EP0014512A2 - Method of installing a ground anchor - Google Patents
Method of installing a ground anchor Download PDFInfo
- Publication number
- EP0014512A2 EP0014512A2 EP80200113A EP80200113A EP0014512A2 EP 0014512 A2 EP0014512 A2 EP 0014512A2 EP 80200113 A EP80200113 A EP 80200113A EP 80200113 A EP80200113 A EP 80200113A EP 0014512 A2 EP0014512 A2 EP 0014512A2
- Authority
- EP
- European Patent Office
- Prior art keywords
- ground
- anchor
- shank
- blade
- screwed
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000000034 method Methods 0.000 title claims abstract description 10
- 239000012530 fluid Substances 0.000 claims abstract description 16
- 238000002347 injection Methods 0.000 claims description 6
- 239000007924 injection Substances 0.000 claims description 6
- 239000002689 soil Substances 0.000 description 4
- 238000007596 consolidation process Methods 0.000 description 3
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 3
- 238000004873 anchoring Methods 0.000 description 2
- 239000003673 groundwater Substances 0.000 description 2
- 238000003825 pressing Methods 0.000 description 2
- 238000003466 welding Methods 0.000 description 2
- 238000011161 development Methods 0.000 description 1
- 230000018109 developmental process Effects 0.000 description 1
- 238000005553 drilling Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 239000007788 liquid Substances 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 239000000203 mixture Substances 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 230000035515 penetration Effects 0.000 description 1
- 230000008092 positive effect Effects 0.000 description 1
- 238000007789 sealing Methods 0.000 description 1
- 238000007711 solidification Methods 0.000 description 1
- 230000008023 solidification Effects 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/74—Means for anchoring structural elements or bulkheads
- E02D5/80—Ground anchors
- E02D5/801—Ground anchors driven by screwing
Definitions
- the invention relates to a method of arranging a ground anchor into the ground, said anchor comprising a shank and at least one helical blade arranged on the outer side of said shank, the shank with the blade being screwed into the ground.
- Such a ground anchor as described, for example, in German Patent Application 1,634,671 is employed for may purposes, for example, for fixing or anchoring dam walls along channels and rivers, for anchoring high masts, air halls and the like.
- Such anchors screwed into the ground generally have a satisfying effect, the force that can be exerted on such anchors always strongly depends upon the conditions of the ground into which the anchor is screwed. During drilling operations it has been found, in practice that even at small intervals appreciable differences in the solidity of the ground can be assessed.
- the invention has for its object to provide a method of the kind set forth by which the ground anchor can be arranged in a simple manner such that in addition a satisfactory ground condition is safeguarded so that optimum fixation of the ground anchor in the ground is invariably obtained.
- this can be achieved in that after the ground anchor is screwed into the ground first air or gas is-injected into the ground surrounding the blade, after which a hardening fluid is injected.
- Hardening fluids solidifying within a comparatively short time after injection into the ground are known, for example, from German Patent Application 2,819,974 and 2,820,963.
- a particularly suitable ground anchor for carrying out the method according to the invention is obtained, when the shank has, over at least part of its lenght, a passage which is open at least near the top side of the anchor and which communicates with the external side of the anchor through at least one bore located near the helical blade.
- the hardening fluid can be injected through the passage and the bore into the ground surrounding the anchor.
- the ground anchor illustrated in the Figure comprises a hollow shank 1 surrounded over part of its circumference in known manner by a helical blade 2.
- the hollow shank 1 has at both ends inner screwthread 3 and 4 respectively.
- a correspondingly screwthreaded end 5 of a closing piece 6 for the shank is screwed Into the lower end of the shank with the screwthread 4 a correspondingly screwthreaded end 5 of a closing piece 6 for the shank.
- the closing piece 6 has a bevelled tip 7.
- the lower end of the shank may be closed in a different manner, for example, by welding the closing piece 6 to the shank or, for example by flattening and/or sealing by welding the lower end of the shank 1.
- the top end of the shank is surrounded by a rectangular or square block 8 having a bore for receiving the top end of the shank.
- the b&ock 8 is welded to the top end of the shank.
- the block 8 may be used for mounting a tool for screwing the anchor into the ground.
- the Figure shows furthermore that near the blade at least one more or less helically extending bore is provided in the wall of the shank 1 so that the passage 9 in the interior of the shank communicates with the )uter side of the ground anchor through said more or less radial bore 10.
- a plurality of such bores will be provided along the length and the circumference of the shank.
- a hose or the like can be connected with the open top end of the passage so that with the aid of a pump or the like air or gas can first be injected through the passage 9 and the bore(s) 10 into the ground surrounding the anchor.
- the introduced air will drive away the water contained in the ground surrounding the ground anchor.
- a fluid can be injected through the passage 9 and the bore(s) 10 into the ground surrounding the ground anchor.
- the composition of the fluid employed is such that after a comparatively short time this fluid will solidify in the ground so that the ground surrounding the anchor is consolidated.
- the blade 2 may, of course , be designed so that it extends through more than 360° around the shank.
- the shank may be provided with a plurality of blades overlapping ene another in the direction of lenght of the shank.
- the ground located between said blades will be solidified, which is advantageous for withstanding both tensile and pressing forces.
- the injection can be carried out beneath and above the lower and upper blades respectively by providing suitable bores 10 in the shank.
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Piles And Underground Anchors (AREA)
- Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
Abstract
Description
- Method of arranging a ground anchor into the ground and ground anchor intended for carrying out said method.
- The invention relates to a method of arranging a ground anchor into the ground, said anchor comprising a shank and at least one helical blade arranged on the outer side of said shank, the shank with the blade being screwed into the ground.
- Such a ground anchor as described, for example, in German Patent Application 1,634,671 is employed for may purposes, for example, for fixing or anchoring dam walls along channels and rivers, for anchoring high masts, air halls and the like. Although such anchors screwed into the ground generally have a satisfying effect, the force that can be exerted on such anchors always strongly depends upon the conditions of the ground into which the anchor is screwed. During drilling operations it has been found, in practice that even at small intervals appreciable differences in the solidity of the ground can be assessed.
- The invention has for its object to provide a method of the kind set forth by which the ground anchor can be arranged in a simple manner such that in addition a satisfactory ground condition is safeguarded so that optimum fixation of the ground anchor in the ground is invariably obtained.
- According to the invention this can be achieved in that after the ground anchor is screwed into the ground first air or gas is-injected into the ground surrounding the blade, after which a hardening fluid is injected.
- The air or the gas will drive out any water contained in the soil surrounding the ground anchor so that the subsequently injected fluid can penetrate into the surrounding soil over a large distance away from the ground anchor without mixing with water. As a result an effective consolidation of the soil around the ground anchor an an effective fixation of the ground anchor are obtained. :
- Hardening fluids solidifying within a comparatively short time after injection into the ground are known, for example, from German Patent Application 2,819,974 and 2,820,963.
- A particularly suitable ground anchor for carrying out the method according to the invention is obtained, when the shank has, over at least part of its lenght, a passage which is open at least near the top side of the anchor and which communicates with the external side of the anchor through at least one bore located near the helical blade. Thus the hardening fluid can be injected through the passage and the bore into the ground surrounding the anchor.
- The invention will be described more fully hereinafter with reference to an embodiment of the ground anchor in accordance with the invention shown schematically in the accompanying Figure.
- The ground anchor illustrated in the Figure comprises a hollow shank 1 surrounded over part of its circumference in known manner by a helical blade 2. In the embodiment shown the hollow shank 1 has at both ends
inner screwthread 3 and 4 respectively. Into the lower end of the shank with the screwthread 4 is screwed a correspondingly screwthreadedend 5 of a closing piece 6 for the shank. The closing piece 6 has a bevelled tip 7. Obviously, the lower end of the shank may be closed in a different manner, for example, by welding the closing piece 6 to the shank or, for example by flattening and/or sealing by welding the lower end of the shank 1. - The top end of the shank is surrounded by a rectangular or square block 8 having a bore for receiving the top end of the shank. The b&ock 8 is welded to the top end of the shank. The block 8 may be used for mounting a tool for screwing the anchor into the ground.
- The Figure shows furthermore that near the blade at least one more or less helically extending bore is provided in the wall of the shank 1 so that the passage 9 in the interior of the shank communicates with the )uter side of the ground anchor through said more or less radial bore 10. In general, a plurality of such bores will be provided along the length and the circumference of the shank.
- After the anchor shown in the Figure is screwed into the ground in a manner known per se, a hose or the like can be connected with the open top end of the passage so that with the aid of a pump or the like air or gas can first be injected through the passage 9 and the bore(s) 10 into the ground surrounding the anchor. The introduced air will drive away the water contained in the ground surrounding the ground anchor. Subsequently with the aid of a pump or by means of pressurized air or the like a fluid can be injected through the passage 9 and the bore(s) 10 into the ground surrounding the ground anchor. The composition of the fluid employed is such that after a comparatively short time this fluid will solidify in the ground so that the ground surrounding the anchor is consolidated. By using a comparatively thin-liquid fluid all cracks set free of any ground water in the ground surrounding the anchor will be effectively filled with this fluid so that a particularly effective consolidation of the ground surrounding the anchor is obtained., which has a positive effect on the magnitude of the force that can be absorbed by the anchor, when after the solidification of the fluid the materials to be supported by the anchor are coupled with the top end of the shank of the anchor remaining in the ground.
- It has been found that by supplanting the ground water the soil surrounding the ground anchor prior to the injection of the fluid an improved penetration of the hardening fluid in the ground is obtained. As a matter or course, after the introduction of air or gas into the ground surrounding the anchor the pressure of the air or the gas in the passage of the ground anchor will preferably be maintained during the change-over from the injection of air or gas to the injection of the fluid.
- As a matter of course further developments and/or modifications of the ambodiment described above are possible. For example, it will be preferred to provide bores 10 beneath and above the blade 2 in order to obtain consolidation of the ground both beneath and above the blade, which is particularly important when in use the anchor may be exposed both to tensile and pressing forces.
- The blade 2 may, of course , be designed so that it extends through more than 360° around the shank.
- As an alternative, the shank may be provided with a plurality of blades overlapping ene another in the direction of lenght of the shank.
- By injecting fluid between the overlapping parts of the blades, the ground located between said blades will be solidified, which is advantageous for withstanding both tensile and pressing forces. As a matter of course, also in this case the injection can be carried out beneath and above the lower and upper blades respectively by providing suitable bores 10 in the shank.
Claims (3)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
AT80200113T ATE1866T1 (en) | 1979-02-13 | 1980-02-11 | PROCEDURE FOR PLACING A GROUND ANCHOR IN THE GROUND. |
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
NL7901116A NL7901116A (en) | 1979-02-13 | 1979-02-13 | METHOD FOR GROUNDING AN GROUND ANCHOR AND GROUND ANCHOR INTENDED FOR CARRYING OUT THIS METHOD |
NL7901116 | 1979-02-13 |
Publications (3)
Publication Number | Publication Date |
---|---|
EP0014512A2 true EP0014512A2 (en) | 1980-08-20 |
EP0014512A3 EP0014512A3 (en) | 1980-09-03 |
EP0014512B1 EP0014512B1 (en) | 1982-11-24 |
Family
ID=19832625
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
EP80200113A Expired EP0014512B1 (en) | 1979-02-13 | 1980-02-11 | Method of installing a ground anchor |
Country Status (4)
Country | Link |
---|---|
EP (1) | EP0014512B1 (en) |
AT (1) | ATE1866T1 (en) |
DE (1) | DE3061118D1 (en) |
NL (1) | NL7901116A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE4424339A1 (en) * | 1994-07-11 | 1996-01-18 | Arthur Keck | Ground anchor for securing metallic or wooden posts |
CZ304086B6 (en) * | 2011-12-22 | 2013-10-09 | Vysoká Skola Bánská Technická - Univerzita Ostrava | Means for grouting with integrated feeding of grouting medium and air bleeding |
WO2014180466A1 (en) | 2013-05-08 | 2014-11-13 | Teske Stefan | Ground anchor |
Families Citing this family (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP0155119B1 (en) * | 1984-02-27 | 1990-07-25 | Multilift Limited | Container and lifting mechanism |
GB2160237A (en) * | 1984-05-25 | 1985-12-18 | Bennett Walter | Ground engaging member |
NL192836C (en) * | 1984-10-17 | 2000-02-18 | Leeuwen Marinus Teunis Van | Screw anchor. |
NL1004746C2 (en) * | 1996-12-11 | 1998-06-15 | Van Leeuwen Harmelen Bv Geb | Method for harvesting resp. moving trees. |
US6058662A (en) * | 1997-07-18 | 2000-05-09 | Secure Products, Llc | Earth anchors and methods for their use |
DE102013105859A1 (en) | 2013-06-06 | 2014-12-11 | SG Holding UG (haftungsbeschränkt) | A soil-hardening substance for permanent fixation of a ground anchor or ground anchor and a method for introducing the same |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE228921C (en) * | ||||
US2603319A (en) * | 1952-07-15 | Ground anchor v | ||
FR1306492A (en) * | 1961-11-20 | 1962-10-13 | S R L E L S E Edilizia Lavori | Process for obtaining the stabilization and consolidation of subsoil soils, and the corresponding perforator-mixer tool |
GB1115796A (en) * | 1965-04-06 | 1968-05-29 | Bauer Karl Heinz | Improvements in and relating to ground anchors and methods of making such anchors |
DE2334418A1 (en) * | 1973-07-06 | 1975-01-23 | Stelag Konstruktion | Soil anchor for support walls and buildings - consists of steel tube with ram point and spiral plate type holder |
-
1979
- 1979-02-13 NL NL7901116A patent/NL7901116A/en not_active Application Discontinuation
-
1980
- 1980-02-11 DE DE8080200113T patent/DE3061118D1/en not_active Expired
- 1980-02-11 EP EP80200113A patent/EP0014512B1/en not_active Expired
- 1980-02-11 AT AT80200113T patent/ATE1866T1/en not_active IP Right Cessation
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE228921C (en) * | ||||
US2603319A (en) * | 1952-07-15 | Ground anchor v | ||
FR1306492A (en) * | 1961-11-20 | 1962-10-13 | S R L E L S E Edilizia Lavori | Process for obtaining the stabilization and consolidation of subsoil soils, and the corresponding perforator-mixer tool |
GB1115796A (en) * | 1965-04-06 | 1968-05-29 | Bauer Karl Heinz | Improvements in and relating to ground anchors and methods of making such anchors |
DE2334418A1 (en) * | 1973-07-06 | 1975-01-23 | Stelag Konstruktion | Soil anchor for support walls and buildings - consists of steel tube with ram point and spiral plate type holder |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE4424339A1 (en) * | 1994-07-11 | 1996-01-18 | Arthur Keck | Ground anchor for securing metallic or wooden posts |
DE4424339C2 (en) * | 1994-07-11 | 1999-02-11 | Arthur Keck | Ground anchor |
CZ304086B6 (en) * | 2011-12-22 | 2013-10-09 | Vysoká Skola Bánská Technická - Univerzita Ostrava | Means for grouting with integrated feeding of grouting medium and air bleeding |
WO2014180466A1 (en) | 2013-05-08 | 2014-11-13 | Teske Stefan | Ground anchor |
DE102013104773A1 (en) | 2013-05-08 | 2014-11-13 | Jörg Pagels | ground anchor |
Also Published As
Publication number | Publication date |
---|---|
NL7901116A (en) | 1980-08-15 |
EP0014512A3 (en) | 1980-09-03 |
ATE1866T1 (en) | 1982-12-15 |
EP0014512B1 (en) | 1982-11-24 |
DE3061118D1 (en) | 1982-12-30 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US4779389A (en) | Method and apparatus for insitu reinforcement, repair and safety enhancement of wooden poles | |
US4253781A (en) | Method and an apparatus for providing a grouted anchorage against hydrostatic pressure | |
EP0014512A2 (en) | Method of installing a ground anchor | |
DE102006058458A1 (en) | Testing device consists of workpiece carrier which has a chamber and temperate system for heating and cooling of chamber | |
ES8503764A1 (en) | Method for making a concrete or similar pile on site. | |
DE2226169C2 (en) | Device for the formation of a grouting anchor | |
US5348424A (en) | Reinforcing block for excavation work and method of construction thereof | |
EP0539630A1 (en) | Method of providing a foundation pile with enlarged base in the ground | |
KR100389936B1 (en) | Ground reinforcement or stabilisation method and apparatus | |
JP3596687B2 (en) | Seismic retrofitting method for existing foundation | |
JPH0762651A (en) | Freezing anchor construction method | |
DE2354764B2 (en) | Method and device for the watertight implementation of a built-in component to be introduced into the ground through a building wall or excavation pit wall or floor | |
EP1075587B1 (en) | Device for a rock wall | |
GB2120304A (en) | Forming concrete piles | |
DE3926787C2 (en) | Method and device for inserting and anchoring a tensile pile | |
DE8800265U1 (en) | Device for injecting injection material | |
EP3542000B1 (en) | Method for dismantling offshore foundation structures | |
AT135768B (en) | Method and device for pressing filling or sealing material into cracked concrete, fissured rock or the like. | |
KR0166423B1 (en) | Direct drilling steel pipe reinforcement multi-stage grouting construction method and direct drilling device | |
JPS6210325A (en) | Foot protecting of pile | |
EP0134379A1 (en) | Anchor element for tie bars in civil works | |
KR100441627B1 (en) | Apparatus for Injecting Grouting Liquid Through Pile Hole | |
JP2521643B2 (en) | Foundation pile construction method | |
DE102004013017B4 (en) | Device for manufacture of in-situ concrete foundations for overhead line masts, for example, comprises prefabricated shuttering component with outer walls or at least one outer wall having circular openings | |
JPS5616727A (en) | Submarine anchor and method of producing the same |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PUAI | Public reference made under article 153(3) epc to a published international application that has entered the european phase |
Free format text: ORIGINAL CODE: 0009012 |
|
PUAL | Search report despatched |
Free format text: ORIGINAL CODE: 0009013 |
|
AK | Designated contracting states |
Designated state(s): AT BE CH DE FR GB IT LU NL SE |
|
AK | Designated contracting states |
Designated state(s): AT BE CH DE FR GB IT LU NL SE |
|
17P | Request for examination filed |
Effective date: 19810130 |
|
ITF | It: translation for a ep patent filed | ||
GRAA | (expected) grant |
Free format text: ORIGINAL CODE: 0009210 |
|
AK | Designated contracting states |
Designated state(s): AT BE CH DE FR GB IT LU NL SE |
|
REF | Corresponds to: |
Ref document number: 1866 Country of ref document: AT Date of ref document: 19821215 Kind code of ref document: T |
|
REF | Corresponds to: |
Ref document number: 3061118 Country of ref document: DE Date of ref document: 19821230 |
|
ET | Fr: translation filed | ||
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: LU Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 19830228 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: CH Payment date: 19840301 Year of fee payment: 5 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: SE Payment date: 19840331 Year of fee payment: 5 Ref country code: BE Payment date: 19840331 Year of fee payment: 5 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: DE Payment date: 19840424 Year of fee payment: 5 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: LU Payment date: 19860303 Year of fee payment: 7 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: AT Payment date: 19870223 Year of fee payment: 8 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: AT Effective date: 19890211 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: SE Effective date: 19890212 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: CH Effective date: 19890228 Ref country code: BE Effective date: 19890228 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: NL Payment date: 19890228 Year of fee payment: 10 Ref country code: GB Payment date: 19890228 Year of fee payment: 10 Ref country code: FR Payment date: 19890228 Year of fee payment: 10 |
|
BERE | Be: lapsed |
Owner name: STOLK MARIE Effective date: 19890228 |
|
REG | Reference to a national code |
Ref country code: CH Ref legal event code: PL |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: DE Effective date: 19891101 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: GB Effective date: 19900211 |
|
ITTA | It: last paid annual fee | ||
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: NL Effective date: 19900901 |
|
GBPC | Gb: european patent ceased through non-payment of renewal fee | ||
NLV4 | Nl: lapsed or anulled due to non-payment of the annual fee | ||
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: FR Effective date: 19901031 |
|
REG | Reference to a national code |
Ref country code: FR Ref legal event code: ST |
|
EUG | Se: european patent has lapsed |
Ref document number: 80200113.1 Effective date: 19900118 |
|
PLBE | No opposition filed within time limit |
Free format text: ORIGINAL CODE: 0009261 |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT |