JP3419252B2 - Method of constructing substructure inside PCV - Google Patents
Method of constructing substructure inside PCVInfo
- Publication number
- JP3419252B2 JP3419252B2 JP16686497A JP16686497A JP3419252B2 JP 3419252 B2 JP3419252 B2 JP 3419252B2 JP 16686497 A JP16686497 A JP 16686497A JP 16686497 A JP16686497 A JP 16686497A JP 3419252 B2 JP3419252 B2 JP 3419252B2
- Authority
- JP
- Japan
- Prior art keywords
- tunnel
- module
- containment vessel
- reactor
- parts
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E30/00—Energy generation of nuclear origin
- Y02E30/30—Nuclear fission reactors
Landscapes
- Structure Of Emergency Protection For Nuclear Reactors (AREA)
- Foundations (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Description
【0001】[0001]
【発明の属する技術分野】本発明は、原子炉格納容器の
建設の技術分野に属している。FIELD OF THE INVENTION The present invention is in the technical field of construction of a containment vessel.
【0002】[0002]
【従来の技術】改良型沸騰水型原子炉(以下、ABWR
と称す。)プラントの建設において、原子炉圧力容器
(以下、RPVと称す。)が据え付けられる円筒状のR
PVの基礎(以下、ペデスタルと称す。)はRPVの荷
重を支えて振動にも十分耐えるように内側と外側はコン
クリート打設の型枠を兼ねた円筒状の鋼板でできてお
り、内側と外側の各円筒状の鋼板で挟まれた空間には、
強度の高いコンクリートが充填された構造となってお
り、上下方向5段程度の数段のブロックに分割されてR
PV内に各々搬入し、設定されている。2. Description of the Related Art Improved boiling water reactor (hereinafter referred to as ABWR
Called. ) In the construction of a plant, a cylindrical R in which a reactor pressure vessel (hereinafter referred to as RPV) is installed.
The PV foundation (hereinafter referred to as the pedestal) is made of a cylindrical steel plate that serves as a concrete pouring formwork inside and outside so that it can support the load of the RPV and withstand vibration sufficiently. In the space sandwiched by each cylindrical steel plate of
It has a structure filled with high-strength concrete, and is divided into several blocks of about 5 steps in the vertical direction,
Each is loaded into the PV and set.
【0003】またペデスタルの内筒の鋼板の筒内空間に
配備される機器,配管,支持構造物等はペデスタル工事
完了後のRPV吊り込み前に単品毎に搬入し設定されて
いた。The equipment, pipes, support structures, etc. arranged in the inner space of the steel plate of the inner cylinder of the pedestal have been loaded and set individually before the RPV suspension after the completion of the pedestal construction.
【0004】また人員アクセス用トンネル(以下、トン
ネルと称する。)に関しては、トンネルが設定される高
さ以上に建屋側とペデスタル側が立上り、トンネルを設
定位置に搬入可能になった時点でトンネルの上方に据え
付けられるダイヤフラムフロアの設定が始まるまでに揚
重機により搬入,設定される。As for the personnel access tunnel (hereinafter referred to as a tunnel), the building side and the pedestal side rise above the height at which the tunnel is set, and the tunnel is above the tunnel when the tunnel can be carried into the set position. Before the setting of the diaphragm floor to be installed at, starts by the lifting machine and is set.
【0005】トンネルを完全に設定するまでは仮設架台
等でトンネルを支持する。Until the tunnel is completely set up, the tunnel is supported by a temporary mount or the like.
【0006】トンネル設定後、トンネル内の壁塗装を行
い、その後、電気や機器を据え付ける工事者に現場エリ
アが引き渡され、配管,支持部材,天井構造部材等が据
え付けられる。After the tunnel is set up, the inside of the tunnel is painted, and then the site area is handed over to a worker who installs electricity and equipment, and piping, support members, ceiling structural members, etc. are installed.
【0007】トンネル内の配管(小口径)のほとんどが
トンネルの天井部に密集した形で布設されており、その
物量も多大である。Most of the pipes (small diameter) in the tunnel are installed densely on the ceiling of the tunnel, and the amount of the material is large.
【0008】その配管の施工には建築側からのエリア引
渡後に足場組み立てを行う必要があり、トンネル内とい
う特殊な状況(作業空間が狭い)から、多量の人員投入
にも限界がある。[0008] The construction of the piping requires scaffold assembly after the area is handed over from the building side, and there is a limit to a large amount of personnel due to the special situation (the working space is narrow) inside the tunnel.
【0009】そのため、配管工事にかなりの時間が必要
となり、原子炉格納容器の建設工程上、クリティカルと
なる。Therefore, a considerable amount of time is required for piping work, which is critical in the process of constructing the containment vessel.
【0010】またトンネルは原子炉格納容器内のドライ
ウェル(以下D/Wと称する)下部へ通じる唯一の製
品,人員アクセスルートとなっているため、D/W内へ
の製品,人員アクセスが頻繁な時間帯を避けてアクセス
トンネル内工事は行わなければならなかった。Since the tunnel is the only product / personnel access route leading to the lower part of the dry well (hereinafter referred to as D / W) in the reactor containment vessel, frequent product / personnel access to the D / W. The work inside the access tunnel had to be carried out at different times.
【0011】[0011]
【発明が解決しようとする課題】原子力発電プラント建
設の最近の流れとして工期短縮が求められている。As a recent trend of nuclear power plant construction, shortening of construction period is required.
【0012】工期短縮にはクリティカルパスである建屋
建築従事者側の建屋工程とサブクリティカルである機器
据え付け従事者側のRPV及び炉内工事を短縮しなけれ
ばならない。In order to shorten the construction period, it is necessary to shorten the building process on the building construction worker side, which is a critical path, and the RPV and in-furnace work on the equipment installation worker side, which are subcritical.
【0013】前者が請け負う工事は技術の進捗で短縮化
される傾向にある。The work contracted by the former tends to be shortened due to the progress of technology.
【0014】それに伴い、サブクリティカルであるRP
V及び炉内工事を併行して短縮する必要がでてきてい
る。Accordingly, RP which is a sub-critical
It has become necessary to shorten V and in-core work concurrently.
【0015】現状では、人員を投入し昼夜作業体制によ
り、短縮工程に対応しているが、本方策にも限度があ
る。At present, the number of personnel is put in and a work system for day and night is used to cope with the shortening process, but this measure is also limited.
【0016】改善的な対応策としては炉内構造物をあら
かじめ工場にてRPVを据え付けた状態で現地に持込
み、搬入する方法があるが、ただし、この場合は現状で
もRPVを吊り込む揚重機の能力がいっぱいであることを
考慮するとRPV吊り込み用揚重機の能力アップが必要
となる。As an improved countermeasure, there is a method of bringing in the reactor internal structure in the factory with the RPV installed in advance and carrying it in. However, in this case, even in the present situation, the lifting machine for suspending the RPV is used. Considering that the capacity is full, it is necessary to improve the capacity of the lifting machine for hanging the RPV.
【0017】一方、炉内構造物の組み立て範囲を変えな
いで工程短縮をはかるには、炉内工事を前倒しで実施す
るためのRPVを先行搬入する必要がある。On the other hand, in order to shorten the process without changing the assembly range of the reactor internal structure, it is necessary to carry in the RPV for carrying out the reactor internal work in advance.
【0018】それを実施するにはRPVペデスタル及び
その周辺の施工を早め、RPVの早期搬入に対応する必
要がある。In order to carry out this, it is necessary to speed up the construction of the RPV pedestal and its surroundings and cope with the early loading of the RPV.
【0019】他方、RPVを取合う配管の施工を早める
ことが求められている。On the other hand, there is a demand for accelerating the construction of piping for RPV.
【0020】RPVは建屋内の無数の配管を取合う必要
があり、特に下部D/W部分にはその部分に配備される
制御棒駆動機構(以下、CRDと称する。)を運転,制
御するための多数の小口径配管がRPVに取合ってい
る。The RPV needs to accommodate a myriad of pipes inside the building, and particularly in order to drive and control the control rod drive mechanism (hereinafter referred to as CRD) provided in the lower D / W portion. A large number of small-diameter pipes are used for RPV.
【0021】即ち、RPVペデスタル内及びアクセスト
ンネル内のCRD配管工事が工程上サブクリティカルに
あがってきている。That is, the CRD piping work inside the RPV pedestal and inside the access tunnel is becoming a sub-critical process.
【0022】またこれらの配管は天井部に多数の小径配
管が密集しており、作業消化に多くの労力と工程を要し
ている。In addition, since many small-diameter pipes are densely packed in the ceiling of these pipes, it takes a lot of labor and steps to complete the work.
【0023】一方、作業環境においてはその施工時には
周辺区域にコンクリートが打ち込まれてるため高温多湿
となり、良い環境とはいえない。On the other hand, in the working environment, concrete is driven into the surrounding area during the construction, resulting in high temperature and high humidity, which is not a good environment.
【0024】このような状況での解決策のひとつにアク
セストンネルモジュール化(配管,支持部材,架台等と
の)があげられるが、前記従来工法でも示したように、
RPVペデスタル,アクセストンネルを別個に搬入するた
め、配管の取合い部が多く、配管モジュールもルーズモ
ジュールとしなければならない。One of the solutions in such a situation is to make an access tunnel module (with a pipe, a supporting member, a pedestal, etc.).
Since the RPV pedestal and access tunnel are carried in separately, there are many piping joints and the piping module must be a loose module.
【0025】そのため現地での設定作業工数が増加し、
モジュール化としてのメリットが少なくなる。Therefore, the number of man-hours for setting work increases,
The advantages of modularization are reduced.
【0026】このような条件下でモジュール化のメリッ
トを上げるには、当該モジュールを構成する製品(配
管,支持部材,本設架台等)に関し、現地での作業を低
減することが重要であり、よりタイトなモジュールにす
る必要がある。In order to increase the merit of modularization under such conditions, it is important to reduce the work on site for the products (pipes, supporting members, main frame, etc.) that make up the module, Need to be a tighter module.
【0027】従って、本発明の目的は原子炉格納容器の
下部構造物を早期に建設して原子炉格納容器を含む原子
力プラントの建設工期を短縮することにある。Therefore, an object of the present invention is to construct a substructure of a reactor containment vessel at an early stage to shorten the construction period of a nuclear power plant including the reactor containment vessel.
【0028】[0028]
【課題を解決するための手段】本発明の目的を達成する
ための第1手段は、原子炉圧力容器の基礎を構成する部
材に前記基礎の外周囲に配備される人員アクセス用のト
ンネル部を取り付けて原子炉格納容器内の下部構造物を
建設する方法において、前記基礎の部分に前記トンネル
部の一部を取り付けてモジュールを構成し、前記原子炉
格納容器内壁の金属製ライナーを設置し、前記トンネル
部の他部を設置された前記金属製ライナーに取り付け、
その後に前記モジュールを据え付け位置に吊り込みによ
り搬入して前記トンネル部の前記一部を前記トンネル部
の前記他部に接続することを特徴とした原子炉格納容器
内下部構造物の建設方法であり、原子炉圧力容器の基礎
の部分と人員用アクセストンネルの一部分とが同時に据
え付け位置に吊り込まれて据え付けられる作用が得ら
れ、その作用によって、原子炉圧力容器の据え付け等の
原子炉格納容器の上部の構成の据え付けが前倒しに行え
て原子力プラントの建設工程が短縮できる。更に、その
作用によって、モジュールを据え付け位置へ向けて金属
製ライナー沿いに降ろしていく際に、モジュールに組み
込まれたトンネルの一部の長さが短いためモジュールに
組み込まれたトンネル部分が金属製のライナーに接触す
る事故を起こすことを抑制できる。A first means for achieving the object of the present invention is to provide a member for forming a foundation of a reactor pressure vessel, which is provided around the outer periphery of the foundation, for access to personnel .
The lower part inside the reactor containment vessel
In the method of constructing the tunnel in the part of the foundation
A part of the reactor is attached to form a module,
Install a metal liner on the inner wall of the containment
Attach the other part of the part to the installed metal liner,
Then, hang the module in the installation position.
And carry in the part of the tunnel part to the tunnel part.
Wherein a construction method of the reactor containment vessel lower structure which is characterized in that connected to the other portion, and a portion of the access portion and personnel basis of the reactor pressure vessel tunnel is incorporated hanging installation position simultaneously As a result, the construction of the upper part of the reactor containment vessel, such as the installation of the reactor pressure vessel, can be installed ahead of time, and the construction process of the nuclear power plant can be shortened . Furthermore, that
The action will move the module toward the mounting position
Assemble it into the module as you lower it along the liner
Due to the short length of the part of the tunnel
Built-in tunnel part contacts metal liner
Ru can be suppressed to cause that accident.
【0029】同じく第2手段は、前記モジュールの搬入
前に、前記原子炉圧力容器又は前記基礎で取り囲まれた
内部空間に設置される機器に連通され、前記内部空間内
及び前記トンネル部の前記一部内に配置された配管と、
前記内部空間に設置される構造躯体とを装備して置くこ
とを特徴とした原子炉格納容器内下部構造物の建設方法
であり、第1手段による作用効果に加えて、前記内部空
間やトンネル内の配管や機器や構造躯体がモジュールの
吊り込みによって同時に据え付け箇所に搬入されて据え
付けられる作用が得られるので、配管工事や機器据え付
け工事や構造躯体据え付け工事が大幅に省略できてトン
ネルを前記内部空間へのアクセスルートに使用している
時間帯を避けて、及び作業環境の悪いトンネル内の配管
工事を行うというわずらわしさも解消でき、原子力プラ
ントの建設工程が一層短縮できるという効果が得られ
る。Similarly, the second means is to carry in the module.
Previously surrounded by the reactor pressure vessel or the foundation
Inside the internal space, which is in communication with equipment installed in the internal space
And piping arranged in the part of the tunnel portion,
Wherein a construction method of this <br/> and reactor containment vessel bottom structure was characterized by placing equipped with a structural framework that is installed in the inner space, in addition to the effects by the first means, wherein Since the piping, equipment and structural frame in the internal space or tunnel can be brought into the installation location and installed at the same time by suspending the module, piping work, equipment installation work and structural structure installation work can be greatly omitted. The effect of avoiding the time zone when the tunnel is used as an access route to the internal space and eliminating the troublesome work of plumbing inside the tunnel with a bad working environment, further shortening the construction process of the nuclear plant can get.
【0030】同じく第3手段は、前記モジュールの搬入
は、前記モジュールを吊り天秤から垂直に垂らしたロー
プで吊り、前記吊り天秤を揚重機によって吊って行うこ
とを特徴とした原子炉格納容器内下部構造物の建設方法
であり、第1手段による作用効果に加えて、原子炉圧力
容器の基礎とトンネルとは、吊り天秤から垂直に垂らし
たロープで垂直に吊られるから、ロープを斜めに掛けて
吊る場合に比べてロープにも原子炉圧力容器の基礎やト
ンネルにも無理が加わりにくい作用が得られ、原子炉圧
力容器の基礎にトンネルを付けて大型大重量となったモ
ジュールを吊った際にモジュールに変形を起こすことな
く無理無しに据え付け位置に吊り込んで据え付けられる
効果が得られる。Similarly, the third means is to carry in the module.
Is a vertical suspension of the module from the suspension balance.
Hanging in flop, a construction method of this <br/> and reactor containment vessel bottom structure was characterized by performing hanging the hanging balance by the crane, in addition to the effects by the first means, the reactor Since the foundation of the pressure vessel and the tunnel are hung vertically with a rope that hangs vertically from the suspension balance, it is not possible to use both the rope and the foundation of the reactor pressure vessel or tunnel as compared with the case where the rope is hung diagonally. It has the effect that it is difficult to add, and when a large and heavy module is hung by attaching a tunnel to the foundation of the reactor pressure vessel, the module can be hung and installed in the installation position without deformation without causing deformation. can get.
【0031】同じく第4手段は、前記原子炉格納容器内
に搬入された前記モジュールの前記トンネル部の前記一
部を予め前記原子炉格納容器内に設置した仮設架台に受
けて前記モジュールの据え付けを行うことを特徴とした
原子炉格納容器内下部構造物の建設方法であり、第1手
段による作用効果に加えて、原子炉格納容器内に吊り込
まれてきたモジュールは原子炉圧力容器の基礎から突き
出たトンネル部分を仮設架台に受けさせて吊り込み時の
吊り手段をトンネルから外してもトンネルが変形するこ
となく所定の相手に取り付けれる作用が得られ、正確な
据え付け作業を迅速に行えるという効果が得られる。Similarly, the fourth means is the inside of the reactor containment vessel.
Of the tunnel portion of the module that has been loaded into
Part is received in a temporary stand installed in the reactor containment vessel in advance.
A method for constructing a lower structure in a reactor containment vessel, characterized in that the module is installed for the first time.
In addition to the effect of the step, the module suspended in the reactor containment vessel receives the tunnel part protruding from the foundation of the reactor pressure vessel on the temporary mount and removes the suspending means at the time of suspension from the tunnel. The effect that the tunnel can be attached to a predetermined partner without deformation is obtained, and the effect that accurate installation work can be performed quickly is obtained.
【0032】[0032]
【0033】[0033]
【0034】[0034]
【0035】[0035]
【発明の実施の形態】原子力プラントの一例として、原
子力発電所のプラントには、図1で示す原子炉建屋1が
採用されている。DESCRIPTION OF THE PREFERRED EMBODIMENTS As an example of a nuclear power plant, a reactor building 1 shown in FIG. 1 is adopted in a plant of a nuclear power plant.
【0036】その原子炉建屋1内には、原子炉圧力容器
2を格納する原子炉格納容器25が建設され、その原子
炉格納容器25の内壁には金属製ライナー3が施工され
て設置されている。In the reactor building 1, a reactor containment vessel 25 for housing the reactor pressure vessel 2 is constructed, and a metal liner 3 is installed on the inner wall of the reactor containment vessel 25. There is.
【0037】その原子炉格納容器25の内壁に施工され
る金属製ライナー3内側には、原子炉圧力容器2を搭載
するための基礎である円筒状のペデスタル4が設置され
ている。A cylindrical pedestal 4 which is a base for mounting the reactor pressure vessel 2 is installed inside the metal liner 3 to be installed on the inner wall of the reactor containment vessel 25.
【0038】そのペデスタル4と原子炉圧力容器2とで
囲われた空間は下部ドライウエル5と称される空間とな
っている。The space surrounded by the pedestal 4 and the reactor pressure vessel 2 is a space called a lower dry well 5.
【0039】この下部ドライウエル5内には、原子炉圧
力容器2内の炉心を制御するための制御棒を操作するた
めの機器である制御棒駆動機構6やその他の機器が多数
配備されている。In the lower dry well 5, a control rod drive mechanism 6 which is a device for operating a control rod for controlling the reactor core in the reactor pressure vessel 2 and many other devices are provided. .
【0040】それらの機器には、圧力流体や電線を通す
ための配管8が接続されている。A pipe 8 for passing a pressure fluid or an electric wire is connected to these devices.
【0041】これらの機器や配管8のサポートを支える
ために下部ドライウエル5内空間には鉄骨による構造躯
体7が構築されている。A structural frame 7 made of steel is constructed in the space inside the lower dry well 5 to support these devices and the support of the pipe 8.
【0042】それらの配管8は、下部ドライウエル5内
から人員アクセス用のトンネル9に通されて原子炉格納
容器25外の原子炉建屋1内へ通されている。These pipes 8 are passed from the inside of the lower dry well 5 through the tunnel 9 for access to personnel to the inside of the reactor building 1 outside the reactor containment vessel 25.
【0043】そのトンネル9は原子炉建屋1内と下部ド
ライウエル5との間のアクセスルート(通路)として使
用される。The tunnel 9 is used as an access route (passage) between the inside of the reactor building 1 and the lower dry well 5.
【0044】トンネル9の上方には、ダイヤフラムフロ
ア10が設置される。A diaphragm floor 10 is installed above the tunnel 9.
【0045】このような原子炉建屋1にあっては、原子
炉格納容器25内の下部構造物であるトンネル9やペデ
スタル4が構築されないと、それよりも上部のダイヤフ
ラムフロア10等の上部構造が建設できないし、原子炉
圧力容器2のペデスタル4への据え付けも遅れることに
なる。In such a reactor building 1, unless the tunnel 9 and the pedestal 4 which are the substructures inside the reactor containment vessel 25 are constructed, the upper structure such as the diaphragm floor 10 and the like located above the tunnel 9 and the pedestal 4 are not constructed. It cannot be built, and installation of the reactor pressure vessel 2 on the pedestal 4 will be delayed.
【0046】その様なプラントの建設が遅れる要因を排
除するために、次のような建設工法が採用される。In order to eliminate the factor that delays the construction of such a plant, the following construction method is adopted.
【0047】ペデスタル4は全部で5段に分けられてい
るが、本実施例では、クレーンの取り扱える荷重容量を
考慮して、図3のように、下から1段目と2段目とを地
組ヤード13にて重ねて溶接等により一体化する。The pedestal 4 is divided into five stages in total, but in this embodiment, considering the load capacity that can be handled by the crane, as shown in FIG. 3, the first stage and the second stage from the bottom are grounded. They are piled up in the assembly yard 13 and integrated by welding or the like.
【0048】ペデスタル4は、鋼板製の内筒11と鋼板
製の外筒12とから成る二重円筒状の構成を有し、内筒
11と外筒12との間は鋼板製の隔壁によって接続され
て一体となって製造される。The pedestal 4 has a double cylindrical structure composed of an inner cylinder 11 made of a steel plate and an outer cylinder 12 made of a steel plate, and the inner cylinder 11 and the outer cylinder 12 are connected by a partition wall made of a steel plate. Are manufactured integrally.
【0049】クレーンがペデスタル4の全段を一気に扱
えるほどの能力があれば地組ヤード13にてペデスタル
4の全段を一体化することが工程短縮にとって理想的で
ある。If the crane has the capacity to handle all stages of the pedestal 4 at a stretch, it is ideal for shortening the process to integrate all stages of the pedestal 4 in the ground yard 13.
【0050】そのペデスタル4の外筒12と内筒11と
の間には、ダイヤフラムフロア10より上方のドライウ
エル空間の流体をダイヤフラムフロア10より下方の圧
力抑制室空間に通すベント流路14が組み込まれてい
る。Between the outer cylinder 12 and the inner cylinder 11 of the pedestal 4, there is incorporated a vent passage 14 for allowing the fluid in the dry well space above the diaphragm floor 10 to pass into the pressure suppression chamber space below the diaphragm floor 10. Has been.
【0051】ベント流路14の下端は水平に設置された
管15によって構成され、水平に流体を吐出するように
流体の吐出口が水平方向に向けられている。The lower end of the vent channel 14 is constituted by a pipe 15 installed horizontally, and the fluid discharge port is oriented horizontally so as to discharge the fluid horizontally.
【0052】このようなペデスタル4の部分が、図3の
ように、原子炉建屋1の建設位置に近い屋外の地組ヤー
ド13で垂直に立てられ、そのペデスタル4の廻りに
は、仮設架台16が置かれる。As shown in FIG. 3, such a pedestal 4 is erected vertically in an outdoor yard 13 near the construction position of the reactor building 1, and around the pedestal 4, a temporary pedestal 16 is installed. Is placed.
【0053】その仮設架台16の上部には図3の右上側
に図示したように、他の場所で作られたトンネル9の部
分がクレーンで吊って運ばれてくる。As shown in the upper right side of FIG. 3, a portion of the tunnel 9 made at another place is hung by a crane and carried on the upper part of the temporary mount 16.
【0054】このトンネル9の部分は、金属製ライナー
3に取り付く側の先端部分が一部分分割されており、そ
の分割された分割トンネル26は予めトンネルが取り付
く位置で図4のように金属製ライナー3に取り付けられ
ている。The tip of the tunnel 9 is attached to the metal liner 3 at a part thereof, and the divided tunnel 26 is preliminarily attached to the metal liner 3 at a position where the tunnel is attached as shown in FIG. Is attached to.
【0055】その運ばれてきたトンネル9は、図3の左
側のトンネル9の部分のように、仮設架台16上に置か
れてペデスタル4と溶接等によって固定される。The carried tunnel 9 is placed on the temporary mount 16 and fixed to the pedestal 4 by welding or the like like the part of the tunnel 9 on the left side of FIG.
【0056】仮設架台16上に運ばれてくるトンネル9
の部分は、図2のように、内部天井部分に配管8のサポ
ート17を介して複数の配管8が予め設置されて配管8
の群を内蔵した状態とされている。The tunnel 9 carried on the temporary mount 16
2, the plurality of pipes 8 are installed in advance on the inner ceiling part via the supports 17 of the pipes 8 as shown in FIG.
It is said to have built in a group of.
【0057】また、トンネル9の内部下方には、本設架
台18が歩行用と作業用を兼ねて足場として設置されて
いる。Further, below the inside of the tunnel 9, a permanent pedestal 18 is installed as a scaffold for both walking and working.
【0058】このように本設架台18や配管8をトンネ
ル9に設置するタイミングは地組ヤード13にトンネル
9を運び込んでくる前に事前に設置しておいても良く、
トンネル9をペデスタル4に取り付けてから設置しても
良い。As described above, the main installation frame 18 and the pipe 8 may be installed in the tunnel 9 in advance before the tunnel 9 is brought into the ground yard 13,
The tunnel 9 may be installed after being attached to the pedestal 4.
【0059】地組ヤード13にトンネル9を運び込んで
くる前に事前に配管8等をトンネル9内に設置して置く
場合には、地組ヤード13内での作業が簡略化されて地
組ヤード13内での組み立て作業が迅速に成せる。When the pipes 8 and the like are installed in advance in the tunnel 9 before the tunnel 9 is brought into the ground yard 13, the work in the ground yard 13 is simplified and the work in the ground yard 13 is simplified. Assembly work in 13 can be done quickly.
【0060】さらに、ペデスタル4についても、ペデス
タル4で囲われた空間内には、図3のように鉄骨ビーム
製の構造躯体7がペデスタル4に固定設置され、その構
造躯体7から配管8のサポートを介して支持した配管8
が設置される。Further, as for the pedestal 4, a structural frame 7 made of a steel beam is fixedly installed on the pedestal 4 in a space surrounded by the pedestal 4, and the structural frame 7 supports the pipe 8 as shown in FIG. Pipe 8 supported via
Is installed.
【0061】そのペデスタル4内の配管8や構造躯体7
の設置は、トンネル9の部分とペデスタル4の部分とを
固定する前であっても後であっても良い。The pipe 8 and the structural frame 7 in the pedestal 4
May be installed before or after fixing the tunnel 9 part and the pedestal 4 part.
【0062】トンネル9内に設置した配管8とペデスタ
ル4で囲われた空間内に設置された配管8とは互いに接
続される本数が多いことから、地組ヤード13にて両者
の配管8を接続して置いても良い。Since the pipe 8 installed in the tunnel 9 and the pipe 8 installed in the space surrounded by the pedestal 4 are connected to each other in a large number, both pipes 8 are connected in the ground yard 13. You can leave it.
【0063】この場合には、ペデスタル4の部分にトン
ネル9の部分を接続固定してから配管8をペデスタル4
とトンネル9とに一気に設置することが、ペデスタル4
とトンネル9とに個々に配管8を設置してから両者の配
管8を最後に接続するのに比べて、配管8の接続位置や
角度の調整作業が伴わないので作業が容易となるし、配
管8の設置もその全長のほとんどの部分で本設内容にて
設置できる。In this case, after connecting and fixing the tunnel 9 to the pedestal 4, the pipe 8 is connected to the pedestal 4.
The pedestal 4 can be installed at once in the tunnel 9
In comparison with connecting the pipes 8 to the tunnel 9 and the tunnel 9 individually and then connecting the pipes 8 to each other lastly, the work is easy because the work of adjusting the connection position and the angle of the pipe 8 is not required. The installation of 8 can be installed with the main contents for most of the entire length.
【0064】このような、地組ヤード13にての組み立
てが終了すると、ペデスタル4の部分とトンネル9の部
分とが一体に組み付けられたモジュール構造物19が完
成する。When the assembly in the ground yard 13 is completed, the module structure 19 in which the part of the pedestal 4 and the part of the tunnel 9 are integrally assembled is completed.
【0065】そのモジュール構造物19には、ワイヤー
ロープ20が引っかけられる吊り金具がペデスタル4の
部分とトンネル9の部分とに分散して複数個固定され
る。On the module structure 19, a plurality of suspension fittings on which the wire rope 20 is hooked are dispersed and fixed to the pedestal 4 and the tunnel 9.
【0066】このようなモジュール構造物19が作成さ
れている間にも原子炉建屋1の建設は進められ、図4の
ように、トンネル9の入り口となる開閉自在なハッチ2
1が原子炉格納容器25の内壁に施工される金属製ライ
ナー3と原子炉建屋1とに据え付けられ、原子炉格納容
器25の内壁に施工される金属製ライナー3もモジュー
ル構造物19が収納できるほどに建設されている。The construction of the reactor building 1 is proceeded even while the modular structure 19 is being prepared, and as shown in FIG.
1 is installed on the metal liner 3 installed on the inner wall of the reactor containment vessel 25 and the reactor building 1, and the metal liner 3 installed on the inner wall of the reactor containment vessel 25 can also accommodate the module structure 19. It has been built so much.
【0067】その金属製ライナー3を施工する際には、
予め金属製ライナー3に分割トンネル26を取り付けて
置いて、その分割トンネル26を取り付けた金属製ライ
ナー3をクレーンで吊って金属製ライナー3の施工位置
に搬入してもよく、金属製ライナー3をクレーンで吊っ
て金属製ライナー3の施工位置に搬入してその金属製ラ
イナーの設置を終えてから分割トンネル26を金属製ラ
イナー3に取り付けて置くようにしても良い。When constructing the metal liner 3,
The split tunnel 26 may be attached to the metal liner 3 in advance, and the metal liner 3 attached with the split tunnel 26 may be hung by a crane to be carried into the construction position of the metal liner 3. Alternatively, the split tunnel 26 may be attached to the metal liner 3 and placed after the metal liner 3 is hung by a crane and carried into the construction position of the metal liner 3 and the installation of the metal liner is completed.
【0068】しかる後に、屋外のクレーン22で地組ヤ
ード13内のモジュール構造物19を吊り上げて金属製
ライナー3内に吊り込む。Thereafter, the module structure 19 in the ground yard 13 is lifted by the outdoor crane 22 and is hung in the metal liner 3.
【0069】吊り込み作業の状態が図4に示されてい
る。The state of the hanging operation is shown in FIG.
【0070】吊り込みに際してはモジュール構造物19
が大型で且つトンネル9が水平に突き出ていて崩れたり
変形し易いから、それを防ぐために次のような吊り方が
採用される。The module structure 19 is used for hanging.
Is large and the tunnel 9 protrudes horizontally and is easily collapsed or deformed. Therefore, in order to prevent this, the following hanging method is adopted.
【0071】即ち、図4のように、クレーン22から吊
り天秤23を吊って、その吊り天秤23から垂直にワイ
ヤーロープ20を垂らしてペデスタル4の部分とトンネ
ル9の部分とに取り付けた吊り金具に掛け渡す。That is, as shown in FIG. 4, the hanging balance 23 is hung from the crane 22, and the wire rope 20 is hung vertically from the hanging balance 23 to form a hanging fitting attached to the pedestal 4 and the tunnel 9. Cross over.
【0072】ワイヤーロープ20が垂直になるように吊
り天秤23は十字形状の平面形状を有している。The suspension balance 23 has a cross-shaped planar shape so that the wire rope 20 is vertical.
【0073】このようにしてモジュール構造物19はク
レーン22によって吊り上げられるが、吊った状態にお
いては、ワイヤーロープ20が垂直であるからワイヤー
ロープ20が斜めになって水平分力がモジュール構造物
19に発生するような現象がなく、モジュール構造物1
9に無理な力が加わることがなくて、モジュール構造物
19の崩れや変形が抑制できる。In this way, the module structure 19 is hoisted by the crane 22. In the suspended state, the wire rope 20 is vertical, so that the wire rope 20 is inclined and a horizontal component force is applied to the module structure 19. There is no phenomenon that occurs, and module structure 1
It is possible to prevent the module structure 19 from collapsing or deforming without applying an unreasonable force to the module 9.
【0074】クレーン22で吊り上げられたモジュール
構造物19はクレーン22によって、図4のように、原
子炉格納容器25の内壁に施工される金属製ライナー3
の真上に運ばれる。The module structure 19 hoisted by the crane 22 is mounted on the inner wall of the reactor containment vessel 25 by the crane 22 as shown in FIG.
Carried directly above.
【0075】その運び作業の前には、原子炉格納容器2
5の底部にトンネル9を撓まないように受ける仮設架台
16が設置されている。Before the carrying operation, the reactor containment vessel 2
A temporary mount 16 for receiving the tunnel 9 without bending is installed at the bottom of the tunnel 5.
【0076】原子炉格納容器25の内壁に施工される金
属製ライナー3の真上に運ばれたモジュール構造物19
はクレーン22で吊り降ろされて、原子炉格納容器25
の底部にペデスタル4の部分が据え付けられ、トンネル
9の部分は仮設架台16に支持された状態で、図5のよ
うに、金属製ライナー3に取り付いている分割トンネル
26と溶接により一連に接続される。The module structure 19 carried directly above the metal liner 3 to be installed on the inner wall of the reactor containment vessel 25.
Is hung by the crane 22 and the reactor containment vessel 25
The pedestal 4 is installed on the bottom of the pedestal, and the tunnel 9 is supported by the temporary mount 16 and connected in series by welding to the split tunnel 26 attached to the metal liner 3 as shown in FIG. It
【0077】このように接続されたトンネル9内にはハ
ッチ21から出入りできるようになる。The hatch 21 can enter and exit the tunnel 9 thus connected.
【0078】分割トンネル26を用いる理由は、分割し
ないでトンネルを扱うと、モジュール構造物19を金属
製ライナー3内に吊り降ろす際に、金属製ライナー3の
内壁面とトンネル9の突端との間で干渉事故を起こすか
ら、これを避けるためである。The reason why the split tunnel 26 is used is that if the tunnel is handled without being split, when the module structure 19 is suspended in the metal liner 3, it is between the inner wall surface of the metal liner 3 and the tip of the tunnel 9. This is to avoid this, as it will cause an interference accident.
【0079】モジュール構造物19のトンネル9の部分
を据え付けている間中そのトンネル9の部分を支えてい
た仮設架台16は、トンネル9の据え付けが終わった後
に原子炉建屋1の外へ撤去される。The temporary pedestal 16 which supports the tunnel 9 portion of the module structure 19 during the installation is removed to the outside of the reactor building 1 after the installation of the tunnel 9 is completed. .
【0080】モジュール構造物19が金属製ライナー3
内に据え付けられると、ペデスタル4の部分で囲われた
空間内とトンネル9の部分内に配管8や構造躯体7や機
器が同時に搬入された状態となるので、それら配管8や
構造躯体7や機器等の物品にまつわる搬入作業や工事が
大幅に削減できてモジュール構造物19より上方での建
設作業を促進することができる。The module structure 19 is the metal liner 3
When installed inside, the pipe 8 and the structural skeleton 7 and equipment are brought into the space surrounded by the pedestal 4 and the tunnel 9 at the same time. It is possible to significantly reduce the carrying-in work and the construction related to the articles such as, and to promote the construction work above the module structure 19.
【0081】また、原子炉格納容器25の底部は原子炉
建屋1の深い部分に位置して建設中は周囲のコンクリー
ト等から大量の水分が出て湿気が多いが、その湿気の多
い且つ狭隘な作業環境下での作業量が低減できる。Further, the bottom of the reactor containment vessel 25 is located in a deep portion of the reactor building 1, and a large amount of moisture is released from the surrounding concrete or the like during the construction to cause a large amount of moisture, but the moisture is large and narrow. The amount of work in the work environment can be reduced.
【0082】また、モジュール構造物19を据え付けた
後には、トンネル9がペデスタル4で囲われた空間内へ
の人員や機材のアクセスルートとして早期に使用できる
のでその空間内、即ち下部ドライウエル5内での作業が
促進できる。After the module structure 19 is installed, the tunnel 9 can be used early as an access route for personnel and equipment to the space surrounded by the pedestal 4, so that the interior of the space, that is, the lower dry well 5 can be used. Work can be promoted.
【0083】モジュール構造物19の据え付け後には、
ペデスタル4の3段目から上方の段数が組み上げられる
とともにペデスタル4の内筒11と外筒12との間にコ
ンクリートが充填されて早期に原子炉圧力容器2をペデ
スタル4に据え付ける作業を行える状況となる。After installation of the modular structure 19,
As the number of stages above the third stage of the pedestal 4 is built up and concrete is filled between the inner cylinder 11 and the outer cylinder 12 of the pedestal 4, it is possible to install the reactor pressure vessel 2 on the pedestal 4 early. Become.
【0084】また、金属製ライナー3周囲の原子炉建屋
1部分の建設も進められる。Further, the construction of the reactor building 1 portion around the metal liner 3 is also advanced.
【0085】本実施例によれば、以下のような効果が得
られる。According to this embodiment, the following effects can be obtained.
【0086】本実施例により、トンネル9内天井部の配
管8がトンネル9内に予め設定されて搬入されるため、
建屋内での配管8の据付作業が省力化されるとともに、
作業環境が整っている場所で配管8がトンネル9内に設
定できるから、据え付け精度の向上も達成できる。According to this embodiment, since the pipe 8 on the ceiling of the tunnel 9 is preset and carried into the tunnel 9,
In addition to labor saving installation work of the pipe 8 in the building,
Since the pipe 8 can be set in the tunnel 9 in a place where the working environment is prepared, the installation accuracy can be improved.
【0087】これによりアクセス用のトンネル9設定後
の配管8工事期間が大幅に短縮され、原子力発電所のプ
ラント建設工程の工期短縮が可能となる。As a result, the construction period of the piping 8 after setting the access tunnel 9 is significantly shortened, and the construction period of the plant construction process of the nuclear power plant can be shortened.
【0088】また原子炉建屋1内の作業量が少なくなる
事により、作業効率が上がり、同様に工期短縮効果が得
られる。Further, since the amount of work in the reactor building 1 is reduced, the work efficiency is improved and the work period shortening effect is also obtained.
【0089】ペデスタル4の部分とトンネル9の部分と
が一体化されて、搬入されるため、搬入後、早期に人員
や機材のアクセス、即ち下部ドライウエル5内での工事
開始が可能となり、同様に工期短縮の効果が得られる。Since the part of the pedestal 4 and the part of the tunnel 9 are integrated and carried in, it becomes possible to access personnel and equipment early after the carry-in, that is, to start the construction in the lower dry well 5. The effect of shortening the construction period can be obtained.
【0090】[0090]
【発明の効果】本発明によれば、原子炉圧力容器の基礎
の部分と人員用アクセストンネルの一部分とが同時に据
え付け位置に吊り込まれて据え付けられるので、原子力
プラントの建設工程が短縮できる上、モジュールと原子
炉格納容器の金属製ライナーとの接触事故を抑制して安
全であるという効果が得られる。According to the present invention, since a portion of the part of the foundation and personnel for access tunnel of the reactor pressure vessel is mounted is incorporated hanging in installed position at the same time, on the construction process of the nuclear plant can be shortened, Modules and atoms
Prevents contact accidents with the metal liner of the reactor containment vessel and reduces safety.
The effect of being complete is obtained.
【0091】[0091]
【0092】[0092]
【0093】[0093]
【0094】[0094]
【0095】[0095]
【0096】[0096]
【図1】原子力発電所のプラントにおける原子炉建屋の
縦断面図である。FIG. 1 is a vertical sectional view of a reactor building in a plant of a nuclear power plant.
【図2】本発明の実施例に用いられるアクセストンネル
のモジュール構造を一部断面表示で示した立面図であ
る。FIG. 2 is an elevation view showing a module structure of an access tunnel used in an embodiment of the present invention in a partial sectional view.
【図3】本発明の実施例によるモジュール構造物を地組
ヤードにて製造している状況を示した一部断面表示によ
る立面図である。FIG. 3 is an elevational view with a partial cross-sectional view showing a situation in which a module structure according to an embodiment of the present invention is manufactured in a ground yard.
【図4】本発明の実施例によるモジュール構造物を据え
付け位置へ吊り込んでいる状況を示した一部断面表示に
よる立面図である。FIG. 4 is an elevational view with a partial cross-sectional view showing a state in which a module structure according to an embodiment of the present invention is suspended in an installation position.
【図5】本発明の実施例によるモジュール構造物を据え
付け位置に据え付けている状況を示した一部断面表示に
よる立面図である。FIG. 5 is an elevational view with a partial cross-sectional view showing a situation in which the module structure according to the embodiment of the present invention is installed at an installation position.
1…原子炉建屋、2…原子炉圧力容器、3…金属製ライ
ナー、4…ペデスタル、5…下部ドライウエル、6…制
御棒駆動機構、7…構造躯体、8…配管、9…トンネ
ル、10…ダイヤフラムフロア、11…内筒、12…外
筒、13…地組ヤード、14…ベント流路、15…管、
16…仮設架台、17…サポート、18…本設架台、1
9…モジュール構造物、20…ワイヤーロープ、21…
ハッチ、22…クレーン、23…吊り天秤、25…原子
炉格納容器、26…分割トンネル。1 ... Reactor building, 2 ... Reactor pressure vessel, 3 ... Metal liner, 4 ... Pedestal, 5 ... Lower dry well, 6 ... Control rod drive mechanism, 7 ... Structural frame, 8 ... Piping, 9 ... Tunnel, 10 ... diaphragm floor, 11 ... inner cylinder, 12 ... outer cylinder, 13 ... ground yard, 14 ... vent passage, 15 ... pipe,
16 ... Temporary mount, 17 ... Support, 18 ... Main mount, 1
9 ... Modular structure, 20 ... Wire rope, 21 ...
Hatch, 22 ... Crane, 23 ... Suspended balance, 25 ... Reactor containment vessel, 26 ... Split tunnel.
フロントページの続き (72)発明者 後田 孝一 茨城県日立市幸町三丁目1番1号 株式 会社 日立製作所 日立工場内 (72)発明者 村山 貢一 茨城県日立市幸町三丁目1番1号 株式 会社 日立製作所 日立工場内 (56)参考文献 特開 平4−128694(JP,A) 特開 平9−113667(JP,A) 特開 昭60−100793(JP,A) 特開 昭64−75749(JP,A) (58)調査した分野(Int.Cl.7,DB名) G21C 13/00 G21C 13/024 Front Page Continuation (72) Koichi Gota, 1-1 1-1 Sachimachi, Hitachi City, Ibaraki Hitachi Ltd. Hitachi factory, Hitachi (72) 3-1-1, Koichi Murayama, Inventor, Koichi Murayama, Hitachi City, Ibaraki Prefecture Stock company Hitachi Ltd. In Hitachi factory (56) Reference JP-A-4-128694 (JP, A) JP-A-9-113667 (JP, A) JP-A-60-100793 (JP, A) JP-A-64- 75749 (JP, A) (58) Fields investigated (Int.Cl. 7 , DB name) G21C 13/00 G21C 13/024
Claims (6)
記基礎の外周囲に配備される人員アクセス用のトンネル
部を取り付けて原子炉格納容器内の下部構造物を建設す
る方法において、前記基礎の部分に前記トンネル部の一
部を取り付けてモジュールを構成し、前記原子炉格納容
器内壁の金属製ライナーを設置し、前記トンネル部の他
部を設置された前記金属製ライナーに取り付け、その後
に前記モジュールを据え付け位置に吊り込みにより搬入
して前記トンネル部の前記一部を前記トンネル部の前記
他部に接続することを特徴とした原子炉格納容器内下部
構造物の建設方法。1. A tunnel for access to personnel, which is provided on a member constituting a foundation of a reactor pressure vessel and is provided around an outer periphery of the foundation.
Parts to build the substructure inside the reactor containment vessel.
In the method of
Parts to form a module, and
Install a metal liner on the inner wall of the vessel and
Parts to the installed metal liner, then
Bring the module into the installation position by hanging it
The part of the tunnel part and the part of the tunnel part
A method for constructing a lower structure in a containment vessel characterized by connecting to another part .
記基礎の外周囲に配備される人員アクセス用のトンネル
部を取り付けて原子炉格納容器内の下部構造物を建設す
る方法において、前記基礎の部分に前記トンネル部の一
部を取り付けてモジュールを構成し、前記トンネル部の
他部を取り付けた金属製ライナーを施工位置に搬入し、
その後に前記モジュールを据え付け位置に吊り込みによ
り搬入して前記トンネル部の前記一部を前記トンネル部
の他部に接続することを特徴とした原子炉格納容器内下
部構造物の建設方法。2. A member forming the basis of a reactor pressure vessel
Tunnel for access to personnel deployed around the outside of the foundation
Parts to build the substructure inside the reactor containment vessel.
In the method of
Parts to form a module,
Bring in the metal liner with other parts attached to the construction position,
Then, hang the module in the installation position.
And carry in the part of the tunnel part to the tunnel part.
A method for constructing a lower structure in a reactor containment vessel, which is characterized in that it is connected to another part .
記基礎の外周囲に配備される人員アクセス用のトンネル
部を取り付けて原子炉格納容器内の下部構造物を建設す
る方法において、前記基礎の部分に前記トンネル部の一
部を取り付けてモジュールを構成し、前記トンネル部の
他部を取り付けた金属製ライナーを設置し、その後に前
記モジュールを据え付け位置に吊り込みにより搬入して
前記トンネル部の前記一部を前記トンネル部の他部に接
続することを特徴とした原子炉格納容器内下部構造物の
建設方法。3. A member forming a foundation of a reactor pressure vessel.
Tunnel for access to personnel deployed around the outside of the foundation
Parts to build the substructure inside the reactor containment vessel.
In the method of
Parts to form a module,
Install the metal liner with the other parts attached, and then
Carry the module into the installation position by hanging it.
Connect the part of the tunnel part to another part of the tunnel part.
A method for constructing a substructure inside a containment vessel characterized by being continued .
て、前記モジュールの搬入前に、前記原子炉圧力容器又
は前記基礎で取り囲まれた内部空間に設置される機器に
連通さ れ、前記内部空間内及び前記トンネル部の前記一
部内に配置された配管と、前記内部空間に設置される構
造躯体とを装備して置くことを特徴とした原子炉格納容
器内下部構造物の建設方法。4. The odor according to any one of claims 1 to 3.
Prior to loading the module, the reactor pressure vessel or
Is for equipment installed in the internal space surrounded by the foundation
The inside of the internal space and the one of the tunnel portions are communicated with each other.
Piping installed inside the unit and the structure installed in the internal space
A method for constructing a lower structure in a nuclear reactor containment vessel, characterized by being equipped with a structure.
て、前記モジュールの搬入は、前記モジュールを吊り天
秤から垂直に垂らしたロープで吊り、前記吊り天秤を揚
重機によって吊って行うことを特徴とした原子炉格納容
器内下部構造物の建設方法。5. The odor according to any one of claims 1 to 4.
When loading the module, suspend the module from the ceiling.
Suspend with a rope that hangs vertically from the scale and lift the suspension balance.
A method for constructing a lower structure inside a containment vessel characterized by being hung by a heavy machine .
て、前記原子炉格納容器内に搬入された前記モジュール
の前記トンネル部の前記一部を予め前記原子炉格納容器
内に設置した仮設架台に受けて前記モジュールの据え付
けを行うことを特徴とした原子炉格納容器内下部構造物
の建設方法。6. The odor according to any one of claims 1 to 5.
The module loaded in the reactor containment vessel
The part of the tunnel part of the reactor containment vessel
Install the module by receiving it on the temporary frame installed inside
A method for constructing a lower structure in a reactor containment vessel, which is characterized by carrying out a mortar .
Priority Applications (3)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP16686497A JP3419252B2 (en) | 1997-06-24 | 1997-06-24 | Method of constructing substructure inside PCV |
TW087108890A TW430820B (en) | 1997-06-24 | 1998-06-04 | Construction method for the substructure inside nuclear reactor containment vessel and the module structure used in this construction method |
CNB981150608A CN1163912C (en) | 1997-06-24 | 1998-06-23 | Method for building structural body at bottom of storing container of atomic reactor and module structural body |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP16686497A JP3419252B2 (en) | 1997-06-24 | 1997-06-24 | Method of constructing substructure inside PCV |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH1114779A JPH1114779A (en) | 1999-01-22 |
JP3419252B2 true JP3419252B2 (en) | 2003-06-23 |
Family
ID=15839060
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP16686497A Expired - Fee Related JP3419252B2 (en) | 1997-06-24 | 1997-06-24 | Method of constructing substructure inside PCV |
Country Status (3)
Country | Link |
---|---|
JP (1) | JP3419252B2 (en) |
CN (1) | CN1163912C (en) |
TW (1) | TW430820B (en) |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP5594987B2 (en) * | 2009-06-24 | 2014-09-24 | 三菱重工業株式会社 | Method for manufacturing concrete mount, concrete mount, and connecting material |
JP7321045B2 (en) * | 2019-09-26 | 2023-08-04 | 日立Geニュークリア・エナジー株式会社 | nuclear power plant |
-
1997
- 1997-06-24 JP JP16686497A patent/JP3419252B2/en not_active Expired - Fee Related
-
1998
- 1998-06-04 TW TW087108890A patent/TW430820B/en not_active IP Right Cessation
- 1998-06-23 CN CNB981150608A patent/CN1163912C/en not_active Expired - Fee Related
Also Published As
Publication number | Publication date |
---|---|
JPH1114779A (en) | 1999-01-22 |
TW430820B (en) | 2001-04-21 |
CN1203428A (en) | 1998-12-30 |
CN1163912C (en) | 2004-08-25 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JPH11514063A (en) | Top-to-foundation lifting method for building construction | |
JP5488895B2 (en) | Module structure, plant, plant construction method using module structure | |
JPH10266602A (en) | Method for constructing building of plant, and module structure to be used for construction thereof | |
JP3419252B2 (en) | Method of constructing substructure inside PCV | |
JP3283735B2 (en) | Method for constructing upper dry well of reactor containment vessel and module used for the method | |
JPH11337675A (en) | Reactor-containment vessel and its building method | |
CN212562460U (en) | Novel template support member for reinforced concrete silo dome | |
JP3399873B2 (en) | How to build a dome structure | |
JP3073155B2 (en) | How to set product groups for construction buildings | |
JP3445907B2 (en) | Construction method of reactor pressure vessel foundation and module used in the method | |
JP4352071B2 (en) | Construction method of reactor containment vessel | |
JPH09177070A (en) | Method and device for placing of steel bar cage for deep foundation | |
JP3462911B2 (en) | Reactor building | |
JP2873139B2 (en) | Condenser construction method for nuclear power plant turbine building. | |
JPH0270845A (en) | Construction apparatus | |
JP2945707B2 (en) | Installation method of pedestal supporting reactor pressure vessel | |
JP2521390B2 (en) | Installation method of pipe whip structure | |
JP3464817B2 (en) | How to build a building | |
JPS6025576B2 (en) | Building construction method | |
JP3559673B2 (en) | Plant building and construction method of the building | |
JPS6326215B2 (en) | ||
CN116181078A (en) | Construction method and hoisting equipment for AAC (advanced construction control) board of steel frame structure building wall | |
JPH08194085A (en) | Shroud suspending method for nuclear reactor and shroud structure | |
JP2000241584A (en) | Placing method for condenser | |
JP2901462B2 (en) | Lower drywell steel structure and method of installation |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20080418 Year of fee payment: 5 |
|
S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20080418 Year of fee payment: 5 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
S111 | Request for change of ownership or part of ownership |
Free format text: JAPANESE INTERMEDIATE CODE: R313111 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20080418 Year of fee payment: 5 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090418 Year of fee payment: 6 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090418 Year of fee payment: 6 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100418 Year of fee payment: 7 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110418 Year of fee payment: 8 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120418 Year of fee payment: 9 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120418 Year of fee payment: 9 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130418 Year of fee payment: 10 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20140418 Year of fee payment: 11 |
|
LAPS | Cancellation because of no payment of annual fees |