Nothing Special   »   [go: up one dir, main page]

KR102714639B1 - Pillar wall for utility tunnels that maximizes productivity and economy through high-quality manufacturability, easy workability, construction safety, and shortened construction period, and a construction method for utility tunnels using the above Pillar walls - Google Patents

Pillar wall for utility tunnels that maximizes productivity and economy through high-quality manufacturability, easy workability, construction safety, and shortened construction period, and a construction method for utility tunnels using the above Pillar walls Download PDF

Info

Publication number
KR102714639B1
KR102714639B1 KR1020240025551A KR20240025551A KR102714639B1 KR 102714639 B1 KR102714639 B1 KR 102714639B1 KR 1020240025551 A KR1020240025551 A KR 1020240025551A KR 20240025551 A KR20240025551 A KR 20240025551A KR 102714639 B1 KR102714639 B1 KR 102714639B1
Authority
KR
South Korea
Prior art keywords
wall
wing
filler
construction
column
Prior art date
Application number
KR1020240025551A
Other languages
Korean (ko)
Inventor
김익배
김총명
Original Assignee
(주)더케이프리캐스트
김익배
김총명
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by (주)더케이프리캐스트, 김익배, 김총명 filed Critical (주)더케이프리캐스트
Priority to KR1020240025551A priority Critical patent/KR102714639B1/en
Application granted granted Critical
Publication of KR102714639B1 publication Critical patent/KR102714639B1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/06Foundation trenches ditches or narrow shafts
    • E02D17/08Bordering or stiffening the sides of ditches trenches or narrow shafts for foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/02Sheet piles or sheet pile bulkheads
    • E02D5/03Prefabricated parts, e.g. composite sheet piles
    • E02D5/10Prefabricated parts, e.g. composite sheet piles made of concrete or reinforced concrete
    • E02D5/105Prefabricated parts, e.g. composite sheet piles made of concrete or reinforced concrete of prestressed concrete
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0023Cast, i.e. in situ or in a mold or other formwork
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0046Production methods using prestressing techniques
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/20Miscellaneous comprising details of connection between elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Chemical & Material Sciences (AREA)
  • Composite Materials (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

본 발명은 고품질 제작성과 용이한 작업성, 시공 안전성과 공기단축을 통한 생산성과 경제성이 극대화된 토목구조물용 필러월에 관한 것이다.
이에 본 발명의 기술적 요지는 토목구조물의 외벽체를 구성함에 있어서 신개념의 필러월('날개기둥'이라 함)을 도입하도록 하되, 이러한 필러월은 기둥부와 날개부(외날개형 또는 양날개형)가 프리캐스트 콘크리트(PC: Precast Concrete)를 통해 일체로 제작된 것으로, 종전 대비 PC제작 품질(제작몰드에 콘크리트 주입시 균일한 분포로 높은 밀도의 주입이 가능하고 한번에 양생이 가능함/ 종전 피씨월 제품은 한쪽을 먼저 타설 양생하고 반대로 뒤집어 다음날 나머지 한쪽을 타설 양생함으로서, 이틀 작업이 소요됨-납기를 맞출 수 없음)이 월등하게 개선되도록 함은 물론 상하부 동시 생산방식에 의해 제작 생산시간과 공사기간을 현저하게 단축시킬 수 있도록 하는 바, 이는 생산성과 경제성이 크게 향상됨은 물론 속채움 콘크리트 채움시 측압에 대한 내력이 보장되면서 안전성과 함께 우수한 품질이 확보되도록 하는 것을 특징으로 한다.
또한, 본 발명의 필러월은 기초 바닥(기초 바닥으로부터 분기된 연결철근이 기둥부 저면에 형성된 스플라이스 슬리브에 삽입된 후 초고강도 무수축 몰탈이 채워져 경화되면 기초 바닥과 구조 일체화가 형성됨)과의 초기 일체화 공정으로 인해 고강성 구조가 확보되도록 하는 바, 종전 대비 측압이나 부력을 방지하기 위한 하드웨어의 사용 및 뒤틀림 방지를 위한 가설보강 작업이 원천적으로 생략되어 시공원가를 크게 절감할 수 있음은 물론 작업시간이 2배 이상 감소되면서 불필요한 인건비 낭비가 완전히 해소되도록 하는 것을 특징으로 한다.
또한, 본 발명은 단위식 필러월들이 날개부측 방향을 향해 연속적으로 이음 조립(필러월 연속화 공법: 기초 바닥으로부터 분기된 연결철근이 기둥부 저면에 형성된 스플라이스 슬리브에 삽입된 후 초고강도 무수축 몰탈이 채워져 경화되면 기초 바닥과 구조 일체화가 형성됨)되면서 벽체 구간을 완성하도록 하는 바, 이는 조립시간을 두배 이상 절감할 수 있음은 물론 필러월에 의한 벽체 조립후 1일 양생이 완료되면 바로 피씨슬래브(JRS 사용)를 조립할 수 있도록 함으로서, 공사기간을 절반 이상으로 줄일 수 있도록 하는 것을 특징으로 한다.
The present invention relates to a filler wall for civil engineering structures that maximizes productivity and economy through high-quality production, easy workability, construction safety, and shortening of construction period.
Accordingly, the technical gist of the present invention is to introduce a new concept of filler wall (referred to as 'wing column') in constructing the outer wall of a civil engineering structure, and this filler wall is manufactured integrally with the column part and the wing part (single wing type or double wing type) using precast concrete (PC), so that the PC manufacturing quality (high density injection is possible with uniform distribution when pouring concrete into the manufacturing mold and curing is possible at once/conventional PC wall products were poured and cured on one side first and then turned over and poured and cured on the other side the next day, which took two days - making it impossible to meet the delivery date) is significantly improved, and the manufacturing time and construction period can be significantly shortened by the upper and lower simultaneous production method, which greatly improves productivity and economy, and is characterized by ensuring the strength against lateral pressure when filling the inner fill concrete, while ensuring safety and excellent quality.
In addition, the filler wall of the present invention secures a high-strength structure due to the initial integration process with the foundation floor (when connecting reinforcing bars branched from the foundation floor are inserted into splice sleeves formed on the bottom surface of the column portion and then ultra-high-strength non-shrink mortar is filled and hardened, structural integration with the foundation floor is formed), so that, compared to conventional methods, the use of hardware to prevent lateral pressure or buoyancy and temporary reinforcement work to prevent distortion are fundamentally omitted, so that the construction cost can be significantly reduced, and the work time is reduced by more than twice, so that unnecessary waste of labor costs is completely eliminated.
In addition, the present invention is characterized in that the unit-type filler walls are continuously joined and assembled toward the wing side (filler wall continuous method: connecting reinforcing bars branched from the foundation floor are inserted into splice sleeves formed on the bottom surface of the column, and then ultra-high-strength non-shrinkage mortar is filled and hardened to form a structural integration with the foundation floor) to complete the wall section, which not only reduces the assembly time by more than twice, but also allows the PC slab (using JRS) to be assembled immediately after one day of curing is completed after the wall assembly using the filler walls, thereby reducing the construction period by more than half.

Description

고품질 제작성과 용이한 작업성, 시공 안전성과 공기단축을 통한 생산성과 경제성이 극대화된 토목구조물용 필러월{Pillar wall for utility tunnels that maximizes productivity and economy through high-quality manufacturability, easy workability, construction safety, and shortened construction period, and a construction method for utility tunnels using the above Pillar walls}Pillar wall for utility tunnels that maximizes productivity and economy through high-quality manufacturability, easy workability, construction safety, and shortened construction period, and a construction method for utility tunnels using the above Pillar walls

본 발명은 공동구, 반도체 폐수처리장, 지하주차장의 옹벽을 포함한 토목구조물의 외벽체를 구성함에 있어서 신개념의 필러월(일명 '날개기둥'이라 함)을 도입하도록 하되, 이러한 필러월은 최근 대형화 추세의 토목구조물(과거에는 물량이나 소화량 또는 소비량이나 처리용량이 크지 않아도 감당이 가능한 소형 박스 구조물로 제작됨/ 종전 박스 일체형 구조물은 사각의 규격 자체만으로 운반 자체가 곤란하거나 불가한 경우가 있음)에 적용 가능하도록 한 것으로, 종전 박스형 토목구조물 대비 기초 바닥, 외벽체, 슬래브를 각각 구분된 구조로 분할 설계한 뒤 외벽체를 이루는 부분에 단위식 필러월을 연속 조립시공할 수 있도록 하는 바, 이는 획기적인 공기단축을 도모함은 물론 월등하게 우수한 운반성과 취급성 및 작업성을 보장하고, 특히 초대형화 구조의 토목구조물(건축구조물에도 적용 가능함) 시공에 더할 나위 없이 적합한 것을 특징으로 하는 고품질 제작성과 용이한 작업성, 시공 안전성과 공기단축을 통한 생산성과 경제성이 극대화된 토목구조물(공동구, 폐수처리장, 지하주차장 포함)용 필러월 및 상기 필러월을 이용한 토목구조물 시공방법에 관한 것이다.The present invention introduces a new concept of filler wall (also called 'wing column') in constructing the outer wall of civil engineering structures including retaining walls of common areas, semiconductor wastewater treatment plants, and underground parking lots, and such filler wall is applicable to civil engineering structures that are recently trending toward large-scale construction (in the past, they were manufactured as small box structures that could handle even when the amount of water, digestion, consumption, or treatment capacity was not large/in some cases, the transportation of conventional box-integrated structures was difficult or impossible due to the square size alone). Compared to conventional box-type civil engineering structures, the foundation floor, outer wall, and slab are each designed as separate structures, and then unit-type filler walls can be continuously assembled and constructed in the part that forms the outer wall. This not only aims for a groundbreaking shortening of the construction period, but also guarantees outstandingly excellent transportability, handling, and workability, and is particularly suitable for the construction of ultra-large civil engineering structures (also applicable to building structures), and is characterized by high-quality production, easy workability, and construction safety. The present invention relates to a filler wall for civil engineering structures (including common areas, sewage treatment plants, and underground parking lots) with maximized productivity and economy through shortening of construction time, and a method for constructing civil engineering structures using the filler wall.

다시 말해, 이러한 본 발명의 필러월은 기둥부와 날개부(외날개형 또는 양날개형)가 프리캐스트 콘크리트(PC: Precast Concrete)를 통해 일체로 제작된 것으로, 종전 대비 PC제작 품질(제작몰드에 콘크리트 주입시 균일한 분포로 높은 밀도의 주입이 가능하고 한번에 양생이 가능함/ 종전 피씨월 제품은 한쪽을 먼저 타설 양생하고 반대로 뒤집어 다음날 나머지 한쪽을 타설 양생함으로서, 이틀 작업이 소요됨-납기를 맞출 수 없음)이 월등하게 개선되도록 함은 물론 상하부 동시 생산방식에 의해 제작 생산시간과 공사기간을 현저하게 단축시킬 수 있도록 하는 바, 이는 생산성과 경제성이 크게 향상됨은 물론 속채움 콘크리트 채움시 측압에 대한 내력이 보장되면서 안전성과 함께 우수한 품질이 확보되도록 하는 것을 특징으로 한다.In other words, the filler wall of the present invention is manufactured integrally with a column section and a wing section (single wing type or double wing type) using precast concrete (PC), and the quality of PC manufacturing is significantly improved compared to conventional methods (high density injection is possible with uniform distribution when pouring concrete into the manufacturing mold, and curing is possible at once/conventional PC wall products were poured and cured on one side first, then turned over and poured and cured on the other side the next day, which took two days - making it impossible to meet the delivery date), and the manufacturing time and construction period can be significantly shortened by the upper and lower simultaneous production method, which greatly improves productivity and economy, and is characterized by ensuring strength against lateral pressure when filling with inner concrete, while ensuring safety and excellent quality.

이에, 본 발명의 필러월은 기초 바닥(기초 바닥으로부터 분기된 연결철근이 기둥부 저면에 형성된 스플라이스 슬리브에 삽입된 후 초고강도 무수축 몰탈이 채워져 경화되면 기초 바닥과 구조 일체화가 형성됨)과의 초기 일체화 공정으로 인해 고강성 구조가 확보되도록 하는 바, 종전 대비 측압이나 부력을 방지하기 위한 하드웨어의 사용 및 뒤틀림 방지를 위한 가설보강 작업이 원천적으로 생략되어 시공원가를 크게 절감할 수 있음은 물론 작업시간이 2배 이상 감소되면서 불필요한 인건비 낭비가 완전히 해소되도록 하는 것을 특징으로 한다.Accordingly, the filler wall of the present invention secures a high-strength structure due to the initial integration process with the foundation floor (where connecting reinforcing bars branched from the foundation floor are inserted into splice sleeves formed on the bottom surface of the column portion, and then ultra-high-strength non-shrinkage mortar is filled and hardened to form a structural integration with the foundation floor), so that, compared to conventional methods, the use of hardware to prevent lateral pressure or buoyancy and temporary reinforcement work to prevent distortion are fundamentally omitted, so that the construction cost can be significantly reduced, and the work time is reduced by more than twice, so that unnecessary waste of labor costs is completely eliminated.

또한, 본 발명은 단위식 필러월들이 날개부측 방향을 향해 연속적으로 이음 조립(필러월 연속화 공법: 기초 바닥으로부터 분기된 연결철근이 기둥부 저면에 형성된 스플라이스 슬리브에 삽입된 후 초고강도 무수축 몰탈이 채워져 경화되면 기초 바닥과 구조 일체화가 형성됨)되면서 벽체 구간을 완성하도록 하는 바, 이는 조립시간을 두배 이상 절감할 수 있음은 물론 필러월에 의한 벽체 조립후 1일 양생이 완료되면 바로 피씨슬래브(JRS 사용)를 조립할 수 있도록 함으로서, 공사기간을 절반 이상으로 줄일 수 있도록 하는 것을 특징으로 한다.In addition, the present invention is characterized in that the unit-type filler walls are continuously joined and assembled toward the wing side (filler wall continuous method: connecting reinforcing bars branched from the foundation floor are inserted into splice sleeves formed on the bottom surface of the column, and then ultra-high-strength non-shrinkage mortar is filled and hardened to form a structural integral part with the foundation floor) to complete the wall section, which not only reduces the assembly time by more than twice, but also allows the PC slab (using JRS) to be assembled immediately after one day of curing is completed after the wall assembly using the filler walls, thereby reducing the construction period by more than half.

또한, 본 발명의 피씨슬래브는 JRS(제이알에스 슬래브: Jointless ribbed slab)를 사용하는 것으로, 일측 자유단이 타측 받침용 리브에 대응되면서 연속적으로 걸침 연결 조립되도록 하는 바, 이는 별도의 연결근이나 보강근 없이도 연속 이음이 이루어져 구조 일체성이 확보하도록 함은 물론 종래 피씨슬래브 대비 연결 지점(맞닿는 부분) 균열 원인을 원천적으로 방지하여 건축물의 내구성과 안정성 및 과 방수성이 크게 개선하도록 하는 것을 특징으로 한다.In addition, the PC slab of the present invention uses a JRS (Jointless ribbed slab), so that one free end corresponds to the other supporting rib and is continuously connected and assembled, which enables a continuous joint to be formed without a separate connecting bar or reinforcing bar, and not only secures structural integrity, but also fundamentally prevents the cause of cracks at the connecting point (contact portion) compared to the conventional PC slab, thereby greatly improving the durability, stability, and waterproofing of the building.

일반적으로 공동구(토목구조물 중 일 예시로 설명함)는 용수나 배수용의 수로가 도로, 철도, 제방 등의 아래에 매설되도록 하거나 지하도로를 포함한 전선로, 통신선로, 수도관, 열수송관, 중수도관, 쓰레기 수송관, 가스관, 하수도관 등 여러 가지 시설물을 도로 지하에 공동으로 매설하기 위하여 설치되도록 형성된다.In general, a common trench (explained as an example of a civil engineering structure) is formed to allow water or drainage channels to be buried under roads, railways, embankments, etc., or to allow for the joint burial of various facilities such as electric cables, communication lines, water pipes, heat transport pipes, waste water pipes, gas pipes, and sewer pipes, including underground roads, under the roads.

이에, 종래의 공동구는 현장에서 콘크리트를 타설 및 양생하는 방법으로 고전적인 시공(통상적으로 재래식 RC 공법이라 함/ 노동 집약적 구조로서, 기능인력이 부족하고, 동바리 공사가 필수적으로 요구되어 붕괴사고 및 중대재해 처벌법에 노출되는 문제 발생, 콘크리트 수급 차질 등의 문제가 지속됨)이 이루어졌으나, 최근에는 공기 단축 및 경제적인 시공을 위해 공장에서 미리 제작된 프리캐스트 콘크리트 구조물(PC자재 등)을 현장으로 운반하여 조립하는 것으로 대체되고 있는 추세이다.Accordingly, the conventional joint tunnel was constructed using the classical method of pouring and curing concrete on site (commonly referred to as the conventional RC method/labor-intensive structure, lack of skilled workers, and problems such as exposure to collapse accidents and the punishment of major disasters due to the indispensable requirement of support work, and continuous problems such as disruption in the supply of concrete), but recently, in order to shorten the construction period and achieve economical construction, the trend is to replace it with precast concrete structures (PC materials, etc.) manufactured in advance at the factory, transported to the site, and assembled.

이러한 프리캐스트 콘크리트 공법을 이용한 공동구는 시공속도가 빠르며 시공 후 즉시 되메우기를 할 수 있어 공사할 때 야기되는 시민 불편사항, 교통 흐름의 방해, 불필요한 시간낭비 등의 문제를 해결할 수 있으므로 복잡한 도심지 공사에 효과적이며, 철저한 품질관리에 의해 공장에서 생산되므로 품질이 균일하고, 고강도 콘크리트를 사용하므로 구조체의 수밀성과 내구성을 보장할 수 있는 등 여러 가지 장점을 가지고 있다.This type of precast concrete construction method for common areas has many advantages, such as the ability to be constructed quickly and to be backfilled immediately after construction, which eliminates problems such as inconvenience to citizens, disruption of traffic flow, and unnecessary waste of time that may arise during construction, making it effective for complex urban construction projects, ensuring uniform quality because it is produced in a factory under strict quality control, and using high-strength concrete to ensure watertightness and durability of the structure.

이를 보다 자세히 설명하면, 통상적으로 공동구가 설치될 장소에 터파기 및 기초 지반 정리작업을 한 후, 기초콘크리트를 타설한다. To explain this in more detail, typically, after excavation and foundation ground preparation work is done at the location where the joint is to be installed, foundation concrete is poured.

이에, 타설된 기초콘크리트가 양생되면 프리캐스트 콘크리트 부재 즉, 벽체와 슬래브를 현장으로 운반하여 조립함으로써 시공을 완료하게 된다.Accordingly, once the poured foundation concrete has cured, the precast concrete members, i.e. the walls and slabs, are transported to the site and assembled to complete the construction.

한편, 종래의 공동구 시공방법 더블월 시공방법은 샌드위치 패널 형태로 된 복수의 피씨 벽체 사이에 현장 콘크리트를 타설하여 양생함으로써, 2중 벽체에 의한 방수 기능을 일부 확보하고 구조의 강성을 유지하도록 실시되고 있다.Meanwhile, the conventional double wall construction method is implemented by pouring and curing on-site concrete between multiple PC walls in the form of sandwich panels to secure some of the waterproofing function of the double wall and maintain structural rigidity.

그러나, 더블월 공법은 복수의 벽체 사이에 측압 제어 및 뒤틀림 제어용 강재를 필수적으로 설치해야 하는 바, 좁은 공간에서의 긴결 작업시 작업자로 하여금 상당히 곤란하고 어려운 작업을 야기하게 되며, 특히 오랜 작업시간과 함께 안전상 위험에 노출되는 문제가 발생된다.However, the double-wall method requires the installation of steel materials for lateral pressure control and distortion control between multiple walls, which makes it considerably difficult and challenging for workers when working in tight spaces, and in particular, it creates problems of long working hours and exposure to safety hazards.

본 발명 필러월과 종전 더블월 간 대비-1Comparison between the filler wall of the present invention and the conventional double wall-1



또한, 종전의 더블월 방식은 위 대비표에서 보는 바와 같이, 한쌍의 벽체 사이에 속채움 콘크리트 채움시 부력(PC 부재가 콘크리트 채움에 따라 위로 상승하는 현상)이 발생되어 필연적으로 부력 제어용 하드웨어 자재(매립 철물에 앵글이 용접되는 것)와 측압 및 비틀림 내력 제어용 하드웨어가 필히 설치되어야 하는 바, 제조 원가상승과 함께 공기지연을 유발하면서 생산성을 저하시키는 문제 또한 발생된다.In addition, as seen in the comparison table above, the conventional double-wall method generates buoyancy (a phenomenon in which the PC member rises as the concrete is filled) when filling the inner wall between a pair of walls, so hardware materials for buoyancy control (angles welded to embedded ironwork) and hardware for controlling lateral pressure and torsional strength must be installed. This causes problems such as increased manufacturing costs, construction delays, and reduced productivity.

또한, 기존 더블월은 상하부 분리 생산방식으로서 제작생산 시간과 작업 인력이 과다하게 소요되며 콘크리트의 과다 충전 또한 발생되며, 상하분리 타설로 인해 충전 부분이 미흡하게 처리되어 불량을 야기하게 된다.In addition, the existing double wall is produced by separating the upper and lower parts, which requires excessive manufacturing time and labor, and also causes excessive filling of concrete. In addition, the filling part is insufficiently processed due to the upper and lower separate pouring, which causes defects.

또한, 종래의 더블월 시공방법은 하부 정착 철근과의 간섭이 발생되고, 프롭 서포트 존치기간이 과다하게 소요(재령 28일 강도 발현시까지)되며, 균열 제어용 와이어 메쉬를 추가로 보강해야 하면서 동시에 벽체 콘크리트 선타설 방식에 의한 비계 작업 발판 가설공사 등 부설작업이 과다하게 발생되고, 벽체 안정화(콘크리트 완전 양생)가 이루어진 후에야 슬래브의 조립이 가능하여 공사의 지연을 야기하게 된다.In addition, the conventional double-wall construction method causes interference with the lower anchorage rebar, requires an excessive prop support retention period (until strength development at 28 days), requires additional reinforcement with wire mesh for crack control, and at the same time, causes excessive auxiliary work such as scaffolding and footing construction due to the wall concrete pre-pouring method, and slab assembly is only possible after the wall is stabilized (concrete is completely cured), which delays the construction.

따라서, 본 발명에 따른 필러월의 개발 배경에 대하여 정리하면 아래 표와 같다.Accordingly, the background of the development of the filler wall according to the present invention is summarized in the table below.

본 발명 필러월의 개발 배경Background of development of the filler wall of the present invention



1. 대한민국 등록특허공보 제10-0924701호(2009.10.27)1. Republic of Korea Patent Publication No. 10-0924701 (October 27, 2009)

본 발명은 상술한 문제점을 해결하기 위한 것으로, 그 기술적 요지는 기둥부와 날개부(외날개형 또는 양날개형)가 프리캐스트 콘크리트(PC: Precast Concrete)를 통해 일체의 필러월로 제작되어 공동구, 반도체 폐수처리장, 지하주차장의 옹벽을 포함한 토목구조물의 외벽체를 구성하도록 하는 것으로, 종전 대비 PC제작 품질이 월등하게 개선되도록 함은 물론 상하부 동시 생산방식에 의해 제작 생산시간과 공사기간을 현저하게 단축시킬 수 있도록 하는 바, 이는 생산성과 경제성이 크게 향상됨은 물론 속채움 콘크리트 채움시 측압에 대한 내력이 보장되면서 안전성과 함께 우수한 품질이 확보되도록 하는 것을 제공함에 그 목적이 있다.The present invention is to solve the above-mentioned problems, and its technical gist is to manufacture a pillar part and a wing part (single wing type or double wing type) as an integral filler wall using precast concrete (PC: Precast Concrete) to form an outer wall of a civil engineering structure including a retaining wall of a common culvert, a semiconductor wastewater treatment plant, and an underground parking lot, thereby significantly improving the quality of PC manufacturing compared to the past, and significantly shortening the manufacturing production time and the construction period through the upper and lower simultaneous production method, which greatly improves productivity and economy, and provides the purpose of ensuring safety and excellent quality while guaranteeing the strength against lateral pressure when filling with inner fill concrete.





이에, 본 발명의 필러월은 기초 바닥과의 초기 일체화 공정으로 인해 고강성 구조가 확보되도록 하는 바, 종전 대비 측압이나 부력을 방지하기 위한 하드웨어의 사용 및 뒤틀림 방지를 위한 가설보강 작업이 원천적으로 생략되어 시공원가를 크게 절감할 수 있음은 물론 작업시간이 2배 이상 감소되면서 불필요한 인건비 낭비가 완전히 해소되도록 하는 것을 제공함에 그 목적이 있다.Accordingly, the filler wall of the present invention secures a high-strength structure due to the initial integration process with the base floor, thereby fundamentally omitting the use of hardware to prevent lateral pressure or buoyancy and the temporary reinforcement work to prevent distortion compared to conventional methods, thereby significantly reducing the construction cost and completely eliminating unnecessary waste of labor costs as the work time is reduced by more than twice.





이러한 본 발명은 가설발판 비계공사가 배제되는 공법으로, 무동바리 시공이 가능하고, 콘크리트 타설 전 수직 포스트 수평 난간대 설치 공사가 용이함은 물론 바닥 콘크리트 타설 후 수직망 설치가 편리한 것을 제공함에 그 목적이 있다.The purpose of the present invention is to provide a method that excludes scaffolding work, enables unsteady construction, makes it easy to install vertical posts and horizontal handrails before pouring concrete, and makes it convenient to install vertical nets after pouring floor concrete.





또한, 본 발명은 단위식 필러월들이 날개부측 방향을 향해 연속적으로 이음 조립(필러월 연속화 공법)되면서 벽체 구간을 완성하도록 하는 바, 이는 조립시간을 두배 이상 절감할 수 있음은 물론 필러월에 의한 벽체 조립후 1일 양생이 완료되면 바로 피씨슬래브(JRS 사용)를 조립할 수 있도록 함으로서, 공사기간을 절반 이상으로 줄일 수 있도록 하는 것을 제공함에 그 목적이 있다.In addition, the present invention provides a method for completing a wall section by continuously assembling unit-type filler walls toward the wing side (filler wall continuous construction method), which not only reduces the assembly time by more than twice, but also allows the PC slab (using JRS) to be assembled immediately after one day of curing is completed after the wall assembly using the filler walls, thereby reducing the construction period by more than half.





그리고, 본 발명의 필러월은 생산성이 매우 높으며 품질이 우수하고 경제적이며, 특히 강성이 확보된 구조로서, 야적과 상하차 작업이 용이한 것을 제공함에 그 목적이 있다.And, the purpose of the filler wall of the present invention is to provide a structure that is highly productive, of excellent quality, economical, and particularly rigid, and that facilitates loading and unloading operations.

다시 말해, 본 발명의 필러월 특징을 종전 더블월과 대비하여 아래와 같이 표로 정리한다.In other words, the filler wall features of the present invention are summarized in the table below in comparison with the conventional double wall.

본 발명 필러월과 종전 더블월 간 대비-2Comparison between the filler wall of the present invention and the conventional double wall-2



즉, 본 발명의 필러월은 최근 대형화 추세의 토목구조물(과거에는 물량이나 소화량 또는 소비량이나 처리성능이 크지 않아도 감당이 가능한 소형 박스 구조물로 제작됨/ 종전 박스 일체형 구조물은 사각의 규격 자체만으로 운반 자체가 곤란하거나 불가한 경우가 있음)에 적용 가능하도록 한 것으로, 종전 박스형 토목구조물 대비 기초 바닥, 외벽체, 슬래브를 각각 구분된 구조로 분할 설계한 뒤 외벽체를 이루는 부분에 단위식 필러월을 연속 조립시공할 수 있도록 하는 바, 이는 획기적인 공기단축을 도모함은 물론 월등한 운반성과 취급성 및 작업성을 보장하고, 특히 초대형화 구조의 토목구조물 시공에 더할 나위 없이 적합한 것을 제공함에 그 목적이 있다.That is, the filler wall of the present invention is applicable to civil engineering structures that have recently become larger (in the past, they were manufactured as small box structures that could handle even large quantities of material, digestion volumes, consumption volumes, or processing performance/conventional box-integrated structures were sometimes difficult or impossible to transport due to their square dimensions alone), and compared to conventional box-type civil engineering structures, the foundation floor, exterior wall, and slab are each designed as separate structures, and then unit-type filler walls can be continuously assembled and constructed in the portion forming the exterior wall. This not only aims to achieve a groundbreaking shortening of the construction period, but also ensures outstanding transportability, handling, and workability, and in particular, provides something that is ideally suited to the construction of ultra-large civil engineering structures.

아울러, 본 발명의 피씨슬래브는 JRS(제이알에스 슬래브: Jointless ribbed slab)를 사용하는 것으로, 일측 자유단이 타측 받침용 리브에 대응되면서 연속적으로 걸침 연결 조립되도록 하는 바, 이는 별도의 연결근이나 보강근 없이도 연속 이음이 이루어져 구조 일체성이 확보하도록 함은 물론 종래 피씨슬래브 대비 연결 지점(맞닿는 부분) 균열 원인을 원천적으로 방지하여 건축물의 내구성과 안정성 및 과 방수성이 크게 개선하도록 하는 것을 제공함에 그 목적이 있다.In addition, the PC slab of the present invention uses a JRS (Jointless ribbed slab), so that one free end corresponds to a supporting rib on the other side and is continuously connected and assembled, which enables a continuous joint without a separate connecting bar or reinforcing bar, and not only secures structural integrity by fundamentally preventing the cause of cracks at the connecting point (contact part) compared to the conventional PC slab, but also provides a purpose of greatly improving the durability, stability, and waterproofing of the building.

이러한 목적을 달성하기 위해 본 발명의 필러월(W)은 상하 높이방향을 따라 일정 길이(5~10m 내외)를 갖는 기둥부(100: 가로_300~500mm * 세로_600~1000mm 내외로 설정된 지지면적을 확보하면서 기립되는 주면적)와 날개부(200: 기둥부의 폭방향 단부 일면 또는 양면에 설정된 간격(200~500mm)을 두고 한쌍의 날개부가 수평하게 분기되는 보조면적)가 프리캐스트 콘크리트(PC: Precast Concrete)를 통해 일체로 결합되도록 형성된다.To achieve this purpose, the filler wall (W) of the present invention is formed by integrally connecting a column part (100: a main surface area that secures a support area set to approximately 300 to 500 mm in width and approximately 600 to 1000 mm in length) having a predetermined length (approximately 5 to 10 m) in the vertical height direction and a wing part (200: an auxiliary area in which a pair of wing parts are horizontally branched at a set interval (200 to 500 mm) on one or both sides of the width direction end of the column part) using precast concrete (PC: Precast Concrete).

이에, 기둥부(100)는 바닥 저면부에 다수의 스플라이스 슬리브(110)가 구비되어 기초로부터 상향 분기된 연결철근(10)이 삽입된 후 초고강도 몰탈이 주입되면 경화시 기초 바닥과 일체화로 접합되도록 형성된다.Accordingly, the pillar part (100) is formed so that a number of splice sleeves (110) are provided on the bottom surface of the floor, into which connecting reinforcing bars (10) branching upward from the foundation are inserted, and then ultra-high strength mortar is injected so that when hardened, it is integrally connected to the foundation floor.

이때, 기둥부(100)로부터 분기된 복수의 날개부(200: 날개부 내부에는 보강철근이 삽입되어 있음)간 사이 공간 합성부(300)에는 속채움 콘크리트(400)가 타설되어 양생된 후 필러월(W) 간 일체성을 확보하도록 형성된다.At this time, the filling concrete (400) is poured into the composite space (300) between the plurality of wing parts (200: reinforcing bars are inserted inside the wing parts) branched from the pillar part (100), cured, and then formed to secure the integrity between the filler walls (W).

또한, 필러월(W)은 기둥부(100)를 기준으로 돌출된 날개부(200) 측으로 단차홈(500: 단차홈에 삽입된 날개부의 외측단 일측에는 직교방향으로 관통된 체결볼트(600)가 구비되거나 누수방지용 러버씰 가스켓(700)이 삽입)이 형성되어 이웃한 필러월(W-1, W-2 ... W-x)들이 연속 이음 연결되면서 토목구조물(예컨데, 공동구)의 외곽 구조(사각 또는 직사각 구조)를 이루도록 형성된다.In addition, the filler wall (W) is formed with a step groove (500: a fastening bolt (600) that penetrates in a orthogonal direction is provided on one side of the outer end of the wing portion inserted into the step groove, or a rubber seal gasket (700) for preventing water leakage is inserted) toward the wing portion (200) protruding from the pillar portion (100), so that neighboring filler walls (W-1, W-2 ... W-x) are continuously connected to form an outer structure (square or rectangular structure) of a civil engineering structure (e.g., a utility tunnel).

한편, 본 발명에 따른 필러월을 이용한 토목구조물(예컨데, 공동구) 시공방법은 기둥부(100)와 날개부(200: 기둥부의 폭방향 단부 일측 또는 양측에 한쌍씩 수평하게 구비)가 프리캐스트 콘크리트(PC: Precast Concrete)를 통해 일체의 필러월(W)이 형성되도록 하되, 기둥부의 바닥 저면부에는 다수의 스플라이스 슬리브(110)가 구비되어 기초로부터 상향 분기된 연결철근이 스플라이스 슬리브(110)에 삽입된 후 초고강도 몰탈 주입에 의해 경화시 기초 바닥과 일체화 접합되도록 형성되고, 필러월(W)은 기둥부를 기준으로 돌출된 날개부 측에는 단차홈(500: 단차홈에 삽입된 날개부의 외측단 일측에는 직교방향으로 관통된 체결볼트(600)가 구비되거나 누수방지용 러버씰 가스켓(700)이 삽입)이 형성되어 이웃한 필러월(W-1, W-2 ... W-x)들이 연속 이음 연결되면서 토목구조물(예컨데, 공동구)의 외곽 구조(사각 또는 직사각 구조)를 이루도록 시공하는 필러월 조립단계(S100)와; 기둥부(100)로부터 분기된 복수의 날개부(200: 날개부 내부에는 보강철근이 삽입되어 있음) 사이 공간 합성부(300)마다 속채움 콘크리트(400)가 타설되어 양생되도록 하는 속채움 콘트리트 타설 및 양생단계(S200)와; 필러월(W)을 통한 토목구조물(예컨데, 공동구)의 외곽구조 시공이 완료되면 상측 단부에 다수의 피씨 슬래브(800)를 나란히 안착시킨 후 배근된 철근에 대하여 철선을 통해 이음 연결하도록 하는 피씨슬래브(JRS 사용) 조립단계(S300)와; 피씨슬래브(800)에 의해 토목구조물(예컨데, 공동구)의 천정부가 조립되면 현장타설 토핑 콘크리트(900)를 타설하여 천정부를 완성하도록 하는 토핑 콘크리트 타설 및 양생단계(S400)가; 구성되어 이루어진다.Meanwhile, a method for constructing a civil engineering structure (e.g., a culvert) using a filler wall according to the present invention is such that a pillar part (100) and a wing part (200: a pair of them are provided horizontally on one side or both sides of the width direction end of the pillar part) are formed as an integral filler wall (W) using precast concrete (PC), and a plurality of splice sleeves (110) are provided on the bottom surface of the pillar part so that connecting reinforcing bars branching upward from the foundation are inserted into the splice sleeves (110) and then formed to be integrally joined with the foundation floor when hardened by injection of ultra-high strength mortar, and the filler wall (W) is formed with a step groove (500: a fastening bolt (600) that penetrates in a orthogonal direction is provided on one side of the outer end of the wing part inserted into the step groove or a rubber seal gasket (700) for preventing water leakage) on the wing part side protruding from the pillar part so that adjacent filler walls (W-1, W-2 ... W-x) are continuous. A filler wall assembly step (S100) in which the outer structure (square or rectangular structure) of a civil engineering structure (e.g., a utility tunnel) is formed by connecting the joints; a filler concrete pouring and curing step (S200) in which filler concrete (400) is poured and cured in each composite part (300) of a plurality of wing parts (200: reinforcing bars are inserted into the inside of the wing parts) branched off from a column part (100); a PC slab (using JRS) assembly step (S300) in which a plurality of PC slabs (800) are placed side by side on the upper end when the outer structure of the civil engineering structure (e.g., a utility tunnel) is completed and then the arranged reinforcing bars are connected by connecting them using steel wires; When the ceiling of a civil engineering structure (e.g., a utility tunnel) is assembled by a PC slab (800), a topping concrete pouring and curing step (S400) is performed to complete the ceiling by pouring on-site topping concrete (900).

이와 같이, 본 발명은 공동구, 반도체 폐수처리장, 지하주차장의 옹벽을 포함한 토목구조물의 외벽체를 구성함에 있어서, 신개념의 필러월('날개기둥'이라 함)을 도입하도록 하되, 이러한 필러월은 기둥부와 날개부(외날개형 또는 양날개형)가 프리캐스트 콘크리트(PC: Precast Concrete)를 통해 일체로 제작된 것으로, 종전 대비 PC제작 품질(제작몰드에 콘크리트 주입시 균일한 분포로 높은 밀도의 주입이 가능하고 한번에 양생이 가능함/ 종전 피씨월 제품은 한쪽을 먼저 타설 양생하고 반대로 뒤집어 다음날 나머지 한쪽을 타설 양생함으로서, 이틀 작업이 소요됨-납기를 맞출 수 없음)이 월등하게 개선되도록 하는 효과가 있다.In this way, the present invention introduces a new concept of filler wall (referred to as 'wing column') in constructing the outer wall of civil engineering structures including retaining walls of joint culverts, semiconductor wastewater treatment plants, and underground parking lots, and this filler wall is manufactured integrally with a column portion and a wing portion (single wing type or double wing type) using precast concrete (PC), which has the effect of significantly improving the PC manufacturing quality (high density injection is possible with uniform distribution when pouring concrete into the manufacturing mold, and curing is possible at once/previous PC wall products were poured and cured on one side first, then turned over and poured and cured on the other side the next day, which required two days of work - making it impossible to meet the delivery date) compared to conventional methods.

다시 말해, 본 발명의 필러월은 최근 대형화 추세의 토목구조물에 적용 가능하도록 한 것으로, 종전 박스형 토목구조물 대비 기초 바닥, 외벽체, 슬래브를 각각 구분된 구조로 분할 설계한 뒤 외벽체를 이루는 부분에 단위식 필러월을 연속 조립시공할 수 있도록 하는 바, 이는 획기적인 공기단축을 도모함은 물론 월등한 운반성과 취급성 및 작업성을 보장하고, 특히 초대형화 구조의 토목구조물 시공에 더할 나위 없이 적합한 효과가 있다.In other words, the filler wall of the present invention is applicable to civil engineering structures that have recently been trending toward large-scale structures. Compared to conventional box-type civil engineering structures, the foundation floor, exterior wall, and slab are each designed as separate structures, and then the unit-type filler walls can be continuously assembled and constructed on the portion forming the exterior wall. This not only achieves a groundbreaking shortening of construction time, but also guarantees outstanding transportability, handling, and workability, and is particularly suitable for the construction of ultra-large civil engineering structures.

또한, 본 발명은 상하부 동시 생산방식에 의해 제작 생산시간과 공사기간을 현저하게 단축시킬 수 있도록 하는 바, 이는 생산성과 경제성이 크게 향상됨은 물론 속채움 콘크리트 채움시 측압에 대한 내력이 보장되면서 안전성과 함께 우수한 품질이 확보되도록 하는 효과가 있다.In addition, the present invention enables the manufacturing time and construction period to be significantly shortened by the upper and lower simultaneous production method, which not only greatly improves productivity and economy, but also has the effect of ensuring safety and excellent quality while guaranteeing the strength against lateral pressure when filling with inner fill concrete.

이에, 본 발명의 필러월은 기초 바닥(기초 바닥으로부터 분기된 연결철근이 기둥부 저면에 형성된 스플라이스 슬리브에 삽입된 후 초고강도 무수축 몰탈이 채워져 경화되면 기초 바닥과 구조 일체화가 형성됨)과의 초기 일체화 공정으로 인해 고강성 구조가 확보되도록 하는 효과가 있다.Accordingly, the filler wall of the present invention has the effect of securing a high-strength structure due to the initial integration process with the foundation floor (when connecting reinforcing bars branched from the foundation floor are inserted into splice sleeves formed on the bottom surface of the column portion and then ultra-high-strength non-shrinkage mortar is filled and hardened, structural integration with the foundation floor is formed).

이러한 본 발명은 종전 대비 측압이나 부력을 방지하기 위한 하드웨어의 사용 및 뒤틀림 방지를 위한 가설보강 작업이 원천적으로 생략되어 시공원가를 크게 절감할 수 있음은 물론 작업시간이 2배 이상 감소되면서 불필요한 인건비 낭비가 완전히 해소되도록 하는 효과가 있다.This invention fundamentally omits the use of hardware to prevent lateral pressure or buoyancy and the reinforcement work to prevent distortion compared to conventional methods, thereby significantly reducing construction costs and completely eliminating unnecessary waste of labor costs as the work time is reduced by more than twice.

또한, 본 발명은 단위식 필러월들이 날개부측 방향을 향해 연속적으로 이음 조립(필러월 연속화 공법: 기초 바닥으로부터 분기된 연결철근이 기둥부 저면에 형성된 스플라이스 슬리브에 삽입된 후 초고강도 무수축 몰탈이 채워져 경화되면 기초 바닥과 구조 일체화가 형성됨)되면서 벽체 구간을 완성하도록 하는 효과가 있다.In addition, the present invention has the effect of completing a wall section by continuously connecting and assembling unit-type filler walls toward the wing side (filler wall continuous method: connecting reinforcing bars branched from the foundation floor are inserted into splice sleeves formed on the bottom surface of the column section, and then ultra-high strength non-shrinkage mortar is filled and hardened to form a structural unit with the foundation floor).

이러한 본 발명은 조립시간을 두배 이상 절감할 수 있음은 물론 필러월에 의한 벽체 조립후 1일 양생이 완료되면 바로 피씨슬래브(JRS 사용)를 조립할 수 있도록 함으로서, 공사기간을 절반 이상으로 줄일 수 있도록 하는 효과가 있다.This invention not only reduces the assembly time by more than two times, but also enables the PC slab (using JRS) to be assembled immediately after the wall assembly using the filler wall is cured for one day, thereby reducing the construction period by more than half.

또한, 본 발명의 피씨슬래브는 JRS(제이알에스 슬래브: Jointless ribbed slab)를 사용하는 것으로, 일측 자유단이 타측 받침용 리브에 대응되면서 연속적으로 걸침 연결 조립되도록 하는 바, 이는 별도의 연결근이나 보강근 없이도 연속 이음이 이루어져 구조 일체성이 확보하도록 하는 효과가 있다.In addition, the PC slab of the present invention uses a JRS (Jointless ribbed slab), so that one free end corresponds to the other supporting rib and is continuously connected and assembled, which has the effect of ensuring structural integrity by forming a continuous joint without a separate connecting bar or reinforcing bar.

이에, 본 발명의 JRS(제이알에스 슬래브: Jointless ribbed slab)는 종래 피씨슬래브 대비 연결 지점(맞닿는 부분) 균열 원인을 원천적으로 방지하여 건축물의 내구성과 안정성 및 과 방수성이 크게 개선하도록 하는 효과가 있다.Accordingly, the JRS (Jointless ribbed slab) of the present invention has the effect of fundamentally preventing the cause of cracks at the connection point (contact portion) compared to the conventional PC slab, thereby greatly improving the durability, stability, and waterproofing of the building.

도 1은 본 발명에 따른 필러월이 적용된 토목구조물(예컨데, 공동구) 측단면 시공 예시도이다.
도 2 내지 도 4는 본 발명에 따른 외날개형 필러월의 조립 예시도이다.
도 5 내지 도 8은 본 발명에 따른 양날개형 필러월의 조립 예시도이다.
도 9 내지 도 10은 본 발명에 따른 피씨슬래브가 JRS 슬래브로 적용되어 시공되는 것을 나타낸 예시도이다.
Figure 1 is an example of a cross-sectional construction of a civil engineering structure (e.g., a utility tunnel) to which a filler wall according to the present invention is applied.
Figures 2 to 4 are assembly diagrams of a single-wing type filler wall according to the present invention.
Figures 5 to 8 are assembly diagrams of a double-wing type filler wall according to the present invention.
Figures 9 and 10 are exemplary views showing that a PC slab according to the present invention is applied and constructed as a JRS slab.

다음은 첨부된 도면을 참조하며 본 발명을 보다 상세히 설명하겠다.The present invention will now be described in more detail with reference to the attached drawings.

먼저, 도 1 내지 도 10에 도시된 바와 같이, 본 발명의 필러월(W)은 상하 높이방향을 따라 일정 길이(5~10m 내외)를 갖는 기둥부(100: 가로_300~500mm * 세로_600~1000mm 내외로 설정된 지지면적을 확보하면서 기립되는 주면적)와 날개부(200: 기둥부의 폭방향 단부 일면 또는 양면에 설정된 간격(200~500mm)을 두고 한쌍의 날개부가 수평하게 분기되는 보조면적)가 프리캐스트 콘크리트(PC: Precast Concrete)를 통해 일체로 결합되도록 형성된다.First, as illustrated in FIGS. 1 to 10, the filler wall (W) of the present invention is formed by integrally combining a column part (100: a main surface area that secures a support area set to approximately 300 to 500 mm in width and approximately 600 to 1000 mm in length) having a predetermined length (approximately 5 to 10 m) in the vertical height direction and a wing part (200: an auxiliary surface area in which a pair of wing parts are horizontally branched at a set interval (200 to 500 mm) on one or both sides of the widthwise end of the column part) using precast concrete (PC).

이에, 기둥부(100)는 바닥 저면부에 다수의 스플라이스 슬리브(110)가 구비되어 기초로부터 상향 분기된 연결철근(10)이 삽입된 후 초고강도 몰탈이 주입되면 경화시 기초 바닥과 일체화로 접합되도록 형성된다.Accordingly, the pillar part (100) is formed so that a number of splice sleeves (110) are provided on the bottom surface of the floor, into which connecting reinforcing bars (10) branching upward from the foundation are inserted, and then ultra-high strength mortar is injected so that when hardened, it is integrally connected to the foundation floor.

이때, 기둥부(100)로부터 분기된 복수의 날개부(200: 날개부 내부에는 보강철근이 삽입되어 있음)간 사이 공간 합성부(300)에는 속채움 콘크리트(400)가 타설되어 양생된 후 필러월(W) 간 일체성을 확보하도록 형성된다.At this time, the filling concrete (400) is poured into the composite space (300) between the plurality of wing parts (200: reinforcing bars are inserted inside the wing parts) branched from the pillar part (100), cured, and then formed to secure the integrity between the filler walls (W).

참고로 합성부 중 내면 중앙부에는 접합면적 증대 겸 방수홈(120)이 더 구비되어 속채움 콘크리트와의 접합성이 강화되도록 하면서 측방향으로 유입되는 우수나 물기가 누수되는 것을 차단할 수 있도록 하는 것이 바람직하다.For reference, it is desirable to provide a waterproof groove (120) in the central part of the inner surface of the composite section to increase the bonding area and strengthen the bonding with the filled concrete while blocking leakage of rainwater or moisture flowing in from the side.

또한, 필러월(W)은 기둥부(100)를 기준으로 돌출된 날개부(200) 측으로 단차홈(500: 단차홈에 삽입된 날개부의 외측단 일측에는 직교방향으로 관통된 체결볼트(600)가 구비되거나 누수방지용 러버씰 가스켓(700)이 삽입)이 형성되어 이웃한 필러월(W-1, W-2 ... W-x)들이 연속 이음 연결되면서 토목구조물(예컨데, 공동구)의 외곽 구조(사각 또는 직사각 구조)를 이루도록 형성된다.In addition, the filler wall (W) is formed with a step groove (500: a fastening bolt (600) that penetrates in a orthogonal direction is provided on one side of the outer end of the wing portion inserted into the step groove, or a rubber seal gasket (700) for preventing water leakage is inserted) toward the wing portion (200) protruding from the pillar portion (100), so that neighboring filler walls (W-1, W-2 ... W-x) are continuously connected to form an outer structure (square or rectangular structure) of a civil engineering structure (e.g., a utility tunnel).

한편, 본 발명에 따른 필러월을 이용한 토목구조물(공동구, 폐수처리장, 지하주차장 포함) 시공방법은 필러월 조립단계(S100), 속채움 콘트리트 타설 및 양생단계(S200), 피씨슬래브(JRS 사용) 조립단계(S300) 및 토핑 콘크리트 타설 및 양생단계(S400)로 구성되어 이루어진다.Meanwhile, the method for constructing a civil engineering structure (including a common culvert, a wastewater treatment plant, and an underground parking lot) using a filler wall according to the present invention is composed of a filler wall assembly step (S100), a filling concrete pouring and curing step (S200), a PC slab (using JRS) assembly step (S300), and a topping concrete pouring and curing step (S400).

이에, 필러월 조립단계(S100)는 기둥부(100)와 날개부(200: 기둥부의 폭방향 단부 일측 또는 양측에 한쌍씩 수평하게 구비)가 프리캐스트 콘크리트(PC: Precast Concrete)를 통해 일체의 필러월(W)이 형성되도록 한다.Accordingly, the filler wall assembly step (S100) forms an integral filler wall (W) by forming a column part (100) and wing parts (200: a pair horizontally provided on one or both sides of the width direction end of the column part) using precast concrete (PC: Precast Concrete).

이때, 기둥부의 바닥 저면부에는 다수의 스플라이스 슬리브(110)가 구비되어 기초로부터 상향 분기된 연결철근이 스플라이스 슬리브(110)에 삽입된 후 초고강도 몰탈 주입에 의해 경화시 기초 바닥과 일체화 접합되도록 형성된다.At this time, a number of splice sleeves (110) are provided on the bottom surface of the column section, and connecting reinforcing bars branching upward from the foundation are inserted into the splice sleeves (110) and then formed to be integrally joined with the foundation floor when hardened by injection of ultra-high strength mortar.

본 발명의 필러월 + 기초 바닥 접합 상세Details of the filler wall + base floor joint of the present invention



그리고, 필러월(W)은 기둥부를 기준으로 돌출된 날개부 측에는 단차홈(500: 단차홈에 삽입된 날개부의 외측단 일측에는 직교방향으로 관통된 체결볼트(600)가 구비되거나 누수방지용 러버씰 가스켓(700)이 삽입)이 형성되어 이웃한 필러월(W-1, W-2 ... W-x)들이 연속 이음 연결되면서 토목구조물(예컨데, 공동구)의 외곽 구조(사각 또는 직사각 구조)를 이루도록 형성된다.And, the filler wall (W) is formed with a step groove (500: a fastening bolt (600) that penetrates in a orthogonal direction is provided on one side of the outer end of the wing portion inserted into the step groove, or a rubber seal gasket (700) for preventing water leakage is inserted) on the wing portion side protruding from the pillar portion, so that neighboring filler walls (W-1, W-2 ... W-x) are continuously connected to form an outer structure (square or rectangular structure) of a civil engineering structure (e.g., a utility tunnel).

이때, 러버씰 가스켓(700)은 일측에 접합부가 형성되고, 타측에 속이 빈 튜브형 신축부가 형성되어 구성된다.At this time, the rubber seal gasket (700) is configured with a joint formed on one side and a hollow tube-shaped elastic part formed on the other side.

이에, 러버씰 가스켓(700)의 접합부는 기둥부 단차홈에 형성된 장착홈에 대입되어 본딩 접합되는 것으로, 해당 장착홈은 일종의 방수벽 역할을 겸하면서 접합용 홈을 이루도록 형성된다.Accordingly, the joint of the rubber seal gasket (700) is bonded by being inserted into the mounting groove formed in the step groove of the pillar part, and the mounting groove is formed to form a joint groove while also serving as a kind of waterproof wall.

이때, 러버씰 가스켓(700)의 신축부는 중공형 탄성체로서 이웃한 필러월의 날개부와 대응(밀착)시 타원형으로 면적이 가변 확장되면서 기밀유지 면적을 넓게 확대시키도록 형성된다.At this time, the elastic portion of the rubber seal gasket (700) is formed as a hollow elastic body so that when it contacts (comes into close contact with) the wing portion of the adjacent filler wall, the area expands variably in an elliptical shape, thereby widely expanding the sealing area.

이러한 러버씰 가스켓은 외날개형 및 양날개형 전부에 적용가능한 것으로 한쌍의 날개부와 대응되도록 복수의 단차홈 내에 각각 장착홈이 형성되어 접합 및 삽입 설치가 가능하도록 하는 것이 바람직하다.These rubber seal gaskets are applicable to both single-wing and double-wing types, and it is preferable that mounting grooves are formed in each of a plurality of step grooves to correspond to a pair of wing sections so that jointing and insertion installation are possible.

또한, 본 발명의 필러월(양날개형을 기준으로 설명함)은 도 8에 도시된 바와 같이, 날개부 단부 일측에 요홈이 형성되어 플랫형 자(길이를 재는 도구 모양) 형태의 워터 스토퍼(Water Stopper)가 수납되면서 방수를 도모할 수 있도록 하되, 특히 날개부 중 어느 하나(토목구조물이 공동구일 경우 내측에 해당하는 부분) 단부에 끼움홈(이웃한 타측 필러월의 날개부와 한쌍을 이루는 것)이 형성되도록 하되, 끼움홈 사이에는 반구형 유로차단-바(bar: 실내측을 향해 볼록한 부분이 위치하도록 형성/ 일명 'Water Drainage downsout' 이라 함)가 장착되어 필러월 폭방향 바깥측으로부터 유입되는 물이 토목구조물 내측으로 유입되지 않고 밑으로 흘러 내릴 수 있도록 하는 것(기초 바닥에 형성된 트렌치 홈을 따라 물이 배수되도록 형성)이 바람직하다.In addition, as illustrated in FIG. 8, the filler wall of the present invention (described based on the double-wing type) has a groove formed on one end of the wing portion so that a water stopper in the shape of a flat ruler (a tool shape for measuring length) can be accommodated to promote waterproofing. In particular, it is preferable that an insertion groove (forming a pair with the wing portion of the adjacent filler wall on the other side) is formed on the end of one of the wing portions (the inner portion if the civil engineering structure is a common duct), and a hemispherical flow-blocking bar (a bar formed so that the convex portion is positioned toward the inner side/also called 'water drainage downsout') is installed between the insertion grooves so that water flowing in from the outer side in the width direction of the filler wall does not flow into the inner side of the civil engineering structure but flows down (formed so that water drains along a trench groove formed in the foundation floor).

이후, 속채움 콘트리트 타설 및 양생단계(S200)는 기둥부(100)로부터 분기된 복수의 날개부(200: 날개부 내부에는 보강철근이 삽입되어 있음) 사이 공간 합성부(300)마다 속채움 콘크리트(400)가 타설되어 양생되도록 형성된다.Thereafter, in the filling concrete pouring and curing step (S200), filling concrete (400) is poured and cured in each composite space (300) between multiple wing sections (200: reinforcing bars are inserted inside the wing sections) branched from the column section (100).

이후, 피씨슬래브(JRS 사용) 조립단계(S300)는 필러월(W)을 통한 토목구조물(예컨데, 공동구)의 외곽구조 시공이 완료되면 상측 단부에 다수의 피씨 슬래브(800)를 나란히 안착시킨 후 배근된 철근에 대하여 철선을 통해 이음 연결하도록 형성된다.Thereafter, the PC slab (JRS usage) assembly step (S300) is formed by placing a plurality of PC slabs (800) side by side on the upper end after the construction of the outer structure of the civil engineering structure (e.g., common area) through the filler wall (W) is completed, and then connecting the arranged reinforcing bars with steel wires.

이때, 피씨슬래브는 JRS(제이알에스 슬래브)로서, 패널(810) 하부에 다수개의 지지리브(820)가 형성되도록 하되, 패널의 폭방향 일측단에는 L자형 걸림턱(830)을 갖는 받침용 리브(840)가 형성되고, 받침용 리브(840)와 대응되는 패널의 반대측에는 ㅡ자형 자유단(850)이 형성되어 이웃한 슬래브와 연결시 연속성이 확보되도록 함은 물론 길이방향 단부는 필러월과의 경간 상면측에 걸침되어 사면지지(Quadrilaterals Supporting)가 이루어지도록 형성된다.At this time, the PC slab is a JRS (JRS slab), and a plurality of support ribs (820) are formed at the bottom of the panel (810), and a support rib (840) having an L-shaped catch (830) is formed at one end in the width direction of the panel, and an ㅡ-shaped free end (850) is formed at the opposite end of the panel corresponding to the support rib (840) so as to ensure continuity when connecting to an adjacent slab, and the longitudinal end is formed so as to hang over the upper surface of the span with the filler wall to achieve quadrilaterals supporting.

이후, 토핑 콘크리트 타설 및 양생단계(S400)는 피씨슬래브(800)에 의해 토목구조물(예컨데, 공동구)의 천정부가 조립되면 현장타설 토핑 콘크리트(900)를 타설하여 천정부를 완성하도록 형성된다.Afterwards, the topping concrete pouring and curing step (S400) is formed by pouring on-site topping concrete (900) to complete the ceiling when the ceiling of a civil engineering structure (e.g., a common area) is assembled by the PC slab (800).

다음은 본 발명에 따른 필러월 시공 프로세스에 대하여 보다 자세히 설명하도록 한다.The following describes in more detail the filler wall construction process according to the present invention.

(1) 기초공사 프로세스(1) Basic construction process

가. 필러월(날개기둥) 기초 바닥 먹매김 - 수평 규준틀 인수 인계, 기준 먹 설정(외부 수평 규준틀 설치)A. Filler wall (wing column) foundation floor mortar - Horizontal standard frame takeover, standard mortar setting (external horizontal standard frame installation)

나. 하부 철근 배근B. Lower reinforcement arrangement

다. 필러월(날개기둥) 앵커 프레임 설치 - Template 중심선 검측, 스플라이스 슬리브 정착 철근 보양D. Installation of filler wall (wing column) anchor frame - Template centerline inspection, splice sleeve fixation reinforcement reinforcement

라. 상부 철근 배근A. Top reinforcement bar arrangement

마. 앵커 프레임 용접 고정B. Anchor Frame Welding Fixing

바. 콘크리트 마감 레벨 표기Bar. Concrete finish level marking

사. 콘크리트 타설4. Concrete pouring

아. 양생(동절기 2일, 하절기 1일)Ah. Yangsaeng (2 days in winter, 1 day in summer)

자. PC기둥 먹매김 - 기준 먹 검측, 기둥 먹 매김 검측Okay. PC pillar feeding - standard feeding inspection, pillar feeding inspection

차. 기둥 하부 레벨 작업 - 기준 레벨 검측Tea. Column lower level work - Reference level inspection

(2) 필러월(날개기둥) 조립 프로세스(2) Filler wall (wing pillar) assembly process

가. 필러월(날개기둥) 하역인양A. Pillar wall (wing pillar) unloading and lifting

나. 필러월(날개기둥) 인양 LUG 몰탈사출 미장B. Filler wall (wing column) lifting LUG mortar injection finishing

다. 필러월(날개기둥) 반전인양D. Filler wall (wing pillar) inversion

라. 필러월(날개기둥) 정착 철근 체크Ra. Check the anchoring reinforcing bars of the filler wall (wing column)

마. 필러월(날개기둥) 수직도 체크 -> 설치Ma. Check the verticality of the pillar (wing column) -> Install

바. 필러월(날개기둥) 리프팅 러그 해체B. Filler Wall (Wing Column) Lifting Lug Dismantling

사. 필러월(날개기둥) + 기초 바닥 - 거푸집 설치4. Filler wall (wing column) + foundation floor - Formwork installation

아. 필러월(날개기둥) + 기초 바닥 - 초고강도 몰탈 교반 -> 충진 -> 양생(50MPa/ 1일)Ah. Filler wall (wing column) + foundation floor - ultra-high strength mortar mixing -> filling -> curing (50MPa/1 day)

자. 필러월(날개기둥) 연속 이음 결합 - 속채움 콘크리트 충진 양생(구조 일체화)Yeah. Filler wall (wing column) continuous joint joint - filling concrete curing (structural integration)

(3) 피씨 슬래브 안착 조립(3) PC slab mounting assembly

JRS 슬래브 인양 후 안착 연속 시공 -> 슬래브 철근 배근(종전 대비 200% 생산성 증대)JRS slab lifting and stabilization continuous construction -> slab reinforcement arrangement (200% increase in productivity compared to previous years)

(4) 토핑콘크리트 현장 타설 양생 마감(4) Finishing of curing and pouring of topping concrete on site

필러월(날개기둥) 벽체 콘크리트 타설 후 슬래브 연속 타설 -> 미장 기계 피니셔 미장 마감After pouring the concrete for the filler wall (wing column), the slab is poured continuously -> Finishing with a finishing machine

본 발명은 상술한 특정의 바람직한 실시예에 한정되지 아니하며, 청구범위에서 청구하는 본 발명의 요지를 벗어남이 없이 당해 고안이 속하는 기술분야에서 통상의 지식을 가진 자라면 누구든지 다양한 변형실시가 가능한 것은 물론이고, 그와 같은 변경은 청구범위 기재의 범위 내에 있게 된다.The present invention is not limited to the specific preferred embodiments described above, and anyone with ordinary skill in the art to which the present invention pertains may make various modifications without departing from the gist of the present invention claimed in the claims, and such modifications are within the scope of the claims.

W ... 필러월 10 ... 연결철근
100 ... 기둥부 110 ... 스플라이스 슬리브
200 ... 날개부 300 ... 합성부
400 ... 속채움 콘크리트 500 ... 단차홈
600 ... 체결볼트 700 ... 러버씰 가스켓
800 ... 피씨슬래브 900 ... 토핑 콘크리트
W...filler wall 10...connecting bar
100 ... Column 110 ... Splice Sleeve
200 ... wing part 300 ... composite part
400 ... Filled concrete 500 ... Step groove
600 ... fastening bolt 700 ... rubber seal gasket
800...PC slab 900...topping concrete

Claims (5)

상하 높이방향을 따라 일정 길이를 갖는 기둥부(100)와 날개부(200)가 프리캐스트 콘크리트(PC)를 통해 일체로 결합되도록 하는 필러월(W)에 있어서,
기둥부(100)는 바닥 저면부에 다수의 스플라이스 슬리브(110)가 구비되어 기초로부터 상향 분기된 연결철근(10)이 삽입된 후 초고강도 몰탈이 주입되면 경화시 기초 바닥(30)과 일체화로 접합되도록 형성되고, 기둥부(100)로부터 분기된 복수의 날개부(200)간 사이 공간 합성부(300)에는 속채움 콘크리트(400)가 타설되어 양생된 후 필러월(W) 간 일체성을 확보하도록 형성되며, 필러월(W)은 기둥부(100)를 기준으로 돌출된 날개부(200) 측으로 단차홈(500)이 형성되어 이웃한 필러월(W-1, W-2 ... W-x)들이 연속 이음 연결되면서 토목구조물의 외곽 구조를 이루도록 형성되고, 기둥부(100)의 지지면적은 가로 300~500mm*세로 600~1000mm이고, 기둥부(100)의 폭방향 단부에는 한쌍의 날개부(200)가 200~500mm 간격으로 수평하게 분기되도록 하되, 단차홈(500)에 삽입된 날개부(200)의 외측단 일측에는 체결볼트(600)가 직교방향으로 관통 결합되도록 하는 것을 특징으로 하는 고품질 제작성과 용이한 작업성, 시공 안전성과 공기단축을 통한 생산성과 경제성이 극대화된 토목구조물용 필러월.
In a filler wall (W) in which a column part (100) and a wing part (200) having a certain length along the vertical height direction are integrally connected through precast concrete (PC),
The column part (100) is formed so that a plurality of splice sleeves (110) are provided on the bottom surface of the floor, and when connecting reinforcing bars (10) branching upward from the foundation are inserted and then ultra-high strength mortar is injected, the column part (100) is formed so that it is integrally connected with the foundation floor (30) when hardened, and the filling concrete (400) is poured into the composite part (300) between the plurality of wing parts (200) branched from the column part (100) and cured, and then the filler wall (W) is formed so that the integrity is secured, and the filler wall (W) is formed so that a step groove (500) is formed toward the wing part (200) protruding from the column part (100) so that the adjacent filler walls (W-1, W-2 ... Wx) are continuously connected to form the outer structure of the civil engineering structure, and the supporting area of the column part (100) is 300 to 500 mm in width and 600 to 1000 mm in length, A pillar wall for civil engineering structures with high quality, easy workability, and maximized productivity and economy through safety in construction and shortening of construction period, characterized in that a pair of wing parts (200) are horizontally branched at intervals of 200 to 500 mm at the widthwise end of a pillar part (100), and a fastening bolt (600) is connected in a orthogonal direction through one side of the outer end of the wing part (200) inserted into the step groove (500).
삭제delete 삭제delete 삭제delete 삭제delete
KR1020240025551A 2024-02-22 2024-02-22 Pillar wall for utility tunnels that maximizes productivity and economy through high-quality manufacturability, easy workability, construction safety, and shortened construction period, and a construction method for utility tunnels using the above Pillar walls KR102714639B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020240025551A KR102714639B1 (en) 2024-02-22 2024-02-22 Pillar wall for utility tunnels that maximizes productivity and economy through high-quality manufacturability, easy workability, construction safety, and shortened construction period, and a construction method for utility tunnels using the above Pillar walls

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020240025551A KR102714639B1 (en) 2024-02-22 2024-02-22 Pillar wall for utility tunnels that maximizes productivity and economy through high-quality manufacturability, easy workability, construction safety, and shortened construction period, and a construction method for utility tunnels using the above Pillar walls

Publications (1)

Publication Number Publication Date
KR102714639B1 true KR102714639B1 (en) 2024-10-11

Family

ID=93118852

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020240025551A KR102714639B1 (en) 2024-02-22 2024-02-22 Pillar wall for utility tunnels that maximizes productivity and economy through high-quality manufacturability, easy workability, construction safety, and shortened construction period, and a construction method for utility tunnels using the above Pillar walls

Country Status (1)

Country Link
KR (1) KR102714639B1 (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100924701B1 (en) 2006-05-30 2009-11-03 삼성엔지니어링 주식회사 Construction method for Utility-pipe conduit
KR101041229B1 (en) * 2011-01-03 2011-06-13 주식회사 한국그린피아 Toilet wall constructing structure using precast concrete panel
JP2013053491A (en) * 2011-09-06 2013-03-21 Shimizu Corp PCa MEMBER AND PCa METHOD
KR101835378B1 (en) * 2017-04-24 2018-03-08 주식회사 우리이앤씨 Wall structure using precast concrete panel and construction method thereof
KR20210154337A (en) * 2020-06-12 2021-12-21 정하동 Construction Method of Underground Structures

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100924701B1 (en) 2006-05-30 2009-11-03 삼성엔지니어링 주식회사 Construction method for Utility-pipe conduit
KR101041229B1 (en) * 2011-01-03 2011-06-13 주식회사 한국그린피아 Toilet wall constructing structure using precast concrete panel
JP2013053491A (en) * 2011-09-06 2013-03-21 Shimizu Corp PCa MEMBER AND PCa METHOD
KR101835378B1 (en) * 2017-04-24 2018-03-08 주식회사 우리이앤씨 Wall structure using precast concrete panel and construction method thereof
KR20210154337A (en) * 2020-06-12 2021-12-21 정하동 Construction Method of Underground Structures

Similar Documents

Publication Publication Date Title
CN105951880A (en) Assembled underground structure of precast concrete planks and construction method thereof
KR101281070B1 (en) Wall structure for the water-storage tank and its constructing method
CN108729564A (en) Assembled architecture system
CN110258640B (en) Construction method of superposed wall system for cover-excavation top-down construction
CN108612110A (en) A kind of Deep Foundation Pit of Metro Stations combined type construction method for supporting
CN105134009A (en) Sill coping concrete structure of frame structure infilled wall and construction method
KR102028899B1 (en) Underground parking lot partition structure of PC method for maximizing cost saving
CN103306497B (en) Shock prevention and strengthening construction method for existing brickwork dwelling house fabricated structure
KR101863627B1 (en) Top-down Construction method using Drainage H-type prestressed concrete wall and drainage JRS slab system
CN109853625B (en) Integrated concrete comprehensive pipe gallery connected and assembled in mixed mode
CN110080247B (en) Basement structure of narrow conflict area of foundation pit supporting slope and construction method
CA2892704C (en) Reinforced blockwork construction method
CN111173042B (en) Advanced water stop post-cast strip of foundation slab and construction method
JP4093428B2 (en) High-strength reinforced concrete precast plate
KR102714639B1 (en) Pillar wall for utility tunnels that maximizes productivity and economy through high-quality manufacturability, easy workability, construction safety, and shortened construction period, and a construction method for utility tunnels using the above Pillar walls
CN209854577U (en) Assembled thin-wall box-shaped channel
CN109680722B (en) Construction method for directly reserving external building access port on basement outer wall
US10829924B2 (en) Composite wall and methods of constructing a composite wall
CN117646497A (en) Basement outer wall post-pouring belt pre-sealing structure and construction method
CN115030556B (en) Repairing and reinforcing method for exposed wall old building of brick
CN217107046U (en) Corrugated steel plate self-plugging structure for highway tunnel transverse passage
KR101234270B1 (en) Method for non excavated excavating construction using steel pipe and steel pipe with hole
KR101774865B1 (en) A double wall
CN212223970U (en) Prefabricated apron post-cast strip stagnant water temporary enclosed construction
CN113863675A (en) Concrete construction method for main transformer tunnel structure

Legal Events

Date Code Title Description
E701 Decision to grant or registration of patent right
GRNT Written decision to grant