Info

Publication number
CN216406692U
CN216406692U CN202122786031.2U CN202122786031U CN216406692U CN 216406692 U CN216406692 U CN 216406692U CN 202122786031 U CN202122786031 U CN 202122786031U CN 216406692 U CN216406692 U CN 216406692U
Authority
CN
China
Prior art keywords
support
rod
welded
positioning device
block
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202122786031.2U
Other languages
Chinese (zh)
Inventor
陈文瑞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Hengfeng Engineering Construction Co ltd
Original Assignee
Guangdong Zhuye Construction Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Zhuye Construction Co ltd filed Critical Guangdong Zhuye Construction Co ltd
Priority to CN202122786031.2U priority Critical patent/CN216406692U/en
Application granted granted Critical
Publication of CN216406692U publication Critical patent/CN216406692U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Drilling And Boring (AREA)

Abstract

The utility model discloses a positioning device for construction engineering construction, which comprises: a lifting mechanism and a clamping mechanism; the lifting mechanism comprises a base, a sliding rod is fixedly mounted at the top of the base, and a movable plate is movably sleeved on the sliding rod; the clamping mechanism comprises a support fixedly arranged on one side of the movable plate, a threaded rod is connected to the inner portion of the support in a threaded mode, and a push block is welded to one end of the threaded rod; according to the positioning device for the construction of the building engineering, through the arrangement of the lifting mechanism and the clamping mechanism, after the threaded rod drives the driving rack to move through the push block and the movable block, the driven rack can drive the clamping plate to clamp the drilling machine under the action of the gear; the movable plate can slide on the sliding rod to facilitate the drilling machine fixed on the clamping mechanism to move up and down; through the arrangement, the drilling machine can be positioned during drilling, and the problem that the drilled hole of the drilling machine is deviated and inclined due to self vibration of the drilling machine is avoided.

Description

Positioner is used in building engineering construction
Technical Field
The utility model relates to the technical field of building construction, in particular to a positioning device for building engineering construction.
Background
As is well known, building construction refers to production activities in the construction and implementation stage of engineering construction, and is a construction process of various buildings, and also can be a process of changing various lines on a design drawing into a real object at a designated place. The method comprises foundation engineering construction, main structure construction, roofing engineering construction, decoration engineering construction and the like.
In the process of building construction, a drilling machine needs to be used for drilling the ground, but the drilling machine in operation is not provided with a positioning device in the prior art, so that the drilling machine can lead to the swinging of a drill bit due to self vibration in the drilling process, and further the problem that the drilled hole of the drilling machine has deviation and inclination is caused.
SUMMERY OF THE UTILITY MODEL
The utility model aims to provide a positioning device for construction engineering construction, which aims to solve the problems in the background technology.
In order to achieve the purpose, the utility model provides the following technical scheme: a positioning device for construction of constructional engineering, comprising: a lifting mechanism and a clamping mechanism;
the lifting mechanism comprises a base, a sliding rod is fixedly mounted at the top of the base, and a movable plate is movably sleeved on the sliding rod; the lifting mechanism is used for facilitating the drilling machine to normally drill after being fixed by the clamping mechanism and limiting the drilling machine;
the clamping mechanism comprises a bracket fixedly arranged on one side of the movable plate, the inner part of the bracket is connected with a threaded rod through threads, one end of the threaded rod is welded with a push block, the outer side of the push block is tightly attached with two movable blocks, one side of the two movable blocks, which is opposite to the other side, is fixedly connected with a driving rack, one side of the driving rack is welded with a sliding block, one side of the sliding block is connected with the bracket in a sliding way, the other side of the sliding block is welded with a spring, one end of the spring is welded on the bracket, the other side of the active rack is engaged and connected with a gear, one side of the gear is rotationally connected to the bracket through the supporting plate, one side of the gear far away from the driving rack is engaged and connected with the driven rack, a movable rod is welded at one side of the driven rack, the outer side wall of the movable rod is connected inside the bracket in a sliding manner, and a clamping plate is fixedly connected at one side of the driven rack away from the movable rod; the clamping mechanism is used for clamping the drilling machine and reducing the vibration amplitude of the drilling machine;
by adopting the technical scheme, the pushing block can simultaneously extrude the two movable blocks under the action of the threaded rod by screwing the threaded rod on the bracket, so that the two movable blocks can respectively drive the driving rack to move towards the direction far away from the pushing block, and the sliding block can slide on the bracket under the action of the driving rack; when the two driving racks move, the two driven racks can be driven by the gears to move in a mutually approaching mode, so that the clamp plate can clamp a main machine of the drilling machine under the action of the driven racks; when drilling work is required, the movable plate can slide downwards on the sliding rod, so that a drill bit of the drilling machine can drill holes on the ground, and the vibration amplitude of the drilling machine during operation can be reduced.
Preferably, the quantity of splint is two, two the equal fixedly connected with equidistance distribution's of one side that the splint are relative antiskid lug.
Through adopting above-mentioned technical scheme, can increase the clamping strength of splint to the rig.
Preferably, the bottom fixed mounting of base has the universal wheel, the welding of top one side of base has the push rod.
Through adopting above-mentioned technical scheme, the base that can be convenient for drives this device and removes.
Preferably, the top of the base is fixedly connected with a weight through a screw, and the movable plate is internally provided with a first through groove.
By adopting the technical scheme, the weight of the base can be increased, so that the device can be kept stable to the greatest extent when being matched with a drilling machine for use, and the movable plate cannot be blocked by the weight when moving downwards.
Preferably, a baffle is welded at the top of the sliding rod.
Through adopting above-mentioned technical scheme, can carry out spacingly to the fly leaf, avoid the fly leaf to break away from the slide bar.
Preferably, one end of the movable rod, which is far away from the driven rack, extends to the outside of the bracket and is welded with a stop block.
Through adopting above-mentioned technical scheme, can carry on spacingly to the movable rod, avoid driven rack to drive the movable rod and break away from with the support when the support is inside to slide.
Preferably, a second through groove is formed in one side, close to the driving rack, of the support.
Through adopting above-mentioned technical scheme, can make the support can not lead to the fact the blockking to the removal of initiative rack.
Preferably, one end of the threaded rod, which is far away from the push block, is welded with a connecting block, and one side of the connecting block is provided with a groove.
Through adopting above-mentioned technical scheme, the spanner can insert and twist the connecting block in the recess to be convenient for the staff operates the screw rod more.
Compared with the prior art, the utility model has the beneficial effects that:
according to the positioning device for the construction of the building engineering, through the arrangement of the lifting mechanism and the clamping mechanism, after the threaded rod drives the driving rack to move through the push block and the movable block, the driven rack can drive the clamping plate to clamp the drilling machine under the action of the gear; the movable plate can slide on the sliding rod to facilitate the drilling machine fixed on the clamping mechanism to move up and down; through the arrangement, the drilling machine can be positioned during drilling, and the problem that the drilled hole of the drilling machine is deviated and inclined due to self vibration of the drilling machine is avoided.
Drawings
FIG. 1 is a schematic structural view of a positioning device for construction of a construction project according to the present invention;
FIG. 2 is a schematic structural view of a movable plate and a bracket in the positioning device for construction of constructional engineering of the present invention;
FIG. 3 is a schematic structural view of a pushing block and a movable block in the positioning device for construction of constructional engineering of the present invention;
fig. 4 is a schematic structural view of a connecting block and a groove in the positioning device for construction of constructional engineering of the present invention.
In the figure: 1. a lifting mechanism; 10. a base; 11. a slide bar; 12. a movable plate; 13. a first through groove; 14. a baffle plate; 15. a weight block; 16. a universal wheel; 17. a push rod; 2. a clamping mechanism; 20. a support; 21. a threaded rod; 22. a push block; 23. a movable block; 24. a driving rack; 25. a slider; 26. a spring; 27. a gear; 28. a support plate; 29. a driven rack; 201. a movable rod; 202. a splint; 203. an anti-slip bump; 204. a stopper; 205. a second through groove; 206. connecting blocks; 207. and (4) a groove.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
Referring to fig. 1-4, the present invention provides a technical solution: a positioning device for construction of constructional engineering, comprising: a lifting mechanism 1 and a clamping mechanism 2; the lifting mechanism 1 is used for facilitating the normal drilling work of the drilling machine after the drilling machine is fixed by the clamping mechanism 2 and limiting the drilling machine; the clamping mechanism 2 is used for clamping the drilling machine and reducing the vibration amplitude of the drilling machine;
in order to enable the movable plate 12 to slide downwards on the sliding rod 11 and further enable the drilling machine fixed on the clamping mechanism 2 to drill the ground when drilling work is required, and to enable the vibration amplitude of the drilling machine during operation to be reduced due to the limiting effect, the lifting mechanism 1 comprises a base 10, the top of the base 10 is fixedly provided with the sliding rod 11, and the movable plate 12 is movably sleeved on the sliding rod 11; in order to facilitate the base 10 to drive the device to move, the bottom of the base 10 is fixedly provided with universal wheels 16, and one side of the top of the base 10 is welded with a push rod 17; in order to increase the weight of the base 10 and further to enable the device to be kept stable to the maximum extent when being matched with a drilling machine for use, and in order that the movable plate 12 cannot be blocked by the weight 15 when moving downwards, the weight 15 is fixedly connected to the top of the base 10 through screws, and the movable plate 12 is internally provided with a first through groove 13; in order to limit the movable plate 12 and further avoid the movable plate 12 from being separated from the sliding rod 11, a baffle plate 14 is welded at the top of the sliding rod 11;
wherein, in order to enable the push block 22 to simultaneously extrude the two movable blocks 23 under the action of the threaded rod 21 by screwing the threaded rod 21 on the bracket 20, so that the two movable blocks 23 can respectively drive the driving rack 24 to move towards the direction far away from the push block 22, and further enable the sliding block 25 to slide on the bracket 20 under the action of the driving rack 24, and the two driving racks 24 can respectively drive the two driven racks 29 to move in a mutual approaching manner through the gear 27 while moving, so that the clamping plate 202 can clamp the main machine of the drilling machine under the action of the driven rack 29, the clamping mechanism 2 comprises the bracket 20 fixedly arranged on one side of the movable plate 12, the threaded rod 21 is connected with the inner thread of the bracket 20, the push block 22 is welded at one end of the threaded rod 21, the two movable blocks 23 are tightly attached to the outer side of the push block 22, the two opposite sides of the two movable blocks 23 are both fixedly connected with the driving rack 24, a sliding block 25 is welded on one side of the driving rack 24, one side of the sliding block 25 is connected with the support 20 in a sliding mode, a spring 26 is welded on the other side of the sliding block 25, one end of the spring 26 is welded on the support 20, the other side of the driving rack 24 is connected with a gear 27 in a meshing mode, one side of the gear 27 is connected to the support 20 in a rotating mode through a supporting plate 28, one side, away from the driving rack 24, of the gear 27 is connected with a driven rack 29 in a meshing mode, a movable rod 201 is welded on one side of the driven rack 29, the outer side wall of the movable rod 201 is connected inside the support 20 in a sliding mode, and a clamping plate 202 is fixedly connected on one side, away from the movable rod 201, of the driven rack 29; in order to increase the clamping force of the clamping plates 202 on the drilling machine, the number of the clamping plates 202 is two, and the opposite sides of the two clamping plates 202 are fixedly connected with anti-skid lugs 203 which are distributed at equal intervals; in order to limit the movable rod 201 and prevent the movable rod 201 from being separated from the support 20 when the movable rod 201 is driven by the driven rack 29 to slide in the support 20, one end of the movable rod 201, which is far away from the driven rack 29, extends to the outside of the support 20 and is welded with a stop block 204; in order to prevent the bracket 20 from blocking the movement of the driving rack 24, a second through groove 205 is formed on one side of the bracket 20 close to the driving rack 24; in order to enable a wrench to be inserted into the groove 207 to screw the connecting block 206, and therefore to be more convenient for a worker to operate the threaded rod 21, the connecting block 206 is welded to one end, away from the push block 22, of the threaded rod 21, and the groove 207 is formed in one side of the connecting block 206.
According to the technical scheme, the working steps of the scheme are summarized and carded: when in use, a drill bit of the drilling machine is downward, and the main machine part of the drilling machine is positioned between the two clamping plates 202; then, a wrench is inserted into the groove 207 to screw the connecting block 206, so that the pushing block 22 can be driven to extrude the two movable blocks 23 in the process that the threaded rod 21 is gradually screwed on the bracket 20; the two driving racks 24 can be driven by the movable block 23 to move away from each other on the sliding chute inside the bracket 20 through the sliding block 25, and the two driven racks 29 can be driven by the gear 27 to move close to each other; the two driven racks 29 slide in the bracket 20 through the movable rod 201 and drive the clamping plate 202 to clamp the main machine part of the drilling machine in the process of gradually approaching each other; after the drilling machine is started, the vibration amplitude of the drilling machine during operation is preliminarily reduced due to the fact that the drilling machine is fixed on the clamping mechanism 2 by the main machine; the staff can slide up and down on the slide bar 11 through the control fly leaf 12 and carry out drilling operation to the rig, because fly leaf 12 can only remove with the mode of sliding up and down on slide bar 11 to make the rig unable horizontal hunting when drilling, and then make the drill bit can drill out more accurate hole, solved the hole of drilling and had the problem of skew slope.
To sum up: according to the positioning device for the construction of the building engineering, through the arrangement of the lifting mechanism 1 and the clamping mechanism 2, after the threaded rod 21 drives the driving rack 24 to move through the push block 22 and the movable block 23, the driven rack 29 can drive the clamping plate 202 to clamp a drilling machine under the action of the gear 27; and the movable plate 12 can slide on the sliding rod 11 to facilitate the up-and-down movement of the drilling machine fixed on the clamping mechanism 2; through the arrangement, the drilling machine can be positioned during drilling, and the problem that the drilled hole of the drilling machine is deviated and inclined due to self vibration of the drilling machine is avoided.
The parts not involved in the present invention are the same as or can be implemented by the prior art. Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the utility model, the scope of which is defined in the appended claims and their equivalents.

Claims (8)

1. The utility model provides a positioner is used in building engineering construction which characterized in that includes: a lifting mechanism (1) and a clamping mechanism (2);
the lifting mechanism (1) comprises a base (10), a sliding rod (11) is fixedly mounted at the top of the base (10), and a movable plate (12) is movably sleeved on the sliding rod (11);
the clamping mechanism (2) comprises a support (20) fixedly installed on one side of a movable plate (12), a threaded rod (21) is connected to the inner thread of the support (20), a push block (22) is welded to one end of the threaded rod (21), two movable blocks (23) are tightly attached to the outer side of the push block (22), an active rack (24) is fixedly connected to one side of each of the two movable blocks (23) opposite to each other, a sliding block (25) is welded to one side of the active rack (24), one side of the sliding block (25) is in sliding connection with the support (20), a spring (26) is welded to the other side of the sliding block (25), one end of the spring (26) is welded to the support (20), a gear (27) is meshed to the other side of the active rack (24), and one side of the gear (27) is rotatably connected to the support (20) through a support plate (28), one side meshing that initiative rack (24) was kept away from in gear (27) is connected with driven rack (29), one side welding of driven rack (29) has movable rod (201), the inside at support (20) of lateral wall sliding connection of movable rod (201), one side fixedly connected with splint (202) of movable rod (201) are kept away from in driven rack (29).
2. The positioning device for construction engineering according to claim 1, wherein: the quantity of splint (202) is two, two the equal fixedly connected with equidistance of one side that splint (202) are relative antiskid lug (203) that distribute.
3. The positioning device for construction engineering according to claim 1, wherein: the bottom fixed mounting of base (10) has universal wheel (16), the welding of top one side of base (10) has push rod (17).
4. The positioning device for construction engineering according to claim 3, wherein: the top of the base (10) is fixedly connected with a heavy block (15) through a screw, and a first through groove (13) is formed in the movable plate (12).
5. The positioning device for construction engineering according to claim 1, wherein: the top of the sliding rod (11) is welded with a baffle (14).
6. The positioning device for construction engineering according to claim 1, wherein: one end, far away from the driven rack (29), of the movable rod (201) extends to the outside of the support (20) and is welded with a stop block (204).
7. The positioning device for construction engineering according to claim 1, wherein: and a second through groove (205) is formed in one side, close to the driving rack (24), of the support (20).
8. The positioning device for construction engineering according to claim 1, wherein: one end of the threaded rod (21) far away from the push block (22) is welded with a connecting block (206), and one side of the connecting block (206) is provided with a groove (207).
CN202122786031.2U 2021-11-15 2021-11-15 Positioner is used in building engineering construction Active CN216406692U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202122786031.2U CN216406692U (en) 2021-11-15 2021-11-15 Positioner is used in building engineering construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202122786031.2U CN216406692U (en) 2021-11-15 2021-11-15 Positioner is used in building engineering construction

Publications (1)

Publication Number Publication Date
CN216406692U true CN216406692U (en) 2022-04-29

Family

ID=81300588

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202122786031.2U Active CN216406692U (en) 2021-11-15 2021-11-15 Positioner is used in building engineering construction

Country Status (1)

Country Link
CN (1) CN216406692U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116080139A (en) * 2023-02-14 2023-05-09 杭州好时景包装材料有限公司 Die cutting machine is used in carton production of convenient clearance

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116080139A (en) * 2023-02-14 2023-05-09 杭州好时景包装材料有限公司 Die cutting machine is used in carton production of convenient clearance
CN116080139B (en) * 2023-02-14 2023-10-31 杭州好时景包装材料有限公司 Die cutting machine is used in carton production of convenient clearance

Similar Documents

Publication Publication Date Title
CN208895234U (en) A kind of flange processing platform
CN205600331U (en) A anchor clamps for steel tube machining
CN216406692U (en) Positioner is used in building engineering construction
CN210421629U (en) A steel-pipe column for assembly type structure
CN219973218U (en) Foundation pit slope protection structure
CN110976959A (en) Quick drilling processing machinery with adjustable cold-drawn shaped steel section field usage
CN201363109Y (en) Travelling drill pipe racking device
CN209908411U (en) Civil engineering pile foundation construction is with double-deck hole enlargement drill bit
CN2296344Y (en) Iron outlet opening machine of blast furnace
CN213175555U (en) Novel petroleum machinery casing power tongs
CN201363106Y (en) Single-arm contraction-type drill pipe racking device
CN115522870A (en) Domatic boring device of geological mineral exploration
CN210790959U (en) Movable track for industrial robot
CN202038676U (en) Hydraulic chain tensioning device of scraper conveyor and lifting mechanism thereof
CN216197847U (en) Automatic drilling machine for fully mechanized coal mining face
CN214601165U (en) Glass door pulley supporting rod straightening device
CN221320932U (en) Anchor rod construction device for building engineering construction
CN220190183U (en) Low-voltage power distribution cabinet convenient to install
CN219012533U (en) Adjustable spacing pipe wrench for petroleum well workover
CN221546484U (en) Crack reinforcing apparatus for construction
CN212200787U (en) Shock attenuation formula connecting device for steel construction
CN221798036U (en) Combined device for improving anchor changing operation efficiency of concrete sleeper screw spike
CN214996004U (en) Municipal construction is with square design braced frame
CN210141109U (en) Civil engineering construction is with drilling coring device
CN117943590B (en) Drilling positioning device for machining electric telescopic door

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20221221

Address after: 529000 first floor, No. 4, Lane 7, tanbian middle lane street, ChaoLian, Pengjiang district, Jiangmen City, Guangdong Province, self compiled 01

Patentee after: Guangdong Hengfeng Engineering Construction Co.,Ltd.