EP3587718B1 - Assembly comprising a base frame and a window frame mounted on the base frame - Google Patents
Assembly comprising a base frame and a window frame mounted on the base frame Download PDFInfo
- Publication number
- EP3587718B1 EP3587718B1 EP19180620.7A EP19180620A EP3587718B1 EP 3587718 B1 EP3587718 B1 EP 3587718B1 EP 19180620 A EP19180620 A EP 19180620A EP 3587718 B1 EP3587718 B1 EP 3587718B1
- Authority
- EP
- European Patent Office
- Prior art keywords
- frame
- wall
- window
- building
- tunnel
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000009413 insulation Methods 0.000 claims description 49
- 230000002093 peripheral effect Effects 0.000 claims description 24
- 239000012528 membrane Substances 0.000 claims description 19
- 238000009422 external insulation Methods 0.000 claims description 4
- 238000009434 installation Methods 0.000 description 12
- 238000009418 renovation Methods 0.000 description 11
- 238000004378 air conditioning Methods 0.000 description 3
- 238000010438 heat treatment Methods 0.000 description 3
- 238000003780 insertion Methods 0.000 description 3
- 230000037431 insertion Effects 0.000 description 3
- 238000011065 in-situ storage Methods 0.000 description 2
- 230000010354 integration Effects 0.000 description 2
- 238000004519 manufacturing process Methods 0.000 description 2
- 229910052751 metal Inorganic materials 0.000 description 2
- 239000002184 metal Substances 0.000 description 2
- 230000002787 reinforcement Effects 0.000 description 2
- 238000007789 sealing Methods 0.000 description 2
- 229910052782 aluminium Inorganic materials 0.000 description 1
- XAGFODPZIPBFFR-UHFFFAOYSA-N aluminium Chemical compound [Al] XAGFODPZIPBFFR-UHFFFAOYSA-N 0.000 description 1
- 230000000712 assembly Effects 0.000 description 1
- 238000000429 assembly Methods 0.000 description 1
- 230000004888 barrier function Effects 0.000 description 1
- 230000015556 catabolic process Effects 0.000 description 1
- 238000000576 coating method Methods 0.000 description 1
- 238000010276 construction Methods 0.000 description 1
- 230000008878 coupling Effects 0.000 description 1
- 238000010168 coupling process Methods 0.000 description 1
- 238000005859 coupling reaction Methods 0.000 description 1
- 238000006731 degradation reaction Methods 0.000 description 1
- 230000000593 degrading effect Effects 0.000 description 1
- 238000005265 energy consumption Methods 0.000 description 1
- 230000007613 environmental effect Effects 0.000 description 1
- 239000004794 expanded polystyrene Substances 0.000 description 1
- 239000003292 glue Substances 0.000 description 1
- 239000011800 void material Substances 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E06—DOORS, WINDOWS, SHUTTERS, OR ROLLER BLINDS IN GENERAL; LADDERS
- E06B—FIXED OR MOVABLE CLOSURES FOR OPENINGS IN BUILDINGS, VEHICLES, FENCES OR LIKE ENCLOSURES IN GENERAL, e.g. DOORS, WINDOWS, BLINDS, GATES
- E06B1/00—Border constructions of openings in walls, floors, or ceilings; Frames to be rigidly mounted in such openings
- E06B1/02—Base frames, i.e. template frames for openings in walls or the like, provided with means for securing a further rigidly-mounted frame; Special adaptations of frames to be fixed therein
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/62—Insulation or other protection; Elements or use of specified material therefor
- E04B1/74—Heat, sound or noise insulation, absorption, or reflection; Other building methods affording favourable thermal or acoustical conditions, e.g. accumulating of heat within walls
- E04B1/76—Heat, sound or noise insulation, absorption, or reflection; Other building methods affording favourable thermal or acoustical conditions, e.g. accumulating of heat within walls specifically with respect to heat only
- E04B1/762—Exterior insulation of exterior walls
- E04B1/7641—Elements for window or door openings, or for corners of the building
-
- E—FIXED CONSTRUCTIONS
- E06—DOORS, WINDOWS, SHUTTERS, OR ROLLER BLINDS IN GENERAL; LADDERS
- E06B—FIXED OR MOVABLE CLOSURES FOR OPENINGS IN BUILDINGS, VEHICLES, FENCES OR LIKE ENCLOSURES IN GENERAL, e.g. DOORS, WINDOWS, BLINDS, GATES
- E06B1/00—Border constructions of openings in walls, floors, or ceilings; Frames to be rigidly mounted in such openings
- E06B1/04—Frames for doors, windows, or the like to be fixed in openings
- E06B1/34—Coverings, e.g. protecting against weather, for decorative purposes
- E06B1/342—Reveal covering members disposed alongside of a window frame
-
- E—FIXED CONSTRUCTIONS
- E06—DOORS, WINDOWS, SHUTTERS, OR ROLLER BLINDS IN GENERAL; LADDERS
- E06B—FIXED OR MOVABLE CLOSURES FOR OPENINGS IN BUILDINGS, VEHICLES, FENCES OR LIKE ENCLOSURES IN GENERAL, e.g. DOORS, WINDOWS, BLINDS, GATES
- E06B1/00—Border constructions of openings in walls, floors, or ceilings; Frames to be rigidly mounted in such openings
- E06B1/56—Fastening frames to the border of openings or to similar contiguous frames
- E06B1/60—Fastening frames to the border of openings or to similar contiguous frames by mechanical means, e.g. anchoring means
- E06B1/6015—Anchoring means
-
- E—FIXED CONSTRUCTIONS
- E06—DOORS, WINDOWS, SHUTTERS, OR ROLLER BLINDS IN GENERAL; LADDERS
- E06B—FIXED OR MOVABLE CLOSURES FOR OPENINGS IN BUILDINGS, VEHICLES, FENCES OR LIKE ENCLOSURES IN GENERAL, e.g. DOORS, WINDOWS, BLINDS, GATES
- E06B1/00—Border constructions of openings in walls, floors, or ceilings; Frames to be rigidly mounted in such openings
- E06B1/62—Tightening or covering joints between the border of openings and the frame or between contiguous frames
-
- E—FIXED CONSTRUCTIONS
- E06—DOORS, WINDOWS, SHUTTERS, OR ROLLER BLINDS IN GENERAL; LADDERS
- E06B—FIXED OR MOVABLE CLOSURES FOR OPENINGS IN BUILDINGS, VEHICLES, FENCES OR LIKE ENCLOSURES IN GENERAL, e.g. DOORS, WINDOWS, BLINDS, GATES
- E06B1/00—Border constructions of openings in walls, floors, or ceilings; Frames to be rigidly mounted in such openings
- E06B1/62—Tightening or covering joints between the border of openings and the frame or between contiguous frames
- E06B1/64—Tightening or covering joints between the border of openings and the frame or between contiguous frames by loosely-inserted means, e.g. strip, resilient tongue
-
- E—FIXED CONSTRUCTIONS
- E06—DOORS, WINDOWS, SHUTTERS, OR ROLLER BLINDS IN GENERAL; LADDERS
- E06B—FIXED OR MOVABLE CLOSURES FOR OPENINGS IN BUILDINGS, VEHICLES, FENCES OR LIKE ENCLOSURES IN GENERAL, e.g. DOORS, WINDOWS, BLINDS, GATES
- E06B1/00—Border constructions of openings in walls, floors, or ceilings; Frames to be rigidly mounted in such openings
- E06B1/62—Tightening or covering joints between the border of openings and the frame or between contiguous frames
- E06B2001/628—Separate flexible joint covering strips; Flashings
Definitions
- the field of the invention is that of the design and manufacture of openings such as windows for buildings.
- the invention relates to a building wall with a window block for the renovation of a building with external thermal insulation (ITE).
- ITE external thermal insulation
- a widely used solution consists of laying a layer of thermal insulation on the outside of the building.
- this solution makes it possible to maintain an internal volume of the building equal to the internal volume before renovation.
- the insulating layer does not reduce the internal volume of the rooms and the occupants of the building can maintain an identical useful surface while benefiting from reduced energy consumption since the needs for heating and/or or air conditioning are less important.
- openings such as doors and windows, for example, are generally changed.
- the new openings also make it possible to reduce heating and/or air conditioning needs and provide a new “outside face” to the building.
- a known type of opening comprising a pre-frame is described by in the patent document published under the number DE 10 2004 015364 .
- EP2333219 describes an assembly comprising a pre-frame carrying insulation at its periphery and a window frame mounted in the pre-frame, the pre-frame being intended to be inserted into a window tunnel of a wall of a building through the 'outside.
- the pre-frame and the peripheral insulation have a different depth. More specifically, the peripheral insulation extends over a depth greater than that over which the pre-frame extends.
- the friction of the peripheral insulation against the walls of the tunnel tends to reduce the thickness of the peripheral insulation and, consequently, to reduce the insulating power of the latter by filling the void between the pre-frame and the tunnel walls.
- Handling the assembly prior to installation can also be made particularly difficult. Indeed, by their difference in depth, when the assembly is manipulated by grasping the pre-frame, the peripheral insulation is then cantilevered and tends to bend. Therefore, the installation of the assembly in the tunnel becomes difficult since it is necessary to straighten the peripheral insulation so that it is straight so as to allow its insertion into the tunnel.
- the object of the invention is in particular to overcome the drawbacks of the prior art. More specifically, the invention aims to provide a building wall with an assembly comprising a pre-frame carrying insulation at its periphery and a window frame mounted in the pre-frame, which is simple and quick to install.
- the invention also aims to provide such an assembly, the handling of which does not present any risk of damage to the peripheral insulation, or at the very least a degradation that is too slight to reduce the thermal insulation power of the assembly. .
- the invention also aims to provide such an assembly which has a high luminosity passage.
- Such a set facilitates the renovation of buildings, in particular the installation of windows offering good insulation, both acoustic and thermal.
- the first part of the pre-frame can be inserted from outside the building (a whole phase of the work can therefore be carried out without having to enter the dwellings possibly occupied by residents ), then the second part from inside the building.
- the presence of the air insulation membrane makes it possible to give the window block (comprising the first part of the pre-frame and the second part of the pre-frame) good thermal insulation.
- the air that can penetrate from the outside is thus blocked by the membrane which extends between the second part of the pre-frame and the window tunnel. It is thus possible to obtain a coefficient.
- the insulating element makes it possible to further improve the airtightness of the window block. This is particularly verified when the insulating element extends from the outer limit to the inner limit of the window tunnel.
- sealing is further improved when the insulating element extends over the entire periphery of the pre-frame.
- the first part of the pre-frame has at least one abutment for positioning the frame on the pre-frame.
- the frame has a slot intended to receive the abutment of the pre-frame.
- the slot and the positioning stop allow the first part of the pre-frame to be manufactured in the factory and to carry the window frame as soon as it leaves the factory. Installation in situ, ie on the building to be renovated, is thus facilitated. Indeed, the window frame is already positioned in relation to the wall, which avoids an operation of positioning and holding the frame prior to fixing it on the renovation site. It is specified that in situ, the working conditions and in particular the positioning conditions can be difficult or even precarious.
- the assembly comprises joint securing means of the pre-frame and the frame to the wall.
- the fixing of the frame and the pre-frame is therefore done by the same means so that the installation of the window unit is simple and quick. This is particularly verified when the fixed frame is already pre-positioned thanks to the positioning stop of the pre-frame and the slot in the fixed frame in which the positioning stop is received.
- this binding is designed to provide a thermal break as will be explained in more detail later.
- the air insulation membrane is attached to the frame.
- Fixing the insulation membrane to the frame ensures correct positioning of the insulation membrane when installing the pre-frame in the window tunnel.
- the fixed frame advantageously has a peripheral notch in which one end of the air insulation membrane is received.
- the peripheral notch ensures complete peripheral coverage by the insulation membrane.
- the first part of the pre-frame comprises a peripheral belt in which is intended to be integrated a thermal insulation layer from the outside fixed to the wall.
- the integration of the thermal insulation layer from the outside in the peripheral belt of the first part of the pre-frame makes it possible to increase the quality of insulation of the window unit. Indeed, the external thermal insulation layer being in contact with the first part of the pre-frame, there is no passageway for air between the external insulation layer and the pre-frame. -frame. The outside air can therefore not rush into the window tunnel towards the interior of the building.
- the first part of the door pre-frame can incorporate a roller shutter box.
- the roller shutter box and the roller shutter it contains can contribute to both thermal insulation (by creating an air zone between the outside of the roller shutter and the window) and light (by preventing light from entering the window). entering the building when the roller shutter is closed).
- the first part of the pre-frame comprises a folded outer edge forming a groove intended to receive a cover profile forming an outer trim of the assembly.
- the finish of the renovation can be made to measure by inserting a covering profile into the groove of the pre-frame, the covering profile being able in particular to be interchangeable at will, for example according to events to decorate the building.
- the first part of the pre-frame can be dismantled later if necessary without degrading the ITE.
- an assembly 1 according to the invention comprises a pre-frame 2 and a window frame 3.
- the assembly 1 is intended to be inserted into a window tunnel 4 of a wall 5 of a building.
- the building is in particular a building to be renovated or a new construction comprising an insulation layer 6 from the outside (ITE).
- the layer 6 of insulation from the outside is positioned outside the wall 5 and has an opening which defines with a light from the wall the tunnel 4 of the window.
- the pre-frame 2 has a first end 2a located towards the outside of the building and a second end 2b located towards the interior of the building.
- the pre-frame 2 is advantageously produced by a folded metal sheet or an assembly of several metal sheets assembled together to form a sheath extending between the first end 2a and the second end 2b, and in which the frame is mounted. 3, the sheath being intended to be inserted into the tunnel 4 of the window.
- the pre-frame 2 comprises a first part 21 in which the frame 3 is mounted, and a second part 22 butted to each other.
- first part 21 is intended to be inserted into the window tunnel 4 from the outside of the building
- second part 22 is intended to be inserted into the window tunnel 4 from the inside of the building.
- the first part 21 of the pre-frame 2 comprises a peripheral belt 23 in which the layer 6 of thermal insulation from the exterior is intended to be integrated. from the wall.
- the peripheral belt 23 extends from the first end 2a towards the second end 2b.
- the peripheral belt 23 forms, when seen in cross section, a notch in which the layer 6 of insulation is received from the outside, this notch being open towards the outside of the tunnel 4 of the window.
- Insulation is also ensured by the fact that the pre-frame 2 carries an insulating element 7 on its periphery.
- each of the first part 21 and of the second part 22 of the pre-frame 2 carries on its periphery the insulating element 7 intended to be inserted between the pre-frame 2 and the tunnel 4 of the window.
- the insulating element 7 is for example a layer of expanded polystyrene (notably known by its initials PSE) which surrounds each part 21, 22 of the pre-frame 2 over its entire periphery.
- PSE expanded polystyrene
- the first part 21 of the pre-frame 2 comprises a membrane 8 for air insulation.
- the insulation membrane 8 also forms a waterproof barrier.
- the air insulation membrane 8 is secured to the first part 21 of the pre-frame, and more particularly to the frame 3 of the window.
- the air insulation membrane 8 having a flexible peripheral strip 81 intended to be inserted between the second part 22 of the pre-frame and the window tunnel 4 when the two parts 21,22 of the pre-frame 2 are inserted in window tunnel 4.
- the frame 3 has a peripheral notch 31 in which is received one end 82 of the membrane 8 for air insulation.
- the end 82 of the membrane 8 can in particular be glued in the peripheral notch 31 to ensure that the membrane 8 is held on the first part 21 of the pre-frame 2.
- the first part 21 of the pre-frame 2 has, at a distal end 211, opposite the first end 2a, at least one abutment 212 for positioning frame 3.
- the abutment 212 is formed by folding the distal end 211 towards the inside of the pre-frame 2.
- the frame 3 then has a slot 32 intended to receive the abutment 212 of the pre-frame 2.
- a pre-solidarisation of the frame 3 on the first part 21 of the pre-frame 2 can be carried out by inserts 33 which sandwich the pre-frame 2 and a wall of the frame 3.
- the inserts 33 can also be replaced by rivets .
- the pre-coupling of the fixed frame 3 on the first part 21 of the pre-frame 2 is also carried out by a band of glue 34 between the fixed frame 3 and the first part 21 of the pre-frame 2.
- the final attachment of the pre-frame 2 with the frame 3 is achieved by means 35 of joint attachment of the pre-frame 2 and the frame 3 to the wall 5, as described below.
- the fixed frame 3 comprises an aluminum reinforcement 36 housed inside the sections constituting the frame of the fixed frame 3.
- the frame then has holes 37 made jointly in the profile and the reinforcement 36 to allow the pre-fixation of the frame 3 on the pre-frame 2 and the fixing of the assembly 1 to the wall 5 by the means 35 of fixing.
- the holes 37 emerging inside the frame that is to say visible from inside the building, can be blocked by plugs 38, as illustrated in the figure 4 .
- the first part 21 of the pre-frame 2 comprises, at the first end 2a, a folded outer edge 213 forming a groove 214 intended to receive a covering profile 9 forming an outer trim of the assembly 1.
- the first part 21 of the pre-frame 2 can incorporate a roller shutter box (not shown) to define an assembly that also allows light insulation between the inside and the outside of the building.
- the pre-frame 2 is equipped with the insulating element 7. More specifically, each part 21, 22 of the pre-frame 2 is formed and then receives, on its periphery, the insulating element 7 .
- the frame 3 (preferably with an opening associated with it) is pre-attached to the first part 21 of the pre-frame 2.
- installers can insert, from the outside, the first part 21 of the pre-frame 2 into the tunnel 4 of the window.
- This operation is advantageously carried out without removing the existing carpentry.
- the renovation operation is carried out in winter in an occupied building, this makes it possible to keep the heat inside the building and to avoid creating numerous drafts making the building unusable.
- the installers can extract the old carpentry from inside the building and then position the second part 22 of the pre-frame 2 in the tunnel 4 of the window.
- the insertion of the second part 22 of the pre-frame 2 in the window tunnel 4 allows the air insulation membrane 8 to be correctly arranged between the second part 22 of the pre-frame 2 and the wall. Furthermore, as shown in the figure 2 , when the second part 22 of the pre-frame 2 is inserted into the window tunnel 4, an inner end of the second part 22 of the pre-frame 2 is positioned between the frame 3 and the wall 5.
- the final fixing of the assembly 1 is then carried out by inserting the securing means 35 which engage in the wall 5.
- the pressure exerted by the securing means 35 tends to press the two parts 21, 22 of the pre-frame 2 on wall 5, thus preventing their removal from inside and outside the building.
- the installers position the cover plate(s) 9 in the or each groove 214 of the pre-frame 2, and the plugs 38 on the fixed frame 3.
- the installation of the assembly according to the invention therefore allows quick and simple renovation of the openings of a building on which a layer 6 of insulation from the outside has been added.
- the assembly 1 according to the invention is adaptable to any type of opening, in particular doors and sliding bays or fixed bays.
Landscapes
- Engineering & Computer Science (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Physics & Mathematics (AREA)
- Architecture (AREA)
- Mechanical Engineering (AREA)
- Acoustics & Sound (AREA)
- Electromagnetism (AREA)
- Specific Sealing Or Ventilating Devices For Doors And Windows (AREA)
- Door And Window Frames Mounted To Openings (AREA)
Description
Le domaine de l'invention est celui de la conception et de la fabrication d'ouvrants tels que les fenêtres pour bâtiments.The field of the invention is that of the design and manufacture of openings such as windows for buildings.
Plus précisément, l'invention concerne un mur de bâtiment avec un bloc de fenêtre pour la rénovation d'un bâtiment avec isolation thermique par l'extérieur (ITE).More specifically, the invention relates to a building wall with a window block for the renovation of a building with external thermal insulation (ITE).
L'évolution des normes environnementales implique que de nombreux bâtiments doivent être rénovés pour éviter les échanges thermiques et notamment les consommations importantes de chauffage ou de climatisation.The evolution of environmental standards means that many buildings must be renovated to avoid heat exchange and in particular high consumption of heating or air conditioning.
Pour cela, une solution fortement utilisée consiste à poser une couche d'isolation thermique à l'extérieur du bâtiment.For this, a widely used solution consists of laying a layer of thermal insulation on the outside of the building.
En effet, les études tendent à démontrer que l'isolation par l'extérieur procure de meilleures performances que l'isolation par l'intérieur.Indeed, studies tend to show that exterior insulation provides better performance than interior insulation.
De plus, cette solution permet de conserver un volume interne au bâtiment égal au volume interne avant rénovation. Autrement dit, en isolant par l'extérieur du bâtiment, la couche isolante ne réduit pas le volume interne des pièces et les occupants du bâtiment peuvent conserver une surface utile identique tout en bénéficiant d'une consommation énergétique réduite puisque les besoins en chauffage et/ou climatisation sont moins importants.In addition, this solution makes it possible to maintain an internal volume of the building equal to the internal volume before renovation. In other words, by insulating from the outside of the building, the insulating layer does not reduce the internal volume of the rooms and the occupants of the building can maintain an identical useful surface while benefiting from reduced energy consumption since the needs for heating and/or or air conditioning are less important.
Outre l'isolation, les ouvrants tels que les portes et fenêtres par exemple sont généralement changés. Les nouveaux ouvrants permettent également de réduire les besoins en chauffage et/ou climatisation et permettent d'offrir un nouveau « visage extérieur » au bâtiment.In addition to the insulation, openings such as doors and windows, for example, are generally changed. The new openings also make it possible to reduce heating and/or air conditioning needs and provide a new “outside face” to the building.
Un type d'ouvrant connu comprenant un pré-cadre est décrit par dans le document de brevet publié sous le numéro
Toutefois, lorsque la rénovation d'un bâtiment fait intervenir l'isolation par l'extérieur, l'intégration de nouvelles fenêtres peut devenir compliquée.However, when the renovation of a building involves external insulation, the integration of new windows can become complicated.
En effet, l'utilisation d'une couche isolante par l'extérieur demande une structure particulière du bloc fenêtre pour que celui-ci soit à la fois facilement installable, mais également qu'il assure une isolation thermique importante entre l'intérieur et l'extérieur du bâtiment.Indeed, the use of an insulating layer from the outside requires a particular structure of the window unit so that it is both easily installable, but also that it provides significant thermal insulation between the interior and the exterior. building exterior.
Le document de brevet publié sous le numéro
Cet ensemble n'est pas sans inconvénient.This set is not without its drawbacks.
En effet, le pré-cadre et l'isolation périphérique présentent une profondeur différente. Plus précisément, l'isolation périphérique s'étend sur une profondeur supérieure à celle sur laquelle s'étend le pré-cadre.Indeed, the pre-frame and the peripheral insulation have a different depth. More specifically, the peripheral insulation extends over a depth greater than that over which the pre-frame extends.
Cette différence de profondeur pose notamment des problèmes en termes d'installation de l'ensemble ainsi qu'en termes de tenue de l'isolation périphérique préalablement à l'installation de l'ensemble et lorsque l'ensemble est installé.This difference in depth poses problems in particular in terms of installation of the assembly as well as in terms of holding the peripheral insulation prior to the installation of the assembly and when the assembly is installed.
L'installation de l'ensemble est rendue difficile notamment lorsque le tunnel présente une profondeur importante. Il est alors nécessaire de correctement positionner l'ensemble en regard du tunnel avant insertion sous peine de dégrader l'isolation périphérique par frottement contre les parois du tunnel.The installation of the assembly is made difficult in particular when the tunnel has a significant depth. It is then necessary to position the assembly correctly opposite the tunnel before insertion, otherwise the peripheral insulation will be damaged by friction against the walls of the tunnel.
Par ailleurs, le frottement de l'isolation périphérique contre les parois du tunnel tend à diminuer l'épaisseur de l'isolation périphérique et, par conséquent, à réduire le pouvoir isolant de cette dernière par remplissage du vide entre le pré-cadre et les parois du tunnel.Moreover, the friction of the peripheral insulation against the walls of the tunnel tends to reduce the thickness of the peripheral insulation and, consequently, to reduce the insulating power of the latter by filling the void between the pre-frame and the tunnel walls.
La manipulation de l'ensemble préalablement à l'installation peut également être rendue particulièrement difficile. En effet, par leur différence de profondeur, lorsque l'ensemble est manipulé en saisissant le pré-cadre, l'isolation périphérique se trouve alors en porte à faux et tend à se courber. Dès lors, l'installation de l'ensemble dans le tunnel devient difficile puisqu'il faut redresser l'isolation périphérique pour que celle-ci soit rectiligne de sorte à permettre son insertion dans le tunnel.Handling the assembly prior to installation can also be made particularly difficult. Indeed, by their difference in depth, when the assembly is manipulated by grasping the pre-frame, the peripheral insulation is then cantilevered and tends to bend. Therefore, the installation of the assembly in the tunnel becomes difficult since it is necessary to straighten the peripheral insulation so that it is straight so as to allow its insertion into the tunnel.
Pour pallier à cela, il est possible d'augmenter l'épaisseur de l'isolation périphérique de sorte à la rigidifier. Toutefois, une telle augmentation de l'épaisseur réduit l'espace alloué à l'ouvrant et réduit d'autant la luminosité entrante dans le bâtiment pour une fenêtre, ou l'espace de passage pour une porte.To overcome this, it is possible to increase the thickness of the peripheral insulation so as to stiffen it. However, such an increase in thickness reduces the space allocated to the sash and correspondingly reduces the light entering the building for a window, or the passage space for a door.
En outre, une telle augmentation de l'épaisseur va alors à l'encontre du souhait général des occupants qui souhaitent des volumes internes les plus lumineux possibles, ou à tout le moins au moins aussi lumineux qu'avant la rénovation du bâtiment, tout en étant correctement isolés thermiquement. C'est d'ailleurs pour répondre à cette attente, que des revêtements isolants de faible épaisseur ont été développés.In addition, such an increase in thickness then goes against the general wish of the occupants who want the brightest possible internal volumes, or at the very least at least as bright as before the renovation of the building, while being properly thermally insulated. It is moreover to meet this expectation that thin insulating coatings have been developed.
Les documents de brevets publiés sous les numéros
L'invention a notamment pour objectif de palier les inconvénients de l'art antérieur. Plus précisément, l'invention a pour objectif de proposer un mur de bâtiment avec un ensemble comprenant un pré-cadre portant à sa périphérie une isolation et un dormant de fenêtre monté dans le pré-cadre, qui soit simple et rapide d'installation.The object of the invention is in particular to overcome the drawbacks of the prior art. More specifically, the invention aims to provide a building wall with an assembly comprising a pre-frame carrying insulation at its periphery and a window frame mounted in the pre-frame, which is simple and quick to install.
L'invention a également pour objectif de fournir un tel ensemble dont la manipulation ne présente pas de risque d'endommagement de l'isolation périphérique, ou à tout le moins une dégradation trop faible pour réduire le pouvoir d'isolation thermique de l'ensemble.The invention also aims to provide such an assembly, the handling of which does not present any risk of damage to the peripheral insulation, or at the very least a degradation that is too slight to reduce the thermal insulation power of the assembly. .
L'invention a en outre pour objectif de fournir un tel ensemble qui présente un passage de luminosité important.The invention also aims to provide such an assembly which has a high luminosity passage.
Ces objectifs, ainsi que d'autres qui apparaîtront par la suite, sont atteints grâce à l'invention qui a pour objet un mur de bâtiment selon la revendication 1.These objectives, as well as others which will appear subsequently, are achieved thanks to the invention which relates to a building wall according to
Un tel ensemble permet de faciliter la rénovation des bâtiments, notamment la mise en place de fenêtres offrant une bonne isolation à la fois acoustique et thermique.Such a set facilitates the renovation of buildings, in particular the installation of windows offering good insulation, both acoustic and thermal.
En effet, lors de la rénovation d'un bâtiment, on peut insérer la première partie du pré-cadre depuis l'extérieur du bâtiment (toute une phase des travaux pouvant donc être réalisée sans avoir à entrer dans les logements éventuellement occupés par des résidents), puis la deuxième partie depuis l'intérieur du bâtiment.Indeed, during the renovation of a building, the first part of the pre-frame can be inserted from outside the building (a whole phase of the work can therefore be carried out without having to enter the dwellings possibly occupied by residents ), then the second part from inside the building.
Par ailleurs la présence de la membrane d'isolation à l'air permet de conférer au bloc fenêtre (comprenant la première patrie du pré-cadre et la deuxième partie du pré-cadre) une bonne isolation thermique. L'air pouvant pénétrer depuis l'extérieur est ainsi bloqué par la membrane qui s'étend entre la deuxième partie du pré-cadre et le tunnel de fenêtre. Il est ainsi possible d'obtenir un coefficient.Furthermore, the presence of the air insulation membrane makes it possible to give the window block (comprising the first part of the pre-frame and the second part of the pre-frame) good thermal insulation. The air that can penetrate from the outside is thus blocked by the membrane which extends between the second part of the pre-frame and the window tunnel. It is thus possible to obtain a coefficient.
L'élément isolant permet d'améliorer encore l'étanchéité à l'air du bloc de fenêtre. Cela est particulièrement vérifié lorsque l'élément isolant s'étend depuis la limite extérieure jusqu'à la limite intérieure du tunnel de fenêtre.The insulating element makes it possible to further improve the airtightness of the window block. This is particularly verified when the insulating element extends from the outer limit to the inner limit of the window tunnel.
De même, l'étanchéité est encore améliorée lorsque l'élément isolant s'étend sur toute la périphérie du pré-cadre.Similarly, sealing is further improved when the insulating element extends over the entire periphery of the pre-frame.
Avantageusement, la première partie du pré-cadre présente au moins une butée de positionnement du dormant sur le pré-cadre.Advantageously, the first part of the pre-frame has at least one abutment for positioning the frame on the pre-frame.
Dans ce cas, le dormant présente une fente destinée à recevoir la butée du pré-cadre.In this case, the frame has a slot intended to receive the abutment of the pre-frame.
La fente et la butée de positionnement permettent que la première partie du pré-cadre puisse être fabriquée en usine et qu'elle porte le dormant de la fenêtre dès sa sortie d'usine. L'installation in situ, c'est-à-dire sur le bâtiment à rénover, s'en trouve ainsi facilitée. En effet, le dormant de fenêtre est déjà positionné par rapport au mur, ce qui évite une opération de positionnement et de maintien du dormant préalablement à sa fixation sur le site de rénovation. Il est précisé qu'in situ, les conditions de travail et notamment les conditions de positionnement peuvent être difficiles voire précaires.The slot and the positioning stop allow the first part of the pre-frame to be manufactured in the factory and to carry the window frame as soon as it leaves the factory. Installation in situ, ie on the building to be renovated, is thus facilitated. Indeed, the window frame is already positioned in relation to the wall, which avoids an operation of positioning and holding the frame prior to fixing it on the renovation site. It is specified that in situ, the working conditions and in particular the positioning conditions can be difficult or even precarious.
Selon un mode de réalisation préféré, l'ensemble comprend des moyens de solidarisation conjointe du pré-cadre et du dormant au mur.According to a preferred embodiment, the assembly comprises joint securing means of the pre-frame and the frame to the wall.
La fixation du dormant et du pré-cadre se fait donc par le même moyen si bien que l'installation du bloc fenêtre est simple et rapide. Cela est notamment vérifié lorsque le dormant est déjà pré-positionné grâce à la butée de positionnement du pré-cadre et à la fente du dormant dans laquelle est reçue la butée de positionnement.The fixing of the frame and the pre-frame is therefore done by the same means so that the installation of the window unit is simple and quick. This is particularly verified when the fixed frame is already pre-positioned thanks to the positioning stop of the pre-frame and the slot in the fixed frame in which the positioning stop is received.
En outre, cette fixation est conçue pour procurer une rupture de pont thermique comme cela va être explicité plus en détails par la suite.In addition, this binding is designed to provide a thermal break as will be explained in more detail later.
La membrane d'isolation à l'air est solidaire du dormant.The air insulation membrane is attached to the frame.
La fixation de la membrane d'isolation au dormant permet d'assurer un bon positionnement de la membrane d'isolation lors de l'installation du pré-cadre dans le tunnel de fenêtre.Fixing the insulation membrane to the frame ensures correct positioning of the insulation membrane when installing the pre-frame in the window tunnel.
A cet effet, le dormant présente avantageusement une encoche périphérique dans laquelle est reçue une extrémité de la membrane d'isolation à l'air.To this end, the fixed frame advantageously has a peripheral notch in which one end of the air insulation membrane is received.
L'encoche périphérique assure une couverture périphérique complète par la membrane d'isolation.The peripheral notch ensures complete peripheral coverage by the insulation membrane.
Selon un mode de réalisation avantageux, la première partie du pré-cadre comprend une ceinture périphérique dans laquelle est destinée à venir s'intégrer une couche d'isolation thermique par l'extérieur solidaire du mur.According to an advantageous embodiment, the first part of the pre-frame comprises a peripheral belt in which is intended to be integrated a thermal insulation layer from the outside fixed to the wall.
L'intégration de la couche d'isolation thermique par l'extérieur dans la ceinture périphérique de la première partie du pré-cadre permet d'augmenter la qualité d'isolation du bloc de fenêtre. En effet, la couche d'isolation thermique par l'extérieur étant au contact de la première partie du pré-cadre, il n'existe pas de couloir de passage d'air entre la couche d'isolation par l'extérieur et le pré-cadre. L'air extérieur ne peut donc pas s'engouffrer dans le tunnel de fenêtre vers l'intérieur du bâtiment.The integration of the thermal insulation layer from the outside in the peripheral belt of the first part of the pre-frame makes it possible to increase the quality of insulation of the window unit. Indeed, the external thermal insulation layer being in contact with the first part of the pre-frame, there is no passageway for air between the external insulation layer and the pre-frame. -frame. The outside air can therefore not rush into the window tunnel towards the interior of the building.
Avantageusement, la première partie du pré-cadre porte peut intégrer un coffre de volet roulant.Advantageously, the first part of the door pre-frame can incorporate a roller shutter box.
Le coffre de volet roulant et le volet roulant qu'il contient peuvent participer à l'isolation à la fois thermique (en créant une zone d'air entre l'extérieur du volet roulant et la fenêtre) et lumineuse (en empêchant la lumière d'entrer dans le bâtiment lorsque le volet roulant est fermé).The roller shutter box and the roller shutter it contains can contribute to both thermal insulation (by creating an air zone between the outside of the roller shutter and the window) and light (by preventing light from entering the window). entering the building when the roller shutter is closed).
De préférence, la première partie du pré-cadre comprend un bord externe replié formant une gorge destinée à recevoir un profil de recouvrement formant un enjoliveur extérieur de l'ensemble.Preferably, the first part of the pre-frame comprises a folded outer edge forming a groove intended to receive a cover profile forming an outer trim of the assembly.
La finition de la rénovation peut être faite sur mesure par l'insertion dans la gorge du pré-cadre d'un profil de recouvrement, le profil de recouvrement pouvant notamment être interchangeable à souhait, par exemple en fonction de manifestations pour décorer le bâtiment.The finish of the renovation can be made to measure by inserting a covering profile into the groove of the pre-frame, the covering profile being able in particular to be interchangeable at will, for example according to events to decorate the building.
Il est à noter que la première partie du pré-cadre peut être démontée ultérieurement en cas de besoin sans dégrader l'ITE.It should be noted that the first part of the pre-frame can be dismantled later if necessary without degrading the ITE.
D'autres caractéristiques et avantages de l'invention apparaîtront plus clairement à la lecture de la description suivante d'un mode de réalisation préférentiel de l'invention, donné à titre d'exemple illustratif et non limitatif, et des dessins annexés parmi lesquels :
- la
figure 1 est une vue schématique en coupe transversale montrant un ensemble selon l'invention installé dans un tunnel de fenêtre d'un bâtiment ; - la
figure 2 est une vue de détail en coupe transversale illustrant la fixation de l'ensemble selon l'invention dans le tunnel de fenêtre ; - la
figure 3 est une vue en section d'un dormant de fenêtre de l'ensemble selon l'invention ; - la
figure 4 est une vue schématique en section transversale montrant la solidarisation du dormant sur le pré-cadre ; - la
figure 5 est une vue de détail schématique en coupe transversale montrant une extrémité de la première partie du pré-cadre de l'ensemble selon l'invention.
- there
figure 1 is a schematic cross-sectional view showing an assembly according to the invention installed in a window tunnel of a building; - there
picture 2 is a cross-sectional detail view illustrating the fixing of the assembly according to the invention in the window tunnel; - there
picture 3 - there
figure 4 is a schematic cross-sectional view showing the attachment of the fixed frame to the pre-frame; - there
figure 5 is a schematic detail view in cross section showing one end of the first part of the pre-frame of the assembly according to the invention.
Tel qu'illustré sur la
L'ensemble 1 est destiné à être inséré dans un tunnel 4 de fenêtre d'un mur 5 de bâtiment.The
Le bâtiment est notamment un bâtiment à rénover ou une construction neuve comprenant une couche d'isolation 6 par l'extérieur (ITE).The building is in particular a building to be renovated or a new construction comprising an
La couche 6 d'isolation par l'extérieur est positionnée à l'extérieur du mur 5 et présente une ouverture qui définit avec une lumière du mur le tunnel 4 de fenêtre.The
Le pré-cadre 2 présente une première extrémité 2a située vers l'extérieur du bâtiment et une deuxième extrémité 2b située vers l'intérieur du bâtiment.The pre-frame 2 has a
Le pré-cadre 2 est avantageusement réalisé par une tôle métallique pliée ou un assemblage de plusieurs tôles métalliques assemblées les unes aux autres pour former un fourreau s'étendant entre la première extrémité 2a et la deuxième extrémité 2b, et dans lequel est monté le dormant 3, le fourreau étant destiné à être inséré dans le tunnel 4 de fenêtre.The pre-frame 2 is advantageously produced by a folded metal sheet or an assembly of several metal sheets assembled together to form a sheath extending between the
En référence aux
Plus précisément, la première partie 21 est destinée à être insérée dans le tunnel 4 de fenêtre par l'extérieur du bâtiment, et la deuxième partie 22 est destinée à être insérée dans le tunnel 4 de fenêtre par l'intérieur du bâtiment.More specifically, the first part 21 is intended to be inserted into the window tunnel 4 from the outside of the building, and the second part 22 is intended to be inserted into the window tunnel 4 from the inside of the building.
Pour permettre d'isoler l'intérieur du bâtiment de l'extérieur, la première partie 21 du pré-cadre 2 comprend une ceinture 23 périphérique dans laquelle est destinée à venir s'intégrer la couche 6 d'isolation thermique par l'extérieur solidaire du mur. La ceinture 23 périphérique s'étend depuis la première extrémité 2a vers la deuxième extrémité 2b.To make it possible to isolate the interior of the building from the exterior, the first part 21 of the pre-frame 2 comprises a
Comme cela est visible sur la
L'isolation est également assurée par le fait que le pré-cadre 2 porte un élément 7 isolant sur sa périphérie.Insulation is also ensured by the fact that the pre-frame 2 carries an insulating
Plus particulièrement, chacune de la première partie 21 et de la deuxième partie 22 du pré-cadre 2 porte sur sa périphérie l'élément 7 isolant destiné à être intercalé entre le pré-cadre 2 et le tunnel 4 de fenêtre.More particularly, each of the first part 21 and of the second part 22 of the pre-frame 2 carries on its periphery the insulating
L'élément 7 isolant est par exemple une couche de polystyrène expansé (notamment connue sous ses initiales PSE) qui entoure chaque partie 21, 22 du pré-cadre 2 sur l'intégralité de sa périphérie.The insulating
Par ailleurs, toujours à des fins d'étanchéité, la première partie 21 du pré-cadre 2 comprend une membrane 8 d'isolation à l'air.Furthermore, still for sealing purposes, the first part 21 of the pre-frame 2 comprises a membrane 8 for air insulation.
La membrane 8 d'isolation forme également une barrière étanche à l'eau.The insulation membrane 8 also forms a waterproof barrier.
Tel qu'illustré sur les
En référence à la
Pour cela, le dormant 3 présente une encoche 31 périphérique dans laquelle est reçue une extrémité 82 de la membrane 8 d'isolation à l'air. L'extrémité 82 de la membrane 8 peut notamment être collée dans l'encoche 31 périphérique pour assurer un maintien de la membrane 8 sur la première partie 21 du pré-cadre 2.For this, the
Pour faciliter l'assemblage du dormant 3 avec la première partie 21 du pré-cadre 2, la première partie 21 du pré-cadre 2 présente, à une extrémité 211 distale, opposée à la première extrémité 2a, au moins une butée 212 de positionnement du dormant 3.To facilitate the assembly of the
Plus précisément, la butée 212 est formée par repli de l'extrémité 211 distale vers l'intérieur du pré-cadre 2.More specifically, the
Le dormant 3 présente alors une fente 32 destinée à recevoir la butée 212 du pré-cadre 2.The
Une pré-solidarisation du dormant 3 sur la première partie 21 du pré-cadre 2 peut être réalisée par des inserts 33 qui prennent en sandwich le pré-cadre 2 et une paroi du dormant 3. Les inserts 33 peuvent également être remplacés par des rivets.A pre-solidarisation of the
Avantageusement, la pré-solidarisation du dormant 3 sur la première partie 21 du pré-cadre 2 est également réalisée par un bandeau de colle 34 entre le dormant 3 et la première partie 21 du pré-cadre 2.Advantageously, the pre-coupling of the fixed
La solidarisation définitive du pré-cadre 2 avec le dormant 3 est réalisée par des moyens 35 de solidarisation conjointe du pré-cadre 2 et du dormant 3 au mur 5, comme décrit ci-après.The final attachment of the pre-frame 2 with the
Par ailleurs, le dormant 3 comprend un renfort 36 en aluminium logé à l'intérieur des profilés constituant le cadre du dormant 3.Furthermore, the fixed
Le dormant présente alors des perçages 37 réalisés conjointement dans le profilé et le renfort 36 pour permettre la pré-solidarisation du dormant 3 sur le pré-cadre 2 et la solidarisation de l'ensemble 1 au mur 5 par les moyens 35 de fixation.The frame then has
Lors de l'installation, les perçages 37 débouchant à l'intérieur du dormant, c'est-à-dire visibles depuis l'intérieur du bâtiment, peuvent bouchés par des bouchons 38, tel qu'illustré sur la
En référence à la
Avantageusement, la première partie 21 du pré-cadre 2 peut intégrer un coffre de volet roulant (non illustré) pour définir un ensemble permettant également une isolation lumineuse entre l'intérieur et l'extérieur du bâtiment.Advantageously, the first part 21 of the pre-frame 2 can incorporate a roller shutter box (not shown) to define an assembly that also allows light insulation between the inside and the outside of the building.
Lors de la fabrication en usine, le pré-cadre 2 est équipé de l'élément isolant 7. Plus précisément, chaque partie 21, 22 du pré-cadre 2 est formée puis reçoit, sur sa périphérie, l'élément 7 isolant. Le dormant 3 (de préférence avec un ouvrant qui lui est associé) est pré-solidarisé à la première partie 21 du pré-cadre 2.During factory production, the pre-frame 2 is equipped with the insulating
Lors de l'installation sur un bâtiment en rénovation, les installateurs peuvent insérer, par l'extérieur, la première partie 21 du pré-cadre 2 dans le tunnel 4 de fenêtre.During installation on a building under renovation, installers can insert, from the outside, the first part 21 of the pre-frame 2 into the tunnel 4 of the window.
Cette opération est avantageusement réalisée dans dépose de la menuiserie existante. Lorsque l'opération de rénovation est réalisée en hiver dans un bâtiment occupé, cela permet de conserver la chaleur à l'intérieur du bâtiment et d'éviter de créer de nombreux courants d'air rendant inutilisable le bâtiment.This operation is advantageously carried out without removing the existing carpentry. When the renovation operation is carried out in winter in an occupied building, this makes it possible to keep the heat inside the building and to avoid creating numerous drafts making the building unusable.
Lorsque la première partie 21 du pré-cadre est insérée dans le tunnel 4 de fenêtre, les installateurs peuvent extraite l'ancienne menuiserie par l'intérieur du bâtiment puis positionner la deuxième partie 22 du pré-cadre 2 dans le tunnel 4 de fenêtre.When the first part 21 of the pre-frame is inserted into the tunnel 4 of the window, the installers can extract the old carpentry from inside the building and then position the second part 22 of the pre-frame 2 in the tunnel 4 of the window.
L'insertion de la deuxième partie 22 du pré-cadre 2 dans le tunnel 4 de fenêtre permet que la membrane 8 d'isolation à l'air soit correctement agencé entre la deuxième partie 22 du pré-cadre 2 et le mur. En outre, tel qu'illustré sur la
La fixation définitive de l'ensemble 1 est alors effectuée par insertion des moyens 35 de solidarisation qui viennent en prise dans le mur 5. La pression exercée par les moyens 35 de solidarisation tend à plaquer les deux parties 21, 22 du pré-cadre 2 sur le mur 5, empêchant ainsi leur retrait par l'intérieur et l'extérieur du bâtiment.The final fixing of the
Pour finir l'installation, les installateurs positionnent le ou les plats 9 de recouvrement dans la ou chaque gorge 214 du pré-cadre 2, et les bouchons 38 sur le dormant 3.To complete the installation, the installers position the cover plate(s) 9 in the or each
L'installation de l'ensemble selon l'invention permet donc une rénovation rapide et simple des ouvrants d'un bâtiment sur lequel une couche 6 d'isolation par l'extérieur a été ajoutée.The installation of the assembly according to the invention therefore allows quick and simple renovation of the openings of a building on which a
Bien que la description concerne un bloc de fenêtre, l'ensemble 1 selon l'invention est adaptable à tout type d'ouvrant, notamment les portes et les baies coulissantes ou les baies fixes.Although the description relates to a window unit, the
Claims (9)
- A wall (5) of a building, the wall having an external insulation layer integral with the wall and a window tunnel (4) into which is inserted an assembly (1) comprising a pre-frame (2) and a window frame (3) mounted in the pre-frame (2), the pre-frame (2) comprising a first part (21) within which the window frame (3) is mounted, the first part (21) being inserted into the tunnel (4) from outside the building;
characterised in that:- the pre-frame (2) comprises a second part (22) to be abutted to the first part (21), the second part (22) being inserted into the tunnel (4) from inside the building,- the first part (21) of the pre-frame comprises an air insulation membrane (8) integral with the window frame (3), the air insulation membrane (8) having a flexible peripheral strip (81) sandwiched between the second part (22) of the pre-frame (2) and the window tunnel (4),and in that the first part (21) and the second part (22) of the pre-frame (2) carry on their periphery an insulating element (7) sandwiched between the pre-frame (2) and the window tunnel (4). - The wall (5) according to claim 1, characterised in that the first part (21) of the pre-frame (2) has at least one stop (212) for positioning the frame (3) on the pre-frame (2).
- The wall (5) according to the preceding claim, characterised in that the frame (3) has a slot (32) for receiving the stop (212) of the pre-frame (2).
- The wall (5) according to any of the preceding claims, characterised in that it comprises means (35) for jointly securing the pre-frame (2) and the frame (3) to the wall (5) .
- The wall (5) according to any of the preceding claims, characterised in that the air insulation membrane (8) is integral with the frame (3).
- The wall (5) according to the preceding claim, characterised in that the frame (3) has a peripheral notch (31) in which one end (82) of the air insulation membrane (8) is received.
- The wall (5) according to any of the preceding claims, characterised in that the first part (21) of the pre-frame (2) comprises a peripheral belt (23) into which a thermal external insulation layer (6) integral with the wall (5) is to become integrated.
- The wall (5) according to any of the preceding claims, characterised in that the first part (21) of the pre-frame (2) integrates a roller shutter box.
- The wall (5) according to any of the preceding claims, characterised in that the first part (21) of the pre-frame comprises a folded external edge (213) forming a groove (214) for receiving a coverage profile (9) forming an external trim for the assembly (1).
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
FR1856046A FR3083257B1 (en) | 2018-06-29 | 2018-06-29 | SET INCLUDING A PRE-FRAME AND A WINDOW FRAME MOUNTED IN THE PRE-FRAME |
Publications (3)
Publication Number | Publication Date |
---|---|
EP3587718A1 EP3587718A1 (en) | 2020-01-01 |
EP3587718C0 EP3587718C0 (en) | 2023-07-12 |
EP3587718B1 true EP3587718B1 (en) | 2023-07-12 |
Family
ID=63638056
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
EP19180620.7A Active EP3587718B1 (en) | 2018-06-29 | 2019-06-17 | Assembly comprising a base frame and a window frame mounted on the base frame |
Country Status (2)
Country | Link |
---|---|
EP (1) | EP3587718B1 (en) |
FR (1) | FR3083257B1 (en) |
Family Cites Families (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CH671995A5 (en) * | 1988-03-15 | 1989-10-13 | Sergio Lucchini | Prefab. metal frame for window opening - has faces for connection to window frame and shutter guide, and has sloping sill and top member |
DE10315263B4 (en) * | 2003-04-03 | 2006-06-29 | Thyssen Polymer Gmbh | Container with window |
DE102004015364A1 (en) * | 2004-03-30 | 2005-10-20 | Hans Schmidt | Rectangular window frame or doorframe for building is permanently attached to the brickwork along two sides |
DE602008004523D1 (en) * | 2008-09-05 | 2011-02-24 | Suedtirol Fenster S R L | Prefabricated door or window frame unit with insulating edging |
DE202009016152U1 (en) * | 2009-11-26 | 2010-03-04 | Mammut Bausysteme Gmbh | frame |
AT518553B1 (en) * | 2016-10-31 | 2017-11-15 | Müller Günther | DENSITY PROFILE FOR SEALING A WINDOW OR DOOR STORE IN THE FIELD OF A WINDOW BENCH |
-
2018
- 2018-06-29 FR FR1856046A patent/FR3083257B1/en active Active
-
2019
- 2019-06-17 EP EP19180620.7A patent/EP3587718B1/en active Active
Also Published As
Publication number | Publication date |
---|---|
EP3587718C0 (en) | 2023-07-12 |
FR3083257B1 (en) | 2020-12-25 |
EP3587718A1 (en) | 2020-01-01 |
FR3083257A1 (en) | 2020-01-03 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
EP3587718B1 (en) | Assembly comprising a base frame and a window frame mounted on the base frame | |
EP1953326A1 (en) | Frame of a door or window with sliding opening including a hidden leaf vertical upright | |
EP2186985B1 (en) | Closure of a building comprising a frame with thermal-bridge breakage equipped with an L-shaped insulating profile. | |
EP3020907B1 (en) | Fastener for outer threshold and combination of such a fastener and a threshold | |
EP2491197A2 (en) | Cover element that can produce electricity | |
EP0643192B1 (en) | Roller shutter box assembly | |
EP3859118A1 (en) | Door leaf equipped with a frame with adaptable thickness | |
EP3670326B1 (en) | Wall covering panel for aircraft with built-in insulation | |
EP3372770B1 (en) | Fastening of a sliding window in a building | |
EP2314815B1 (en) | Doors, windows or the like for buildings having means for increasing their insulation | |
EP3587719B1 (en) | Assembly for installing and/or renovating a window | |
EP0745750B1 (en) | Glazing panel | |
WO2021160962A1 (en) | System for fastening a side glazing of a means of transport with a lock | |
EP1443171A1 (en) | Sealing arrangement for a closing system of an opening with at least one sliding wing | |
FR2849463A1 (en) | Access trap door for pipes and cables in buildings has one-piece fixed surround and door with stepped surfaces and fire-resistant seal | |
EP3296498A1 (en) | Hidden frame and method of mounting of corresponding finishing wall | |
FR3151867A1 (en) | JOINERY RECEPTION FRAME FOR LIGHT-FRAME BUILDING, LIGHT-FRAME BUILDING EQUIPPED WITH AT LEAST ONE SUCH FRAME AND METHOD FOR ASSEMBLING SUCH A FRAME | |
EP1985791B1 (en) | Metal slat for roller shutters or sectional gates | |
FR2968690A1 (en) | Covering module for roofing and cladding of roofs or facades of e.g. restoration building, has insulating block formed with cavity extending longitudinally in block for emerging on sides of block such that block is traversed by flow of air | |
EP2426301A1 (en) | Device for integrating a roller shutter in a construction opening | |
FR3106845A1 (en) | DOOR OPENER EQUIPPED WITH AN EXPANSION COMPENSATION SYSTEM | |
EP1046777A1 (en) | Finishing strip for roller shutter box | |
EP3916168A1 (en) | Bracing device for cladding elements | |
EP0687791B1 (en) | Mounting of a roller shutter box on the outside of a building | |
EP1988247A2 (en) | Load-bearing frame, in particular for a door or window frame, door and method for installing a panel in such frame |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PUAI | Public reference made under article 153(3) epc to a published international application that has entered the european phase |
Free format text: ORIGINAL CODE: 0009012 |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: THE APPLICATION HAS BEEN PUBLISHED |
|
AK | Designated contracting states |
Kind code of ref document: A1 Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR |
|
AX | Request for extension of the european patent |
Extension state: BA ME |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: REQUEST FOR EXAMINATION WAS MADE |
|
17P | Request for examination filed |
Effective date: 20200214 |
|
RBV | Designated contracting states (corrected) |
Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: EXAMINATION IS IN PROGRESS |
|
17Q | First examination report despatched |
Effective date: 20220222 |
|
RIC1 | Information provided on ipc code assigned before grant |
Ipc: E04B 1/76 20060101ALI20230202BHEP Ipc: E06B 1/34 20060101ALI20230202BHEP Ipc: E06B 1/62 20060101ALI20230202BHEP Ipc: E06B 1/64 20060101ALI20230202BHEP Ipc: E06B 1/60 20060101ALI20230202BHEP Ipc: E06B 1/02 20060101AFI20230202BHEP |
|
GRAP | Despatch of communication of intention to grant a patent |
Free format text: ORIGINAL CODE: EPIDOSNIGR1 |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: GRANT OF PATENT IS INTENDED |
|
INTG | Intention to grant announced |
Effective date: 20230313 |
|
GRAS | Grant fee paid |
Free format text: ORIGINAL CODE: EPIDOSNIGR3 |
|
GRAA | (expected) grant |
Free format text: ORIGINAL CODE: 0009210 |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: THE PATENT HAS BEEN GRANTED |
|
AK | Designated contracting states |
Kind code of ref document: B1 Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR |
|
REG | Reference to a national code |
Ref country code: CH Ref legal event code: EP |
|
REG | Reference to a national code |
Ref country code: IE Ref legal event code: FG4D Free format text: LANGUAGE OF EP DOCUMENT: FRENCH |
|
REG | Reference to a national code |
Ref country code: DE Ref legal event code: R096 Ref document number: 602019032427 Country of ref document: DE |
|
U01 | Request for unitary effect filed |
Effective date: 20230718 |
|
U07 | Unitary effect registered |
Designated state(s): AT BE BG DE DK EE FI FR IT LT LU LV MT NL PT SE SI Effective date: 20230802 |
|
REG | Reference to a national code |
Ref country code: LT Ref legal event code: MG9D |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: GR Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20231013 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: ES Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20230712 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: IS Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20231112 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: RS Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20230712 Ref country code: NO Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20231012 Ref country code: IS Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20231112 Ref country code: HR Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20230712 Ref country code: GR Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20231013 Ref country code: ES Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20230712 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: PL Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20230712 |
|
REG | Reference to a national code |
Ref country code: DE Ref legal event code: R097 Ref document number: 602019032427 Country of ref document: DE |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: SM Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20230712 Ref country code: RO Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20230712 Ref country code: CZ Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20230712 Ref country code: SK Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20230712 |
|
PLBE | No opposition filed within time limit |
Free format text: ORIGINAL CODE: 0009261 |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT |
|
26N | No opposition filed |
Effective date: 20240415 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: GB Payment date: 20240612 Year of fee payment: 6 |
|
U20 | Renewal fee paid [unitary effect] |
Year of fee payment: 6 Effective date: 20240612 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: CH Payment date: 20240701 Year of fee payment: 6 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: MC Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20230712 |