CN208669004U - Adjustable post-cast strip supporting device for house construction - Google Patents
Adjustable post-cast strip supporting device for house construction Download PDFInfo
- Publication number
- CN208669004U CN208669004U CN201821235155.3U CN201821235155U CN208669004U CN 208669004 U CN208669004 U CN 208669004U CN 201821235155 U CN201821235155 U CN 201821235155U CN 208669004 U CN208669004 U CN 208669004U
- Authority
- CN
- China
- Prior art keywords
- pedestal
- bevel gear
- built
- support device
- supporting sleeve
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000010276 construction Methods 0.000 title description 13
- 230000005540 biological transmission Effects 0.000 claims abstract description 11
- NJPPVKZQTLUDBO-UHFFFAOYSA-N novaluron Chemical compound C1=C(Cl)C(OC(F)(F)C(OC(F)(F)F)F)=CC=C1NC(=O)NC(=O)C1=C(F)C=CC=C1F NJPPVKZQTLUDBO-UHFFFAOYSA-N 0.000 claims description 45
- 230000003028 elevating effect Effects 0.000 claims description 9
- 229910000831 Steel Inorganic materials 0.000 claims description 5
- 239000010959 steel Substances 0.000 claims description 5
- 239000011148 porous material Substances 0.000 abstract 1
- 238000000034 method Methods 0.000 description 5
- 239000000463 material Substances 0.000 description 3
- TVEXGJYMHHTVKP-UHFFFAOYSA-N 6-oxabicyclo[3.2.1]oct-3-en-7-one Chemical compound C1C2C(=O)OC1C=CC2 TVEXGJYMHHTVKP-UHFFFAOYSA-N 0.000 description 2
- 238000010586 diagram Methods 0.000 description 2
- 239000002699 waste material Substances 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000004140 cleaning Methods 0.000 description 1
- 230000007423 decrease Effects 0.000 description 1
- 238000012423 maintenance Methods 0.000 description 1
Landscapes
- Foundations (AREA)
Abstract
The utility model relates to a post-cast strip supports technical field, discloses a post-cast strip strutting arrangement with adjustable room is built. The utility model discloses a support foundation comprises a base and a support sleeve which is positioned above the base and is vertically arranged, and a pair of limiting rods is vertically arranged on the top end surface of the support sleeve; the lifting mechanism is positioned in the supporting foundation and comprises a threaded rod which is positioned in the supporting sleeve and can rotate relatively and a connecting rod for connecting the threaded rod with the base, and the top end of the threaded rod is in threaded connection with the top supporting rod; limiting grooves matched with the limiting rods are correspondingly formed in the two sides of the lifting groove respectively; the transmission mechanism comprises a first bevel gear fixedly sleeved outside the connecting rod, a transmission rod positioned in the pore passage of the base, a second bevel gear fixedly sleeved at one end of the transmission rod, and a turntable arranged at the other end of the transmission rod; the second bevel gear is meshed with the first bevel gear. The utility model discloses simple structure, it is with low costs, easy and simple to handle, height-adjustable festival can have enough to meet the need the use.
Description
Technical field
The utility model relates to late poured band support technical fields, build more particularly to a kind of room with adjustable late poured band support
Device.
Background technique
Post-cast strip is a kind of deformation joint in the setting of cast-in-place Integratde concrete struction construction period, primarily to overcoming
Because of temperature or the issuable harmful cracks of concrete shrinkage, after monolithic concrete structure construction carries out again after for a period of time
Closing is poured, overall structure is formed.
Before structural slab is unclosed, the structural slab of two sides is overhanging state, and lower section needs to be arranged temporary support structure, simultaneously
The bottom of alter-pouring strips mould plate is also required to supporting apparatus, to ensure the normal construction of post-cast strip.Current existing post-cast strip is faced
When support device, one is more traditional steel tube frames, are built by a large amount of steel pipe, and it is big to set up project amount, time-consuming
Arduously, the maintenance workload in use process is big, needs to repeat when reusing after dismounting to build, construction efficiency is low, convenience
Difference;One is being supported using the support column poured, construction workload is big, and construction cost is high, and flexibility is poor, can not repeat to make
With, and heavy workload is abolished, waste of material is serious, and construction cost is high;There are also one is pvc pipe upright supports are used, remove
Heavy workload can generate a large amount of concrete rubbish and PVC rubbish, and cleaning difficulty is big, can not be used in turn, at high cost.
Utility model content
It is simple that the utility model provides a kind of structure, at low cost, easy to operate, height-adjustable, the room that can be used in turn
It builds with adjustable late poured band support device.
The technical issues of solution, is: existing post-cast strip supporting apparatus, takes that tear project amount open big, time-consuming and laborious, convenient
Property it is poor, flexibility is poor, can not reuse, and waste of material is serious, and construction cost is high.
In order to solve the above technical problems, the utility model adopts the following technical solution:
The utility model room is built with adjustable late poured band support device, including underlying brace foundation, the top of top
Strut connects the elevating mechanism of shore and brace foundation, and the transmission mechanism of control elevating mechanism;
Brace foundation includes pedestal and above pedestal, the supporting sleeve that is vertically arranged, and chassis interior is provided with hollow
Main chamber, offer through-hole at the top of main chamber, through-hole is connected to setting with supporting sleeve inner cavity;Main chamber side offers hole
Road, duct one end are connected to main chamber, and the other end extends to a side elevation of pedestal, the top end of supporting sleeve horizontally outward
A pair of of gag lever post is vertically arranged on face;
Elevating mechanism is located inside brace foundation, including is located in supporting sleeve, relatively turnable threaded rod, Yi Jilian
Connect the connecting rod of threaded rod and pedestal;
Shore and supporting sleeve are coaxially disposed, and top is provided with top plate, and bottom end center is offered to be matched with threaded rod
Lifting groove, lifting groove is arranged along the short transverse of shore, and threaded rod tip protrudes into lifting groove, connects with lifting groove screw thread
It connects;Lifting groove two sides respectively correspond the limiting slot for offering and matching with gag lever post, and gag lever post is located in limiting slot opposite sliding;
Transmission mechanism includes the first bevel gear being fixedly attached to outside connecting rod, the drive rod in pedestal duct, point
The second bevel gear and turntable of drive rod two sides are not set;Drive rod one end is protruded into main chamber, is connect with second bevel gear,
The other end stretches out pedestal to be fixed with turntable, and second bevel gear and first bevel gear are intermeshed.
The utility model room is built with adjustable late poured band support device, further, the pedestal by fixing bolt with
Ground is fixed.
The utility model room is built with adjustable late poured band support device, and further, main chamber room is located in pedestal
Entreat position.
The utility model room is built with adjustable late poured band support device, further, the connecting rod is located in main chamber,
Bottom end is connect with base rotation, and connecting rod top is welded and fixed after being upward through through-hole with threaded rod bottom end.
The utility model room is built with adjustable late poured band support device, and further, the supporting sleeve is that wall thickness is not small
In the round steel pipe of 4mm, bottom end is fixed with tube chamber welds with base.
The utility model room is built with adjustable late poured band support device, further, the central axis of the supporting sleeve
It is Chong Die with the geometric center of pedestal.
The utility model room is built with adjustable late poured band support device, and further, the gag lever post is oppositely arranged, bottom end
It is welded and fixed with the top end surface of supporting sleeve.
The utility model room, which is built, is further provided with locking screw on the turntable with adjustable late poured band support device
Bolt, clamping screw tail end, which is bonded after turntable with the side elevation of pedestal, shores setting.
The utility model room is built with adjustable late poured band support device compared with prior art, is had the following beneficial effects:
The utility model structure is simple, is realized and is driven with intermeshing bevel gear, by the turntable outside rotating base,
Threaded rod rotation is driven, and then kinetic energy is passed to the shore being threadedly coupled with threaded rod, and is turned by limitation shore
It is dynamic, and realize the adjusting of its rise and fall, the structural support of various height can be cooperated, had wide range of applications;Operation is just
Victory after being transported to construction site, adjusts height, can be completed and shore arrangement without largely setting up and dismantling construction, live work
Work amount is few, time saving and energy saving, and construction efficiency is high, and support device may be reused, take the process of tearing open and generate without any obsolete material, existing
Field is revolving flexibly, and construction cost is low.
The utility model fixes on chassis by fixing bolt on the ground, and structural stability is strong, after height adjustment,
With the fixed turntable of clamping screw, avoid turntable rotation that shore is caused to decline suddenly, supporting & stablizing is not easy to skid and fall off.
The room of the utility model is built with reference to the accompanying drawing and is described further with adjustable late poured band support device.
Detailed description of the invention
Fig. 1 is that the structural schematic diagram with adjustable late poured band support device is built in the utility model room;
Fig. 2 is the structural schematic diagram that position is arranged in the position A, that is, clamping screw in Fig. 1.
Appended drawing reference:
1- pedestal;11- fixing bolt;12- main chamber;The duct 13-;2- supporting sleeve;21- gag lever post;31- threaded rod;
32- connecting rod;4- shore;41- lifting groove;42- limiting slot;5- top plate;6- first bevel gear;7- drive rod;8- second is bored
Gear;9- turntable;91- clamping screw.
Specific embodiment
As depicted in figs. 1 and 2, it includes underlying support that the utility model room, which is built with adjustable late poured band support device,
Basis, the shore 4 of top connect the elevating mechanism of shore 4 and brace foundation, and the driver of control elevating mechanism
Structure.
Brace foundation includes pedestal 1 and the supporting sleeve 2 above pedestal 1, and pedestal 1 passes through fixing bolt 11 and ground
Fixed, pedestal 1 is internally provided with hollow main chamber 12, and central location, the top that main chamber 12 is located at pedestal 1 offer logical
Hole, through-hole are connected to setting with 2 inner cavity of supporting sleeve;12 side of main chamber offers duct 13,13 one end of duct and main chamber 12
Connection, the other end extend to a side elevation of pedestal 1 horizontally outward;Supporting sleeve 2 is the round steel pipe that wall thickness is not less than 4mm,
It is vertically arranged, the central axis of supporting sleeve 2 is Chong Die with the geometric center of pedestal 1, and bottom end is welded and fixed with pedestal 1;Support sleeve
A pair of of gag lever post 21 is vertically arranged in the top end surface of pipe 2, gag lever post 21 is oppositely arranged, the top of bottom end and supporting sleeve 2
End face is welded and fixed.
Elevating mechanism is located inside brace foundation, including is located in supporting sleeve 2, relatively turnable threaded rod 31, with
And the connecting rod 32 of connection screw thread bar 31 and pedestal 1, connecting rod 32 are located in main chamber 12, bottom end and pedestal 1 are rotatablely connected, top
End is welded and fixed after being upward through through-hole with 31 bottom end of threaded rod, and supporting sleeve 2 is stretched out on 31 top of threaded rod upwards, and with shore
Bar 4 connects.
Shore 4 and supporting sleeve 2 are coaxially disposed, and top is provided with top plate 5, and bottom end center offers and 31 phase of threaded rod
The lifting groove 41 of cooperation, lifting groove 41 are arranged along the short transverse of shore 4,31 top of threaded rod protrudes into lifting groove 41, with
Lifting groove 41 is threadedly coupled;41 two sides of lifting groove respectively correspond the limiting slot 42 for offering and matching with gag lever post 21, gag lever post
21 are located at opposite sliding in limiting slot 42.
Transmission mechanism includes the first bevel gear 6 being fixedly attached to outside connecting rod 32, the transmission in 1 duct 13 of pedestal
Bar 7, is fixedly attached to the second bevel gear 8 of 7 one end of drive rod, and the turntable 9 of 7 other end of drive rod is arranged in;Drive rod 7
One end is protruded into main chamber 12, is connect with second bevel gear 8, and it is fixed that the other end stretches out pedestal 1 and turntable 9, second bevel gear 8 with
First bevel gear 6 is intermeshed;Be provided with clamping screw 91 on turntable 9,91 tail end of clamping screw pass through after turntable 9 with pedestal 1
Side elevation fitting shore setting.
The application method with adjustable late poured band support device is built in the utility model room, comprising the following steps:
Step 1: determining Support Position, pedestal 1 is fixed on the ground by fixing bolt 11;
Step 2: unscrewing clamping screw 91, turntable 9 is rotated, shore 4 is increased, top plate 5 is supported on structural slab bottom,
Then clamping screw 91 is tightened, completion is temporarily shored;
The raised specific work process of shore 4 is as follows:
When turntable 9 rotates, turntable 9 drives second bevel gear 8 to rotate by drive rod 7, and the drive of second bevel gear 8 is nibbled with it
The first bevel gear 6 for closing transmission rotates, and first bevel gear 6 drives connecting rod 32 and threaded rod 31 to rotate, and then kinetic energy is transmitted
The shore 4 for giving the threaded connection of threaded rod 31, since gag lever post 21 limits the rotation trend of shore 4, with threaded rod
31 rotation, shore 4 rise;
Step 3: unscrewing clamping screw 91 after the completion of post empiricism, turntable 9 is rotated, shore 4 is reduced, removes branch
Support arrangement is reused.
Embodiment described above is only that preferred embodiments of the present invention are described, not practical to this
Novel range is defined, and under the premise of not departing from the spirit of the design of the utility model, those of ordinary skill in the art are to this
The various changes and improvements that the technical solution of utility model is made should all fall into the protection that the utility model claims book determines
In range.
Claims (8)
1. room is built with adjustable late poured band support device, it is characterised in that: including underlying brace foundation, top is shored
Bar (4) connects the elevating mechanism of shore (4) and brace foundation, and the transmission mechanism of control elevating mechanism;
Brace foundation includes pedestal (1) and is located above pedestal (1), the supporting sleeve (2) that is vertically arranged, is set inside pedestal (1)
It is equipped with hollow main chamber (12), offers through-hole at the top of main chamber (12), through-hole is connected to setting with supporting sleeve (2) inner cavity;
Main chamber (12) side offers duct (13), and duct (13) one end is connected to main chamber (12), and the other end extends horizontally outward
To a side elevation of pedestal (1), a pair of of gag lever post (21) are vertically arranged in the top end surface of supporting sleeve (2);
Elevating mechanism is located inside brace foundation, including is located in supporting sleeve (2), relatively turnable threaded rod (31), with
And the connecting rod (32) of connection screw thread bar (31) and pedestal (1);
Shore (4) and supporting sleeve (2) are coaxially disposed, and top is provided with top plate (5), and bottom end center offers and threaded rod
(31) lifting groove (41) matched, lifting groove (41) are arranged along the short transverse of shore (4), and threaded rod (31) top is protruded into
It is threadedly coupled in lifting groove (41), with lifting groove (41);Lifting groove (41) two sides, which respectively correspond, to be offered and gag lever post (21) phase
The limiting slot (42) of cooperation, gag lever post (21) are located in limiting slot (42) opposite sliding;
Transmission mechanism includes being fixedly attached to the first bevel gear (6) of connecting rod (32) outside, is located in pedestal (1) duct (13)
Drive rod (7), and it is separately positioned on the second bevel gear (8) and turntable (9) of drive rod (7) two sides;It stretches drive rod (7) one end
Enter in main chamber (12), be socketed with second bevel gear (8), the other end, which stretches out pedestal (1) and turntable (9), to be fixed, second bevel gear
(8) it is intermeshed with first bevel gear (6).
2. room according to claim 1 is built with adjustable late poured band support device, it is characterised in that: the pedestal (1) is logical
Fixing bolt (11) is crossed to fix with ground.
3. room according to claim 1 is built with adjustable late poured band support device, it is characterised in that: main chamber room (12)
Positioned at the central location of pedestal (1).
4. room according to claim 1 is built with adjustable late poured band support device, it is characterised in that: the connecting rod (32)
In the main chamber (12), bottom end and pedestal (1) be rotatablely connected, connecting rod (32) top is upward through after through-hole and threaded rod
(31) bottom end is welded and fixed.
5. room according to claim 1 is built with adjustable late poured band support device, it is characterised in that: the supporting sleeve
(2) it is not less than the round steel pipe of 4mm for wall thickness, bottom end is welded and fixed with pedestal (1).
6. room according to claim 1 is built with adjustable late poured band support device, it is characterised in that: the supporting sleeve
(2) central axis is Chong Die with the geometric center of pedestal (1).
7. room according to claim 1 is built with adjustable late poured band support device, it is characterised in that: the gag lever post (21)
It is oppositely arranged, the top end surface of bottom end and supporting sleeve (2) is welded and fixed.
8. room according to claim 1 is built with adjustable late poured band support device, it is characterised in that: on the turntable (9)
It is provided with clamping screw (91), clamping screw (91) tail end is bonded to shore and set with the side elevation of pedestal (1) afterwards across turntable (9)
It sets.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821235155.3U CN208669004U (en) | 2018-08-02 | 2018-08-02 | Adjustable post-cast strip supporting device for house construction |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821235155.3U CN208669004U (en) | 2018-08-02 | 2018-08-02 | Adjustable post-cast strip supporting device for house construction |
Publications (1)
Publication Number | Publication Date |
---|---|
CN208669004U true CN208669004U (en) | 2019-03-29 |
Family
ID=65833047
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201821235155.3U Expired - Fee Related CN208669004U (en) | 2018-08-02 | 2018-08-02 | Adjustable post-cast strip supporting device for house construction |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN208669004U (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112012480A (en) * | 2020-08-25 | 2020-12-01 | 圣峰建设有限公司 | Tool type independent formwork structure for post-cast strip and construction process |
CN112482749A (en) * | 2020-12-04 | 2021-03-12 | 陈轶 | Adjustable supporting device for building engineering construction |
CN112942897A (en) * | 2021-02-02 | 2021-06-11 | 浙江工业职业技术学院 | Support device for civil engineering and operation method thereof |
CN114207233A (en) * | 2019-08-08 | 2022-03-18 | 格罗夫设计(彭布里奇)有限公司 | Supporting structure |
-
2018
- 2018-08-02 CN CN201821235155.3U patent/CN208669004U/en not_active Expired - Fee Related
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114207233A (en) * | 2019-08-08 | 2022-03-18 | 格罗夫设计(彭布里奇)有限公司 | Supporting structure |
CN114207233B (en) * | 2019-08-08 | 2023-09-22 | 格罗夫设计(彭布里奇)有限公司 | Supporting structure |
CN112012480A (en) * | 2020-08-25 | 2020-12-01 | 圣峰建设有限公司 | Tool type independent formwork structure for post-cast strip and construction process |
CN112482749A (en) * | 2020-12-04 | 2021-03-12 | 陈轶 | Adjustable supporting device for building engineering construction |
CN112942897A (en) * | 2021-02-02 | 2021-06-11 | 浙江工业职业技术学院 | Support device for civil engineering and operation method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN208669004U (en) | Adjustable post-cast strip supporting device for house construction | |
CN109779270B (en) | Prefabricated post installation device | |
CN111576597A (en) | Municipal works drainage open channel construction fixing device | |
CN209891347U (en) | Pipe ditch inner formwork support device | |
CN215907512U (en) | Adjustable post-cast strip independent supporting device | |
CN221760475U (en) | Precast T roof beam diaphragm strutting arrangement | |
CN213027889U (en) | Civilian photovoltaic power generation board base support of simple and convenient loading and unloading | |
CN211472474U (en) | Be used for public road bridge roof beam pile foundation fixing device | |
US3614050A (en) | Reusable forming unit | |
CN208844919U (en) | A kind of construction form and shoring early-dismantling device | |
CN220080917U (en) | Supporting device for repairing ancient building | |
CN218779973U (en) | Half grout sleeve clamping device | |
CN208026478U (en) | A kind of traffic construction quality detection device | |
CN217150200U (en) | Club-footed pile for building immersed tube | |
CN113006374B (en) | Column support component for construction of steel structure factory building | |
CN218813165U (en) | Box girder wet joint template supporting structure | |
CN221031669U (en) | Template support bracket | |
CN220319166U (en) | Steel construction post concrete placement auxiliary member | |
CN221398966U (en) | Civil engineering pile body reinforcing apparatus | |
CN221030309U (en) | Pipe gallery steel mould | |
CN219620836U (en) | PC prefabricated part tilting mechanism | |
CN216108103U (en) | A high stability hopper for roof beam body concrete is pour | |
CN217460672U (en) | Square inspection well template device | |
CN209394911U (en) | Post-cast strip steel wire mesh template device | |
CN222025437U (en) | Assembled Z-shaped support |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20190329 Termination date: 20210802 |