and 19 and wire lashed thereto. The superimposed wallpoles 68 are wire-lashed .-29- to the posts 43, scored interlapped and lashed at angles,
and `the cell walls 69 and floors 70, and floor`- of the whole dike, lined with a suitable thickness of said finer materials; and this marginal line of cells filled with the earth `filling 50.
AtE the dikes are repeated in a line of direction agreeing with the angled position of that one at the end of the line on the bank ofthe new channel; extending the work across the plateau F to and across the lake 12 and into the bench-bank 9. This operates conjointly with D, C and B to still the high-water current and cause a heavy flood deposit in the lake and raise the rtliil ie dikes in this line of dikes are separated end from end leaving the embrasures or open spaces 13 between; these serve as driveways in delivering materials on the work during construction and are left open to allow a part of the current to pass through; thus avoiding a too strong deflection of the whole current, an undermining fall over the dike or a destructive eddy below. lf this dike or line of dikes have a sunken anchor portion T, it should be continued under said open spaces or special work be put 1n to prevent the current from cutting down therein. After the flood has nearly subsided and little `further surface lilling of lake or plateau can be gained, the conjunct mines are exploded Vto open out the new channel. And if laid of suflicient magnitude and followed by dredging, and diking` on the stream below, future Hoods or damaging erosions may be avoided. Otherwise the flooding and raising of the surface of the plateau .and operations along the channel may contmue throughout several high-water periods; until the altitude of the plateau and the magnitudeand protection of the banks of the channel are such that floods and erosions do not occur. ln emergencies this work is always advantageously supplemented by the use of cellulated fascines rolled in independently or carried down on running cables attached to heavy box anchors in the bed of the stream. Thefascines 35 are sometimes expediently substituted for the inclined part at C, breaking joints in placing them end to end, employing the anchor boxes and at- .tached cables, encompassing cables 46, i8
and 49, in the manner set forth with the A square cell work, to retain the fascines in position', and finishingwith the same top worltw Lf f' .i
y Any ofthe cellular work described above is supposedfto be added to in height'by building upf'on topf-as it settles away by-being undermined for sinking in soft strata, if, it is found necessary so to do to attain a permanent result.
It :is obvious that the riprapping herein shown and described can be placed on or in any land, according tor conditions, to anticipate the approach of an eroding stream and to control its'iow along desired lines.
I claimh i 1. A riprap cell filled withweighting material and a supplemental weight-anchor attached to said cell. 12. A riprap cell disposed above the surface 'of the ground and a weight-anchor attachedV and sunk beneath said cell.
A permeably walled riprap cell connected by a cable to a dependent weightanchor. Y 1
4;- A riprap cellinclosed by a permeable wall, a-weight-anchor, and' a-cable to connect said anchor to said cell.
5. yAiriprap dike comprising two abutted structures adapted to slide upon each other at their? contact surfaces and settle independently.
" 6. A'riprap dike comprising two abutted structures adapted to support and slide against each otherand settle independently.
riprap dike comprisinga Vvvertically disposed vstructure7 a structure, abutted against VAsaid vertically disposed structure, and said vertically disposed structure adapted to slide' along said abutting structure and settle independently thereagainst.
8. riprap dike comprising a weighted structure, a structure abutted against said weightedstructure, and said weighted structure adapted to slide along the contact surdependently thereof.
9. A riprap dike comprising two independentlyconstructed weighted structures abutted together and'adapted to slide upon Y face of said vabutting structure and settle ineach other and settle independently.
10. A riprap dike'comprising a horizontally extended structurej a vertical structure disposed against the edge of said horizontally extended structure and adapted toslidev thereon and settle independently thereagainst. Y K l 11. Ariprap dike comprising a structure weighted by heavy anchors sunk beneath 1t, a structure abutted against. said weighted i structure, and said weighted structure adapted to settle `independently of said abutting structure. Y
1Q. A riprapdike comprising an inclinedly extended structure, and a contiguous vertical structure adapted to settle independently against the edge of said inclined structure.
13. A riprap dike comprising a cellulated structure built up from the ground surface and anchored by weight-anchors sunk in the ground beneatl 14. A riprap dike comprising a cellulated structure, weight-anchors attached and sunk beneath said cellulated structure, and an independent structure abutted against said cellulated anchored structure.
' 15. A riprap dike comprising a cellulated structure, weighting materials 1n the cells of said structure, and weight-anchors sunk beneath and attached to said structure.
16. A riprap dike comprising a Verti cally disposed structure, and a subjacent laterally extended mattress structure having one edge abutted against to support said vertical y disposed structure.
, 17. A riprap dike comprising a vertically disposed cellulated structure, weighting materials in the cells of said structure, and an inclined cellular structure abutted against said vertical structure but not attached thereto.
18. A riprap dike comprising a cellula-ted structure having weighting materials in the cells thereof and a subjacent structure abutted against said cellulated structure.
19. A riprap dike comprising a vertically disposed structure, and a subjacent inclined laterally extended mattress structure abutted against said vertically disposed structure.
' 20. A riprap dike comprising a laterally extended structure having an integral downwardly extended smaller portion embedded in. the earth below to anchor said structure.
21. A riprap dike comprising a structure having a downward extension embedded in the earth below said structure, and an attached weight-anchor suspended in a pit beneath said extension.
23. A riprap dike comprising a fiat cellulated structure having anintegral downwardly projected cell built in a pit. below the general structure and filled with earth or other weighting material to anchor said dike.
24. A riprap dike comprising a structure having an integral downwardly projected part embedded below the general structure and an attached weight-anchor disposed below said embedded part.
25. A riprap dike comprising a cellulated structure having an integral portion containing an additional lower story embedded in the ground to anchor said dike.
26. A floor tor cellulated riprap dikes,
Cri
consisting of poles disposed parallelly and post fastened centrally to said diagonal pole.4
Q8. In a storied cellular riprap dike having walls of librous materials, a retaining frame comprising longitudinal side-poles, cross-poles fastened across said side-poles, tall posts fastened in anglesbetween crosspolesand side-poles, diagonal poles fastened o-n said cross-poles and side-poles across the angles opposite to said tall posts, and short posts fastened centrally to said diagonal poles.
29. A cellular riprap dike bottom, comprising side bottom-poles and a central bottom-pole, cross-poles fastened on said central and` side bottom-poles, posts fastened y in angles between cross-poles and.. side bottompoles, diagonal poles fastened `to said side bottom-poles and cross-poles across the angle opposite to said posts, other posts fastened centrally to said diagonal poles, a layer of fibrousmaterial laid across said central and side bottom-poles, and a central binding-pole disposed on said layer ofiibrous material and fastened therethroughto said central bottom-pole.
30. In a riprap dike, the combination of top and bottom pole members, a cable disposed vertically through the dike and made fast to said top and bottom members, and a` weight-anchor disposed beneath the dike and made fast to the lower end of said cable.
3l. A sub-anchor for riprap dikes, comprising a heavy body disposed in an excavation beneath the dike and connected by a cable fastened to said heavy body and to the structure of the dike.
32. A dike having an anchored edge, a binding cable disposed to laterally embrace the whole dike including said anchored edge, and a binding cable to laterally embrace only a part ofthe dike including said anchored edge.
33. A dike having binding cables of different lengths disposed to secure together different quantities ofthe dike and all of said binding cables disposed to embrace a selected portion of said dike.
34. In an anticipatory riprap, the combination with a riprap dike of a superimposed fascine adapted to be launched by rolling oif from the dike when the edge of the dike is undermined and settles down.
35. In an anticipatoryriprap the combination of ,a dike having a head edge projecting above the surface of the ground, a fascine disposed on said ground surface parallel with said edge and a distance away toward the anticipated flood and there anchored securely.
36. An anchorage to secure a fascine lying above the surface of the ground, consisting of an inclined post having its base fastened to a buried cross-log and its top above the fascine crossed with and fastened to a post set on the opposite side of said fascine.
' 37. A long. low-land dike having narrow cross-openings for driveways and to let pass through a small portion of the flood.
38. A long Acontinuous dike constructed `partly above and partly below the surface of the ground, the portion above the ground transversely cut to leave narrow7 embrasures between merlons of greater length.
39. The method of opening and controlling a new course for a stream, consisting in disposing anticipatory riprap dikes along theproposed lines `of banks for said new course, and then discharging an intermediate line of conjunct explosive mines to open out the new channel.
40. A method of anticipatory riprapping, consisting in forming and protecting new banks along a predetermined course for a stream by building riprap dikes in excavations made in the high land to arrest the erosions and form and protect the new banks therein, and building riprap dikes above the surface of the low land to raise said new banks thereon by flood deposits.
41. A method of anticipatory riprapping consisting in forming and protecting new banks along a predetermined course for a stream by building riprap dikes in excavations made in the high land to arrest the erosions and form and protect the new banks therein and building ripr'ap dikes above the surface of the low land to raise new banks thereon by flood deposits and to protect said new banks and extending said low -land dikes out from said predetermined course across contiguous low land to raise the surface thereof by flood deposits.
42. The method of depositing anticipatory cellulated riprap dikes in high land or banks, consisting in excavating for a small lower part of the structure, building up the cells in this first excavated part, and filling and burying the cells with the earth from excavation for space to further extend said cell structure as fast as said cells are built up filled and closed.
4:3. The art of construct-ing and placing dikes for `riprapping the banks of streams, consisting in extending part of the dike structure out from the bank onto the ice of a stream, setting piles through perforations through the ice to form part of the structure into said bank, and extending said structure and control the slnklng thereof, and bulld- Wlth sald lllng lnto sald eXcavatlon. 1a lng up the dlke structure as 1t settles wlth In testnnony whereof I ax my slgnature the hrokenfce Support beneath t.- in presence of two witnesses.
44. The art of rprapping high banks of 4 DAVID NEALE. streams, consisting in starting a cellulated Ttnessesz structure on the stream ice close to said MARION O. V'ILLSON,
bank, filling said `cells from an excavation l' F. R. KLINE.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
US47529109A US932565A (en) | 1909-01-30 | 1909-01-30 | Anticipatory riprap-dikes. |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
US47529109A US932565A (en) | 1909-01-30 | 1909-01-30 | Anticipatory riprap-dikes. |
Publications (1)
Publication Number | Publication Date |
---|---|
US932565A true US932565A (en) | 1909-08-31 |
Family
ID=3000988
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
US47529109A Expired - Lifetime US932565A (en) | 1909-01-30 | 1909-01-30 | Anticipatory riprap-dikes. |
Country Status (1)
Country | Link |
---|---|
US (1) | US932565A (en) |
-
1909
- 1909-01-30 US US47529109A patent/US932565A/en not_active Expired - Lifetime
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US4045965A (en) | Quay structure | |
Etcheverry | Irrigation Practice and Engineering... | |
US3465530A (en) | Dam construction | |
US2466343A (en) | Jetty | |
US932565A (en) | Anticipatory riprap-dikes. | |
US1083289A (en) | Method of building concrete dock-walls. | |
US855584A (en) | Anchor-revetment for shores or banks. | |
RU81505U1 (en) | UNDERWATER TRANSPORT TUNNEL SYSTEM | |
GB2159863A (en) | Flexible wall dams | |
US864481A (en) | Wing-dam or dike construction for riprap. | |
US699729A (en) | System of submarine construction. | |
US1394571A (en) | Subaqueous structure and method | |
US5118222A (en) | Method and apparatus for constructing seawalls and docks | |
US1900341A (en) | Means for protecting earthen dams, river levees, etc. | |
US2435568A (en) | Method of and means for protecting river banks | |
US517879A (en) | Mattress for riprap | |
US2338110A (en) | Graving dry dock and method of construction | |
IL34532A (en) | System for the deepening of the bottom in front of moles and retaining walls of marine and river installations and the re-inforced moles so obtained | |
US1444622A (en) | John a | |
US1006247A (en) | Dock construction and method of constructing docks. | |
US426807A (en) | Wire riprap and jetty work | |
Haas et al. | Bank stabilization by revetments and dikes | |
US400804A (en) | Sub-river tunnel | |
HAIGH | THE EMERSON BARRAGE. | |
US419237A (en) | Jetty |