RU2547863C1 - Well stage cementing method - Google Patents
Well stage cementing method Download PDFInfo
- Publication number
- RU2547863C1 RU2547863C1 RU2014120490/03A RU2014120490A RU2547863C1 RU 2547863 C1 RU2547863 C1 RU 2547863C1 RU 2014120490/03 A RU2014120490/03 A RU 2014120490/03A RU 2014120490 A RU2014120490 A RU 2014120490A RU 2547863 C1 RU2547863 C1 RU 2547863C1
- Authority
- RU
- Russia
- Prior art keywords
- cementing
- cement
- stage
- well
- casing
- Prior art date
Links
Landscapes
- Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
Abstract
Description
Изобретение относится к нефтяной промышленности и может найти применение при ступенчатом цементировании скважины.The invention relates to the oil industry and may find application in step cementing wells.
Известен способ ступенчатого цементирования, включающий цементирование первой ступени обсадной колонны с верхней продавочной пробкой, открывание отверстий в цементировочной муфте, цементирование второй ступени с повышением давления в колонне до величины, необходимой для продавки тампонажного раствора в заколонное пространство на установленную высоту, и сбрасывание давления в обсадной колонне (Временное руководство по применению пакера для двухступенчатого и манжетного цементирования. М.: ВНИИБТ, 1974 г.)A known method of step cementing, including cementing the first stage of the casing string with the upper cork plug, opening holes in the cementing sleeve, cementing the second stage with increasing the pressure in the casing to the value necessary to push the cement slurry into the annulus to a specified height, and relieving the pressure in the casing the column (Interim guidance on the use of the packer for two-stage and lip-cementing. M: VNIIBT, 1974)
Наиболее близким к предложенному изобретению по технической сущности является способ ступенчатого цементирования, включающий цементирование первой ступени, ввод в колонну нижней пробки для открытия циркуляционных отверстий цементировочной муфты, периодическую промывку ствола скважины через циркуляционные отверстия в период ожидания затвердения цемента первой ступени, цементирование второй ступени с вводом в колонну верхней пробки для закрытия циркуляционных отверстий муфты. Нижняя пробка создает в обсадной колонне перегородку, которая необходима при ступенчатом цементировании для исключения возможности попадания тампонажного раствора второй ступени в колонну ниже цементировочной муфты (Булатов А.И. Справочник по креплению нефтяных и газовых скважин. М.: «Недра», 1977 г., с. 217, 218 - прототип).Closest to the proposed invention, the technical essence is a step cementing method, including cementing the first stage, introducing a lower plug into the column to open the circulation holes of the cement sleeve, periodically flushing the wellbore through the circulation holes while waiting for the cement to harden the first stage, cementing the second stage with the inlet into the column of the upper plug to close the circulation holes of the coupling. The lower plug creates a baffle in the casing, which is necessary for step cementing to exclude the possibility of cementing the second stage cement slurry into the string below the cement sleeve (Bulatov A.I. Oil and Gas Wells Handbook. M .: Nedra, 1977 , p. 217, 218 - prototype).
Общим недостатком известных технических решений является опасность преждевременного открытия муфты ступенчатого цементирования при цементировании первой ступени и ее неоткрытие при цементировании второй ступени. И в том, и в другом случае возникает необходимость ремонта скважины с подъемом обсадной колонны и заменой муфты ступенчатого цементирования.A common disadvantage of the known technical solutions is the danger of premature opening of the coupling of step cementing during cementing of the first stage and its non-opening during cementing of the second stage. And in fact, and in another case, there is a need to repair the well with the rise of the casing and the replacement of the coupling of step cementing.
В предложенном изобретении решается задача повышения надежности работы оборудования при ступенчатом цементировании скважины.In the proposed invention solves the problem of increasing the reliability of the equipment during step cementing wells.
Задача решается тем, что в способе ступенчатого цементирования скважины, включающем цементирование первой ступени, ввод в колонну нижней пробки для открытия циркуляционных отверстий цементировочной муфты ступенчатого цементирования, периодическую промывку ствола скважины через циркуляционные отверстия в период ожидания затвердения цемента первой ступени, цементирование второй ступени с вводом в колонну верхней пробки для закрытия циркуляционных отверстий цементировочной муфты ступенчатого цементирования, согласно изобретению при цементировании первой ступени продавливают тампонажный цемент порциями бурового раствора, воды и снова бурового раствора с установкой тампонажного цемента в затрубном пространстве выше муфты ступенчатого цементирования, а порции воды в обсадной колонне в интервале цементировочной муфты ступенчатого цементирования при ожидании затвердения цемента первой ступени проводят циклическую циркуляцию бурового раствора по обсадной колонне через цементировочную муфту ступенчатого цементирования с выходом на устье через затрубное пространство до полного удаления тампонажного цемента в интервале цементировочной муфты ступенчатого цементирования, после затвердения тампонажного цемента первой ступени при цементировании второй ступени по обсадной колонне прокачивают порцию буферного раствора и расчетный объем тампонажного цемента, размещают верхнюю пробку и продавливают технической водой до размещения пробки в интервале цементировочной муфты ступенчатого цементирования и перекрытия отверстий последней, повышают давление в обсадной колонне на 0,5-1,5 МПа выше рабочего при закачке до закрытия отверстий цементировочной муфты ступенчатого цементирования и проводят ожидание затвердения цемента, а при освоении скважины разбуривают верхнюю пробку.The problem is solved in that in the method of stepwise cementing of a well, including cementing the first stage, introducing a lower plug into the column to open the circulation holes of the cementing coupling of step cementing, periodically flushing the wellbore through circulation holes while waiting for the cement to harden the first stage, cementing the second stage with the input in the column of the upper plug for closing the circulation holes of the cementing coupling of step cementing, according to the invention and cementing the first stage, grouting cement is pushed with portions of drilling mud, water and again drilling mud with cement grout installed in the annulus above the step cementing clutch, and a portion of the water in the casing in the interval of the step cementing clutch while cycling the cement of the first stage is solidified, a cyclic the solution along the casing through the cementing sleeve step cementing with access to the mouth through the annulus In order to completely remove the cement cement in the interval of the cementing coupler of step cementing, after hardening the cement cement of the first stage during cementing of the second stage, a portion of the buffer solution and the calculated volume of cement cement are pumped through the casing, place the upper plug and squeeze technical water until the plug is placed in the cement cement step cementing and overlapping of the holes of the latter, increase the pressure in the casing by 0.5-1.5 MPa above the working when injected before closing the openings cementing collar stage cementing and carried waiting on cement and top plug drilled out during the development of wells.
В качестве буферного раствора используют водный раствор поверхностно-активного вещества и триполифосфата натрия.An aqueous solution of a surfactant and sodium tripolyphosphate is used as a buffer solution.
Сущность изобретенияSUMMARY OF THE INVENTION
Ступенчатое цементирование скважины вызывает опасность преждевременного открытия муфты ступенчатого цементирования при цементировании первой ступени и ее неоткрытие при цементировании второй ступени. Существующие технические решения не в полной мере устраняют эти сложности. В предложенном изобретении решается задача повышения надежности работы оборудования при ступенчатом цементировании скважины. Задача решается следующим образом.Step cementing of a well causes the risk of premature opening of the step cementing sleeve during cementing of the first stage and its non-opening during cementing of the second stage. Existing technical solutions do not completely eliminate these difficulties. In the proposed invention solves the problem of increasing the reliability of the equipment during step cementing wells. The problem is solved as follows.
При ступенчатом цементировании скважины проводят цементирование первой ступени, ввод в колонну нижней пробки для открытия циркуляционных отверстий цементировочной муфты ступенчатого цементирования, периодическую промывку ствола скважины через циркуляционные отверстия в период ожидания затвердения цемента первой ступени, цементирование второй ступени с вводом в колонну верхней пробки для закрытия циркуляционных отверстий цементировочной муфты ступенчатого цементирования. При цементировании первой ступени продавливают тампонажный цемент порциями бурового раствора, воды и снова бурового раствора с установкой тампонажного цемента в затрубном пространстве выше муфты ступенчатого цементирования, а порции воды в обсадной колонне в интервале цементировочной муфты ступенчатого цементирования. Размещение порции воды в интервале муфты необходимо для того, чтобы не испортить буровой раствор цементным раствором, т.к. при смешивании бурового раствора с цементным, буровой раствор меняет свои реологические свойства.In step cementing of a well, cementing of the first stage is carried out, a lower plug is inserted into the column to open the circulation holes of the cementing coupler of step cementing, periodic washing of the wellbore through the circulation holes while waiting for the cement to harden the first stage, cementing of the second stage with the introduction of the upper plug in the column to close the circulation holes cementing coupling step cementing. When cementing the first stage, grouting cement is pushed with portions of drilling mud, water and again drilling mud with cement grout installed in the annulus above the step cementing sleeve, and portions of water in the casing in the interval of the step cementing sleeve. Placing a portion of water in the interval of the coupling is necessary in order not to spoil the drilling fluid with cement mortar, because when mixing drilling fluid with cement, the drilling fluid changes its rheological properties.
При ожидании затвердения цемента первой ступени проводят циклическую циркуляцию бурового раствора по обсадной колонне через цементировочную муфту ступенчатого цементирования с выходом на устье через затрубное пространство до полного удаления тампонажного цемента в интервале цементировочной муфты ступенчатого цементирования. После затвердения тампонажного цемента первой ступени при цементировании второй ступени по обсадной колонне прокачивают порцию буферного раствора и расчетный объем тампонажного цемента, размещают верхнюю пробку и продавливают технической водой до размещения пробки в интервале цементировочной муфты ступенчатого цементирования и перекрытия отверстий последней. Повышают давление в обсадной колонне на 0,5-1,5 МПа выше рабочего при закачке до закрытия отверстий цементировочной муфты ступенчатого цементирования и проводят ожидание затвердения цемента, а при освоении скважины разбуривают верхнюю пробку. Повышение давления необходимо для того, чтобы срезать штифты на стакане муфты ступенчатого цементирования, который закрывает окна.While waiting for the hardening of the cement of the first stage, the drilling fluid is circulated through the casing through the cementing sleeve of step cementing with access to the mouth through the annulus to completely remove the cement in the interval of the cementing coupling of step cementing. After hardening of the cement of the first stage during cementing of the second stage, a portion of the buffer solution and the estimated volume of cement are pumped through the casing, the upper plug is placed and pushed with process water until the plug is placed in the interval of the cemented cement coupling of step cementing and overlaps the holes of the latter. Increase the pressure in the casing by 0.5-1.5 MPa higher than the working one when pumping until the holes of the cementing coupler of step cementing are closed and wait for cement to harden, and when the well is developed, the upper plug is drilled. An increase in pressure is necessary in order to cut off the pins on the glass of the stepped cementing sleeve, which closes the windows.
В качестве буферного раствора используют водный раствор поверхностно-активного вещества и триполифосфата натрия. Это необходимо, чтобы удалить корку со стенок скважины.An aqueous solution of a surfactant and sodium tripolyphosphate is used as a buffer solution. This is necessary to remove the crust from the walls of the well.
Примеры конкретного выполненияCase Studies
Пример 1. Выполняют ступенчатое цементирование скважины глубиной 2026 м. Скважина оборудована обсадной колонной диаметром 146 мм с цементировочной муфтой ступенчатого цементирования на глубине 880 м. Проводят цементирование первой ступени, для чего закачивают в колонну тампонажный цемент, вводят в колонну нижнюю пробку, продавливают тампонажный цемент порциями бурового раствора, воды и снова бурового раствора с установкой тампонажного цемента в затрубном пространстве выше муфты ступенчатого цементирования, а порции воды в обсадной колонне в интервале цементировочной муфты ступенчатого цементирования. Ожидают затвердения цемента первой ступени. При этом проводят циклическую циркуляцию бурового раствора по обсадной колонне через цементировочную муфту ступенчатого цементирования с выходом на устье через затрубное пространство до полного удаления тампонажного цемента в интервале цементировочной муфты ступенчатого цементирования по режиму 1 час - прокачка, 1 час - остановка. Через 8 часов приступают к цементированию второй ступени.Example 1. Perform step cementing of a well with a depth of 2026 m. The well is equipped with a casing with a diameter of 146 mm and a cementing sleeve of step cementing at a depth of 880 m. Cementing of the first stage is carried out, for which cement is pumped into the column, the bottom plug is introduced into the column, cement is pressed in portions of drilling mud, water and again mud with the installation of cement in the annulus above the step cementing sleeve, and portions of water in the casing ranging cementing collar stage cementing. Hardening of cement of the first stage is expected. In this case, cyclic circulation of the drilling fluid through the casing through the cementing sleeve of step cementing is carried out with access to the mouth through the annulus until the cement is completely removed in the interval of the cementing coupler of cementing according to the regime of 1 hour - pumping, 1 hour - stop. After 8 hours, they begin to cement the second stage.
При цементировании второй ступени по обсадной колонне прокачивают порцию буферного раствора и расчетный объем тампонажного цемента, размещают верхнюю пробку, продавливают технической водой. Повышают давление в обсадной колонне на 0,5 МПа выше рабочего при закачке до закрытия отверстий цементировочной муфты ступенчатого цементирования и проводят ожидание затвердения цемента. При освоении скважины разбуривают верхнюю пробку. В качестве буферного раствора используют водный раствор, содержащий 0,1% поверхностно-активного вещества МЛ-81Б и 0,1% триполифосфата натрия.When cementing the second stage, a portion of the buffer solution and the estimated volume of cement cement are pumped along the casing, the upper plug is placed, and pressed through with technical water. Increase the pressure in the casing by 0.5 MPa higher than the working one when pumping until the holes of the cementing coupler of step cementing are closed and wait for the cement to harden. During well development, the upper plug is drilled. An aqueous solution containing 0.1% ML-81B surfactant and 0.1% sodium tripolyphosphate is used as a buffer solution.
Пример 2. Выполняют, как пример 1.Example 2. Perform as example 1.
Проводят цементирование первой ступени, для чего закачивают в колонну тампонажный цемент, вводят в колонну нижнюю пробку, продавливают тампонажный цемент порциями бурового раствора, воды и снова бурового раствора с установкой тампонажного цемента в затрубном пространстве выше муфты ступенчатого цементирования, а порции воды в обсадной колонне в интервале цементировочной муфты ступенчатого цементирования. Ожидают затвердения цемента первой ступени. При этом проводят циклическую циркуляцию бурового раствора по обсадной колонне через цементировочную муфту ступенчатого цементирования с выходом на устье через затрубное пространство до полного удаления тампонажного цемента в интервале цементировочной муфты ступенчатого цементирования по режиму 0,5 часа - прокачка, 0,5 часа - остановка. Через 6 часов приступают к цементированию второй ступени.Cementing of the first stage is carried out, for which grouting cement is pumped into the column, a lower plug is introduced into the column, grouting cement is pushed with portions of drilling mud, water and again drilling mud with cement grout installed in the annulus above the step cementing sleeve, and portions of water in the casing in interval cement clutch step cementing. Hardening of cement of the first stage is expected. In this case, cyclic circulation of the drilling fluid through the casing through the cementing sleeve of step cementing is carried out with access to the mouth through the annular space until the cement cement is completely removed in the interval of the cementing sleeve of cementing according to the regime of 0.5 hours - pumping, 0.5 hours - stop. After 6 hours, they begin to cement the second stage.
При цементировании второй ступени по обсадной колонне прокачивают порцию буферного раствора и расчетный объем тампонажного цемента, размещают верхнюю пробку, продавливают технической водой. Повышают давление в обсадной колонне на 1,0 МПа выше рабочего при закачке до закрытия отверстий цементировочной муфты ступенчатого цементирования и проводят ожидание затвердения цемента. При освоении скважины разбуривают верхнюю пробку. В качестве буферного раствора используют водный раствор, содержащий 0,2% поверхностно-активного вещества МЛ-70 и 0,2% триполифосфата натрия.When cementing the second stage, a portion of the buffer solution and the estimated volume of cement cement are pumped along the casing, the upper plug is placed, and pressed through with technical water. Increase the pressure in the casing by 1.0 MPa higher than the working one when pumping until the holes of the cementing coupler of step cementing are closed and wait for the cement to harden. During well development, the upper plug is drilled. As a buffer solution, an aqueous solution is used containing 0.2% ML-70 surfactant and 0.2% sodium tripolyphosphate.
Пример 3. Выполняют, как пример 1.Example 3. Perform as example 1.
Проводят цементирование первой ступени, для чего закачивают в колонну тампонажный цемент, вводят в колонну нижнюю пробку, продавливают тампонажный цемент порциями бурового раствора, воды и снова бурового раствора с установкой тампонажного цемента в затрубном пространстве выше муфты ступенчатого цементирования, а порции воды в обсадной колонне в интервале цементировочной муфты ступенчатого цементирования. Ожидают затвердения цемента первой ступени. При этом проводят циклическую циркуляцию бурового раствора по обсадной колонне через цементировочную муфту ступенчатого цементирования с выходом на устье через затрубное пространство до полного удаления тампонажного цемента в интервале цементировочной муфты ступенчатого цементирования по режиму 1,5 часа - прокачка, 1,5 часа - остановка. Через 4 часа приступают к цементированию второй ступени.Cementing of the first stage is carried out, for which grouting cement is pumped into the column, a lower plug is introduced into the column, grouting cement is pushed with portions of drilling mud, water and again drilling mud with cement grout installed in the annulus above the step cementing sleeve, and portions of water in the casing in interval cement clutch step cementing. Hardening of cement of the first stage is expected. In this case, cyclic circulation of the drilling fluid through the casing through the cementing sleeve of step cementing is carried out with access to the mouth through the annular space until the cement cement is completely removed in the interval of the cementing coupling of step cementing according to the regime of 1.5 hours - pumping, 1.5 hours - stop. After 4 hours, they begin to cement the second stage.
При цементировании второй ступени по обсадной колонне прокачивают порцию буферного раствора и расчетный объем тампонажного цемента, размещают верхнюю пробку, продавливают технической водой. Повышают давление в обсадной колонне на 1,5 МПа выше рабочего при закачке до закрытия отверстий цементировочной муфты ступенчатого цементирования и проводят ожидание затвердения цемента. При освоении скважины разбуривают верхнюю пробку. В качестве буферного раствора используют водный раствор, содержащий 0,3% поверхностно-активного вещества МЛ-80 и 0,3% триполифосфата натрия.When cementing the second stage, a portion of the buffer solution and the estimated volume of cement cement are pumped along the casing, the upper plug is placed, and pressed through with technical water. Increase the pressure in the casing string by 1.5 MPa above the worker during injection until the holes of the cementing coupler of step cementing are closed and wait for the cement to harden. During well development, the upper plug is drilled. As a buffer solution, an aqueous solution is used containing 0.3% ML-80 surfactant and 0.3% sodium tripolyphosphate.
В результате по примерам 1-3 удается зацементировать скважину от забоя до устья без сбоев при цементировании.As a result, according to examples 1-3, it is possible to cement the well from the bottom to the well without failures during cementing.
Claims (2)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
RU2014120490/03A RU2547863C1 (en) | 2014-05-21 | 2014-05-21 | Well stage cementing method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
RU2014120490/03A RU2547863C1 (en) | 2014-05-21 | 2014-05-21 | Well stage cementing method |
Publications (1)
Publication Number | Publication Date |
---|---|
RU2547863C1 true RU2547863C1 (en) | 2015-04-10 |
Family
ID=53296503
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
RU2014120490/03A RU2547863C1 (en) | 2014-05-21 | 2014-05-21 | Well stage cementing method |
Country Status (1)
Country | Link |
---|---|
RU (1) | RU2547863C1 (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
RU2606744C1 (en) * | 2016-03-14 | 2017-01-10 | Публичное акционерное общество "Татнефть" им. В.Д. Шашина | Well stage cementing method |
RU2615188C1 (en) * | 2016-05-04 | 2017-04-04 | Григорий Александрович Тыртышный | Well stage cementing method |
CN110734259A (en) * | 2019-11-21 | 2020-01-31 | 嘉华特种水泥股份有限公司 | thermoelastic heavy oil thermal recovery well cementation cement |
CN114109299A (en) * | 2020-08-27 | 2022-03-01 | 中国石油化工股份有限公司 | Stage cementing device and method for top cementing |
CN114109297A (en) * | 2020-08-25 | 2022-03-01 | 中国石油化工股份有限公司 | Stage cementing method |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3633671A (en) * | 1970-01-19 | 1972-01-11 | Murphy Ind Inc G W | Cementing collar |
US3948322A (en) * | 1975-04-23 | 1976-04-06 | Halliburton Company | Multiple stage cementing tool with inflation packer and methods of use |
SU926240A1 (en) * | 1980-06-09 | 1982-05-07 | Всесоюзный Ордена Трудового Красного Знамени Научно-Исследовательский Институт Буровой Техники | Method for stepwise grouting of wells |
RU2038462C1 (en) * | 1991-06-17 | 1995-06-27 | Еременко Валентин Васильевич | Method for step-by-step well grouting |
RU2199000C2 (en) * | 2001-04-23 | 2003-02-20 | Открытое акционерное общество "Татнефть" | Method of well stage cementing |
-
2014
- 2014-05-21 RU RU2014120490/03A patent/RU2547863C1/en active IP Right Revival
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3633671A (en) * | 1970-01-19 | 1972-01-11 | Murphy Ind Inc G W | Cementing collar |
US3948322A (en) * | 1975-04-23 | 1976-04-06 | Halliburton Company | Multiple stage cementing tool with inflation packer and methods of use |
SU926240A1 (en) * | 1980-06-09 | 1982-05-07 | Всесоюзный Ордена Трудового Красного Знамени Научно-Исследовательский Институт Буровой Техники | Method for stepwise grouting of wells |
RU2038462C1 (en) * | 1991-06-17 | 1995-06-27 | Еременко Валентин Васильевич | Method for step-by-step well grouting |
RU2199000C2 (en) * | 2001-04-23 | 2003-02-20 | Открытое акционерное общество "Татнефть" | Method of well stage cementing |
Non-Patent Citations (1)
Title |
---|
БУЛАТОВ А.И., Справочник по креплению нефтяных и газовых скважин, Москва: "Недра", 1981, с.220-221. * |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
RU2606744C1 (en) * | 2016-03-14 | 2017-01-10 | Публичное акционерное общество "Татнефть" им. В.Д. Шашина | Well stage cementing method |
RU2615188C1 (en) * | 2016-05-04 | 2017-04-04 | Григорий Александрович Тыртышный | Well stage cementing method |
CN110734259A (en) * | 2019-11-21 | 2020-01-31 | 嘉华特种水泥股份有限公司 | thermoelastic heavy oil thermal recovery well cementation cement |
CN114109297A (en) * | 2020-08-25 | 2022-03-01 | 中国石油化工股份有限公司 | Stage cementing method |
CN114109297B (en) * | 2020-08-25 | 2024-05-14 | 中国石油化工股份有限公司 | Stage cementing method |
CN114109299A (en) * | 2020-08-27 | 2022-03-01 | 中国石油化工股份有限公司 | Stage cementing device and method for top cementing |
CN114109299B (en) * | 2020-08-27 | 2024-04-19 | 中国石油化工股份有限公司 | Stage cementing device for top cementing and method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
RU2547863C1 (en) | Well stage cementing method | |
RU2397319C2 (en) | Hydraulic stratum fracture method | |
RU2483209C1 (en) | Method of hydraulic fracturing of well formation | |
RU2410514C1 (en) | Method for well construction | |
RU2578095C1 (en) | Method for isolation of water flow in open horizontal section producing wells | |
RU2610967C1 (en) | Method of selective treatment of productive carbonate formation | |
RU2379472C1 (en) | Method of well's horizontal borehole part repair insulation works | |
RU2382171C1 (en) | Gas and gas condensate wells with leaky casing string repair method | |
RU2615188C1 (en) | Well stage cementing method | |
RU2167273C1 (en) | Method of casing liner installation in well | |
RU2564316C1 (en) | Method of completion of horizontal production well construction with deposit interval hydraulic fracturing | |
WO2019104007A1 (en) | Method and apparatus for washing an upper completion | |
RU2541981C1 (en) | Completion method for well with horizontal shaft | |
RU2576253C1 (en) | Method for multistage well cementing and set of equipment therefor | |
RU2560018C1 (en) | Water flow isolation technique in uncased horizontal borehole section of producing well | |
RU2576416C1 (en) | Method to fix process wells of underground storages of gaseous and liquid hydrocarbons (versions) | |
US3417816A (en) | Method of cementing well casing | |
RU2792128C1 (en) | Method for cementing the conductor, a technical column during the construction of wells | |
RU2519262C1 (en) | Method of formation isolation with cement-silicate mud | |
RU2606744C1 (en) | Well stage cementing method | |
RU2324050C2 (en) | Method of hydrolic fracturing of formation of condensate borehole | |
RU2661935C1 (en) | Method of conducting water-insulating works in the extracting well, excluding the water oil deposit | |
RU2541979C1 (en) | Completion method of horizontal well | |
RU2541985C1 (en) | Cementing method for horizontal shaft of well | |
SU1659626A1 (en) | Method of well completion |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
MM4A | The patent is invalid due to non-payment of fees |
Effective date: 20170522 |
|
NF4A | Reinstatement of patent |
Effective date: 20180829 |