JPH10102423A - Pca form and construction method of pier using the same pca form - Google Patents
Pca form and construction method of pier using the same pca formInfo
- Publication number
- JPH10102423A JPH10102423A JP27289296A JP27289296A JPH10102423A JP H10102423 A JPH10102423 A JP H10102423A JP 27289296 A JP27289296 A JP 27289296A JP 27289296 A JP27289296 A JP 27289296A JP H10102423 A JPH10102423 A JP H10102423A
- Authority
- JP
- Japan
- Prior art keywords
- pca
- formwork
- pier
- concrete
- assembly
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
Description
【0001】[0001]
【発明の属する技術分野】本発明は、鉄筋コンクリート
の橋脚を、プレキャストコンクリート(以下、PCaと
略称する)型枠を用いて構築する技術に関する。The present invention relates to a technique for constructing a reinforced concrete pier using a precast concrete (hereinafter abbreviated as PCa) formwork.
【0002】[0002]
【従来の技術】鉄筋コンクリートからなる橋脚の施工
は、従来、例えば図19乃至図22に示すような方法で
行われている。すなわち従来工法においては、まず地盤
に基礎部(フーチング)101を施工し、その上に、橋
脚102を所定の施工高さずつ第一リフト1021 から
第nリフト102n まで順次施工して行く。各リフトの
施工においては、図20に示すように、施工高さに対応
して仮設足場103を延長構築し、当該リフトにおける
橋脚施工空間に主筋、剪断補強筋及び帯筋等の鉄筋10
2aをクレーン104で揚重して組み立てた後、図21
に示すように、前記橋脚施工空間を取り囲むように型枠
102bを組み立て、この型枠102b内にコンクリー
トを打設するといった手順で行われる。図22に示すよ
うに、第nリフト102n までの施工によって橋脚10
2が構築されたら、その上に橋桁を架設するための梁部
105を施工する。2. Description of the Related Art Conventionally, a pier made of reinforced concrete is constructed by a method as shown in FIGS. 19 to 22, for example. Specifically, in the conventional method, first applying a foundation (footing) 101 ground, thereon successively construction from the first lift 102 1 piers 102 by a predetermined execution height to the n lift 102 n. In the construction of each lift, as shown in FIG. 20, the temporary scaffold 103 is extended and constructed in accordance with the construction height, and the reinforcing bars 10 such as the main reinforcement, the shear reinforcement and the band reinforcement are provided in the pier construction space of the lift.
After lifting and assembling 2a with a crane 104, FIG.
As shown in (1), a form 102b is assembled so as to surround the pier construction space, and concrete is poured into the form 102b. As shown in FIG. 22, the pier 10 by application of up to the n lift 102 n
When 2 is constructed, a beam portion 105 for erection of a bridge girder is constructed thereon.
【0003】[0003]
【発明が解決しようとする課題】上記従来工法によれ
ば、次のような問題が指摘される。 (1) 主筋、剪断補強筋、帯筋等の鉄筋102bの組み立
てや型枠102bの組み立て等の煩雑な作業が殆どが高
所作業となるので、時間がかかるばかりでなく、危険で
ある。 (1) 型枠102bの組み立てにあたっては、コンクリー
ト打設時の側圧に対抗するためにこの型枠102bを多
数のセパレータ(図示省略)で締結する必要があり、し
たがって施工が煩雑であり、時間がかかる。 (2) コンクリートに所要の強度が発現されるのを待っ
て、型枠102bの解体・撤去作業が必要である。 (3) 仮設足場103は橋脚施工空間の全周を取り囲むよ
うに構築しなければならないため、多くの仮設材や労
力、時間が必要である。According to the above conventional method, the following problems are pointed out. (1) Most of the complicated work such as assembling the reinforcing bars 102b such as the main reinforcing bars, the shear reinforcing bars, and the stirrups, and assembling the formwork 102b is performed at a high place, so that it takes time and is dangerous. (1) When assembling the formwork 102b, it is necessary to fasten the formwork 102b with a large number of separators (not shown) in order to counteract the lateral pressure at the time of concrete casting. Take it. (2) It is necessary to dismantle and remove the formwork 102b after the required strength is developed in the concrete. (3) Since the temporary scaffold 103 must be constructed so as to surround the entire circumference of the pier construction space, a lot of temporary materials, labor and time are required.
【0004】本発明は、上記のような事情のもとになさ
れたもので、その技術的課題とするところは、鉄筋コン
クリートからなる橋脚の施工において、現場での省力
化、省人化及び工期短縮を図ると共に、橋脚の耐久性を
向上させることにある。[0004] The present invention has been made under the above circumstances, and a technical problem thereof is that, in the construction of a pier made of reinforced concrete, labor saving, labor saving, and shortening of the construction period at the site. And to improve the durability of the pier.
【0005】[0005]
【課題を解決するための手段】上述した技術的課題を有
効に解決するため、本発明は、PCa型枠を用いて橋脚
を施工する技術を提供するものである。この橋脚施工に
用いられるPCa型枠は、コンクリートで成形されたP
Ca堰板と、このPCa堰板にそのコンクリート打設側
の面から離れた位置を左右に延在された状態に取り付け
られた複数の剪断補強筋と、前記のコンクリート打設側
の面に配設されたセパレータ取付部とを備え、前記PC
a堰板の左右端部近傍に達する前記剪断補強筋の両端に
橋脚主筋への結合部が形成されたものである。なお、
「PCa」とは、先に述べたように「プレキャストコン
クリート」の略称であって、すなわちPCa堰板は予め
工場生産した板状のコンクリート成形品であり、「左
右」とは当該PCa型枠を組み立てた状態での略水平方
向となる方向をいう。SUMMARY OF THE INVENTION In order to effectively solve the above-mentioned technical problems, the present invention provides a technique of constructing a pier using a PCa formwork. The PCa formwork used for this pier construction is made of concrete molded P
A Ca weir plate, a plurality of shear reinforcing bars attached to the PCa weir plate so as to extend from the surface on the concrete casting side to the left and right, and arranged on the concrete placing surface And a separator mounting part provided.
(a) At both ends of the shear reinforcement reaching the vicinity of the left and right ends of the weir plate, connecting portions to the bridge pier main reinforcement are formed. In addition,
“PCa” is an abbreviation of “precast concrete” as described above, that is, the PCa dam is a plate-shaped concrete molded product produced in advance in a factory, and “left and right” means the PCa formwork. It refers to a direction that is substantially horizontal when assembled.
【0006】PCa堰板は、現場打ちコンクリートによ
って橋脚を成形するための型枠本体であると共に、打設
後経時的に硬化していく前記現場打ちコンクリートと一
体化されることによって橋脚の外壁面となるものであ
る。好ましくは、PCa堰板のコンクリート打設側の面
には所要数のリブが形成され、このリブは、PCa堰板
の補強作用を有するほか、剪断補強筋の取付手段及びセ
パレータ取付部の配設手段として利用される。The PCa weir plate is a formwork body for forming a pier by cast-in-place concrete, and is integrated with the cast-in-place concrete, which hardens over time after casting, to form an outer wall surface of the pier. It is what becomes. Preferably, a required number of ribs are formed on the surface of the PCa weir plate on the concrete casting side, and the ribs have a reinforcing effect on the PCa weir plate, and are provided with mounting means for shear reinforcing bars and separator mounting portions. Used as a means.
【0007】本発明による橋脚の施工においては、ま
ず、上述の構成を備えるPCa型枠を地上で方形枠状に
配置し、互いに衝き合わされた前記各PCa型枠の端部
同士を連結すると共に、互いに対向する前記PCa型枠
同士をセパレータを用いて締結することによってPCa
型枠組立体を組み立てる。PCa型枠組立体を構成する
各PCa型枠には予め剪断補強筋が配設されているが、
好ましくは、地上でPCa型枠組立体を組み立てる際に
帯筋も組み込んでおく。In the construction of a bridge pier according to the present invention, first, the PCa formwork having the above-described configuration is arranged in a rectangular form on the ground, and the ends of the PCa formworks that have been abutted against each other are connected to each other. The PCa molds facing each other are fastened to each other by using
Assemble the formwork assembly. Each PCa formwork constituting the PCa formwork assembly is provided with a shear reinforcement in advance,
Preferably, straps are also incorporated when assembling the PCa formwork assembly on the ground.
【0008】次に、このPCa型枠組立体を揚重して橋
脚施工位置に設置し、前記PCa型枠組立体の内側空間
に所要数の主筋を組み込み、一部の主筋を前記各PCa
型枠と一体の剪断補強筋の両端結合部に結合する。そし
て、前記各PCa型枠組立体の内側空間に現場打ちコン
クリートを打設することによって、各PCa型枠のPC
a堰板が前記現場打ちコンクリートに経時的に一体化さ
れ、かつ主筋、剪断補強筋、帯筋、セパレータ等が前記
現場打ちコンクリートに埋設一体化される。Next, the PCa formwork assembly is lifted and installed at a pier construction position, a required number of main reinforcements are installed in the inner space of the PCa formwork assembly, and a part of the main reinforcements is connected to each PCa formwork.
It is connected to both ends of the shear reinforcing bar integrated with the formwork. Then, the cast-in-place concrete is poured into the space inside each of the PCa form assemblies, so that the PCa form of each PCa form is assembled.
a The weir plate is integrated with the cast-in-place concrete over time, and a main reinforcing bar, a shear reinforcing bar, a stirrup, a separator, and the like are embedded and integrated in the cast-in-place concrete.
【0009】[0009]
【発明の実施の形態】以下、図1乃至図11を参照しな
がら、中実の橋脚2を施工する場合の本発明の第一の実
施形態について説明する。まず図1は、地盤Gに基礎部
(フーチング)1を施工し、その上に、第一リフト21
の施工のための複数組のPCa型枠組立体20及び仮設
足場3をクレーン4によって揚重し、順次設置している
過程を示すものである。DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS Hereinafter, a first embodiment of the present invention when a solid pier 2 is constructed will be described with reference to FIGS. First, FIG. 1 shows that a foundation (footing) 1 is constructed on a ground G, and a first lift 2 1 is placed thereon.
2 shows a process in which a plurality of sets of PCa form assemblies 20 and temporary scaffolds 3 for construction of the above are lifted by the crane 4 and sequentially installed.
【0010】PCa型枠組立体20は、図2の平面図に
示すように、横幅の異なる各一対のPCa型枠20A,
20Bからなる。このうち、PCa型枠20Aは、図3
の斜視図に示すように、長方形の板状のプレキャストコ
ンクリート成形体であってコンクリート打設側となる内
側面に3本のリブ21a〜21cが形成されたPCa堰
板21と、前記内側面から適宜離間した位置に配置され
て前記リブ21a〜21cを貫通した状態で取り付けら
れた多数の剪断補強筋22と、前記各リブ21a〜21
cに所定間隔で埋設されたインサートボルト23とを備
えている。またPCa堰板21はその厚さが50〜100mm
程度であって、運搬時あるいはコンリート打設時のクラ
ック等を防止するための補強手段として鉄筋24が格子
状に埋設され、あるいは引っ張り強度の大きい繊維等が
混入されている。また、PCa堰板21の内側面と剪断
補強筋22との間の間隔は、コンクリート打設時のコン
クリート充填性を考慮して、このコンクリートの最大粗
骨材寸法以上とする。As shown in the plan view of FIG. 2, the PCa mold assembly 20 includes a pair of PCa molds 20A having different widths.
20B. Among them, the PCa form 20A is shown in FIG.
As shown in the perspective view of FIG. 1, a PCa dam plate 21 which is a rectangular plate-shaped precast concrete molded body and has three ribs 21 a to 21 c formed on an inner surface serving as a concrete casting side, A large number of shear reinforcing bars 22 which are disposed at appropriate distances and are attached while penetrating the ribs 21a to 21c;
c and insert bolts 23 embedded at predetermined intervals. The PCa dam 21 has a thickness of 50 to 100 mm.
The reinforcing bar 24 is buried in a lattice shape as reinforcing means for preventing cracks or the like at the time of transportation or concreting, or fibers with high tensile strength are mixed. The distance between the inner surface of the PCa dam 21 and the shear reinforcement 22 is set to be equal to or larger than the maximum coarse aggregate size of the concrete in consideration of the concrete filling property at the time of placing the concrete.
【0011】リブ21a〜21cは、PCa型枠組立体
20としての組立状態において略鉛直となる方向に延び
ており、したがってこれを直角に貫通した状態に取り付
けられた剪断補強筋22は、前記組立状態において略水
平となる方向に延びている。これら剪断補強筋22の左
右両端は、前記PCa型枠組立体20の四隅部に相当す
る前記PCa堰板21の左右端部内側に達しており、こ
の部分が内側へ略J字形に屈曲されることによって結合
部22aが形成されている。The ribs 21a to 21c extend in a substantially vertical direction in the assembled state as the PCa formwork assembly 20, and therefore, the shear reinforcement 22 attached to penetrate it at a right angle is in the assembled state. At a substantially horizontal direction. The left and right ends of the shear reinforcement 22 reach the inside of the left and right ends of the PCa dam plate 21 corresponding to the four corners of the PCa formwork assembly 20, and this portion is bent inward into a substantially J-shape. Thus, a connecting portion 22a is formed.
【0012】PCa型枠20Bは、その横幅がPCa型
枠20Aの横幅よりも大きく、4本のリブ21d〜21
gが形成されているほかは、基本的には上記と同様の構
造を有するものである。The width of the PCa frame 20B is larger than the width of the PCa frame 20A, and the four ribs 21d to 21d are provided.
Except that g is formed, it has a structure basically similar to the above.
【0013】PCa型枠組立体20の組立に際しては、
まず地上で図2に示すように各一対のPCa型枠20
A,20Bを配置し、このPCa型枠20A,20B同
士を、図4に示すように、L字形の複数の固定金具25
を介して略長方形の枠状に連結する。図5は、前記固定
金具25によるPCa型枠20Aと20Bの連結構造の
詳細を示すもので、すなわち、固定金具25は、互いに
直角をなして衝き合わされる前記PCa型枠20A,2
0Bの端部近傍で互いに隣接するリブ21aと21g
(及びリブ21cと21d)に、これらのリブ21a,
21g(21c,21d)に埋設されたインサートボル
ト23及びこれに螺合するナット23aによって緊結さ
れる。この連結状態においては、PCa型枠20A,2
0Bにおける剪断補強筋22の結合部22a同士が互い
に略U字形をなすように重なり合い、この部分が後述す
る隅部の主筋28aと結合されるようになっている。When assembling the PCa mold assembly 20,
First, on the ground, as shown in FIG.
A and 20B are arranged, and the PCa molds 20A and 20B are connected to each other by a plurality of L-shaped fixing brackets 25 as shown in FIG.
To form a substantially rectangular frame. FIG. 5 shows the details of the connection structure of the PCa molds 20A and 20B by the fixing bracket 25, that is, the fixing bracket 25 is abutted at right angles to the PCa molds 20A and 20A.
Ribs 21a and 21g adjacent to each other near the end of 0B
(And ribs 21c and 21d), these ribs 21a,
It is tightened by an insert bolt 23 embedded in 21g (21c, 21d) and a nut 23a screwed to the insert bolt 23. In this connected state, the PCa formwork 20A, 2A
The connecting portions 22a of the shear reinforcing bars 22 at 0B overlap each other so as to form a substantially U-shape, and this portion is connected to a main bar 28a at a corner described later.
【0014】次に図6に示すように、互いに対向するP
Ca型枠20A,20A間及びPCa型枠20B,20
B間を、それぞれセパレータ26を介して連結・拘束す
ると共に、PCa型枠20A,20Bにおける各剪断補
強筋22間に架設するようにして帯筋27を格子状に配
筋する。前記セパレータ26は、図7に詳細に示すよう
に、長手方向中央部に設けたターンバックル部26a
と、PCa型枠20Aにおける中間のリブ21b又はP
Ca型枠20Bにおける中間のリブ21e,21fに、
これら各リブ21b,21e,21fに埋設されたイン
サートボルト23及びこれに螺合するナット23aによ
って緊結される両端の金具26bとを有し、PCa型枠
20A,20A間を拘束するものと、PCa型枠20
B,20B間を拘束するものとは、PCa型枠20A,
20Bの横幅の違いに対応して異なる長さとなってい
る。Next, as shown in FIG.
Between the Ca molds 20A, 20A and the PCa molds 20B, 20
B are connected and restrained via the separators 26, and the straps 27 are arranged in a grid pattern so as to extend between the shear reinforcements 22 in the PCa frames 20A and 20B. As shown in detail in FIG. 7, the separator 26 is provided with a turnbuckle portion 26a provided at a central portion in the longitudinal direction.
And an intermediate rib 21b or P in the PCa form 20A.
On the intermediate ribs 21e and 21f in the Ca form 20B,
One having an insert bolt 23 embedded in each of the ribs 21b, 21e, and 21f and metal fittings 26b at both ends tightened by a nut 23a screwed into the insert bolt 23, for restraining between the PCa molds 20A, 20A; Formwork 20
B and 20B are restricted by PCa formwork 20A,
The length is different according to the difference in the width of 20B.
【0015】上述のようにして長方形枠状に組まれたP
Ca型枠組立体20を、クレーン4によって揚重し、第
一リフト21 の施工高さまで順次設置して連結したら、
図8及び図9に示すように、このPCa型枠組立体20
によって画成されたコンクリート打設空間S内に、クレ
ーン4によって所要数の主筋28を建て込む。主筋28
の建て込み作業等においては、作業員に対して、PCa
型枠組立体20が一種の安全柵として機能する。The P framed in a rectangular frame as described above
The Ca-type frame assembly 20, once fried weigh sequentially installed by connecting to the first lifting 2 1 construction height by a crane 4,
As shown in FIG. 8 and FIG.
The required number of main bars 28 are erected by the crane 4 in the concrete placing space S defined by. Main bar 28
In the construction work of the
The formwork assembly 20 functions as a kind of safety fence.
【0016】主筋28は、PCa型枠20A,20Bに
おける剪断補強筋22の内側に配置され、PCa型枠組
立体20の隅部に建て込まれる主筋28aは、前記隅部
で互いに略U字形をなすように重なり合った剪断補強筋
22の結合部22aに通されて結合され、これによって
前記剪断補強筋22同士が互いに略長方形状に連結され
た状態となる。主筋28の建て込み終了後は、前記コン
クリート打設空間内にコンクリートを打設し、第一リフ
ト21 の施工が終わる。The main reinforcement 28 is disposed inside the shear reinforcement 22 in the PCa formwork 20A, 20B, and the main reinforcement 28a built at the corner of the PCa formwork assembly 20 has a substantially U-shape with each other at the corner. As described above, the shear reinforcing bars 22 are passed through the connecting portions 22a of the shear reinforcing bars 22 and connected to each other, whereby the shear reinforcing bars 22 are connected to each other in a substantially rectangular shape. After like an anchor end of the main reinforcement 28 Da設concrete in between the concrete設空, ending the first lift 2 1 construction is.
【0017】PCa型枠20A,20BのPCa堰板2
1は、先に述べたように鉄筋24を埋設したコンクリー
ト製品であって、成形後の収縮・乾燥が完了した状態で
現場に搬入されたものであるため剛性が高く、しかもリ
ブ21a〜21c,21d〜21gによって補強されて
いる。したがって、PCa堰板21を内側から支保する
ためのセパレータ26が、図6及び図9に示すように少
ないものであっても、現場打ちコンクリートの打設時の
側圧に対する十分な耐性を有する。The PCa dam 2 of the PCa formwork 20A, 20B
Reference numeral 1 denotes a concrete product in which the reinforcing bar 24 is buried as described above, which has been transported to the site in a state where shrinkage and drying after molding have been completed, and has high rigidity, and furthermore, the ribs 21a to 21c, Reinforced by 21d to 21g. Therefore, even if the number of the separators 26 for supporting the PCa dam plate 21 from the inside is small as shown in FIGS. 6 and 9, the separator 26 has sufficient resistance to the lateral pressure at the time of casting the cast-in-place concrete.
【0018】また、PCa堰板21は、その内側面が打
設後経時的に硬化していく現場打ちコンクリートと一体
接合状態となることによって橋脚2の外壁面を構成する
ものであり、前記リブ21a〜21c,21d〜21g
を貫通した状態に設けられた剪断補強筋22がジベル筋
として作用するため、良好な接合状態となる。また、前
記現場打ちコンクリートとの接合性を一層向上させるた
めには、PCa堰板21の内側面を粗面状に形成してお
くことも有効である。The PCa dam plate 21 constitutes an outer wall surface of the pier 2 by being integrally joined with cast-in-place concrete whose inner surface hardens with time after casting. 21a-21c, 21d-21g
Since the shear reinforcing bars 22 provided in a state penetrating through serve as a dowel bar, a good joining state is achieved. In order to further improve the bondability with the cast-in-place concrete, it is also effective to form the inner surface of the PCa dam plate 21 into a rough surface.
【0019】第一リフト21 の施工終了後は、直ちに第
二リフト22 の施工を開始する。この第二リフト22 の
施工は、仮設足場3を施工高さまで延長して構築し、あ
とは上述の第一リフト21 の施工と同様、地上でPCa
型枠20A,20B及びセパレータ26、帯筋27等に
よりPCa型枠組立体20を組み立て、このPCa型枠
組立体20をクレーン4で揚重して第一リフト21 上に
所定高さまで順次設置し、主筋28を建て込み、コンク
リートを打設するといった手順で行われる。以下、この
ような一連の工程が第五リフト25 まで繰り返され、図
11に示すような橋脚2が構築される。また、この橋脚
2の天端上には橋桁を架設するための梁部5を施工す
る。[0019] after the end of the first lift 2 1 of the construction is, to immediately start the construction of the second lift 2 2. The second lift 2 2 construction is constructed by extending the temporary scaffold 3 the execution height, similar to the first lift 2 1 construction described above after, PCa ground
Mold 20A, 20B and the separator 26, assembled PCa type frame assembly 20 by hoop 27, and the like, the PCa-type frame assembly 20 sequentially installed to a predetermined height on the first lift 2 1 to Agekasane a crane 4, The main bars 28 are erected and concrete is cast. Hereinafter, such a series of steps are repeated until the fifth lift 2 5, the piers 2 as shown in FIG. 11 is constructed. On the top end of the pier 2, a beam 5 for erection of a bridge girder is constructed.
【0020】先に述べたように、PCa堰板21(PC
a型枠20A,20B)は、その内側に打設されたコン
クリートと一体化されて橋脚2の外壁部となるものであ
るため、PCa型枠20A,20Bの解体・撤去作業を
伴わない。また、PCa型枠組立体20は地上で組み立
てられるため、仮設足場3は、橋脚施工位置の全周を取
り囲むように構築する必要がなく、例えば図示のよう
に、橋脚施工位置の片側に沿って構築するだけで良い。
しかもPCa型枠組立体20の内周には予め剪断補強筋
22が一体化されており、帯筋27等も組み込まれた状
態で設置されるため、高所での作業は主筋28の建て込
みだけであり、したがって危険を伴う高所作業が著しく
減少する。As described above, the PCa dam 21 (PC
Since the a-forms 20A and 20B) are integrated with the concrete cast therein and become the outer wall of the pier 2, the PCa-forms 20A and 20B do not need to be dismantled / removed. Further, since the PCa formwork assembly 20 is assembled on the ground, the temporary scaffold 3 does not need to be constructed so as to surround the entire circumference of the pier construction position. For example, as shown in the figure, the temporary scaffold 3 is constructed along one side of the pier construction position. Just do it.
In addition, the shear reinforcement 22 is integrated in the inner periphery of the PCa formwork assembly 20 in advance, and the stirrups 27 and the like are installed in a built-in state. And therefore dangerous work at height is significantly reduced.
【0021】上述の第一の実施形態では中実の橋脚を施
工する場合について説明したが、本発明の第二の実施形
態として、中空の橋脚を施工する場合について説明す
る。In the above-described first embodiment, a case where a solid pier is constructed has been described. However, as a second embodiment of the present invention, a case where a hollow pier is constructed will be described.
【0022】この実施形態においては、PCa型枠組立
体20は、図18に示すように、先の第一の実施形態と
同様のPCa型枠20A,20Bからなる外側枠20’
と、その内側に、横幅の異なる各一対のPCa型枠20
C,20Dからなる中空部形成用の内側枠20”を有す
る。PCa型枠20C,20Dは、第一の実施形態にお
いて説明したPCa型枠20A,20Bと基本的には同
様であって、例えばPCa型枠20Cは、図13の斜視
図にも示すように、コンクリート打設側となる外側面の
幅方向中央に1本のリブ21hが形成されたPCa堰板
21’と、このPCa堰板21’に前記リブ21hを貫
通した状態で取り付けられた多数の剪断補強筋22’
と、前記リブ21h及び前記外側面の左右両端に所定間
隔で埋設されたインサートボルト23’とを備えてい
る。また、PCa堰板21’には、鉄筋24’が格子状
に埋設され、あるいは引っ張り強度の大きい繊維等が混
入されている。In this embodiment, as shown in FIG. 18, a PCa formwork assembly 20 comprises an outer frame 20 'made of the same PCa formwork 20A, 20B as in the first embodiment.
And a pair of PCa molds 20 having different widths inside thereof.
C, 20D. The PCa molds 20C, 20D are basically the same as the PCa molds 20A, 20B described in the first embodiment. As shown in the perspective view of FIG. 13, the PCa formwork 20C includes a PCa dam plate 21 'having a single rib 21h formed at the center in the width direction of the outer surface serving as the concrete placing side, and a PCa dam plate. Numerous shear reinforcing bars 22 'attached to the 21' through the ribs 21h.
And insert bolts 23 'buried at predetermined intervals on both left and right ends of the rib 21h and the outer side surface. In the PCa dam plate 21 ', a reinforcing bar 24' is buried in a lattice shape, or fibers having high tensile strength are mixed.
【0023】リブ21hは、PCa型枠組立体20とし
ての組立状態において鉛直となる方向に延びており、し
たがってこれを直角に貫通した状態に取り付けられた剪
断補強筋22’は、前記組立状態において水平となる方
向に延びている。この剪断補強筋22’の両端は、内側
枠20”の角部に相当する前記PCa堰板21’の端部
内側に達しており、この部分が外側へ略J字形に屈曲さ
れることによって、結合部22a’が形成されている。The rib 21h extends in the vertical direction in the assembled state as the PCa formwork assembly 20. Therefore, the shear reinforcement 22 'attached to the rib 21h so as to penetrate it at right angles is horizontal in the assembled state. It extends in the direction as follows. Both ends of the shear reinforcement 22 'reach the inside of the end of the PCa dam plate 21' corresponding to the corner of the inner frame 20 ", and this portion is bent outward in a substantially J-shape. A coupling portion 22a 'is formed.
【0024】PCa型枠20Dは、その横幅が上述のP
Ca型枠20Cの横幅よりも大きく、2本のリブ21
i,21jが形成されており、その他は上記PCa型枠
20Cと同様の構造を有する。The width of the PCa mold 20D is the above-mentioned P
The width of the two ribs 21 is larger than the width of the Ca form 20C.
i, 21j are formed, and the others have the same structure as the PCa formwork 20C.
【0025】PCa型枠組立体20の組み立てに際して
は、まず地上で、図12の平面図に示すように各一対の
PCa型枠20C,20Dを配置し、隣接するPCa型
枠20C,20Dの端部同士を、図14及び図15に示
すようにL字形の複数の固定金具25’を介して略長方
形の枠状に連結することによって内側枠20”を組み立
てる。固定金具25’は、互いに直角をなして衝き合わ
される前記PCa型枠20C,20Dの端部に埋設され
たインサートボルト23’及びこれに螺合するナット2
3a’によって緊結される。この連結状態においては、
PCa型枠20C,20Dにおける剪断補強筋22’の
結合部22a’同士が互いに略U字形をなすように重な
り合い、この部分が後述する角部外周の主筋28bと結
合されるようになっている。When assembling the PCa mold assembly 20, first, a pair of PCa molds 20C and 20D are arranged on the ground as shown in the plan view of FIG. The inner frame 20 "is assembled by connecting them to each other in a substantially rectangular frame shape through a plurality of L-shaped fixing brackets 25 'as shown in FIGS. 14 and 15. The fixing brackets 25' are perpendicular to each other. Insert bolts 23 'embedded in the ends of the PCa molds 20C and 20D to be abutted against each other and a nut 2 screwed to the insert bolts 23'
It is tied by 3a '. In this connected state,
The joint portions 22a 'of the shear reinforcing bars 22' in the PCa frames 20C and 20D overlap each other so as to form a substantially U-shape, and this portion is joined to a main bar 28b on the outer periphery of a corner portion described later.
【0026】次に、PCa型枠20C,20Dからなる
内側枠20”の外側に、PCa型枠20A,20Bを配
置し、第一の実施形態の場合と同様、固定金具25を介
して長方形の枠状に連結することによって、外側枠2
0’を組み立てる。このとき、外側枠20’における横
幅の小さいPCa型枠20Aは内側枠20”における横
幅の小さいPCa型枠20Cと平行に、また、外側枠2
0’における横幅の大きいPCa型枠20Bは内側枠2
0”における横幅の大きいPCa型枠20Dと平行に配
置する。Next, PCa frames 20A and 20B are arranged outside the inner frame 20 "formed by the PCa frames 20C and 20D, and the rectangular shape is fixed via the fixing bracket 25 as in the first embodiment. By connecting in a frame shape, the outer frame 2
Assemble 0 '. At this time, the PCa mold 20A having a small width in the outer frame 20 'is parallel to the PCa mold 20C having a small width in the inner frame 20 "and the outer frame 2A.
The PCa mold 20B having a large width at 0 ′ is the inner frame 2.
It is arranged in parallel with the PCa mold 20D having a large width at 0 ".
【0027】上述のようにしてPCa型枠20A,20
Bからなる外側枠20’及びPCa型枠20C,20D
からなる内側枠20”の双方を組み立てたら、図16に
示すように、互いに対向するPCa型枠20AとPCa
型枠20Cとの間及びPCa型枠20BとPCa型枠2
0Dとの間をそれぞれセパレータ26’を介して拘束す
ることによって、前記外側枠20’と内側枠20”を互
いに連結する。また、PCa型枠20A,20Bにおけ
る剪断補強筋22とPCa型枠20C,20Dにおける
剪断補強筋22’間に架設するようにして帯筋27を配
筋する。As described above, the PCa molds 20A, 20A
B outside frame 20 'and PCa molds 20C, 20D
After assembling both of the inner frames 20 "made of PCa, as shown in FIG.
Between the mold 20C and the PCa mold 20B and the PCa mold 2
The outer frame 20 'and the inner frame 20 "are connected to each other by restricting the space between the outer frame 20' and the outer frame 20 'via a separator 26'. Also, the shear reinforcement 22 and the PCa frame 20C in the PCa frames 20A and 20B are connected. , 20D are arranged between the shear reinforcing bars 22 '.
【0028】前記セパレータ26’は、図17に示すよ
うに、ターンバックル部26cの両端に取付金具26d
を設けたものであって、第一の実施形態で用いたものよ
りも短尺である。すなわちこのセパレータ26’は、両
端の取付金具26dが、PCa型枠20A,20Bのリ
ブ21b,21e又は21fとPCa型枠20C,20
Dのリブ21h〜21jに、これら各リブに埋設された
インサートボルト23,23’及びこれに螺合するナッ
ト23a,23bで緊結されることによって、外側のP
Ca型枠20A,20Bと内側のPCa型枠20C,2
0Dとを橋絡して互いに支保するものである。As shown in FIG. 17, the separator 26 'is provided with mounting brackets 26d at both ends of the turnbuckle portion 26c.
, Which is shorter than that used in the first embodiment. That is, this separator 26 'is configured such that the mounting brackets 26d at both ends are connected to the ribs 21b, 21e or 21f of the PCa frames 20A, 20B and the PCa frames 20C, 20C.
D ribs 21h to 21j are tightened by insert bolts 23, 23 'embedded in these ribs and nuts 23a, 23b screwed to the ribs, so that the outer P
Ca formwork 20A, 20B and inner PCa formwork 20C, 2
OD is bridged and mutually supported.
【0029】上記のようにして二重長方形枠状に組まれ
たPCa型枠組立体20を、図1に示すように橋脚施工
位置へ第一リフト21 の施工高さまで設置したら、図1
8に示すように、前記PCa型枠組立体20のPCa型
枠20A,20Bからなる外側枠20’とPCa型枠2
0C,20Dからなる内側枠20”との間のコンクリー
ト打設空間Sに、所要数の主筋28を建て込む。これら
の主筋28は、図18に示すように、前記外側枠20’
の内周及び前記内側枠20”の外周に沿って一定間隔で
建て込まれる。そして、外側枠20’の隅部内周に建て
込まれる主筋28aは、互いに略U字形をなすように重
なり合った剪断補強筋22の結合部22aに通され、内
側枠20”の角部外周に建て込まれる主筋28bは、互
いに円をなすように重なり合った剪断補強筋22’の結
合部22a’に通され、これによって外側の剪断補強筋
22同士及び内側の剪断補強筋22’同士が主筋28a
又は28bを介して互いに略長方形状に連結された状態
となる。主筋28の建て込み終了後は、前記コンクリー
ト打設空間S内にコンクリートを打設し、第一リフト2
1 の施工が終わる。[0029] Once the PCa-type frame assembly 20 assembled in a double rectangular frame shape as described above, was placed the execution height of the first lift to the pier construction location 2 1 As shown in FIG. 1, FIG. 1
As shown in FIG. 8, an outer frame 20 'composed of PCa molds 20A and 20B of the PCa mold assembly 20 and a PCa mold 2
A required number of main reinforcing bars 28 are erected in the concrete placing space S between the inner frame 20 "and the inner frame 20" composed of the outer frames 20 ', as shown in FIG.
The main reinforcement 28a, which is erected at regular intervals along the inner periphery of the inner frame and the outer periphery of the inner frame 20 ". The main bars 28a erected at the inner periphery of the corners of the outer frame 20 'overlap each other so as to form a substantially U-shape. The main reinforcement 28b which is passed through the joint 22a of the reinforcement 22 and is built around the corner of the inner frame 20 "is passed through the joint 22a 'of the shear reinforcement 22' which overlaps in a circle with each other. The outer shear reinforcements 22 and the inner shear reinforcements 22 'are connected by the main reinforcement 28a.
Or, they are connected to each other in a substantially rectangular shape via 28b. After the main bars 28 have been built, concrete is poured into the concrete placing space S, and the first lift 2
The construction of 1 is completed.
【0030】第一リフト21 の施工終了後は、直ちに第
二リフト22 の施工を開始し、上述と同様の一連の作業
を繰り返すことによって、中空の橋脚が所定の高さまで
順次施工されて行く。この実施形態においては、外側枠
20’におけるPCa型枠20A,20BのPCa堰板
21は、その内側面が経時的に硬化して行く現場打ちコ
ンクリートと一体接合状態となることによって橋脚2の
外壁面を構成し、内側枠20”におけるPCa型枠20
C,20DのPCa堰板21’は、その外側面が経時的
に硬化して行く現場打ちコンクリートと一体接合状態と
なることによって橋脚2の中空部壁面を構成する。[0030] The first lift 2 1 after construction completion immediately starts second lift 2 2 construction, by repeating the same series of operations as described above, are successively construction hollow piers to a predetermined height go. In this embodiment, the PCa dams 21 of the PCa molds 20A and 20B in the outer frame 20 'are integrated with the cast-in-place concrete whose inner surface hardens with time, so that the outer surface of the pier 2 is joined. PCa form 20 in inner frame 20 "which constitutes the wall
The PCa dam 21 ′ of C and 20D forms the hollow portion wall surface of the pier 2 by being integrally joined with the cast-in-place concrete whose outer surface hardens with time.
【0031】なお、本発明は、図示の実施形態によって
限定的に解釈されるものではない。例えば、PCa堰板
21,21’におけるリブの本数は、橋脚の断面積や形
状、現場打ちコンクリートの打設高さ、コンクリート温
度、打設速度、その他の設計条件に応じて適宜に決定さ
れるものであり、主筋28の建て込み位置や帯筋27の
配置等も前記諸条件によって適宜に決定される。また、
橋脚の外壁面となるPCa型枠20A,20BのPCa
堰板21の外側面には、工場での成形過程で適当な浮き
出し模様等を形成しておくことによって、橋脚の美観を
向上させることができる。The present invention is not construed as being limited to the illustrated embodiment. For example, the number of ribs in the PCa dams 21 and 21 'is appropriately determined according to the cross-sectional area and shape of the pier, the casting height of the cast-in-place concrete, the concrete temperature, the casting speed, and other design conditions. The position at which the main bar 28 is laid and the arrangement of the band bars 27 are appropriately determined according to the above-mentioned conditions. Also,
PCa of PCa formwork 20A, 20B to be the outer wall surface of pier
By forming an appropriate raised pattern or the like on the outer surface of the weir plate 21 during the molding process at the factory, the appearance of the pier can be improved.
【0032】[0032]
【発明の効果】本発明によると、次のような効果が実現
される。 (1) 現場打ちコンクリートと一体化されて橋脚の壁面部
となるPCa型枠を使用することによって、型枠解体や
撤去作業が不要となる。 (2) 現場打ちコンクリートと一体化されて橋脚の壁面部
となるPCa型枠を使用することによって、精度良く施
工することができる。 (3) PCa型枠は剛性の高いものとすることができるの
で、コンクリート打設時の側圧に対抗するために設ける
セパレータの数を減少させ、型枠の組み立てを容易に行
うことができる。 (4) PCa型枠によるPCa型枠組立体の組立作業を地
上で行い、しかもこのPCa型枠組立体は、セパレータ
や、剪断補強筋及び帯筋等が組み込まれた状態で橋脚施
工空間へ設置されるため、高所作業が著しく減少し、安
全性が向上すると共に、仮設足場も縮小することができ
る。 (5) 上記(1)(3)(4) の理由から、現場での省力化・省人
化が可能であり、かつ工期を著しく短縮することができ
る。According to the present invention, the following effects are realized. (1) The use of PCa formwork that is integrated with cast-in-place concrete and becomes the wall of the pier eliminates the need to dismantle and remove the formwork. (2) By using a PCa formwork which is integrated with cast-in-place concrete and serves as a wall portion of a pier, construction can be performed with high accuracy. (3) Since the PCa form can be made to have high rigidity, the number of separators provided to counter lateral pressure at the time of placing concrete can be reduced, and the form can be easily assembled. (4) PCa formwork assembly work using the PCa formwork is performed on the ground, and the PCa formwork assembly is installed in the pier construction space with the separator, the shear reinforcement, the band reinforcement, and the like incorporated therein. Therefore, work at height can be significantly reduced, safety can be improved, and the temporary scaffold can be reduced. (5) For the reasons (1), (3), and (4) above, labor and labor can be saved at the site, and the construction period can be significantly reduced.
【図1】本発明の第一の実施形態において、基礎部の上
に、第一リフトの施工のためのPCa型枠組立体及び仮
設足場を組み立てる過程を示す説明図である。FIG. 1 is an explanatory view showing a process of assembling a PCa formwork assembly and a temporary scaffold for construction of a first lift on a foundation in the first embodiment of the present invention.
【図2】上記第一の実施形態におけるPCa型枠の連結
過程を示す平面図である。FIG. 2 is a plan view showing a connecting process of a PCa formwork in the first embodiment.
【図3】上記PCa型枠を示す斜視図である。FIG. 3 is a perspective view showing the PCa mold.
【図4】上記第一の実施形態におけるPCa型枠の連結
状態を示す平面図である。FIG. 4 is a plan view showing a connected state of the PCa formwork in the first embodiment.
【図5】上記PCa型枠の連結構造を示す説明図であ
る。FIG. 5 is an explanatory view showing a connection structure of the PCa formwork.
【図6】上記第一の実施形態におけるPCa型枠組立体
の組立完了状態を示す平面図である。FIG. 6 is a plan view showing an assembled state of the PCa mold assembly according to the first embodiment.
【図7】セパレータによる上記PCa型枠組立体の支保
構造を示す説明図である。FIG. 7 is an explanatory view showing a support structure of the PCa form assembly by a separator.
【図8】上記第一の実施形態において、設置したPCa
型枠組立体に主筋を建て込む過程を示す説明図である。FIG. 8 shows the PCa installed in the first embodiment.
It is explanatory drawing which shows the process which builds a main reinforcement in a formwork assembly.
【図9】上記PCa型枠組立体に主筋を建て込んだ状態
を示す平面図である。FIG. 9 is a plan view showing a state in which main reinforcing bars are erected in the PCa mold assembly.
【図10】上記第一の実施形態において、第二リフトの
施工のためのPCa型枠組立体及び仮設足場を組み立て
る過程を示す説明図である。FIG. 10 is an explanatory diagram showing a process of assembling a PCa formwork assembly and a temporary scaffold for construction of a second lift in the first embodiment.
【図11】上記第一の実施形態による橋脚の施工完了状
態を示す説明図である。FIG. 11 is an explanatory diagram showing a completed construction state of the pier according to the first embodiment.
【図12】本発明の第二の実施形態において、PCa型
枠を連結してPCa型枠組立体の内側枠を形成する過程
を示す平面図である。FIG. 12 is a plan view showing a process of connecting PCa molds to form an inner frame of a PCa mold assembly in the second embodiment of the present invention.
【図13】上記内側枠として用いるPCa型枠を示す斜
視図である。FIG. 13 is a perspective view showing a PCa mold used as the inner frame.
【図14】上記内側枠の連結部を拡大して示す説明図で
ある。FIG. 14 is an explanatory diagram showing a connection portion of the inner frame in an enlarged manner.
【図15】上記PCa型枠組立体の内側枠及び外側枠の
配置状態を示す平面図である。FIG. 15 is a plan view showing an arrangement state of an inner frame and an outer frame of the PCa mold assembly.
【図16】上記第二の実施形態におけるPCa型枠組立
体の組立完了状態を示す平面図である。FIG. 16 is a plan view showing an assembled state of the PCa mold assembly in the second embodiment.
【図17】セパレータによる上記PCa型枠組立体の内
側枠と外側枠の支保構造を示す説明図である。FIG. 17 is an explanatory view showing a support structure of the inner frame and the outer frame of the PCa frame assembly by a separator.
【図18】上記PCa型枠組立体に主筋を建て込んだ状
態を示す平面図である。FIG. 18 is a plan view showing a state where main bars are erected in the PCa formwork assembly.
【図19】従来技術において、基礎部の上に、第一リフ
トを施工している過程を示す説明図である。FIG. 19 is an explanatory view showing a process of constructing a first lift on a foundation in a conventional technique.
【図20】従来技術において、第二リフトの配筋過程を
示す説明図である。FIG. 20 is an explanatory view showing a bar arrangement process of a second lift in a conventional technique.
【図21】従来技術において、第二リフトの型枠施工状
態を示す説明図である。FIG. 21 is an explanatory view showing a state in which a formwork of a second lift is constructed in a conventional technique.
【図22】従来技術による橋脚の施工完了状態を示す説
明図である。FIG. 22 is an explanatory view showing a completed state of construction of a bridge pier according to a conventional technique.
2 橋脚 20 PCa型枠組立体 20A〜20D PCa型枠 21 PCa堰板 21a〜21k リブ 22,22’ 剪断補強筋 22a,22a’ 結合部 26 セパレータ 27 帯筋 28,28’ 主筋 2 Bridge Pier 20 PCa Formwork Assembly 20A-20D PCa Formwork 21 PCa Weir Plate 21a-21k Rib 22, 22 'Shear Reinforcement 22a, 22a' Joint 26 Separator 27 Band 28, 28 'Main Bar
フロントページの続き (72)発明者 平野 勝識 東京都渋谷区千駄ヶ谷四丁目6番15号 株 式会社フジタ内Continued on the front page (72) Inventor Masanori Hirano 4-6-115 Sendagaya, Shibuya-ku, Tokyo Inside Fujita Co., Ltd.
Claims (4)
と、 このPCa堰板のコンクリート打設側の面から離れた位
置を左右に延在された状態に取り付けられた複数の剪断
補強筋と、 前記コンクリート打設側の面に配設されたセパレータ取
付部とを備え、 前記PCa堰板の左右端部近傍に達する前記剪断補強筋
の両端に橋脚主筋への結合部が形成されていることを特
徴とするPCa型枠。1. A PCa weir plate formed of concrete, a plurality of shear reinforcing bars attached to the PCa weir plate at a position distant from a surface on a concrete casting side and extending in a left-right direction. A separator mounting portion disposed on a surface on the concrete casting side, wherein joint portions to pier main bars are formed at both ends of the shear reinforcement reaching near the left and right ends of the PCa dam plate. PCa formwork.
成された所要数のリブを介して取り付けられ、 セパレータ取付部がこのリブに形成されたことを特徴と
するPCa型枠。2. The method according to claim 1, wherein the shear reinforcement is attached via a required number of ribs formed on the surface of the PCa dam plate on the concrete casting side, and the separator attachment portion is formed on the ribs. PCa formwork characterized by the above-mentioned.
上で方形枠状に配置して互いに衝き合わされた前記各P
Ca型枠の端部同士を連結すると共に互いに対向する前
記PCa型枠同士をセパレータを用いて締結することに
よりPCa型枠組立体を組み立てる工程と、 橋脚施工位置に前記PCa型枠組立体を揚重・設置する
工程と、 設置された前記PCa型枠組立体の内側空間に所要数の
主筋を組み込むと共に一部の主筋を前記各PCa型枠と
一体の剪断補強筋の両端結合部に結合する工程と、 前記PCa型枠組立体の内側空間にコンクリートを打設
する工程と、からなることを特徴とするPCa型枠を用
いた橋脚の施工方法。3. The PCa formwork according to claim 1 or 2, wherein the PCa formwork is arranged in a rectangular frame shape on the ground and abuts against each other.
Assembling a PCa formwork assembly by connecting ends of the Ca formwork with each other and fastening the PCa formworks facing each other using a separator; and lifting and lifting the PCa formwork assembly at a pier construction position. Installing, installing a required number of main reinforcements in the inner space of the installed PCa formwork assembly, and coupling a part of the main reinforcements to both end joints of the shear reinforcement integrated with each PCa formwork; Casting concrete into the inner space of the PCa formwork assembly. A method for constructing a pier using a PCa formwork, the method comprising:
の帯筋を配設することを特徴とするPCa型枠を用いた
橋脚の施工方法。4. The method for constructing a pier using a PCa formwork according to claim 3, wherein a required number of straps are arranged on the PCa formwork assembly when assembling the PCa formwork assembly.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP27289296A JP3841498B2 (en) | 1996-09-25 | 1996-09-25 | PCa formwork and pier construction method using this PCa formwork |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP27289296A JP3841498B2 (en) | 1996-09-25 | 1996-09-25 | PCa formwork and pier construction method using this PCa formwork |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH10102423A true JPH10102423A (en) | 1998-04-21 |
JP3841498B2 JP3841498B2 (en) | 2006-11-01 |
Family
ID=17520220
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP27289296A Expired - Fee Related JP3841498B2 (en) | 1996-09-25 | 1996-09-25 | PCa formwork and pier construction method using this PCa formwork |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3841498B2 (en) |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2004176361A (en) * | 2002-11-26 | 2004-06-24 | Tokyu Construction Co Ltd | Repair method of damaged concrete construction |
CN106545083A (en) * | 2016-12-27 | 2017-03-29 | 阿博建材(昆山)有限公司 | A kind of building frame |
JP2018135688A (en) * | 2017-02-22 | 2018-08-30 | 三井住友建設株式会社 | Bridge pier and construction method thereof |
CN109322248A (en) * | 2018-10-12 | 2019-02-12 | 中铁隧道集团二处有限公司 | A kind of Bridge Piers bar reinforcement positioning device and installation method |
JP2019060236A (en) * | 2019-01-25 | 2019-04-18 | 鹿島建設株式会社 | Concrete structure construction method, concrete structure |
JP2022074883A (en) * | 2020-11-05 | 2022-05-18 | 鹿島建設株式会社 | Panel unit and method of constructing structure |
KR20230052741A (en) * | 2021-10-13 | 2023-04-20 | 송성민 | Precast inner mould and precast structure using the same |
-
1996
- 1996-09-25 JP JP27289296A patent/JP3841498B2/en not_active Expired - Fee Related
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2004176361A (en) * | 2002-11-26 | 2004-06-24 | Tokyu Construction Co Ltd | Repair method of damaged concrete construction |
CN106545083A (en) * | 2016-12-27 | 2017-03-29 | 阿博建材(昆山)有限公司 | A kind of building frame |
JP2018135688A (en) * | 2017-02-22 | 2018-08-30 | 三井住友建設株式会社 | Bridge pier and construction method thereof |
CN109322248A (en) * | 2018-10-12 | 2019-02-12 | 中铁隧道集团二处有限公司 | A kind of Bridge Piers bar reinforcement positioning device and installation method |
JP2019060236A (en) * | 2019-01-25 | 2019-04-18 | 鹿島建設株式会社 | Concrete structure construction method, concrete structure |
JP2022074883A (en) * | 2020-11-05 | 2022-05-18 | 鹿島建設株式会社 | Panel unit and method of constructing structure |
KR20230052741A (en) * | 2021-10-13 | 2023-04-20 | 송성민 | Precast inner mould and precast structure using the same |
Also Published As
Publication number | Publication date |
---|---|
JP3841498B2 (en) | 2006-11-01 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP5620344B2 (en) | Construction method of pier | |
JPH1030212A (en) | Reinforced concrete structure and its construction method | |
JPH10102423A (en) | Pca form and construction method of pier using the same pca form | |
JP4136049B2 (en) | Concrete pier construction method | |
JPH09310405A (en) | Reinforced concrete column and precast form | |
JP2586224B2 (en) | Building method using precast concrete formwork | |
JP3945668B2 (en) | Construction method of concrete pier | |
KR20210004289A (en) | Transfer Structure Construction Method Using U-shaped Steel Girder | |
JP3835716B2 (en) | Reinforced concrete pier construction method | |
JP3973577B2 (en) | Bridge, bridge structure and bridge construction method | |
JP3137448B2 (en) | Construction method of concrete main tower | |
JPH1129910A (en) | Method for constructing concrete pier | |
JP3830055B2 (en) | Concrete formwork and method for constructing concrete structure using the concrete formwork | |
KR101078292B1 (en) | Concrete slab mold assembly and method for constructing slab | |
JPH08100464A (en) | Joint structure and work execution method for structure using it | |
JP2000160687A (en) | Construction method for composite structure and precast concrete column | |
JPH084196A (en) | Panel for building | |
JP3824242B2 (en) | Viaduct-free support construction method | |
JP2600531B2 (en) | Foundation structure for steel column and its construction method | |
JPH0881918A (en) | Pipe and construction method thereof | |
JPH10196027A (en) | Deck panel for concrete form | |
JPH05239810A (en) | Constructing method for reinforced concrete arch bridge | |
JPH1121860A (en) | Construction method for wall-form concrete structure | |
JP2578671B2 (en) | Column and beam construction method | |
JP3312945B2 (en) | Construction method of concrete structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20060223 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20060322 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20060516 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Effective date: 20060712 Free format text: JAPANESE INTERMEDIATE CODE: A01 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20060808 |
|
R150 | Certificate of patent (=grant) or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090818 Year of fee payment: 3 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100818 Year of fee payment: 4 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110818 Year of fee payment: 5 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110818 Year of fee payment: 5 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Year of fee payment: 6 Free format text: PAYMENT UNTIL: 20120818 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120818 Year of fee payment: 6 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130818 Year of fee payment: 7 |
|
LAPS | Cancellation because of no payment of annual fees |