Nothing Special   »   [go: up one dir, main page]

CN214364583U - Building pipeline's package pipe support reaches package tubular construction and building including it - Google Patents

Building pipeline's package pipe support reaches package tubular construction and building including it Download PDF

Info

Publication number
CN214364583U
CN214364583U CN202120024089.0U CN202120024089U CN214364583U CN 214364583 U CN214364583 U CN 214364583U CN 202120024089 U CN202120024089 U CN 202120024089U CN 214364583 U CN214364583 U CN 214364583U
Authority
CN
China
Prior art keywords
stand
type
building
shaped
external corner
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202120024089.0U
Other languages
Chinese (zh)
Inventor
王凯华
王亮亮
程慧
贠博
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Modern Green Development Co ltd
Original Assignee
Modern Green Development Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Modern Green Development Co ltd filed Critical Modern Green Development Co ltd
Priority to CN202120024089.0U priority Critical patent/CN214364583U/en
Application granted granted Critical
Publication of CN214364583U publication Critical patent/CN214364583U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Building Environments (AREA)
  • Supports For Pipes And Cables (AREA)
  • Pipe Accessories (AREA)

Abstract

The utility model discloses a building pipeline's package pipe holder reaches package tubular construction and building including it belongs to the building field, including U type stand, external corner stand and a plurality of connecting rod, the connecting rod is used for connecting between U type stand and external corner stand, U type stand is equipped with fore-and-aft U type groove, U type stand is used for fixing on the wall, the external corner stand is including erecting the stand and connecting two L type stands of erectting the post both sides, and two L type stands are relative or parallel arrangement forms the draw-in groove, U type groove and draw-in groove cooperation card solid ceramic tile and/or soundproof cotton. The utility model discloses a U type stand and external corner stand are assembled, belong to dry operation method, realize that the technology freely assembles and reach unanimity with the wall body effect, have really realized that simple process, usage space are little, the maintenance is simple, durable reliable, have overcome the temperature stereo set, provide the efficiency, the at utmost accomplished cost adaptation, the best effect, save time and carry the effect.

Description

Building pipeline's package pipe support reaches package tubular construction and building including it
Technical Field
The utility model relates to a building field especially relates to a building pipeline's package pipe support reaches package tubular construction and building including it.
Background
With the rapid development of batch fine-mounting of various properties, in the age of little earth, the traditional wet-working ceramic tile tube wrapping process is complex, the occupied area is large, the maintenance is complex, the ceramic tile tube wrapping process is easy to fall off, the quality is influenced by a large temperature factor, the development rhythm of the existing house is already restricted, the strength of the tube wrapping structure depends on the bonding degree of the ceramic tile and the XPS and the gap between the ceramic tile and the bracket, the ceramic tile tube wrapping structure is easy to damage due to severe impact, and the color of the male and female angle bars can be selected within a single range.
SUMMERY OF THE UTILITY MODEL
The to-be-solved technical problem of the utility model is to provide a building pipeline's package pipe holder reaches package tubular construction and building including it, the utility model discloses a U type stand and external corner stand are assembled, belong to dry operation method, realize that the technology freely assembles and reach unanimity with the wall body effect, really realized that simple process, usage space are little, easy maintenance, durable reliable, overcome the temperature influence, provide the efficiency, the at utmost accomplished cost adaptation, effect best, saved time and carried the effect.
In order to solve the technical problem, the utility model provides a technical scheme as follows:
in one aspect, the utility model provides a building pipeline's envelope pipe support, including U type stand, external corner stand and a plurality of connecting rod, the connecting rod is used for connecting between U type stand and external corner stand, U type stand is equipped with fore-and-aft U type groove, U type stand is used for fixing on the wall, the external corner stand is including erecting the stand and connecting two L type stands of erectting the post both sides, and two L type stands are relative or parallel arrangement form the draw-in groove, solid ceramic tile and/or soundproof cotton of U type groove and draw-in groove cooperation card.
Further, the two L-shaped columns are arranged oppositely and respectively are a short-arm L-shaped column and a long-arm L-shaped column.
Further, the vertical columns of the external corner columns are as high as the L-shaped columns.
Furthermore, the U-shaped upright post can be provided with a connecting hole according to the site, and the connecting hole is used for fixing the U-shaped upright post on the wall through a bolt.
Further, the steel keel reinforcing structure is further included and is used for being installed at the top and/or the bottom of the tube wrapping support.
On the other hand, provide a building pipeline's envelope tubular construction, include building pipeline's envelope pipe support, wherein, two U type stands are used for connecting respectively on the wall, the external corner stand passes through the connecting rod and is connected with two U type stands respectively, has clamped soundproof cotton and ceramic tile between U type groove and draw-in groove, soundproof cotton and ceramic tile's connected mode is for bonding.
Furthermore, gaps of the ceramic tiles are subjected to pointing through viscose and pointing agent.
Further, the soundproof cotton adopts xps plates.
In still another aspect, a building is provided, and a pipe wrapping structure of the building pipeline is installed.
Further, the U-shaped upright posts are connected with the wall through expansion bolts.
After adopting such design, the utility model discloses following advantage has at least:
the utility model discloses a package pipe support is laid bricks to the wet operation of tradition, plaster, the package pipe has carried out the technology innovation, the wet operation way of tradition has been abandoned, dry-type assembled equipment way has been changed into, through doing the operation method, the temperature influence has been overcome, the access hole setting has been cancelled, the package pipe area is little, construction speed is fast, it is effectual to give sound insulation, the maintenance is simple and easy, xps board, the marble is glued, the use that AB is glued, the collision buffering has been strengthened, very big reinforcing the anti impact of brick, this technical application can be according to high free customization, the effectual workman's energy efficiency ratio that has improved, the circulation speed of the wet operation of smart dress in batches has been promoted.
Drawings
The foregoing is only an overview of the technical solutions of the present invention, and in order to make the technical means of the present invention more clear, the present invention will be further described in detail with reference to the accompanying drawings and the detailed description.
Fig. 1 is a schematic top view of an embodiment of a piping structure of a building pipeline according to the present invention;
fig. 2 is a schematic perspective view of an assembled embodiment of the tube-wrapping structure of the building pipeline according to the present invention.
Detailed Description
Exemplary embodiments of the present invention will be described in more detail below with reference to the accompanying drawings. While exemplary embodiments of the invention are shown in the drawings, it should be understood that the invention can be embodied in various forms and should not be limited to the embodiments set forth herein. Rather, these embodiments are provided so that this disclosure will be thorough and complete, and will fully convey the scope of the invention to those skilled in the art.
The utility model provides an embodiment of building pipeline's envelope pipe support, as shown in figure 1, figure 2, including U type stand 1, external corner stand 2 and a plurality of connecting rod 7, connecting rod 7 is used for connecting between U type stand 1 and external corner stand 2, and U type stand 1 is equipped with fore-and-aft U type groove, and U type stand 1 is used for fixing on the wall, and external corner stand 2 is including erecting the stand and connecting two L type stands of erectting the post both sides, and two relative or parallel arrangement of L type stand form the draw-in groove, and U type groove and draw-in groove cooperation card solid ceramic tile 3 and/or soundproof cotton 4.
When the utility model is used, the U-shaped upright posts are fixed on the wall through bolts on the wall around the kitchen pipeline or the public area pipeline to be wrapped, two U-shaped upright posts are generally fixed, the external corner upright posts are fixed at the right-angle line intersection points of the two U-shaped upright posts and are transversely reinforced through the connecting rods, the reinforcing interval is not more than 600mm, and the non-same plane is crossed and reinforced; filling an XPS plate (which can be 15mm) between the U-shaped groove and the clamping groove, approaching the pipe as close as possible, controlling the gap between the XPS plate and the pipe within 10mm, then bonding and installing the back of the tile and the XPS plate (the marble glue and AB glue combined thin paste can be adopted), reserving a gap of 1.5-2mm which is as wide as the adjacent wall surface, and jointing the gap of the tile by using the marble glue and AB glue combined jointing agent, thereby completing the pipe wrapping.
The utility model discloses a U type stand and external corner stand are assembled, belong to dry operation method, realize that the technology freely assembles and reach unanimity with the wall body effect, have really realized that simple process, usage space are little, the maintenance is simple, durable reliable, have overcome the temperature influence, provide the efficiency, the at utmost accomplished cost adaptation, effect best, save time and carry the effect.
The U-shaped groove can be a U-shaped groove with the width of 25mm, and the pitch of the connecting rods can be 20 mm.
As a preferred embodiment, two L-shaped columns are oppositely arranged, namely a short-arm L-shaped column and a long-arm L-shaped column. As shown in fig. 1.
Further, the vertical columns of the external corner columns 2 are equal in height to the L-shaped columns.
Further, the U-shaped upright 1 is provided with a connecting hole for the bolt 4 to fix the U-shaped upright on the wall.
Further, a steel keel reinforcing structure 6 is also included for mounting on the top and/or bottom of the piping bracket. The light steel keel of 1.5mm 20X 30mmU shape can be adopted for reinforcement (the plastic-covered tube is recommended for kitchen and bath for sound insulation and buffering heavy collision)
On the other hand, a building pipeline's envelope tubular construction is provided, including foretell building pipeline's envelope pipe support, wherein, two U type stands 1 are used for connecting respectively on the wall, and the usable light gauge steel of steel joist reinforced structure 6 or dry frame are consolidated U type stand according to actual use environment, and external corner stand 2 passes through the connecting rod and is connected with two U type stands 2 respectively, has clamped soundproof cotton 4 and ceramic tile 3 between U type groove and draw-in groove, and soundproof cotton 4 and ceramic tile 3's connected mode is for bonding.
Furthermore, gaps of the ceramic tiles 3 are subjected to pointing by pointing agents 8.
Further, the soundproof cotton 4 is xps plate.
In still another aspect, a building is provided, and the pipe wrapping structure of the building pipeline is installed.
Further, the U-shaped columns 1 are connected to the wall by expansion bolts.
The utility model discloses accessible adjustment customization xps thickness and adopt AB glue and marble glue to combine to consolidate, the colour chooses for use to be close to the look with the ceramic tile or spouts the look and handle.
The utility model discloses a package pipe support is laid bricks to the wet operation of tradition, plaster, the package pipe has carried out the technology innovation, the wet operation way of tradition has been abandoned, dry-type assembled equipment way has been changed into, through doing the operation method, the temperature influence has been overcome, the access hole setting has been cancelled, the package pipe area is little, construction speed is fast, it is effectual to give sound insulation, the maintenance is simple and easy, xps board, the marble is glued, the use that AB is glued, the collision buffering has been strengthened, very big reinforcing the anti impact of brick, this technical application can be according to high free customization, the effectual workman's energy efficiency ratio that has improved, the circulation speed of the wet operation of smart dress in batches has been promoted.
The above description is only for the preferred embodiment of the present invention, and not intended to limit the present invention in any way, and those skilled in the art can make various modifications, equivalent changes and modifications using the above-described technical content, all of which fall within the scope of the present invention.

Claims (10)

1. The utility model provides a building pipeline's package pipe holder, its characterized in that, includes U type stand, external corner stand and a plurality of connecting rod, the connecting rod is used for connecting between U type stand and external corner stand, U type stand is equipped with fore-and-aft U type groove, U type stand is used for fixing on the wall, the external corner stand is including erecting the stand and connecting two L type stands of erectting the post both sides, and two L type stands are relative or parallel arrangement form the draw-in groove, solid ceramic tile and/or soundproof cotton of U type groove and draw-in groove cooperation card.
2. The tube-wrapping bracket for construction pipes according to claim 1, wherein the two L-shaped columns are oppositely arranged and respectively comprise a short-arm L-shaped column and a long-arm L-shaped column.
3. The pipe-wrapping bracket for building pipelines according to claim 1, wherein the vertical columns of the external corner columns and the L-shaped columns are equal in height.
4. The pipe wrapping bracket for building pipelines according to any one of claims 1 to 3, wherein the U-shaped upright is provided with a connecting hole for a bolt to pass through to fix the U-shaped upright on a wall.
5. A tube-wrapping bracket for a construction pipe according to any one of claims 1 to 3 further comprising steel keel reinforcing structures for mounting at the top and bottom of the tube-wrapping bracket.
6. A pipe wrapping structure of a building pipeline is characterized by comprising the pipe wrapping support of the building pipeline as claimed in any one of claims 1 to 5, wherein two U-shaped stand columns are used for being connected to a wall respectively, the external corner stand columns are connected with the two U-shaped stand columns respectively through connecting rods, soundproof cotton and ceramic tiles are clamped between the U-shaped grooves and the clamping grooves, and the soundproof cotton and the ceramic tiles are connected in a bonding mode.
7. The pipe wrapping structure for building pipelines according to claim 6, wherein gaps between the tiles are caulked by glue and a caulking agent.
8. The pipe wrapping structure for building ducts according to claim 6 or 7, wherein the soundproof cotton is xps plate.
9. A building incorporating the pipe-wrapping structure of the building pipe according to any one of claims 7 to 8.
10. The building of claim 9 wherein the U-shaped studs are connected to the wall by expansion bolts.
CN202120024089.0U 2021-01-06 2021-01-06 Building pipeline's package pipe support reaches package tubular construction and building including it Expired - Fee Related CN214364583U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202120024089.0U CN214364583U (en) 2021-01-06 2021-01-06 Building pipeline's package pipe support reaches package tubular construction and building including it

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202120024089.0U CN214364583U (en) 2021-01-06 2021-01-06 Building pipeline's package pipe support reaches package tubular construction and building including it

Publications (1)

Publication Number Publication Date
CN214364583U true CN214364583U (en) 2021-10-08

Family

ID=77953289

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202120024089.0U Expired - Fee Related CN214364583U (en) 2021-01-06 2021-01-06 Building pipeline's package pipe support reaches package tubular construction and building including it

Country Status (1)

Country Link
CN (1) CN214364583U (en)

Similar Documents

Publication Publication Date Title
CN109083308B (en) Anti-seismic prefabricated assembly type wall and construction method thereof
CN103924710A (en) Steel plate welding node structure of low-layer assembly type composite wall house
CN207017445U (en) A kind of connecting structure of girder steel and retaining wall
CN110258878B (en) Hidden beam assembled disassembly-free heat preservation floor structure
CN204059760U (en) A kind of square steel post post core self-compacting concrete pouring construction structure
CN105401671A (en) Structured injection wall and construction process thereof
CN201011009Y (en) Cast-in-situ light compound wall
CN106088400A (en) A kind of modular assembly formula light gauge cold-formed steel shape combined wall
CN108130950A (en) A kind of component component of assembled arthitecutral structure and include its building
CN214364583U (en) Building pipeline's package pipe support reaches package tubular construction and building including it
CN206636041U (en) A kind of building block with inner supporting structure
CN215406639U (en) Prefabricated steel plate structure of post-cast strip pretreatment for advance construction of top plate backfill
CN201155162Y (en) Granite, terrazzo emulated heat insulation composite board
CN101408071A (en) On-site injecting method for energy-saving rebuilding old building exterior wall face into heat-insulating layer
CN212866588U (en) Contain assembled decoration heat preservation integration wallboard of skeleton
CN204920196U (en) Grout wallboard formwork
CN110130556B (en) Waterproof board frame and one-floor board structure and production method thereof
CN204040246U (en) Two plate holder layer insulated wall
CN203270854U (en) Inflatable skeleton filler wall sprayed and plastered on spot
CN206693491U (en) A kind of hollow heat-insulation building block with reinforcing bar locating framework structure
CN220555861U (en) Sandwich structure
KR101171613B1 (en) Construction work method for Wall structure of korean style house
CN207110132U (en) The novel crossed cast-in-place composite wall of support
CN201047126Y (en) Prefabricated building module component
CN206571244U (en) A kind of fabricated wall

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20211008