Nothing Special   »   [go: up one dir, main page]

CN202055821U - Two-arm top slope anchor rod and anchor rope construction drill wagon with movable lifting platform - Google Patents

Two-arm top slope anchor rod and anchor rope construction drill wagon with movable lifting platform Download PDF

Info

Publication number
CN202055821U
CN202055821U CN2011201291769U CN201120129176U CN202055821U CN 202055821 U CN202055821 U CN 202055821U CN 2011201291769 U CN2011201291769 U CN 2011201291769U CN 201120129176 U CN201120129176 U CN 201120129176U CN 202055821 U CN202055821 U CN 202055821U
Authority
CN
China
Prior art keywords
platform
lift platform
anchor
pedal
oil cylinder
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN2011201291769U
Other languages
Chinese (zh)
Inventor
马晓山
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN2011201291769U priority Critical patent/CN202055821U/en
Application granted granted Critical
Publication of CN202055821U publication Critical patent/CN202055821U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Earth Drilling (AREA)

Abstract

The utility model relates to a two-arm top slope anchor rod and anchor rope construction drill wagon with a movable lifting platform, which comprises a crawler belt traveling part, a machine body platform, a lifting platform, a platform lifting device, a drilling arm part, a hydraulic drilling machine part, a temporary supporting device, a hydraulic operating system, a pump station part and a main motor. The two-arm top slope anchor rod and anchor rope construction drill wagon is mainly characterized in that the lifting platform is also provided with two levels of pedals which are respectively a primary level of rotary pedal and a secondary level of turnover pedal; the temporary supporting device comprises a vertical column, an angle adjusting oil cylinder, a cross rod, a flexible oil cylinder, a flexible beam and a support and protection part; and the lifting platform adopts a structure of three lifting oil cylinders, a thee-point-support structure, an integral four-connecting-rod top beam structure, a parallel-movement structure, a vertical-lifting structure and the like. The two-arm top slope anchor rod and anchor rope construction drill wagon can be used for constructing top anchor rods and anchor ropes and slope anchor rods and anchor ropes, simultaneously, has the functions of constructing shot holes, gas discharge holes, water probing and discharge drilling holes and the like, has the functions of better temporary support and protection capability, ultrahigh laneway support and protection, and the like, and adopts the full-hydraulic system for transmission, thus having good anti-explosion property and safety.

Description

A kind of removable lift platform two-arm hanging wall anchor rod and anchor cable construction drill carriage
Technical field
The utility model belongs to heading equipment under the coal mine, and particularly a kind of large, medium and small moulded coal ore deposit that is applicable to is to connect to adopt, connect pick, the needed removable lift platform two-arm hanging wall anchor rod and anchor cable construction drill carriage in the comprehensive pick various tunnels of construction.
Background technology
At present, the main mode of all kinds of coal mine roadway drivings is adopted, is connected pick, combines pick for connecting, support pattern is anchor pole, anchor cable, joist, anchor net combination supporting, all adopt monomer rig or crawler-type lifting top and slope bolt and anchor construction drill for the top anchor shaft anchor cable construction, as China Patent No. be: 200720102731.2 disclosed crawler-type lifting top and slope bolt and anchor construction drills have two drilling apparatus, an advance support, crawler type walking mechanism, advance support; Walking mechanism is by fluid motor-driven, rigging up platform on the frame of walking mechanism; The front portion of the below track unit of drilling machine platform is equipped with one and is pushed away the coal shovel plate; The advance support that a hydraulic oil cylinder type is housed foremost of platform, a side of advance support is equipped with a hydraulic drill rig that is used for the construction of anchor bar anchor cable; The top-assisting anchor rod and anchor cable construction hydraulic drill rig adopts two columns, and the slideway of move left and right part is contained on two columns, and hydraulic drill rig left or right rotation 30 degree; The hydraulic drill rig that is used for the construction of assisting anchor rod and anchor cable is loaded on drilling machine platform middle part one side, or the side of taking back, or the side that takes over, hydraulic drill rig revolves to the left or to the right and turn 90 degrees, the slideway of arranging before and after on drilling machine platform, being provided with, the column of hydraulic drill rig is seated on the slideway, and is moved forward and backward by the oil cylinder promotion rig integral body that is contained on the drilling machine platform.
Adopt monomer rig (jackhammer) for assisting anchor rod and anchor cable construction, there is following problem in this construction anchor shaft anchor cable construction method:
1, the tunnelling section is little: excavated section is generally at 15M 2About, when head-room surpasses 2 meters, must just can carry out top-assisting anchor rod and anchor cable construction by scaffolding.
2, on-mechanical equalization, the company of employing adopts, connects the mine top anchor shaft anchor cable construction of tunneling process and realized mechanization substantially, adopts the mine top anchor shaft anchor cable construction of combining tunneling process, if still be monomer rig manual work, the thrust of perforating derives from people's arm and arm, and worker's labour intensity is big.Because assisting anchor rod and anchor cable construction mainly relies on manpower, the construction quality of assisting anchor rod and anchor cable can not fundamentally be guaranteed.
3, speed of application is slow, and building and remove scaffold when the construction section surpasses 2 meters needs a large amount of time.
4, efficient is low: because perforating quantity is many, the constructor is also many, causes operating efficiency low.
5, safety factor is low: the constructor is staggered operation in the high-altitude, and the job safety environment is poor.
Adopt above-mentioned existing crawler-type lifting top and slope bolt and anchor construction drill for top-assisting anchor rod and anchor cable construction, there is following problem in this construction anchor shaft anchor cable construction method:
1, two complete uses of crawler-type lifting top and slope bolt and anchor rig of palpus, what promptly use is to be loaded on the hydraulic drill rig that the left and right side of drilling machine platform is used for the construction of assisting anchor rod and anchor cable, each crawler-type lifting top and slope bolt and anchor rig of different size, the hydraulic drill rig direction of rotation in these two equipment is different.Construct in the both sides that are emitted on the tunnel before and after two equipment need when tunnelling successively.
2, advance and retreat the machine time long, the back work amount is big.Owing to during tunneling construction, need two equipment to drive or withdraw from driving face successively into, add dragging of cable, the time is long, and the back work amount is big.
3, to the complex geological condition bad adaptability.Meet complex geological conditions such as tomography, high gas district, high water aquifer, this drill carriage can not be finished the construction of the pre-gaging hole of gas, drawing-off gas hole, geology detecting hole, vibrations borehole.
4, the construction of anchor bar anchor cable does not reach zero lag, and is unfavorable to the control of lane group.
5, the workload of top-assisting anchor rod and anchor cable construction does not match, and the workload of crown drill is big, and the workload that group bores is little, influences support time, causes personnel's work holdup.
6, constructor's staggered operation in the high-altitude, the job safety environment is relatively poor.
7, personnel selection is many, and two equipment need 8 of manninves.
Summary of the invention
The purpose of this utility model is exactly to solve the problem that above-mentioned coal mine underground tunneling roadway top-assisting anchor rod and anchor cable construction exists, a kind of constructor's of reducing labour intensity is provided, reduce the constructor, improve driving speed and operating efficiency, create the safety work environment, and have mobile voluntarily, but operating platform integral elevating, the top anchor shaft anchor cable of can constructing, the assisting anchor rod and anchor cable of also can constructing, also possesses the construction borehole simultaneously, the drawing-off gas hole, the spy functions such as boring that discharge water, possesses better temporary lining ability, functions such as superelevation roadway support, adopt the full hydraulic system transmission, the removable lift platform two-arm hanging wall anchor rod and anchor cable construction drill carriage that explosion-proof performance and security performance are good.
The technical solution of the utility model is to achieve these goals:
A kind of removable lift platform two-arm hanging wall anchor rod and anchor cable construction drill carriage comprises track unit 1, body platform 2, lift platform 3, platform lifting device 4, drill boom part 5, hydraulic drill rig part 6, temporary support device 7, hydraulic operating system 8, pump station part 9 and main motor 10; Described body platform is loaded on the track unit, at body platform mounting platform lifting gear, connects lift platform on the platform lifting device; Described drill boom partly is loaded on the rear side on the top of lift platform, and the and arranged on left and right sides of lift platform; Two groups of drill boom parts and hydraulic drill rig part promptly are housed on lift platform altogether; Described hydraulic drill rig partly is loaded on drill boom part front end; Described temporary lining is fixedly mounted on the lift platform front end; Described hydraulic operating system, pump station part and main motor are loaded on the back on the body platform; It is characterized in that:
On described lift platform 3, also have the two-stage pedal, be respectively one-level rotation pedal 31 and secondary overturning pedal 32; Described one-level rotation pedal is positioned at the front end both sides of lift platform, is same plane with lift platform, is fixed on the lift platform by rotary oil cylinder 33; Described secondary overturning pedal is a kind of overturn structure pedal that is provided with at one-level rotation pedal, the secondary pedal is positioned at one-level rotation pedal top, the outer ledge of outer ledge and one-level pedal is hinged, and the secondary overturning pedal can overturn 180 ° at one-level rotation pedal;
Described temporary support device comprises column 71, angular adjustment oil cylinder 72, crossbeam 73, telescopic oil cylinder 74, extensible canopy 75 and supporting part 76; Described column by bearing pin be fixed on lift platform before free bearing be connected, the angular adjustment oil cylinder is contained between column lower end and the lift platform, and be used to regulate the angle of the column of temporary lining, crossbeam is connected by bearing pin with column, in crossbeam, adorn two telescopic oil cylinders, and respectively adorn an extensible canopy on the both sides of crossbeam, telescopic oil cylinder difference crossbeam and extensible canopy are hinged, the hinged supporting part that is used for roof supporting in end that extensible canopy is outer.
Described platform lifting device comprises lift platform oil cylinder 41 and quadric chain composition; Described lift platform oil cylinder has three, lift platform oil cylinder be loaded on before the lift platform with body platform 2 on, in addition two lift platform oil cylinders be loaded on behind the lift platform with the body platform on.Quadric chain is made up of with mid link 45 connecting rod support 42, last connecting rod 43, lower link 44; The connecting rod support is fixed on above the body platform, and connecting rod and lower link are positioned at the both sides of mid link on two groups, and lower link and last connecting rod and connecting rod support are hinged, last connecting rod and lift platform following hinged, and the middle part of mid link and last connecting rod and connecting rod support are hinged.
A kind of removable lift platform two-arm hanging wall anchor rod and anchor cable construction drill carriage of the utility model is compared with existing crawler-type lifting top and slope bolt and anchor construction drill technology, has outstanding substantive distinguishing features with remarkable beneficial effect to be:
1, the lift platform of this drill carriage adopt three hoist cylinders and supported at three point, four connecting rod integral back timbers, parallelly move, structure and operating principle such as vertical lift, this car overall performance is more stable, it is big, wider to adapt to head-room, more production safety.
2, two 180 ° of oscillating oil cylinders controls are adopted in the rotation of the hydraulic drill rig of this drill carriage, can realize the 180 ° of rotations in all around, use the swing of swing pinion control rig than existing crawler-type lifting top and slope bolt and anchor construction drill, safer, flexible and reliable.
3, this drill carriage adopts unit two arm support process, in a tunnel, only need to be equipped with an equipment, can reduce by an equipment than existing crawler-type lifting top and slope bolt and anchor construction drill, reduce advance and retreat machine time in the supporting process and the maintenance workload in the maintenance process, reduced the dynamo-electric cost of overhaul.
4, the personnel of determining a post are 2 people in this drill carriage supporting process, have reduced 3/4ths than the personnel that determine a post 8 people of existing crawler-type lifting top and slope bolt and anchor construction drill, reach and increase efficiency by downsizing payrolls, the purpose of high-yield and high-efficiency.
5, the engineering time of top, assisting anchor rod and anchor cable can reach zero lag, and these characteristics are very favorable to the soft seam driving, can control wall caving effectively, prevent the generation of roof accident.
6, be highly suitable for combining the pick single entry driving.This drill carriage can be parked in any side in tunnel when single entry driving, and principle is not influence the fully-mechanized digging machine coal cutting to get final product; After the fully-mechanized digging machine coal cutting, this drill carriage can retreat under the permanent support the supporting of empty jacking row.
7, the employing of this drill carriage can change and existing the company adopts, connects two lanes of pick or three lane driving technologies, to operation, changes the machine operation of alternately advancing and retreat by the place of original Lian Caiji or high-power development machine and roof-bolter into, has reduced influence time, has improved driving speed.
8, safety factor height.Because this drill carriage has temporary support device, can be before the anchor shaft anchor cable supporting supporting roof effectively, both made at Gao Maoqu and also can control top board.
In a word, this drill carriage reduces constructor's labour intensity, reduce the constructor, improve driving speed and operating efficiency, create the safety work environment, but and have voluntarily move, operating platform integral elevating, the top anchor shaft anchor cable of can constructing, the assisting anchor rod and anchor cable of also can constructing also possesses construction borehole, drawing-off gas hole simultaneously, visits function such as the boring that discharges water, and possesses functions such as better temporary lining ability, superelevation roadway support, adopt the full hydraulic system transmission, explosion-proof performance and security performance are good.
Description of drawings
Fig. 1 is a front view of the present utility model.
Fig. 2 is a vertical view of the present utility model.
Fig. 3 is the structural representation of drill boom part of the present utility model, hydraulic drill rig part.
Fig. 4 is drill boom part of the present utility model, hydraulic drill rig part and temporary lining work schematic diagram.
Fig. 5 is the structural representation of lift platform of the present utility model and platform lifting device.
Fig. 6 is the structural representation of lift platform of the present utility model and rotation pedal
Fig. 7 is the front view of hydraulic drill rig part of the present utility model.
Fig. 8 is the vertical view of hydraulic drill rig part of the present utility model.
Fig. 9 is the front view of temporary support device part.
Figure 10 is the vertical view of temporary support device part.
Figure 11 is the partial schematic diagram of drill boom part.
The specific embodiment
Be elaborated below in conjunction with accompanying drawing:
As Fig. 1, Fig. 2 and shown in Figure 3, a kind of removable lift platform two-arm hanging wall anchor rod and anchor cable construction drill carriage.It mainly comprises track unit 1, body platform 2, lift platform 3, platform lifting device 4, drill boom part 5, hydraulic drill rig part 6, temporary support device 7, hydraulic operating system 8, pump station part 9 and main motor 10; Described body platform is loaded on the track unit, at body platform mounting platform lifting gear, connects lift platform on the platform lifting device; Described drill boom partly is loaded on the rear side on the top of lift platform, and the and arranged on left and right sides of lift platform; Two groups of drill boom parts and hydraulic drill rig part promptly are housed on lift platform altogether.Described hydraulic drill rig partly is loaded on drill boom part front end; Temporary lining is fixedly mounted on the lift platform front end; Described hydraulic operating system, pump station part and main motor are loaded on the back on the body platform.
The structure design of parts such as described hydraulic operating system, track unit, hydraulic drill rig, drill boom part, temporary lining all is to use prior art, as: track unit is the track unit that adopts engineering machinery, as track frame, undercarriage bea and Hydraulic Power Transmission System etc.
A kind of removable lift platform two-arm hanging wall anchor rod and anchor cable construction drill carriage of the present invention is that the complete machine structure and the layout of this drill carriage are improved, and reconfigures with integrated.The top of track unit 1 is the body platform 2 of this drill carriage, wherein:
The drill boom part: as Fig. 4 and shown in Figure 11, drill boom partly comprises connecting rod 51 on the drill boom, drill boom lower link 52, drill boom hoist cylinder 53, drill boom oscillating oil cylinder 54, drill boom rotation seat 55 and drill boom holder 56; Described drill boom rotation seat is loaded on the drill boom holder by axle etc., and drill boom oscillating oil cylinder 54 is loaded on drill boom rotation seat 55 and drill boom holder 56, and the drill boom hoist cylinder is loaded on the drill boom on connecting rod 51 or drill boom lower link 52 and the drill boom rotation seat 55.
Be fitted with expansion link 57 on the described drill boom in the connecting rod 51, and load onto telescopic oil cylinder 58 in the connecting rod on drill boom, connecting rod is connected with last expansion link on telescopic oil cylinder and the drill boom; In drill boom lower link 52, also be fitted with down expansion link 59, in the drill boom lower link, load telescopic oil cylinder 510, following telescopic oil cylinder 510 at the drill boom lower link below following expansion link and be connected.
Lift platform: as shown in Figure 5, on lift platform, also have the two-stage pedal, be respectively one-level rotation pedal 31 and secondary overturning pedal 32.
Described one-level rotation pedal is positioned at the front end both sides of lift platform, is same plane with lift platform, is fixed on the lift platform by rotary oil cylinder 33; When this drill carriage carried out support work, one-level rotation pedal to platform both sides inner rotary, and was 90 ° with the lift platform rotation under the promotion of rotary oil cylinder; When this drill carriage moved, one-level rotation pedal was regained to the rotation of platform front end under the pulling of rotary oil cylinder, and is same plane with lift platform.
Described secondary overturning pedal is a kind of overturn structure pedal that is provided with at one-level rotation pedal, the secondary pedal is positioned at one-level rotation pedal top, the outer ledge of outer ledge and one-level pedal is hinged, and the secondary overturning pedal can overturn 180 ° at one-level rotation pedal; When this drill carriage carried out support work, the secondary overturning pedal can be routed up from lift platform one-level rotation pedal; When this drill carriage moved, the secondary expansion plate can plough under on the lift platform one-level rotation pedal.
Platform lifting device: as shown in Figure 5 and Figure 6, platform lifting device is fixed on the body platform, and its platform lifting device is connected with lift platform.Platform lifting device comprises lift platform oil cylinder 41 and quadric chain composition; Described lift platform oil cylinder has three, lift platform oil cylinder be loaded on before the lift platform with body platform 2 on, in addition two lift platform oil cylinders be loaded on behind the lift platform with the body platform on.Quadric chain is made up of with mid link 45 connecting rod support 42, last connecting rod 43, lower link 44; The connecting rod support is fixed on above the body platform, and connecting rod and lower link are positioned at the both sides of mid link on two groups, and lower link and last connecting rod and connecting rod support are hinged, last connecting rod and lift platform following hinged, and the middle part of mid link and last connecting rod and connecting rod support are hinged.Described lift platform has three lift platforms, is supported at three point, and its effect is to make the lift platform lifting, and this platform lifting device structure can make the more balance and stability of lift platform.
The hydraulic drill rig part: as shown in Figure 7 and Figure 8, hydraulic drill rig partly is positioned at the front portion of drill boom 4; The hydraulic drill rig part is made up of hydraulic drill rig 61 and revolution support; Described revolution support comprises that 62,180 ° of left rotation and right rotation oil cylinders of support 63 and 64,180 ° of tops of the sliding connection plate rotary oil cylinder 65 of left rotation and right rotation oil cylinder and junction plate 66, the rig of top rotary oil cylinder stretch out oil cylinder 67; Plug-in mounting left rotation and right rotation oil cylinder sliding connection plate in the described support, between support and the sliding connection plate rig is installed and stretches out oil cylinder, described left rotation and right rotation oil cylinder is installed on the cylinder body sliding connection plate, the piston of left rotation and right rotation oil cylinder is connected on the junction plate of top rotary oil cylinder, the cylinder body of top rotary oil cylinder is fixed on the rotary oil cylinder junction plate of top, and the piston of top rotary oil cylinder is connected with hydraulic drill rig; The left rotation and right rotation oil cylinder is vertical mutually with the axis of top rotary oil cylinder.Hydraulic drill rig part can make drill bit realize forwards moving, left or right-hand, and the top rotate.
Hydraulic drill rig 61 can be realized forwards, rotation left or right-hand, the top, hydraulic drill rig 61 left or the rotation of right-hand, top finish by 180 ° of left rotation and right rotation oil cylinders 63 and 180 ° of top rotary oil cylinders 65, hydraulic drill rig 61 stretching out forwards stretched out oil cylinder 67 by rig and finished.
Temporary support device: as Fig. 9 and shown in Figure 10, described temporary support device comprises column 71, angular adjustment oil cylinder 72, crossbeam 73, telescopic oil cylinder 74, extensible canopy 75 and supporting part 76; Described column by bearing pin be fixed on lift platform before free bearing be connected, the angular adjustment oil cylinder is contained between column lower end and the lift platform, and be used to regulate the angle of the column of temporary lining, crossbeam is connected by bearing pin with column, in crossbeam, adorn two telescopic oil cylinders and respectively adorn an extensible canopy on the both sides of crossbeam, promptly adorn an extensible canopy on one side, telescopic oil cylinder difference crossbeam and extensible canopy are hinged, the hinged supporting part that is used for roof supporting in end that extensible canopy is outer.
The present invention to the main improvement part of existing slope anchor shaft anchor cable construction drilling machine is:
(1), structure and principles such as the lift platform of this drill carriage adopts three hoist cylinders and supported at three point, four connecting rod integral back timbers, parallelly moves, vertical lift, more balance and stability realizes safety, efficient construction.
(2), the hydraulic drill rig of this drill carriage can be finished the construction in the place ahead, right and left, three orientation, top.
(3), on lift platform, be set to a level rotation pedal 31 and a secondary overturning pedal 32, be more convenient for operating rig and supporting construction.
(4), the temporary lining of the angle oil cylinder 72 of the supporting angle that is used to regulate temporary lining is housed.Increased effective temporary lining area, and shunk freely with easy to use.
A kind of removable lift platform two-arm hanging wall anchor rod and anchor cable construction drill carriage of the utility model, adopt, connect pick for connecting, combine the used support apparatus in pick tunnel, but the operating platform integral elevating, and two drill booms can be constructed simultaneously, shorten the activity duration greatly, improved supporting efficient.Particularly at the mine of high gas and complex geological condition, it can meet head on to carry out top pressing type temporary lining to work plane, can carry out the construction in the pre-gaging hole of gas, drawing-off gas hole, geology detecting hole simultaneously.

Claims (2)

1. a removable lift platform two-arm hanging wall anchor rod and anchor cable construction drill carriage comprises track unit (1), body platform (2), lift platform (3), platform lifting device (4), drill boom part (5), hydraulic drill rig part (6), temporary support device (7), hydraulic operating system (8), pump station part (9) and main motor (10); Described body platform is loaded on the track unit, at body platform mounting platform lifting gear, connects lift platform on the platform lifting device; Described drill boom partly is loaded on the rear side on the top of lift platform, and the and arranged on left and right sides of lift platform; Two groups of drill boom parts and hydraulic drill rig part promptly are housed on lift platform altogether; Described hydraulic drill rig partly is loaded on drill boom part front end; Described temporary lining is fixedly mounted on the lift platform front end; Described hydraulic operating system, pump station part and main motor are loaded on the back on the body platform; It is characterized in that:
Go up two-stage pedal in addition at described lift platform (3), be respectively one-level rotation pedal (31) and secondary overturning pedal (32); Described one-level rotation pedal is positioned at the front end both sides of lift platform, is same plane with lift platform, is fixed on the lift platform by rotary oil cylinder (33); Described secondary overturning pedal is a kind of overturn structure pedal that is provided with at one-level rotation pedal, the secondary pedal is positioned at one-level rotation pedal top, the outer ledge of outer ledge and one-level pedal is hinged, and the secondary overturning pedal can overturn 180 ° at one-level rotation pedal;
Described temporary support device comprises column (71), angular adjustment oil cylinder (72), crossbeam (73), telescopic oil cylinder (74), extensible canopy (75) and supporting part (76); Described column by bearing pin be fixed on lift platform before free bearing be connected, the angular adjustment oil cylinder is contained between column lower end and the lift platform, and be used to regulate the angle of the column of temporary lining, crossbeam is connected by bearing pin with column, in crossbeam, adorn two telescopic oil cylinders, and respectively adorn an extensible canopy on the both sides of crossbeam, telescopic oil cylinder difference crossbeam and extensible canopy are hinged, the hinged supporting part that is used for roof supporting in end that extensible canopy is outer.
2. a kind of removable lift platform two-arm hanging wall anchor rod and anchor cable construction drill carriage according to claim 1 is characterized in that: described platform lifting device comprises lift platform oil cylinder (41) and quadric chain composition; Described lift platform oil cylinder has three, lift platform oil cylinder be loaded on before the lift platform with body platform (2) on, in addition two lift platform oil cylinders be loaded on behind the lift platform with the body platform on; Quadric chain is made up of with mid link (45) connecting rod support (42), last connecting rod (43), lower link (44); The connecting rod support is fixed on above the body platform, and connecting rod and lower link are positioned at the both sides of mid link on two groups, and lower link and last connecting rod and connecting rod support are hinged, last connecting rod and lift platform following hinged, and the middle part of mid link and last connecting rod and connecting rod support are hinged.
CN2011201291769U 2011-04-25 2011-04-25 Two-arm top slope anchor rod and anchor rope construction drill wagon with movable lifting platform Expired - Lifetime CN202055821U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011201291769U CN202055821U (en) 2011-04-25 2011-04-25 Two-arm top slope anchor rod and anchor rope construction drill wagon with movable lifting platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011201291769U CN202055821U (en) 2011-04-25 2011-04-25 Two-arm top slope anchor rod and anchor rope construction drill wagon with movable lifting platform

Publications (1)

Publication Number Publication Date
CN202055821U true CN202055821U (en) 2011-11-30

Family

ID=45015796

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011201291769U Expired - Lifetime CN202055821U (en) 2011-04-25 2011-04-25 Two-arm top slope anchor rod and anchor rope construction drill wagon with movable lifting platform

Country Status (1)

Country Link
CN (1) CN202055821U (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102278110A (en) * 2011-04-25 2011-12-14 马晓山 Movable two-arm of lifting platform hanging wall anchor rod and anchor cable construction drill carriage
CN102900362A (en) * 2012-10-16 2013-01-30 廊坊景隆重工机械有限公司 Narrow-machine-body full-hydraulic bolt and anchor cable drill carriage for coal mine tunnel
CN103470184A (en) * 2013-09-27 2013-12-25 山西天巨重工机械有限公司 Double-arm hydraulic tunneling jumbo
CN104775837A (en) * 2015-04-28 2015-07-15 蒲长晏 Railway tunnel anchor jumb drill
CN107489440A (en) * 2017-08-11 2017-12-19 淮北矿业(集团)有限责任公司 Tunnel low-angle lift canopy and hacking shed tunnel low-angle lift canopy method
CN110410007A (en) * 2019-08-21 2019-11-05 山西天巨重工机械有限公司 Turn round telescopic big cross section drill boom device

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102278110A (en) * 2011-04-25 2011-12-14 马晓山 Movable two-arm of lifting platform hanging wall anchor rod and anchor cable construction drill carriage
CN102900362A (en) * 2012-10-16 2013-01-30 廊坊景隆重工机械有限公司 Narrow-machine-body full-hydraulic bolt and anchor cable drill carriage for coal mine tunnel
CN103470184A (en) * 2013-09-27 2013-12-25 山西天巨重工机械有限公司 Double-arm hydraulic tunneling jumbo
CN103470184B (en) * 2013-09-27 2015-06-10 山西天巨重工机械有限公司 Double-arm hydraulic tunneling jumbo
CN104775837A (en) * 2015-04-28 2015-07-15 蒲长晏 Railway tunnel anchor jumb drill
CN107489440A (en) * 2017-08-11 2017-12-19 淮北矿业(集团)有限责任公司 Tunnel low-angle lift canopy and hacking shed tunnel low-angle lift canopy method
CN107489440B (en) * 2017-08-11 2023-08-15 淮北矿业股份有限公司 Small-angle shed lifting method for roadway and small-angle shed lifting method for shed roadway
CN110410007A (en) * 2019-08-21 2019-11-05 山西天巨重工机械有限公司 Turn round telescopic big cross section drill boom device

Similar Documents

Publication Publication Date Title
CN101832102B (en) Movable two-platform partitioned four-arm hanging wall anchor rod and anchor cable construction drill carriage
CN102278110A (en) Movable two-arm of lifting platform hanging wall anchor rod and anchor cable construction drill carriage
CN201106451Y (en) Track-mounted liftable top-side construction drilling machine for anchor bar and anchor wire
CN101832103B (en) Movable two-arm hanging wall anchor rod and anchor cable construction drill carriage
CN101858213B (en) Drilling, loading, transporting and anchoring integrated machine with dual platforms and four arms for coal roadway
CN100559013C (en) Tunneling, anchoring and drilling composite machine
CN201826837U (en) Movable double-platform partitioned four-arm drill carriage for construction of hangwall anchor rods and anchor cables
CN101169036B (en) Pedrail type lifting top slope anchor shaft anchor cable construction drilling machine and single-alley fast tunneling technique
CN202055821U (en) Two-arm top slope anchor rod and anchor rope construction drill wagon with movable lifting platform
CN204716251U (en) Circular orbit formula multifunctional rock drilling trolley
CN101403302B (en) Crawler-type liftable top-side anchor rod and anchor cable construction drilling machine and double-lane rapid tunneling process
CN104895578A (en) Circular-rail multifunctional drill jumbo system
CN104695871A (en) Drilling boom device of two-boom hydraulic rock bolt drilling carriage
CN104196443A (en) Narrow-fuselage six-arm fully hydraulic anchor rod anchor cable drill carriage
CN203796297U (en) Temporary supporting device of driving working face
CN101812974A (en) Lifting platform of construction vehicle
CN212359776U (en) Multifunctional hard rock tunneling integrated machine
CN112360340A (en) Automatic anchor rod drill carriage
CN101781972B (en) Crawler-type lifting top and slope bolt and anchor construction drill
CN101845952B (en) Movable three-arm top-assisting anchor rod and anchor cable construction drill carriage
CN201635656U (en) Side-propping anchor rod-anchor cable construction drill carriage with three movable arms
CN213743235U (en) Small single-arm drill carriage for coal mine
CN103628903B (en) Roadway full-fracture-surface anchoring-rod and anchoring-rope integrated parallel installation method and device
CN201696041U (en) Double-platform four-arm drilling, loading, conveying and anchoring integrated machine for coal roadways
CN201635655U (en) Side-propping anchor rod-anchor cable construction drill carriage with two movable arms

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20111130