KR100239392B1 - Precasted culvert which is grouted on the spot and method for carrying out the same - Google Patents
Precasted culvert which is grouted on the spot and method for carrying out the same Download PDFInfo
- Publication number
- KR100239392B1 KR100239392B1 KR1019970038612A KR19970038612A KR100239392B1 KR 100239392 B1 KR100239392 B1 KR 100239392B1 KR 1019970038612 A KR1019970038612 A KR 1019970038612A KR 19970038612 A KR19970038612 A KR 19970038612A KR 100239392 B1 KR100239392 B1 KR 100239392B1
- Authority
- KR
- South Korea
- Prior art keywords
- side wall
- plate portion
- culvert
- bottom plate
- frame
- Prior art date
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/045—Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
-
- E—FIXED CONSTRUCTIONS
- E03—WATER SUPPLY; SEWERAGE
- E03F—SEWERS; CESSPOOLS
- E03F3/00—Sewer pipe-line systems
- E03F3/06—Methods of, or installations for, laying sewer pipes
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F16—ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
- F16L—PIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
- F16L1/00—Laying or reclaiming pipes; Repairing or joining pipes on or under water
- F16L1/024—Laying or reclaiming pipes on land, e.g. above the ground
- F16L1/028—Laying or reclaiming pipes on land, e.g. above the ground in the ground
- F16L1/038—Laying or reclaiming pipes on land, e.g. above the ground in the ground the pipes being made in situ
Landscapes
- Engineering & Computer Science (AREA)
- Environmental & Geological Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Sewage (AREA)
Abstract
본 발명은, 저판부, 상판부 및 상기 저판부와 상기 상판부사이에 설치되는 적어도 한 쌍의 측벽부를 갖는 현장타설형 조립식 암거 및 그 설치방법에 관한 것이다. 본 발명에 따른 현장타설형 조립식 암거는 상기 측벽부중 적어도 어느 하나는 소정의 간격을 두고 상호 평행하게 배치되는 한 쌍의 미리 형성된 측벽형틀부와, 상기 한 쌍의 측벽형틀부 사이에 충전되는 측벽현장성형부로 이루어지며; 상기 상판부는 상기 측벽형틀부와 조립되는 상판형틀부와, 상기 상판형틀부의 상면에 현장타설되는 상판현장성형부를 갖는 것을 특징으로 한다. 이에 의하여, 운반 및 설치가 용이하며 암거의 외력에 의한 변형을 극소화할 수 있다.The present invention relates to a field casting type culvert having a bottom plate portion, a top plate portion and at least one pair of side wall portions provided between the bottom plate portion and the top plate portion, and a method of installing the same. According to the present invention, at least one of the side wall prefabricated culverts includes a pair of pre-formed side wall frame parts arranged in parallel with each other at a predetermined interval, and a side wall site filled between the pair of side wall frame parts. Consisting of a molded part; The upper plate portion is characterized in that it has an upper plate frame portion to be assembled with the side wall frame portion, and a top plate field molding portion cast in the field on the upper surface of the upper frame portion. Thereby, it is easy to carry and install, and the deformation by the external force of a culvert can be minimized.
Description
본 발명은 저판부, 상판부 및 상기 저판부와 상기 상판부사이에 설치되는 적어도 한쌍의 측벽부를 갖는 현장타설형 조립식 암거 및 그 설치방법에 관한 것으로서, 보다 상세하게는 공장에서 암거의 일부 및 보강철근을 가공하고, 현장에서 이들을 상호 조립한 후 그라우팅을 타설하도록 하여 암거조립체의 변형이 방지될 수 있도록 한 현장타설형 조립식 암거 및 그 설치방법에 관한 것이다.The present invention relates to a field-pouring prefabricated culvert having a bottom plate portion, a top plate portion and at least a pair of side wall portions provided between the bottom plate portion and the top plate portion, and a method of installing the same. The present invention relates to an on-site pour type prefabricated culvert and its installation method which can prevent deformation of the culvert assembly by processing and placing the grout after assembling each other in the field.
암거는 우수·오수 및 농공업용수 등의 수로를 형성하거나, 인도 및 차도 등의 통행로를 만들거나, 전기통신 및 온·냉관로 등의 매설을 위한 지하공동구의 제작 및 농수산물의 저장창고 등의 제작 등에 다양하게 사용되고 있다.Culvert forms waterways such as rainwater, sewage and agricultural industrial waters, makes passages such as sidewalks and roadways, manufactures underground joint wards for laying telecommunications and hot and cold pipelines, and manufactures warehouses of agricultural and marine products. It is used in various ways.
특히, 암거를 부분별로 분할하여 예를 들면, 덮개판, 측면판, 바닥판 등을 공장에서 다량으로 제작하고 현장에서 이들이 조립되도록 함으로써, 공기를 단축할 수 있으며, 경제적 시공이 가능하도록 한 조립식 암거가 널리 이용되고 있다.Particularly, the prefabricated culverts can be shortened and economical construction by dividing the culvert into parts, for example, by making a large amount of cover plates, side plates, and bottom plates in the factory and allowing them to be assembled in the field. Is widely used.
이러한 조립식 암거의 예로, 암거를 덮개판, 측면판 그리고 바닥판으로 나누어 제작하는 것으로 측면판의 전후방에는 사다리꼴형 결합돌조를 돌설하고, 그 중심부에 투입공과 연통되게 밀폐접합층을 형성하여 상호 결합시키는 조립식 암거가 대한민국 실용신안공보 공고번호 제85-28호에 알려져 있다.As an example of such a prefabricated culvert, the culvert is divided into a cover plate, a side plate, and a bottom plate to protrude a trapezoidal coupling protrusion in the front and rear sides of the side plate, and form a hermetically sealed layer in communication with an input hole at the center thereof to mutually bond. Prefabricated culverts are known from Korean Utility Model Publication No. 85-28.
그런데, 이러한 종래의 조립식 암거에 있어서는, 암거가 대형화할 경우 제작 자체가 용이하지 않을 뿐만 아니라, 현장까지의 운반 및 설치가 용이하지 않다. 특히, 현장에서의 조립시 자체하중에 의한 암거의 손상 및 균열의 우려가 있으며, 설치후에도 지반침하 또는 지반상승에 따른 외력에 암거결합체가 쉽게 변형될 우려가 크다는 문제점이 있다.By the way, in such a conventional prefabricated culvert, when the culvert becomes large, not only manufacturing itself is easy but also carrying and installation to a site is not easy. In particular, there is a risk of damage and cracking of the culvert due to its own load when assembling in the field, there is a problem that the culvert assembly is easily deformed by the external force due to ground subsidence or ground rise even after installation.
따라서, 본 발명의 목적은, 운반 및 설치가 용이하며 외력에 의한 변형을 극소화할 수 있는 현장타설형 조립식 암거 및 그 설치방법을 제공하는 것이다.Accordingly, it is an object of the present invention to provide a site-mounted prefabricated culvert that can be easily transported and installed and minimizes deformation due to external force, and a method of installing the same.
제1도는 본 발명에 따른 현장타설형 조립식 암거의 조립상태 사시도,1 is a perspective view of the assembled state of the cast-in-place culvert according to the present invention,
제2도는 제1도에 대한 암거의 분해사시도,2 is an exploded perspective view of the culvert relative to FIG.
제3도는 제1도에 대한 현장성형부의 성형후 사시도,3 is a perspective view after the molding of the in-situ forming part relative to FIG.
제4도는 본 발명의 일 실시예에 따른 현장타설형 조립식 암거의 설치방법을 설명하기 위한 흐름도이다.Figure 4 is a flow chart for explaining the installation method of the cast-in-place culvert according to an embodiment of the present invention.
〈도면의 주요부분에 대한 부호의 설명〉<Explanation of symbols for main parts of drawing>
10 : 저판부 17, 33 : 물림턱10:
19, 34 : 물림연부 20 : 측벽부19, 34: bite edge 20: side wall
21 : 측벽형틀부 22 : 외측형틀부21: side frame portion 22: outer frame portion
26 : 내측형틀부 27, 37 : 현장성형부26:
28, 38 : 보강철근 29, 39 : 연결부재28, 38: reinforcing
30 : 상판부 31 : 상판형틀부30: upper plate portion 31: upper plate frame portion
35 : 지지턱35: support jaw
상기 목적은, 본 발명에 따라, 저판부, 상판부 및 상기 저판부와 상기 상판부사이에 설치되는 적어도 한쌍의 측벽부를 갖는 현장타설형 조립식 암거에 있어서, 상기 측벽부중 적어도 어느 하나는 소정의 간격을 두고 상호 평행하게 배치되는 한 쌍의 미리 형성된 측벽형틀부와, 상기 한 쌍의 측벽형틀부 사이에 충전되는 측벽현장성형부로 이루어지며; 상기 상판부는 상기 측벽형틀부와 조립되는 상판형틀부와, 상기 상판형틀부의 상면에 현장타설되는 상판현장성형부를 갖는 것을 특징으로 하는 현장타설형 조립식 암거에 의해서 달성된다.The above object is, according to the present invention, in the field casting type culvert having a bottom plate portion, a top plate portion and at least a pair of side wall portions provided between the bottom plate portion and the top plate portion, at least one of the side wall portions at a predetermined interval. A pair of preformed sidewall frame portions arranged in parallel with each other, and sidewall field molding portions filled between the pair of sidewall frame portions; The upper plate portion is achieved by a site-casting prefabricated culvert, characterized in that it has an upper plate frame portion to be assembled with the side wall frame portion, and an upper plate field forming portion that is cast in the field on the upper surface of the upper frame portion.
그리고, 상기 측벽형틀부 및 상기 상판형틀부는 콘크리트, 금속재, 섬유보강재중 어느 하나로 형성되도록 하는 것이 바람직하다.The side wall frame portion and the upper plate frame portion may be formed of any one of concrete, metal, and fiber reinforcement.
한편, 본 발명의 다른 분야에 따르면, 조립식 암거의 설치방법에 있어서, 저판부, 상판부의 적어도 일부를 형성하는 단계와; 상기 저판부 및 상기 상판부사이에 설치되는 각 측벽부를 형성하기 위한 측벽형틀부를 성형하는 단계와; 상기 저판부상에 각 측벽부의 형성을 위한 측벽형틀부를 소정의 간격을 두고 배치하는 단계와; 상기 측벽형틀부상에 상기 상판부를 조립하는 단계와; 상기 각 측벽형틀부사이에 콘크리트를 충전하여 측벽부를 성형하는 단계; 상기 측벽부의 충전후, 상기 상판형틀부의 상면에 현장성형부를 형성하는 단계를 포함하는 것을 특징으로 하는 조립식 암거의 설치방법에 의해서도 달성된다.On the other hand, according to another field of the present invention, in the installation method of the prefabricated culvert, the step of forming at least a portion of the bottom plate, the upper plate; Shaping a side wall mold portion to form each side wall portion provided between the bottom plate portion and the top plate portion; Disposing side wall frame portions for forming each side wall portion at predetermined intervals on the bottom plate portion; Assembling the upper plate portion on the sidewall frame portion; Forming a side wall part by filling concrete between each side wall frame part; After filling the side wall portion, it is also achieved by the installation method of the prefabricated culvert characterized in that it comprises the step of forming a field molding on the upper surface of the upper frame portion.
상기 측벽부의 충전 후, 상기 암거의 전후개구를 차단하고 내부공간에 스팀을 공급하는 단계를 더 포함하는 것이 바람직할 수 있다.After filling the side wall portion, it may be preferable to further include the step of blocking the front and rear opening of the culvert and supplying steam to the internal space.
이하에서는 첨부된 도면을 참조하여 본 발명에 대하여 상세히 설명한다.Hereinafter, with reference to the accompanying drawings will be described in detail with respect to the present invention.
도 1은 본 발명에 따른 현장타설형 조립식 암거의 결합상태의 사시도이고, 도 2는 도 1의 암거의 분해사시도이며, 도 3은 도 1의 그라우팅 타설후의 사시도이다. 이들 도면중 일부는 설명의 편의상 사실과 다소 다르게 과장되거나 생략되어 도시되어 있다. 이들 도면에 도시된 바와 같이, 본 현장타설형 조립식 암거는 사각단면형상을 가지는 복수개의 암거유니트로 구성된다. 각 암거유니트는 바닥면에 설치되어 암거체를 지지하는 저판부(10)와, 저판부(10)상의 양측연부에 상호 소정간격으로 이격배치되는 외측형틀부(22)와 내측형틀부(26)을 갖는 측벽형틀부(21)와 이들 외측형틀부(22)와 내측형틀부(26)사이에 형성되는 현장성형부(27)를 포함하는 측벽부(20)와, 측벽부(20)상에 거의 저판부(10)와 나란하게 결합되는 상판부(30)를 가진다. 각 암거유니트는 암거유니트의 연결방향을 따라 그 폭에 있어 저판부(10)와 상판부(30)는 거의 동일한 크기로 형성되고, 측벽부(20)는 대략 이들의 2/3정도의 크기를 갖도록 형성됨으로써, 부등침하 등에 보다 효과적으로 대응하게 된다.1 is a perspective view of the assembled state of the cast-in-place culvert according to the present invention, Figure 2 is an exploded perspective view of the culvert of Figure 1, Figure 3 is a perspective view after the grouting pour of FIG. Some of these drawings are shown to be exaggerated or omitted somewhat different from the fact for the convenience of description. As shown in these figures, the present site casting type culvert is composed of a plurality of culvert units having a rectangular cross-sectional shape. Each culvert unit is provided on the bottom surface to support the culvert and the
저판부(10)는 직사각형상을 가지며 대개 공장에서 미리 제작된다. 저판부(10)의 전방단부와 후방단부에는 다른 저판부(10)와의 연장결합을 위하여 각각 하부표면과 상부표면으로부터 두께방향으로 절취된 물림턱(17)과 물림연부(19)가 형성되어 있다. 저판부(10)의 양측연부에는 외측형틀부(22) 및 내측형틀부(26)의 하단부를 지지할 수 있도록 상부표면으로부터 함몰된 외측형틀수용부(11) 및 내측형틀수용부(15)가 각각 형성되어 있다. 외측형틀수용부(11)의 중앙영역에는 판면으로부터 돌출된 물림리브(12)가 형성되어 있으며, 외측형틀수용부(11)의 내측에는 외측형틀수용부(11)와 나란하게 판면으로부터 내측형틀수용부(15)가 함몰형성되어 있다. 외측형틀수용부(11)와 내측형틀수용부(15)사이에는 현장성형부(27)의 형성을 위한 망상의 보강철근(28)이 결합될 수 있도록 판면으로부터 복수의 철근(13)이 돌출형성되어 있다.The
측벽부(20)는 저판부(10)상의 양측연부에 기립하게 설치되며, 각각 공장에서 미리제작되는 외측형틀부(22) 및 내측형틀부(26)를 갖는 측벽형틀부(21)와, 외측형틀부(22)와 내측형틀부(26)사이에 현장에서 콘크리트를 타설하여 형성되는 현장성형부(27)를 포함한다. 외측형틀부(22)는 다른 외측형틀부(22)와 연장결합을 위하여 사각판상의 연결부재(29)에 볼트로 연결되어 있으며, 하단부에는 외측형틀부(22)가 안정적으로 기립상태를 유지할 수 있도록 두께방향으로 연장성형된 외측플랜지(23)와 내측플랜지(24)가 각각 형성되어 있다. 이들 외측플랜지(23)와 내측플랜지(24)사이에는 저판부(10)에 형성된 물림리브(12)와 맞물릴 수 있도록 물림리브수용홈(25)이 형성되어 있다.The
내측형틀부(26)도 외측형틀부(22)와 마찬가지로 다른 내측형틀부(26)와 사각판상의 연결부재(29)에 의하여 연장결합되어 있으며, 안정적 기립상태를 유지할 수 있도록 하단부는 두께방향으로 연장형성되어 있다. 내측형틀부(26)의 상단부는 외측으로부터의 압력에 대응할 수 있도록 상판형틀부(31)의 측연부를 따라 형성된 지지턱(35)에 접촉지지되어 있다.Like the
이러한 외측형틀부(22) 및 내측형틀부(26)는 콘크리트, 금속부재 또는 섬유보강재 중 어느 것으로나 구성될 수 있으며, 외측형틀부(22)와 내측형틀부(26)의 상호 인접측면은 통상 현장에서 타설되는 콘크리트가 용이하게 접착될 수 있는 구조로 형성된다.The
한편, 외측형틀부(22)와 내측형틀부(26)사이에는 다수의 철근을 수평방향과 수직방향으로 배치결속하여 형성된 망상의 보강철근(28)이 결합되어 현장에서 타설되는 콘크리트를 결집함으로써 현장성형부(27)가 공고히 되도록 한다.On the other hand, between the
상판부(30)는 내측형틀부(26)상에 결합되는 상판형틀부(31)와, 상판형틀부(31)상에 설치되는 망상의 보강철근(38)에 콘크리트를 타설하여 형성되는 현장성형부(37)를 포함한다. 상판형틀부(31)의 전방단부 및 후방단부에는 다른 상판형틀부(31)와 연장결합될 수 있도록 각각 하부표면과 상부표면으로부터 두께방향으로 절취된 물림턱(33)과 물림연부(34)가 각각 형성되어 있다. 상판형틀부(31)의 양측하단에는 측단부로부터 소정간격 즉, 내측형틀부(26)의 상단부 두께정도로 간격을 두고 판면으로부터 하향돌출된 지지턱(35)이 각각 형성되어 있으며, 이 지지턱(35)은 내측형틀부(26)의 상단부가 외측으로부터 작용하는 압력에 의하여 내측으로 밀리게 되는 것을 방지하게 된다.The
상판형틀부(31)는 외측형틀부(22)와 거의 "L"자 형상을 갖는 연결부재(39)에 의하여 볼트로 연결되어 현장성형부(37) 성형시 콘크리트의 압력에 의하여 외측형틀부(22)가 외측으로 이탈되는 것을 방지하게 된다. 상판형틀부(31)의 상측에는 현장에서 콘크리트를 타설하여 현장성형부(37)를 형성할 수 있도록 망상의 보강철근(38)이 결합되어 있다. 암거조립체의 상판형틀부(31)중 전방에 결합되는 상판형틀부(31)의 전방단부에는 전방플랜지(36)가 형성되어 있으며, 암거조립체의 후방에 결합되는 상판형틀부(31)의 후방단부에는 후방플랜지(미도시)가 판면으로부터 각각 거의 수직하게 절곡형성되어 있다. 이들 전면플랜지(36)와 후방플랜지는 현장성형부의 형성시 타설되는 콘크리트의 누설을 방지하게 된다.The
이러한 구성에 의하여, 바닥면에 저판부(10)를 연결하여 설치하고, 각 내측형틀수용부(15)에 내측형틀부(26)의 하단부가 각각 결합되도록 설치한다. 다음, 내측형틀부(26)가 사각판상의 연결부재에 의하여 연장결합되도록 하고, 내측형틀부(26)상에 상판형틀부(31)가 각각 결합되도록 한다. 내측형틀수용부(15)와 외측형틀수용부(11)사이에 보강철근(28)이 결합되도록 하고, 외측형틀수용부(11)상에 외측형틀부(22)가 기립설치되도록 한다. 외측형틀부(22) 상호 간을 연결부재(29)를 사용하여 연결하고, 상판형틀부(31)와 외측형틀부(22)를 "L"자 형상을 갖는 연결부재(39)로 연결하여 외측형틀부(22)가 콘크리트 타설시 외측으로 벌어지는 것이 방지되도록 한다. 상판형틀부(31)상에 콘크리트 타설을 위한 보강철근(38)을 결합하고, 외측형틀부(22)와 내측형틀부(26)사이 및 상판형틀부(31)의 상부표면에 콘크리트가 타설되도록 하여 현장성형부(37)를 형성한다. 콘크리트타설이 완료되면 암거조립체의 전방과 후방을 차단하고 이동 보일러 등을 가동하여 현장성형부(27, 37)에 스팀이 공급되도록 하여 콘크리트의 양생이 촉진되도록 한다. 현장성형부(27, 37)의 고화가 완료되면 되메우기를 실시한다.By such a configuration, the
도 4는 본 발명의 일실시예에 따른 현장타설형 조립식 암거의 설치방법을 설명하기 위한 흐름도이다. 이 도면에 도시된 바와 같이, 저판부(10) 및 상판형틀부(31)를 공장에서 미리 제작하고(S10), 측벽부(20)의 형성을 위한 측벽형틀부(21) 즉, 내측형틀부(26) 및 외측형틀부(22)를 공장에서 미리 제작되도록 한다(S20). 저판부(10), 상판형틀부(31) 및 측벽형틀부(21)이 완료되면 소정의 시공위치에 저판부(10)를 연결하여 설치하고 저판부(10)상에 각각 내측형틀부(26) 및 외측형틀부(22)를 조립하고(S30), 내측형틀부(26)의 상단부에 상판형틀부(31)가 조립되도록 한다(S40). 외측형틀부(22)와 내측형틀부(26) 사이 및 상판형틀부(31)상에 보강철근(28, 38)을 배치결합하고(S50), 측벽형틀부(21) 사이에 콘크리트가 충전되도록 한다(S60). 측벽형틀부(21) 사이에 콘크리트가 충전되면 상부형틀부(31)상에 결합된 보강철근(38)에 콘크리트를 타설하여 현장성형부(37)를 형성한다(S70). 콘크리트의 타설이 완료되면 암거조립체의 전후개구를 차단하고(S80), 차단된 내부공간내에 이동보일러 등을 가동하여 스팀이 공급되도록 하여 현장성형부(27, 37)의 양생 고화가 촉진되도록 한다(S90).Figure 4 is a flow chart for explaining the installation method of the cast-in-place culvert according to an embodiment of the present invention. As shown in this figure, the
이와 같이, 측벽형틀부와, 상판형틀부를 공장에서 미리제작하고, 측벽형틀부 사이 및 상판형틀부의 상부표면에 현장에서 콘크리트가 타설되도록 함으로써 제작을 용이하게 할 수 있다. 측벽부와 상판부의 일부만을 형성함으로써, 운반 및 설치가 용이할 뿐만 아니라, 현장에서 콘크리트를 타설하여 암거체를 완성함으로써 암거체의 변형을 극소화할 수 있다. 그리고, 스팀을 통한 양생고화의 촉진으로 공기를 단축할 수 있다.In this way, the side wall frame portion and the upper plate frame portion are manufactured in advance at the factory, and concrete can be easily cast in the field between the side wall frame portions and the upper surface of the upper frame portion. By forming only a part of the side wall portion and the upper plate portion, not only is easy to transport and install, but also the concrete can be cast in the field to complete the culvert, thereby minimizing the deformation of the culvert. And, it is possible to shorten the air by promoting curing solidification through steam.
이상 설명한 바와 같이, 본 발명에 따르면, 운반 및 설치가 용이하며 외력에 의한 변형을 극소화할 수 있는 현장타설형 조립식 암거 및 그 설치방법이 제공된다.As described above, according to the present invention, there is provided an on-site cast-type culvert and its installation method which are easy to transport and install and can minimize deformation caused by external force.
Claims (4)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1019970038612A KR100239392B1 (en) | 1997-08-13 | 1997-08-13 | Precasted culvert which is grouted on the spot and method for carrying out the same |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1019970038612A KR100239392B1 (en) | 1997-08-13 | 1997-08-13 | Precasted culvert which is grouted on the spot and method for carrying out the same |
Publications (2)
Publication Number | Publication Date |
---|---|
KR19990016159A KR19990016159A (en) | 1999-03-05 |
KR100239392B1 true KR100239392B1 (en) | 2000-01-15 |
Family
ID=19517398
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR1019970038612A KR100239392B1 (en) | 1997-08-13 | 1997-08-13 | Precasted culvert which is grouted on the spot and method for carrying out the same |
Country Status (1)
Country | Link |
---|---|
KR (1) | KR100239392B1 (en) |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100891617B1 (en) * | 2007-10-17 | 2009-04-02 | 김현국 | The steel box for the concrete filling type closed conduit construction |
KR100926173B1 (en) * | 2009-03-31 | 2009-11-10 | 정병양 | Piping structure and method for constructing the same |
-
1997
- 1997-08-13 KR KR1019970038612A patent/KR100239392B1/en not_active IP Right Cessation
Also Published As
Publication number | Publication date |
---|---|
KR19990016159A (en) | 1999-03-05 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR100640716B1 (en) | Precast concrete block for cantilever retaining wall and construction method using the same | |
KR20080061580A (en) | Precast concrete file and method for constructing thereof | |
JP2004232328A (en) | Structure of half precast type arch culvert and its construction method | |
KR100239392B1 (en) | Precasted culvert which is grouted on the spot and method for carrying out the same | |
KR100265397B1 (en) | Precasted culvert which is grouted on the spot | |
KR100779608B1 (en) | Precast concrete block for retaining wall | |
KR100297823B1 (en) | Cuvert And Production Method Therof | |
KR102263318B1 (en) | Arch-type Precast Structure with Improved Assembly Structure and Construction Method Thereof | |
KR100696910B1 (en) | The method of making the temporary retaining wall block using a temporary retaining wall block type and this | |
KR20040091241A (en) | Supportor for supporti ng synthetic resin pipe and method for laying pipes using thereof | |
KR20070076560A (en) | Sectional manhole | |
KR100805555B1 (en) | Sectional manhole using multi-divided segments | |
KR200148172Y1 (en) | Precasted culvert | |
KR102120849B1 (en) | Installation structure and method of precast concrete culvert | |
KR100492516B1 (en) | Mold for manufacturing breast wall and method thereof | |
KR20090006320A (en) | Retaining wall structure for expanding road | |
KR200339018Y1 (en) | Manhole for underground electric power distribution manufactured from precast concrete | |
KR200329055Y1 (en) | Structure of side coupling part of pc wall member with function of waterproof in corner part and pc wall member therefor | |
KR100793684B1 (en) | Assemble type wall structure and constructing method thereof | |
CN220183971U (en) | Outdoor assembled drainage mechanism | |
JP3563662B2 (en) | Concrete block | |
KR100201490B1 (en) | Precasted culvert and method for installing the same | |
KR101006687B1 (en) | Two-segment assembly retaining wall | |
KR20010016132A (en) | Arch-box Type Prefab Culvert | |
KR200221907Y1 (en) | Arch-box Type Prefab Culvert |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A201 | Request for examination | ||
E902 | Notification of reason for refusal | ||
E701 | Decision to grant or registration of patent right | ||
GRNT | Written decision to grant | ||
FPAY | Annual fee payment |
Payment date: 20121022 Year of fee payment: 14 |
|
FPAY | Annual fee payment |
Payment date: 20131022 Year of fee payment: 15 |
|
FPAY | Annual fee payment |
Payment date: 20141021 Year of fee payment: 16 |
|
J206 | Request for trial to confirm the scope of a patent right | ||
J204 | Request for invalidation trial [patent] | ||
FPAY | Annual fee payment |
Payment date: 20151021 Year of fee payment: 17 |
|
J206 | Request for trial to confirm the scope of a patent right | ||
J301 | Trial decision |
Free format text: TRIAL NUMBER: 2015100003491; TRIAL DECISION FOR CONFIRMATION OF THE SCOPE OF RIGHT_AFFIRMATIVE REQUESTED 20150608 Effective date: 20160922 Free format text: TRIAL NUMBER: 2015100003951; TRIAL DECISION FOR INVALIDATION REQUESTED 20150717 Effective date: 20160922 Free format text: TRIAL NUMBER: 2016100000672; TRIAL DECISION FOR CONFIRMATION OF THE SCOPE OF RIGHT_DEFENSIVE REQUESTED 20160316 Effective date: 20160922 |
|
FPAY | Annual fee payment |
Payment date: 20161011 Year of fee payment: 18 |
|
EXPY | Expiration of term |