The present invention relates in the first instance to a bearing element for
supporting infrastructure such as roads, railways, runways and airports, which is intended
for placing at least partially in the ground, the average weight of the bearing element per
linear metre being at most equal to the average weight per linear metre of the soil which
has been removed for the purpose of placing the bearing element.
When infrastructure, such as roads and railways, is laid over relatively soft
ground, such as that commonly found in the Netherlands, sand is generally used to
support the infrastructure. A supporting element is laid in the ground with the aid of the
sand. Railway tracks, for example, are generally placed on an embankment of sand,
which sand is poured into a trench dug in the ground. So much sand is supplied here that
the embankment projects partially above ground level. A ballast bed in which the track
rails can be fixed with the aid of sleepers is subsequently placed on top of this so-called
"earth track".
A major disadvantage of the use of a supporting element made of sand is
that the weight of the constructed element, so in the case of railway tracks the weight of
the earth track is much greater than the weight of the soil which was excavated for
laying of the support. That means that the stress profile in the ground below the
supporting element of sand changes because of the great weight of the latter. As a result
of the stresses caused in the ground, the ground will be subject to subsidence, which
means that the foundation becomes permanently deformed by the weight of the earth
track.
A first major consequence of this is that in the case of a railway track the
rails cannot be placed immediately on the embankment. Before the rails can be placed on
an embankment, a substantial part of the permanent deformation of the foundation must
already have occurred. During the construction of a railway track that means a
considerable extension of the construction time.
Another consequence is that the rails have to be aligned repeatedly, because
the high weight of the earth track causes the foundation of the railway track to be
deformed permanently also during use.
A subsidence-free support for infrastructure, according to the type mentioned
in the preamble is known, inter alia, from British Patent Application GB 2,300,009. The
support according to this publication is constructed by placing plastic blocks, for
example polyurethane or polystyrene, in an excavated trench. The trench is subsequently
filled up with concrete. Although the support according to the British application can be
placed in the ground so that it is subsidence-free, the rigidity and strength of the
construction in its longitudinal direction are limited. If the known support is used, for
example, in a foundation with weak spots locally, the support can subside locally. When
the support has subsided locally, it cannot be aligned again.
If the known support is to be used for supporting track rails, one of the
important requirements, particularly from an acoustic point of view, is that the
construction should have a high input impedance under the track rails. This cannot be
achieved with the known construction.
It is the object of the present invention to provide a support of the type
mentioned in the preamble which itself forms a rigid and strong element in the
longitudinal direction.
That object is achieved in the present invention by the fact that the bearing
element (1) forms a tube in the longitudinal direction.
The advantage of this is that the bearing element is supported along its entire
length, which means that the bearing element can span relatively weak points (for
example, old ditches) in the route itself. The road, railway track or, for example, runway
cannot therefore subside very locally. The bearing element according to the present
invention is consequently particularly suitable for laying high-speed lines (HSLs).
The bearing element according to the present invention preferably comprises
one or more channels in its longitudinal direction. This has the advantage that the
bearing element need not be in the form of a solid element, which means that "ordinary"
construction means such as, for example, prestressed, fibre-reinforced and armoured
concrete can be used for the construction of the bearing element.
The presence of the channels here has the advantage that the free space in
the bearing element can be used, for example, for transporting shuttles, for containers or
for other forms of transport. The channels can also be used for passing lines through
them. The bearing element in that last instance acts as a pipe alley. In other words, by
using the bearing element according to the present invention it is relatively simple to
achieve dual ground use.
In an advantageous embodiment the bearing element comprises a lower half
in the form of a shell, having at least a bottom and two side walls to be placed
substantially horizontally, and a substantially flat upper half to be placed on the lower
half.
One of the advantages of this is that a trench for laying a bearing element
according to the present invention which is substantially the shape of a trapezium is
relatively easy to dig in the ground. Furthermore, because of the shape, the lower half
can be poured from concrete, in which case removable concrete shuttering can be used.
It is possible according to the invention for longitudinal walls extending in
the longitudinal direction to be placed in the tube. It is advantageous here for transverse
walls extending in the transverse direction to be placed between the side walls and/or the
longitudinal walls.
These walls in the first place support the upper half of the bearing element.
Furthermore, the rigidity of the element is increased by the presence of the walls. An
additional advantage is that the walls can be placed in such a way that at the places
where the infrastructure is subjected to the greatest load (for example, just underneath
the track rails) walls are fitted.
The bearing element according to the present invention preferably has in its
longitudinal direction edges extending in the transverse direction.
The advantage of this is that jacks can be placed under these edges. Railway
tracks, certainly the railway tracks used for high-speed trains, must have a high degree of
accuracy as regards unevennesses in the vertical direction. If the bearing element has
subsided locally owing to a disaster, the transverse edges fixed to the bearing element
make it possible to place jacks underneath the bearing element, in order to raise the
bearing element to the desired level.
The bearing element according to the present invention is further improved if
means for pumping away leakage water are placed in the channels of the bearing
element.
This has the advantage that any leakage water out of the ground, or leakage
water which has reached the element through the top side, can be removed from the
element by means of the pumps. In this way the weight of the bearing element is
prevented from increasing at the moment when leakage water penetrates into the
element.
It is also possible to fill the hollows in the bearing element with a plastic
foam, for example a closed-cell foam.
That has the advantage that the foam forms a physical barrier against the
penetration of leakage water into the bearing element.
As already stated above, the bearing element according to the present
invention is particularly suitable for supporting track rails. In the prior art it is known to
use a concrete slab as a support for the track rails, as an alternative to an earth track. In
order to prevent subsidence of the foundation in the case of such a "slab track", the
concrete slab can be supported on piles. However, the use of a slab track has two major
disadvantages. First, it is relatively expensive to lay (certainly in the case of pile
supports). Secondly, a slab track produces much more noise than a conventional ballast
track.
The bearing element according to the present invention is therefore further
improved by the fact that the top side of the bearing element is provided with means for
fixing track rails, the channels and the longitudinal walls being placed in the bearing
element in such a way that the bearing element has a high input impedance.
The advantage of this is that the track rails can be fitted relatively easily on
the bearing element, the relatively simply constructed trenches serving as fixing means.
The fact that underneath the rail supports is precisely where the bearing element has no
hollows, but actually a relatively heavy cross-section, has the advantage that the bearing
element has a relatively great input impedance to vibrations. That means that at the
moment when a train passes over the bearing element it will be difficult for the bearing
element itself to be set in vibration by the train. The advantageous effect of this is that
the use of the bearing element according to the present invention therefore produces a
relatively low-noise railway track.
It is further possible according to the invention for the bearing element to be
made of concrete. It is possible here for the bearing element to be made of fibre-reinforced,
armoured or prestressed concrete, or any suitable combination thereof.
The present invention further provides the possibility of fitting road furniture
on or in the bearing element. That means that the support of the overhead line, for
example, is fitted on the bearing element, with the result that the overhead line can be
coupled directly to the bearing element. That means that the distance between the
bearing element and the overhead line is always constant, and it has the advantage that
the bearing element cannot subside relative to the overhead line. In the case of roads, the
lighting or the crash barriers, for example, can be fitted on the bearing element.
The present invention also relates to a method for manufacturing a bearing
element for supporting track rails. Said method comprises the following steps: digging a
long trench of suitable cross-section in the ground; laying a watertight membrane on the
ground and along the walls of the trench, the bearing element provided with channels
being made of concrete by means of sliding shuttering or another suitable shuttering,
with the exception of the deck; and subsequently pouring the deck from concrete, with
permanent shuttering or another suitable shuttering.
That has the advantage that the bearing element can be laid quickly and
efficiently, and consequently relatively cheaply. Moreover, the construction of the
bearing element in two phases makes it possible to carry out the first phase (lower half)
relatively "roughly", while a relatively "accurately" manufactured upper part is placed on
the lower half. That means a further possibility for saving costs during the construction
of the bearing element.
It is also possible according to the present invention for the bearing element
provided with channels to be made of concrete by means of sliding shuttering.
Furthermore, it is possible for the bearing element to be made fully or partially of
prefabricated concrete.
The method according to the present invention is advantageously expanded
by the following steps:
placing at least two supports underneath the bearing element, at a distance from each
other, and removing the soil present underneath the bearing element and between the supports.
The advantage of this is that an appreciable saving can be made on the
construction of smaller structures underneath the railway track. If, for example, a cycle
underpass or pedestrian subway is to be constructed underneath the railway track, two
supports, for example walls, are placed underneath the bearing element according to the
present invention. The soil between these walls is then excavated, and a passage is
thereby produced underneath the bearing element. Such a method for the construction of
small structures is out of the question in the case of a railway track according to the
prior art.
Furthermore, the small structures according to the above method can be laid
while the railway track remains in use. That produces considerable cost advantages.
The present invention will be described further with reference to the
following drawings, in which:
Figure 1 shows a cross-section of the bearing element according to the
present invention; Figure 2 shows the bearing element according to Figure 1, provided with
track rails on the top side; Figure 3 shows a cut-away side view of the bearing element according to
Figure 2, with a cycle underpass underneath it; Figure 4 shows a possible embodiment of the upper part of the bearing
element provided with a derailment guide; Figure 5 shows a possible embodiment of a track rail fastening. Figure 6 shows the bearing element according to the invention, used as a
runway for aircraft.
Figure 1 shows the bearing element 1 for supporting infrastructure according
to the invention. The bearing element 1 is preferably made of prestressed, armoured or
fibre-reinforced concrete. The bearing element 1 can be manufactured in one piece, but it
is advantageous if the bearing element consists of a lower half 2 and an upper half 7. In
the present description the upper half 7 is also known as the "deck". Since the load
exerted upon the ground per unit length by the bearing element may not exceed the load
exerted by the soil at the position of the bearing element prior to the building of the
infrastructure, the bearing element 1 is preferably in the form of a hollow tube. Viewed
in the longitudinal direction, the average weight of the bearing element per linear metre
may not exceed the average weight per linear metre of the soil removed.
The lower half 2 can be placed with the aid of sliding shuttering or in
another way in a trench dug in the ground. The laying of this lower part 2 can be largely
mechanized. For instance, it is possible to convey a laying train over an already laid
track, in order to excavate, deposit the structure in the correct position and in the correct
form, and provide the necessary longitudinal and transverse reinforcement. During the
laying of this lower half 2 a watertight sheeting 4, which prevents adverse effects of
groundwater on the structure, is rolled out underneath the structure. If desired, the
construction train (not shown) can act as a mobile concrete plant during the laying. The
supply of the necessary materials (and the removal of the excavated soil) is by way of
the laid structure (bearing element), so that working roads themselves are unnecessary.
For the transportation of these materials, robot carriers commute between the starting
point (i.e. supply point) and the construction train. These carriers travel along one track
to the construction train and unload their conveyed building materials there, and
subsequently return laden with soil by way of points along the other track to the supply
point.
One or more longitudinal walls 50 can be placed in the lower half 2. In
addition, one or more transverse walls 51 can be placed in the bearing element 1. These
walls give the bearing element increased rigidity and strength.
After laying of the lower half 2, by means of sliding shuttering, the upper
half 7 is laid. Said upper half 7 can be made by means of a permanent shuttering
method. During the placing of the upper half 7 it is advantageous if a bearing
element 1 which has a projecting edge 15 at both sides is produced. Said edge 15 can be
used during use of the bearing element should the bearing element 1 as a whole begin to
subside. Jacks can be placed under the edges 15 in the longitudinal direction of the
bearing element 1, by means of which a subsided bearing element 1 can be moved
upwards.
In order to prevent the bearing element 1 from filling up with water during
use, the hollows of the bearing element 1 can, for example, be filled with foam 5. As an
alternative, it is possible to place pumps 9 in the hollows, in order to be able to pump
any leakage water out of the bearing element 1.
Figure 2 shows the case where the bearing element 1 is used for supporting
track rails 6. The shape of the lower part 2 of the bearing element 1 is selected in such a
way that when the rails 6 are fixed on the bearing element 1 a relatively large amount of
mass is situated underneath the rails. The relatively large amount of material underneath
the rails 6 means that the input impedance of the bearing element 1 is relatively great.
That means that the bearing element 1 cannot easily be set in vibration by passing trains.
The bearing element 1 in use consequently causes a relatively low sound emission.
The shape of the upper half depends, inter alia, on the way in which the rails
are placed on the upper half 7. There are numerous possibilities for fixing the rails 6 on
the bearing element 1. Figure 2 shows the case where the upper half 7 is provided with
longitudinal trenches 8, for accommodating the rails 6. Another possibility for fixing the
rails 6 on the bearing element can be seen in Figure 4. The longitudinal trenches 8 can
be formed in one piece, simultaneously with the upper half 7. It is important for the
longitudinal trenches 8 to be placed with great dimensional accuracy on the upper half 7.
That can be achieved by using a paver.
The rails 6 are fixed in the longitudinal trenches 8 in the bearing element 1
and secured there by means of an elastic material 10, which can be, for example,
Flexapad, made by Edilon. The use of this cork rubber 10 ensures additional acoustic
insulation of the railway construction.
The trenches are also provided with an acoustic cover 17. After the rails 6
have been placed in the bearing element 1, a thermally insulating and sound-absorbent
layer 11 of, for example, gravel can be placed on the bearing element 1. Stress changes
will occur in the bearing element 1 as a result of temperature changes (day/night and
summer/winter). Owing to the sound-absorbent and thermally insulating top layer 11, the
temperature change in the bearing element will be relatively low, thereby ensuring that
stress changes in the bearing element 1 remain limited.
The abovementioned method for the laying of the bearing element 1 is only
an example. The bearing element 1 could also be manufactured in one piece using
sliding shuttering.
Moreover, in order to permit the use of changeover points, two bearing
elements can be coupled to each other, or a plate resting on both bearing elements can
be used, on which plate the changeover track can be laid.
Figure 3 shows a partially cut-away side view of the bearing element 1
according to Figure 2. It can be seen in the figure that the use of the bearing element 1
provides the possibility for easy fitting of small structures underneath the bearing
element 1. For instance, it is possible to make, for example, a cycle underpass 20
underneath the bearing element 1. For the construction of the underpass it will suffice to
construct two walls 21. After these two walls 21 have been positioned, the soil between
said walls is removed and a road surface constructed, so that the cycle underpass 20 is
produced.
It can also be seen in Figure 3 that the longitudinal trenches 8 in which the
rails 6 are accommodated are interrupted at openings 12. These openings 12 can be made
in the longitudinal trenches every 15 to 20 metres, in order to allow rainwater collecting
between the longitudinal trenches to drain off. Since the rails 6 are supported almost
over their entire length, the openings 12 can be made without jeopardizing the stability
or alignment of the rails 6.
An additional advantage of the use of the bearing element 1 according to the
present invention is that the supports 25 of the overhead line 23 can be coupled directly
to the bearing element 1. That means that the distance between the bearing element 1
and the overhead line 23 is always constant, which has the advantage that the bearing
element 1 cannot subside relative to the overhead line 23.
This in turn has the advantage that during passing of the train the pantograph
(not shown) cannot become detached from the overhead line 23. If the pantograph
becomes detached from the overhead line 23, a spark is drawn between the two. The
drawing of such a spark is accompanied by material loss from both the overhead line 23
and the pantograph.
Figure 4 shows an embodiment of the upper half 7 of the bearing element 1,
which is provided with a derailment guide. If a train becomes derailed, it is very
important that a railway track can still guide the derailed train to some extent as best it
can. For instance, a derailed train must always be prevented from landing on another
track.
The derailment guide according to Figure 4 is formed by the elevation 30
between two rails 6. The top side of this elevation 30 can be provided with an
acoustically absorbent layer, for example a layer of sound-absorbent concrete 31. The
height of the elevation 30 and the layer 31 is selected in such a way that the top surface
32 of the layer 31 projects a number of centimetres, for example 3 cm, above the top
surface of the rails 6. This produces hollows 35 between the rails 6 and the elevation 30,
in which hollows a train wheel which may have become derailed is caught, and which
will guide that train wheel.
Placing a layer 31 of acoustic concrete on the elevation not only ensures that
the railway track is quieter, but also that the concrete 31 has a function when derailments
occur. Acoustically absorbent concrete is generally relatively soft. The relatively soft
concrete layer 31 will therefore effectively be able to brake a derailed train wheel.
Figure 5 shows a possible embodiment of a fastening of a rail 6 to the upper
half 7. A "runner" of elastic material 40 is fixed to the underside of the rail 6, for
example by means of adhesive. The rail 6 is also wedged between two elastic, for
example rubber, elements 44. These elements 44 are fixed to steel sections 43. The
sections are fixed on the upper half 7 by means of fastening means 45.
With the rail support according to Figure 5 it is ensured that when a rail 6 is
placed on the upper half 7 and aligned, any openings or hollows between the runner 40
and the surface of the upper half 7 can be filled up by means of an injectable layer 41.
In this way the rail 6 is positioned in an efficient manner relative to the upper half 7.
During injection of the layer 41 a temporary seal 42, for example consisting of foam
strip, can be fitted next to the runner 40.
The embodiment according to Figure 5 further makes it possible to inject
additional material 41 underneath a locally subsided rail 6 underneath the runner 40, also
during use. In this way, the position of the rail relative to the upper half can be adjusted
during use.
In order to prevent the underside of the runner 40 from adhering to the top
side of the upper half 7 or to the injected layer 41, an intermediate layer 46 is preferably
present on the underside of the runner material 40.
The lateral confinement of the rail 6 by means of the sections 43 can be
carried out in such a way that most of the noise of the rail 6 is screened off.
A further advantage of the use of the bearing element according to the
present invention, both in the embodiment according to Figure 2 and in the embodiment
according to Figure 5, is that the height of the rails relative to the top surface 16 of the
bearing element 1 can also be adjusted subsequently. That means that, for example in a
bend, where the rails are always laid at a certain inclination relative to each other, said
inclination can be adjusted. The angle of inclination at which the two rails are situated
relative to each other in a bend is directly dependent on the speed at which the trains
have to be able to travel along the railway track. When this speed changes, the angle of
inclination must also change with it. That is possible when the bearing element 1
according to the present invention is used.
Figure 6 shows a view of the bearing element 1 according to the invention,
which is used as a runway for aircraft. It can be seen from Figure 6 that the tubular
construction makes it possible to use the open space in the bearing element 1, for
example, for fitting lighting 60 in the road surface. The wiring 61 and the like can be
conducted underneath the road surface. This makes it possible to carry out maintenance
work on the runway without having to stop the use thereof.