- KR960000108B1 KR960000108B1 KR1019920020774A KR920020774A KR960000108B1 KR 960000108 B1 KR960000108 B1 KR 960000108B1 KR 1019920020774 A KR1019920020774 A KR 1019920020774A KR 920020774 A KR920020774 A KR 920020774A KR 960000108 B1 KR960000108 B1 KR 960000108B1
- Authority
- KR
- South Korea
- Prior art keywords
- boom
- auger
- dry
- crane
- stage
- Prior art date
Links
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C23/00—Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
Landscapes
- Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Jib Cranes (AREA)
Abstract
Description
제1도는 본 발명의 한 실시예의 측면도.1 is a side view of one embodiment of the present invention.
제2도는 동실예의 평면도.2 is a plan view of the same example.
제3도는 동실시예의 배면도.3 is a rear view of the same embodiment.
제4도는 동실시예에서 채용되는 3단붐상의 오거고정장치의 개략도.4 is a schematic diagram of the auger fixing device on the three-stage boom employed in the embodiment.
제5도는 동실시예의 3단붐의 신축상태도로써,5 is a drawing of a state of expansion and contraction of the three-stage boom of the embodiment;
(a)는 1단으로 신축된 상태.(a) is stretched in one stage.
(b)는 2단으로 신축된 상태.(b) is stretched in two stages.
(c)는 3단으로 신축된 상태를 나타낸다.(c) shows the state stretched in three steps.
제6도는 동실시예에 훅평행이동장치의 개략도로써,6 is a schematic diagram of a hook parallelism moving device according to the embodiment;
(a)는 평면도.(a) is a plan view.
(b)는 정면도이다.(b) is a front view.
제7도는 동실시예의 오거고정장치의 개략도로써,7 is a schematic view of the auger fixing device of the embodiment,
(a)는 평면도.(a) is a plan view.
(b)는 정면도.(b) is a front view.
(c)는 측면도이다.(c) is a side view.
제8도는 동실시예의 붐 고정핀의 설치상태도.8 is an installation state of the boom fixing pin of the embodiment.
제9도는 제8도에 대비한 종래의 붐 고정핀의 설치상태도.9 is a view showing the installation state of a conventional boom fixing pin in FIG.
* 도면의 주요부분에 대한 부호의 설명* Explanation of symbols for main parts of the drawings
1 : 건주크레인 10 : 차량본체1: dry crane 10: vehicle body
11 : 조작석 12 : 조작레버11: operator's seat 12: operation lever
20 : 하이포스트 30 : 붐20: high post 30: boom
31 : 1단붐 32 : 2단붐31: 1st stage boom 32: 2nd stage boom
33 : 3단붐 34 : 붐헤드33: 3-stage boom 34: Boom head
35 : 고정핀 36 : 신축실린더35: fixed pin 36: expansion cylinder
37 : 신장용 와이어 37 : 쉬브37: extension wire 37: sheave
39 : 단축용 와이어 40 : 오거39: shortening wire 40: auger
50 : 훅 60 : 건주50: hook 60: dry
70 : 건주받침대 80 : 수평이동 쉬브70: dry support 80: horizontal movable sheave
100 : 윈치 110 : 잭실린더100: winch 110: jack cylinder
120 : 잭 받침대 130 : 아우트리거120: jack base 130: outrigger
본 발명은 건주작업 및 중량물 견인작업등을 더욱 신속하고 안전하게 수행할 수 있도록 개선한 건주크레인(Auger Crane)에 관한 것이다.The present invention relates to an improved crane (Auger Crane) to be carried out more quickly and safely, such as dry work and heavy weight traction work.
일반적으로 건주크레인은 건설현장에서 건주작업이나 중량물 견인작업등을 수행하게 되는 바, 종래에 제안된 것들은 작업반경이 협소하여 폭넓은 작업을 수행하는 데에 많은 장애가 있었고, 붐(Boom)을 신축할 때에 붐헤드(Boom Head)와 훅(Hook)과의 간격이 자동으로 이루어지지 않기 때문에 윈치와이어(Winch Wire)가 파손된 우려가 많게 되는 문제가 있었으며, 이를 방지하기 위해서는 신축레버와 훅위치 조절레버를 동시에 작동해야 하는 불편함이 있었다.In general, dry cranes perform dry work or heavy weight towing work at construction sites, and the conventionally proposed ones have many obstacles to performing a wide range of tasks due to their narrow working radius. Since the gap between the boom head and the hook is not made automatically, there is a problem that the winch wire is broken. To prevent this, the expansion lever and the hook position adjustment lever There was an inconvenience to work at the same time.
뿐만 아니라 종래의 건주크레인에 있어서는 오거(Auger) 작업을 할 때에 혹의 위치를 별도로 조절하여야하는 번거로움이 있었으며, 특히 오거의 안전장치가 없기 때문에 오거를 고정할 데에 부주의로 붐을 완전히 단축하지 않는 경우에는 오거장치가 붐헤드측에 확실하게 결속되지 않아 작업중에 오거가 급격히 낙하할 수 있는 위험이 있었고, 낮은 포스트(Post)이기 때문에 건주를 적재한 상태에서는 굴착작업을 할 수 없게 되는 등의 문제가 있었다.In addition, in the conventional dry crane, there was a need to separately adjust the position of the hump when performing the auger, and in particular, the auger was not inadvertently shortened to fix the auger due to the lack of the auger's safety device. If not, there is a risk that the auger device may not fall tightly on the boom head side, and the auger may fall sharply during operation.As it is a low post, the excavation work cannot be carried out while the dry loader is loaded. There was a problem.
본 발명은 상기 종래의 실정을 감안하여 안출한 것이며, 그 목적은 더욱 넓은 작업변경을 갖도록 하고, 훅과 붐헤드사이의 간격이 일정하게 유지되도록 함은 물론 건주 적재시에도 굴착작업을 행할 수 있도록 하고, 오거의 추락을 방지하여 작업의 안전성을 더욱 향상시킬 수 있도록 하는 건주크레인을 제공하는 데에있다.The present invention has been made in view of the above-mentioned conventional situation, the object is to have a wider work change, to maintain a constant distance between the hook and the boom head, as well as to be able to carry out excavation work during dry loading In addition, to prevent the fall of the auger to provide a dry crane that can further improve the safety of the work.
이하 상기의 목적을 달성하기 위한 본 발명의 구체적인 내용을 첨부도면에 도시한 한 실시예를 통하여 더욱 자세히 설명하면 다음과 같다.Hereinafter will be described in more detail through an embodiment shown in the accompanying drawings, the specific content of the present invention for achieving the above object.
즉, 본 발명의 건주크레인(1)은 제4도와 같이 3단붐(30)상에 오거장치를 고정할 수 있게 하여 작업반경을 크게 늘린 것이며, 아울러 제5도와 같이 3단붐(30)이 동시에 신축되도록 함으로써 더욱 편리하게 작업 할 수 있게 한 것이다.That is, the dry crane (1) of the present invention is to increase the working radius significantly by allowing the auger device to be fixed on the three-stage boom 30 as shown in FIG. By doing so, you can work more conveniently.
또한 본 발명의 건주크레인(1)은 제 7 도와 같이 오거장치가 붐헤드(34)측에 확실하게 고정되지 않으면 1단붐(31)측에 그대로 남아있게 함으로써 보다 안전하게 오거(40)를 고정할 수 있게 되는 것이며, 제4도와 같이 하이포스트(20)를 채택하여 건주(60)를 건주받침대(70)에 적재한 상태에서도 굴착작업이 가능하게 한 것이다.In addition, the dry crane (1) of the present invention can secure the auger (40) more securely by remaining in the first stage boom (31), if the auger device is not securely fixed to the boom head 34 side as shown in the seventh degree By adopting the high post 20 as shown in FIG. 4, the excavation work is possible even when the dry column 60 is loaded on the dry base 70.
그리고 본 발명의 건주크레인(1)은 제8도와 같이 기복능력을 향상시키기 위해서 붐(30)의 상면에 고정핀(35)을 설치함으로써 붐각이 30°부근에서 최대의 기복력이 발휘될 수 있도록 하고, 더욱 균형이 향상된 기복능력을 갖게 한 것이다.And the dry crane (1) of the present invention by installing a fixing pin 35 on the upper surface of the boom 30 to improve the up and down ability as shown in FIG. 8 so that the maximum up and down force can be exhibited in the boom angle around 30 ° And more balanced ups and downs.
제1도에서 제3도까지는 본 발명의 외형도가 도시되어 있다.1 to 3 show the outline of the invention.
본 발명에 있 어서 각 장비를 조작할 수 있도록 하는 조작선(11)과 조작레버 (12)는 제1도 및 제2도와 같이 차량본체(10)의 상부 전방에 마련되며, 차량본체(10)의 중앙부에는 하단에 선회기어(21)가 설치되는 하이포스트(20)가 설치되고, 이 하이포스트(20)에 3단붐(30)과 오거(40), 훅(50), 사다리(90)등이 설치된다.In the present invention, the operation line 11 and the operation lever 12 for operating each equipment is provided in the upper front of the vehicle body 10 as shown in Figs. 1 and 2, the vehicle body 10 The central portion of the high post 20 is provided with a turning gear 21 is installed at the lower end, the high post 20, the three-stage boom 30, the auger 40, the hook 50, the ladder 90, etc. This is installed.
제4도는 3단붐상의 오거고정장치의 개략도이다.4 is a schematic view of the auger fastening device on the three-stage boom.
본 발명에 있어서는, 제4도와 같이 3단붐(30) 및 오거(40)를 지지하는 하이포스트(20)가 채용되는 바, 이에 따라 건주 적재상태에서도 굴착작업이나 크레인작업을 할 수 있게 된다.In the present invention, as shown in FIG. 4, the high post 20 supporting the three-stage boom 30 and the auger 40 is employed, whereby excavation work or crane work can be performed even in a dry loading state.
또한 본 발명에 있어서는 오거(40)를 고정대(41)를 통해 3단붐(30)의 선단에 고정함으써 아래의 표 1과 같이 종래에 비해 큰 작업반경 및 보다 깊은 굴착깊이를 갖을 수 있게 된다.In addition, in the present invention, by fixing the auger 40 to the tip of the three-stage boom 30 through the fixing table 41, as shown in Table 1 below it can have a larger working radius and deeper drilling depth than in the prior art.
[표 1]TABLE 1
제5도에는 본 발명의 3단붐의 신축상태도가 도시되어 있다.5, there is shown a state of expansion and contraction of the three-stage boom of the present invention.
본 발명에 있어서는 제5도와 같이 붐(30)의 내부에 설치한 하나의 신축실린더 (36)를 통해 1단붐(31)과 2단붐(32) 및 3단붐(33)을 동시에 신축시킬 수 있게 되는 바, 신축실린더(36)가 신장된 만큼 2단붐(32)이 신장되고, 1단붐(31)의 후상면에 고정된 신장용 와이어(37)가 2단붐(32)의 내선단부에 위치하는 쉬브(38)를 통해 3단붐(33)의 내후단에 고정되어 2단붐(32)이 신장된 만큼 3단붐(33)을 비례 신장시키게 된다.In the present invention, the first stage boom 31, the second stage boom 32, and the third stage boom 33 can be simultaneously expanded and contracted through one expansion cylinder 36 installed inside the boom 30 as shown in FIG. Bar, a sheave in which the two-stage boom 32 is extended as the expansion cylinder 36 is extended, and the extension wire 37 fixed to the rear upper surface of the first-stage boom 31 is located at the inner end of the two-stage boom 32. It is fixed to the inner and rear ends of the three-stage boom 33 through 38 to extend the three-stage boom 33 proportionally as the two-stage boom 32 is extended.
역으로 붐(30)이 동시에 축소되는 때에는 신축실린더(36)가 축소되는 만큼 2단붐이 축소되고, 1단붐(31)의 내하단면에 고정된 단축용 와이어(39)를 통해 3단붐 (33)이 동시에 비례 축소된다.Conversely, when the boom 30 is simultaneously reduced, the two-stage boom is reduced as the expansion and contraction cylinder 36 is reduced, and the three-stage boom 33 is provided through a shortening wire 39 fixed to the lower and lower end surfaces of the first-stage boom 31. This is proportionally reduced at the same time.
따라서 본 발명에 의하면 붐의 신축작동시 1단붐과 2단붐이 동시에 작동하지 않음으로 해서 겪었던 종래의 사용상의 많은 불편을 해소할 수 있게 됨은 물론 텔레스코프 실린더(Telescope Cylinder)를 사용함으로 해서 붐의 자중증대와 자격상승을 야기했던 종래의 문제를 일소할 수 있게된다.Therefore, according to the present invention, the first stage boom and the second stage boom do not operate at the same time during the expansion and contraction of the boom, and thus, many inconveniences of the conventional use, as well as the use of the telescope cylinder (Telescope Cylinder), the weight of the boom It is possible to eliminate the conventional problems that caused the increase and qualification rise.
제6도에는 본 발명의 훅 평형장치의 개략도가 도시되어 있다.6 shows a schematic diagram of the hook balancer of the present invention.
제6도와 같이 본 발명에 있어서는 2단붐(32)상에 수평이동 쉬브(80)가 설치되며, 이 수평이동 쉬브(80)는 윈치(100)의 와이어(101)에 연결된다.In the present invention as shown in FIG. 6, the horizontal movable sheave 80 is installed on the two-stage boom 32, and the horizontal movable sheave 80 is connected to the wire 101 of the winch 100.
따라서 붐(30)의 신축시에는 수평이동 쉬브(80)가 2단붐(32)상을 전후방향으로 수평이동하면서 훅(50)과 붐헤드(34)와의 간격을 일정하게 유지시켜 줄수 있게 되고, 그에 따라 훅(50)의 위치를 별도로 조정하지 않고 사용할 수 있게 된다.Accordingly, when the boom 30 is expanded and contracted, the horizontal movable sheave 80 may horizontally move the two-stage boom 32 in the front-rear direction while maintaining a constant distance between the hook 50 and the boom head 34. Thereby, the position of the hook 50 can be used without adjusting separately.
본 발명의 훅 평형장치에 의하면 훅(50)과 붐헤드(34)와의 간격을 자동으로 조절할 수 없어 윈치와이어가 절단되거나 파손되었던 종래의 문제를 해결할 수 있게 된다.According to the hook balancer of the present invention, the gap between the hook 50 and the boom head 34 may not be automatically adjusted, thereby solving the conventional problem that the winch wire is cut or broken.
제7도는 본 발명의 오거장치의 개략도이다.7 is a schematic view of the auger device of the present invention.
기존의 크레인에 있어서는 오거(40)를 고정할 때에 부주의하게 되면 오거(40)가 급격하게 추락하여 안전사고가 일어날 우려가 높았던 바, 본 발명에 있어서는 오거(40)를 고정할 때에 붐(30)이 완전히 단축되지 않도록 함은 물론 오거장치가 붐헤드(34)측에 확실하게 고정되지 않으면 1단붐(31)에 남아 있도록 함으로써 종래의 위험을 미연에 방지할 수 있게 된다.In the conventional crane, if the auger 40 is inadvertently fixed when fixing the auger 40, there is a high possibility that a safety accident may occur due to the auger 40 falling rapidly. In the present invention, the boom 30 is fixed when the auger 40 is fixed. This is not completely shortened, as well as the auger device to remain in the first stage boom 31 if it is not securely fixed to the boom head 34 side it is possible to prevent the conventional risk in advance.
즉, 본 발명에 있어서는 제7도와 같이 붐헤드(34)가 완전히 단축되면서 로드조립체(90)의 끝단을 밀어주게 되고, 로드조립체(90)에 부착된 고정훅(91)의 고정상태가 해제되어 오거(40)가 하강하게 된다.That is, in the present invention, as shown in FIG. 7, the boom head 34 is completely shortened, pushing the end of the rod assembly 90, and the fixing state of the fixing hook 91 attached to the rod assembly 90 is released. Auger 40 is lowered.
그리고 오거(40)를 통해 굴착작업을 행하고자 할 때는 조작석(11)의 전방에 위치한 조작레버(12)를 이용하여 작업하면 된다.And when the excavation work is to be carried out through the auger 40, the operation lever 12 located in front of the operator seat 11 may be used.
또한 붐(30)상에 오거(40)를 고정하여 사용할 때는 앞에서 행한 순서대로 작업한 후 고정훅(91)을 붐헤드 고정핀(92)에 고정시키고, 붐(30)을 신장시키면 붐(30)상에 오거(40)가 고정되어 보다 넓은 범위의 굴착작업을 행할 수 있게 된다.In addition, when the auger 40 is fixed on the boom 30, the fixed hook 91 is fixed to the boom head fixing pin 92 after the work in the order described above, and when the boom 30 is extended, the boom 30 The auger 40 is fixed on) so that a wider range of excavation work can be performed.
제8도는 본 발명의 붐 고정핀의 설치상태도가 도시되어 있다.8 is a diagram showing the installation state of the boom fixing pin of the present invention.
일반적으로 크레인에는 붐(30)의 강도와 안전도와의 관계에서 붐각이 30°∼80°인 경우에 최대의 기복력을 필요로 하게 된다.In general, the crane requires the maximum undulation force when the boom angle is 30 ° to 80 ° in relation to the strength and safety of the boom 30.
그러나 기존의 대부분의 크레인은 제9도와 같이 붐 고정핀(35')이 붐(30')의 하부면 또는 주위에 설치되어 붐각이 (-)일 때에 최대의 기복력이 걸리게 되므로 역부족일 때는 과다한 리 트(Lift)력이 생겨 붐(30')등의 구조물이 손상되는 문제가 있었다.However, most existing cranes, as shown in FIG. 9, have a boom fixing pin 35 'installed on the lower surface of or around the boom 30', so that the maximum undulation force is applied when the boom angle is negative. There was a problem that the lift (Lift) is generated to damage the structure, such as boom (30 ').
이에 본 발명은 종래의 문제를 해결하기 위해 붐(30)의 상부면에 고정핀(35)을 설치하였다.Therefore, the present invention has been provided with a fixing pin 35 on the upper surface of the boom 30 to solve the conventional problem.
도면부호중 미설명부호 110은 잭실린더, 120은 잭받침대, 130은 아우트리거 (outigger), 140은 공구박스, 150은 작업등이다.In the drawing, reference numeral 110 is a jack cylinder, 120 is a jack support, 130 is an outrigger, 140 is a tool box, 150 is a work lamp.
상기와 같이 구성된 본 발명의 건주크레인(1)을 통해 각종작업을 수행하는 방법을 설명하면 다음과 같다.Referring to the method of performing various operations through the dry crane (1) of the present invention configured as described above are as follows.
즉, 운전자가 본 발명의 건주 크레인(1)을 작동하려면 우선 작업하고자 하는 장소에 차량본체(10)를 이동한 후 조작석(11)에 않은 채로 조작레버(12)를 조작하면 된다.That is, in order for the driver to operate the dry crane 1 of the present invention, the operator first moves the vehicle body 10 to a place to be worked on, and then operates the operation lever 12 without being in the operator seat 11.
상기에서 더욱 안전한 작업을 위하여 조작레버(12)를 통해 아우트리거(130)와 잭실린더(110)를 조작하여 차량을 수평으로 유지한 후 지면에 단단하게 고정해야 하는 것은 물론이다.Of course, for safer operation in the above operation by operating the outrigger 130 and the jack cylinder 110 through the operating lever 12 to maintain the vehicle horizontally of course it must be firmly fixed to the ground.
지면에 차량에 지지가 견고하게 되면 오거(40)에 의한 굴착작업 및 붐(30) 및 훅(50)에 의한 중량물 견인 작업등을 조작석(11)의 조작레버(12)를 통해 수행할 수 있게 된다.When the vehicle is firmly supported on the ground, excavation work by the auger 40 and heavy load traction work by the boom 30 and the hook 50 can be performed through the operation lever 12 of the operator seat 11. do.
그중 우선 중량물 견인작업의 예를 살펴보면, 먼저 장비 조작레버(12)를 이용하여 아우트리거(130)와 잭실린더(110)를 신장시켜 차량의 수평상태를 유지한 후 조작레버(12)를 이용하여 장비운전자가 조작하고자 하는 의도대로 붐(30) 및 훅(50)을 움직이게 되며, 이와 같은 견인작업을 통해서는 변압기 및 시설물과 그밖의 중량물을 효과적으로 견인하거나 옮길 수 있게 된다.Looking at the example of the heavy weight towing operation, first, the outrigger 130 and the jack cylinder 110 is extended by using the equipment operation lever 12 to maintain the horizontal state of the vehicle using the operation lever 12 As the equipment driver intends to operate, the boom 30 and the hook 50 are moved, and the towing operation can effectively tow or move the transformer and facilities and other heavy objects.
다음에 오거(40)를 조작하는 예를 살펴보면, 우선 오거(40)를 조작하기 위해서는 조작레버(12)를 이용하여 붐(30)을 최대한 신축시켜야 하는 바, 오거 조작레버 (12)를 "좌회전"으로 하여 오거(40)를 천천히 감아 올리면 고정장치가 아래로 움직이게 되고, 조작레버(12)를 "우회전"으로 하면 오거(40)가 우회전하면서 상승하게 된다.Next, referring to an example of operating the auger 40, first, in order to operate the auger 40, the boom 30 should be expanded and contracted as much as possible using the operation lever 12. When the auger 40 is slowly rolled up, the fixing device moves downward, and when the operation lever 12 is turned "right", the auger 40 is raised while being turned right.
오거장치가 하강한 후 오거(40)를 계속 우회전시키면 격납와이어로 스톱퍼(미도시)에서 자동으로 빠지게 되며, 하강된 오거(40)를 굴착하고자 하는 위치까지 이동시킨 후 오거(40)의 끝단부가 지면에 닿을 때까지 붐(30)을 내리고 오거(40)를 우회전시키면서 붐(30)를 하강시키면 지면에 구멍을 팔수 있게 된다.After the auger is lowered, if the auger 40 continues to turn right, the auger 40 is automatically removed from a stopper (not shown) with a containment wire, and the end of the auger 40 is moved to a position to be excavated. Lowering the boom 30 and lowering the boom 30 while turning the auger 40 right until it touches the ground is able to sell holes in the ground.
상기에서 붐(30)을 하강시킬 때에는 토질의 상황을 고려하여 조작석(11)에 위치한 악셀레이터(미도시)로 굴착속도를 조절하는 것이 바람직함은 물론이다.When the boom 30 is lowered in the above, it is of course preferable to adjust the excavation speed with an accelerator (not shown) located in the operator's seat 11 in consideration of the soil conditions.
이상에서와 같은 본 발명의 건주크레인(1)은 종래의 건주크레인이 수행할 수 없었던 원거리 굴착작업 및 중량물의 견인과 이동작업을 원활하게 수행할 수 있게 될 뿐 아니라 보다 안전하고 효과적으로 건주작업을 수행할 수 있게 되면서도 작업에 필요한 인력은 크게 감소시킬 수 있게 되고, 안전성과 경제성, 그리고 작업시간의 단축등을 통해 건설현장의 작업성 및 생산성을 크게 향상시킬 수 있게 되는 것이다.As described above, the dry crane 1 of the present invention can smoothly perform the long distance excavation work and the towing and moving work of the heavy dry crane, which can not be performed by the conventional dry crane, and perform the dry work more safely and effectively. While being able to do so, the manpower required for the work can be greatly reduced, and the workability and productivity of the construction site can be greatly improved through safety, economical efficiency, and shortening of working time.
Claims (4)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1019920020774A KR960000108B1 (en) | 1992-11-06 | 1992-11-06 | Auger crane |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1019920020774A KR960000108B1 (en) | 1992-11-06 | 1992-11-06 | Auger crane |
Publications (2)
Publication Number | Publication Date |
---|---|
KR940011338A KR940011338A (en) | 1994-06-21 |
KR960000108B1 true KR960000108B1 (en) | 1996-01-03 |
Family
ID=19342603
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR1019920020774A KR960000108B1 (en) | 1992-11-06 | 1992-11-06 | Auger crane |
Country Status (1)
Country | Link |
---|---|
KR (1) | KR960000108B1 (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101538909B1 (en) * | 2014-10-28 | 2015-07-24 | 대원전기 주식회사 | Construction method for poles moving of electric-wire-stringing using pole holding divice |
KR101638389B1 (en) * | 2016-05-16 | 2016-07-11 | 주식회사 태강기업 | Vertical force assist device of Auger crane by triple stage beam of movable support |
KR101649542B1 (en) * | 2016-05-16 | 2016-08-19 | 주식회사 태강기업 | Auxiliary outrigger of Auger crane by triple stage assist beam of movable support |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN118164357B (en) * | 2024-05-13 | 2024-07-05 | 新乡市锦盛建设工程有限公司 | Hoisting machine for transferring building construction materials |
-
1992
- 1992-11-06 KR KR1019920020774A patent/KR960000108B1/en not_active IP Right Cessation
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101538909B1 (en) * | 2014-10-28 | 2015-07-24 | 대원전기 주식회사 | Construction method for poles moving of electric-wire-stringing using pole holding divice |
WO2016068472A1 (en) * | 2014-10-28 | 2016-05-06 | 대원전기 주식회사 | Construction method for moving electric pole using pole holding device system without replacing aerial conductor wire |
KR101638389B1 (en) * | 2016-05-16 | 2016-07-11 | 주식회사 태강기업 | Vertical force assist device of Auger crane by triple stage beam of movable support |
KR101649542B1 (en) * | 2016-05-16 | 2016-08-19 | 주식회사 태강기업 | Auxiliary outrigger of Auger crane by triple stage assist beam of movable support |
Also Published As
Publication number | Publication date |
---|---|
KR940011338A (en) | 1994-06-21 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US4118010A (en) | Multi-purpose lifting and mounting assembly | |
US20080038106A1 (en) | Mobile lift device | |
US4446976A (en) | Reversible outrigger crane support | |
US10611616B2 (en) | Aerial device with quick-coupling implement | |
US20110150613A1 (en) | Integrated Boom/Underlift Assembly and Support Device | |
US5445281A (en) | Light-duty electric crane | |
US3937443A (en) | Crankcase guard jack utilizing double parallelogram | |
US10662046B1 (en) | Boom-mountable material handler | |
KR960000108B1 (en) | Auger crane | |
US5119961A (en) | Electric pickup winch | |
KR20130069535A (en) | Multipurpose folding type mounting posts for vehicle auger crane | |
US2595897A (en) | Tractor mounted crane | |
US4050259A (en) | Safety shield and temporary roof support | |
GB2552222B (en) | Mobile suspended platform apparatus | |
WO2020071844A1 (en) | Excavator having extendable boom | |
JP7132821B2 (en) | Work vehicle safety device | |
JP6468297B2 (en) | Construction machine scaffold mounting structure and mounting method | |
CN217173057U (en) | Fixed lifting device that uses on girder steel | |
JPS5925961Y2 (en) | Pile driving leader with jib boom | |
JP4953500B2 (en) | Control device for work equipment | |
CN221565606U (en) | Hoisting and installing device for hoisting large-diameter pipeline | |
KR100354335B1 (en) | Apparatus For Assembling Tunnel Support | |
KR200354660Y1 (en) | Outrigger variable Apparatus of Vehicle for Industry | |
JPH08217372A (en) | Main hook for crane | |
JP3075513B2 (en) | Work vehicle for mounting reinforcement |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A201 | Request for examination | ||
E902 | Notification of reason for refusal | ||
G160 | Decision to publish patent application | ||
E701 | Decision to grant or registration of patent right | ||
GRNT | Written decision to grant | ||
FPAY | Annual fee payment |