Nothing Special   »   [go: up one dir, main page]

KR101650232B1 - Semipermeable breakwater of combined power generation facility - Google Patents

Semipermeable breakwater of combined power generation facility Download PDF

Info

Publication number
KR101650232B1
KR101650232B1 KR1020140034814A KR20140034814A KR101650232B1 KR 101650232 B1 KR101650232 B1 KR 101650232B1 KR 1020140034814 A KR1020140034814 A KR 1020140034814A KR 20140034814 A KR20140034814 A KR 20140034814A KR 101650232 B1 KR101650232 B1 KR 101650232B1
Authority
KR
South Korea
Prior art keywords
pile
caisson
piles
prefabricated
pipe
Prior art date
Application number
KR1020140034814A
Other languages
Korean (ko)
Other versions
KR20150110238A (en
Inventor
김상훈
Original Assignee
김상훈
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 김상훈 filed Critical 김상훈
Priority to KR1020140034814A priority Critical patent/KR101650232B1/en
Publication of KR20150110238A publication Critical patent/KR20150110238A/en
Application granted granted Critical
Publication of KR101650232B1 publication Critical patent/KR101650232B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/06Moles; Piers; Quays; Quay walls; Groynes; Breakwaters ; Wave dissipating walls; Quay equipment
    • AHUMAN NECESSITIES
    • A01AGRICULTURE; FORESTRY; ANIMAL HUSBANDRY; HUNTING; TRAPPING; FISHING
    • A01KANIMAL HUSBANDRY; AVICULTURE; APICULTURE; PISCICULTURE; FISHING; REARING OR BREEDING ANIMALS, NOT OTHERWISE PROVIDED FOR; NEW BREEDS OF ANIMALS
    • A01K61/00Culture of aquatic animals
    • A01K61/70Artificial fishing banks or reefs
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B9/00Water-power plants; Layout, construction or equipment, methods of, or apparatus for, making same
    • E02B9/08Tide or wave power plants
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D23/00Caissons; Construction or placing of caissons
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/52Submerged foundations, i.e. submerged in open water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F03MACHINES OR ENGINES FOR LIQUIDS; WIND, SPRING, OR WEIGHT MOTORS; PRODUCING MECHANICAL POWER OR A REACTIVE PROPULSIVE THRUST, NOT OTHERWISE PROVIDED FOR
    • F03BMACHINES OR ENGINES FOR LIQUIDS
    • F03B13/00Adaptations of machines or engines for special use; Combinations of machines or engines with driving or driven apparatus; Power stations or aggregates
    • F03B13/08Machine or engine aggregates in dams or the like; Conduits therefor, e.g. diffusors
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F03MACHINES OR ENGINES FOR LIQUIDS; WIND, SPRING, OR WEIGHT MOTORS; PRODUCING MECHANICAL POWER OR A REACTIVE PROPULSIVE THRUST, NOT OTHERWISE PROVIDED FOR
    • F03BMACHINES OR ENGINES FOR LIQUIDS
    • F03B13/00Adaptations of machines or engines for special use; Combinations of machines or engines with driving or driven apparatus; Power stations or aggregates
    • F03B13/12Adaptations of machines or engines for special use; Combinations of machines or engines with driving or driven apparatus; Power stations or aggregates characterised by using wave or tide energy
    • F03B13/14Adaptations of machines or engines for special use; Combinations of machines or engines with driving or driven apparatus; Power stations or aggregates characterised by using wave or tide energy using wave energy
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F03MACHINES OR ENGINES FOR LIQUIDS; WIND, SPRING, OR WEIGHT MOTORS; PRODUCING MECHANICAL POWER OR A REACTIVE PROPULSIVE THRUST, NOT OTHERWISE PROVIDED FOR
    • F03DWIND MOTORS
    • F03D13/00Assembly, mounting or commissioning of wind motors; Arrangements specially adapted for transporting wind motor components
    • F03D13/20Arrangements for mounting or supporting wind motors; Masts or towers for wind motors
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0061Production methods for working underwater
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A10/00TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE at coastal zones; at river basins
    • Y02A10/11Hard structures, e.g. dams, dykes or breakwaters
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A40/00Adaptation technologies in agriculture, forestry, livestock or agroalimentary production
    • Y02A40/80Adaptation technologies in agriculture, forestry, livestock or agroalimentary production in fisheries management
    • Y02A40/81Aquaculture, e.g. of fish
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/30Energy from the sea, e.g. using wave energy or salinity gradient
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/70Wind energy
    • Y02E10/72Wind turbines with rotation axis in wind direction
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/70Wind energy
    • Y02E10/728Onshore wind turbines
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P60/00Technologies relating to agriculture, livestock or agroalimentary industries
    • Y02P60/60Fishing; Aquaculture; Aquafarming
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P70/00Climate change mitigation technologies in the production process for final industrial or consumer products
    • Y02P70/50Manufacturing or production processes characterised by the final manufactured product

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Combustion & Propulsion (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Chemical & Material Sciences (AREA)
  • Environmental Sciences (AREA)
  • Sustainable Energy (AREA)
  • Marine Sciences & Fisheries (AREA)
  • Zoology (AREA)
  • Animal Husbandry (AREA)
  • Biodiversity & Conservation Biology (AREA)
  • Sustainable Development (AREA)
  • Environmental & Geological Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Revetment (AREA)

Abstract

본 발명은 하부후팅의 현장타설 말뚝에서 조립식 판넬과 받침대 조립판넬이 설치되도록 조립식 케이슨의 현장타설말뚝을 이용한 반투과성 방파제의 축조구조물에다 설치할 수 있는 지지반력벽과 파력발전기, 풍력발전기를 구비한 종합발전설비의 반투과성 방파제에 관한 것이다.
이를 위한 본 발명은, 투입재가 비교적 적게 들고 선박 유효통로 확보가 용이하며 깊은 심도에서도 설치가 가능한 직립식 방파제중 독립후팅 기초방식에 조립식 케이슨의 현장타설 말뚝공법을 적용하여 해저면에 하부후팅을 설치하고; 지지말뚝을 RCD 장비를 이용하여 기반암까지 굴착하여 접속시키며; 매립지역을 구분하여 구역별로 말뚝 보강 지지대에 조립식 판넬을 쌓아 방파판 역할을 수행하면서 그 내부를 쇄석으로 충진시켜 그 적재물을 늘리고 파력이 쇄석을 통과하여 유통하도록 하고; 커튼월방식으로 받침대 조립판넬을 상기 조립식 판넬이 적층된 다수의 현장타설 말뚝사이에서 전면으로 적층되며; 상기 인공어초까지의 설치가 끝나면 현장타설 말뚝과 지지 반력벽 상부의 두부를 정리하고, 각 말뚝과지지 반력벽체간의 철근, 콘크리트, 캡 비임을 설치하여 일체화시키며, 상기 캡 비임위에 다시 상판(마루판)을 설치하게 되고; 상기 상판의 그 여유 공간은 태양광 집전판을 설치하고, 마루턱 후면에 말뚝 지지대와 연계해 풍력 발전기의 타워를 설치함으로, 상기 풍력 발전기의 회전력과 양력을 충분히 감당하도록 설치되며; 상기 풍력발전기에는 다수개의 송전관 거치대 부분 조립식 케이슨과 송전관 말뚝부분 케이슨으로 구성된 송전관을 설치된 것을 그 특징으로 한다.
The present invention relates to a composite power generation system having a support reaction force wall, a wave power generator, and a wind power generator, which can be installed on a structure of a semi-permeable breakwater using a cast-in-place pile of a prefabricated caisson so that a prefabricated panel and an assembly- To a semipermeable breakwater of a facility.
The present invention for this purpose is to install a bottom hoeing on the sea floor by applying the cast-in-place pile method of the prefabricated caisson to the independent float basis method of the upright type breakwater which is relatively easy to secure the effective passage of the ship, and; The support pile is connected to the bedrock using RCD equipment; The piles are stacked on the pile reinforcing supports by dividing the landfill area, and the piles are stacked on the piles so that the piles are filled with the crushed stones so that the load is increased and the waves are distributed through the crushed stones; A pedestal assembly panel in a curtain wall manner is laminated to the front between a plurality of field drilled piles stacked with the prefabricated panels; When the installation up to the artificial tongue is completed, the pile and the head of the supporting reaction force wall are assembled and the reinforcing bars, concrete, and cap beam between the piles and the supporting reaction force wall are installed and integrated, Lt; / RTI > The space of the upper plate is provided to accommodate the rotational force and the lift of the wind power generator by installing a solar collecting plate and installing a tower of the wind power generator in connection with the pile support on the rear side of the floor tile. The wind power generator is characterized in that a transmission pipe composed of a plurality of transmission line cage partly-assembled caissons and a power transmission pipe pile caisson is provided.

Figure 112014500960391-pat00001
Figure 112014500960391-pat00001

Description

종합발전설비의 반투과성 방파제{SEMIPERMEABLE BREAKWATER OF COMBINED POWER GENERATION FACILITY}{SEMIPERMEABLE BREAKWATER OF COMBINED POWER GENERATION FACILITY}

본 발명은 하부후팅의 현장타설 말뚝에서 조립식 판넬과 받침대 조립판넬이 설치되도록 조립식 케이슨의 현장타설말뚝을 이용한 반투과성 방파제의 축조구조물에다 설치할 수 있는 지지반력벽과 파력발전기, 풍력발전기를 구비한 종합발전설비의 반투과성 방파제에 관한 것이다.The present invention relates to a composite power generation system having a support reaction force wall, a wave power generator, and a wind power generator, which can be installed on a structure of a semi-permeable breakwater using a cast-in-place pile of a prefabricated caisson so that a prefabricated panel and an assembly- To a semipermeable breakwater of a facility.

일반적으로 토목구조물공사의 파일공사에 있어, 토질 및 기초 분야의 깊은 기초는 말뚝기초, 현장타설 말뚝 및 케이슨(Caisson) 기초로 나누어지고 있는 바, 상기 말뚝기초는 재료에 따라 강관, PHC 및 RC 말뚝으로 구분되고 있으며, 말뚝기초에서 시공법에 따라 타입(항타)말뚝과 매입 말뚝으로 구분한다.Generally, deep foundation of soil and foundation field is divided into foundation of pile foundation, cast-in-place pile and caisson foundation in pile construction of civil engineering structure construction, and the pile foundation is composed of steel pipe, PHC and RC pile , And it is classified into type (hoe) pile and embedded pile according to the construction method in the pile foundation.

통상적으로 구조물에서 지지력은 항타 말뚝일 경우에는, 공사비 측면에서 경제적이고 지지력 발휘가 큰데 비하여 소음 진동의 영향으로 공사 여건이 쉽지 않다. 그리고, 지층상에 자갈이나 단단한 층이 있을 때 항타의 경우에는, 말뚝이 부러지는 경우가 발생하므로 적용 여건이 쉽지 않다.Generally, the bearing capacity of the structure is economical in terms of construction costs and the bearing capacity is large in the case of the pile, but the construction condition is not easy due to the noise vibration. And, when there is a gravel or a hard layer on the stratum, the piling is broken in case of hitting, so the application condition is not easy.

따라서, 상기 조건에 맞지 않을 때에는 매입이나 현장타설 말뚝을 쓰게 되는바, 상기 매입은 지반을 선굴착후 말뚝을 삽입하는데에 SIP, SDA 및 PRD등 시공방법이 발달되어 지층조건 등에 따라 적용공법이 많다. 상기 및 PRD등 시공방법이 발달되어 지층조건 등에 따라 적용공법이 많다. 상기 현장타설 말뚝은 기성제품이 아닌 현장에서 타설하는 관계로 시공관리와 품질관리에 어려움이 많으며, 대체적으로 교량에서는 대구경으로 많이 사용되고 있다.Therefore, when the above conditions are not met, the pile is buried or buried in the field, and the buried pile is inserted into the pile after the excavation of the ground, and the application methods such as SIP, SDA and PRD are developed, . The above methods such as PRD and the like are developed, and there are many application methods depending on the layer conditions. Since the above-mentioned cast-in-place pile is installed at the site instead of the ready-made product, there are many difficulties in construction management and quality control, and in general, the bridge is widely used as a large diameter.

한편, 해상에서 설치되고 있는 방파제가 세굴로 인한 침식문제가 발생하여 큰 사회적 문제로 대두되고 있는 데, 그 원인의 주된 부분은 입사 파랑의 부분반사로 형성되는 반사파의 중첩으로 인한 중복파가 발생함으로 기초부를 깎아내리는 이유가 주된 원인이며, 이에 반사파 제어기술 확보가 시급한 실정이다.On the other hand, the breakwater installed on the sea is becoming a big social problem due to the erosion problem caused by scouring. The main cause of this is the occurrence of overlapping waves due to overlapping of the reflected waves formed by the partial reflection of incident waves. This is the main cause of the reduction of the base part, and it is urgent to secure the reflection wave control technology.

상기 방파제의 축조 방식에는 사석식 경사제, 직립제, 혼성제 등 크게 세 가지로 대별할 수 있다. 먼저, 상기 사석식 경사 방파제는 막대한 석재가 소요되어 재료조달 및 공급이 용이하지 않으며, 자연환경 피해 복구가 곤란하고 유지 보수비가 많이 들어 비경제적이며, 설치지역 수심이 20 m ∼ 40 m 내외라야 하므로 설치 장소가 제한되고 있다.The breakwater construction methods can be broadly classified into three types, namely, a slope type inclining agent, an upright agent, and a hybrid agent. Firstly, the above-mentioned sloping type breakwater requires an enormous amount of stone, so it is not easy to procure and supply the material, it is difficult to recover from the damage to the natural environment, the maintenance cost is high and it is uneconomical and the water depth of the installation area should be about 20 m to 40 m The installation site is limited.

따라서, 사용 재료가 비교적 적게 들고 제체 폭을 넓게 하지 않아도 유로 항구폭 확보가 용이한 직립식을 많이 선호하고 있으나, 반사파가 많이 발생하여 중복파가 형성되므로 이를 저감시키기 위한 혼성제로 많이 사용되고 있다.Therefore, although it is preferable to use the upright type which is easy to secure the width of the flow channel, it is often used as a hybrid agent to reduce the deterioration because many waves are generated due to the generation of reflected waves.

상기 직립제 중에서도 케이슨식을 선호하고 있으나, 케이슨이 점차 대형화 되어 그 크기가 1.000 톤∼15,000 톤까지 이르러 그것의 육상 제작, 진수, 운송, 설치에 사용되는 권상장비 또한 최소 2,000 톤 이상의 것을 사용하여야 하며, 극히 제한되어 있는 운용 장비의 일정에 따라 공사 시점이 정해져야 하는 불이익을 감수해야 한다.Caisson type is preferred among the upright types but the caisson is gradually enlarged and its size reaches 1.000 to 15,000 tons and its hoisting equipment used for land preparation, launching, transportation and installation should be at least 2,000 tons. , The disadvantage that the construction time should be fixed according to the schedule of the operating equipment which is extremely limited.

상기 방파제들은 대부분 중력식 방파제로 내습파랑의 차단과 항내 정온도 측면에서 역할을 수행하고 있지만, 불투과성인 구조 형식으로 인한 인위적인 흐름 변화를 유발하여 항내 및 주변지역에 침식, 퇴적환경 변화와 항내 수질오염 등의 문제를 발생시키고 있다.Although most of these breakwaters are gravity type breakwater, they play an important role in the blocking of the wet wave and the port temperature. However, they cause an artificial flow change due to the impermeable structure type, causing erosion in the port and surrounding areas, And the like.

이에 해수면에서 차지하는 면적이 비교적 적고 방파제 하부를 통하여 항내,외의 해수유통을 원활하게 하기 위해 커튼(방파판)과, 이를 지지하는 파일 구조물로 이루어진 커튼월(Curtain Wall) 방식의 방파제를 채택하여 시공하기도 한다. 이는 연약지반 및 내해의 적용이 우수하나 구조적인 특성상 적재하중이나 다른 부재의 하중을 분담하지 않는 칸막이형 장막벽 형태로 자체 무게외는 하중을 받지 않는 비 내력벽인 관계로 각 부재의 접합성과 내파손 성능이 요구됨과 유공율을 줄이기 위해 파일의 배치가 주열식이나 말뚝군 형성으로 조성되어야 함으로, 시공중 발생하는 항타로 인접공의 보일링(boiling)현상은 불가피 하며, 이로 인한 기저부의 지반 교란은 극복할 수 없는 한계인 것이다.The area occupied by the sea surface is relatively small and a curtain wall type breakwater consisting of a curtain (wave plate) and a pile structure supporting it is used to smooth the circulation of sea water through the lower part of the breakwater. do. This is because it is a non-bearing wall that is not subjected to loads other than its own weight in the form of a partitioned curtain wall which is excellent in application of soft ground and inland water but does not share load or other member loads due to its structural characteristics. In order to reduce the required porosity, the piles should be formed by the main heat type or the pile group formation. Therefore, the boiling phenomenon of the adjacent holes is inevitable due to the hitches generated during the construction, It is the limit that can not be done.

따라서 방파판의 한계치를 넘는 큰 파랑 내습시 구조물 유지가 어렵다. 그 때문에 기능상 수심이 깊은 곳이나 대형 방파제에의 적용이 적합하지 않다.Therefore, it is difficult to maintain the structure during a large wave invasion exceeding the limit of the wave plate. Therefore, it is not suitable for application to a deep water depth or a large breakwater.

한편, 전력수급 문제에 있어서도 화석연료 발전소 및 원자력 발전등 대규모 발전시설로 인한 고압선로를 설치하여 송전문제가 많은 민원을 야기시키고 있으며, 점진적인 전력수요 증가로 인한 블랙아웃(black out) 현상 등이 우려되고 있는 바, 지방자치단체별 전력수급 계획이 중앙 정부와의 협력이 이루어져야 한다.On the other hand, in the power supply and demand problem, there is a problem of transmission problems due to the installation of high-voltage lines due to large-scale power generation facilities such as fossil fuel power plants and nuclear power plants, and black out due to the gradual increase in demand for electric power. And the power supply and demand plan for each municipality should be coordinated with the central government.

이에 청정 에너지인 풍력, 파력, 태양광 발전시설을 방파제의 유휴공간과 그 주변지역에 병행 설치함으로, 발전단지를 따로 조성, 건설하지 않도록 한다. 상기 태양광 발전을 시설하고자 할 때 가장 큰 문제중 하나가 집광판 설치 부지확보가 관건이므로, 이에 대한 대책으로 수상부양식 집광판 제작 설치 등이 대안으로 제시되고 있으나, 이는 계류장치 설치와 그 이동에 따른 송전설비 시설이 만만하지 않다.Therefore, the wind power, wave, and solar power generation facilities, which are clean energy, are installed in the idle space of the breakwaters and the surrounding area. One of the biggest problems in installing the solar power generation system is to secure the installation site of the condenser, and as a countermeasure, it is proposed to construct an aquarium type condenser plate as an alternative. However, Transmission facilities are not perfect.

상기 파력 발전시설인 경우에는 이용 가능한 파력의 에너지원을 획득하기 위해서는 적정 수심이 보장되어야 하므로, 이에 대한 잠함의 설치 지역내 자립, 정착을 위한 시설공사시 비용도 생각해 볼 문제다.In the case of the above-mentioned wave power generation facility, the appropriate water depth must be secured in order to obtain the energy source of the available wave power. Therefore, it is a problem to consider the cost of self-sustaining in the installation area of the building.

상기 풍력 발전시설인 경우에 대단지로 조성해야만 막대한 건설비에 대한 경제적 효과가 있으므로, 이에 대한 설치비용과 그에 따른 민원 또한 해결해야 할 과제이다.In the case of the above-mentioned wind power generation facility, since it is economically effective to incur huge construction costs only when it is formed as a large lot, the installation cost and the complaints thereof are also a problem to be solved.

이와 더불어, 상기 발전시설 및 단지조성에 필요한 인허가시 득해야 할 법령은 환경기본법, 수상기본법, 국토이용계획법을 비롯한 자연환경 보호법, 수질오염 방지법, 해안법, 하천법, 산림법, 소방법, 항만법, 항만운송 사업법, 어업법, 수산자연 보호법, 연안어장 개발법, 수산자원 보호법, 공수수면매립법, 폐기물처리법, 채석법, 대륙붕법, 항로법, 전파법 등 그 외 기타 여러 관례법령의 비준을 받아야만 하는 번거로움이 있다. 이에 대한 시간적, 공간적, 경제적 절감을 도모하기 위해 복합 기능형 방파제를 구축하고자 한다.In addition, the laws and ordinances that must be granted for licenses and permits required for the above-mentioned power generation facilities and complexes include natural environment protection law, water pollution prevention law, coastal law, river law, forest law, fire prevention law, harbor law, port transportation There are hurdles that must be ratified by other customs laws such as business law, fisheries law, fisheries protection law, coastal fishery development law, fisheries resource protection law, airborne water reclamation law, waste treatment method, quarrying method, continental shelf method, In order to reduce the time, space and economical efficiency, we intend to build a multifunctional breakwater.

이에 본 발명자는 모든 공정이 300 톤 크레인으로 운용될 수 있는 조립식 케이슨을 이용한 현장타설 말뚝공법을 도입하여 추가 공정을 병합 시공함으로, 장비의 수배 조달 운용을 용이하게 하며 인허가 취득시 번거로움을 생략하고자 한다.Therefore, the present inventor has introduced a cast-in-place pile method using a prefabricated caisson which can be operated as a 300-ton crane, and the present invention can be applied to the combined process of the additional process, thereby facilitating the operation of procuring equipment and eliminating the hassle do.

즉, 본 발명자의 발명특허 10-1256274에서는 조립 케이슨을 투하 연결하여 조립 케이슨끼리 결속하여 해저면에 사각형태의 구조체를 만들고 그 내부를 크람쉘 버켓을 사용하여 풍화암(사암) 상단까지 준설한 다음 유도 강관이 부착된 철재류 쟈켓을 설치하고 수중 콘크리트를 타설하여 일체화 시킴으로 교각의 후팅(footing)역할과 기능을 증대시킬 뿐 아니라 강관 근입시 오차범위를 줄임으로 작업의 안정성을 확보, 시간적, 경제적 절감을 기할 수 있는 조립 케이슨을 이용한 현장 타설 말뚝을 제공하고 있다.That is, in the inventor's invention patent No. 10-1256274, the assembly caissons are connected to each other to bind the assembly caissons to each other to form a square-shaped structure on the undersurface, and the inside thereof is dredged up to the top of the weathered rock (sandstone) By installing steel jackets with steel pipes and installing underwater concrete, it is possible to increase the role of footing and function of the piers. By reducing the error range of steel pipes, it is possible to secure the stability of work and save time and economy. Which can be used as a foundation pile.

발명특허 10-1211811에서는 직접기초 방식의 확대 기초로 사용하는 후팅을 해저면에 설치함으로써 연직 또는 수평방향의 지지력과 휨모멘트, 편심하중을 상쇄시킬 수 있으며, 지반 반력에 의한 응력과 부등침하에 대한 저항력은 말뚝 기초로 감소시켜 상부전체의 상재하중의 경감에 따른 대응력을 증가 시킬 수 있는 조립케이슨 및 쟈켓을 이용한 알시디(R.C,D) 공법을 제공하고 있다,In the invention patent 10-1211811, it is possible to offset the vertical or horizontal support force, bending moment and eccentric load by providing a float which is used as an extension base of the direct basis method, and the stress due to the ground reaction force and the uneven settlement (RC, D) method using an assembly caisson and a jacket which can reduce the resistivity to a pile base and increase the responsiveness according to the reduction of the overhead load on the entire upper part.

따라서, 본 발명자는, 각종 발전설비를 위한 구조물을 병행 시공함과 해수를 일부 항내로 유통시킴으로, 환경오염을 방지할 수 있는 복합발전기능의 방파제를 완성시키는데 다각적이고 효율적으로 파력발전기와 풍력발전기의 적용함을 강구한 것이다.Accordingly, the present inventors have succeeded in constructing a breakwater having a combined power generation function capable of preventing environmental pollution by simultaneously constructing structures for various power generation facilities and circulating seawater in a part of the waters, thereby efficiently and efficiently controlling wave generators and wind turbines To be applied.

특허등록 10 - 1256274 조립케이슨 쟈켓을 이용한 R.C.D공법Patent registration 10 - 1256274 R.C.D method using assembly caisson jacket 특허등록 10 - 1211811 조립케이슨을 이용한 현장타설말뚝Patent Registration 10 - 1211811 Field casting piles using assembly caisson

실무토목기초설계와 시공, 토목발전연구회편저Practical civil engineering basic design and construction, 최신설계시공핸드북, 건설문화사The latest design work handbook, construction history 토목시공학, 이양구,강인식, 서문당Civil Engineering, Lee Yang-gu, Kang In-sik, Introduction 해양구조공학, 최경석저 문운당Marine Structural Engineering, Kyungsuk Choi 항만 2013년 가을호, 한국항만협회Ports Fall 2013, Korean Port Authority 방파제 기저부 방지공 개발에 관한 연구, 서울시립대학교대학원, 최윤주A Study on the Development of Breakwater Prevention Ball, Seoul Metropolitan University Graduate School,

본 발명은 상기와 같은 제반 사정을 감안하여 발명한 것으로, 직립식 방파제를 채택하여 직접 기초방식중 독립후팅 기초방식에 조립식 케이슨의 현장타설 말뚝공법을 적용하여 해저면에 하부 후팅을 설치함으로 파일(PILE)에 직접 영향을 미치는 세굴을 방지함과 동시에, 지지말뚝을 RCD(Reverse Circulation Drill)장비를 이용하여 기반암까지 굴착함으로 접속(socketing)시키며, 매립지역을 구분하여 조립식 판넬을 쌓아 그 내부를 쇄석 및 토사로 충진시켜 그 적재물을 늘림으로 자중에 의한 안정성을 확보하고 지지반력벽을 설치함으로써 파력에 대한 대응력을 증가시킴과 동시에, 전면 말뚝간 연결하는 받침판넬을 요철(凹凸)화, 적층 설치하여 제체의 획일적인 직선화를 탈피,일체화시킴으로 입사파의 첨두 분리 및 대항 면적을 증가시켜 제체의 단위 면적당 대응하는 파력을 감소시키고 연직 또는 수평방향에 휨 모멘트, 편심하중을 상쇄시키고 말뚝기초로 부등침화의 여지를 감소시킬 수 있는 방파제의 축조구조물에서 파력발전기와 풍력발전기를 제공하고자 함에 그 목적이 있다.The present invention has been made in view of the above circumstances, and it is an object of the present invention to provide a method of installing a standing pile of a prefabricated caisson in an independent float basis method using an upright type breakwater, PILE is prevented from scouring and the piles are socked to the bedrock using RCD (Reverse Circulation Drill) equipment. The pile is divided into the landfill areas and the prefabricated panels are stacked, And the soil is filled to increase the load, the stability by self weight is ensured and the supporting reaction force wall is provided to increase the responsiveness against the wave force and at the same time, the supporting panel connecting the front piles is provided with unevenness and lamination By separating and integrating the uniform linearization of the body, it is possible to increase the peak separation of the incident wave and the area of the counterpart, The present invention aims to provide a wave generator and a wind turbine generator in a breakwater structure capable of reducing a corresponding wave and canceling a bending moment and an eccentric load in a vertical or horizontal direction and reducing the possibility of anisotropy in a pile foundation.

본 발명의 다른 목적은, 방파제체 구축으로 인한 해수의 흐름을 인위적으로 완전히 차단하지 않고, 구간별로 유통시킴으로 파력을 일부 감쇄시킴과 동시에 항내 수질오염을 방지하여 생태계 훼손을 경감시킬 수 있는 반투과성 방파제 축조구조물의 파력발전기와 지지반력벽을 제공할 수 있다.It is another object of the present invention to provide a semi-permeable breakwater construction capable of partially attenuating waves by preventing the flow of seawater due to the construction of a breakwater body, The wave generator of the structure and the support reaction force wall can be provided.

본 발명의 또 다른 목적은, 직립제의 취약점인 반사파로 인한 중복파의 생성을 감소시키고 지지말뚝 시공시 세굴에 의한 함몰로 인한 공기 지연과 강관파일 정착에 대한 효율성을 기하기 위해 조립식케이슨의 현장타설 말뚝 공법을 도입하여 독립후팅 기초방식으로 저변 거점을 확보하며, 각 말뚝간의 구획을 설정 조립식 판넬을 쌓아 체적을 유지하여 그 내부를 쇄석으로 충진시켜 단위 구역당 매립을 실시하여 매립식 축조 방식의 장점을 극대화하고, 각 구역별 구조체를 일체화시켜 상재하중을 균등하게 기반암 및 해저면에 전달하여 구조적 안정성을 확보함과 구역내에 해수통로를 설치함으로, 파랑의 입사시 파력의 첨두(peak)가 분할되어 통수로 부분에 입사되어 쇄석을 통과하게 하여 첨두가 동시에 작용하지 않고, 위상차를 가지게 하여 순차적으로 에너지를 소산시켜 압력을 감소시키는 역할을 하는 반투과성 방파제를 제공할 수 있다.Another object of the present invention is to reduce the generation of overlapping waves due to the reflected wave, which is a weak point of the upright, and to improve the air delay due to the sinking due to the burrs and the efficiency of the settlement of the steel pipe, In this study, the pile foundation method was adopted to establish the base point of each pile, and the pile between each pile was set. The pile was built up by the prefabricated panel to fill the inside with the crushed stones. By maximizing the merit and integrating the structure of each zone, the top load is evenly distributed to the bedrock and the sea bed to secure the structural stability and the seawater channel is installed in the zone, So that the peaks pass through the crushed stones and the peaks do not act at the same time, To provide a semipermeable breakwater that serves to dissipate energy to reduce pressure.

본 발명의 또 다른 목적은. 발전시설될 제체에 파력, 풍력, 태양광 설비를 설치할 근간을 마련하며 그에 대한 송전선로에 대한 안정성을 확보하고자 함에 있으며, 소요 수급 전력량이 부족할 시 추가적인 독립 시설과 그 시설을 이용한 생태서식 공간을 제공하고자 하는 데에 있다.Still another object of the present invention is to provide In order to secure the stability of the transmission line, it is necessary to provide additional independent facilities and ecological habitat space using the facility. I want to.

본 발명의 다른 목적은, 각 형태별 발전시설을 효율적으로 제체내에 설치하여 이에 대한 시설물 구축비용을 절감하고, 송전 선로에 대한 파주력을 증대시켜 파랑에 의한 변화 유발을 방지하며 안정성을 확보하고자 하는 데에 있다.It is another object of the present invention to provide a power generation system in which each type of power generation facility is efficiently installed in a vehicle to reduce the cost of constructing the power generation facility and increase the power of the power transmission line to prevent fluctuation caused by the wave, There is.

상기 목적을 달성하기 위한 본 발명은, 투입재가 비교적 적게 들고 선박 유효통로 확보가 용이하며 깊은 심도에서도 설치가 가능한 직립식 방파제중 독립후팅 기초방식에 조립식 케이슨의 현장타설 말뚝공법을 적용하여 해저면에 하부후팅을 설치하고; 지지말뚝을 RCD 장비를 이용하여 기반암까지 굴착하여 접속시키며; 매립지역을 구분하여 구역별로 말뚝 보강지지대에 조립식 판넬을 쌓아 방파판 역할을 수행하면서 그 내부를 쇄석으로 충진시켜 그 적재물을 늘리고 파력이 쇄석을 통과하여 유통하도록 하고; 요철형태로 받침대 조립판넬을 상기 조립식 판넬이 적층된 다수의 현장타설 말뚝사이에서 전면으로 적층되며; 상기 인공어초까지의 설치가 끝나면 현장타설 말뚝과 지지 반력벽 상부의 두부를 정리하고, 각 말뚝과지지 반력벽체간의 철근, 콘크리트, 캡 비임을 설치하여 일체화시키며, 상기 캡 비임위에 다시 상판(마루판)을 설치하게 되고; 상기 상판의 그 여유 공간은 태양광 집전판을 설치하고, 마루턱 후면에 현장타설말뚝과 연계해 풍력 발전기의 타워를 설치함으로, 상기 풍력발전기의 회전력과 양력을 충분히 감당하도록 설치되며; 상기 풍력발전기에는 다수개의 송전관 거치대 부분 조립식 케이슨과 송전관 말뚝부분 케이슨으로 구성된 송전관을 설치된 것을 그 특징으로 한다.In order to achieve the above object, the present invention provides a method of installing a ground-breaking pile of a prefabricated caisson in an independent backing-type method of an upright type breakwater which is relatively easy to secure the effective passage of a ship, A lowering footing is installed; The support pile is connected to the bedrock using RCD equipment; The piles are stacked on the pile reinforcing supports by dividing the landfill area, and the piles are stacked on the piles so that the piles are filled with the crushed stones so that the load is increased and the waves are distributed through the crushed stones; A pedestal assembly panel in the form of a concavoconvex is stacked on the entire surface between a plurality of field drilled piles stacked with the prefabricated panels; When the installation up to the artificial tongue is completed, the pile and the head of the supporting reaction force wall are assembled and the reinforcing bars, concrete, and cap beam between the piles and the supporting reaction force wall are installed and integrated, Lt; / RTI > The space of the upper plate is provided to accommodate the rotational force and the lift of the wind power generator by installing a solar collecting plate and installing a tower of the wind power generator in connection with the casting pile on the rear side of the floor tile. The wind power generator is characterized in that a transmission pipe composed of a plurality of transmission line cage partly-assembled caissons and a power transmission pipe pile caisson is provided.

이상 설명한 바와 같이 본 발명에 의하면, 조립식 케이슨의 현장타설 말뚝공법을 채택하여 해저 지형조건의 여러 가지 제약요건을 극복하고 보다 폭 넓은 입지를 선정할 수 있으며, 구역별로 블록을 정해 매립하여 통수로 부분을 설정하고 제체 전면부에 파력 발전기 거치대 부분을 돌출시켜 입사파 파력의 첨두 부분을 분할시켜 집중력을 감소시킴과 동시에, 소파기능을 수행하는 인공어초를 설치함과 파력 발전기 배출수의 와류를 이용, 접근 파랑에 대한 반사파를 저감시키는 동시에 그 흡인력을 이용, 일방향 와류세기를 최대화, 해수 흡출효과를 극대화하여 용승류 작용을 유발시켜 해수유통 원할을 기할 수 있다.As described above, according to the present invention, it is possible to overcome various constraint requirements of the submarine topography condition and to select a wider area by adopting the cast-in-place pile method of the prefabricated caisson, And the peak part of the incident wave is divided by projecting the part of the wave generator stand in the front part of the body to reduce the concentration of the wave and the artificial fish which performs the sofa function is installed and the vortex of the wave generator water is used It is possible to reduce the reflection wave to the wave and to maximize the one-way vortex intensity by utilizing the attraction force, maximize the seawater suction effect, and to induce the action of the seawater, thereby making it possible to distribute the seawater.

본 발명은 철근 콘크리트로 지지 반력벽을 현장타설 벽체로 구축함으로 파력에 대한 반력과 구조체 전체의 안정성을 증진시킬 수 있고, 조립식 케이슨의 현장타설 말뚝공법을 적용함으로 매립 지역의 기초부분은 기반암과 접속되어 있으므로, 매립으로 인한 액상화, 압밀침하, 부등침하등 연약지반 생성 및 이에 대한 보강 처리 및 치환 공정이 불필요하다.The present invention can increase the reaction force against the wave and the stability of the whole structure by constructing the support reaction force wall with the reinforced concrete wall as the field piling wall, and applying the field piling method of the prefabricated caisson, Therefore, it is unnecessary to produce soft ground such as liquefaction, consolidation settlement, uneven settlement due to landfill, and reinforcement treatment and replacement process therefor.

본 발명은 제체 외부에 인공어초를 수직으로 부착 시설함으로 어초의 공용적 감소를 막아 어초의 기능저하를 방지하고, 다양한 생태계의 서식처를 제공하여 인근어장의 수산 자원 증식을 도모하므로 민원 해소에 기여할 수 있다.The present invention can prevent degradation of fish reefs by preventing artificial fishes from decreasing by restricting the reduction of fish reefs by installing artificial fishes vertically on the outside of the fishes and providing various habitats of ecosystems, have.

본 발명은 다양한 형태의 청정 에너지 발전 시설을 수용할 수 있으므로 지역내 전력 수급에 적극 대응할 수 있고, 또한 송전관 시설시에도 조립식 케이슨을 이용한 현장 타설말뚝 공법으로 송전로의 구조적인 체적을 유지하여 해저면과의 마찰력을 증가시키고, 지지말뚝을 병행 시공함으로 조류에 의해 송전선로가 이동하는 것을 막을 뿐아니라 어선의 저인망으로부터의 전선을 보호하고 파주력을 증대시킴으로, 파랑에 대한 시설물 안정을 확보함으로 안전하게 전력 이송을 할 수 있다.
본 발명도 독립후팅 기초방식에 조립식 케이슨의 현장타설 말뚝공법을 적용하여 해저면에 하부후팅을 1 차 콘크리트 타설하고; 지지말뚝을 RCD 장비를 이용하며 기반암까지 굴착하여 접속시켜 상기 하부후팅상에 다수개 현장타설말뚝을 2 차 콘크리트 타설하며; 하부훗팅 상부에 구역별로 조립식 판넬을 쌓아 그 내부를 쇄석 및 토사를 충진시키고 ; 요철형태로 받침대 조립판넬을 상기 조립식 판넬이 적층된 다수의 현장타설 말뚝사이에서 전면으로 적층시키는 축조구조물에서,
상기 현장타설 말뚝들 사이에 설치된 받침대 조립판넬위에 파력발전기를 설치하고,파력발전기 후방에는 지지 반력벽이 설치되며 지지반력벽의 측면 인접구역은 해수를 유통시킬 수 있는 통수구와 격자망이 나있는 조립식 판넬을 설치하며 파력발전기의 전면에 다수의 인공어초가 적층되며;
상기 인공어초까지의 설치가 끝나면 현장타설 말뚝과 지지 반력벽 상부의 두부를 정리하고, 각 말뚝과지지 반력벽체간의 철근, 콘크리트, 캡 비임을 설치하여 일체화시키며, 상기 캡 비임위에 다시 상판(마루판)을 설치하게 되고;
상기 상판의 그 여유 공간은 태양광 집전판을 설치하고, 마루턱 후면에 현장타설말뚝과 연계해 풍력 발전기의 타워를 설치함으로, 상기 풍력 발전기의 회전력과 양력을 충분히 감당하도록 설치되며;
상기 풍력발전기에는 다수개의 송전관 거치대 부분 조립식 케이슨과 송전관 말뚝부분 케이슨으로 구성된 송전관을 설치되는 종합발전설비의 반투과성 방파제에 있어서,
상기 하부후팅과의 연결은 송전관 연결부에 맞도록 설치하는 데, 이 조립식 케이슨들을 길이 방향대로 조립하며 거치부 송전관 연결부 마다 송전관 말뚝부분 조립 케이슨이 놓여지도록 배치하며,
거치가 끝나면 쟈켓을 말뚝부분과 거치대 부분에 설치하여 연결판끼리 볼트와 넛트로 조립 연결하고,
조립식 케이슨내에 해상 콘크리트 작업선과 트레미파이프를 사용하여 수중 콘크리트 타설을 하며,
상기 타설이 끝나면 유도강관내에 근입강관을 집어넣고, 바이브로 햄머로 요동 압입시킨 후 철근망을 근입하되, 이때 철근망의 높이는 유도강관보다 10cm 낮게 제작하여 설치하고, 해상 콘크리트 작업선과 트레미파이프를 이용하여 수중 콘크리트 타설을 하며, 이때 타설 높이는 조립식 케이슨 상단과 같이 한 것을 특징으로 하는 종합발전설비의 반투과성 방파제.
Since the present invention can accommodate various types of clean energy generation facilities, it can actively cope with the supply and demand of power in the area. Also, in the case of the transmission facility, the structure volume of the transmission line is maintained by the pile- By increasing the frictional force with the surface and constructing the supporting pile in parallel, it prevents the transmission line from moving by the algae, protects the wire from the fishing net of the fishing boat, increases the breaking force, Power transfer can be performed.
In the present invention, first cast concrete is laid on the seabed surface by applying the pre-cast pile method of the prefabricated caisson to the independent float basis method; The supporting piles are connected to the bedrock by using RCD equipment to connect a plurality of piles to the second finishing pile; A prefabricated panel is stacked on top of the lower footing to fill the interior with crushed stone and gypsum; In a building structure in which a pedestal assembly panel is stacked on a front surface between a plurality of field drilled piles stacked with the prefabricated panels,
A wave generator is installed on a pedestal assembly panel installed between the excavated piles and a supporting reaction wall is provided on the rear side of the wave generator and a side adjoining area of the supporting reaction wall is provided with a water hole and a lattice net, A panel is installed and a plurality of artificial ear sheets are stacked on the front surface of the wave generator;
When the installation up to the artificial tongue is completed, the pile and the head of the supporting reaction force wall are assembled and the reinforcing bars, concrete, and cap beam between the piles and the supporting reaction force wall are installed and integrated, Lt; / RTI >
The space of the upper plate is provided to accommodate the rotational force and the lift of the wind power generator by installing a solar collecting plate and installing a tower of the wind power generator in connection with the casting pile on the rear side of the floor tile.
The present invention relates to a semi-permeable breakwater of a general power generation plant having a power transmission line composed of a plurality of transmission line holder partly assembled caissons and a power transmission pipe pile part caisson,
The connection between the lower fitting and the connecting pipe is made to fit the connection of the transmission pipe. The prefabricated caissons are assembled in the lengthwise direction, and the caisson assembly of the transmission pipe pile is placed in each connection part of the mounting part transmission pipe,
When the mounting is completed, the jacket is installed on the pile and the mounting base, and the connection plates are assembled and connected by bolts and nuts,
Inside the prefabricated caisson, underwater concrete is laid using marine concrete work line and tremie pipe,
When the above installation is completed, the main pipe is inserted into the induction steel pipe, and the reinforcing net is inserted into the pipe after the vibration is press-fitted into the vibro hammer. At this time, the height of the reinforcing bar is set 10 cm lower than the guide pipe, And the height of the pile is the same as that of the prefabricated caisson.

도 1 은 본 발명의 조립식 케이슨의 현장 타설말뚝 공법을 이용한 반투과성 방파제를 도시해 놓은 설치 상태도,
도 2 는 본 발명의 실시예에 따른 축조구조물에서 파력발전기와 지지반력벽을 도시해놓은 상태도,
도 3 은 본 발명의 조립식 케이슨과 쟈켓의 설치, 1 차 콘크리트 타설을 위한 순서도,
도 4 는 본 발명의 조립식 케이슨의 상세도 및 연결 방법,
도 5 는 본 발명의 하부후팅 보강용 철근망 및 쟈켓, 지지반력벽 철근망의 상세도,
도 6 은 본 발명의 강관근입 및 RCD의 순서도,
도 7 은 본 발명의 하부 그라우팅(grouting), 조립식 판넬을 이용한 구조물의 설치 및 쇄석 충진도,
도 8 은 본 발명의 강관지지대 연결부, 상하단 판넬 및 받침대 조립판넬의 상세도,
도 9 는 본 발명의 강관지지대 상세도 및 설치도,
도 10 은 본 발명의 지지반력벽 철근망 설치 및 콘크리트 타설, 파력발전기, 인공어초, 캡 비임(cap beam)의 설치 및 상판(마루판) 설치도,
도 11 은 파력발전기 및 받침대 케이슨 및 철근망, 인공어초, 파력발전기의 상세도,
도 12 는 독립형 풍력발전기 설치 및 송전관 거치부분의 상세도,
도 13 은 송전관 거치부 조립식 케이슨 및 자켓의 상세도,
도 14 는 송전관의 설치상세도이다.
FIG. 1 is an installation view showing a semi-permeable breakwater using the piling method of the prefabricated caisson of the present invention,
FIG. 2 is a state diagram illustrating a wave generator and a support reaction force wall in a construction structure according to an embodiment of the present invention. FIG.
FIG. 3 is a flow chart for installation of a prefabricated caisson and jacket of the present invention,
4 is a detailed view of the assembled casings of the present invention,
FIG. 5 is a detailed view of the reinforcing net and jacket for supporting the lower backing of the present invention,
6 is a flow chart of the steel pipe insertion and RCD of the present invention,
FIG. 7 is a view showing the grouting of the present invention, the installation of a structure using a prefabricated panel,
8 is a detailed view of the steel pipe support connection part, the upper and lower end panels, and the pedestal assembly panel of the present invention,
FIG. 9 is a detailed view and installation view of a steel tube support according to the present invention,
10 is a view showing the installation of a reinforcing wall reinforcing bar network of the present invention and the installation of a concrete beam, a wave generator, an artificial fishing rod, a cap beam and a floorboard,
Fig. 11 is a detailed view of the wave generator and pedestal caisson and reinforcing net,
Fig. 12 is a detailed view of a stand-alone wind turbine installation and a transmission pipe mount portion,
Fig. 13 is a detailed view of a transmission-pipe-mounted, assembled caisson and a jacket,
14 is a detail view of the installation of the transmission pipe.

이하, 본 발명의 바람직한 실시예를 예시도면에 의거하여 상세히 설명한다.Hereinafter, preferred embodiments of the present invention will be described in detail with reference to the accompanying drawings.

도 1 은 본 발명의 조립식 케이슨의 현장타설말뚝 공법을 이용한 방파제를 도시해 놓은 상태이고, 하부후팅(101)의 풍력발전기(102)와 파력발전기(104), 태양광발전기(103)등 복합발전설비로써 병행 설치하고, 케이슨(Cassion) 방식과 커튼 월(Curtain wall) 방식의 장점을 살려 내,외해의 해수를 유통시킴으로, 항내의 수질 환경오염을 해소시키기 위하여 구간별 해수 유통로를 확보하고 소파기능을 가진 인공어초(108)를 부가 설치가 가능한 독립후팅 기초지지 방식으로 조립식 케이슨의 현장 타설 말뚝 공법을 적용, 시공하고 있다.FIG. 1 is a view showing a breakwater using a piercing method of cast-in-place pile method of a prefabricated caisson of the present invention. FIG. 1 is a perspective view showing a breakwater of a composite power generation system including a wind power generator 102, a wave generator 104, a solar generator 103, In order to solve the pollution of the water environment in the port by securing the advantages of the caisson method and the curtain wall method and circulating the seawater of the outer sea, The artificial pile 108 having the function of installing the artificial fish pile 108 can be installed on the foundation supporting method, and the pile piling method of the pile construction method is applied.

그러므로, 반투과성 방파제 구축시 입지 선정의 폭을 넓히며 시공 지역 및 주변 어장의 어패류 증식에 기여하고, 내항의 수질 오염 악화를 방지하여 민원 발생 소지 감소, 권역별 지역내의 전력난 해소에 기여할 수 있어, 별도로 전력생산 시설 건설시 막대한 비용의 들지 않고도 제체구축시 병행작업을 실시함으로, 시간적, 공간적, 경제적 절감을 기할 수 있다.Therefore, it is possible to contribute to the proliferation of seafood in the construction area and surrounding fisheries by preventing the deterioration of water pollution in the inner harbor, It is possible to save time, space, and economies by carrying out the parallel operation at the time of constructing the product without having to incur huge cost when constructing the production facility.

본 발명자의 발명 특허를 활용하여 해저면 후팅 방식에다 하부후팅(101)의 다수 현장타설 말뚝(416)을 첨가해 기반암에 정착시켜 안정성을 확보시키고, 그곳을 거점으로 조립식 판넬(109)을 쌓아 단위 췌적별로 쇄석을 충진하며, 인접 구역을 반력 및 지지벽체로 조성함과 동시에 현장타설 말뚝(416)간의 결속을 일체화시켜 전체 구조물의 안정성을 확보하면서 조류를 일부 교통시킴으로 자연 환경 훼손 방지에 적극 대응하는 것이다.By using the invention patent of the present inventor, a plurality of field drilled piles 416 of the lower hood 101 are added to the sea bottom surface float method to secure stability to the bedrock, and the prefabricated panels 109 are stacked The crushed rocks are packed by each pile, and the adjoining area is constituted as a reaction force and support wall, and the ties between the drilled piles 416 are united to secure the stability of the entire structure. will be.

반투과성 방파제에서는 제체 전면부 파력 발전시설(104)과 풍력 발전시설(102), 태양광 발전시설(103. 111)과 인공어초(108), 작업구(110)와 파력인입구(113), 파력발전기 받침대 조립판넬(433), 송전 시설(106)등으로 구성되어져 있다. 독립 풍력발전소(105)에는 가두리 양식장(122)을, 송전관(106)에 송전탑(107)을 각각 설치할 수 있다.In the semi-permeable breakwater, the wave front power generation facility 104, the wind power generation facility 102, the solar power generation facility 103. 111, the artificial fish foundation 108, the work site 110 and the wave inlet 113, A pedestal assembly panel 433, a transmission facility 106, and the like. The cage farm 122 can be installed in the independent wind farm 105 and the transmission tower 107 can be installed in the transmission pipe 106.

본 발명의 방파제 축조는 직접기초 방식중 독립후팅 기초 방식에 조립식 케이슨의 현장타설 말뚝공법을 적용하여 해저면에 하부후팅(101)을 설치하고(도 3 참조), 지지말뚝을 RCD(Reverse Circulation Drill) 장비를 이용 기반암까지 굴착하여 접속시키며(도 6 참조), 매립지역을 구분하여 구역별로 조립식 판넬(109)을 쌓아 그 내부를 쇄석으로 충진시켜(도 7 참조), 그 적재물을 늘림으로 자중에 의해 안정성을 확보함과 동시에 통수로 구역내의 충진된 쇄석들의 마찰표면적이 확대됨으로 인해 입사파의 에너지 소산 효과를 유발시키며, 입사파가 세력이 큰 장파인 경우 수면부터 바닥까지 균일하게 분포되어 대응면적이 확대되어 저항력을 증가시키므로 진동폭 감소를 야기시켜 파력에 대한 대응력을 증가시키고, 지반 반력에 의한 응력과 부등 침하에 대한 대응력을 증가시킴과 동시에 받침대 조립판넬(433)을 적층 설치함으로 연직 또는 수평 방향의 휨 모멘트, 편심하중을 감소시키고 말뚝기초로 부등침하의 여지를 감소시킬 수 있다.In the breakwater construction of the present invention, the cast-in-place piling method of the prefabricated caisson is applied to the independent float basis method of the direct-based method to install the lower footing 101 on the sea floor (see FIG. 3) (See FIG. 6). The landfill area is divided and the assembled panel 109 is piled up for each district, and the inside thereof is filled with crushed stone (refer to FIG. 7). By increasing the load, And the friction surface area of the filled crushed stone in the channel area is enlarged to induce the energy dissipation effect of the incident wave. When the incident wave is a long wave having a large force, it is uniformly distributed from the water surface to the bottom, Is increased to increase the resistance, so that the vibration width is reduced to increase the response force against the wave force, and the stress due to the ground reaction force and the response to the uneven settlement Sikkim increased and at the same time it is possible to reduce the bending moment, the eccentric load in the vertical or horizontal direction by installing the laminated base panel assembly 433 to reduce the room for differential settlement a pile foundation.

도 2 는 본 발명의 실시예에 대한 방파제 축조구조물에서 파력발전소와 지지반력벽의 정면도 및 평면도이고, 이는 도 3 의 조립식 케이슨과 쟈켓의 설치. 1차 콘크리트 타설을 위한 순서와 도 6 의 강관근입 및 RCD의 순서, 도 7 의 하부 그라우팅, 조립식 판넬의 설치 및 쇄석충진에 의해 완성된 축조구조물과; 도 10 의 지지반력벽 철근망 설치 및 콘크리트 타설, 파력발전기, 인공어초, 캡 비임(cap beam)의 설치 및 상판(마루판)인 것이다.FIG. 2 is a front view and a plan view of a wave power plant and a support reaction force wall in a breakwater construction structure according to an embodiment of the present invention, which is the installation of the prefabricated caisson and the jacket of FIG. The order of the primary concrete pouring, the order of the steel pipe insertion and the RCD of FIG. 6, the lower grouting of FIG. 7, the installation of the assembled panel and the crushing filling; 10, the installation of the reinforcing bar wall, the installation of the concrete, the wave generator, the artificial ear, the installation of the cap beam, and the roof (floorboard).

즉, 축조구조물에서 파력발전기(104)와 지지반력벽(439)의 정면도와 평면도에 현장타설 말뚝(416)을 기준으로 한 구역은 파력 발전기(104)가 적층된 받침대 조립판넬 433)위에 설치되고, 또 지지 반력벽(439)이 설치되며 인접구역은 해수를 유통시킬 수 있는 통수구(435)와 격자망(436)이 나있는 조립식 판넬(109)을 설치하게 되면, 그 전면에 다수의 인공어초(108)가 적층되고 설치되어 있다.That is, in the front view and the plan view of the wave generator 104 and the support reaction force wall 439 in the building structure, the area based on the cast-in-place pile 416 is installed on the pedestal assembly panel 433 on which the wave generator 104 is stacked And a supporting reaction force wall 439 are provided in the vicinity of the water supply port 435 and the water supply port 435 capable of circulating the seawater and the lattice nets 436 are provided in the adjacent area, A second layer 108 is stacked and installed.

상기 파력발전기(104)에는 작업구(110), 파력인입구(113), 공기인입구(441)와 공기배출구(442)가 구성되어져 있다.The wave generator 104 includes a working tool 110, a wave power inlet 113, an air inlet 441, and an air outlet 442.

요철형태로 전면 적층의 받침대 조립판넬(433)과 말뚝 지지대에서는 체결하기 위해 말뚝지지대 연결구멍(410)이 형성되어 있고, 쇄석(306)이 적재되는 하부후팅(101)상의 판넬(425 - 423)에는 다수개의 연결고리(607)와 견인 및 연결고리(606), 다수개의 상하 연결고리(412)와 원형부분 연결고리(411)가 각기 형성되어 와이어(611)로 고정시킬 수 있도록 구성되어 있다.A pile support connection hole 410 is formed in the pile support frame for connection with the pedestal assembly building panel 433 of the front stacked structure in a concave and convex shape and the panels 425 to 423 on the lower flooring 101 on which the crushed stone 306 is mounted, A plurality of connecting rings 607, a pulling and connecting ring 606, a plurality of upper and lower connecting rings 412 and a circular part connecting ring 411 are formed and fixed by wires 611, respectively.

상기 받침대 조립판넬(433)에도 다수개의 상하 연결고리(412)와 원형부분 연결고리(411)가 각기 형성되어 와이어로 고정시킬 수 있다.The pedestal assembly panel 433 is also provided with a plurality of upper and lower connecting rings 412 and a circular portion connecting ring 411, and can be fixed by wires.

파력발전기(104)는 외해에서 내해로 들어오는 유입수(437), 부호 438은 내해에서 외해로 나가는 배출수(438), 부호 446은 파력 발전기에서 나오는 배출수(446)로 해수의 흐름을 나타내고 있다.The wave generator 104 represents the flow of seawater to the inflow water 437 entering from the outer sea to the sea, the drain 438 from the inner sea to the sea, and the drainage 446 from the wave generator.

그리고, 쇄설의 매립부(407)와 더불어지지 반력벽 설치부(450), 파력발전기 설치부(448), 인공어초 설치부(449) 및 반침대 조립판넬(433)과 연결부 상판판넬(423)이 설치되어 있다.The supporting reaction force wall installation part 450, the wave generator installation part 448, the artificial fish supporter part 449 and the half-bed assembly panel 433 and the connection part upper panel panel 423 together with the clogged embedding part 407, Is installed.

본 발명의 방파제 축조 구조물에서 파력발전기와 지지반력벽은 지지말뚝 시공시 세굴에 의해 함몰로 인한 품질저하, 강관파일에 대한 효율성을 기하기 위해 조립식 케이슨의 현장 타설 말뚝 공법을 도입, 독립후팅 기초방식으로 저변거점을 확보하며, 각 말뚝간의 구역을 설정 통수구가 설치된 조립식 판넬(109)을 쌓아 체적을 유지하며, 그 내부를 쇄석으로 충진시켜 해수를 유통, 파력을 감소시키게 하고, 한쪽 구역은 쇄석으로 일부 충진시킨 후 전면부에는 받침대 조립판넬(433)을 이용하여 파력발전기(104)를 설치하고, 그 배면에는 철근 콘크리트 벽체를 조성 파력발전기에 대한 반력과 지지력을 증대시키고, 각 구역별 구조체를 일체화시켜 상재 하중을 균등하게 기반암부 해저면에 전달, 구조적 안정성을 확보한 것이다.In the breakwatershed structure of the present invention, the wave generator and the support reaction force wall are introduced by the cast-in-place pile method of the prefabricated caisson for the quality deterioration due to the depression and the efficiency of the steel pipe file when the support pile is constructed, And the bottom area of each pile is secured by stacking a prefabricated panel (109) provided with a pouring port to fill the inside of the prefabricated panel with crushed stone to distribute the seawater and reduce the wave power. On the other hand, A wave generator 104 is installed on the front part using a pedestal assembly panel 433 and a reinforcing concrete wall is formed on the rear surface of the wave generator 104. The reaction force and support force for the wave generator are increased, And uniformly distributes the overhead load to the base of the base arm, ensuring structural stability.

도 3 은 조립식 케이슨과 쟈켓의 설치, 1 차 콘크리트 타설을 위한 시공 순서도이다.Fig. 3 is a construction flowchart for installation of a prefabricated caisson and a jacket, and first concrete pouring.

본 발명의 방파제 축조 구조물은 해상파일작업 시공중 조류가 센 지역이나 기상 상태 악화 및 부득이한 일시 장비 철수후 재작업 진입시 근입된 강관이 세굴로 인한 함몰현상이 생겨, 원위치 재정착에 소요되는 시간적, 경제적 손실을 절감하기 위해 해저면(203)에 자중을 늘린 6 개의 유도강관(208)이 부착된 구조체를 설치하고, 그 속에 각각 근입강관(211)을 집어넣어 조류 및 외부환경에 대응, 연속적인 작업이 가능하게 하여 품질 향상을 도모시킨다.The breakwater construction structure of the present invention is characterized in that the steel pipe inserted at the time of entering the reworking operation after the withdrawal of the temporary equipment and the inevitable temporary equipment deteriorates in the area where the bird is caught during the construction work of the sea pile is depressed due to scouring, In order to reduce the loss, there is provided a structure in which six guide steel pipes 208 are attached to the seabed surface 203 to increase their own weights, and the main steel pipes 211 are inserted into the structure, Thereby improving the quality.

도 3(a)에 도시된 바와 같이, 하부 후팅(footing)설치 지역을 바지선(202)상의 크레인(201)을 사용하여 크람쉘 버켓(205)으로 구역내 해저면(203)의 해저 침전물(204)과 토사층, 풍화암 상단까지 걷어낸다. 그 잔여물은 샌드 펌프(도 4 참조 : 604)를 이용, 바닥 청소를 할 수 있다.As shown in Figure 3 (a), the lower footing installation area is connected to the submarine sediment 204 (204) of the subsea surface 203 in the zone with a crumbshell bucket 205 using a crane 201 on the barge 202 ) And to the top of the soil layer, to the top of weathered rock. The residue can be ground-cleaned using a sand pump (see FIG. 4: 604).

도 3(b)에 도시된 바와 같이, 바지선(202)의 크레인(201)을 이용하여 조립식 케이슨(206)을 설치할 수 있다. 도 7(a)(b)의 하부 그라우팅, 조립식 판넬의 설치와 같이 조립 연결하며 도 4(c)에 도시된 조립식 케이슨과 같이 원형구멍(603)에 샌드펌프(604)를 집어넣어 공기압을 각각 주입(605, 608) 상기 조립식 케이슨(206)의 바닥면을 청결하게 할 수 있다.As shown in FIG. 3 (b), the crane 201 of the barge line 202 can be used to provide a prefabricated caisson 206. The sand pump 604 is inserted into the circular hole 603 like the prefabricated caisson shown in Fig. 4 (c) to connect the lower grouting and the assembled panel as shown in Figs. 7 (a) Injection (605, 608) The bottom surface of the prefabricated caisson (206) can be cleaned.

도 4(a)에 도시된 조립식 케이슨은 도 4(b)에 도시된 좌, 우 숫 연결부(609)의 숫 조립식 케이슨(601)과, 일축 암 연결부와 원형구멍(603)의 암 조립식 케이슨(602)을 순차적으로 결합시켜서 해당 크기의 사각형으로 제작하여 사용한다. 그리고, 모서리 케이슨(612)을 이용하여 각모서리를 마무리한다.The prefabricated caisson shown in Fig. 4 (a) has a male-faced caisson 601 of the left and right male connector 609 shown in Fig. 4 (b), and a male preformed caisson 601 of the unicast female connector and the circular hole 603 602) are successively combined into a square having a corresponding size. Then, the corner caisson 612 is used to finish each corner.

사각형의 크기는 콘크리트 타설후 구조체의 자중이 1,000 톤이 넘어야 태풍, 해일등 파력에 의한 전도 및 기타 환경 외력에 대응하여 예방할 수 있음으로, 가로 10 m, 세로10 m, 높이 2 m 이상 유지해야 한다.The size of the square should be more than 1,000 tons of the structure after concrete pouring, so that it can be prevented against propagation by waves and other environmental external forces such as typhoons and tsunamis. .

도 4(d)에 도시된 숫 조립식 케이슨(601)에는 원형구멍(603)과 그 주변으로 공기압 주입구(605)가 형성되어 있다.4 (d), a circular hole 603 and an air pressure inlet 605 are formed in the periphery of the circular hole 603.

도 4(e)에 도시된 암 조립식 케이슨(602)에는 원형구멍(603)과 그 주변의 견인 연결고리(606)가 설치되고 측면으로 2 개의 연결고리(607)가 설치된다.In the arm-assembled caisson 602 shown in FIG. 4 (e), a circular hole 603 and a traction coupling ring 606 around the circular hole 603 are provided, and two coupling rings 607 are provided on the side.

케이슨 조립이 끝나면 와이어를 각 조립체간의 연결고리(607)에 끼워 넣어 유압 실린더를 사용 인장하여 와이어 소켓으로 체결함으로 요동을 막고 구조체의 형상을 견고하게 한다.When the caisson assembly is finished, the wires are inserted into the connection rings (607) between the respective assemblies, and the hydraulic cylinder is tensioned and tightened with a wire socket to prevent the swing and to secure the shape of the structure.

해저면(203)의 평탄함이 고르지 않을 때는 고일목을 사용하여 평형을 맞추고 그 사이의 공간은 모래주머니로 채워 빈 공간을 채운다.When the flatness of the underside surface 203 is uneven, it is balanced by using a solid wood, and the space between them is filled with sand bags to fill an empty space.

그 다음에는 도 3(c)와 같이 크레인(201)으로 쟈켓(207 : 도 5(b) 참조)을 투하하여 설치한다. 여기서 쟈켓(207)에는 6 개의 유도강관(208)과 그라우팅 파이프 (403)로 구성되어 있다. 유도강관(208)은 근입강관 보다 직경 200 m/m 가 커야 한다.Then, the jacket 207 (see Fig. 5 (b)) is dropped and installed in the crane 201 as shown in Fig. 3 (c). Here, the jacket 207 is made up of six guide steel pipes 208 and a grouting pipe 403. The induction steel pipe 208 should have a diameter 200 m / m larger than the adjacent steel pipe.

도 5(a)는 H 비임(401)내에서의 철근(402)과 유도강관 보호대(231), 그라우팅 파이프 보호대(232) 및 다수의 연결부(409)로 된 하부후팅 보강용 철근망인 것이다. 여기서 넛트(406), 와샤(408) 및 볼트(407)를 이용하여 해당 연결부(409)에 체결되고 있다.5A is a bottom reinforcing reinforcing bar made of reinforcing bars 402 and guiding steel pipe guards 231, a grouting pipe guards 232 and a plurality of connecting portions 409 in the H beam 401. And is fastened to the connecting portion 409 by using the nut 406, the washer 408 and the bolt 407.

그 후 도 3(d)와 같이 해상 콘크리트 작업선(210)에서 콘크리트 주입호스(225)와 트레미 파이프(209)를 이용하여 수중 콘크리트를 1 차 타설할 수 있다. 이때 타설높이는 쟈켓(207)의 1/2 지점까지만 한다. 이는 추후 설치할 하부후팅(101)의 보강용 철근망으로써 원활한 조립을 위한 것이다.Thereafter, as shown in FIG. 3 (d), the underwater concrete can be firstly laid by using the concrete injection hose 225 and the trapezium pipe 209 at the marine concrete working line 210. At this time, the height of the mounting is limited to half of the jacket 207. This is for smooth assembly of the reinforcing steel net of the lower mounting 101 to be installed later.

이상 설명한 바와 같이 직접 기초방식중 독립 후팅 기초방식에 조립식 케이슨의 현장 타설 말뚝공법을 적용하여 해저면(203)에 하부후팅(101)을 설치함으로 조립식 케이슨(206)과 쟈켓(207)에 1 차 콘크리트 타설이 완성된다.As described above, by applying the ground piling method of the prefabricated caisson to the independent float basis method of the direct basic method and installing the lower backing 101 on the seabed surface 203, the prefabricated caisson 206 and the jacket 207 are provided with primary Concrete pouring is completed.

도 6 은 강관근입 및 RCD(Reverse Circulation Drill)의 순서도이다. 바지선의(202)의 크레인(201)을 이용하여 도 6(a)에 도시된 바와 같이, 도 3 에 도시된 하부후팅(101)에서의 유도강관(208)내에 근입강관(211)을 집어넣는다.6 is a flowchart of steel pipe insertion and RCD (Reverse Circulation Drill). A crowned steel pipe 211 is inserted into the induction steel pipe 208 in the lower footing 101 shown in Fig. 3 by using the crane 201 of the barge 202 as shown in Fig. 6 (a) .

상기 근입강관(211)의 규격은 직경 2,000 ∼ 2,500 mm 를 사용하며, 그 두께는 50 년 부식 한계치 12 m/m이상의 강관, 통상 20 ∼ 25 mm 를 사용할 수 있다.The diameter of the near-inlet steel pipe 211 is 2,000 to 2,500 mm, and the thickness thereof is 50 to 20 mm or more, and usually 20 to 25 mm.

이때 도 4(f)에 도시된 바와 같이, 근입강관 연결고리(227)에 와이어(611)를 연결하고, 붓싱로울러(226)를 매개로 유도강관 원형구멍(228)을 통해 와이어(611)를 끌어당기면 순적하게 근입강관(211)이 안착된다.At this time, as shown in FIG. 4 (f), the wire 611 is connected to the adjacent steel pipe connection ring 227, and the wire 611 is connected through the guide pipe circular hole 228 via the bushing roller 226 And when it is pulled, the close-fitting steel pipe 211 is seated.

따라서, 도 6(a)와 같이 근입강관(211)을 하부후팅(101)의 유도강관(208)내에 집어넣고 크레인(201)에 바이브로 햄머(212)를 장착하여 요동 압입시킨다.Therefore, as shown in FIG. 6 (a), the near-intake pipe 211 is inserted into the guide pipe 208 of the lower backing 101, and the vibrohammer 212 is mounted on the crane 201 and pushed in.

이렇게 압입이 끝나면 굴착토 운반선(218)과 RCD 장비(216)의 RCD 파워팩 (215)을 이용하여, 도 6(b)와 같이 RCD 장비(216)의 RCD 비트(213)를 이용하여 기반암 소정의 깊이까지 굴착한다.When the press-fitting is completed, the RCD bit 213 of the RCD equipment 216 is used as the bedrock of the RCD equipment 216, as shown in FIG. 6 (b), using the excavated soil conveying line 218 and the RCD power pack 215 of the RCD equipment 216 Excavate to depth.

여기서 도면부호 214는 하부후팅(101)밑의 굴착면을 나타낸다. 굴착의 깊이는 기반암이 연암일 경우 1.5 D(D = 직경), 풍화암일 경우 3D 이상 굴착하는 것이 접속(socking)의 조건에 충족된다.Here, reference numeral 214 denotes an excavation surface under the lower lighting 101. The depth of excavation is 1.5 D (D = diameter) when the bedrock is soft rock, and more than 3 D when it is weathered rock is satisfied with the condition of socking.

상기 바지선(202)의 크레인(201)을 이용하여 육상에서 미리 조립된 현장타설 말뚝의 철근망(217)을 집어넣는다(도 6(c) 참조).The reinforcing net 217 of the field drilled piles assembled in advance on the ground is inserted into the barge 202 using the crane 201 of the barge line 202 (see FIG. 6 (c)).

이렇게 공내 설치가 끝나면, 도 5(a)의 하부후팅 보강용 철근망을 도 6(c)에 도시된 콘크리트 타설면(229)위에 거치한 후 쟈켓(도 5(b) 참조)과 연결 조립한다.5 (a) is mounted on the concrete installation surface 229 shown in Fig. 6 (c), and then assembled and connected to a jacket (see Fig. 5 (b)) .

도 6(d)에 도시된 바와 같이, 해상 콘크리트 작업선(210)의 콘크리트 주입호스(225)와 트레미 파이프(209)를 이용하여 굴착 공내 콘크리트 타설을 한다. 여기서 도면 부호 219는 현장타설말뚝의 철근망(217)의 콘크리트 타설 부분인 것이다.As shown in FIG. 6 (d), the concrete is injected into the excavation hole by using the concrete injection hose 225 and the tremy pipe 209 of the marine concrete working line 210. Here, reference numeral 219 denotes a concrete piercing portion of the reinforcing net 217 of the cast-in-place pile.

이후 근입강관(211)과 유도강관(208)사이의 빈공간 속채움과 하부후팅(101) 잔여분, 즉 콘크리트 타설면(229)부분의 상부에 2 차 콘크리트를 타설하여 조립식 케이슨 상단부분과 맞춘다. 이때 상단부 마무리 작업은 수중 진동바이브레이타를 사용하여 평활하게 한다.Thereafter, the secondary concrete is poured into the empty space between the intake pipe 211 and the induction steel pipe 208 and the remaining portion of the lower footing 101, that is, the upper part of the concrete installation surface 229, At this time, the upper end finishing work is done by using the underwater vibration vibrator.

따라서, 조립식 케이슨(206)과 쟈켓(207)의 1 차 콘크리트 타설상에 철근 콘크리트 말뚝으로서의 2 차 콘크리트 타설이 도 3 내지 도 6 에 도시된 바와 같이 다수개의 구조체를 완성시키게 되고, 여기서는 6 개의 철근, 콘크리트 말뚝, 즉 현장타설 말뚝(416)으로 완성된 것으로 설명한다.Thus, the secondary concrete casting as the reinforced concrete pile on the primary concrete installation of the prefabricated caisson 206 and the jacket 207 completes a plurality of structures as shown in FIGS. 3 to 6, , Concrete pile, that is, a cast-in-place pile (416).

도 7 은 하부 그라우팅(grouting), 조립식 판넬을 이용한 축조구조물의 설치 및 쇄석 충진도이다.FIG. 7 is a view showing the lower grouting, the installation of a building structure using a prefabricated panel, and a crushing filling diagram.

도 7(a)는 하부 후팅(505)과 기반암사이 지반의 공극을 차단하여 피압수 침투를 방지하기 위해 시멘트를 주입시켜 구조체와 기반암 사이 존재하는 지반의 공극을 충진시키는 그라우팅 순서도이다.7 (a) is a grouting flowchart in which voids in the ground between the lower float 505 and the bedrock are blocked and cement is injected to prevent infiltration of water under pressure, thereby filling voids existing between the structure and the bedrock.

즉, 도 3 에 도시된 조립식 케이슨(206)과 쟈켓(207)의 1 차 콘크리트 타설후 시멘트 주입기 (221)와 천공기(220)을 이용하여 1 차 콘크리트 타설된 조립식 케이슨의 그라우팅용 파이프(403)를 통해 기반암 상단까지 굴착하고, 상기 시멘트 주입기(221)를 사용하여 주입압(222)을 이용함으로써 그라우팅 단면구역 (223)을 고결화시킨다.That is, the grouting pipe 403 of the prefabricated caisson poured into the primary concrete by using the cement injector 221 and the perforator 220 after the primary concrete installation of the prefabricated caisson 206 shown in FIG. 3 and the jacket 207, And the cement injector 221 is used to consolidate the grouting section section 223 by using the infusion pressure 222. In this way,

이때 그라우팅은 국부 단면적만 실시하면 된다. 여기서 도면부호 224는 그라우팅 단면구역(223)의 주입 방향을 나타낸다.At this time, grouting can be performed only at the local cross-sectional area. Here, reference numeral 224 denotes an injection direction of the grouting section section 223.

도 7(b)는 구역별 도시된 매립부, 파력 발전기 받침대 설치부, 인공어초 설치부, 지지반력벽 설치부의 작업순서도로서, 조립식 판넬(도 8 참조)의 4 가지 형태를 이용하여 각기 적층한다.Fig. 7 (b) is a view showing the operation sequence of the embedding section, the wave generator stand installation section, the artificial root assembly installation section, and the support reaction force wall installation section shown in each zone, and they are stacked using four types of assembled panels .

도 8(a)는 하단 조립식 판넬 상세도이고, 도 8(b)는 연결부 상단판넬의 상세도이고, 도 8(c)는 연결부 하단부 상세도이며, 도 8(d)는 파력발전기의 받침대 조립판넬이고, 도 9 은 강관 지지대 상세도인 것이다.8 (b) is a detailed view of the upper end panel of the joint part, FIG. 8 (c) is a detailed view of the lower end of the joint part, and FIG. 8 (d) Panel, and Fig. 9 is a detailed view of a steel pipe support.

먼저, 중기 양생한 철근 콘크리트로 제작 사용하며, 판넬의 크기는 높이 2 m, 길이 10 m, 폭 80 cm 자중이 50 톤을 넘지 않게 사용하는 것이 바람직하며, 조립식 판넬 양단에는 원형부분(415)의 곡선의 형태는 근입강관 말뚝의 원주와 동일하게, 그 길이는 말뚝 원주의 1/4 이하로 한다.First, it is used as a medium-cured reinforced concrete. It is preferable to use the panels so that the panel size is 2 m in height, 10 m in length and 80 cm in width do not exceed 50 tons, and circular sections 415 The shape of the curve shall be equal to or less than 1/4 of the circumference of the pile in the same way as the circumference of the adjacent steel pipe pile.

상기 원형부분(415)은 해저면 설치시 상부에서부터 말뚝을 타고 내려가서 떠밀림을 방지하여 상, 하부 체결이 용이하고, 외부 파력에 대해 말뚝을 지지대로 지탱할 수 있으므로 파력에 대한 대응력을 높이는데 그 목적이 있다.The circular portion 415 can be easily pushed down from the upper portion of the pile to prevent pivoting of the pile, so that the upper and lower portions can be fastened to each other and the pile can be supported by a support member against external waves. There is a purpose.

상기 하부후팅 상단부에 도 8 (a)에 도시된 바와 같이. 하단 조립식 판넬을 차례대로 점층식으로 쌓아 올리며 3 ∼ 5 단 사이에 조립식 판넬 간의 요동을 막고, 각지지 말뚝간 지지를 할 수 있는 지지대로서 말뚝 보강지지대(303, 도 9 참조)를 설치한다.As shown in Fig. 8 (a) in the upper end of the lower hooding. The pile lower reinforcement support 303 (see Fig. 9) is installed as a support for supporting the pile between the support piles.

도 8(a)에 도시된 하단 조립식 판넬(425)에는 상부걸쇠(413)와 연결부 거치부분(414) 좌우측 반원형 부분(415), 그리고 반 원형부분 연결고리 (411)와 상하 연결고리(412)로 구성되고 있다. 여기에 통수구(435)와 격자망(436)이 일정한 간격으로 형성되어 있다.The lower assembled panel 425 shown in Figure 8A includes the upper latch 413 and the left and right semicircular parts 415 of the connecting part 414 and the semicircular part connecting hook 411 and the upper connecting link 412, . Here, a water inlet 435 and a grid net 436 are formed at regular intervals.

상기 말뚝 지지대(303)의 하단은 도 8(b)에 도시된 바와 같이, 말뚝 지지대(303)의 연결부 하단 판넬(424)을 설치하며, 그 속에 말뚝 지지대(303)를 티타늄이나 내해성이 강한 스테인레스 도금강을 사용하며, 피복의 두께는 0.4 mm 정도면 50 년 내구성과 충분한 내식성을 가져 재료비를 절감할 수 있다. 이때 통수구의 직경은 500 m/m, 격자망의 크기는 가로, 세로 100 m/m로 한다.The lower end of the pile support 303 is provided with a connection lower panel 424 of the pile support 303 as shown in Fig. 8 (b), in which the pile support 303 is made of titanium, Stainless steel plated steel is used. If the thickness of the coating is 0.4 mm, it has 50 years durability and sufficient corrosion resistance, which can reduce the material cost. At this time, the diameter of the water supply port is 500 m / m, and the size of the grid network is 100 m / m in width and length.

도 8(b)에 도시된 연결부 거치부분(414)의 조립식 판넬 상단부(423)와 연결부 거치부분(414)의 조립식 판넬 하단부(424), 그리고 각각의 말뚝 지지대 연결부 거치부분(417)로 구성되어져 있다. 여기에 통수로(435)와 격자망(436)이 일정한 간격으로 형성되어 있다.The assembled panel upper end portion 423 of the connecting portion mounting portion 414 shown in Figure 8 (b), the assembled panel lower end portion 424 of the connecting portion mounting portion 414, and the respective pile support connecting portion mounting portions 417 have. The water channel 435 and the lattice nets 436 are formed at regular intervals.

상기와 같이 하단 조립식 판넬과 연결부 하단 판넬을 결합한 강관지지대(303)의 조립이 끝난 다음, 도 9 에 도시된 바와 같이 연결부 상단판넬(423)을 말뚝 지지대 연결대 거치부분(417)에 잘 맞을 수 있도록 적재한다.9, the upper end panel 423 of the connection part is fitted to the peg support rod mount part 417, as shown in FIG. 9, after assembling the steel pipe support 303 having the bottom assembled panel and the connection part lower panel as described above. Load.

도 8(c)에 도시된 연결부 상단판넬(423)에는 상부걸쇠(413)의 조립식 란넬 상단부(427)와 하부 연결부 거치부분(414)의 조립식 판넬 하단부(428), 말뚝 지지대 연결부 거치부분(417)로 구성되어져 있다. 상기 연결부 하단 상판 판넬에도 반 원형부분 연결고리(411)와 상하 연결고리(412), 통수구(435), 격자망(436)이 구성되어져 있다.The lower panel 423 of the connection part shown in FIG. 8 (c) is provided with a lower panel mounting part 418 of the upper assembly 423 of the upper clasp 413, a lower panel mounting part 428 of the lower connection part 414, ). The semi-circular part connection ring 411, the upper and lower connection rings 412, the water inlet 435, and the lattice nets 436 are also formed on the lower panel of the connection part.

한구간씩 - 한구간은 말뚝 지지대까지의 적재 - 적재가 끝나면 와이어를 연결고리(412)에 끼워 넣어 조립식 케이슨 연결고리(607)까지 넣어 상하로 인장 체결하며 원형부분 원형 연결고리(411)끼지 결속한다.- After the loading, the wire is inserted into the connecting ring (412) and put up to the prefabricated caisson connecting ring (607), tensioned up and down, and the circular part circular connecting rings (411) are fastened together .

도 2 에 도시된 지지반력벽(439)과 파력 발전기(104)의 거치부분 구간은 통수구가 없는 판넬을 같은 4 가지의 형태로 제작 사용한다.The supporting reaction force wall 439 shown in FIG. 2 and the stationary section of the wave generator 104 are manufactured in the same four types of panels without the water inlet.

즉, 도 8(d)에 도시된 바와 같이, 요철형태의 파력발전기 받침대 조립판넬(433)은 다수의 상하연결고리(412), 3 군데의 상부 걸쇠(413) 및 원형부분(415)으로 구성되어져 있다. 따라서, 상기 받침대 조립판넬(433)은 도 8(a) - 도 8(c) 와 같이 3 가지 결합부 형태로 제작 사용할 수 있으며, 같은 조립 방법으로 적층 조립한다.8 (d), the wave generator base assembly panel 433 having a concavo-convex shape is constituted by a plurality of upper and lower connecting rings 412, three upper catches 413 and a circular portion 415 . Therefore, the pedestal assembly panel 433 can be manufactured in the form of three coupling parts as shown in Figs. 8 (a) to 8 (c), and is stacked and assembled by the same assembling method.

도 7(c)에 도시된 바와 같이, 쇄석 집중 투하장비(304)를 사용하여 포설하고자 하는 지점에 쇄석(306)을 굴삭기(305)를 사용 투하함으로 기존의 포설시 생기는 투입 할증량을 줄일 수 있다.As shown in FIG. 7 (c), by using the crush stone discharging equipment 304, the crush stone 306 is discharged by using the excavator 305 at a point to be installed, have.

이때 사용되는 투하장비(304)는 신규 제작도 가능하나, 현장 타설말뚝 시공용으로 사용하고 있는 케이싱 오실레이터(oscillator)의 좌, 우, 상하용 유압 실린더와 클램핑(clamping)실린더를 사용하여 낙하지점을 조정할 수 있으며, 사용되는 투하용 파이프(307)는 직경 1.500 ∼ 2,000 m/m사이의 케이싱 3 m ∼ 6 m 짜리를 조합 연결하고 탈. 부착하여 이용 길이를 조절 사용하면 된다. 상기 쇄석의 직경은 1.5 m 이하여야만 한다.The dropping equipment (304) used in this case can be newly manufactured, but the hydraulic cylinder and the clamping cylinder for the left, right, upper and lower sides of the casing oscillator, The pipe 307 used for the unloading operation is a combination of 3 m to 6 m of casings having a diameter of 1,500 to 2,000 m / It can be used by adjusting the length of use. The diameter of the crushed stone should be 1.5 m or less.

상기 쇄석(306)의 투하 시점은 구역별로 하단 조립식판넬(425), 연결부 하단판넬(424) 및 연결부 상단판넬(423)을 결합한 말뚝간 지지대(303)의 조립이 끝나고, 각각 받침대 조립판넬(433)은 전면 현장타설 말뚝(416)에서 설치되어 후면 연결부 판넬 및 연결부 상단판넬과의 결합을 실시하면 된다.The pile support frame 303 having the lower assembled panel 425, the lower panel 424 and the upper panel 423 connected thereto is assembled and installed on the pedestal assembly panel 433 May be installed at the front-side drilling pile 416 and combined with the rear connection panel and the connection upper panel.

구역내의 충진된 토사의 유출을 막기 위해서 각 조립식 판넬 상단부(427)에는 상부걸쇠(413),하단부(428)에는 연결부 거치부분 (414), 안쪽 원형부(415)에는 그 가장자리 전체를 무독성 발포스폰지 (E.V.A)중 운동화 밑창소재를 선택 제작하여 접합시키며 이는 육상에서 부착한다.An upper latch 413 is attached to each of the assembled panel upper end portions 427, a connection portion 414 is fixed to the lower end portion 428, and the entire periphery of the inner circular portion 415 is sealed with a non-toxic foam sponge (EVA) sneakers outsole material is selected and made to join, which attaches on the ground.

그 조립이 먼저된 구역부터 실시하며, 그 구역은 지지 반력벽(439)을 제외한 전구간에 실시한다. 이렇게 투하가 끝나면 도 7(d)와 같이 사석 고르기 장비(308)나 수중 진동로울러로 평활 작업을 한다.The assembly is carried out from the area where the assembly is performed first, and the area is provided between the whole area excluding the support reaction force wall 439. When the dropping is completed, as shown in FIG. 7 (d), a smoothing operation is performed with the sandstone picking apparatus 308 or an underwater vibrating roller.

따라서, 매립 지역을 구분하여 구열별로 도 8 에 도시된 조립식 판넬을 순차적으로 쌓아서 도 9 에 도시된 강관 지지대로 완성시키고, 쇄석(306)을 투하하되 제일 처음에는 직경이 큰 것부터 그 다음에는 직경이 작은 것 순으로, 직경 15 mm까지 3 ∼ 4차례 실시하여 큰 쇄석(306) 사이의 공간을 채워 파력에 의한 격실내에 골재의 유동을 감소시킨다.Thus, the assembled panels shown in FIG. 8 are successively stacked for each tier by dividing the landfill area to complete the steel pipe support shown in FIG. 9, and the crushed stone 306 is dropped. At first, the diameter is large, And the smallest ones are carried out three to four times to a diameter of 15 mm to fill the space between the large craters (306), thereby reducing the flow of aggregate in the compartment by the wave force.

이때 파력발전기 설치부분(448)은 토사와 함께 번갈아 도 2 에 도시된 쇄석 및 토사를 버림콘크리트 타설부(453) 하단까지 충진하고, 연결부 상단 판넬(424)상단부분까지 버림콘크리트를 타설한다. 그 후 도 9(a)에서 파력발전기 받침대용 말뚝지지대(434)의 철근망연결부(452)와 철근망 연결판(451)이 조립된 말뚝 지지대와 도 11(b)에 도시된 파력발전기 받침대용 철근망(430)을 연결판(451)끼리 맞추어 볼트와 넛트체결하여 조립하며, 이때 말뚝 지지대 세로 연결대(418)과 철근망 걸쇠부(445)가 잘 맞도록 한다.At this time, the wave generator installation part 448 alternately pours the crushed stones and soil as shown in FIG. 2 up to the lower end of the concrete pouring part 453 and pours abandoned concrete up to the upper part of the connection part upper panel 424. Thereafter, as shown in FIG. 9 (a), the pile support is assembled with the reinforcing net connecting portion 452 and the reinforcing net connecting plate 451 of the pile support 434 for the wave generator support and the wave generator support shown in FIG. 11 (b) The reinforcing net 430 is assembled by fastening the bolts and the nuts with the connecting plates 451 aligned with each other. At this time, the pile support vertical link 418 and the reinforcing net hook 445 are aligned with each other.

상기 철근망 설치 높이는 도 11(a)에 도시된 철근망 거치부(454)의 부분 상단까지 하며, 그 후 파력발전기 실린더실을 설치할 매트(mat) 콘크리트를 철근망 거치부 위 콘크리트 타설부(455)의 부분까지 타설하며 연결부 상단판넬 (423)의 상단까지 1 m 정도는 남겨두어 파력발전기(104 : 도 11(c) 참조)가 그 속에 들어 갈수 있도록 한다.The reinforcing net installation height reaches the upper end of the reinforcing net mounting portion 454 shown in FIG. 11 (a), and then the mat concrete to be installed in the wave generator cylinder chamber is inserted into the concrete installation portion 455 And the wave generator 104 (see FIG. 11 (c)) is allowed to enter into the gap by leaving about 1 m to the upper end of the connection upper panel 423.

상기 파력발전기(104)를 설치한 후 상, 하연결고리(412)에 와이어를 조립식 케이슨 연결고리(607)까지 끼워넣고, 가로는 조립식판넬 원형부분 연결고리(411)까지 끼워 넣어 유압실린더로 인장하여 와이어소켓으로 체결한다.After the wave generator 104 is installed, the wire is inserted into the upper and lower connecting rings 412 up to the prefabricated caisson connecting ring 607, the side is inserted into the prefabricated panel circular portion connecting ring 411, Tighten with wire socket.

도 9 는 강관지지대의 상세도로써, 하부후팅(101)상에 타설된 6 개의 현장타설 말뚝(416)은 축조 구조물로써 강관지지대의 상세도에 있어 하단 조립식 판넬(425), 연결부 하단판넬(424) 및 연결부 상단판넬(423)을 결합한 말뚝간 지지대에서 말뚝 지지대 세로 연결판(418), 바깥쪽 말뚝 지지대 원형부분(419), 안쪽부분의 말뚝 지지대 원형부분 (420)와; 말뚝 지지대 가로 연결대(421)와 말뚝 지지대 연결부(422), 조립식 판넬 상단부의 거치부분(417) 조립식 판넬 하단부의 거치부분(417, 414)을 이용하여, 다시 하단 조립식 판넬(425), 연결부 하단판넬(424) 및 연결부 상단판넬(423)을 결합할 수 있거나 다른 하부후팅(101)상에 설치할 수 있다.FIG. 9 is a detailed view of a steel pipe support. As shown in FIG. 9, the six cast-in-place piles 416 poured on the lower fitting 101 are the lower structure panel 425, the lower section panel 424 A pile support vertical connection plate 418, an outer pile support circular portion 419, and a pile support circular portion 420 of the inner portion; The pile support transverse linkage 421 and the pile support linkage 422 and the mounting portion 417 of the assembled panel upper portion 417 and the mounting portions 417 and 414 of the lower portion of the assembled panel are used to connect the lower assembled panel 425, (424) and the connection top panel (423) or can be mounted on the other lower fitting (101).

결합부분 요철형태로 전면 적층의 받침대 조립판넬(433)은 말뚝지지대(434), 파력발전기 받침대철근망 연결판(451) 및 받침대보강용 철근망 연결부(452)로 구성되어져 있다.The front panel assembly 433 of the front panel assembly in the form of the concave-convex portion is composed of a pile support 434, a wave generator base reinforcing net connection plate 451 and a reinforcing bar network connection portion 452 for bracket reinforcement.

상기 말뚝지지대에서는 체결하기 위해 말뚝지지대 연결구멍(410)이 형성되어 있고, 쇄석(306)이 적재되는 하부후팅(101)상의 판넬(425 - 423)에는 다수개의 연결고리(607)와 견인 및 연결고리(606), 다수개의 상하 연결고리(412)와 원형부분 연결고리(411)가 각기 형성되어 와이어로 고정시킬 수 있도록 구성되어 있다.A pile support connection hole 410 is formed in the pile support and the panels 425 to 423 on the lower hooing 101 on which the crush stone 306 is mounted are provided with a plurality of connection rings 607, A ring 606, a plurality of upper and lower connecting rings 412 and a circular part connecting ring 411 are respectively formed and fixed by wires.

상기 받침대 조립판넬(433)에서도 다수개의 상하 연결고리(412)와 원형부분 연결고리(411)가 각기 형성되어 와이어로 고정시킬 수 있다.Also in the pedestal assembly panel 433, a plurality of upper and lower connecting rings 412 and a circular part connecting ring 411 are formed and fixed by wires.

도 10 은 파력 발전기 거치부, 지지 반력벽, 인공어초 설치부 및 캡 비임 및 상판의 설치도이고, 도 11 은 파력발전기 및 받침대 케이슨 및 철근망, 인공어초(도 11(d)), 파력발전기(도 11(c))의 상세도이다.Fig. 10 is a view showing the installation of the wave generator, the support reaction force wall, the artificial fish supporter, the cap beam and the upper plate, Fig. 11 is a view showing the wave generator and the pedestal caisson and reinforcing net, (Fig. 11 (c)).

먼저, 도 5(c)에 도시된 바와 같이, 지지반력벽(439) 철근망을 사용하게 되는 바, 이는 H 비임(401)에 철판(431)과 철근(402), 그리고 앵글(404)과 철근망 연결구멍(432)이 구성되어져 있다.First, as shown in FIG. 5 (c), a reinforcing net of the support reaction force wall 439 is used. This is because the steel plate 431, the reinforcing bars 402, the angles 404, A reinforcing net connecting hole 432 is formed.

그 후에 지지 반력벽(439)에 사용되는 철근망은 부식을 방지하기 위한 아연 도금된 철근을 사용할 수 있으나, 경제적인 문제를 고려할 때 에폭시 코팅된 철근(402)을 사용하며, 코팅의 두께는 150 ㎛ 정도로 한다.After that, the reinforcing net used for the supporting reaction force wall 439 can use galvanized reinforcing bars to prevent corrosion, but considering the economic problem, the epoxy coated reinforcing bars 402 are used, and the thickness of the coating is 150 Mu m.

도 10(a)에 도시된 크레인(201)의 지지 반력벽 철근망(429)에서 보는 바와 같이, 한 구간씩 - 한 구간은 지지대와 지지대간의 크기 - 의 크기로 만들되 그 가장자리는 H 비임(401)으로 직사각형 형태로 제작하고, 그 중간에 앵글로 보강지지대를 좌, 우로 넣어 만든 후 철근(402)을 철판(431)에 용접하여 부착시키며, 그 상부와 하부는 철근망 연결구멍(432)을 낸 철판(431)을 용접 부착한다.As shown in the supporting reaction force wall reinforcing net 429 of the crane 201 shown in FIG. 10 (a), one section is made to have a size of the size between the support and the support, The reinforcing bars 402 are attached to the steel plate 431 by welding. The upper and lower portions of the reinforcing bars 402 are connected to the reinforcing bar connecting holes 432 The welded steel plate 431 is welded.

이때 철판(431)의 두께는 15 mm 이상을 사용한다. 상기 철근(431)의 조립방법은 제일 하단에 들어갈 지지 반력벽 철근망(429)을 크레인(201)으로 들어서 조립식판넬(301 : 도 10(a) 참조)에 거치한 후, 그 위에 다음 철근망(429)을 들어 올려 철근망 연결구멍(432)끼리 맞춘 후 고강도 볼트와 너트를 사용하여 체결하고 내리며 차례로 조립하여 하부후팅(505) 상단에 안착시킨다.At this time, the thickness of the steel plate 431 is 15 mm or more. The method of assembling the reinforcing bars 431 is such that the supporting reaction force wall reinforcing net 429 to be placed at the bottom end is received by the crane 201 and is mounted on the assembled panel 301 (see FIG. 10 (a)), The reinforcing net connecting holes 432 are lifted up to fit the reinforcing net connecting holes 432, and then the reinforcing net connecting holes 432 are fastened together using a high strength bolt and a nut.

상기 지지 반력벽(439)은 육상에서 지하 흙막이 용벽이나 차수벽으로 많이 사용되고 있는 연속벽(slurry wall) 공법의 장점 중 철근망 근입과 콘크리트타설 방법을 도입 시공한다.The support reaction force wall 439 introduces a reinforcing net insertion method and a concrete pouring method among advantages of a slurry wall method which is widely used as an underground earth retaining wall or a water wall on the land.

연속벽 공법과 다른점은 안내벽(guide wall)과 트렌치(trench)가 형성되지 않으므로 안정액 사용액관리가 필요없고, 연결부(joint)처리가 불필요하다는 점, 굴착 및 수직도 관리가 필요없다는 점을 들수 있다.The difference from the continuous wall method is that no guide wall and trench are formed, so there is no need to manage the amount of stabilizing solution, no joint treatment is required, and no excavation and vertical management is necessary. have.

본 발명의 공법의 장점중 하나는 조립식판넬 조립 자체가 벽체의 형상을 이루고 자체 자중과 말뚝지지대 연결이 거푸집 및 보강지지대가 되므로, 콘크리트 타설시 거푸집 설치 한계로 인한 콘크리트 타설 높이 제한, 타설횟수 연장 및 그에 대한 거푸집 보강 설치, 해체 공종이 불필요하며, 단면 강성이 강한 철근콘크리트 벽체의 현장타설 공법으로 제체가 타공법에서 사용되는 부재를 서로 연결하는 번거러움과 시공상의 문제를 해결할 수 있는 방법으로 시공되므로, 하부후팅 조립체가 안착된 상태에서 기반암에 연결되어 일체화되는 구조적 강점을 지니고 있다.One of the advantages of the method of the present invention is that since the assembled panel assembly itself forms the shape of the wall and its self weight and pile support connection form a formwork and a reinforcing support base, it is possible to limit the height of the concrete casting height, Since it is constructed in such a way as to solve the troubles and construction problems of connecting the members used in the other method by the field installation method of the reinforced concrete wall having a strong section, which does not require form reinforcement installation and dismantling work, And has a structural strength in which the bottom fitting assembly is connected to the bedrock in a state in which the bottom fitting assembly is seated.

또한, 내항이 해수유통보다 정온유지를 우선시하는 액화 천연가스 저장시설이라면, 인접 통수로 구역을 같은 방법으로 철근 콘크리트 벽체를 조성하면 어떤 환경 외력에도 대응 가능한 우수한 방파제라 할수 있다.In addition, if the inner port is a liquefied natural gas storage facility that prioritizes maintaining a constant temperature rather than seawater circulation, constructing a reinforced concrete wall in the same way as an adjacent waterway area is an excellent breakwater capable of coping with any environmental external force.

도 10(b)에 도시된 해상 콘크리트 작업선(210)과 트레미파이프(209)를 이용 콘크리트타설을 하며 철근 콘크리트 벽체를 조성함으로 파력을 상쇄시킴과 동시에 제체의 구조적 안정성을 확보하는데 있다. 지지반력벽체의 두께는 지지말뚝의 직경 1.5 ∼ 2 배인 3 ∼ 4m 정도로 한다.10 (b) and the tremy pipe 209 shown in FIG. 10 (b) to construct a reinforced concrete wall. In this way, the wave is canceled and the structural stability of the fluid is secured. The thickness of the supporting reaction force wall should be 3 ~ 4m, which is 1.5 ~ 2 times the diameter of the supporting pile.

이때 사용되는 콘크리트는 동결, 융해 저항성이 강하고 황산염 공격을 감소시키는 플라이에쉬와 같은 포졸란이 함유된 시멘트 함량이 385 - 565 kg/㎥짜리의 포틀랜트 시멘트나 ASTM type-Ⅱ 시멘트를 사용한다.The concrete used is Portland cement or ASTM type-Ⅱ cement with 385 - 565 kg / ㎥ of cement content containing pozzolans such as fly ash which is resistant to freezing, melting and reducing sulphate attack.

상기 철근망(429)의 지지 반력벽(439) 작업이 끝나면 파력 발전기 거치부에 조립식 판넬(433)위의 받침대(430), 보강용 철근망을 도 11에 도시된 바와 같이 철근망 걸쇠부(445)를 말뚝 지지대 세로 연결대(418)위에 잘 맞춘 다음 파력 발전기 받침대의 철근망 연결판(451)끼리 볼트와 넛트를 사용하여 결합한다.When the support reaction force wall 439 of the reinforcing net 429 is finished, the pedestal 430 on the assembled panel 433 and the reinforcing steel net are connected to the reinforcing net clasp 445 are aligned on the pile support vertical connection base 418, and then the reinforcing mesh connection plates 451 of the wave generator base are coupled with each other using bolts and nuts.

이와 같이 철근망 조립이 끝나면 받침대 콘크리트 타설부까지 트레미 파이프(209)를 이용하여 콘크리트를 타설한다(도 10(b) 참조).When the rebar net assembly is finished, the concrete is laid by using the trampeye pipe 209 to the concrete pouring portion of the pedestal (see Fig. 10 (b)).

기 제작된 파력 발전기 실린더실을 콘크리트 타설면위에 거치한 뒤 상하 연결고리(412)와 상부 및 옆면에 있는 와이어 연결고리(227)에 와이어를 끼워 넣고 상. 하. 좌. 우 방향으로 인접 연결고리와 인장 결속한다.After mounting the manufactured wave generator cylinder chamber on the concrete installation surface, the wire is inserted into the upper and lower connection rings 412 and the upper and side wire connection rings 227, Ha. Left. And tensions are bound to the adjacent link rings in the right direction.

도 11(c)에 도시된 파력 발전기(104)의 종류에는 진동수주형과 월파형 2 가지가 있으며, 파랑에너지 변환 효율이 용이하고 파고의 크기에 관계없이 에너지 취득이 가능한 진동수주형 설치를, 예컨데 진동수주형은 유수실과 터어빈을 회전시키기 위한 공기순환실이 먼저 확보되어야 한다.There are two types of wave power generators 104 shown in Fig. 11 (c), that is, a vibration frequency mold and a wall wave form, and a vibration frequency casting installation capable of easily obtaining wave energy conversion efficiency and obtaining energy regardless of the wave height, The mold should be provided with an air circulation chamber for rotating the watertight chamber and the turbine.

상기 파력 발전기(104)를 가동시키기 위한 파력을 획득하기 위해 어느 일정한 수심을 필요로 하며, 그 조건에 맞는 지역에 설치시 잠함의 깊이 또한 어느 정도의 깊이를 유지하기 위한 체적과 설치를 위한지지 수단이 필요한 것이다.A certain depth of water is required to obtain the wave power for operating the wave generator 104, and a volume for maintaining the depth of the submergence and a certain depth at the time of installation in the area satisfying the condition, .

이에 따른 시설 공사를 할 필요없이 본 발명의 공법 제체 구축시 약간의 추가 공정만 가미하면 설치가 가능한 것이다.The construction of the method of the present invention can be carried out only by adding a little additional process.

상기 파력 발전기(104)의 설치가 끝나면, 도 2 와 같이 통수로 구역 전면에 크레인(201)을 이용하여 인공어초(108)를 조립식 판넬 전면에 부착 수직으로 설치한다.When the wave generator 104 is installed, the artificial fish candle 108 is vertically installed on the front surface of the assembled panel using the crane 201 on the entire surface of the water channel as shown in FIG.

설치 높이는 수면위 육안으로 식별될 수 있는 위치까지만 적재(이는 선박의 충돌을 방지하기 위한 충돌 방지턱 역할을 수행하기 위함이다), 도 11(d)에 도시된 인공어초(108)의 상하 연결고리(443)와 좌, 우 연결고리(444)에 와이어(611)를 끼워 넣고, 상하는 제일 상부에 위치한 조립식 판넬(109) 상단 연결고리에서부터 조립식 케이슨 연결고리(607)까지 좌우는 좌, 우측에 설치된 현장 타설말뚝(416)의 원형부 조립식 판넬 연결고리에 각각 넣어 유압실린더로 인장하여 체결하며 와이어 소켓으로 결속한다.The installation height is limited only to the position where it can be visually recognized on the water surface (this is to serve as a collision preventing chin for preventing the collision of the ship), the upper and lower connecting links of the artificial fish weights 108 shown in FIG. 11 (d) 443 and the left and right connection rings 444 and the left and right sides installed on the left and right sides from the upper connection link of the assembled panel 109 located at the uppermost position to the assembled casement connection link 607 Are inserted into the circular assembled panel connection rings of the piercing piles (416), respectively, and are tightened with hydraulic cylinders and fastened by wire sockets.

이는 입사파의 집중력을 분산시켜 파력을 감쇄시킴과 동시에 반사파로 인한 중복파가 발생할 수 있는 여지를 대폭 감소시킬 수 있는 소파기능을 수행함과 동시에, 지금까지 인공어초(108) 포설시 가장 큰 난제인 수심대별 포설을 위한 숙제도 해결됨과 동시에 다양한 어패류의 증식을 기대, 인근 어장의 수산업 증대에도 크게 기여할 수 있다.This is because it disperses the concentration of the incident wave to attenuate the wave power, and at the same time, it functions as a sofa that can greatly reduce the possibility of occurrence of the overlapping wave due to the reflected wave, and at the same time, Homework for installation of water depths is solved, and at the same time, various fish and shellfish proliferation can be expected, which can contribute greatly to the fisheries growth of nearby fisheries.

상기 인공어초(108)까지의 설치가 끝나면, 도 10(c)와 같이 현장타설 말뚝(416)과 지지 반력벽(439) 상부의 두부를 정리하고, 각 말뚝과지지 반력벽체간의 철근, 콘크리트, 캡 비임(310)을 설치하여 일체화시키며, 측방향(수평 방향)의 휨모멘트와 편심하중을 감소시켜 지지말뚝의 두부의 손괴 변형을 예방함과 동시에 구조물 전체를 안정화시키며, 상재하중을 균등하게 연직 방향으로 전달시켜 기반암과 하부후팅(505)을 통한 해저면에 전달시킴으로 부등침하를 예방할 수 있다.10 (c), the head portions of the above-ground drilled piles 416 and the upper portion of the support reaction force wall 439 are arranged, and the reinforcing bars, concrete, The cap beam 310 is installed and integrated, the bending moment and the eccentric load in the lateral direction (horizontal direction) are reduced to prevent the deformation of the head of the pile of the support pile and to stabilize the entire structure, And transmitted to the seabed surface through the bedrock and the lower hood 505, thereby preventing the differential settlement.

상기 캡 비임(310)위에 다시 도 10(d)와 같이 상판(마루판 : 311)을 설치한다. 통상의 방파제 상치 콘크리트(마루판 : 311)는 케이슨과 커튼월식, 사석식 공히 반사파에 의한 반복파로 인한 제체 저변에 부분 침식이 일어나므로, 이에 대한 대책으로 방파제 외측에 설치된 커튼월과 배후벽사이에 유수실을 설치한다.10 (d), a top board (floor board) 311 is installed on the cap beam 310 again. As a countermeasure against the occurrence of partial erosion at the bottom of the embankment due to repetitive waves caused by reflected waves due to the caisson, curtain wall lattice, and lagoon type, the conventional breakwater concrete flooring (flooring: 311) Install a thread.

그 밑에 통수로를 확보하거나 유공 케이슨을 설치한 형상의 해수 교환식 반사파 저감 공법을 사용하고 있으나, 본 발명의 공법에서는 구간별 전 구역이 수심대별 통수로 역할을 수행하도록 되어 있음으로 별도의 해수 교환시설이 필요없다.In the method of the present invention, since the whole area of each section is assumed to serve as a water passage for each water depth, a seawater exchange system .

큰 파랑 내습시 커튼월일 경우 방파판 간의 결속이 흐트러지거나, 사석식일 경우 피복석의 손실로 인한 제체 전체의 미세한 균열로 인한 마루판(311)이 균열되는 등의 여지가 있으나, 상기와 같은 캡 비임(310)을 설치함으로 각 지지말뚝과 지지 반력벽이 일체화됨으로 인해 상기와 같은 우려에 대응할 수 있다.There is a possibility that the coupling between the diaphragms is disturbed in the case of a large wave invasion, and the floor plate 311 is cracked due to the minute cracks of the entire body due to the loss of the clay stone in the case of the quartz type, 310 are installed, the respective support piles and the support reaction force wall are integrated, thereby being able to cope with the above-mentioned concerns.

상기 상판(마루판 : 311)의 그 여유 공간은 도 1 에 도시된 태양광 집전판(103)을 설치하고, 집전 면적이 부족할 때 마루턱(120)위에 추가 설치함으로, 태양광 발전시 가장 큰 애로요인중 하나인 집전판 설치시설 및 부지 확보 문제를 해결할 수 있다.The solar collector plate 103 shown in FIG. 1 is installed in the clearance space of the upper board (floorboard 311), and the solar collector plate 103 is additionally installed on the floor cover 120 when the current collecting area is insufficient. One of the problems is that you can solve the problem of installing the front plate installation facility and site.

상기 마루턱(120) 후면에 말뚝 지지대와 연계해 풍력 발전기의 타워를 설치함으로, 상기 풍력 발전기(102)의 회전력과 양력을 충분히 감당할 수 있다.The tower of the wind power generator is installed in connection with the pile support on the rear surface of the floor tile 120, so that the rotational force and the lift of the wind power generator 102 can be sufficiently provided.

방파제 설치 지역 권역내 소요되는 전력량이 부족할 시에는 도 1 와 같이 독립 풍력발전 기능(105)을 추가 설치하여 방파제 구축시 같은 공법으로 설치할 수 있는 바, 시설 공사시 병행 작업을 함으로 시간적, 공간적, 경제적 절감을 기할 수 있다.If the required amount of electric power is insufficient in the area where the breakwater is installed, it is possible to install the independent wind power generation function (105) as shown in FIG. 1 and install it by the same method when constructing the breakwater. You can save money.

이 독립형 풍력 전기 주변에는 인공어초(108)를 설치함으로, 형태적 특성에 따라 공간 구성비가 높은 인공어초(108)를 설치시 파랑 및 조류에 영향을 받아 한 장소에 겹쳐지면서 군집을 이루는 현상이 발생, 세굴에 의한 매몰과 자중에 의한 침하발생으로 어초의 공용적이 감소, 어초의 기능이 감소되어 어족자원의 위집이나 흐름을 자극하는 기능이 떨어지는 것을 예방할 수 있다.The artificial fish (108) is installed around the independent wind power generator, and when the artificial fish (108) having a high spatial composition ratio is installed according to the morphological characteristics, it is affected by the waves and algae, , Sinking due to burrowing by crypts and sinking due to self weight, reduction of the common enemy of the reefs, and reduction of the function of the reefs can prevent the degradation of the function of irritating the flow of fish stock.

한편, 해상풍력발전기의 설치방법에는 중력식, 부유식, 파일식등 세 가지로 대별되고 있으며, 상기 중력식은 그 자체 무게가 크고 설치 지반이 극히 제한적이며 심도가 깊을수록 규모가 기하급수적으로 증대되기 때문에 적용 조건이 까다롭다.On the other hand, the installation methods of offshore wind power generators are classified into gravity type, floating type, pile type, and the gravity type has its own weight, the installation ground is extremely limited, and the deeper the depth, Application conditions are tricky.

상기 부유식은 설치지역이 깊은 심도에도 적용 가능하고 입지조건이 보다 자유로우나 강재 가격의 상승, 계류장치의 시설, 송전로에 관한 제반 문제 등이 부수적으로 따른다.The floating type is applicable to the deep depth of the installation area, and the location condition is more free, but the increase of the steel price, the facilities of the mooring device, and all the problems related to the transmission route are incidental.

상기 파일식은 시설이 비교적 까다롭지 않고 연약지반 적용을 할 수 있는 등의 강점이 있고, 모노파일과 쟈켓식 두 가지로 대별되며 모노파일은 적용성은 좋으나 편심하중의 우려, 부재에 대한 피로하중과 세굴에 대한 문제가 근본적으로 해결되지 않으며 쟈켓식을 많이 채택하고 있다.The above-mentioned file system has the advantages such as the facility is relatively difficult and the soft ground can be applied. There are two types of mono file and jacket type. Mono file has good applicability, but there are concerns about eccentric load, The problem with oysters is not fundamentally solved, and many adopts a jacket formula.

그러나, 심도가 깊어질수록 쟈켓의 규모 역시 비례해서 커야 하므로, 이에 대한 육상제작, 운송, 진수, 설치에 따른 권상장비 또한 대형화 되어야 하기에 최소 800톤 이상의 대형장비가 사용되므로, 극히 제한적인 장비 일정에 따라 공사기간이 정해 져야 되는 불이익을 감수해야 한다.However, since the size of the jacket must also be proportionally larger as the depth of deeper becomes deeper, the hoisting equipment required for land manufacturing, transportation, launching and installation must also be enlarged. Therefore, The construction period must be determined according to the disadvantages.

이 역시 세굴에 대한 문제를 예방하기 위해 쟈켓 설치후 해저면 파일 주위에 근고블럭 설치 등 추가 시설이 불가피하며, 이미 진행된 세굴은 피할수 없는 현상이다.In order to prevent the problem of scouring, additional facilities such as the installation of a vertical block around the seafloor file after installation of the jacket are inevitable, and the already scouring is inevitable.

본 발명의 공법은 파일 설치전 미리 조립식케이슨을 설치하여 파일 주변을 휘감는 집중와류를 하부후팅에서 저변 분산시킴으로, 그로 인한 함몰현상은 발생하지 않는다. 또한 모든 공정이 300 톤 이하로 운용 가능하다.In the method of the present invention, a prefabricated caisson is installed in advance to install a file, and a concentrated vortex around the file is dispersed in the bottom soffit, so that the depression phenomenon does not occur. In addition, all processes can be operated under 300 tons.

독립 풍력발전기(105)의 하부구조인 현장타설 말뚝을 이용 그물망 지지대로 한 외해 가두리 양식장(122)을 설치할 수 있으므로 비교적 대형 어종의 수산 증식에 기대를 도모할 수 있다.It is possible to install an outer sea cage farm (122) having a mesh support using a cast-in-place pile, which is a lower structure of an independent wind power generator (105), so that expectation can be expected for aquaculture of relatively large fish species.

가두리양식은 연안수역의 일부를 차지하므로 주변 해수의 환경영향을 직접적으로 받는다. 많은 양식장이 설치되면서 양식어의 배설물 섭식이 되지 못한 사료, 폐사어, 잔유동물 약품 등으로 인해 지층에 퇴적되어 부패 분해되면서 많은 용존산소를 소비하게 되어, 무산소환경이 조성되면서 적조현상 등 여러 가지 환경오염을 유발하고 있다.The cage culture forms part of the coastal waters, so it directly receives the environmental impacts of the surrounding waters. As many farms have been installed, they have been deposited on the ground due to feedstuffs, dead fishes, and residual animal drugs that have not been consumed in the aquaculture and are consuming a large amount of dissolved oxygen as a result of decomposition and decomposition. .

이에 오, 폐물 방류에도 영향을 받지 않는 외해에서의 가두리양식은 이런 잠재적인 문제들을 감소시킬 수 있다. 가두리양식은 침하형, 반침하형, 부양형 등 3 가지로 나누어 지고 있는 바, 상기 부양형은 이동성이 양호하나 케이지(cage)제작에 한계가 있으며, 양어용량(수용한계 : 40 - 70톤)이 적을 수밖에 없으며, 반침하형과 양식장규모를 보다 크게 키울수 있으나 계류시킬 수 있는 시설이 필요하며, 그 설치조건이 적합해야만 하므로 제한적이며 케이지(cage)를 부상시킬수 없으며 규모 또한 10,000 ㎥(수용한계 2,000톤)를 넘지 못한다.Thus, cage culture in offshore waters that are not affected by wastewater discharges can reduce these potential problems. The cage culture is divided into three types: subsidence type, semi-submerged type, and floating type. Although the floating type has good mobility, there is a limit to the production of cages, (Cage) can not be injured and the scale is also 10,000 m3 (capacity limit 2,000 tons). The size of the cage can not be increased, .

따라서, 상업적 이익을 창출하기 위해서는 수십 개의 방(chamber)을 마련해야 한다. 하지만 본 발명의 공법은 해수면(121)의 독립풍력발전기(105)에 설치된 크레인을 이용, 케이지(cage)에 설치된 와이어를 사용, 인양을 용이롭게 할 수 있으며 케이지(cage) 규모 또한 얼마든지 증가시킬 수 있으며, 모든 환경외력에 대해서도 상기 방식보다 우월하며 경제적이다.Therefore, dozens of chambers are required to create commercial profit. However, according to the method of the present invention, the cage installed in the independent wind turbine generator 105 of the sea surface 121 can be used to make use of the wire installed in the cage, and the cage size can be increased And is superior to the above-mentioned method for all environmental external forces and is economical.

상기 독립 풍력발전기(105) 상판위에 관리사무실 및 비품창고를 설치 운용할 수 있으므로, 접근성 또한 자유롭고 효율적인 운영관리 생산을 할수 있으므로 소득증대를 기할 수 있다.Since the management office and the equipment warehouse can be installed and operated on the top plate of the independent wind power generator 105, the accessibility is also free and efficient operation management production can be performed, so that the income can be increased.

설치방법은 각 독립 풍력발전기(105)의 현장타설 말뚝(416)에 주 와이어를 묶어 유압실린더로 인장 결속하고, 크레인으로 인양 할 수 있도록 하며 보조 와이어를 각 인공어초 연결고리에 연결하고, 보조 와이어끼리 연결해서 원하는 정도의 방을 만들어 최소 200,000 ㎥이상의 대규모 양식장을 종류별로 설치, 운용 가능하다.The installation method is such that a main wire is bundled into a cast-in-place pile (416) of each independent wind power generator (105), tensioned by a hydraulic cylinder, lifted by a crane, the auxiliary wire is connected to each artificial- It is possible to install and operate large scale farms with a minimum size of 200,000 ㎥ by type.

이렇게 하여 생선된 전력을 육상으로 이송하기 위한 방법으로 케이블을 매설하며 침설하는 방법으로 해저지반을 굴삭하여 그 홈에 전선을 매설하고 주변 해저토를 이용 매설하며 그 위에 쇄석으로 그물망을 만들어 채우고 그 위에 얹어서 요동을 막으며 중간 중간에 매설 앵커를 설치하여 태풍, 해일 등으로 인한 떠밀림을 방지하고 있다.As a way to transfer the fish power to the land, the cable is buried and the submarine ground is digged by buried cable, the cable is buried in the groove, the surrounding sea bed is buried, and the net is filled with crushed stone. It prevents the rocking due to typhoons and tsunamis by placing anchors in the middle of the bridge.

도 12 은 본 발명의 독립형 풍력 발전기 설치 및 송전관 거치부분의 상세도이며, 도 13 은 본 발명의 송전관 거치부 조립식케이슨 및 쟈켓 상세도이다.FIG. 12 is a detailed view of a stand-alone wind turbine generator installation and a transmission tower mount portion of the present invention, and FIG. 13 is a detailed view of a transmission tower mountable caisson and a jacket of the present invention.

도 1 에 도시된 해저면에 파이프를 침설하고 그 속에 송전선을 넣어 이송하는 송전관(614)을 각기 사용하고자 한다.It is desired to use each of the transmission pipes 614 for transferring a transmission line into the underside surface shown in Fig.

파이프 침설 방법으로는 해저면을 굴삭하여 자갈층을 포설하여 평탄함을 이룬 다음, 침매함을 투하하여 몰탈을 주입하는 몰탈주입 공법과 굴삭기로 선행 굴착한 다음 파이프를 침설하여 세굴현상을 이용하여 침설한 후 모래와 자갈을 포설한 후 주변 해저토를 이용하는 스크리트 공법 등이 있으나, 이 2 가지 방법다 장시간 소요시 압밀 침하의 발생 우려가 농후하므로 말뚝기초에 의한 침하 대책이 필수 불가결 하다.As a method of pipe incineration, the gravel layer is laid on the seabed to make it flat. Then, the mortar is injected by injecting the mortar and the mortar is poured into the pipe. However, these two methods are indispensable for the settlement due to the pile foundation since the risk of consolidation settlement is high for a long period of time.

따라서, 전술한 조립식 케이슨을 이용한 현장 타설말뚝 공법을 적용해서 해저 지반에 길다란 형태로 하부후팅(101)을 조성하여 파주력을 높이고, 압밀 침하와 부등침하에 대응하기 위해 말뚝기초를 사용하여 구조체를 조성하고, 그 위에 송전관을 부착하여 조립식 케이슨의 연결고리를 이용하여 와이어를 결속함으로, 송전로를 안정하게 시설함으로 조류 및 태풍, 해일등에 의한 송전관(614)이 이동하는 것과 어선에 의한 저인망 등으로부터 송전관(614)을 방호하기 위함이다.Therefore, by applying the above-mentioned cast-in-place pile method using the above-mentioned prefabricated caisson, the lower float 101 is formed in a long form on the bottom of the sea floor to increase the breaking force. In order to cope with consolidation settlement and uneven settlement, The transmission line is stably installed by bonding a wire using the connection ring of the prefabricated caisson by attaching a transmission line on the transmission line. The transmission line 614 is moved by algae, typhoon, tidal wave, etc., So as to protect the power transmission pipe 614. [

구체적인 설치 방법은 전술한 도 3(a)와 같이 준설을 한 다음 도 3(b)와 같이 조립식 케이슨을 설치하되, 도 13 에 도시된 바와 같이 형태가 다른 송전관 거치대 부분 조립식 케이슨(623)과 송전관 말뚝부분 케이슨(622)로 구성되어 있으며, 송전관 거치대 부분도 숫 조립식 케이슨 연결부(624)와 암 조립식 케이슨 연결부(625)로 나누어져 있다.As shown in FIG. 3A, the concrete installation method is performed by dredging as shown in FIG. 3 (a), and then a prefabricated caisson is installed as shown in FIG. 3 (b) And a power transmission pipe pile portion caisson 622. The transmission line rest portion is also divided into male and female caisson connecting portions 624 and 625, respectively.

하부후팅(101)과 연결의 송전관 연결부에 맞도록 설치한다(도 13(a) 참조). 이 조립식 케이슨(622, 623)을 길이 방향대로 조립하며, 거치부 케이슨 연결부 마다 말뚝부분 케이슨이 놓여 지도록 배치한다. 거치가 끝나면 도 13(b)에 도시된 쟈켓을 말뚝부분과 거치대 부분에 설치하여 연결판끼리 볼트와 넛트로 조립 연결한다.(See Fig. 13 (a)). The prefabricated caissons 622 and 623 are assembled in the lengthwise direction, and placed so that the caisson of the pile portion is placed on each caisson connection portion of the mounting portion. When the mounting is completed, the jacket shown in FIG. 13 (b) is installed at the pile portion and the mounting portion, and the connecting plates are assembled and connected with the bolts and the nuts.

도 12(b)에 도시된 바와 같이, 조립식 케이슨(622, 623)내에 해상 콘크리트 작업선(210)과 트레미파이프(209)를 사용하여 수중 콘크리트 타설을 하며, 이때 타설 높이는 조립식 케이슨 상단 높이와 같게 한다.As shown in FIG. 12 (b), underwater concrete is poured into the prefabricated caissons 622 and 623 using a marine concrete working line 210 and a tremipule pipe 209, The same.

상기 타설이 끝나면, 도 6(a)와 같이 유도강관(208)내에 근입강관(211)을 집어넣고, 바이브로 햄머(212)로 요동 압입시킨 후 철근망(217)을 근입하되, 이때 철근망(217)의 높이는 유도강관(208) 보다 10cm 낮게 제작하여 설치한다.6A, after inserting the inserted steel pipe 211 into the induction steel pipe 208, the reinforcing steel pipe 217 is inserted into the reinforcing steel pipe 208 after pivotally pressing the inserted steel pipe 211 into the vibro hammer 212. At this time, (217) is lower than the induction steel pipe (208) by 10 cm.

도 6(c)와 같이 해상 콘크리트 작업선(210)과 트레미파이프(209)를 이용하여 수중 콘크리트 타설을 하며, 이때 타설 높이는 조립식 케이슨 상단과 같이 한다.As shown in FIG. 6 (c), the underwater concrete is poured using the marine concrete work line 210 and the tremy pipe 209, and the height of the pile is made like the top of the prefabricated caisson.

그 다음 도 12(a)와 같이 후렌지(615)가 부착된 파이프를 고무패킹(621)을 끼워 넣고, 볼트와 너트로 조립하여 송전관 거치대위에 거치한 다음, 도 12(b)에 도시된 유도강관(208)에 연결된 연결고리(607)에 와이어(611)를 끼워 넣어 반대편 연결고리(607)에 인장, 체결한다. 거치대 부분 연결고리는 같은 방법으로 실시한다.Next, as shown in FIG. 12 (a), the pipe with the flange 615 is fitted into the rubber packing 621, assembled with bolts and nuts, and mounted on the transmission line rest. Then, The wire 611 is inserted into the connecting ring 607 connected to the steel pipe 208 and is tensioned and fastened to the opposite connecting ring 607. The cradle should be connected in the same way.

도면 중 부호 503 은 조류흐름, 617 은 강관절단부, 618 은 강관내 콘크리트 타설부, 619 는 송전관 받침대 콘크리트 타설부를 나타낸다.In the drawings, reference numeral 503 denotes a tidal flow, 617 denotes a steel pipe cutting portion, 618 denotes a concrete pouring portion in a steel pipe, and 619 denotes a transmission pipe support concrete pouring portion.

따라서, 상기와 같은 복합 발전기능의 반투과성 방파제는 어떠한 형태의 지반에서도 적용이 가능하며, 산업잠수부가 투입 가능한 수심 80 m 까지 시설이 가능하므로, 입지 선정의 폭이 넓고 또한 복합발전 설비를 수용할 수 있는 장점이 많다. 그러므로, 전력수급계획의 지방 분권화 사업에도 활용하여 적극 반영할 수 있으며, 특히 제주도 및 울릉도와 같은 전략적 거점지역에 적용하면 시너지 효과가 탁월하게 나타난다.Therefore, the semi-permeable breakwater of combined power generation function as described above can be applied to any type of ground, and the industrial divers can be installed up to a depth of 80 m, so that the range of site selection is wide and the complex power generation facility can be accommodated There are many advantages. Therefore, it can be applied to local decentralization projects of power supply and demand plan, and synergy effect is excellently applied to strategic bases such as Jeju and Ulleungdo.

도 1 에 도시된 마루턱(120)을 높이므로 월파를 방지하고, 그 배후에 배관시설을 함으로써 돌핀으로서의 기능을 충분히 감당할 수 있음으로, 유류나 천연가스 배송 터미널로서의 역할을 수행하기도 가능하다. 저장소까지의 배관라인은 송전관 옆에 나란히 설치하면 된다.Since the flooring 120 shown in FIG. 1 is heightened, it is possible to prevent the flooding and to provide a piping facility behind the flooring 120 to sufficiently fulfill its function as a dolphin. The piping line to the storage can be installed side by side beside the transmission line.

도 12(c)에 도시된 독립풍력 발전기(105)와 연계해 풍력 발전기(102)의 타워(114)를 설치함으로, 상기 풍력 발전기(102)의 회전력과 양력을 충분히 감당할 수 있다. 그리고 타워크레인(115), 출입구(119), 조명등(116), 계류장(118) 및 자재창고(117)가 설치되어 있다.The tower 114 of the wind power generator 102 is installed in connection with the independent wind power generator 105 shown in FIG. 12 (c), so that the rotational force and the lift of the wind power generator 102 can be sufficiently accommodated. A tower crane 115, an entrance 119, an illumination lamp 116, a mooring platform 118, and a material warehouse 117 are installed.

도 14 는 송전관 설치도이다. 송전관로지역을 따라 전술한 방파제 구축과 같은 방법으로, 지역내의 해저 침전층(204)을 크레인(201)의 버켓으로 굴착해 내고, 도 13(b)와 같이 송전관 말뚝부분 조립식 케이슨(622)과 거치대부분 조립식케이슨(623)을 따라 모태 한쪽은 암조립 케이슨 연결부 (625)와 다른쪽은 숫조립케이슨 연결부(624)를 방파제 하부후팅 송전관 연결부에 맞도록 조립하여 도 1 에 도시된 송전탑(107)과 독립파력 발전기 (105)까지 각기 설치한다.14 is a view showing a transmission pipe installation. The subseismic sediment layer 204 in the area is excavated with the bucket of the crane 201 in the same manner as the construction of the breakwater along the transmission line region and the transmission pipe pile partially assembled caisson 622 is excavated as shown in FIG. Assembled to the arm assembly caisson connecting portion 625 on one side and the male caisson connecting portion 624 on the other side are assembled to fit the connecting portion of the breakwater lower backing power transmission pipe along the caisson 623, 107 and the independent wave generator 105, respectively.

설치시 판넬 간격을 유지하기 위해서 판넬내부에는 목재를 고이고 연결고리(607)에 와이어를 끼워 넣어 반대편 연결고리까지 넣고 인장하여 체결한다. 목재와 와이어 해체는 쟈켓을 넣을 때 제거한다.To maintain the panel spacing during installation, hold the wood inside the panel, insert the wire into the connection ring (607), insert it to the opposite connection ring, and tighten it by tightening. Dismantle the wood and wire when removing the jacket.

케이슨 쟈켓은 도 13(b)와 같이 말뚝부분 쟈켓과 거치대부분 쟈켓으로 나누어지며, 연결부(409)끼리 맞추어 볼트와 너트로 조립하여 체결 설치한다. 앞서 시공한 방파제와 같은 방법으로, 크레인(201)과 해상 콘크리트 작업선 (210)과 트레미파이프(209)를 이용하여 수중 콘크리트 타설을 하며, 이때는 1 차 및 2 차 구분없이 한꺼번에 타설한다. 이는 근입강관(211)을 사장시키지 않고 인발 재사용할 수 있는 케이싱(307 : 투하용 파이프)을 사용하는 까닭이다.As shown in FIG. 13 (b), the caisson jacket is divided into a pile portion jacket and a cradle portion jacket. The caisson jacket is assembled with bolts and nuts by fitting together the connecting portions 409 and fastened. The underwater concrete is poured by using the crane 201, the marine concrete work line 210 and the tremy pipe 209 in the same manner as the breakwater constructed in the previous step. In this case, it is poured at once without primary and secondary distinction. This is because the casing (307: discharge pipe) which can pull and reuse the core steel pipe 211 without using it is used.

상기 근입강관(211)의 직경은 1,500 mm 를 사용한다. 조립식 케이슨내 콘크리트 타설이 끝나면, 유도강관(208)안으로 케이싱(307)를 조립 연결해서 유도강관(208)내에 집어넣고, RCD장비를 장착하여 기반암까지 굴착하고 철근망(217)을 집어넣는다. 상기 철근망 높이는 유도강관 상단 10cm 이하까지 맞춘다.The diameter of the near-inlet steel pipe 211 is 1,500 mm. Once the concrete pouring in the prefabricated caisson is completed, the casing 307 is assembled and connected into the induction steel pipe 208 and inserted into the induction steel pipe 208. The RCD equipment is mounted to the bedrock and the reinforcing mesh 217 is inserted. The height of the reinforcing net is adjusted to 10 cm or less at the top of the induction steel pipe.

이는 콘크리트 피복의 두께를 유지하기 위함이다. 상기 철근망 근입이 끝나면 크레인(201)과 해상콘크리트 작업선(210)과 트레미파이프(209)를 이용하여 공내 콘크리트 타설을 하며, 타설 높이는 유도강관(208) 상단부분까지 한다.This is to maintain the thickness of concrete cladding. When the reinforcing net is completely inserted, the in-hole concrete is poured using the crane 201, the marine concrete work line 210 and the tremy pipe 209, and the height of the concrete is laid up to the upper portion of the guide steel pipe 208.

이렇게 타설이 끝나면 케이싱 오실레이타(304)를 이용하여 클램핑 실린더(506)로 케이싱(307)을 압착한 다음, 좌, 우 유압실린더(507)를 사용하여 좌, 우로 번갈아 돌리면서 상, 하 유압실린더(508)를 이용하여 인발한다.When the installation is completed, the casing 307 is compressed by the clamping cylinder 506 using the casing oscillator 304, and then the left and right hydraulic cylinders 507 are used to alternately rotate left and right, And is withdrawn using the cylinder 508. [

조립된 파이프가 올라오면 케이싱 오실레이타(304)위에서 1 본씩 해체하여 크레인(201)으로 들어올려 근입강관을 제거한다. 이렇게 제거후 송전관(614)을 크레인(201)을 이용하여 송전관받침 콘크리트 타설부(619)위에 놓고, 고무패킹(621)을 끼워넣어 송전관(614)끼리 볼트와 너트로 체결한다. 상기 송전관(614)의 직경은 1 m 이상이라야 한다.When the assembled pipe comes up, it is disassembled one by one on the casing oscillator 304 and lifted up to the crane 201 to remove the inserted steel pipe. After the removal, the transmission pipe 614 is placed on the transmission pipe supporting concrete pouring portion 619 by using the crane 201, the rubber packing 621 is inserted, and the power transmission pipes 614 are fastened with bolts and nuts. The diameter of the transmission pipe (614) is not less than 1 m.

이상과 같이 설치가 완료되면 와이어를 조립식케이슨 연결고리(607)에 각각 끼워넣어 반대편 연결고리에 걸고 유압실린더를 인장하여 결속한 후 전선(620)을 집어넣고 각 발전시설과 송전시설까지 연결한다.After the installation is completed, the wires are inserted into the assembled caisson connection rings 607, respectively, and the wires are connected to the opposite connection rings. The hydraulic cylinders are tied together and then the wires 620 are inserted and connected to each power generation facility and transmission facility.

이상 설명한 바와 같이 본 발명은 조립식 케이슨의 현장타설 말뚝공법을 채택하여 해저 지형조건의 여러 가지 제약요건을 극복하고 보다 폭 넓은 입지를 선정할 수 있으며, 구역별로 블록을 정해 매립하여 통수로 부분을 설정하고 제체 전면부에 파력 발전기 거치대 부분을 돌출시켜 입사파 파력의 첨두 부분을 분할시켜 집중력을 감소시킴과 동시에, 입사파의 흐름을 분리하여 소파기능을 수행하는 인공어초를 설치함과 파력 발전기 배출수의 와류를 이용, 접근 파랑에 대한 반사파를 저감시키는 동시에 그 흡인력을 이용, 일방향 와류세기를 최대화, 해수 흡출효과를 극대화하여 용승류 작용을 유발시켜 해수유통 원할을 기할 수 있다.As described above, the present invention adopts the field piling method of the prefabricated caisson to overcome various constraint requirements of the seabed topography condition and to select a wider location, And the peak part of the wave power is divided by the protruding part of the wave generator in the front part of the body to reduce the concentration of the wave and to separate the flow of the incident wave to install the artificial fish candle functioning as a sofa function, By using the vortex, it is possible to reduce the reflection wave to the approach wave, maximize the strength of the one-way vortex using the suction force, maximize the seawater suction effect, and induce the action of the seawater.

본 발명은 철근 콘크리트로 지지반력벽을 현장타설 벽체로 구축함으로 파력에 대한 반력과 구조체 전체의 안정성을 증진시킬 수 있고, 조립식 케이슨의 현장타설 말뚝공법을 적용함으로 매립 지역의 기초부분은 기반암과 접속되어 있으므로, 매립으로 인한 액상화, 압밀침하, 부등침하등 연약지반 생성 및 이에 대한 보강 처리 및 치환 공정이 불필요하다.The present invention can increase the reaction force against the wave and the stability of the whole structure by constructing the support reaction force wall with the reinforced concrete wall as the field piling wall, and applying the field piling method of the prefabricated caisson, Therefore, it is unnecessary to produce soft ground such as liquefaction, consolidation settlement, uneven settlement due to landfill, and reinforcement treatment and replacement process therefor.

또한 수심 80m(산업잠수부가 투입 가능한 심도)까지 시설작업이 가능함으로 입지 선정의 폭이 확대 될수 있다.In addition, it is possible to work on facilities up to 80m depth (the depth that industrial divers can inject).

본 발명은 제체 외부에 인공어초를 수직으로 부착 시설함으로 어초의 공용적 감소를 막아 어초의 기능저하를 방지하고, 다양한 생태계의 서식처를 제공하여 인근어장의 수산 자원 증식을 도모하므로 민원 해소에 기여할 수 있다.The present invention can prevent degradation of fish reefs by preventing artificial fishes from decreasing by restricting the reduction of fish reefs by installing artificial fishes vertically on the outside of the fishes and providing various habitats of ecosystems, have.

본 발명은 다양한 형태의 청정 에너지 발전 시설을 수용할 수 있으므로 지역내 전력 수급에 적극 대응할 수 있다. 또한 송전관 시설시에도 조립식 케이슨을 이용한 현장 타설말뚝 공법으로 송전로의 구조적인 체적을 유지하여 해저면과의 마찰력을 증가시키고, 지지말뚝을 병행 시공함으로 조류에 의해 송전선로가 이동하는 것을 막을 뿐아니라 어선의 저인망으로부터의 전선을 보호하고 파주력을 증대시킴으로, 파랑에 대한 시설물 안정을 확보함으로 안전하게 전력 이송을 할 수 있다.Since the present invention can accommodate various types of clean energy generating facilities, it can actively cope with power supply and demand in the area. Also, in the case of power transmission facilities, by using the built-in caisson, it is possible to maintain the structural volume of the transmission line by increasing the frictional force with the sea floor and to prevent the transmission line from moving by the algae However, by protecting the wire from the fishing net of the fishing boat and increasing the breaking power, it is possible to safely transfer the electric power by securing the facility stability against the wave.

본 발명의 종합 발전설비의 반투과성 방파제는 기재된 실시예에 한정되는 것이 아니고, 본 발명의 사상 및 범위를 벗어나지 않고 다양하게 수정 및 변형을 할 수 있음은 이 기술 분야에서 통상의 지식을 가진 자에게는 자명하다.It should be understood by those skilled in the art that the semipermeable breakwater of the general power generation facility of the present invention is not limited to the described embodiments but can be variously modified and modified without departing from the spirit and scope of the present invention. Do.

따라서, 그러한 변형예 또는 수정예들은 본 발명의 특허 청구범위에 속한다 해야 할 것이다.It is therefore intended that such variations and modifications fall within the scope of the appended claims.

101: 하부 후팅(footing)
102: 풍력발전기
103: 태양광 집전판
104: 파력발전기
105: 독립풍력발전기
106: 송전관
107: 송전탑
108:: 인공어초
109: 조립식판넬
110: 작업구
111: 태양광 발전실
112: 풍력발전기 받침판넬
113: 파력 인입구
114: 풍력발전기 타워(tower)
115: 타워크레인
116: 조명등
117: 자재창고
118: 계류장
119: 출입구
120: 마루턱
121: 해수면
122: 가두리양식장
201: 크레인
202: 바지선
203: 해저면
204: 해저침전물
205: 크람쉘버켓
206: 조립식케이슨
207: 쟈켓
208: 유도강관
209: 트레미파이프
210: 해상콘크리트 작업선
211: 근입강관
212: 바이브로 햄머
213: R.C.D비트
314: 굴착면
215: R.C,D파워팩
216: R.C.D 장비
217: 철근망(현장타설 말뚝용)
218: 굴착토 운반선
219: 콘크리트 타설부분
220: 천공기(그라우팅용)
221: 시멘트 주입기
222: 주입압
223: 그라우팅 단면구역
224: 주입방향
225: 콘크리트 주입호스
226: 붓싱 로울러
227: 와이어 연결고리
228: 원형 구멍
229: 1차 콘크리트 타설면
230: 집토탱크
231: 유도강관 보호대
232: 그라우팅파이프 보호대
301: 조립식 판넬
302: 조립식 판넬 원형부분
303: 말뚝보강 지지대
304: 쇄석집중 트하기
305: 굴삭기
306: 쇄석
307: 투하용 파이프
308: 사석고르기 장치
309: 두부정리면
310: cap beam
311: 상판 (마루판, 상치 콘크리트)
312: 레미콘 차량
401: H-beam
402: 철근
403: 그라우팅용 파이프
404: 앵글
405: 연결지지대
406: 넛트
407 : 볼트
408: 와샤
409: 연결부
410: 말뚝지지대 연결구멍
411: 원형부분 연결고리
412: 상.하.연결고리
413: 상부걸쇠(key)
414: 연결부 거치부분(home)
415: 원형부분
416: 현장타설말뚝
417: 말뚝 지지대 연결대 거치부분
418: 말뚝 지지대 세로 연결대
419: 말뚝 지지대 원형부분 (바깥쪽)
420: 말뚝 지지대 원형부분 (안쪽부분)
421: 말뚝 지지대 가로 연결대
422: 말뚝 지지대 연결부
423: 말뚝 지지대 연결부 상단판넬
424: 말뚝 지지대 연결부 하단판넬
425: 하단 조립식 판넬
426: 쟈켓 연결 지지대
427: 조립식 판넬 상단부
428: 조립식 판넬 하단부
429: 철근망(지지 반력벽용)
430: 철근망(파력발전기 받침대용)
431: 철판
432: 철근망 연결구멍
433: 파력발전기 받침대 조립식 판넬
434: 파력발전기 받침대용 말뚝 지지대
435: 통수구
436: 격자망(grate)
437: 외해→내해 유입수
438: 내해→외해 배출수
439: 지지반력벽
440: 파력발전기 해수 배출구
441: 공기 인입구
442: 공기 배출구
443: 인공어초 상하 연결고리
444: 인공어초 좌우 연결고리
445: 철근망 걸쇠부
446: 터빈 와류에 의한 배출수
447: 매립부
448: 파력발전기 설치부
449: 인공어초 설치부
450: 지지반력벽 설치부
451: 파력발전기 받침대 철근망 연결판
452: 받침대 보강용 철근망 연결부
453: 버림 콘크리트 타설부분
454: 파력발전기 받침대 철근망 거치부
455: 파력발전기 받침대 콘크리트 타설부
501: 매립부분
502: 통수부분
503: 조류의 흐름
504: 송전관 연결부
505: 하부 후팅
506: 크램핑 유압실린더
507: 좌,우 유압실린더
508: 상,하 유압실린더
509: 지지반력벽 상부 철근망
510: 지지반력벽 하부 철근망
601: 숫조립식케이슨
602: 암조립식케이슨
603: 원형구멍
604: 샌드펌프
605: 공기압주입구
606: 견인 및 연결고리
607: 연결고리
608: 공기압
609: 숫케이슨 연결부
610: 붓싱로울러
611: 와이어
612: 모서리케이슨
613: 양수호스
614: 송전관
615: 파이프 연결 후렌지(flange)
616: 후렌지 연결구멍
617: 강관 절단부
618: 강관내 콘크리트 타설부
619: 송전관 방침대 콘크리트 타설부
620: 전선
621: 고무팻킹
622: 송전관 말뚝부분 조립식 케이슨
623: 송전관 거치대 부분 조립식 케이슨
624: 숫조립식 케이슨 연결부
625: 암조립식 케이슨 연결부
101: Lower footing
102: Wind generator
103: Solar photovoltaic panel
104: wave generator
105: Independent wind power generator
106: transmission line
107: Transmission tower
108 :: artificial fishes
109: Prefabricated panel
110: Work area
111: Photovoltaic power generation room
112: Wind power generator support panel
113: Wave Inlet
114: Wind power generator tower (tower)
115: Tower crane
116: Lighting light
117: Material warehouse
118: Mooring
119: Entrance and exit
120: Floor tiles
121: sea level
122: Cage farm
201: Crane
202: Barge
203: Sea floor
204: Subsea sediment
205: Kramshell bucket
206: Prefabricated caisson
207: Jacket
208: Induction steel pipe
209: Treme Pipe
210: Marine concrete working line
211: Inserted steel pipe
212: Vibrohammer
213: RCD bit
314: excavation surface
215: RC, D power pack
216: RCD equipment
217: Reinforcing mesh (for casting piles in the field)
218: Excavated soil carrier
219: Concrete pouring part
220: Perforator (for grouting)
221: Cement injector
222: injection pressure
223: Grouting section section
224: injection direction
225: Concrete injection hose
226: Bushing roller
227: Wire connection ring
228: Circular hole
229: Primary concrete casting surface
230: Oyster tank
231: Induction Steel Pipe Protector
232: Grouting pipe protector
301: Prefabricated panel
302: Prefabricated panel circular portion
303: Pile reinforcement support
304: Crushed stone concentrate
305: Excavator
306: Crushed stone
307: Pipe for discharge
308: Rock-solidifying device
309: Tofu arrangement surface
310: cap beam
311: Top board (flooring, ceiling concrete)
312: Remicon vehicle
401: H-beam
402: Rebar
403: Pipes for grouting
404: Angle
405: connection support
406: Nut
407: Bolt
408: Washer
409:
410: Pile support connection hole
411: Circular section linkage
412: Upper and lower connecting links
413: Upper key (key)
414: connection part (home)
415: Circular portion
416: Field casting piles
417: Pile support linkage mounting part
418: Pile support vertical linkage
419: Pile support circular part (outside)
420: pile support circular part (inner part)
421: Pile support transverse links
422: Pile support connection
423: Upper panel of connection part of pile support
424: Lower panel of pile support connection
425: bottom panel
426: Jacket connection support
427: Prefabricated panel top
428: Lower part of the assembled panel
429: Reinforcing mesh (for support reaction wall)
430: Reinforcement net (for wave generator stand)
431: Iron plate
432: Reinforcing mesh connection hole
433: Wave generator stand assembly panel
434: Pile support for wave generator stand
435:
436: Grate
437: Outer sea → Inland sea influent
438: Inland Sea → Outside water discharge
439: support reaction force wall
440: Wave generator water discharge outlet
441: air inlet
442: Air outlet
443: Artificial fish supplements
444: Left and right articulation hooks
445: Reinforcing mesh clasp
446: Drainage by turbine vortex
447:
448: Wave generator installation part
449: Artificial fish supporter
450: support reaction force wall mounting portion
451: Wave generator stand Reinforcement net plate
452: Reinforcing net connection for bracket reinforcement
453: Discarded concrete part
454: wave generator stand base reinforcing mesh mount
455: Wave generator stand concrete pouring part
501: landfill portion
502:
503: Flow of algae
504: Transmission pipe connection
505: Lower backing
506: Cramping hydraulic cylinder
507: Left and right hydraulic cylinders
508: Up and down hydraulic cylinder
509: Supporting Reaction Wall Upper Reinforcement Network
510: Support Reaction Wall Lower Rebar Network
601: Male-built caisson
602: Cylinder with built-in arm
603: Circular hole
604: Sand pump
605: air pressure inlet
606: Towing and Connecting Hooks
607: Connection ring
608: Air pressure
609: Male caisson connection
610: Bushing roller
611: Wire
612: Edge caisson
613: Piping hose
614: Transmission pipe
615: Pipe connection flange
616: Flange connection hole
617: steel pipe cutting section
618: Concrete putting part in steel pipe
619: Transmission pipe policy to concrete installation part
620: Wires
621: Rubber packing
622: Transmission pipe pile partially assembled caisson
623: Transmission line cage partly assembled caisson
624: male assembled caisson connection
625: Female prefabricated caisson connection

Claims (5)

삭제delete 독립후팅 기초방식에 조립식 케이슨의 현장타설 말뚝공법을 적용하여 해저면에 하부후팅을 1 차 콘크리트 타설하고; 지지말뚝을 RCD 장비를 이용하며 기반암까지 굴착하여 접속시켜 상기 하부후팅상에 다수개 현장타설말뚝을 2 차 콘크리트 타설하며; 하부훗팅 상부에 구역별로 조립식 판넬을 쌓아 그 내부를 쇄석 및 토사를 충진시키고 ; 요철형태로 받침대 조립판넬을 상기 조립식 판넬이 적층된 다수의 현장타설 말뚝사이에서 전면으로 적층시키는 축조구조물에서,
상기 현장타설 말뚝들 사이에 설치된 받침대 조립판넬위에 파력발전기를 설치하고,파력발전기 후방에는 지지 반력벽이 설치되며 지지반력벽의 측면 인접구역은 해수를 유통시킬 수 있는 통수구와 격자망이 나있는 조립식 판넬을 설치하며 파력발전기의 전면에 다수의 인공어초가 적층되며;
상기 인공어초까지의 설치가 끝나면 현장타설 말뚝과 지지 반력벽 상부의 두부를 정리하고, 각 말뚝과지지 반력벽체간의 철근, 콘크리트, 캡 비임을 설치하여 일체화시키며, 상기 캡 비임위에 다시 상판(마루판)을 설치하게 되고;
상기 상판의 그 여유 공간은 태양광 집전판을 설치하고, 마루턱 후면에 현장타설말뚝과 연계해 풍력 발전기의 타워를 설치함으로, 상기 풍력 발전기의 회전력과 양력을 충분히 감당하도록 설치되며;
상기 풍력발전기에는 다수개의 송전관 거치대 부분 조립식 케이슨과 송전관 말뚝부분 케이슨으로 구성된 송전관을 설치되는 종합발전설비의 반투과성 방파제에 있어서,
상기 하부후팅과의 연결은 송전관 연결부에 맞도록 설치하는 데, 이 조립식 케이슨들을 길이 방향대로 조립하며 거치부 송전관 연결부 마다 송전관 말뚝부분 조립 케이슨이 놓여지도록 배치하며,
거치가 끝나면 쟈켓을 말뚝부분과 거치대 부분에 설치하여 연결판끼리 볼트와 넛트로 조립 연결하고,
조립식 케이슨내에 해상 콘크리트 작업선과 트레미파이프를 사용하여 수중 콘크리트 타설을 하며,
상기 타설이 끝나면 유도강관내에 근입강관을 집어넣고, 바이브로 햄머로 요동 압입시킨 후 철근망을 근입하되, 이때 철근망의 높이는 유도강관보다 10cm 낮게 제작하여 설치하고, 해상 콘크리트 작업선과 트레미파이프를 이용하여 수중 콘크리트 타설을 하며, 이때 타설 높이는 조립식 케이슨 상단과 같이 한 것을 특징으로 하는 종합발전설비의 반투과성 방파제.
Casting a first concrete to the bottom of the sea floor by applying the ground piling method of the prefabricated caisson to the independent float basis method; The supporting piles are connected to the bedrock by using RCD equipment to connect a plurality of piles to the second finishing pile; A prefabricated panel is stacked on top of the lower footing to fill the interior with crushed stone and gypsum; In a building structure in which a pedestal assembly panel is stacked on a front surface between a plurality of field drilled piles stacked with the prefabricated panels,
A wave generator is installed on a pedestal assembly panel installed between the excavated piles and a supporting reaction wall is provided on the rear side of the wave generator and a side adjoining area of the supporting reaction wall is provided with a water hole and a lattice net, A panel is installed and a plurality of artificial ear sheets are stacked on the front surface of the wave generator;
When the installation up to the artificial tongue is completed, the pile and the head of the supporting reaction force wall are assembled and the reinforcing bars, concrete, and cap beam between the piles and the supporting reaction force wall are installed and integrated, Lt; / RTI >
The space of the upper plate is provided to accommodate the rotational force and the lift of the wind power generator by installing a solar collecting plate and installing a tower of the wind power generator in connection with the casting pile on the rear side of the floor tile.
The present invention relates to a semi-permeable breakwater of a general power generation plant having a power transmission line composed of a plurality of transmission line holder partly assembled caissons and a power transmission pipe pile part caisson,
The connection between the lower fitting and the connecting pipe is made to fit the connection of the transmission pipe. The prefabricated caissons are assembled in the lengthwise direction, and the caisson assembly of the transmission pipe pile is placed in each connection part of the mounting part transmission pipe,
When the mounting is completed, the jacket is installed on the pile and the mounting base, and the connection plates are assembled and connected by bolts and nuts,
Inside the prefabricated caisson, underwater concrete is laid using marine concrete work line and tremie pipe,
When the above installation is completed, the main pipe is inserted into the induction steel pipe, and the reinforcing net is inserted into the pipe after the vibration is press-fitted into the vibro hammer. At this time, the height of the reinforcing bar is set 10 cm lower than the guide pipe, And the height of the pile is the same as that of the prefabricated caisson.
삭제delete 삭제delete 삭제delete
KR1020140034814A 2014-03-24 2014-03-24 Semipermeable breakwater of combined power generation facility KR101650232B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020140034814A KR101650232B1 (en) 2014-03-24 2014-03-24 Semipermeable breakwater of combined power generation facility

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020140034814A KR101650232B1 (en) 2014-03-24 2014-03-24 Semipermeable breakwater of combined power generation facility

Publications (2)

Publication Number Publication Date
KR20150110238A KR20150110238A (en) 2015-10-02
KR101650232B1 true KR101650232B1 (en) 2016-08-22

Family

ID=54341437

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020140034814A KR101650232B1 (en) 2014-03-24 2014-03-24 Semipermeable breakwater of combined power generation facility

Country Status (1)

Country Link
KR (1) KR101650232B1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20220091973A (en) 2020-12-24 2022-07-01 (주)구조실험네트워크 basic structure for marine wind power generation having dual tube CFT column

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106049351B (en) * 2016-07-28 2017-12-26 大连理工大学 Vertical breakwater with saturating stream berthing function
CN108552097B (en) * 2018-03-21 2020-09-25 大连理工大学 Anti-wave closed type deep-sea net cage convenient to move, consign and capable of generating power through wave energy
CN110984170B (en) * 2019-11-25 2021-07-16 上海水务建设工程有限公司 Semi-automatic foundation pit steel support installation method and steel support installation auxiliary device
CN114508093B (en) * 2022-02-11 2024-06-07 中冶华南建设工程有限公司 Construction process of ultra-deep underground continuous wall
CN117397622A (en) * 2023-04-19 2024-01-16 中国海洋大学 Offshore wind power foundation scour prevention and cultivation net cage integration device and method
CN117703659A (en) * 2023-12-26 2024-03-15 上海勘测设计研究院有限公司 Wave energy power generation device combined with breakwater

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100928569B1 (en) * 2009-07-30 2009-11-24 주식회사 항도엔지니어링 Apparatus for generating offshore wind power combined with tidal current power and wave force generation by utilizing a breakwater

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100872992B1 (en) * 2006-11-13 2008-12-08 라소선 Submarine fixation type sea structure which carries out the function of artificial reef and manufacturing method thereof
KR100939311B1 (en) * 2007-12-26 2010-01-28 주식회사 도화종합기술공사 Prestressed quay wall and construction method thereof
KR101256274B1 (en) 2010-08-02 2013-04-18 김상훈 Reverse Drill Method With precast type Caisson and Jacket
KR101211811B1 (en) * 2010-08-02 2012-12-12 김상훈 Cast in concrete pile With precast type Caisson

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100928569B1 (en) * 2009-07-30 2009-11-24 주식회사 항도엔지니어링 Apparatus for generating offshore wind power combined with tidal current power and wave force generation by utilizing a breakwater

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20220091973A (en) 2020-12-24 2022-07-01 (주)구조실험네트워크 basic structure for marine wind power generation having dual tube CFT column

Also Published As

Publication number Publication date
KR20150110238A (en) 2015-10-02

Similar Documents

Publication Publication Date Title
KR101650232B1 (en) Semipermeable breakwater of combined power generation facility
CN105544460B (en) Cast-in-place plant growing type eco-concrete slope protection construction method
KR20160080028A (en) Multipurpose artifical island
KR101650231B1 (en) Construction structures with wave power generator of semipermeable breakwater
CN104452829A (en) Piled raft foundation anti-floating structure and construction method
KR20150137725A (en) Construction structures of semipermeable breakwater with wind power generator
KR101256274B1 (en) Reverse Drill Method With precast type Caisson and Jacket
JP2004522012A (en) Artificial island and support for artificial island and method of constructing artificial island
JP2013002086A (en) Pile frame structure and structure of the same
KR102294871B1 (en) Core wall structure method of the independent cassion for offshore runway
CN204326119U (en) A kind of pile-raft foundation float Structure
KR20150137728A (en) Construction structures of semipermeable breakwater
JPH09165725A (en) Revetment structure with consideration given to ecological system
KR102294870B1 (en) Core wall structure of composite cassion for offshore runway
KR101684340B1 (en) Scour protection system for shore and its installation methods
CN102613116A (en) Artificial low-tide elevation device for protecting islands
JP3796690B2 (en) Artificial fishing reef, dam / dam construction method, river bed construction method, intake method, and river side wall construction method using the artificial fishing reef
KR20150105891A (en) The underground facilities for offshore airfield of semi land reclamation type
KR101082410B1 (en) Unit Module of Marine Structure for Forming Artificial Fishing Reef and Weakening Wavers
JP2011179204A (en) Revetment panel material for living-object symbiosis, and living-object-symbiotic-type revetment
JP3209503B2 (en) Water intake / discharge equipment underwater construction method
JP3977903B2 (en) Seaweed bed outside the breakwater and its construction method
JP3209502B2 (en) Water intake / discharge equipment underwater construction method
KR102483534B1 (en) Sofa block caisson and its installation method
WO2004113621A1 (en) Method of constructing underwater tunnel

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
AMND Amendment
E601 Decision to refuse application
AMND Amendment
X701 Decision to grant (after re-examination)
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20190806

Year of fee payment: 4