US20120310697A1 - Variance management - Google Patents
Variance management Download PDFInfo
- Publication number
- US20120310697A1 US20120310697A1 US13/588,698 US201213588698A US2012310697A1 US 20120310697 A1 US20120310697 A1 US 20120310697A1 US 201213588698 A US201213588698 A US 201213588698A US 2012310697 A1 US2012310697 A1 US 2012310697A1
- Authority
- US
- United States
- Prior art keywords
- project
- variance
- tasks
- task
- estimates
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Abandoned
Links
Images
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0631—Resource planning, allocation, distributing or scheduling for enterprises or organisations
- G06Q10/06312—Adjustment or analysis of established resource schedule, e.g. resource or task levelling, or dynamic rescheduling
Definitions
- the present disclosure relates generally to determining and managing variances in project development life cycles by using updated and/or newly available information to reduce the variance in estimates.
- a project life cycle is an ongoing process, in which subtasks complete and new information surfaces.
- Current approaches e.g., COCOMO II, SLIM, SEER, Price-S
- COCOMO II, SLIM, SEER, Price-S do not systematically update their estimates based on ongoing availability of information, nor do they actively reflect on the changes in variance that such updates provide.
- COCOMO II, SLIM, SEER, Price-S do not systematically update their estimates based on ongoing availability of information, nor do they actively reflect on the changes in variance that such updates provide.
- a method of determining estimation variance associated with project planning may comprise obtaining information associated with a project.
- the project may comprise a plurality of tasks.
- the method may further include determining initial estimates and estimate variances of the plurality of tasks from the information, and obtaining actual measurements associated with a selected task from the plurality of tasks after said selected task is executed.
- the method may also include computing a difference between an initial estimate associated with the selected task and the actual measurements.
- the method may yet further include revising using the computed difference the initial estimates of remaining one or more tasks, and determining estimate variances of said remaining one or more tasks based on the revised estimates.
- a method of determining estimation variance associated with project planning may comprise identifying a plurality of phases associated with a project, determining an initial estimate and variance associated with completing each of the plurality of phases. For each of the plurality of phases, the method may further include collecting actual measurements from one or more tasks executed as part of performing said each phase. The method may also include revising estimates and variances associated with completing rest of the plurality of phases based on the actual measurements, and determining an estimate and variance for the project based on the revised estimates.
- a system for determining estimation variance associated with project planning may comprise a processor operable to identify a plurality of tasks associated with a project and determine an initial estimate associated with completing each of the plurality of task.
- the processor is further operable to collect actual measurements resulting from executing one or more of the plurality of tasks and to revise one or more initial estimates associated with rest of the plurality of tasks not yet executed, based on the actual measurements.
- the processor is further operable to determine estimation and variance of the project based on the revised estimates.
- a program storage device readable by a machine, tangibly embodying a program of instructions executable by the machine to perform above methods of determining estimation variance associated with project planning may be also provided.
- FIG. 1 is a flow diagram illustrating a method in one embodiment of the present disclosure for determining and managing the variance of an estimate on a product or project.
- FIG. 2 illustrates leveraging new information that becomes available in a typical development project in one embodiment of the present disclosure.
- a method and system for determining and managing the variance of project estimates are provided.
- the method and system of the present disclosure in one embodiment provide a way of computing the variance and managing the variance through the course of the project. Estimates are treated as random variables rather than discrete values, and are actively managed across the lifecycle of the project, rather than simply being computed at the beginning and referred to later in a static manner. Although the current description is specific to software development, the method is applicable to all kinds of project management and the description is not meant to suggest limitations to this applicability.
- Variance of a statistical estimate is computed as the average deviation of an estimate from its estimated mean. Variance for an estimate, thus, is a measure of uncertainty in the estimation. The variance may be equated to the risk associated with the project. Variance management is synonymous to management of risk associated with the project.
- the method and system of the present disclosure in one embodiment provides the estimation of mean and the associated variance not only during the planning phase of the project but also after completion of each task in the project.
- FIG. 1 is a flow diagram illustrating a method for determining and managing the variance of effort estimates on a project.
- a project starts with an initial planning activity.
- Information associated with the project is obtained.
- the information may include cost information, duration of the project or project schedule, as itemized or categorized into different tasks or phases, actual data associated with one or more past projects, including projects that produced prior releases of the same product as the current project, information related to projects that are similar to the project, etc.
- Projects that are similar may be, for example, of the same or similar type, those having a number of common tasks, etc.
- the waterfall model is a sequential process for the creation of software, in which development is seen as flowing steadily downwards like a waterfall through the phases of requirements analysis, design, implementation, testing, integration, and maintenance.
- the application is developed incrementally in short cycles. Each cycle may contain activities for requirement analysis, software design, implementation and testing.
- the effort may be estimated for each task in the project, as well as for any phases and the project itself. There are many ways to create such estimates, such as using actual duration or complexity of a similar task based on past data.
- an available task is selected from the set of tasks comprising the project and the selected task is performed.
- the actual effort required to complete the task is gathered. Further, new information associated with this completed or executed task may be gathered. This new information can be used to compute new estimates, which can take advantage of that new data to be more precise, resulting in smaller variances for the subsequent tasks.
- Step 110 determines whether more tasks remain. If so, at step 112 the actual information gathered at step 108 is used to create new estimates for all of the remaining tasks, as well as any remaining phases and the project as a whole. The procedure returns to step 106 and continues in this manner until the project is complete.
- Nominal estimate for Variance on the Task # schedule estimated schedule 1 1a 3.0 months 0.75 month ⁇ circumflex over ( ) ⁇ 2 1b 5.0 months 0.25 month ⁇ circumflex over ( ) ⁇ 2 8.0 months 1.86 month ⁇ circumflex over ( ) ⁇ 2
- task 1 a has nominal value of 3, upper bound of 5.1213, and lower bound of 0.8787.
- Task 1 b has nominal value of 5, upper bound of 6.225, and lower bound of 3.775. This yields an overall estimate on task 1 of 8.0 months, with a variance of 1.86 mont ⁇ 2.
- Variance appears as mont ⁇ 2 (month squared) because for a triangular distribution with lower bound L, nominal N, and upper bound U, the variance is computed as ((U ⁇ N) ⁇ 2+(N ⁇ L) ⁇ 2+(U ⁇ N)(N ⁇ L))/18, as known to a person of ordinary skill in probability theory and statistics.
- This information can be determined via automatic examination of task properties, or it can be provided by the user. Given the information, we can use the information regarding the actual length of task 1 a to update our expectation as to how long 1 b will take. For instance, task 1 a took 2.2 months, but was estimated at 3.0 months. Task 1 b is estimated at 5.0 months. Because it is similar to 1 a, we could scale this estimate by 2.2/3.0, which would give an estimate of 3.67 months. The scaling can also take variance into account. For example, the standard deviation of task 1 a is 0.8660 (the square root of the variance). This means that the one standard deviation range of the expected value for completing the task goes from 2.134 to 3.866.
- the variance management approach described above leverages different kinds of information that can be used to improve estimates as the project proceeds. This information becomes available at different stages of the project life cycle.
- One example is the monitored difference between previous estimations and ongoing actual values in order to progressively reduce the variance in estimates of future tasks, phases, or the project as a whole.
- an estimate is treated as an artifact that goes through different states in its lifecycle with its variance continuously changing or reducing as more information becomes available.
- a project may be classified into different phases such as inception, elaboration, construction and transition as shown at 202 .
- Each phase may in turn have one or more tasks associated with it, for example, model, implementation, test, deployment configuration management, project management, environment, shown in FIG. 2 .
- the phases may be further broken down into iterations, as shown at 204 .
- the construction phase 212 includes C 1 and C 2 iterations.
- the Transition phase 214 includes T 1 and T 2 iterations.
- the transition between different phases and iterations may be referred to as gates. At each gate, estimation may be performed or updated.
- New information may be new or revised design documents, requirements documents, information about defects discovered during the running of the task, etc. This information may be used to further revise estimates for the remaining tasks and the entire project plan. For instance, a revised design document could mean different resources needed for the next task, for example, the implementation task of that design.
- upstream artifacts such as requirements and initial models may be used to predict the estimation for the entire project as shown in 208 .
- new information such as design artifacts that become available may be used to revise the estimates for the remaining tasks (e.g., construction and transition) and the entire project plan as shown in 210 .
- more new information such as design and code artifacts that become available may be used again to revise the estimates for the remaining tasks (e.g., transition) and the entire project plan, as shown in 212 .
- transition phase shown in 214
- code and test artifacts that become available may be used to further revise the estimates.
- the method and system of the present disclosure may be used to determine estimation and variance on any other parameters associated with project or product planning. Examples include, but are not limited to, cost, quality, resources needed, profit, revenue, or any other parameters or attributes that affect project planning. Further, while the above examples showed determining estimation and variances of projects divided into tasks, subtasks and phases, the method and system of the present disclosure may perform estimation and determine variances at any level of granularity in the project.
- aspects of the present disclosure may be embodied as a program, software, or computer instructions embodied in a computer or machine usable or readable medium, which causes the computer or machine to perform the steps of the method when executed on the computer, processor, and/or machine.
- the system and method of the present disclosure may be implemented and run on a general-purpose computer or computer system.
- the computer system may be any type of known or will be known systems and may typically include a processor, memory device, a storage device, input/output devices, internal buses, and/or a communications interface for communicating with other computer systems in conjunction with communication hardware and software, etc.
- the terms “computer system” and “computer network” as may be used in the present application may include a variety of combinations of fixed and/or portable computer hardware, software, peripherals, and storage devices.
- the computer system may include a plurality of individual components that are networked or otherwise linked to perform collaboratively, or may include one or more stand-alone components.
- the hardware and software components of the computer system of the present application may include and may be included within fixed and portable devices such as desktop, laptop, and/or server.
- a module may be a component of a device, software, program, or system that implements some “functionality”, which can be embodied as software, hardware, firmware, electronic circuitry, or etc.
Landscapes
- Business, Economics & Management (AREA)
- Human Resources & Organizations (AREA)
- Engineering & Computer Science (AREA)
- Strategic Management (AREA)
- Economics (AREA)
- Entrepreneurship & Innovation (AREA)
- Educational Administration (AREA)
- Game Theory and Decision Science (AREA)
- Development Economics (AREA)
- Marketing (AREA)
- Operations Research (AREA)
- Quality & Reliability (AREA)
- Tourism & Hospitality (AREA)
- Physics & Mathematics (AREA)
- General Business, Economics & Management (AREA)
- General Physics & Mathematics (AREA)
- Theoretical Computer Science (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
- Stored Programmes (AREA)
Abstract
Method and system for determining estimation variance associated with project planning are provided. In one aspect, information associated with a project is obtained and initial estimations for the tasks in the project are determined using available information. The tasks are performed and actual measurements are obtained from the completed tasks. The actual measurements are used to revise the estimates of the remaining tasks. The revised estimates are used to compute a project level estimate and a variance on that estimate, and to enable better project management.
Description
- This application is a divisional of U.S. patent application Ser. No. 12/130,674 filed on May 30, 2008, which is related to U.S. patent application Ser. No. 12/039,415, filed on Mar. 4, 2008, entitled “Risk Reduction” (Attorney Docket No. YOR920070218US1 (21127)), having a common assignee, the entire contents of each of which are incorporated herein by reference.
- The present disclosure relates generally to determining and managing variances in project development life cycles by using updated and/or newly available information to reduce the variance in estimates.
- Accurate estimation of project parameters such as cost, schedule, or quality is an invaluable asset to a business. Estimating project parameters fairly accurately saves company's time, money, and enhances the company's goodwill and relationship with its customers. However, it is not an easy task to estimate an overall cost, schedule or quality of a project, especially a complex project involving multiple phases and components that depend on and/or interact with another.
- A project life cycle is an ongoing process, in which subtasks complete and new information surfaces. Current approaches (e.g., COCOMO II, SLIM, SEER, Price-S) do not systematically update their estimates based on ongoing availability of information, nor do they actively reflect on the changes in variance that such updates provide. In sum, there is an inability to reflect on or consider the variance in the estimates and manage it effectively using new or updated information that becomes available as the project proceeds.
- Method, system and program storage device having instructions executable on a machine for determining estimation variance associated with project planning are provided. A method of determining estimation variance associated with project planning, in one aspect, may comprise obtaining information associated with a project. The project may comprise a plurality of tasks. The method may further include determining initial estimates and estimate variances of the plurality of tasks from the information, and obtaining actual measurements associated with a selected task from the plurality of tasks after said selected task is executed. The method may also include computing a difference between an initial estimate associated with the selected task and the actual measurements. The method may yet further include revising using the computed difference the initial estimates of remaining one or more tasks, and determining estimate variances of said remaining one or more tasks based on the revised estimates.
- In another aspect, a method of determining estimation variance associated with project planning may comprise identifying a plurality of phases associated with a project, determining an initial estimate and variance associated with completing each of the plurality of phases. For each of the plurality of phases, the method may further include collecting actual measurements from one or more tasks executed as part of performing said each phase. The method may also include revising estimates and variances associated with completing rest of the plurality of phases based on the actual measurements, and determining an estimate and variance for the project based on the revised estimates.
- A system for determining estimation variance associated with project planning, in one aspect, may comprise a processor operable to identify a plurality of tasks associated with a project and determine an initial estimate associated with completing each of the plurality of task. The processor is further operable to collect actual measurements resulting from executing one or more of the plurality of tasks and to revise one or more initial estimates associated with rest of the plurality of tasks not yet executed, based on the actual measurements. The processor is further operable to determine estimation and variance of the project based on the revised estimates.
- A program storage device readable by a machine, tangibly embodying a program of instructions executable by the machine to perform above methods of determining estimation variance associated with project planning may be also provided.
- Further features as well as the structure and operation of various embodiments are described in detail below with reference to the accompanying drawings. In the drawings, like reference numbers indicate identical or functionally similar elements.
-
FIG. 1 is a flow diagram illustrating a method in one embodiment of the present disclosure for determining and managing the variance of an estimate on a product or project. -
FIG. 2 illustrates leveraging new information that becomes available in a typical development project in one embodiment of the present disclosure. - A method and system for determining and managing the variance of project estimates are provided. The method and system of the present disclosure in one embodiment provide a way of computing the variance and managing the variance through the course of the project. Estimates are treated as random variables rather than discrete values, and are actively managed across the lifecycle of the project, rather than simply being computed at the beginning and referred to later in a static manner. Although the current description is specific to software development, the method is applicable to all kinds of project management and the description is not meant to suggest limitations to this applicability. Variance of a statistical estimate is computed as the average deviation of an estimate from its estimated mean. Variance for an estimate, thus, is a measure of uncertainty in the estimation. The variance may be equated to the risk associated with the project. Variance management is synonymous to management of risk associated with the project. The method and system of the present disclosure in one embodiment provides the estimation of mean and the associated variance not only during the planning phase of the project but also after completion of each task in the project.
-
FIG. 1 is a flow diagram illustrating a method for determining and managing the variance of effort estimates on a project. A project starts with an initial planning activity. Information associated with the project is obtained. The information may include cost information, duration of the project or project schedule, as itemized or categorized into different tasks or phases, actual data associated with one or more past projects, including projects that produced prior releases of the same product as the current project, information related to projects that are similar to the project, etc. Projects that are similar may be, for example, of the same or similar type, those having a number of common tasks, etc. - At 102, depending on the type of development cycle (e.g., agile or iterative, waterfall, etc.) the project is divided into various phases and tasks within the phases. Briefly, the waterfall model is a sequential process for the creation of software, in which development is seen as flowing steadily downwards like a waterfall through the phases of requirements analysis, design, implementation, testing, integration, and maintenance. In contrast, in an iterative software development process the application is developed incrementally in short cycles. Each cycle may contain activities for requirement analysis, software design, implementation and testing.
- At 104, the effort may be estimated for each task in the project, as well as for any phases and the project itself. There are many ways to create such estimates, such as using actual duration or complexity of a similar task based on past data.
- At
step 106, an available task is selected from the set of tasks comprising the project and the selected task is performed. Atstep 108, the actual effort required to complete the task is gathered. Further, new information associated with this completed or executed task may be gathered. This new information can be used to compute new estimates, which can take advantage of that new data to be more precise, resulting in smaller variances for the subsequent tasks. -
Step 110 determines whether more tasks remain. If so, atstep 112 the actual information gathered atstep 108 is used to create new estimates for all of the remaining tasks, as well as any remaining phases and the project as a whole. The procedure returns tostep 106 and continues in this manner until the project is complete. - As an example, consider a task that has subtasks tasks, as shown in the table below.
-
Nominal estimate for Variance on the Task # schedule estimated schedule 1 1a 3.0 months 0.75 month{circumflex over ( )}2 1b 5.0 months 0.25 month{circumflex over ( )}2 8.0 months 1.86 month{circumflex over ( )}2 - For simplicity sake, we assume that the distribution on both tasks 1 a and 1 b is a triangular distribution, and that they are both symmetric. As known to a person of ordinary skill in probability theory and statistics, a triangular distribution refers to a continuous probability distribution with lower limit L, a mode or nominal value N, and upper limit U, where U>L, and L<=N<=U. In this example, task 1 a has nominal value of 3, upper bound of 5.1213, and lower bound of 0.8787. Task 1 b has nominal value of 5, upper bound of 6.225, and lower bound of 3.775. This yields an overall estimate on
task 1 of 8.0 months, with a variance of 1.86 montĥ2. Variance appears as montĥ2 (month squared) because for a triangular distribution with lower bound L, nominal N, and upper bound U, the variance is computed as ((U−N)̂2+(N−L)̂2+(U−N)(N−L))/18, as known to a person of ordinary skill in probability theory and statistics. - In the above example, if task 1 a is completed in 2.2 months, we can now update the estimate for
task 1 taking into account this new information. There are several methods for doing this; one method is to use the known value of 2.2 months in conjunction with the estimate for 1 b. This will give an updated time fortask 1 of 7.2 months with a variance of 0.25 montĥ2 (the variance remaining comes solely from 1 b, as we now know the actual value for 1 a, that is, variance associated withtask 1 is zero). Techniques also exist for updating the estimates of future tasks using the actual values from similar tasks that have been completed. This will then allow us to update the overall task in a more sophisticated way. As an example, suppose that task 1 b was known to be similar in content and complexity to task 1 a. This information can be determined via automatic examination of task properties, or it can be provided by the user. Given the information, we can use the information regarding the actual length of task 1 a to update our expectation as to how long 1 b will take. For instance, task 1 a took 2.2 months, but was estimated at 3.0 months. Task 1 b is estimated at 5.0 months. Because it is similar to 1 a, we could scale this estimate by 2.2/3.0, which would give an estimate of 3.67 months. The scaling can also take variance into account. For example, the standard deviation of task 1 a is 0.8660 (the square root of the variance). This means that the one standard deviation range of the expected value for completing the task goes from 2.134 to 3.866. We could use this information to determine scaling for task 1 b, whose range for one standard deviation goes from 4.5 to 5.5. Because the low end of task 1 a is 2.134, and it came in at 2.2, we could scale from the low end of task 1 b as follows: 4.5 * 2.2/2.134. This gives an estimate for task 1 b of 4.64. We have presented two examples of scaling, but techniques such as this can be combined to rely on multiple factors and multiple actual values. - The variance management approach described above leverages different kinds of information that can be used to improve estimates as the project proceeds. This information becomes available at different stages of the project life cycle. One example is the monitored difference between previous estimations and ongoing actual values in order to progressively reduce the variance in estimates of future tasks, phases, or the project as a whole. In one embodiment, an estimate is treated as an artifact that goes through different states in its lifecycle with its variance continuously changing or reducing as more information becomes available.
- This approach allows for better management of resources, increased value delivery and reduction of risks.
- In addition to more information such as actual values becoming available as tasks get completed, new information can also be extracted from artifacts that get created. Some examples of artifacts that get created on completion of tasks may include, but are not limited to, requirements documents, design documents, source code, etc. Such information can further help in variance management. We consider design models as an example. Teams creating systems frequently build models that describe the design of the system. Furthermore, these models are often built using common design patterns. Given a design model, we can extract information and patterns from it that can be compared with the models of known completed projects whose actual development times are known. We can gather information from the projects that have similar models and patterns. This information can then be used in a way similar to the task scaling approach outlined on the previous page to refine estimates and their variances.
FIG. 2 illustrates leveraging new information that becomes available in a typical development project. A project may be classified into different phases such as inception, elaboration, construction and transition as shown at 202. Each phase may in turn have one or more tasks associated with it, for example, model, implementation, test, deployment configuration management, project management, environment, shown inFIG. 2 . The phases may be further broken down into iterations, as shown at 204. For example, theconstruction phase 212 includes C1 and C2 iterations. TheTransition phase 214 includes T1 and T2 iterations. The transition between different phases and iterations may be referred to as gates. At each gate, estimation may be performed or updated. As each discrete task actually completes, new information is collected, new artifacts are available, and new estimates can be computed based on the new information shown at 206. New information may be new or revised design documents, requirements documents, information about defects discovered during the running of the task, etc. This information may be used to further revise estimates for the remaining tasks and the entire project plan. For instance, a revised design document could mean different resources needed for the next task, for example, the implementation task of that design. - At inception stage of the project, upstream artifacts such as requirements and initial models may be used to predict the estimation for the entire project as shown in 208. At elaboration phase of the project, new information such as design artifacts that become available may be used to revise the estimates for the remaining tasks (e.g., construction and transition) and the entire project plan as shown in 210. Similarly, at construction phase of the project, more new information such as design and code artifacts that become available may be used again to revise the estimates for the remaining tasks (e.g., transition) and the entire project plan, as shown in 212. At transition phase (shown in 214) of the project, code and test artifacts that become available may be used to further revise the estimates.
- While the above examples showed determining estimation and variance in relation to project effort, the method and system of the present disclosure may be used to determine estimation and variance on any other parameters associated with project or product planning. Examples include, but are not limited to, cost, quality, resources needed, profit, revenue, or any other parameters or attributes that affect project planning. Further, while the above examples showed determining estimation and variances of projects divided into tasks, subtasks and phases, the method and system of the present disclosure may perform estimation and determine variances at any level of granularity in the project.
- Various aspects of the present disclosure may be embodied as a program, software, or computer instructions embodied in a computer or machine usable or readable medium, which causes the computer or machine to perform the steps of the method when executed on the computer, processor, and/or machine.
- The system and method of the present disclosure may be implemented and run on a general-purpose computer or computer system. The computer system may be any type of known or will be known systems and may typically include a processor, memory device, a storage device, input/output devices, internal buses, and/or a communications interface for communicating with other computer systems in conjunction with communication hardware and software, etc.
- The terms “computer system” and “computer network” as may be used in the present application may include a variety of combinations of fixed and/or portable computer hardware, software, peripherals, and storage devices. The computer system may include a plurality of individual components that are networked or otherwise linked to perform collaboratively, or may include one or more stand-alone components. The hardware and software components of the computer system of the present application may include and may be included within fixed and portable devices such as desktop, laptop, and/or server. A module may be a component of a device, software, program, or system that implements some “functionality”, which can be embodied as software, hardware, firmware, electronic circuitry, or etc.
- The embodiments described above are illustrative examples and it should not be construed that the present invention is limited to these particular embodiments. Thus, various changes and modifications may be effected by one skilled in the art without departing from the spirit or scope of the invention as defined in the appended claims.
Claims (3)
1. A computer-implemented method of determining estimation variance associated with project planning, comprising:
identifying a plurality of phases associated with a project;
determining an initial estimate and variance associated with completing each of the plurality of phases;
for each of the plurality of phases, collecting actual measurements from one or more tasks executed as part of performing said each phase;
revising estimates and variances associated with completing rest of the plurality of phases based on the actual measurements; and
determining an estimate and variance for the project based on the revised estimates.
2. The method of claim 1 , wherein the step of collecting actual measurements further includes:
collecting new information that becomes available as a result of executing said one or more tasks.
3. The method of claim 2 , wherein the new information includes one or more tangible artifact produced during the execution of said one or more tasks.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
US13/588,698 US20120310697A1 (en) | 2008-05-30 | 2012-08-17 | Variance management |
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
US12/130,674 US8781869B2 (en) | 2008-05-30 | 2008-05-30 | Determining estimation variance associated with project planning |
US13/588,698 US20120310697A1 (en) | 2008-05-30 | 2012-08-17 | Variance management |
Related Parent Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
US12/130,674 Division US8781869B2 (en) | 2008-05-30 | 2008-05-30 | Determining estimation variance associated with project planning |
Publications (1)
Publication Number | Publication Date |
---|---|
US20120310697A1 true US20120310697A1 (en) | 2012-12-06 |
Family
ID=41380897
Family Applications (2)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
US12/130,674 Expired - Fee Related US8781869B2 (en) | 2008-05-30 | 2008-05-30 | Determining estimation variance associated with project planning |
US13/588,698 Abandoned US20120310697A1 (en) | 2008-05-30 | 2012-08-17 | Variance management |
Family Applications Before (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
US12/130,674 Expired - Fee Related US8781869B2 (en) | 2008-05-30 | 2008-05-30 | Determining estimation variance associated with project planning |
Country Status (1)
Country | Link |
---|---|
US (2) | US8781869B2 (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103914755A (en) * | 2014-03-18 | 2014-07-09 | 北京农业信息技术研究中心 | Method and system for determining spatial scales of field investigation and field management |
US20160004982A1 (en) * | 2014-07-03 | 2016-01-07 | International Business Machines Corporation | Method and system for estimating the progress and completion of a project based on a bayesian network |
Families Citing this family (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102598073B (en) * | 2009-09-16 | 2014-10-08 | 拉尔斯·福斯伯格 | A system and a method for motivating and/or prompting persons to wash hands |
US20130218625A1 (en) * | 2012-02-22 | 2013-08-22 | International Business Machines Corporation | Utilizing historic projects to estimate a new project schedule based on user provided high level parameters |
US9679249B2 (en) * | 2013-11-19 | 2017-06-13 | Bank Of America Corporation | Dynamic risk evaluation for proposed information technology projects |
US9575799B2 (en) * | 2014-07-11 | 2017-02-21 | International Business Machines Corporation | Task association analysis in application maintenance service delivery |
WO2017037677A1 (en) * | 2015-09-04 | 2017-03-09 | Werklund Ventures Ltd. | Electronic communications and data storage systems and processes for industrial projects |
US20190026663A1 (en) * | 2017-07-20 | 2019-01-24 | Ca, Inc. | Inferring time estimates in workflow tracking systems |
US20240330804A1 (en) * | 2023-03-27 | 2024-10-03 | Sam Prudhomme | System and method for organizing, processing, and accessing a database |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20040111306A1 (en) * | 2002-12-09 | 2004-06-10 | Hitachi, Ltd. | Project assessment system and method |
US20040148209A1 (en) * | 2003-01-28 | 2004-07-29 | Church David E. | System and method for producing an infrastructure project estimate for information technology |
US20050021384A1 (en) * | 2002-12-02 | 2005-01-27 | Pershing Investments, Llc | Capacity planning method and system with approved accuracy and confidence indication |
US20050234758A1 (en) * | 2004-04-15 | 2005-10-20 | Matsushita Electric Industrial Co., Ltd. | Task progress management method, task progress management device and program |
US20080243575A1 (en) * | 2007-03-30 | 2008-10-02 | Keith Weinberger | System and Method for Dynamically Allocating Human Resources to a Project Plan |
US7908167B1 (en) * | 2006-07-26 | 2011-03-15 | Sprint Communications Company L.P. | System and method for analysis of project variances |
US8155996B1 (en) * | 2008-03-06 | 2012-04-10 | Sprint Communications Company L.P. | System and method for customer care complexity model |
US8280756B1 (en) * | 2005-08-03 | 2012-10-02 | Sprint Communications Company L.P. | Milestone initial scheduling |
Family Cites Families (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CA2228574A1 (en) * | 1997-06-05 | 1999-08-02 | Attention Control Systems, Inc. | An automatic planning and cueing system and method |
US6037945A (en) * | 1997-12-16 | 2000-03-14 | Xactware, Inc. | Graphical method for modeling and estimating construction costs |
US7212986B1 (en) * | 1999-06-16 | 2007-05-01 | Metier, Ltd. | Method and apparatus for planning and monitoring multiple tasks based on user defined criteria and predictive ability |
US7062449B1 (en) * | 1999-06-16 | 2006-06-13 | Metier Ltd. | Method and apparatus for planning and monitoring multiple tasks based on user defined criteria and predictive ability and for automatically detecting task related work |
US6606546B2 (en) * | 1999-12-01 | 2003-08-12 | Sinex Holdings, Llc | Aircraft maintenance program manager |
US20020082889A1 (en) * | 2000-12-20 | 2002-06-27 | Electronic Data Systems Corporation | System and method for project management and assessment |
US7324954B2 (en) * | 2001-06-29 | 2008-01-29 | International Business Machines Corporation | System and method for organizational risk based on personnel planning factors |
US20030229618A1 (en) * | 2002-05-14 | 2003-12-11 | Deborah Judy | System and method for project tracking and reporting |
-
2008
- 2008-05-30 US US12/130,674 patent/US8781869B2/en not_active Expired - Fee Related
-
2012
- 2012-08-17 US US13/588,698 patent/US20120310697A1/en not_active Abandoned
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20050021384A1 (en) * | 2002-12-02 | 2005-01-27 | Pershing Investments, Llc | Capacity planning method and system with approved accuracy and confidence indication |
US20040111306A1 (en) * | 2002-12-09 | 2004-06-10 | Hitachi, Ltd. | Project assessment system and method |
US20040148209A1 (en) * | 2003-01-28 | 2004-07-29 | Church David E. | System and method for producing an infrastructure project estimate for information technology |
US20050234758A1 (en) * | 2004-04-15 | 2005-10-20 | Matsushita Electric Industrial Co., Ltd. | Task progress management method, task progress management device and program |
US8280756B1 (en) * | 2005-08-03 | 2012-10-02 | Sprint Communications Company L.P. | Milestone initial scheduling |
US7908167B1 (en) * | 2006-07-26 | 2011-03-15 | Sprint Communications Company L.P. | System and method for analysis of project variances |
US20080243575A1 (en) * | 2007-03-30 | 2008-10-02 | Keith Weinberger | System and Method for Dynamically Allocating Human Resources to a Project Plan |
US8155996B1 (en) * | 2008-03-06 | 2012-04-10 | Sprint Communications Company L.P. | System and method for customer care complexity model |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103914755A (en) * | 2014-03-18 | 2014-07-09 | 北京农业信息技术研究中心 | Method and system for determining spatial scales of field investigation and field management |
US20160004982A1 (en) * | 2014-07-03 | 2016-01-07 | International Business Machines Corporation | Method and system for estimating the progress and completion of a project based on a bayesian network |
Also Published As
Publication number | Publication date |
---|---|
US20090299782A1 (en) | 2009-12-03 |
US8781869B2 (en) | 2014-07-15 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US20120310697A1 (en) | Variance management | |
US11836487B2 (en) | Computer-implemented methods and systems for measuring, estimating, and managing economic outcomes and technical debt in software systems and projects | |
Trietsch et al. | PERT 21: Fitting PERT/CPM for use in the 21st century | |
US8631384B2 (en) | Creating a test progression plan | |
CN110309975A (en) | Project-developing process control method, device, equipment and computer storage medium | |
US20120035972A1 (en) | Optimizing Resources Allocation for Global Service Delivery | |
Cabri et al. | Earned value and agile reporting | |
US11281557B2 (en) | Estimating treatment effect of user interface changes using a state-space model | |
US8478627B2 (en) | Method for reducing risk associated with a task | |
Acebes et al. | On the project risk baseline: Integrating aleatory uncertainty into project scheduling | |
Bhalerao et al. | Incorporating Vital Factors in Agile Estimation through Algorithmic Method. | |
Garmabaki et al. | Modeling two-dimensional software multi-upgradation and related release problem (a multi-attribute utility approach) | |
Chandrika | Study on software reliability and reliability testing | |
US7640531B1 (en) | Productivity measurement and management tool | |
Sun et al. | Computing degree of parallelism for BPMN processes | |
Dabkowski et al. | Network science enabled cost estimation in support of MBSE | |
Huang et al. | A Study on Optimal Release Schedule for Multiversion Software | |
Peralta et al. | Workflow models: Management and quality of process in the cloud | |
Bezerra et al. | A simulation model for risk management support in IT outsourcing | |
Meli | Measuring change requests to support effective project management practices | |
EP4191487A1 (en) | Enhancing batch predictions by localizing jobs contributing to time deviation and generating fix recommendations | |
Bertazzi et al. | Dynamic project expediting: a stochastic shortest-path approach | |
Arekete et al. | Project Time and Cost Management | |
US20140358621A1 (en) | Time-dependent reorder points in supply chain networks | |
Khan et al. | Managing information systems requirements volatility in development projects: Mapping research and surveying practices |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
STCB | Information on status: application discontinuation |
Free format text: ABANDONED -- FAILURE TO PAY ISSUE FEE |