CN208734034U CN201821116265.8U CN201821116265U CN208734034U CN 208734034 U CN208734034 U CN 208734034U CN 201821116265 U CN201821116265 U CN 201821116265U CN 208734034 U CN208734034 U CN 208734034U
Authority
CN
China
Prior art keywords
plate
supporting leg
construction bracket
construction
station
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201821116265.8U
Other languages
Chinese (zh)
Inventor
瑁存椽
裴洪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Shangdu Decoration Engineering Co Ltd
Original Assignee
Zhejiang Shangdu Decoration Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Shangdu Decoration Engineering Co Ltd filed Critical Zhejiang Shangdu Decoration Engineering Co Ltd
Priority to CN201821116265.8U priority Critical patent/CN208734034U/en
Application granted granted Critical
Publication of CN208734034U publication Critical patent/CN208734034U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Ladders (AREA)

Abstract

The utility model discloses a kind of Multifunctional decoration construction brackets, are related to fitting-up field, its key points of the technical solution are that including the multiple supporting legs being supported and the station plate stood on supporting leg one end for construction personnel is arranged in;The edge of station plate is arranged in the supporting leg;The lifting assembly that height adjustment is carried out convenient for construction bracket is additionally provided on the supporting leg.The utility model solve construction bracket deploy and construction personnel station when constructing on construction bracket, there are problems that the case where higher position construction personnel does not reach sometimes, by setting construction bracket to convenient for lifting, so that construction personnel is more convenient to carry out operation to eminence when carrying out finishing work.

Description

Multifunctional decoration construction bracket
Technical field
The utility model relates to fitting-up field, in particular to a kind of Multifunctional decoration construction bracket.
Background technique
Construction bracket, refer to construction site be worker operation and solving vertically and horizontally transport and the various brackets set up, build The generic term for building boundary refers to and is used in exterior wall, interior decoration or the higher place that can not directly construct of layer height on construction site.Mainly In order to which operation above and below construction personnel or perimeter security net are gone along with sb. to guard him and high-altitude installation component etc., popular saying is exactly to build a framework, foot hand Frame making material usually has: bamboo and wood, steel pipe or synthetic material etc..Some engineerings are also with scaffold when template uses, furthermore wide The departments such as industry, municipal administration, traffic road bridge, mine are accused also to be used extensively.
There is some deficiency in the existing construction bracket used in fitment process, be exactly construction bracket in use Deploy and construction personnel station when constructing on construction bracket, have what higher position construction personnel did not reached sometimes Situation, construction personnel also need replacing and rearrange construction bracket, make the Comparision of construction personnel cumbersome.
Utility model content
In view of the deficienciess of the prior art, the purpose of this utility model is to provide a kind of Multifunctional decoration construction branch Frame, by by construction bracket be set as convenient for lifting so that construction personnel when carrying out finishing work be more convenient to eminence into Row operation.
The above-mentioned purpose of the utility model has the technical scheme that
A kind of Multifunctional decoration construction bracket including the multiple supporting legs being supported and is arranged on supporting leg one end for applying The station plate that worker person stands;The edge of station plate is arranged in the supporting leg;Be additionally provided on the supporting leg convenient for construction bracket into The lifting assembly of row height adjustment;
The lifting assembly includes the lift span arranged along leg length direction being provided with supporting leg far from station plate one end, wears It is located at the elevating lever cooperated in lift span with lift span, is provided on elevating lever and is inserted into the equidistant cloth in lift span direction along elevating lever Multiple connecting holes for setting are provided on supporting leg and the mounting hole of lift span vertical connection and are threaded through in mounting hole and connecting hole Installation bolt for elevating lever and supporting leg to be fixed together.
By using above-mentioned technical proposal, before construction personnel constructs, first by the height of wanted operating area Range measures, length when then elevating lever being inserted into lift span, and elevating lever being cooperated with supporting leg and the data measured It corresponds to, construction bracket is allowed to deploy rear construction personnel convenient for operation.When elevating lever is inserted into lift span, construction personnel It is mounting hole is corresponding with the connecting hole on elevating lever together, wherein construction personnel selects and pacified according to the data measured Hole connecting hole the most corresponding is filled, then installation bolt is passed through into mounting hole and connecting hole and is tightened, so that supporting leg and elevating lever are solid Surely it links together.After being lengthened supporting leg, construction personnel arranges construction bracket.Construction personnel stands again to construct On the station plate of bracket, the work fitted up.By the way that lifting assembly is arranged on construction bracket, so that the height of construction bracket is just In adjusting, construction personnel is allowed to construct when carrying out operation convenient for the operating area to eminence, allows the construction work of construction personnel It is more easy to make.
The utility model is further arranged to: multiple ladder bars as ladder are provided on supporting leg;Ladder bars are connected to two On supporting leg, and it is located on two supporting legs of station plate one end.
By using above-mentioned technical proposal, allow construction personnel can be more square after arranging construction bracket after raising Just it arrives at a station on plate on.
The utility model is further arranged to: the both ends on plate of standing are additionally provided with the bar with station plate Relative vertical.
By using above-mentioned technical proposal so that construction personnel when constructing by the blocking of bar, be not easy slave station The both ends of plate are fallen down, and make construction personnel safer at work.
The utility model is further arranged to: the two sides for plate of standing, which are also vertically installed with, further stops construction personnel Baffle.
By using above-mentioned technical proposal so that construction personnel when constructing by the blocking of baffle, further mention High safety of the construction personnel in operation.
The utility model is further arranged to: plate of standing is set as doubling plate, and is provided with more between doubling plate and is used for Increase the mandril of intensity.
It is able to bear bigger power, will not applied so that the support strength of station plate is bigger by using above-mentioned technical proposal The case where being bent when worker person is constructed.
The utility model is further arranged to: the support being equipped between plate and supporting leg for increasing construction bracket intensity of standing Bar, one end of the support rod and station plate are hinged, and the other end and a ladder bars on supporting leg are hinged;Support rod with ladder bars and station It is as axis that support rod and station plate and ladder bars is hinged by the bolt being threaded through on support rod when plate is hinged;On the station plate There are two support rods for setting.
By using above-mentioned technical proposal, increase the intensity between station plate and supporting leg with two support rods, and passes through Support rod carrys out the layout angle of support leg and plate of standing, so that construction bracket is more secured when in use.
The utility model is further arranged to: the connection between supporting leg and station plate is rotation connection, and on each leg It is provided at least one traveling wheel, the position of traveling wheel is located at supporting leg on the direction of station plate center position.
By using above-mentioned technical proposal, when packing up construction bracket, construction personnel is by the hinged solution at support rod both ends It removes, when releasing, the work for completing to remove support rod is taken off by the bolt that support rod is connected on station plate and supporting leg, After removing support rod, the layout angle between supporting leg and station plate loses support, and construction personnel can carry out supporting leg curved Folding.When being bent to supporting leg, the direction of bending towards the middle position of station plate so that supporting leg after bending with station plate It is contacted, and the direction of the traveling wheel on supporting leg deviates from station plate after supporting leg is bent, and is placed on ground in construction bracket On face and when supporting leg is packed up, traveling wheel and ground face contact, the bar stood on plate is as pushing hands, so that construction bracket is integrally formed one A carriage type, is transported convenient for construction personnel, in addition, due to being provided with baffle on the plate of station, so that construction bracket formation is small Vehicle is when transporting object, blocking of the object by baffle, and transport is more convenient on the trolley that construction bracket is formed.Construction personnel exists When construction bracket is pushed as trolley, ground gives supporting leg one upward thrust, so that supporting leg is not easy to open up automatically when packing up It opens.By setting construction bracket to be folded into trolley shape, so that the purposes of construction bracket is wider.
The utility model is further arranged to: standing to be placed on the downside of plate contact and is used for station plate to standing what plate was raised Dumbwaiter.
By using above-mentioned technical proposal, after construction bracket deploys, dumbwaiter is placed on by construction personnel Stand plate downside and contacted with station plate, and the installation bolt installed on supporting leg is removed so that dumbwaiter to station plate into Row support, then construction personnel it is direct on arrive at a station on plate, construct, need increase station plate height when, construction personnel opens Dynamic dumbwaiter, allows dumbwaiter to raise the height for plate of standing, so that construction personnel is in the height of regulation station plate It is more convenient.
The utility model is further arranged to: the mounting plate for place tool is vertically installed on bar.
It is not needed by using above-mentioned technical proposal so that construction personnel is convenient for putting tool at work It places the tool above on the plate of station, makes the job security of construction personnel higher.
The utility model is further arranged to: mounting plate, which protrudes above, is provided with handle.
By using above-mentioned technical proposal, so that more convenient when being pushed to construction bracket.
In conclusion the utility model has the following beneficial effects:
1, by setting lifting assembly, construction bracket is enabled to be more convenient to be raised;
2, doubling plate is set as by the plate that will stand, so that station plate has better support effect;
3, by setting traveling wheel, so that the application range of construction bracket is wider.
Detailed description of the invention
Fig. 1 is the schematic diagram of construction bracket in embodiment 1;
Fig. 2 is the schematic diagram of lifting assembly in embodiment 1;
Fig. 3 is that construction bracket folds the schematic diagram packed up in trolley in embodiment 1;
Fig. 4 is the schematic diagram of construction bracket in embodiment 2;
Fig. 5 is the schematic diagram of construction bracket in embodiment 3.
In figure, 1, supporting leg;2, it stands plate;3, lifting assembly;31, lift span;32, elevating lever;33, connecting hole;34, it installs Hole;35, bolt is installed;4, ladder bars;5, bar;6, baffle;7, mandril;8, support rod;9, traveling wheel;10, dumbwaiter; 11, mounting plate;12, handle.
Specific embodiment
The utility model is described in further detail below in conjunction with attached drawing.
Embodiment 1: a kind of Multifunctional decoration construction bracket, as shown in Figure 1, include the multiple supporting legs 1 played a supporting role, The station plate 2 stood for construction personnel is connected on supporting leg 1.The edge of station plate 2 is arranged in supporting leg 1.It is additionally provided on supporting leg 1 The lifting assembly 3 of height adjustment is carried out convenient for construction bracket.
Specifically, after construction bracket deploys, in conjunction with Fig. 2, lifting assembly 3 includes being provided with supporting leg 1 far The lift span 31 along 1 length direction of supporting leg arrangement of 2 one end of plate leaving from station, the liter cooperated with lift span 31 is equipped in lift span 31 Bar 32 is dropped, multiple connecting holes 33 being equally spaced along the insertion of elevating lever 32 31 direction of lift span are offered on elevating lever 32, And offered on supporting leg 1 perpendicular to lift span 31 and the mounting hole 34 that is connected to lift span 31, when arranging construction bracket, Elevating lever 32 is inserted into lift span 31, and mounting hole 34 is aligned with connecting hole 33.In order to enable elevating lever 32 is inserted into lift span 31 length is conveniently fixed, and is equipped in mounting hole 34 and connecting hole 33 and is fixedly connected on elevating lever 32 and supporting leg 1 Installation bolt 35 together.
As shown in Figure 1 and Figure 2, before construction personnel constructs, the altitude range of wanted operating area is measured first It is good, length when then elevating lever 32 being inserted into lift span 31, and elevating lever 32 and supporting leg 1 being cooperated and the data pair measured Ying Hao allows construction bracket to deploy rear construction personnel convenient for operation.When elevating lever 32 is inserted into lift span 31, constructor Member is corresponding together by mounting hole 34 and the connecting hole 33 on elevating lever 32, wherein construction personnel selects according to the data measured Connecting hole 33 the most corresponding with mounting hole 34 is selected out, then installation bolt 35 is passed through into mounting hole 34 and connecting hole 33 and is tightened, So that supporting leg 1 is fixed together with elevating lever 32.After being lengthened supporting leg 1, construction personnel is by construction bracket cloth It sets.Construction personnel is stood again on the station plate 2 of construction bracket, the work fitted up.By the way that lifting is arranged on construction bracket Component 3 so that the height of construction bracket convenient for adjust, allow construction personnel when carrying out operation convenient for the operating area to eminence into Row construction, makes the construction working of construction personnel more easy.
As shown in Figure 1, being provided with as the more of ladder on supporting leg 1 in order to enable arrive at a station on plate 2 on construction personnel is convenient A ladder bars 4, ladder bars 4 are connected on two supporting legs 1, and are on two supporting legs 1 of station 2 one end of plate.By the way that ladder bars are arranged 4, construction personnel can be more convenient to arrive at a station on plate 2 after arranging construction bracket after raising.
Both ends on the plate 2 of station are additionally provided with the bar 5 with station 2 Relative vertical of plate, so that construction personnel is constructing When blocking by bar 5, the both ends for being not easy slave station plate 2 fall down, and make construction personnel safer at work.And in station plate 2 two sides are also vertically installed with the baffle 6 further stopped to construction personnel, further improve construction personnel in operation When safety.
In order to enable the case where station plate 2 is able to bear bigger power, will not bend when construction personnel constructs, Doubling plate is set by station plate 2, and is provided with more for increasing the mandril 7 of intensity between doubling plate.
Support rod 8 for increasing construction bracket intensity is installed between station plate 2 and supporting leg 1, wherein support rod 8 One end and station plate 2 are hinged, and a ladder bars 4 on the other end and supporting leg 1 are hinged, and support rod 8 is cut with scissors with ladder bars 4 and station plate 2 It is as axis that support rod 8 and station plate 2 and ladder bars 4 is hinged by the bolt being threaded through on support rod 8 when connecing.In construction bracket Upper setting increases the intensity between station plate 2 and supporting leg 1 by two support rods 8 there are two support rod 8, and passes through support Bar 8 carrys out the layout angle of support leg 1 and plate 2 of standing, so that construction bracket is more secured when in use.
As shown in Figure 1, Figure 3, the connection between supporting leg 1 and station plate 2 is rotation connection, and is provided on each supporting leg 1 At least one traveling wheel 9, the position of traveling wheel 9 is located at supporting leg 1 on the direction of station 2 center position of plate, in the branch that will construct When frame is packed up, construction personnel is by the hinged releasing at 8 both ends of support rod, when releasing, by the way that support rod 8 is connected to station 2 He of plate Bolt on supporting leg 1 takes off the work for completing to remove support rod 8, after removing support rod 8, between supporting leg 1 and station plate 2 Layout angle lose support, construction personnel can bend supporting leg 1.When being bent to supporting leg 1, the side of bending To the middle position towards station plate 2, so that supporting leg 1 is contacted after bending with station plate 2, and the walking on supporting leg 1 The direction of wheel 9 is after supporting leg 1 is bent away from station plate 2, when construction bracket is placed on the ground and supporting leg 1 is packed up, walking Wheel 9 and ground face contact, the bar 5 stood on plate 2 is used as pushing hands, so that a carriage type is integrally formed in construction bracket, convenient for construction Personnel transport, in addition, due to station plate 2 on be provided with baffle 6 so that construction bracket formed trolley when transporting object, Blocking of the object by baffle 6 is more convenient transport on the trolley that construction bracket is formed.Construction personnel using construction bracket as When trolley pushes, ground gives supporting leg 1 one upward thrusts, so that supporting leg 1 is not easy Automatic-expanding when packing up.By that will construct Bracket is set as that trolley shape can be folded into, so that the purposes of construction bracket is wider.
The specifically used method of the present embodiment is, when transporting construction bracket to job location, construction personnel is by bar 5 Construction bracket is pushed to job location in the form of cart as pushing hands, then construction bracket is unfolded to arrange by construction personnel again It is good, it constructs.When needing the height to construction bracket to be adjusted, construction personnel carries out supporting leg 1 by lifting assembly 3 It lengthens, so that the range of construction bracket effect is bigger.
Embodiment 2: a kind of Multifunctional decoration construction bracket, the present embodiment the difference from embodiment 1 is that, as shown in figure 4, After construction bracket deploys, dumbwaiter 10 is placed on the downside of station plate 2 and contacted with station plate 2 by construction personnel, and And remove the installation bolt 35 installed on supporting leg 1, so that 10 pairs of station plates 2 of dumbwaiter are supported, then construction personnel It arrives at a station on plate 2, constructs on directly, when needing to increase the height of station plate 2, construction personnel starts dumbwaiter 10, allows Dumbwaiter 10 raises the height for plate 2 of standing, so that construction personnel is more convenient fast in the height of regulation station plate 2 It is prompt.
Embodiment 3: a kind of Multifunctional decoration construction bracket, the present embodiment the difference from example 2 is that, as shown in figure 5, The mounting plate 11 for place tool is vertically installed on bar 5, mounting plate 11, which protrudes above, is provided with handle 12, both to apply Worker person, which facilitates, puts tool, do not need place the tool above station plate 2 on, allow construction personnel job security more Height, but also more convenient when being pushed to construction bracket.
This specific embodiment is only the explanation to the utility model, is not limitations of the present invention, ability Field technique personnel can according to need the modification that not creative contribution is made to the present embodiment after reading this specification, but As long as all by the protection of Patent Law in the scope of the claims of the utility model.

Claims (10)

1. a kind of Multifunctional decoration construction bracket, it is characterised in that: propped up including the multiple supporting legs (1) being supported and setting The station plate (2) stood on leg (1) one end for construction personnel;Edge of supporting leg (1) setting at station plate (2);The supporting leg (1) lifting assembly (3) that height adjustment is carried out convenient for construction bracket is additionally provided on;
The lifting assembly (3) includes being provided with supporting leg (1) far from station plate (2) one end along supporting leg (1) length direction arrangement Lift span (31) is threaded through the elevating lever (32) cooperated in lift span (31) with lift span (31), is provided on elevating lever (32) Along elevating lever (32) length insertion lift span (31) direction be equally spaced multiple connecting holes (33), be provided on supporting leg (1) With the mounting hole (34) of lift span (31) vertical connection and be threaded through in mounting hole (34) and connecting hole (33) for that will go up and down The installation bolt (35) that bar (32) and supporting leg (1) are fixed together.
2. a kind of Multifunctional decoration construction bracket according to claim 1, it is characterised in that: supporting leg is provided with work on (1) For multiple ladder bars (4) of ladder;Ladder bars (4) are connected on two supporting legs (1), and are located at two supporting legs (1) of station plate (2) one end On.
3. a kind of Multifunctional decoration construction bracket according to claim 1, it is characterised in that: the both ends on plate of standing (2) are also It is provided with the bar (5) with station plate (2) Relative vertical.
4. a kind of Multifunctional decoration construction bracket according to claim 1, it is characterised in that: also hang down the two sides of plate of standing (2) Directly it is provided with the baffle (6) further stopped to construction personnel.
5. a kind of Multifunctional decoration construction bracket according to claim 1, it is characterised in that: plate of standing (2) is set as double-deck Plate, and more are provided with for increasing the mandril (7) of intensity between doubling plate.
6. a kind of Multifunctional decoration construction bracket according to claim 2, it is characterised in that: plate of standing (2) and supporting leg (1) it Between support rod (8) for increasing construction bracket intensity is installed, one end and station plate (2) of the support rod (8) are hingedly, another End and a ladder bars (4) on supporting leg (1) are hinged;Support rod (8) is when with ladder bars (4) and hinged station plate (2), by being threaded through Bolt on support rod (8) is hinged by support rod (8) and station plate (2) and ladder bars (4) as axis;It is arranged on the station plate (2) There are two support rod (8).
7. a kind of Multifunctional decoration construction bracket according to claim 1, it is characterised in that: supporting leg (1) and station plate (2) it Between connection be rotation connection, and at least one traveling wheel (9) is provided on each supporting leg (1), the position position of traveling wheel (9) In supporting leg (1) on the direction of station plate (2) center position.
8. a kind of Multifunctional decoration construction bracket according to claim 1, it is characterised in that: be placed on the downside of plate of standing (2) The dumbwaiter (10) for being contacted with station plate (2) and being used to raise station plate (2).
9. a kind of Multifunctional decoration construction bracket according to claim 3, it is characterised in that: vertically set on bar (5) It is equipped with the mounting plate (11) for place tool.
10. a kind of Multifunctional decoration construction bracket according to claim 9, it is characterised in that: mounting plate (11) protrudes above It is provided with handle (12).
CN201821116265.8U 2018-07-13 2018-07-13 Multifunctional decoration construction bracket Active CN208734034U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821116265.8U CN208734034U (en) 2018-07-13 2018-07-13 Multifunctional decoration construction bracket

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821116265.8U CN208734034U (en) 2018-07-13 2018-07-13 Multifunctional decoration construction bracket

Publications (1)

Publication Number Publication Date
CN208734034U true CN208734034U (en) 2019-04-12

Family

ID=66027234

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821116265.8U Active CN208734034U (en) 2018-07-13 2018-07-13 Multifunctional decoration construction bracket

Country Status (1)

Country Link
CN (1) CN208734034U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112343320A (en) * 2020-11-02 2021-02-09 广东电网有限责任公司 Combined working support

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112343320A (en) * 2020-11-02 2021-02-09 广东电网有限责任公司 Combined working support

Similar Documents

Publication Publication Date Title
CN107268969A (en) A kind of scaffold structure for work high above the ground
CN201605792U (en) Foldable lifting scaffold
AU2013301976B2 (en) Floor-mounted conveyor device with a self-supporting supporting structure
CN208734034U (en) Multifunctional decoration construction bracket
US2600199A (en) Extensible scaffold
CN205171978U (en) Foldable aerial work hanging flower basket of split
CN205077893U (en) A support frame for building decoration
CN206693595U (en) A kind of scaffold car for building
CN102966312B (en) Operation platform device for wellhead operation
CN206858013U (en) Movable detachable manual-automatic integrated support lift device
CN206016841U (en) Development machine temporary support device
CN211473327U (en) Building external climbing type building construction operation platform
CN205777428U (en) Elevator is from climbing platforms
US2859066A (en) Adjustable foldable scaffold
CN208734036U (en) A kind of Multifunctional decoration construction bracket
CN206031120U (en) Equal adjustable of height and track prevents smooth right angle tower wagon of preventing inclining
CN216008506U (en) Scaffold for tunnel engineering convenient to adjust
CN207420430U (en) A kind of multi-functional herring ladder
CN206971699U (en) Combination hanging basket for the construction of wet seam
CN203394008U (en) Suspension type hanging bracket used on plane truss
CN205010855U (en) Take novel goods shelves of folding ladder
CN211397417U (en) Operation ladder for electromechanical engineering
CN209586241U (en) A kind of mobile folding ladder
CN210313183U (en) Truss tower and contain its strideing across construction protective equipment
CN107605142A (en) A kind of attachment type raise scaffold structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant