Nothing Special   »   [go: up one dir, main page]

JPH0412111Y2 - - Google Patents

Info

Publication number
JPH0412111Y2
JPH0412111Y2 JP10564586U JP10564586U JPH0412111Y2 JP H0412111 Y2 JPH0412111 Y2 JP H0412111Y2 JP 10564586 U JP10564586 U JP 10564586U JP 10564586 U JP10564586 U JP 10564586U JP H0412111 Y2 JPH0412111 Y2 JP H0412111Y2
Authority
JP
Japan
Prior art keywords
concrete
block body
reinforcing bars
hole
foundation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP10564586U
Other languages
Japanese (ja)
Other versions
JPS6314642U (en
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed filed Critical
Priority to JP10564586U priority Critical patent/JPH0412111Y2/ja
Publication of JPS6314642U publication Critical patent/JPS6314642U/ja
Application granted granted Critical
Publication of JPH0412111Y2 publication Critical patent/JPH0412111Y2/ja
Expired legal-status Critical Current

Links

Landscapes

  • Foundations (AREA)

Description

【考案の詳細な説明】 産業上の利用分野 本考案は建造物のコンクリート造独立基礎に関
し、とくにつなぎ梁(地中梁)との接続に改善を
はかつたプレキヤスト・コンクリート造の基礎に
関するものである。
[Detailed explanation of the invention] Industrial application field This invention relates to independent concrete foundations for buildings, and in particular to precast concrete foundations with improved connection to connecting beams (underground beams). be.

従来の技術 従来から、通常のコンクリート基礎はつなぎ梁
と、要すれば底盤と一体に現場打ちコンクリート
によつて構築されていた。即ち、地表から根切り
を行い、捨てコンクリートの地業を行い、型枠を
建て込んで鉄筋を配置し、つなぎ梁や底盤と同時
にコンクリートを打設する。コンクリートの硬化
後に型枠を脱型し埋戻しを行つて上方への工程を
進める。
BACKGROUND OF THE INVENTION Traditionally, conventional concrete foundations have been constructed of cast-in-place concrete with tie beams and, if necessary, a base plate. In other words, roots are cut from the ground surface, concrete is laid, forms are erected, reinforcing bars are placed, and concrete is poured at the same time as the connecting beams and base. After the concrete has hardened, the formwork is removed and backfilled to proceed with the upward process.

一方、現今のコンクリート工事では各主要構造
部ごとにできるだけプレキヤスト・コンクリート
を用いることによつてプレハブ化のメリツトを得
るようにしており、部材の規格化によつて型枠の
効率をあげ、特定の製造場所において精度を向上
させ、作業員の慣熟度によつて能率を挙げてい
る。一般に最大のメリツトは工期の短縮にあると
いわれており、工事現場での設置、組立て、接続
のための搬入までの諸工程はすべて他工程と平行
した日程で行われるから、全工期での短縮に大き
く寄与する。材料の搬入は製品の形で行われるか
ら実質的には相違はないものであり、大型で重量
のあるコンクリート部材の揚重施設を必要とする
点も工事の機械化の傾向で吸収される。
On the other hand, in current concrete construction, precast concrete is used as much as possible for each major structural part to obtain the benefits of prefabrication, and the efficiency of formwork is increased by standardizing parts, and specific Efficiency is improved by improving precision at the manufacturing site and by increasing the familiarity of workers. Generally speaking, the biggest advantage is said to be shortening the construction period. All the processes from installation at the construction site, assembly, and delivery for connection are carried out on parallel schedules with other processes, so the overall construction period is shortened. greatly contributes to Materials are brought in in the form of products, so there is virtually no difference, and the need for lifting facilities for large and heavy concrete members will be absorbed by the trend toward mechanization of construction work.

しかし、基礎の設計条件は個々に相異があり、
主として規格化の面でプレハブ化になじまないも
のであるため、コンクリート基礎をプレキヤス
ト・コンクリートのブロツク体にすることはあま
り行われず、つなぎ梁によつて柱脚のモーメント
を処理する必要のないような、比較的軽微な構造
物以外には採用されていない。
However, the design conditions for each foundation are different.
Mainly because it is not compatible with prefabrication in terms of standardization, concrete foundations are not often made into precast concrete blocks, and concrete foundations are not often made into precast concrete blocks. , has not been adopted for anything other than relatively light structures.

考案が解決しようとする問題点 基礎を現場打ちコンクリートで構築するときの
問題点は、主として鉄筋の配筋と型枠に関するも
のである。基礎は、杭、柱、つなぎ梁の接合点で
あり、これに基礎自体の鉄筋が加わるから精度よ
い配筋には手間がかかる。これらの問題をプレキ
ヤストによつて解決しようとするときには、基礎
と各部材との接続、一体化を解決しなければなら
ない。これらはすべて精度のよい設置と、鉄筋の
接合にかかることであつて、基礎に限らず、すべ
てのペレキヤスト・コンクリート造部材の問題で
ある。いいかえれば、既に硬化したコンクリート
同志、または既設コンクリートと後打ちコンクリ
ートとの接合に一体化がはかられなければならな
い、ということである。このために、同規模の基
礎を多数要するような条件のもとでも、この接続
手段が障害となつて、基礎のプレハブ化は一向に
促進されていないのが現状である。
Problems that the invention aims to solve Problems when constructing a foundation with cast-in-place concrete mainly concern the arrangement of reinforcing bars and formwork. The foundation is the joint point of piles, columns, and connecting beams, and since the foundation's own reinforcing bars are added to this, it takes time to accurately arrange the reinforcement. When trying to solve these problems by precasting, it is necessary to solve the problem of connection and integration between the foundation and each member. These are all issues related to accurate installation and reinforcing steel connections, and are not limited to foundations, but all Pelecast concrete construction components. In other words, integration must be achieved between already hardened concrete or between existing concrete and post-cast concrete. For this reason, even under conditions where a large number of foundations of the same size are required, this connection means becomes an obstacle, and the use of prefabricated foundations is currently not promoted at all.

問題点を解決するための手段 本考案は上記のような現状に鑑みて開発された
ものであつて、支持杭、柱、つなぎ梁との垂直、
水平方向の接合用の手段を備えてコンクリート基
礎をプレキヤスト・コンクリートによつて構築す
ることを要旨としている。そしてそのような意図
を達成するために、つなぎ梁の方向に適合させて
接合用の鉄筋を具備するとともに、杭と柱との接
合を現場打コンクリートによつて行うために中央
部に上下の貫通孔を設けたことを特徴とする基礎
ブロツク体の考案を完成させたものである。これ
によつて基礎のプレハブ化が、接合手段を備えた
ブロツクとして達成されている。
Means for Solving the Problems The present invention was developed in view of the above-mentioned current situation.
The main idea is to construct a concrete foundation using precast concrete with means for horizontal connections. In order to achieve this intention, reinforcing bars were installed to match the direction of the connecting beams, and upper and lower penetrations were installed in the center to connect the piles and columns using cast-in-place concrete. This completes the idea of a basic block body characterized by the provision of holes. This allows the foundation to be prefabricated as a block equipped with joining means.

実施例 本考案のプレキヤスト・コンクリート基礎ブロ
ツクを図面に示す実施例にもとづいて説明する。
Embodiment The precast concrete foundation block of the present invention will be explained based on the embodiment shown in the drawings.

第1図において1は基礎の全体を示し、2はプ
レキヤスト・コンクリートによつて形成される基
礎用のブロツク体である。このブロツク体2は1
図の平面で見るように概略正方形に形成され、そ
の対角線をブロツク体2に接続されるつなぎ梁
(地中梁)3の方向に合致させて菱形をしており、
その隅角部をつなぎ梁3の幅に合わせて面取りし
て接合面4としてある。ブロツク体2の高さ(厚
さ)は2図に見るように、つなぎ梁3の高さと等
しくしてある。このブロツク体2は中心部に上下
に貫通する円形の孔を設けて貫通孔5としてあ
り、この内径は杭6の外周との間に10cmの間隔を
有するようにしてあり、7は杭6の上方に接続さ
れ、この基礎1によつて支持されることになる柱
を示している。8はブロツク体2とつなぎ梁との
接続用の鉄筋であつて、ブロツク体2を水平に貫
通しており、内端は貫通孔5内に臨み、外端は接
合面4より延長して突出させてある。9は貫通孔
5内に後打ちで打設されるコンクリートである。
In FIG. 1, numeral 1 indicates the entire foundation, and numeral 2 represents a block body for the foundation made of precast concrete. This block 2 is 1
It is formed into a roughly square shape as seen from the plane of the figure, and its diagonal line matches the direction of the connecting beam (underground beam) 3 connected to the block body 2 to form a diamond shape.
The corner portion is chamfered to match the width of the connecting beam 3 to form a joint surface 4. As shown in Figure 2, the height (thickness) of the block body 2 is made equal to the height of the connecting beam 3. This block body 2 has a circular hole in the center that passes through it vertically as a through hole 5, and the inner diameter of this hole is such that there is a distance of 10 cm from the outer circumference of the pile 6. It shows the column connected above and which will be supported by this foundation 1. Reference numeral 8 denotes a reinforcing bar for connecting the block body 2 and the connecting beam, which passes through the block body 2 horizontally, the inner end facing into the through hole 5, and the outer end extending and protruding from the joint surface 4. I have let you. 9 is concrete placed in the through hole 5 by post-casting.

上記の構成を第2図1,2及び第3図によつて
さらに詳細に説明する。第2図1はブロツク体2
の上部平面図、第2図2は同じく下部の平面図、
第3図は垂直断面図を示し、いずれも対称となる
部分を省略してある。
The above configuration will be explained in more detail with reference to FIGS. 1, 2 and 3. Figure 2 1 is block body 2
FIG. 2 is a plan view of the lower part,
FIG. 3 shows a vertical sectional view, with symmetrical parts omitted in both cases.

ブロツク体2は貫通孔5の周囲に補強鉄筋21
を有し、変形環状体であることから、上下に主筋
22とスタラツプ23を有しており、これとは別
に基礎のベース筋24を直角方向に配筋して外端
を立ち上げてある。また、ブロツク体2の上面に
は全体の揚重用の吊りフツク25が4個設けられ
る。
The block body 2 has reinforcing steel bars 21 around the through hole 5.
Since it is a deformed annular body, it has main reinforcing bars 22 and pillars 23 on the upper and lower sides, and in addition to these, base reinforcing bars 24 of the foundation are arranged in a right angle direction to raise the outer end. Furthermore, four hanging hooks 25 are provided on the upper surface of the block body 2 for lifting the whole block.

次に貫通孔5の内面には円周方向に複数段の凹
溝51を形成してあり、後打ちコンクリート9と
ブロツク体2との接合用キー溝となつている。こ
の貫通孔5に1端を臨ませて接続鉄筋8が設けら
れ、81はつなぎ梁3の上端筋31との接続用、
82は下端筋32との接続用であり、接続鉄筋8
1の内端同志は接続鉄筋83を介して、スリーブ
を用いた機械的圧縮継手84によつて接続されて
おり、下方の接続鉄筋82は内端の接続を省略し
て通し材になつており、前記したベース筋24と
同一面に組立ててある。
Next, a plurality of concave grooves 51 are formed in the inner surface of the through hole 5 in the circumferential direction, and serve as key grooves for joining the post-cast concrete 9 and the block body 2. A connecting reinforcing bar 8 is provided with one end facing the through hole 5, and 81 is for connection with the upper end reinforcing bar 31 of the connecting beam 3;
82 is for connection with the lower end reinforcement 32, and the connecting reinforcement 8
The inner ends of 1 are connected via a connecting reinforcing bar 83 by a mechanical compression joint 84 using a sleeve, and the lower connecting reinforcing bar 82 is made into a through material by omitting the connection at the inner end. , are assembled on the same plane as the base reinforcement 24 described above.

作 用 本考案の基礎ブロツクの作用をその施工方法に
基いて工程順に説明する。
Function The function of the basic block of the present invention will be explained step by step based on its construction method.

基礎1は一般に地表から根切りした位置に設置
される。そこで、その他盤面において杭6を構築
する。杭6は作業環境上一般に場所打ちコンクリ
ート杭が選ばれ、杭頭高さが定められ、その上方
には接続定着用の鉄筋61を所要長突出させてあ
り、杭上面はベースモルタル62によつて水平平
坦に仕上げられる。ついで、ブロツク体2の下面
を支持する捨てコンクリート11を栗石地業とと
もに完成させ上面高さを調整し、芯出しをする。
つなぎ梁3の下面の地業11もこれに前後して完
成させるのがよい。
The foundation 1 is generally installed at a position cut off from the ground surface. Therefore, piles 6 are constructed on other board surfaces. Cast-in-place concrete piles are generally selected as the piles 6 due to the working environment, the height of the pile head is determined, and a required length of reinforcing bars 61 for connecting and anchoring are protruded above the piles, and the top surface of the piles is covered with base mortar 62. Finished horizontally and flatly. Next, the sacrificial concrete 11 supporting the lower surface of the block body 2 is completed together with Kuriishijiyo, the height of the upper surface is adjusted, and centering is performed.
It is best to complete the ground work 11 on the lower surface of the connecting beam 3 around this time.

次に吊りフツク25を使用してブロツク体2を
吊り上げ、杭6の鉄筋61を嵌挿させながら吊り
おろして据付ける。貫通孔5は杭6の外径に対し
て余猶があり、杭6に多少の偏心があつても精度
よく設置することができる。また、下方の接続鉄
筋82は杭6の頂面より高く位置を定められ、設
置に際しては杭鉄筋61をかわすだけでよい。次
に、柱7の鉄筋71を先組みしたものを貫通孔5
内で杭6上に建込む。接続鉄筋81と内側の接続
鉄筋83とは柱筋71の建込み後に接続され、外
方においては接続鉄筋81,82の外端につなぎ
梁3の上下の主筋31,32を接続する。この接
合はスリーブ84を挿通して機械圧縮によつて行
う。
Next, the block body 2 is hoisted up using the hoisting hook 25, and the reinforcing bars 61 of the piles 6 are inserted into the block body 2, and the block body 2 is hoisted down and installed. The through hole 5 has a margin for the outer diameter of the pile 6, and even if the pile 6 is slightly eccentric, it can be installed with high accuracy. Further, the lower connecting reinforcing bar 82 is positioned higher than the top surface of the pile 6, and it is only necessary to dodge the pile reinforcing bar 61 during installation. Next, the reinforcing bars 71 of the pillars 7 are assembled into the through holes 5.
Built on pile 6 inside. The connecting reinforcing bars 81 and the inner connecting reinforcing bars 83 are connected after the column reinforcements 71 are erected, and the upper and lower main reinforcing bars 31, 32 of the connecting beam 3 are connected to the outer ends of the connecting reinforcing bars 81, 82 on the outside. This joining is performed by inserting the sleeve 84 and mechanical compression.

柱7の鉄筋71は下端にベース・プレートを有
してモルタル62上に据付けられ、杭へのアンカ
ーは後打ちコンクリート9を介して杭鉄筋61に
よつて行われる。
The reinforcing bars 71 of the columns 7 have base plates at their lower ends and are installed on the mortar 62, and anchoring to the piles is done by the pile reinforcing bars 61 through post-cast concrete 9.

高さの高いつなぎ梁3が腹筋33を有するとき
には、ブロツク体2の接合面4に予めインサート
34を埋設しておいて腹筋33の端部を挿入して
固定する。つなぎ梁3の鉄筋は先組みしておい
て、上下鉄筋31,32をスリーブ84によつて
接続後コンクリートを打設する。
When the connecting beam 3 having a high height has an abdominal muscle 33, an insert 34 is buried in the joint surface 4 of the block body 2 in advance, and the end of the abdominal muscle 33 is inserted and fixed. The reinforcing bars of the connecting beam 3 are assembled in advance, and after the upper and lower reinforcing bars 31 and 32 are connected by sleeves 84, concrete is poured.

柱7が鉄骨造のときには柱脚部のみを杭6上に
建込み、前記と同様にしてブロツク体2を貫通孔
5によつて嵌挿する。
When the pillar 7 is of steel construction, only the pillar base is built on the pile 6, and the block body 2 is inserted through the through hole 5 in the same manner as described above.

上記によつて杭6と柱7とは現場打コンクリー
ト9によつて接続され、同時にブロツク体2とも
一体化され、凹溝51内のコンクリート9はせん
断キーを形成する。
As described above, the pile 6 and the column 7 are connected by the cast-in-place concrete 9, and are also integrated with the block body 2 at the same time, and the concrete 9 in the groove 51 forms a shear key.

つなぎ梁3の主筋31,32は接続鉄筋8によ
つてブロツク体2を貫通して接続され、従つて配
筋の精度は万全であり、しかも杭筋61、柱筋7
1と錯綜することはない。
The main reinforcing bars 31 and 32 of the connecting beam 3 are connected by the connecting reinforcing bars 8 through the block body 2, so that the precision of the reinforcement arrangement is perfect, and the pile reinforcing bars 61 and the column reinforcing bars 7
There is no confusion with 1.

ブロツク体2は接合面4,4の間を斜辺で結ん
でおり、菱形に形成してあるから、その外方の三
角形部分をそぎおとして軽量化をはかつてある
(第2図1)。
Since the block body 2 is formed into a diamond shape with the oblique side connecting the joint surfaces 4, 4, the weight of the block body 2 can be reduced by cutting off the triangular part on the outside (Fig. 2, 1).

考案の効果 本考案のブロツク体は上記のように構成され、
使用施工されるので、ブロツク体をプレキヤス
ト・コンクリートで形成したプレハブ化のメリツ
トが全面的に発揮され、型枠のコストと精度の確
保ができ、同時に工期が短縮される。また、中央
部に貫通孔を形成しているので、この部分へのコ
ンクリート打設によつてプレハブ化に伴う接続の
問題も同時に解決されている。この貫通孔の構成
はまた大形のピレキヤスト・コンクリートのブロ
ツク体の設置精度に有利であるばかりでなく、菱
形形成とともに全体の重量を軽減させており、そ
のための揚重設備も特別大きくならない。この貫
通孔部分にはブロツク体とは別個に、比較的小量
な部分に現場打ちコンクリートを必要とするが、
このコンクリートはつなぎ梁と同時に打設するこ
とができるから別段取を必要としない。
Effects of the invention The block body of the invention is constructed as described above,
Since it is used for construction, the advantages of prefabrication, in which the block body is made of precast concrete, are fully utilized, and the cost and accuracy of the formwork can be ensured, while at the same time the construction period is shortened. Additionally, since a through hole is formed in the center, the connection problems associated with prefabrication are also solved by pouring concrete into this area. This arrangement of through-holes is also advantageous not only for the precision of installation of large blocks of pyrecast concrete, but also, together with the diamond-shaped formation, reduces the overall weight, and the lifting equipment for this does not need to be particularly large. This through-hole area requires a relatively small amount of cast-in-place concrete, separate from the block body.
This concrete can be cast at the same time as the connecting beams, so no separate setup is required.

【図面の簡単な説明】[Brief explanation of the drawing]

図面は本考案の実施例を示し、第1図は基礎の
全体を示し1図は平面図、2図は断面図である。
第2図、第3図はブロツク体の詳細図であつて、
第2図1図、2図はそれぞれ上面と下面の平面
図、第3図は断面図を示す。 1……基礎、2……ブロツク体、3……つなぎ
梁、4……接合面、5……貫通孔、6……杭、7
……柱、8……接続鉄筋、9……後打ちコンクリ
ート、21……補強鉄筋、25……吊りフツク、
51……キー溝、61……杭鉄筋、71……柱鉄
筋、84……機械継手。
The drawings show an embodiment of the present invention, and FIG. 1 shows the entire foundation, where FIG. 1 is a plan view and FIG. 2 is a sectional view.
Figures 2 and 3 are detailed diagrams of the block body.
2. FIGS. 1 and 2 are top and bottom plan views, respectively, and FIG. 3 is a sectional view. 1...Foundation, 2...Block body, 3...Connection beam, 4...Joint surface, 5...Through hole, 6...Pile, 7
... Column, 8 ... Connection reinforcing bar, 9 ... Post-cast concrete, 21 ... Reinforcement bar, 25 ... Hanging hook,
51... Key groove, 61... Pile reinforcing bar, 71... Column reinforcing bar, 84... Mechanical joint.

Claims (1)

【実用新案登録請求の範囲】[Scope of utility model registration request] プレキヤスト・コンクリート造の基礎ブロツク
体であつて、このブロツク体は、直交するつなぎ
梁の方向を対角線の方向とし、隅角部につなぎ梁
との接合面を面取りした形状の概略正方形の平面
と、つなぎ梁と等しい高さを有するとともに、そ
の平面の中央部に柱、杭用の円形の貫通孔を設け
てあり、この貫通孔の内面には、コンクリート打
継ぎ用のキー溝を円周方向に複数段形成してあ
り、この貫通孔に一端を臨ませ、他端をつなぎ梁
の接続用に外方に延長させた水平の接続鉄筋と、
このブロツク体の補強鉄筋とを有することを特徴
とするプレキヤスト・コンクリート基礎ブロツ
ク。
A foundation block body made of precast concrete, which has a generally square plane with the direction of the orthogonal connecting beams being the diagonal direction, and the joint surfaces with the connecting beams being chamfered at the corners; It has the same height as the connecting beam, and a circular through hole for columns and piles is provided in the center of the plane, and a key groove for concrete pouring is installed in the circumferential direction on the inner surface of this through hole. Horizontal connecting reinforcing bars formed in multiple stages, with one end facing the through hole and the other end extending outward for connecting the connecting beam;
A precast concrete foundation block characterized by having reinforcing reinforcing bars for the block body.
JP10564586U 1986-07-11 1986-07-11 Expired JPH0412111Y2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP10564586U JPH0412111Y2 (en) 1986-07-11 1986-07-11

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP10564586U JPH0412111Y2 (en) 1986-07-11 1986-07-11

Publications (2)

Publication Number Publication Date
JPS6314642U JPS6314642U (en) 1988-01-30
JPH0412111Y2 true JPH0412111Y2 (en) 1992-03-25

Family

ID=30980273

Family Applications (1)

Application Number Title Priority Date Filing Date
JP10564586U Expired JPH0412111Y2 (en) 1986-07-11 1986-07-11

Country Status (1)

Country Link
JP (1) JPH0412111Y2 (en)

Families Citing this family (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2012117327A (en) * 2010-12-02 2012-06-21 Shimizu Corp Vibration control structure
JP6180856B2 (en) * 2013-09-04 2017-08-16 鹿島建設株式会社 Joining structure, construction method of joining structure
JP6383558B2 (en) * 2014-04-07 2018-08-29 株式会社竹中工務店 Footing basic structure
JP6412754B2 (en) * 2014-09-19 2018-10-24 株式会社竹中工務店 Pile-column connection structure
JP6418876B2 (en) * 2014-10-01 2018-11-07 株式会社竹中工務店 Foundation structure
JP6703845B2 (en) * 2016-02-04 2020-06-03 株式会社竹中工務店 Foundation structure
JP2017166213A (en) * 2016-03-16 2017-09-21 戸田建設株式会社 Half-precast concrete foundation for base-isolation device and construction method of foundation for base-isolation device
JP7232660B2 (en) * 2019-02-15 2023-03-03 株式会社安藤・間 pile foundation structure
JP7200042B2 (en) * 2019-05-08 2023-01-06 株式会社安藤・間 pile foundation structure
JP7200048B2 (en) * 2019-06-07 2023-01-06 株式会社安藤・間 pile foundation structure
JP7416606B2 (en) * 2019-11-15 2024-01-17 株式会社安藤・間 pile foundation structure

Also Published As

Publication number Publication date
JPS6314642U (en) 1988-01-30

Similar Documents

Publication Publication Date Title
JPH0412111Y2 (en)
JPH1077607A (en) Method of executing viaduct by using pca concrete member
JP3044459B2 (en) Tower structure construction method
US7073300B1 (en) Reinforced concrete part for producing foundations of buildings
JP2000160687A (en) Construction method for composite structure and precast concrete column
JPH02164934A (en) Foundation construction method
JPH0657710A (en) Construction of concrete main tower
JPH08302808A (en) Connecting method of large pc wall board
JPH02164930A (en) Foundation structure for building
JPH10299003A (en) Foundation work using precast concrete member
JP2757032B2 (en) Construction method of underground building with pillars with capital by reverse hitting method
JP2763488B2 (en) Prefabricated pillar and inverted ramen prefabricated construction method
JPH03279533A (en) Constructing method for rigid-frame type rc super-high building
JPH0452815B2 (en)
JP2972955B2 (en) Column and beam joining method and its structure
JPS6217233A (en) Foundation base column
JP2643760B2 (en) How to build foundation beams
JPH0347321A (en) Shore strut and underground construction work by composite steel beam
JPS6035638Y2 (en) panel foundation
JPH02229337A (en) Constructing technique for concrete column
JPH0410935B2 (en)
JPH0588331B2 (en)
JPH0571748B2 (en)
JPS61270462A (en) Construction of reinforced concrete structure
JPS59158830A (en) Construction of strip foundation