EP1980709A1 - Method for simultaneous handling and loading of drilling rods and casings by means of two independent rotaries - Google Patents
Method for simultaneous handling and loading of drilling rods and casings by means of two independent rotaries Download PDFInfo
- Publication number
- EP1980709A1 EP1980709A1 EP08006077A EP08006077A EP1980709A1 EP 1980709 A1 EP1980709 A1 EP 1980709A1 EP 08006077 A EP08006077 A EP 08006077A EP 08006077 A EP08006077 A EP 08006077A EP 1980709 A1 EP1980709 A1 EP 1980709A1
- Authority
- EP
- European Patent Office
- Prior art keywords
- loader
- rod
- rods
- casings
- rotary
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000005553 drilling Methods 0.000 title claims abstract description 27
- 238000000034 method Methods 0.000 title claims abstract description 11
- 238000000605 extraction Methods 0.000 claims abstract description 15
- 230000000284 resting effect Effects 0.000 claims abstract description 10
- 239000004568 cement Substances 0.000 claims description 2
- 239000011248 coating agent Substances 0.000 claims description 2
- 238000000576 coating method Methods 0.000 claims description 2
- 239000011440 grout Substances 0.000 claims description 2
- 230000002787 reinforcement Effects 0.000 claims description 2
- 238000006073 displacement reaction Methods 0.000 description 1
- 238000011084 recovery Methods 0.000 description 1
- 230000009467 reduction Effects 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21B—EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B7/00—Special methods or apparatus for drilling
- E21B7/20—Driving or forcing casings or pipes into boreholes, e.g. sinking; Simultaneously drilling and casing boreholes
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D11/00—Methods or apparatus specially adapted for both placing and removing sheet pile bulkheads, piles, or mould-pipes
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21B—EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B19/00—Handling rods, casings, tubes or the like outside the borehole, e.g. in the derrick; Apparatus for feeding the rods or cables
- E21B19/14—Racks, ramps, troughs or bins, for holding the lengths of rod singly or connected; Handling between storage place and borehole
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21B—EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B19/00—Handling rods, casings, tubes or the like outside the borehole, e.g. in the derrick; Apparatus for feeding the rods or cables
- E21B19/16—Connecting or disconnecting pipe couplings or joints
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21B—EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B3/00—Rotary drilling
- E21B3/02—Surface drives for rotary drilling
- E21B3/022—Top drives
Definitions
- the present invention relates to a method for simultaneous handling and loading of drilling rods and casings by means of two independent rotaries.
- the equipment is based upon the possibility, due to the capacity for sliding throughout the length of the mast of the two, top and bottom, rotating end pieces, of performing the monoeuvre of loading of a drilling battery made up of rods and casings for drilling a hole in the earth and its subsequent recovery to bring the battery itself back into a resting condition in the automatic loader.
- the equipment consisting of loaders may be of the following types:
- the invention proposes a method for simultaneous handling and loading of drilling rods and casings by means of two independent rotaries according to Claim 1.
- Figure 1 Represented in Figure 1 is the machine according to the invention. It basically has two rotaries 1 and 2 slidably mounted, independent of one another, on a mast 9.
- a loader 3 for rods 7 and casings 8.
- the loader 3 is located underneath the rotaries 1 and 2 when these are at their top end of travel.
- the rotaries 1 and 2 set the battery constituted by the rod 7 and the corresponding casing 8, screwed on the underlying rod 7' and the corresponding casing 8', in rotation and cause it to advance, thus drilling into the earth.
- the casing 8 is filled with a reinforcement 10 and cement grout or whatever is envisaged in the project.
- the rotary 1 is held up high so as not to hamper access to the hole.
- the rotary 2 is preferably held up high to reduce the encumbrance in the working area, facilitate the operation of unscrewing, and protect it from any accidental damage.
- FIGS 10 to 13 once again show schematically the second phase of the operation of extraction of the rods and the corresponding casings, namely, the phase of extraction of just the casings 8.
- the loader 3 receives the rod 7 and the casing 8 in a coaxial position to set them in a resting condition.
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Geology (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Fluid Mechanics (AREA)
- Environmental & Geological Engineering (AREA)
- Physics & Mathematics (AREA)
- Mechanical Engineering (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Earth Drilling (AREA)
- Drilling Tools (AREA)
- Perforating, Stamping-Out Or Severing By Means Other Than Cutting (AREA)
- Drilling And Boring (AREA)
Abstract
a) operation of loading the rods/casings to carry out drilling in the earth down to the desired depth;
b) operation of extraction of the battery of the rods, including the starting rod provided with the bit, and the casings that contain them, setting them resting in the loader, this operation being carried out in the following steps, namely: the first step b1) of extraction and arrangement of the rods (7) in the loader, and the second step b2) of extraction and arrangement of the casings (8) in the loader.
Description
- The present invention relates to a method for simultaneous handling and loading of drilling rods and casings by means of two independent rotaries.
- The equipment is based upon the possibility, due to the capacity for sliding throughout the length of the mast of the two, top and bottom, rotating end pieces, of performing the monoeuvre of loading of a drilling battery made up of rods and casings for drilling a hole in the earth and its subsequent recovery to bring the battery itself back into a resting condition in the automatic loader.
- For handling the rods and rods/casings in earth-drilling machines, the following equipment is mainly used: loaders, articulated cranes, mixed systems of cranes plus gripping accessories or winch end pieces.
- The equipment consisting of loaders may be of the following types:
- a. rack loaders, with possibilities of stocking rods or rods and casings on the mast and with hydraulic manipulating gripper that picks the rod up off the rack and positions it at pile centre;
- b. revolver loaders, with possibilities of stocking rods or rods and casings on the mast and with a system for hydraulic rotation of the supporting arm or jib of the loader that picks the rod up from the rack and positions it at pile centre;
- c. simplified-rack loaders: in some machines for digging wells the rack is fixed to the mast, and the rotary, provided with lateral displacement, moves to pick the rod up; the advantage lies in the fact that the manipulator is not required, and the limit is represented by the fact that the rods can be just a few, two or three at the most;
- d. well-rack loaders: in well-drilling machines the rack is located on the basic machine and an arm picks the rod and sets it aligned (larger number of rods, more complex system).
- As compared to the use of double loaders or single loaders for rods and single loaders for pipes or of both types of loaders of the revolver type considerable reductions in terms of weights and volumes are obtained, as well as a greater simplicity of manoeuvre.
- For the above and further purposes that will be more clearly understandable from what follows, the invention proposes a method for simultaneous handling and loading of drilling rods and casings by means of two independent rotaries according to
Claim 1. - The method according to the invention will now be described with reference to the annexed plates of drawings, in which:
-
Figure 1 illustrates an earth-drilling machine provided with the equipment that implements the method according to the present invention; -
Figures 2 to 5 are schematic representations of the machine ofFigure 1 , which illustrate the sequence of drilling, with simultaneous loading of rods and casings; -
Figures 6 to 9 show, once again schematically, the sequence of extraction of just the rods; and -
Figures 10 to 13 show, once again schematically, the sequence of extraction of just the casings. - Represented in
Figure 1 is the machine according to the invention. It basically has tworotaries mast 9. - Set alongside the
mast 9 is aloader 3 forrods 7 andcasings 8. As may be noted, theloader 3 is located underneath therotaries - At the bottom, applied on the
mast 9 are three ?vices rods 7 and thecasings 8. - We shall first consider the step of loading of the rods/casings for carrying out drilling into the earth down to the depth required. Reference will be made for this first step to
Figures 2 to 5 . It may first of all be noted inFigure 2 that the top rotary 1 and the bottom rotary 2 are in the position at the top of themast 9, and theloader 3 is brought onto the drilling axis of therod 8. - In
Figure 3 , the tworotaries loader 3 and made to rotate so as to screw a rod to the top rotary 1 and the casing to the bottom rotary 2, the rod and casing being ready in theloader 3. - In
Figure 4 , theloader 3 is moved away, therod 7 and thecasing 8 being left on the drilling axis suspended from the respective rotaries. - In
Figure 5 , therotaries rod 7 and thecorresponding casing 8, screwed on the underlying rod 7' and the corresponding casing 8', in rotation and cause it to advance, thus drilling into the earth. - As the battery sinks into the earth, it is necessary to add on top of it another
rod 7 with thecorresponding casing 8 so that, with the aid of thevices rotaries vice 6 withholds thecasing 8. The cycle starts again from the step illustrated inFigure 2 and is repeated until drilling is completed. - Once drilling is completed, it is necessary to extract the battery of rods, including the starting rod provided with the bit, and the casings that contain them, setting them resting in the loader. This operation is performed in two successive steps: a first step of extraction of the
rods 7 and their arrangement in the loader and a second step of extraction of thecasings 8 and their arrangement in the loader. - The first of the two steps is represented in
Figures 6 to 9 . InFigure 6 , it may first of all be noted that therotary 1 has come up together with the rotary 2, extracting afirst rod 7 from thecasing 8 and, with the aid of thevices loader 3 sets itself back again on the drilling axis to receive therod 7. - In
Figure 7 , therotary 1 has disconnected from the rod, and theloader 3, which has received it, brings it into the resting position. - In
Figure 8 , therotary 1 is lowered together with therotary 2 and, setting itself in rotation, screws onto thenext rod 7, which is held stationary by thevice 5. - The
rotary 1 can now come up together with the rotary 2, whilst theunscrewing vice 4 loosens the next joint, and the sequence returns to the step represented inFigure 6 , from which the cycle just described is repeated until all the rods, including the bit have been completely extracted. - In
Figure 9 , thecasing 8 is filled with areinforcement 10 and cement grout or whatever is envisaged in the project. Therotary 1 is held up high so as not to hamper access to the hole. - The
rotary 2 is preferably held up high to reduce the encumbrance in the working area, facilitate the operation of unscrewing, and protect it from any accidental damage. - The operating sequence described in
Figures 6 to 9 can, however, be performed also with the rotary 2 kept permanently in the bottom position. In this case, the sleeve for connection of the rotary 2 to the casing must be kept outside thevices -
Figures 10 to 13 once again show schematically the second phase of the operation of extraction of the rods and the corresponding casings, namely, the phase of extraction of just thecasings 8. - In
Figure 10 , therotary 1 is up and therotary 2 is down, connected to thefirst casing 8. Therods 7 are all on theloader 3. - In
Figure 11 , theloader 3 has been brought up in alignment with the drilling rod, and therotary 1 has picked up arod 7 so that theloader 3 can return into the resting condition. - In
Figure 12 , therotary 2 has moved up, so coating therod 7 with acasing 8 that is disconnected from the subsequent casing 8', which is withheld by thevice 6. - In
Figure 13 , theloader 3 receives therod 7 and thecasing 8 in a coaxial position to set them in a resting condition. - The sequence returns to the step illustrated in
Figure 10 , and the cycle is repeated until all therods 7 are in theloader 3 coated with therespective casings 8.
Claims (3)
- A method for simultaneous handling and loading of drilling rods and casings by means of a machine provided with two rotaries (1 and 2), slidably mounted, independent of one another, on the mast (9) of the machine; there being positionable alongside the mast (9) the loader (3) for loading rods (7) and casings (8), there being applied on the mast (9), at the bottom end, three vices (4, 5 and 6), designed for unscrewing/screwing of the rods (7) and of the casings (8); the method being characterized by the following operations carried out in succession:a) operation of loading of the rods/casings to carry out drilling in the earth down to the desired depth, wherein the following steps are carried out in succession:a1) the top rotary (1) and bottom rotary (2) are in the position at the top of the mast (9), and the loader (3) is brought onto the axis of drilling of the rod (7);a2) the two rotaries (1 and 2) are lowered onto the loader (3) and made to turn so as to screw, respectively, a rod (7) to the top rotary (1) and the corresponding casing (8) to the bottom rotary (2), the rod and casing being ready in the loader (3) ;a3) the loader (3) is moved away, leaving the rod (7) and the casing (8) on the drilling axis suspended from the respective rotaries (1 and 2);a4) the rotaries (1 and 2) set the battery, constituted by the rod (7) and the corresponding casing (8), screwed on the underlying rod (7') and the corresponding casing (8'), in rotation and cause it to advance, thus drilling into the earth;a5) a further rod (7) with the corresponding casing (8) is added on top with the aid of the two top vices (4, 5), by means of which the rotaries (1 and 2) are screwed off the rod and off the casing that project from the ground and can rise, whilst the bottom vice (6) withholds the casing (7');a6) the cycle from step a2 to step a5 is repeated until completion of the drilling operation;b) operation of extraction of the battery of rods, including the starting rod provided with the bit, and casings that contain them, setting them resting in the loader, this operation being carried out in the following steps, namely: the first step b1) of extraction and arrangement of the rods (7) in the loader, and the second step b2) of extraction and arrangement of the casings (8) in the loader;
the step b1) of extraction and arrangement of the rods (7) in the loader consisting in succession of the following steps:b1a) the top rotary (1) is made to come up together with the bottom rotary (2), extracting a first rod (7) from the casing (8), which, with the aid of the vices (4, 5 and 6) has disconnected it from the subsequent rods; the loader (3) goes back onto the drilling axis to receive the rod (7);b1b) the top rotary (1) is disconnected from the rod (7), and the loader (3), which has received it, brings it into the resting position;b1c) the top rotary (1) is lowered together with the bottom rotary (2) and, setting itself in rotation, screws onto the next rod (7), which is held stationary by the intermediate vice (5);b1d) the top rotary (1) goes up, together with the bottom rotary (2), whilst the top unscrewing vice (4) loosens the next joint;b1e) the cycle from step b1a to step bld is repeated until complete extraction of all the rods, including the bit;the step b2) of extraction and arrangement of the casings (8) in the loader consisting in succession of the following steps:b2a) the top rotary (1) is positioned at the top and the bottom rotary (2) at the bottom, connected to the first casing (8);b2b) the loader (3) is brought into alignment with the drilling axis, and the rotary (1) picks up a rod (7) so that the loader (3) can go back into the resting position;b2c) the bottom rotary (2) is raised, thus coating the rod (7) with a casing (8), disconnected from the next casing (8'), which is withheld by the bottom vice (6);b2d) the loader (3) receives the rod (7) and the casing (8) in a coaxial position to bring them into a resting condition;b2e) the cycle from step b2a to step b2d is repeated until all the rods (7) are in the loader (3), coated with the corresponding casings (8). - The method according to Claim 1,
characterized in that, following upon step b1e), the casing (8), connected to the bottom rotary (2), is filled with a reinforcement (10) and cement grout or whatever is envisaged in the project. - The method according to Claim 1,
characterized in that in steps b1a to b1e the rotary 2 is held permanently in a bottom position.
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
IT000253A ITTO20070253A1 (en) | 2007-04-12 | 2007-04-12 | PROCEDURE FOR THE HANDLING AND CONTEMPORARY LOADING OF DRILL RODS AND LINING PIPES BY MEANS OF TWO INDEPENDENT ROTARY. |
Publications (2)
Publication Number | Publication Date |
---|---|
EP1980709A1 true EP1980709A1 (en) | 2008-10-15 |
EP1980709B1 EP1980709B1 (en) | 2009-12-09 |
Family
ID=39691126
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
EP08006077A Not-in-force EP1980709B1 (en) | 2007-04-12 | 2008-03-28 | Method for simultaneous handling and loading of drilling rods and casings by means of two independent rotaries |
Country Status (4)
Country | Link |
---|---|
EP (1) | EP1980709B1 (en) |
DE (1) | DE602008000359D1 (en) |
ES (1) | ES2337745T3 (en) |
IT (1) | ITTO20070253A1 (en) |
Cited By (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2010098672A1 (en) * | 2009-02-26 | 2010-09-02 | West Drilling Products As | Method for withdrawal and insertion of a drill pipe string in a borehole and also a device for use when practising the method |
CN102400648A (en) * | 2011-10-28 | 2012-04-04 | 恒天九五重工有限公司 | Detachable follow-up frame and installation process thereof |
WO2013125961A1 (en) * | 2012-02-22 | 2013-08-29 | West Drilling Products As | Device for a pipe handling unit and method of inserting and withdrawing a pipe string in/from a borehole |
US9091128B1 (en) * | 2011-11-18 | 2015-07-28 | T&T Engineering Services, Inc. | Drill floor mountable automated pipe racking system |
US9476267B2 (en) | 2013-03-15 | 2016-10-25 | T&T Engineering Services, Inc. | System and method for raising and lowering a drill floor mountable automated pipe racking system |
WO2017139828A1 (en) * | 2015-06-09 | 2017-08-24 | Southern Seawall Solutions Pty Limited | Improved caisson emplacement system and method |
CN110029951A (en) * | 2019-05-31 | 2019-07-19 | 贵州大学 | A kind of segmentation drilling rod docking facilities |
CN110566141A (en) * | 2019-10-18 | 2019-12-13 | 江苏如石机械股份有限公司 | Dual-purpose power tongs for drill rod and casing |
KR20200098956A (en) * | 2019-02-13 | 2020-08-21 | 강익희 | A Improved Punching Machine For Straight Punching and Construction Method Thereof |
IT201900003035A1 (en) * | 2019-03-01 | 2020-09-01 | Beretta Alfredo S R L | ARTICULATED SUPPORT OF MAST DEVICE FOR A DRILLING AND RELATIVE DRILLING MACHINE |
US11512535B2 (en) * | 2018-05-24 | 2022-11-29 | Benthic Usa Llc | Dual rotary elevating geotechnical drill |
US11692324B2 (en) | 2018-04-23 | 2023-07-04 | Southern Seawall Solutions Pty Limited | Wall element system and method and apparatus for constructing shoring walls |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH02157388A (en) * | 1988-12-07 | 1990-06-18 | Yoshihiko Kawai | Large bore drilling device |
EP0527460A2 (en) * | 1991-08-14 | 1993-02-17 | Stump Bohr GmbH | Method and device for drilling holes in soil or rock, particularly for the insertion of injection anchors |
DE29706264U1 (en) * | 1997-02-25 | 1997-06-05 | Hütte & Co Bohrtechnik GmbH, 57462 Olpe | Device for double head and overlay drilling |
NL1003072C1 (en) * | 1996-05-09 | 1997-11-18 | Visser & Smit Bouw Bv | Method for inserting foundation-component in ground |
US20030221870A1 (en) * | 2002-06-01 | 2003-12-04 | Johnson Howard E. | Earth loop heat exchange methods and systems |
WO2006061459A1 (en) * | 2004-12-07 | 2006-06-15 | Sandvik Mining And Construction Oy | Method for casing drilling, drilling unit and adapter device |
WO2007129337A1 (en) * | 2006-05-09 | 2007-11-15 | Comacchio International S.A. | Drilling machine with carousel-type drill stem and shroud tube loader |
-
2007
- 2007-04-12 IT IT000253A patent/ITTO20070253A1/en unknown
-
2008
- 2008-03-28 EP EP08006077A patent/EP1980709B1/en not_active Not-in-force
- 2008-03-28 DE DE602008000359T patent/DE602008000359D1/en active Active
- 2008-03-28 ES ES08006077T patent/ES2337745T3/en active Active
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH02157388A (en) * | 1988-12-07 | 1990-06-18 | Yoshihiko Kawai | Large bore drilling device |
EP0527460A2 (en) * | 1991-08-14 | 1993-02-17 | Stump Bohr GmbH | Method and device for drilling holes in soil or rock, particularly for the insertion of injection anchors |
NL1003072C1 (en) * | 1996-05-09 | 1997-11-18 | Visser & Smit Bouw Bv | Method for inserting foundation-component in ground |
DE29706264U1 (en) * | 1997-02-25 | 1997-06-05 | Hütte & Co Bohrtechnik GmbH, 57462 Olpe | Device for double head and overlay drilling |
US20030221870A1 (en) * | 2002-06-01 | 2003-12-04 | Johnson Howard E. | Earth loop heat exchange methods and systems |
WO2006061459A1 (en) * | 2004-12-07 | 2006-06-15 | Sandvik Mining And Construction Oy | Method for casing drilling, drilling unit and adapter device |
WO2007129337A1 (en) * | 2006-05-09 | 2007-11-15 | Comacchio International S.A. | Drilling machine with carousel-type drill stem and shroud tube loader |
Cited By (18)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2010098672A1 (en) * | 2009-02-26 | 2010-09-02 | West Drilling Products As | Method for withdrawal and insertion of a drill pipe string in a borehole and also a device for use when practising the method |
US8844616B2 (en) | 2009-02-26 | 2014-09-30 | West Drilling Products As | Method for withdrawal and insertion of a drill pipe string in a borehole and also a device for use when practicing the method |
CN102400648A (en) * | 2011-10-28 | 2012-04-04 | 恒天九五重工有限公司 | Detachable follow-up frame and installation process thereof |
CN102400648B (en) * | 2011-10-28 | 2013-10-23 | 恒天九五重工有限公司 | Detachable follow-up frame and installation process thereof |
US9945193B1 (en) | 2011-11-18 | 2018-04-17 | Schlumberger Technology Corporation | Drill floor mountable automated pipe racking system |
US9091128B1 (en) * | 2011-11-18 | 2015-07-28 | T&T Engineering Services, Inc. | Drill floor mountable automated pipe racking system |
US9822593B2 (en) | 2012-02-22 | 2017-11-21 | West Drilling Products As | Device for a pipe handling unit and method of inserting and withdrawing a pipe string in/from a borehole |
WO2013125961A1 (en) * | 2012-02-22 | 2013-08-29 | West Drilling Products As | Device for a pipe handling unit and method of inserting and withdrawing a pipe string in/from a borehole |
US9476267B2 (en) | 2013-03-15 | 2016-10-25 | T&T Engineering Services, Inc. | System and method for raising and lowering a drill floor mountable automated pipe racking system |
WO2017139828A1 (en) * | 2015-06-09 | 2017-08-24 | Southern Seawall Solutions Pty Limited | Improved caisson emplacement system and method |
US11692324B2 (en) | 2018-04-23 | 2023-07-04 | Southern Seawall Solutions Pty Limited | Wall element system and method and apparatus for constructing shoring walls |
US11512535B2 (en) * | 2018-05-24 | 2022-11-29 | Benthic Usa Llc | Dual rotary elevating geotechnical drill |
KR20200098956A (en) * | 2019-02-13 | 2020-08-21 | 강익희 | A Improved Punching Machine For Straight Punching and Construction Method Thereof |
IT201900003035A1 (en) * | 2019-03-01 | 2020-09-01 | Beretta Alfredo S R L | ARTICULATED SUPPORT OF MAST DEVICE FOR A DRILLING AND RELATIVE DRILLING MACHINE |
EP3702578A1 (en) * | 2019-03-01 | 2020-09-02 | Beretta Alfredo S.r.l. | A revolving magazine unit for drill rods and pipes |
CN110029951A (en) * | 2019-05-31 | 2019-07-19 | 贵州大学 | A kind of segmentation drilling rod docking facilities |
CN110566141A (en) * | 2019-10-18 | 2019-12-13 | 江苏如石机械股份有限公司 | Dual-purpose power tongs for drill rod and casing |
CN110566141B (en) * | 2019-10-18 | 2024-06-11 | 江苏如石机械股份有限公司 | Dual-purpose power tongs for drill pipe and casing |
Also Published As
Publication number | Publication date |
---|---|
ITTO20070253A1 (en) | 2008-10-13 |
DE602008000359D1 (en) | 2010-01-21 |
EP1980709B1 (en) | 2009-12-09 |
ES2337745T3 (en) | 2010-04-28 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
EP1980709B1 (en) | Method for simultaneous handling and loading of drilling rods and casings by means of two independent rotaries | |
CN102913162B (en) | Deep-sea sediment continuous pressure maintaining coring submarine drilling machine and operation method | |
US4703811A (en) | Drilling and/or lifting machine | |
CN105443037B (en) | A kind of top jumbolter and the top roofboltier comprising the drilling machine | |
US3835940A (en) | Earth drilling apparatus and method | |
US10119346B2 (en) | Tool for use on exit side of bore and method of use thereof | |
CN111433430B (en) | Sequencing for drill rod handling | |
US20070251700A1 (en) | Tubular running system | |
US6360830B1 (en) | Blocking system for a directional drilling machine | |
US6283702B1 (en) | Drill rod loader | |
CN205259938U (en) | Anchor rod drilling carriage of four arms group | |
US6374928B1 (en) | Method of blocking a pocket of a multi-pocket feed member for a directional drilling machine | |
US20150259993A1 (en) | Exit Side Tool For Makeup And Breakout Of Pipe | |
CN204238883U (en) | A kind of drilling rod automatic loading and unloading storage device | |
CN112343525B (en) | Compact type efficient operation drilling machine and method | |
EP0565502B1 (en) | Pipe handling equipment and method for a rock drilling machine | |
CN110977930A (en) | Sedimentation type drill floor surface manipulator for drilling and repairing well | |
CN203362092U (en) | Retractable fishing cylinder | |
CN106013150A (en) | Pile pressing machine | |
CN202866720U (en) | Drilling bucket latch jack for rotary drilling machine | |
NO854131L (en) | STEEL LOADING AND LOOSING DEVICE FITTED FOR FASTENING TO A DRILL. | |
CN211565881U (en) | Sedimentation type drill floor surface manipulator for drilling and repairing well | |
CN211081696U (en) | Anchor rod trolley | |
EP0188190A2 (en) | A drilling and/or lifting machine | |
CN113153182A (en) | Drilling equipment, automatic rod retracting method thereof and readable storage medium |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PUAI | Public reference made under article 153(3) epc to a published international application that has entered the european phase |
Free format text: ORIGINAL CODE: 0009012 |
|
AK | Designated contracting states |
Kind code of ref document: A1 Designated state(s): AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MT NL NO PL PT RO SE SI SK TR |
|
AX | Request for extension of the european patent |
Extension state: AL BA MK RS |
|
17P | Request for examination filed |
Effective date: 20090312 |
|
GRAP | Despatch of communication of intention to grant a patent |
Free format text: ORIGINAL CODE: EPIDOSNIGR1 |
|
AKX | Designation fees paid |
Designated state(s): DE ES FR GB IT NL |
|
GRAS | Grant fee paid |
Free format text: ORIGINAL CODE: EPIDOSNIGR3 |
|
GRAA | (expected) grant |
Free format text: ORIGINAL CODE: 0009210 |
|
AK | Designated contracting states |
Kind code of ref document: B1 Designated state(s): DE ES FR GB IT NL |
|
REG | Reference to a national code |
Ref country code: GB Ref legal event code: FG4D |
|
REF | Corresponds to: |
Ref document number: 602008000359 Country of ref document: DE Date of ref document: 20100121 Kind code of ref document: P |
|
REG | Reference to a national code |
Ref country code: NL Ref legal event code: T3 |
|
REG | Reference to a national code |
Ref country code: ES Ref legal event code: FG2A Ref document number: 2337745 Country of ref document: ES Kind code of ref document: T3 |
|
PLBE | No opposition filed within time limit |
Free format text: ORIGINAL CODE: 0009261 |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT |
|
26N | No opposition filed |
Effective date: 20100910 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: NL Payment date: 20120321 Year of fee payment: 5 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: ES Payment date: 20120419 Year of fee payment: 5 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: GB Payment date: 20130327 Year of fee payment: 6 |
|
REG | Reference to a national code |
Ref country code: NL Ref legal event code: V1 Effective date: 20131001 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: NL Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20131001 |
|
REG | Reference to a national code |
Ref country code: ES Ref legal event code: FD2A Effective date: 20140606 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: ES Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20130329 |
|
GBPC | Gb: european patent ceased through non-payment of renewal fee |
Effective date: 20140328 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: GB Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20140328 |
|
REG | Reference to a national code |
Ref country code: FR Ref legal event code: PLFP Year of fee payment: 9 |
|
REG | Reference to a national code |
Ref country code: FR Ref legal event code: PLFP Year of fee payment: 10 |
|
REG | Reference to a national code |
Ref country code: FR Ref legal event code: PLFP Year of fee payment: 11 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: FR Payment date: 20210325 Year of fee payment: 14 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: DE Payment date: 20220322 Year of fee payment: 15 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: IT Payment date: 20220324 Year of fee payment: 15 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: FR Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20220331 |
|
REG | Reference to a national code |
Ref country code: DE Ref legal event code: R119 Ref document number: 602008000359 Country of ref document: DE |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: DE Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20231003 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: IT Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20230328 |