KR100538272B1 - The methods of trenchless underway construction using pre-cast assembly concrete box - Google Patents
The methods of trenchless underway construction using pre-cast assembly concrete box Download PDFInfo
- Publication number
- KR100538272B1 KR100538272B1 KR1020050039011A KR20050039011A KR100538272B1 KR 100538272 B1 KR100538272 B1 KR 100538272B1 KR 1020050039011 A KR1020050039011 A KR 1020050039011A KR 20050039011 A KR20050039011 A KR 20050039011A KR 100538272 B1 KR100538272 B1 KR 100538272B1
- Authority
- KR
- South Korea
- Prior art keywords
- propulsion
- ground
- prefabricated
- prefabricated structure
- steel pipe
- Prior art date
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/045—Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2200/00—Geometrical or physical properties
- E02D2200/16—Shapes
- E02D2200/1607—Shapes round, e.g. circle
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2300/00—Materials
- E02D2300/0004—Synthetics
- E02D2300/0018—Cement used as binder
- E02D2300/0021—Mortar
Landscapes
- Engineering & Computer Science (AREA)
- Environmental & Geological Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Excavating Of Shafts Or Tunnels (AREA)
Abstract
본 발명은 조립식 구조물을 이용한 비개착 지하통로 구축공법 (TUPAC공법)에 관한 것으로서, 보다 상세히 설명하면, 파이프 루프를 아치형(Arched-type) 또는 열린 박스형(門形)으로 추진 배열하여 1차 보강 목적을 달성한 후, 토사 굴착과 동시에 아치형 또는 박스형의 조립식 콘크리트 세그먼트를 이용하여 추진, 설치하는 공법을 국내 실정에 맞게 개발하여 공사 비용의 절감 및 공사 기간의 단축하는 조립식 구조물을 이용한 비개착 지하통로 구축공법에 관한 것이다.The present invention relates to an unattached underground passage construction method (TUPAC method) using a prefabricated structure, and in more detail, the primary purpose of reinforcing by arranging pipe loops in an arched or open box type. After attaining the excavation of soil, at the same time, the construction method of propulsion and installation using prefabricated concrete segments of arched or box type is developed according to the domestic situation. It is about public law.
Description
본 발명은 조립식 구조물을 이용한 비개착 지하통로 구축공법에 관한 것으로서, 보다 상세히 설명하면, 파이프 루프를 아치형(Arched-type) 또는 열린 박스형(門形)으로 추진 배열하여 1차 보강 목적을 달성한 후, 토사 굴착과 동시에 아치형 또는 박스형의 조립식 콘크리트 세그먼트를 이용하여 추진, 설치하는 공법을 국내 실정에 맞게 개발하여 공사 비용의 절감 및 공사 기간의 단축하는 조립식 구조물을 이용한 비개착 지하통로 구축공법에 관한 것이다.The present invention relates to an unattached underground passage construction method using a prefabricated structure, which will be described in more detail, after arranging pipe loops in an arched type or an open box type to achieve a primary reinforcement object. And unearthed underground passage construction method using prefabricated structure to reduce construction cost and shorten construction period by developing method to propel and install using prefabricated concrete segment of arch or box type at the same time .
보다 안전하고 편리한 도로환경 구축을 위한 사회 기반 정비가 활발하게 진행되고 있는 지금, 교통시설 상호간의 교차는 피할 수 없는 현실이 되고 있다. 특히, 철로나 도로 밑을 횡단하는 구조물을 건설할 경우, 철도 궤도 나 도로 포장 면에의 영향을 최소화하면서, 횡단 구조물의 크기를 크게 하고, 구조물의 연장거리를 길게 하기 위해서 비개착 추진공법으로 시공하는 경우가 매년 증가하고 있다. Nowadays, the social infrastructure for the safer and more convenient road environment is being actively promoted, and the intersection between transportation facilities is inevitable. In particular, when constructing a structure that crosses railroads or roadways, it is constructed by non-adhesive propulsion to increase the size of the transverse structure and increase the extension distance of the structure while minimizing the influence on railroad tracks or road pavement. The number of cases increases every year.
지금까지, 국내에서 철로나 도로 밑을 횡단하는 구조물을 건설할 경우, 주로 일본에서 개발된 파이프 루프 공법을 보조 공법으로 하며, 프론트 잭킹 추진공법을 주공법으로 하여 박스 추진 구조물을 완성하는 공법이 대부분을 차지하였으나, 파이프 루프 공법과 박스 추진 공법을 이중으로 진행함으로 인해 막대한 공사비가 소요되는 단점이 있으며, 공사기간이 길어지는 단점이 존재했다. Until now, when constructing a structure crossing railroads or roads in Korea, most of the construction methods to complete the box propulsion structure are mainly the pipe loop method developed in Japan as the auxiliary method, and the front jacking method as the main method. However, due to the double process of the pipe loop method and the box propulsion method, there is a disadvantage in that a huge construction cost is required, and the construction period is long.
외국의 예를 들면, 철로나 도로를 횡단하는 구축하는 공법은 크게 5가지로 나눌 수 있다. In foreign countries, for example, construction methods that cross railroads or roads can be divided into five types.
첫 번째, 프론트재킹(Front-jacking) 공법으로 공장이나 현장에서 미리 제조한 콘크리트 박스를 견인식 프론트 잭킹에 의하여 순차적으로 견인 추진하면서 횡단구조물을 구축하는 공법으로서, 주요특징은 선단부에 강철제의 도구(刀口)를 부착한 박스 구조물을 선도지반으로 견인하고, 박스구조물의 크기에 상관없이 추진 가능하며, 모든 토질 조건에 대응 가능하고, 기존 제품의 박스 구조물을 사용함으로 인해 공사기간의 대폭적인 단축이 가능하다. 시공순서는 파이프 루프 추진공사, 박스 구조물에 강철제의 도구(刀口)를 부착, 박스 구조물 조립, 박스구조물의 결속, 박스 구조물 조립 완료, 박스 구조물 추진순서로 완료한다.First, a front-jacking method is a method of constructing a cross-section structure by towing and pushing concrete boxes manufactured in advance in a factory or a field by a towing type front jacking. The main feature is a steel tool at the tip. It can tow the box structure attached with the gut to the leading ground, and can propel it regardless of the size of the box structure, to cope with all soil conditions, and to significantly shorten the construction period by using the box structure of the existing product. Do. The construction sequence is completed by pipe loop propulsion work, attaching steel tools to the box structure, assembling the box structure, binding the box structure, completing the box structure assembly, and pushing the box structure.
두 번째, 유알티(URT(Under Railway Tunnel)) 공법은 현재 사용중의 철도 노선, 도로 하부를 횡단하는 터널 구조물을 직접 구축하는 터널 공법으로 터널 복공 단면을 여러 개의 적당한 크기 단위로 분할하여 각 단위를 터널 축 방향에 굴착하면서 압입 하여 터널 복공을 실시한 후, 흙을 굴착 제거하여 터널을 완성시키는 공법이다. 본 공법은 각 단위를 본체 구조로 하기 때문에 가설공사가 적고 피복 제약이 현저하게 완화된 특징이 있다. Second, ULT (Under Railway Tunnel) method is a tunnel method that directly constructs the tunnel structure crossing the railway line and the road under current use, and divides the tunnel return section into several suitable size units. After digging in the tunnel axial direction and tunnel tunneling, the soil is excavated and removed to complete the tunnel. Since this method uses each unit as a main body structure, there is a feature that there is little construction work and coating restrictions are remarkably relaxed.
세 번째, 에취이피(HEP(High Speed Element Pull)) 공법은 각종 교통 노선 밑의 횡단 구조물 공사를 단기간에 시공하기 위하여 개발된 신 공법으로 종래에 사용되던 엘레멘트(Element)를 전진기지(A)로부터 압입 추진하는 공법 대신에 도달기지(B)에 설치한 견인장치를 이용하여 굴착 장치에 부착된 피시(PC)강 부착선을 인장하는 방법에 의해 굴착 장치에 직결된 엘레멘트(Element)를 전진 기지 측으로 부터 견인하는 공법으로서, 견인 방식에 의한 고정밀 시공, 전진 기지 측의 반력벽 설비가 불필요, 선도 지반의 장애물에 신속하게 대응, 시공 관리의 시스템화하는 장점이 있으며, 도11에 도시된 바와 같이, 에취이피(HEP) 공법에 있어서의 엘레멘트(Element) 견인 방법은 기준 엘레멘트(Element)는 수평 보링 방법에 의해 선두지반에 굴착된 구멍에 피시(PC)강 부착선을 삽입한 후, 이 피시(PC)강 부착선에 굴착 장치와 엘레멘트(Element)를 접속해서 도달 기지 측으로부터 유압잭을 이용하여 견인하며, 다음 연결되는 엘레멘트(Element)들의 견인은 선행 추진된 엘레멘트(Element)의 한쪽 면에 부착되어 추진 완료된 피시(PC)강 부착선을 사용하여 순차적으로 실시하기 때문에 두번째 이후의 엘레멘트(Element)들의 추진에 있어서 수평 보링은 필요가 없게 된다. Third, the HEP (High Speed Element Pull) method is a new method developed for short-term construction of transverse structures under various traffic routes. Instead of the press-propulsion method, the element directly connected to the excavation device is moved to the forward base side by tensioning the PC steel attachment line attached to the excavation device by using a traction device installed at the arrival base B. As a towing method from the ground, high-precision construction by the traction method, no reaction force wall equipment on the forward base side is required, and there is an advantage of quickly responding to obstacles in the leading ground and systemizing the construction management, as shown in FIG. The element pulling method in the HEP method is that the reference element inserts a PC steel attachment line into the hole excavated in the leading ground by the horizontal boring method. Then, the excavation device and the element are connected to the PC steel attachment line and towed by the hydraulic jack from the arrival base side, and the towing of the next connected elements is performed by the elements of the pre-propelled element. Horizontal boring is not necessary for the propulsion of the elements after the second one, since it is carried out sequentially using a PC steel attachment line which is attached to one side and is completed.
네 번째, 제이이에스(JES(Jointed Element Structure Method))공법은 철도나 도로 노선 밑의 교차 횡단 구조물을 단기간에 안전하게 시공하기 위한 새로운 구축법 으로, 엘레멘트(Element)는 축의 직각방향으로 힘의 전달이 가능한 조인트를 갖춘 철강재 엘레멘트(Element)를 사용한다. Fourth, the JES (Jointed Element Structure Method) method is a new construction method for constructing a cross-section structure under a railroad or road line in a short period of time, and an element can transmit force in the direction perpendicular to the axis. Use steel elements with joints.
이 엘레멘트(Element)에 조인트가 상호 교차 융합하는 본체 시스템을 사용함으로써 각종 노선 하부의 구조물을 비개착으로 박스형이나 원형 등으로 연장거리에 제한 없이 구축하는 것이 가능하다. 제이이에스(JES) 공법은 도12에 도시된 바와 같이, 부재에 발생하는 인장력을 엘레멘트(Element) 간의 조인트 연결에 의하여 전달하는 구조를 가지고 있어 충분한 구조 강도를 지니며, 기준 엘레멘트(Element), 일반부 엘레멘트(Element), 모서리부분 엘레멘트(Element), 티(T)자부분 엘레멘트(Element), 조정 엘레멘트(Element)등에 의해 구성되며, 순차적으로 조인트를 연결하면서 엘레멘트(Element)를 소정의 위치에 삽입시켜 조립하여 구조체를 구축한다. 철도 궤도면이나 도로 포장면에 끼치는 영향이 적고, 일체화된 구조물을 용이하게 구축할 수 있으며, 시공성이 뛰어나고 경제적인 장점이 있다. By using a main body system in which joints cross-fuse each other for this element, it is possible to construct structures under various routes without any limitation in extension of box-type or circular shape. JES method has a structure that transmits the tensile force generated in the member by the joint connection between the elements (Element), as shown in Figure 12 has a sufficient structural strength, the reference element (Element), the general part It is composed of elements, corner elements, tee elements, adjustment elements, etc. and inserts elements at predetermined positions while connecting joints sequentially. Assemble to build structure. Less influence on the rail track surface or pavement surface, can easily build an integrated structure, excellent construction and economical advantages.
다섯 번째, 파이프 루프 공법은 터널굴착 전에 강관을 적절한 형상으로 배열ㆍ설치, 터널 굴착시 강관의 빔(Beam)작용을 유발시켜 터널에 가해지는 상재하중, 토압등의 분산작용 및 경감효과를 얻는 것이기 때문에 터널의 전 지보공 위치에서 막장전방의 이완영역을 고려한 가상 지중 지점간의 강관 스판(Span)을 단순보 혹은 연속보 개념으로 해석, 강관 및 터널 구조물의 안전성을 검토 . 분석해 나가는 해석 방법을 설계시에 주로 채택하고 있다. 파이프루프공법은 강시판 혹은 메셀(Messel)공법 등과 같은 원리로 터널 굴착전에 지지재를 설치하여 상부의 토압 및 이완영역의 경감효과를 얻는 공법이므로 다소의 자립성이 있는 지반에서는 각 강관사이의 간격 틈이 존재한다 할지라도 흙의 전단강도 유발로 인해 지지될 수 있으므로 단관 분리 설치방법이 경제성 및 시공성 측면에서 주로 이용된다. 그러나 지하수위가 높고 자립성이 낮아 강관사이의 간격 틈을 통해 토사의 유출이 예상되는 곳이나 토피가 극히 얕아 큰 상재 하중을 직접적으로 받는 곳인 경우는 강관 사이에 연결 조인트를 설치, 각 강관을 연결시켜 완전한 강관구조물을 형성시킴으로써 강관의 처짐량 및 지하수 배출정도에 따른 영향을 터널 및 상부구조물의 안정에 반영해 나가는 방법이 적용되고 있다.Fifth, the pipe loop method arranges and installs steel pipes in proper shape before tunnel excavation, and induces beam action of steel pipes during tunnel excavation, so as to obtain dispersion effect and relief effect of load, earth pressure, etc. applied to tunnel. Therefore, the steel pipe span between virtual underground points considering the relaxation area of the membrane front at the front hole location of the tunnel is analyzed by the concept of simple beam or continuous beam, and the safety of the steel pipe and tunnel structure is examined. The analysis method to analyze is mainly adopted at the time of design. The pipe loop method is a method that obtains the effect of reducing the earth pressure and relaxation area of the upper part by installing a support material before tunnel excavation in the same principle as the steel plate or the Messel method. Even if it is present, it can be supported by causing the shear strength of the soil, so the single pipe separation installation method is mainly used in terms of economy and constructability. However, if the groundwater level is high and the independence is low, and the soil is expected to leak through the gap between the steel pipes, or if the toffee is extremely shallow and directly receives a large load, the connection joints are installed between the steel pipes. By forming a complete steel pipe structure, a method of reflecting the effects of the deflection amount of the steel pipe and the degree of groundwater discharge on the stability of the tunnel and the upper structure has been applied.
파이프루프공법은 굴착 전에 일정규모의 강관을 지중에 삽입, 지반굴착시에 강관의 빔(Beam)작용을 유발시켜 상부 및 주변 지반을 지지해 주는 역할을 하기 때문에 하중 경감효과를 크게 얻을 수 있어 최근 다양한 용도로 이용되고 있다. 파이프루프공법은 상재하중 크기나 지질조건, 인접구조물의 특성 및 규모, 터널의 토피두께 등에 따라 강관을 적절한 형상으로 배열시켜 주변환경적, 지질적 요소에 강력히 대처해 나가는 것이므로 장비의 출반입 및 발진 개구경의 설치가 가능한 곳에서는 어느 장소에서나 시공 할 수 있는 것으로 간주되어 왔으나, 최근 퍼쿠션형(Percussion Type)의 수평천공장비가 개발 . 보급됨에 따라서 지질적인 요소는 시공상 문제화되지 안고 있다. 파이프루프공법은 일반적으로 도로 . 철도 횡단시의 보조수단: 도로 . 철도의 방호, 굴착터널 자체안정과, 단면 터널 시공시의 보조 수단: 지하 확대 단면부의 방호, 지하역, 복합 대단면 시공시의 터널 방호의 용도로 사용되고 있다. The pipe loop method inserts a certain size of steel pipe into the ground before excavation and causes the beam of the steel pipe to act on the ground to support the upper and surrounding ground, thus greatly reducing the load. It is used for various purposes. Pipe loop method is to arrange steel pipes in proper shape according to the size of load, geological condition, characteristics and size of adjacent structures, toffee thickness of tunnel, and to cope with environmental and geological elements. It has been considered that it can be installed in any place where the aperture can be installed, but recently, Percussion Type horizontal drilling equipment has been developed. As it spreads, geological elements are not a problem in construction. Pipe loops are generally on the road. Auxiliary means for rail crossings: roads. It is used for railroad protection, excavation tunnel self-stabilization, and auxiliary means for the construction of single-sided tunnels: protection of underground enlarged cross-sections, underground stations, and tunnel protection in the construction of large cross-sections.
파이프루프공법은 굴착 전에 일정규모의 강관을 지중에 삽입, 지반굴착시에 강관의 Beam작용을 유발시켜 상부 및 주변 지반을 지지해 주는 역할을 하기 때문에 하중 경감효과를 크게 얻을 수 있어 최근 다양한 용도로 이용되고 있다. 파이프루프공법은 상재하중 크기나 지질조건, 인접구조물의 특성 및 규모, 터널의 토피두께 등에 따라 강관을 적절한 형상으로 배열시켜 주변환경적, 지질적 요소에 강력히 대처해 나가는 것이므로 장비의 출반입 및 발진 개구경의 설치가 가능한 곳에서는 어느 장소에서나 시공 할 수 있는 것으로 간주되어 왔으나, 최근Percussion Type의 수평천공장비가 개발 . 보급됨에 따라서 지질적인 요소는 시공상 문제화되지 안고 있다. 파이프루프공법은 일반적으로 도로 . 철도 횡단시의 보조수단: 도로 . 철도의 방호, 굴착터널 자체안정과, 단면 터널 시공시의 보조 수단: 지하 확대 단면부의 방호, 지하역, 복합 대단면 시공시의 터널 방호의 용도로 사용되고 있다. The pipe loop method inserts a certain size of steel pipe into the ground before excavation, and it acts to support the upper and surrounding ground by inducing the beam action of the steel pipe during the ground excavation. It is used. Pipe loop method is to arrange steel pipes in proper shape according to the size of load, geological condition, characteristics and size of adjacent structures, toffee thickness of tunnel, and to cope with environmental and geological elements. It has been considered that it can be installed at any place where the aperture can be installed, but recently, Percussion type horizontal drilling equipment was developed. As it spreads, geological elements are not a problem in construction. Pipe loops are generally on the road. Auxiliary means for rail crossings: roads. It is used for railroad protection, excavation tunnel self-stabilization, and auxiliary means for the construction of single-sided tunnels: protection of underground enlarged cross-sections, underground stations, and tunnel protection in the construction of large cross-sections.
추진공법의 도입 역사가 짧은 국내의 경우, 아직도 추진공법에 대한 인식수준이 매우 낮으며, 기존의 터널공법과 같은 지반공학 분야에서도 추진공법이 하나의 완성된 공법으로 인정받지 못하고 있는 상황이다. 그러나 현재, 추진공법의 선두 주자인 일본의 경우는 대구경 터널공법과 다른 하나의 독립된 분야로서 추진공법을 설정하고 있으며, 새로운 추진기술의 개발에 많은 정성과 노력을 기울이고 있다. 일본과는 다른 여러 가지 국내 사정상, 한국실정에 맞는 독자적인 추진공법이 개발되어야 한다.In Korea, where the introduction of the propulsion method is short, the recognition level of the propulsion method is still very low, and the propulsion method is not recognized as a completed method in the geotechnical field such as the existing tunnel method. At present, however, Japan, the leader of the propulsion method, is setting up the propulsion method as a separate field from the large-diameter tunnel method, and is making great efforts to develop new propulsion technologies. Due to various domestic circumstances different from Japan, an independent propulsion method should be developed for the Korean situation.
상기와 같은 문제점을 해결하기 위하여 본 발명은 파이프 루프를 아치형(Arched-type) 또는 열린 박스형(門形)으로 추진 배열하여 1차 보강 목적을 달성한 후, 토사 굴착과 동시에 아치형 또는 박스형의 조립식 콘크리트 세그먼트를 이용하여 추진, 설치하는 공법을 국내 실정에 맞게 개발하여 공사비용의 절감 및 공사 기간의 단축하는 조립식 구조물을 이용한 비개착 지하통로 구축공법을 제공하는 것이 본 발명이 이루고자 하는 기술적 과제인 것이다. In order to solve the above problems, the present invention achieves the primary reinforcement object by arranging the pipe loops in an arced (Arched-type) or an open box type (,)), and at the same time as the earth and sand excavated arch or box-shaped prefabricated concrete It is a technical task of the present invention to provide a method for constructing an underground passageway using a prefabricated structure that reduces construction costs and shortens the construction period by developing a construction method to promote and install using segments.
상기와 같은 목적을 해결하기 위하여, 본 발명은 조립식 구조물을 이용한 비개착 지하통로의 구축공법을 공정 순서대로 설명하면, In order to solve the above object, the present invention describes the construction method of the non-adhesive underground passage using the prefabricated structure in the order of the process,
그 다음에 조립식 구조물의 추진 작업 중 강관 파이프가 움직이지 않도록, 강관 파이프(루프공)의 양 선단면을 에취빔(H-Beam)(10)으로 고정 및 부착하여 연결 구조를 만들고, 에취빔(H-Beam)(10)의 여러 부분에 티로드(Tie-Rod)(11)를 연결한 후, 지면에 수직방향의 앵커(Anchor)(12)를 설치하여 고정한다. Then, both ends of the steel pipes (loop holes) are fixed and attached to the H-Beam 10 so that the steel pipes do not move during the propulsion of the prefabricated structure, and a connection structure is formed. After connecting the tie rod (Tie-Rod) (11) to the various parts of the H-Beam (10), it is fixed by installing an anchor (12) in the vertical direction on the ground.
그리고 수직 세로 방향의 에취빔(H-Beam)(10)은 기초 부분을 지중에 삽입하여 고정한 후, 상기와 같은 방법으로 티로드(Tie-Rod)(11)를 연결한 후 지면에 앵커(12)를 설치하여 고정한다.In addition, the H-Beam 10 in the vertical and vertical direction is fixed by inserting the foundation portion into the ground, and then connecting the tie rods 11 in the same manner as described above. ) To fix it.
그 다음에 조립식 구조물의 추진 작업 중 강관 파이프가 움직이지 않도록, 강관 파이프(루프공)의 양 선단면을 에취빔(H-Beam)(10)으로 고정 및 부착하여 연결 구조를 만들고, H-Beam(10)의 여러 부분에 티로드(Tie-Rod)(11)를 연결한 후, 지면에 수직방향의 앵커(Anchor)(12)를 설치하여 고정한다. Then, in order to prevent the steel pipes from moving during the propulsion of the prefabricated structure, both end faces of the steel pipes (loop holes) are fixed and attached with H-Beam 10 to form a connection structure, and H-Beam After connecting the tie rod (Tie-Rod) (11) to the various parts of the (10), the anchor (12) in the vertical direction to the ground (installation) is fixed.
그리고 수직 세로 방향의 H-Beam(10)은 기초 부분을 지중에 삽입하여 고정한 후, 상기와 같은 방법으로 Tie-Rod(11)를 연결한 후 지면에 앵커(12)를 설치하여 고정한다.And the H-Beam (10) in the vertical and vertical direction is fixed by inserting the base portion in the ground, and after connecting the tie-Rod (11) in the same manner as above to install the anchor 12 on the ground.
두 번째 공정 (도5참조)은 전진기지(A)내에 유압잭 추진용 반력벽을 설치한 후, 유압잭 및 레일, 사각 밀대 등을 설치한다. 그 다음 공정에서 현장 공정 및 여건에 맞게 생산된 조립식 구조물 (아치형 또는 박스형 철근 콘크리트 구조물)(100,100')을 강관 파이프(루프공)의 하부면에 부착한 레일 연결 접합부에 맞춰, 조립식 구조물의 외부면에 접합부 연결용 레일을 부착한다. (도7,8 참조)The second process (see Fig. 5) is to install the hydraulic jack propulsion reaction wall in the forward base (A), and then install the hydraulic jack and rail, square bar and the like. In the next process, the prefabricated structure (arc or box reinforced concrete structure) 100,100 'produced according to the field process and the conditions in accordance with the rail connection joint attached to the lower surface of the steel pipe (loop hole), the outer surface of the prefabricated structure Attach the rail for connection to the joint. (See Figures 7,8)
또한 지반조건에 따라 필요시 조립식 구조물 박스 하부에 자갈을 부설하기 전에 에취빔(H-Beam) 등의 강재를 사용하거나, 조강시멘트 등을 사용하여 기초콘크리트를 타설하고 자갈을 부설하여 기초부를 보강하고 조립식 구조물 박스 추진용 레일을 설치하고 추진하여 작업을 시행한다. In addition, depending on the ground conditions, before laying gravel in the prefabricated structure box, use steel materials such as H-Beam or reinforce the foundation by laying foundation concrete and laying gravel using crude steel cement. The work is performed by installing and pushing the prefabricated box propulsion rails.
그리고 조립식 구조물(100,100')이 추진되기 전에 추진 선단부의 지반을 지반 조건에 따라 0.5m 1.5m 정도 선굴착 한 후, 지면 하부에 자갈 등을 부설하고 기초콘크리트(조강시멘트 사용)를 타설하여 기초를 튼튼하게 한 후, 레일을 설치하고 유압펌프 유니트와 유압잭 등을 사용하여 조립식 구조물을 원활하게 추진 시공하여 설치한다.And before the prefabricated structure (100,100 ') is propelled, the ground of the propulsion tip is excavated about 0.5m 1.5m according to the ground condition, and then the gravel is laid at the bottom of the ground and the foundation concrete (using the steel cement) is laid. After strengthening, install the rail and use the hydraulic pump unit and hydraulic jack to smoothly push and install the prefabricated structure.
또한 지반조건에 따라 필요시 조립식 구조물 박스 하부에 자갈을 부설하기 전에 H-Beam 등의 강재를 사용하거나, 조강시멘트 등을 사용하여 기초콘크리트를 타설하고 자갈을 부설하여 기초부를 보강하고 조립식 구조물 박스 추진용 레일을 설치하고 추진하여 작업을 시행한다. In addition, if necessary, depending on the ground conditions, before laying gravel in the prefabricated structure box, use steel materials such as H-Beam, or use crude steel cement, etc. to install the foundation concrete, and install the gravel to reinforce the foundation and promote the prefabricated structure box. Work is carried out by installing and pushing the rails.
그 다음 강관 파이프 양 선단에 위치한 에취빔(H-Beam) 의 철거 및 티로드(Tie-Rod) 을 철거한 후, 지하통로 양 단면의 미장 작업 및 밑마무리 작업을 실시한다.After that, the demolition and tie-rod of H-Beam located at both ends of the steel pipe are removed, and then plastering and finishing work on both sides of the underground passage is performed.
세 번째 공정 (도6 참조)은 조립식 구조물의 추진 작업이 완료된 후, 전진기지(A)내의 각종 추진장비 철수 및 반력벽 철거 작업을 한 후, 조립식 구조물과 강관 파이프루프공의 하부면 사이의 틈새에 모르터 등의 충진재를 사용하여 충진작업을 실시하여, 본 구조체의 구조적인 강도를 증가시킨다.In the third process (see FIG. 6), after the completion of the propulsion work of the prefabricated structure, after the withdrawal of various propulsion equipment and the removal of the reaction wall in the forward base A, the gap between the prefabricated structure and the lower surface of the steel pipe pipe-roof hole The filling operation is carried out using a filler such as mortar to increase the structural strength of the structure.
그 다음 강관 파이프 양 선단에 위치한 H-Beam 의 철거 및 Tie-Rod 을 철거한 후, 지하통로 양 단면의 미장 작업 및 밑마무리 작업을 실시한다.Then, after demolition and tie-rod of H-Beam located on both ends of the steel pipe, the plastering and finishing work on both sides of the underground passage is carried out.
그리고 철로 및 도로 상부면에서 하부면을 향한 배수 처리가 필요할 때는 강관 파이프 부분의 상단에 수평 보링 작업을 한 후, 유공관을 설치하여 배수가 원활하게 되도록 한다.And when the drainage treatment from the upper surface of the railway and the road to the lower surface is required to perform horizontal boring work on the top of the steel pipe pipe portion, install a perforated pipe so that the drainage is smooth.
이하 본 발명을 실시예를 참고하여 상세히 설명하면 다음과 같다.Hereinafter, the present invention will be described in detail with reference to Examples.
실시예Example
시공된 강관 파이프(3)의 양 선단면을 에취빔(H-Beam)(10)으로 고정 부착(용접)하여 연결구조를 만들고, 에취빔(H-Beam)(10)의 여러 부분에 티로드(Tie-Rod)(11)를 연결한 후, 지면에 수직방향의 앵커(Anchor)(12)를 설치하여 고정하며, Both ends of the constructed steel pipe 3 are fixedly attached (welded) to the H-Beam 10 to form a connection structure, and the T-rods are formed on various parts of the H-Beam 10. After connecting (Tie-Rod) (11), by fixing the anchor (12) in the vertical direction on the ground,
일정간격으로 시공된 수직 세로 방향의 강관파이프(3)의 전면을 에취빔(H-Beam)(10)을 이용하여 고정 부착(용접)하되 에취빔(H-Beam)(10)의 하부인 기초 부분을 지중에 삽입하여 고정한 후, 상기와 같은 방법으로 티로드(Tie-Rod)(11)를 연결한 후 지면에 앵커(12)를 설치하여 고정하여 준비한 다음, The front surface of the vertical and longitudinal steel pipes 3 constructed at regular intervals is fixedly attached (welded) using an H-Beam 10, but is a lower part of the H-Beam 10. After inserting the part into the ground and fixing it, the tie rod (Tie-Rod) 11 is connected in the same manner as above, and then the anchor 12 is installed on the ground to fix and prepare.
시공된 강관 파이프(3)의 양 선단면을 H-Beam(10)으로 고정 부착(용접)하여 연결구조를 만들고, H-Beam(10)의 여러 부분에 Tie-Rod(11)를 연결한 후, 지면에 수직방향의 앵커(Anchor)(12)를 설치하여 고정하며, After connecting both end faces of the constructed steel pipe (3) with H-Beam (10), make a connection structure, and connect Tie-Rod (11) to various parts of H-Beam (10). , Fixed by installing the anchor (12) in the vertical direction on the ground,
일정간격으로 시공된 수직 세로 방향의 강관파이프(3)의 전면을 H-Beam(10)을 이용하여 고정 부착(용접)하되 H-Beam(10)의 하부인 기초 부분을 지중에 삽입하여 고정한 후, 상기와 같은 방법으로 Tie-Rod(11)를 연결한 후 지면에 앵커(12)를 설치하여 고정하여 준비한 다음, After fixing (welding) the front surface of the vertical and vertical steel pipe (3) constructed at regular intervals using H-Beam (10), insert the base part, which is the lower part of H-Beam (10), in the ground and fix it. After the tie-rod 11 is connected in the same manner as above, the anchor 12 is installed on the ground to be fixed and prepared.
제2공정(추진공정)Second Process (Promotion Process)
전진기지(A)내에 유압잭 추진용 반력벽(25)을 설치한 후, 유압기(20)와 유압호스(21)에 의해 연결된 유압잭(22)과, 상기 유압잭(22)의 하부에 구비된 하부레일(31)과, 상기 유압잭(22)의 실린더(23)의 전면에 사각 밀대(24)를 설치 한 다음, After installing the hydraulic jack propulsion reaction wall 25 in the forward base A, the hydraulic jack 22 connected by the hydraulic press 20 and the hydraulic hose 21 and the lower rail provided under the hydraulic jack 22 are provided. 31 and the square bar 24 is installed on the front surface of the cylinder 23 of the hydraulic jack 22,
전진기지(A)의 하부레일(31) 위에 상부 및 측면에 레일부착접합부(101)가 구비된 조립식 구조물 (100,100')을 위치시킨 후에, 최초 조립식 구조물(100,100')의 선단부에 굴착 보호용 선단슈 (Shoe)(200)를 부착하고, After placing the prefabricated structures 100 and 100 'having the rail attachment joints 101 on the upper and side surfaces thereof on the lower rail 31 of the forward base A, the front end shoe for the excavation protection at the tip of the prefabricated structure 100 and 100'. (Shoe) (200) attached,
(이때, 상기 조립식구조물(100,100')의 레일부착접합부(101)를 강관 파이프(3)의 하부면에 부착한 연결접합부레일(4)에 일치시킨 후에,) (도7,8 참조) (At this time, after the rail attachment joints 101 of the prefabricated structures 100 and 100 'are matched to the joint joint rails 4 attached to the lower surface of the steel pipe 3, see Figs. 7 and 8)
조립식 구조물의 추진 작업이 완료된 다음, 전진기지(A)내의 각종 추진장비 철수 및 반력벽 철거 작업을 한 후, 조립식 구조물과 강관 파이프(3)의 하부면 사이의 틈새에 모르터 등의 충진재를 사용하여 충진작업을 실시하여, 조립식구조물(100,100')의 구조적인 강도를 증가시키고, 강관 파이프(2) 양 선단에 위치한 에취빔(H-Beam)(10) 의 철거 및 티로드(Tie-Rod)(11)를 철거한 후, 지하통로 양 단면의 미장 작업 및 밑마무리 작업을 실시하고, 철로 및 도로 상부면에서 하부면을 향한 배수 처리를 위하여 강관 파이프(3)의 상단에 수평 보링 작업을 한 후, 필요시 배수가 원활하게 유공관을 설치하여 조립식구조물 비개착 지하통로를 시공하였다.After the propulsion of the prefabricated structure is completed, the withdrawal of various propulsion equipment and the reaction wall dismantling work in the forward base (A) is carried out, and then the filling material such as mortar is used in the gap between the prefabricated structure and the lower surface of the steel pipe pipe (3). Filling operation is performed to increase the structural strength of the prefabricated structures (100, 100 ') and to remove and tie-rod (H-Beam) 10 located at both ends of the steel pipe (2). After dismantling 11), perform plastering and finishing work on both sides of the underground passage, and horizontal boring work on the upper part of the steel pipe 3 for drainage treatment from the rail and the upper surface of the road to the lower surface. In addition, if necessary, drainage was installed smoothly, and the underground passages were constructed without prefabricated structures.
제3공정(보강 및 마무리공정)3rd process (reinforcement and finishing process)
도1 및 도2 본 발명의 조립식구조물을 이용한 비개착 지하통로 정면 상세도, 도3 본 발명의 조립식구조물을 이용한 비개착 지하통로 측단면 상세도, 도4 본 발명의 제1공정 상세도, 도5 본 발명의 제2공정 상세도, 도6 본 발명의 제3공정 상세도, 도7 및 도8 본 발명의 조립식 구조물 상세도를 도시한 것이며, 도로 및 철로(1), 지반(2), 강관파이프(3), 연결접합부레일(4), 강관파이프루프연결(5), 에취빔(10), 티-로드(11), 앵커(12), 유압기(20), 유압호스(21), 유압잭(22), 실린더(23), 사각밀대(24), 반발벽(25), 하부레일(31), 자갈기초 및 조강콘크리트바닥(32), 조립식구조물(100,100'), 레일부착접합부(101), 구조물연결부(110), 선단슈(200), 전진기지(A), 도달기지(B)를 나타낸 것임을 알 수 있다.1 and 2 detailed front view of an unattached underground passage using the prefabricated structure of the present invention, FIG. 3 a detailed cross-sectional side view of an unattached underground passage using the prefabricated structure of the present invention, FIG. 5 is a detailed view of the second process of the present invention, FIG. 6 is a detailed view of the third process of the present invention, and FIGS. 7 and 8 are detailed views of the prefabricated structure of the present invention, and the road and the railway line (1), the ground (2), Steel pipe pipe (3), connection joint rail (4), steel pipe pipe connection (5), ech beam (10), tee-rod (11), anchor (12), oil press (20), hydraulic hose (21), Hydraulic jack (22), cylinder (23), square rod (24), repellent wall (25), lower rail (31), gravel foundation and rough concrete floor (32), prefabricated structure (100, 100 '), rail attachment joint (101) ), The structure connection portion 110, the tip shoe 200, the forward base (A), it can be seen that the base shown (B).
이하 본 발명의 조립식 구조물을 이용한 지하통로 구축장치를 도면을 참고하여 상세히 설명하면 다음과 같다.Hereinafter, an underground passage building apparatus using the prefabricated structure of the present invention will be described in detail with reference to the accompanying drawings.
도1 및 도2 본 발명의 조립식구조물을 이용한 비개착 지하통로 정면 상세도, 도3 본 발명의 조립식구조물을 이용한 비개착 지하통로 측단면 상세도, 도4 본 발명의 제1공정 상세도, 도5 본 발명의 제2공정 상세도, 도6 본 발명의 제3공정 상세도, 도7 및 도8 본 발명의 조립식 구조물 상세도, 도9 내지 도13 종래의 조립식 구조물을 이용한 지하통로 구축 공법 예를 도시한 것이며, 도로 및 철로(1), 지반(2), 강관파이프(3), 연결접합부레일(4), 강관파이프루프연결(5), 에취빔(10), 티-로드(11), 앵커(12), 유압기(20), 유압호스(21), 유압잭(22), 실린더(23), 사각밀대(24), 반발벽(25), 하부레일(31), 자갈기초 및 조강콘크리트바닥(32), 조립식구조물(100,100'), 레일부착접합부(101), 구조물연결부(110), 선단슈(200), 전진기지(A), 도달기지(B)를 나타낸 것임을 알 수 있다.1 and 2 detailed front view of an unattached underground passage using the prefabricated structure of the present invention, FIG. 3 a detailed cross-sectional side view of an unattached underground passage using the prefabricated structure of the present invention, FIG. 5 is a detailed view of the second process of the present invention, FIG. 6 is a detailed view of the third process of the present invention, FIGS. 7 and 8 are detailed views of the prefabricated structure of the present invention, and FIGS. 9 to 13. The road and track (1), the ground (2), steel pipe pipe (3), connection joint rail (4), steel pipe pipe connection (5), ech beam 10, tee-rod (11) , Anchor 12, hydraulic 20, hydraulic hose 21, hydraulic jack 22, cylinder 23, square bar 24, rebound wall 25, lower rail 31, gravel foundation and steel concrete It can be seen that the bottom 32, the prefabricated structure (100, 100 '), the rail attachment joint 101, the structural connection portion 110, the tip shoe 200, the forward base (A), the reach base (B).
구조를 살펴보면, 철로나 도로(1)의 하부에 구축하고자 하는 지하통로의 크기와 위치를 설정 (도4참조) 한 후, 철로나 도로면의 양 측면에 공사를 위해 가시설을 이용하여, 설치된 전진기지(A)에 조립식구조물(100,100')을 추진하기 위한 유압기(20)와 유압호스(21)에 의해 연결된 유압잭(22)과, 상기 유압잭(22)의 하부에 구비된 하부레일(31)과, 상기 유압잭(22)의 실린더(23)의 전면에 설치된 사각 밀대(24)와, 상기 유압잭(22)의 후면에 설치된 반력벽(25)으로 구성된 조립식 구조물을 이용한 지하통로 구축장치의 구조인 것이다.Looking at the structure, after setting the size and location of the underground passage to be built on the track or the lower part of the road (see Fig. 4), using the provisional facilities for construction on both sides of the rail or road surface, A hydraulic jack 22 connected by a hydraulic unit 20 and a hydraulic hose 21 for propelling the assembled structures 100 and 100 'to the base A, and a lower rail 31 provided below the hydraulic jack 22; And, it is a structure of the underground passage building device using a prefabricated structure consisting of a square push rod 24 installed on the front of the cylinder 23 of the hydraulic jack 22, and the reaction force wall 25 provided on the rear of the hydraulic jack 22. .
본 발명의 장치는 조립식구조물(100,100')를 전진시키기 위한 장치이다. 삭제된부분The device of the present invention is a device for advancing a prefabricated structure (100, 100 '). Deleted part
본 발명에서 사용되는 조립식 구조물(100,100')은 아치형 또는 문형(門形)으로 제작할 수 있으며, 조립식 구조물(100,100')과 접면하는 하부를 제외한 상부 및 측면에 레일부착접합부(101)가 구비되어 있고,Prefabricated structures (100, 100 ') used in the present invention can be manufactured in an arched or door-shaped, and the rail attachment joints 101 are provided on the upper and side surfaces except for the lower side in contact with the prefabricated structures (100,100') and ,
선단에는 선단슈(200)가 부착되어 있고, 연결되는 조립식구조물(100,100')위치에는 구조물 연결부(110)가 설치되어 있다. The tip shoe 200 is attached to the tip, and the structure connecting portion 110 is installed at the prefabricated structure (100, 100 ') position to be connected.
또한 본 발명의 강관파이프(3)는 하부 일측에 연결접합부레일(4)이 설치된 구조인 것이다. In addition, the steel pipe 3 of the present invention is a structure in which the connection joint rail 4 is installed on one side of the lower portion.
상기와 같은 본 발명은 첫 번째 기존의 여러 공법들에 비해 대폭적인 공사기간의 단축 효과를 들 수 있다. 이는 기존의 공법들이 파이프루프공을 이용하여 상부지반 선 보강작업을 실시한 후, 정밀 추진작업을 위하여 프론트잭킹과 원압추진 유압기를 동시에 사용하여 공사 기간의 장기화를 요구하거나, 선 굴착 후, 2차 보강, 3차 보강 작업을 실시 후, 통로 본체를 구성하거나 하여 공사 기간이 오래 소요되는 단점이 있으나, 본 공법은 강관 파이프루프공을 실시 한 후, 곧바로 공장에서 현장 여건에 맞춰 주문 생산된 조립식 구조물 통로 본체를 유압잭으로 추진한 후, 한번에 모르터 등으로 2차 충전을 실시하기 때문에 공사 기간을 대폭적으로 단축할 수 있다. The present invention as described above may have a significant reduction in the construction period compared to the first several existing construction methods. This requires existing methods to reinforce the upper ground line by using pipe loops, and to prolong the construction period by simultaneously using the front jacking and the pneumatic propulsion oil press for precision propulsion, or after the line excavation, the secondary reinforcement. However, there is a disadvantage that it takes a long time to construct the aisle body after carrying out the 3rd reinforcement work, but this method is a prefabricated structure aisle which is made to order in the factory immediately after the steel pipe pipe roofing work. After propelling the main body with a hydraulic jack, secondary charging is performed at one time with a mortar or the like, which can greatly shorten the construction period.
두 번째, 기존의 여러 공법들에 비해 대폭적인 공사비의 절감 효과를 들 수 있다. 본 공법에 소요되는 장비들은 기존 공법에 비해 장비 조합 소요가 적고, 추진장비가 비교적 간단하기 때문에 대폭적인 비용 절감 효과가 실현될 수 있고, 재료비 및 인건비 또한 대폭적인 절감이 가능해져 저렴한 비용으로 공사를 수행할 수 있게 된다.Second, there is a significant reduction in construction costs compared to many existing construction methods. The equipment required for this process requires less equipment combinations and the propulsion equipment is relatively simple compared to the existing method, so that significant cost savings can be realized, and material and labor costs can be significantly reduced. It can be done.
세 번째, 본 공법은 기존 철로나 도로 하부의 지하통로 뿐 아니라 지하수로, 야생동물 이동통로 등 여러 가지 통로에 응용할 수 있어 현장에서의 적용 범위가 매우 넓다. Third, this method can be applied to various passages such as groundwater passages and wildlife movement passages as well as the existing passages or underground passages below the roads, so the scope of application in the field is very wide.
네 번째는 현재 국내에서 많이 사용되는 프론트잭킹공법을 이용한 박스통로 추진공사의 경우, 추진되는 박스통로의 상부면과 선 보강작업으로 기 시공된 파이프루프공의 하부면 사이를 추진작업 중에 박스 상부의 경계면에서 인력으로 모래를 삽입 부설하여 충진하고 있으나, 대부분 불균형 충진이 이루어지기 때문에 공사 완료 후 지반 침하 등의 현상을 야기할 소지가 존재하지만, 본 공법은 박스 통로의 상부면과 선 보강용도로 시공된 파이프루프공의 하부면 사이에 모르터 등의 재료 충진용 파이프를 설치하며, 전진기지(A) 측과 도달기지(B) 측에 에어벤트 파이프를 설치하여 조립식 구조물 박스를 추진 시공 완료한 후, 모르터 등의 충진 재료를 전용 그라우트 펌프 등을 사용하여 완전 충진시키기 때문에 공사 완료 후, 지반 침하 발생 우려가 없게 된다. Fourth, in the case of box passage propulsion work using the front jacking method, which is widely used in Korea, the upper part of the box passage is pushed between the upper surface of the box passage being propelled and the lower surface of the pipe loop hole constructed by line reinforcement. Although sand is filled by inserting and laying sand at the interface, most of it is unbalanced, so there is a possibility of causing ground subsidence after the completion of the construction. After the pipes for filling material such as mortar are installed between the lower surfaces of the pipe loop holes, air vent pipes are installed on the forward base (A) side and the reaching base (B) side to complete the prefabricated structure box. Filling materials, such as mortar, are completely filled with dedicated grout pumps, etc., so that there is no risk of ground subsidence after completion of construction. do.
또한 본 공법은 선보강용으로 시공되는 강관 파이프루프공 하부 및 양 측부와 조립식 구조물박스 상부 및 양 측부에 접합부 연결용 레일을 설치하여 상호간에 맞물리는 상태에서 시공되기 때문에 시공 중에라도 상부 지반 침하 발생이 초래되지 않게 된다.In addition, this method is installed in the state of interlocking with each other by installing joint connection rails at the lower side and both sides of the steel pipe pipe loop hole and the prefabricated structure box and both sides, which are constructed for the introduction steel. It is not caused.
다섯번째, 지반 상부면에서의 지하통로를 향한 지하수 등의 유출 문제가 발생하는 것을 예방하기 위하여 지반 조건에 따라 파이프루프공 경계면 상부에 수평보링 작업을 실시한 후, 배수용 유공관을 설치하여 배수작업이 원활하게 진행되도록 할 수 있기 때문에 지하수 등의 유출 문제로 인한 우려를 없애는 것이 가능하게 된다.Fifth, in order to prevent the occurrence of leakage of groundwater, etc. from the upper surface of the ground to the underground passage, horizontal boring work is performed on the upper part of the pipe loop hole interface according to the ground conditions, and drainage work is installed by installing drainage pipes. Because it can proceed smoothly, it is possible to eliminate the concerns caused by the leakage problem such as groundwater.
도1 및 도2 본 발명의 조립식구조물을 이용한 비개착 지하통로 정면1 and 2 the front of the non-adhesive underground passage using the prefabricated structure of the present invention
상세도 Detail
도3 본 발명의 조립식구조물을 이용한 비개착 지하통로 측단면 상세도Figure 3 is a side cross-sectional view of the non-adhesive underground passage using the prefabricated structure of the present invention
도4 본 발명의 제1공정 상세도4 is a detailed view of the first process of the present invention.
도5 본 발명의 제2공정 상세도5 is a detailed view of a second process of the present invention.
도6 본 발명의 제3공정 상세도6 is a detailed view of the third process of the present invention
도7 및 도8 본 발명의 조립식 구조물 상세도7 and 8 detail of the prefabricated structure of the present invention
도면의 부호 설명 Explanation of symbols in the drawings
삭제delete
도로 및 철로(1), 지반(2), 강관파이프(3), 연결접합부레일(4), 강관파이프루프연결(5), H-Beam(10), 티-로드(11), 앵커(12), 유압기(20), 유압호스(21), 유압잭(22), 실린더(23), 사각밀대(24), 반발벽(25), 하부레일(31), 자갈기초 및 조강 콘크리트 바닥 (32), 조립식구조물(100,100'), 레일부착접합부(101), 구조물연결부(110), 선단슈(200), 전진기지(A), 도달기지(B). Road and track (1), ground (2), steel pipe pipe (3), connection joint rail (4), steel pipe pipe connection (5), H-Beam (10), tee-rod (11), anchor (12) ), Hydraulic press 20, hydraulic hose 21, hydraulic jack 22, cylinder 23, square rod 24, rebound wall 25, lower rail 31, gravel foundation and crude concrete floor (32) , Prefabricated structure (100, 100 '), rail attachment junction 101, structure connection unit 110, tip shoe 200, forward base (A), reach base (B).
Claims (3)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020050039011A KR100538272B1 (en) | 2005-05-10 | 2005-05-10 | The methods of trenchless underway construction using pre-cast assembly concrete box |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020050039011A KR100538272B1 (en) | 2005-05-10 | 2005-05-10 | The methods of trenchless underway construction using pre-cast assembly concrete box |
Publications (1)
Publication Number | Publication Date |
---|---|
KR100538272B1 true KR100538272B1 (en) | 2005-12-21 |
Family
ID=37306847
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR1020050039011A KR100538272B1 (en) | 2005-05-10 | 2005-05-10 | The methods of trenchless underway construction using pre-cast assembly concrete box |
Country Status (1)
Country | Link |
---|---|
KR (1) | KR100538272B1 (en) |
Cited By (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100712593B1 (en) | 2005-06-30 | 2007-04-30 | 한미기초개발주식회사 | Construction method of pipe roof structures |
KR100773118B1 (en) | 2006-10-25 | 2007-11-02 | 석정건설(주) | A method of equipment for passage that use underdrain and stell pipe propulsion |
KR100801776B1 (en) * | 2006-05-01 | 2008-02-11 | 주식회사 도화종합기술공사 | The infrastructure which is established in underground and construction method therefor |
CN102535473A (en) * | 2010-12-09 | 2012-07-04 | 上海市基础工程有限公司 | Connection method of pipe curtain and underground structure |
KR101387954B1 (en) * | 2013-04-16 | 2014-04-22 | 주식회사 엔티에스건설 | Mehod for constructing underground wall in extension of undergound parking lot |
KR101771491B1 (en) * | 2016-01-29 | 2017-08-25 | 현진이앤씨 주식회사 | steel pipe pressing method |
CN109778905A (en) * | 2019-01-04 | 2019-05-21 | 中铁第四勘察设计院集团有限公司 | Prefabricated assembling type reinforced concrete back block jacking box culvert construct method |
KR20200024679A (en) | 2018-08-28 | 2020-03-09 | 주식회사 특수건설 | Apparatus and method for constructing non-open cut structure |
CN112922031A (en) * | 2021-03-25 | 2021-06-08 | 福州大学 | Protective structure and construction method for underground chamber under existing building |
CN114575380A (en) * | 2022-03-02 | 2022-06-03 | 厦门市市政工程设计院有限公司 | Existing underground passage widening process |
-
2005
- 2005-05-10 KR KR1020050039011A patent/KR100538272B1/en not_active IP Right Cessation
Cited By (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100712593B1 (en) | 2005-06-30 | 2007-04-30 | 한미기초개발주식회사 | Construction method of pipe roof structures |
KR100801776B1 (en) * | 2006-05-01 | 2008-02-11 | 주식회사 도화종합기술공사 | The infrastructure which is established in underground and construction method therefor |
KR100773118B1 (en) | 2006-10-25 | 2007-11-02 | 석정건설(주) | A method of equipment for passage that use underdrain and stell pipe propulsion |
CN102535473A (en) * | 2010-12-09 | 2012-07-04 | 上海市基础工程有限公司 | Connection method of pipe curtain and underground structure |
CN102535473B (en) * | 2010-12-09 | 2014-09-03 | 上海市基础工程集团有限公司 | Connection method of pipe curtain and underground structure |
KR101387954B1 (en) * | 2013-04-16 | 2014-04-22 | 주식회사 엔티에스건설 | Mehod for constructing underground wall in extension of undergound parking lot |
KR101771491B1 (en) * | 2016-01-29 | 2017-08-25 | 현진이앤씨 주식회사 | steel pipe pressing method |
KR20200024679A (en) | 2018-08-28 | 2020-03-09 | 주식회사 특수건설 | Apparatus and method for constructing non-open cut structure |
KR102134603B1 (en) * | 2018-08-28 | 2020-07-17 | 주식회사 특수건설 | Apparatus and method for constructing non-open cut structure |
CN109778905A (en) * | 2019-01-04 | 2019-05-21 | 中铁第四勘察设计院集团有限公司 | Prefabricated assembling type reinforced concrete back block jacking box culvert construct method |
CN112922031A (en) * | 2021-03-25 | 2021-06-08 | 福州大学 | Protective structure and construction method for underground chamber under existing building |
CN114575380A (en) * | 2022-03-02 | 2022-06-03 | 厦门市市政工程设计院有限公司 | Existing underground passage widening process |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US9322137B2 (en) | Method for building structures, particularly passages under operating railways or the like | |
KR101022382B1 (en) | Precast horizontality tubular roof and tunnel construction method using the same | |
KR200415268Y1 (en) | Tubular arch tunnel for underground tunnelling | |
CN102733413A (en) | Method for controlling subsidence of operating subway tunnel | |
CN113294166B (en) | Oblique starting method for large-section rectangular jacking pipe | |
KR20090100867A (en) | The method construction work and unit metal tubing constructing system for the road underground driveway | |
CN111395391B (en) | Construction method for multi-hole rectangular jacking pipe and light and dark excavation joint pipe gallery joint | |
CN102966356A (en) | Method for controlling upward flotation and deformation of liquefiable ground operating tunnel under action of earthquake | |
KR100538272B1 (en) | The methods of trenchless underway construction using pre-cast assembly concrete box | |
KR100834076B1 (en) | None open cut tunnelling method and tunnel | |
CN105909268A (en) | Pre-stress combined well/tunnel module structure construction method and module structure | |
KR101468613B1 (en) | Underground structure construction method using the moveable temporary supporting frame | |
KR20130014160A (en) | The tunel execution method | |
KR100509707B1 (en) | None open cut tunnelling of arch type with hume pipe and con'c rib | |
CN110486062B (en) | Method for mechanically underground excavating multi-layer multi-span underground engineering in soft soil | |
KR20210078779A (en) | Underground roadway removed upper structure between upper slab and surface of road after constructing the steel continuous wall in the earth by top-down method and method for constructing the same | |
KR20070079675A (en) | Method for construction of tunnel | |
KR20210055980A (en) | Underground roadway by top-down method using steel continuous wall in the earth without traffic control and temporary road and method for constructing the same | |
KR20120048152A (en) | Non-excavation type constructed tunnels and conduits using arc-shaped divided segments or rugged panels and its constructing method thereof | |
JP5073960B2 (en) | Construction method of underground structure and underground structure | |
CN212405212U (en) | Urban bridge construction support foundation | |
CN212271003U (en) | Porous rectangular jacking pipe and light and shade digging connection pipe gallery joint | |
KR100443819B1 (en) | Underway Tunneling Methods of arch typed Triangle Elementary pipe-roof | |
KR101824440B1 (en) | Construction of Tunnel Structure including shallow ground surface and curved linear section | |
KR20210055981A (en) | Underground roadway using steel continuous wall in the earth with minimum traffic control in constructing by top-down method and method for constructing the same |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A201 | Request for examination | ||
A302 | Request for accelerated examination | ||
E902 | Notification of reason for refusal | ||
E701 | Decision to grant or registration of patent right | ||
GRNT | Written decision to grant | ||
LAPS | Lapse due to unpaid annual fee |