CN208594572U CN201821308189.0U CN201821308189U CN208594572U CN 208594572 U CN208594572 U CN 208594572U CN 201821308189 U CN201821308189 U CN 201821308189U CN 208594572 U CN208594572 U CN 208594572U
Authority
CN
China
Prior art keywords
template
piping lane
door frame
lane door
single layer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201821308189.0U
Other languages
Chinese (zh)
Inventor
郭延军
钟云伦
杨天明
胡志荣
漆伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 11th Bureau Group Co Ltd
Fifth Engineering Co Ltd of China Railway 11th Bureau Group Co Ltd
Original Assignee
China Railway 11th Bureau Group Co Ltd
Fifth Engineering Co Ltd of China Railway 11th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 11th Bureau Group Co Ltd, Fifth Engineering Co Ltd of China Railway 11th Bureau Group Co Ltd filed Critical China Railway 11th Bureau Group Co Ltd
Priority to CN201821308189.0U priority Critical patent/CN208594572U/en
Application granted granted Critical
Publication of CN208594572U publication Critical patent/CN208594572U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

It is hydraulic from walking formwork jumbo that the utility model discloses a kind of double cabin pipe galleries of underground single layer, including two piping lane door frames, electric walking mechanism, traveling steel rail, each piping lane door frame includes structural steel frame, top template, inner side template, structural steel frame drives one lifting of top template under the promotion of jacking cylinder, inner side template, which is realized to stretch out outward by horizontally disposed cheek board oil cylinder, to be connected with the end of top template or is detached to the end of contract and top template, positioned at the left side of the piping lane door frame in left side, an outboard template is each provided on the right side of the piping lane door frame on right side;When top template rises in place, and inner side template is stretched out outward when connecting with the end of top template, and the inner side template that outboard template is oppositely arranged with immediate inner side template, two piping lane door frames is respectively by being strained and fixed to wire drawing bar.For realizing the concreting of the double cabin pipe gallery main structures of underground single layer rapidly and efficiently.

Description

Single layer double cabin pipe galleries in underground are hydraulic from walking formwork jumbo
Technical field
The utility model relates to Construction Technology fields, and in particular to a kind of concreting of underground pipe gallery Formwork jumbo.
Background technique
Currently, domestic underground pipe gallery main structure concreting mainly uses full framing plank sheathing support system System, steel or aluminum alloy pattern plate support system.That there are wastes is big for wooden model system, the number of turnover is few, labour cost is high, structure Linear Control The problem that difference, Surface Quality of Concrete are poor, the group demoulding period is long;Steel aluminum dipping form system exist be self-possessed it is larger, need crane coordinative construction, The group demoulding period is longer, disposably puts into high problem.
Utility model content
In view of the above technical problems, it is hydraulic from walking to be intended to provide a kind of double cabin pipe galleries of underground single layer for the utility model Formwork jumbo, for realizing the concreting of the double cabin pipe gallery main structures of underground single layer rapidly and efficiently.
For this purpose, the technology employed by the present utility model is a kind of double cabin pipe galleries of underground single layer are hydraulic from walking Formwork jumbo, including left and right two piping lane door frames arranged side by side, the bottom of each piping lane door frame is respectively arranged with electric walking Mechanism, be provided on bottom plate with the one-to-one traveling steel rail of electric walking mechanism, each piping lane door frame includes structural steel frame, solid The inner side template for being located at the top template at the top of structural steel frame, being slidably mounted at left and right sides of structural steel frame, structural steel frame are jacking Under the promotion of oil cylinder drive one lifting of top template, inner side template by horizontally disposed cheek board oil cylinder realize outward stretch out with The end of top template connects or is detached to the end of contract and top template, positioned at the left side of the piping lane door frame in left side, positioned at the right side An outboard template is each provided on the right side of the piping lane door frame of side;
When top template rises in place, and inner side template is stretched out outward when connecting with the end of top template, outboard template with most The inner side template that close inner side template, two piping lane door frames are oppositely arranged is respectively by being strained and fixed to wire drawing bar.
Application method: having poured bottom plate first, and two piping lane door frames run to bottom plate under the drive of electric walking mechanism On the traveling steel rail that top is laid with, after structural steel frame drives top template to rise in place under the promotion of jacking cylinder, inner side template Realized under the promotion of cheek board oil cylinder and stretch out and connect with the end of top template outward, then by wire drawing bar by outboard template with The inner side template that immediate inner side template, two piping lane door frames are oppositely arranged is strained and fixed respectively, then carries out concreting; After the completion of pouring, demould exactly the opposite with process in place.
The centre of the bottom plate is low as a preferred embodiment of the above solution, the high formation gradient in left and right ends, is reserved with two on bottom plate The gutter that a front and back extends, when piping lane pours, gutter is clogged by chock respectively, and two gutters respectively correspond setting At the inner side position in the bottom of two piping lanes.So that bottom plate is formed gradient, adds gutter and clogged by chock, made after pouring Each cabin on pipe gallery ground have gutter, the indoor superfluous water in cabin can be discharged in time, avoid the occurrence of ponding.Two A gutter, which respectively corresponds, to be arranged at the inner side position in bottom of two piping lanes, facilitates arrangement and entirety is more coordinated.
Further, each piping lane door frame is equipped with there are four cheek board oil cylinder, and four cheek board oil cylinders point two-by-two one Group, in the two sides of piping lane door frame between the upper and lower every setting, cheek board oil cylinder pushing inner side template is led jointly pulley and guide groove It is stretched out outward under to effect or to contract;Two piping lane door frames share four jacking cylinders in rectangular layout, jacking cylinder Piston rod and corresponding piping lane door frame front-rear side walls on the bracket that welds be connected.Optimize cheek board oil cylinder, jacking cylinder quantity, Position and mounting means not only can guarantee steady in place and demoulding, but also can simplify cost, facilitate integral layout.
Further, when the top template rises in place, and inner side template is stretched out outward when connecting with the end of top template, top Four inside locks for pouring chamber that template and inner side template, inner side template and bottom plate surround have chamfering, avoid pouring comprehensive Close the cabin inside lock band wedge angle of piping lane.
Further, two piping lane door frames are contour, but width differs, and two equal cabins do not meet difference to size width Piping lane use demand.
The utility model has the beneficial effects that it is lossless in work progress, can repeatedly be used in turn, labour cost is low, structure Linear Control is good, pour after Surface Quality of Concrete is good, the group demoulding period is short, and be not necessarily to crane coordinative construction, be able to achieve fast The concreting of the fast double cabin pipe gallery main structures of efficient underground single layer.
Detailed description of the invention
Fig. 1 is the structural schematic diagram (position) of the utility model.
Fig. 2 is the side view of Fig. 1.
Specific embodiment
By way of example and in conjunction with the accompanying drawings, the utility model is described in further detail:
As shown in Figure 1, Figure 2, a kind of double cabin pipe galleries of underground single layer are hydraulic from walking formwork jumbo, mainly by piping lane Door frame 2, electric walking mechanism 3, traveling steel rail 4, jacking cylinder 5, cheek board oil cylinder 6, outboard template 7, to wire drawing bar 8, chock 9, pulley 10 and guide groove 11 etc. form.
Piping lane door frame 2 totally two, left and right is arranged side by side.The bottom of each piping lane door frame 2 is respectively arranged with an electric walking Walk mechanism 3, be provided on bottom plate 1 with the one-to-one traveling steel rail 4 of electric walking mechanism 3, piping lane door frame 2 is in electric walking machine Under the driving of structure 3, it can be moved forward and backward along corresponding traveling steel rail 4.
Each piping lane door frame 2 includes structural steel frame 2a, the top template 2b being installed at the top of structural steel frame 2a, is slidably mounted on Inner side template 2c composition at left and right sides of structural steel frame 2a.Structural steel frame 2a drives top template 2b under the promotion of jacking cylinder 5 One lifting, inner side template 2c realizes to stretch out outward by horizontally disposed cheek board oil cylinder 6 to connect with the end of top template 2b Or it is detached to the end of contract and top template 2b.Left side positioned at the piping lane door frame 2 in left side, the piping lane door frame 2 positioned at right side Right side be each provided with an outboard template 7.
When top template 2b rises in place, and inner side template 2c is stretched out when connecting with the end of top template 2b outward as shape in place State, the inner side template 2c that outboard template 7 and immediate inner side template 2c, two piping lane door frames 2 are oppositely arranged pass through pair respectively Wire drawing bar 8 is strained and fixed, and can carry out concreting.
Preferably, the centre of bottom plate 1 is low, the high formation gradient in left and right ends, and the gradient of bottom plate 1 is preferably 1%.On bottom plate 1 Reserved there are two the gutter that front and back extends, when piping lane pours, gutter passes through chock 9 respectively and clogs, two gutter difference It is correspondingly arranged at the inner side position in bottom of two piping lanes.
In addition, each piping lane door frame 2 is equipped with, there are four cheek board oil cylinders 6, and four cheek board oil cylinders 6 divide in pairs, In the two sides of piping lane door frame 2 between the upper and lower every setting.Cheek board oil cylinder 6 pushes inner side template 2c being total in pulley 10 and guide groove 11 With being stretched out outward under guiding role or to contract.Two piping lane door frames 2 share four jacking cylinders 5 in rectangular layout, top The bracket 2d welded on the piston rod of oil-lifting jar 5 and corresponding 2 front-rear side walls of piping lane door frame is connected.
Preferably, when top template 2b rises in place, and inner side template 2c is stretched out outward when connecting with the end of top template 2b, Four inside locks for pouring chamber that top template 2b and inner side template 2c, inner side template 2c and bottom plate 1 are surrounded have chamfering 2e.
In addition, two piping lane door frames 2 are contour, but width differs, to form size width not two equal cabins.

Claims (6)

1. a kind of double cabin pipe galleries of underground single layer are hydraulic from walking formwork jumbo, it is characterised in that: be arranged side by side including left and right Two piping lane door frames (2), the bottom of each piping lane door frame (2) is respectively arranged with electric walking mechanism (3), and bottom plate is set on (1) It is equipped with and includes structural steel frame (2a), consolidates with the one-to-one traveling steel rail (4) of electric walking mechanism (3), each piping lane door frame (2) It is located at the top template (2b) at the top of structural steel frame (2a), the inner side template being slidably mounted at left and right sides of structural steel frame (2a) (2c), structural steel frame (2a) drive top template (2b) lifting under the promotion of jacking cylinder (5), and inner side template (2c) passes through Horizontally disposed cheek board oil cylinder (6), which is realized to stretch out outward, to be connected with the end of top template (2b) or to contract and top template The end of (2b) is detached from, the left side positioned at the piping lane door frame (2) in left side, the piping lane door frame (2) positioned at right side right side be respectively arranged There is an outboard template (7);
When top template (2b) rises in place, and inner side template (2c) is stretched out outward when connecting with the end of top template (2b), outside The inner side template (2c) that template (7) and immediate inner side template (2c), two piping lane door frames (2) are oppositely arranged respectively by pair Wire drawing bar (8) is strained and fixed.
2. the double cabin pipe galleries of underground single layer described in accordance with the claim 1 are hydraulic from walking formwork jumbo, it is characterised in that: institute The centre for stating bottom plate (1) is low, the high formation gradient in left and right ends, reserves that there are two the gutters that front and back extends on bottom plate (1), in pipe Gutter passes through chock (9) respectively and clogs when corridor pours, two gutters respectively correspond be arranged in two piping lanes bottom it is inner At side position.
3. the double cabin pipe galleries of underground single layer according to claim 1 or 2 are hydraulic from walking formwork jumbo, feature exists In: there are four cheek board oil cylinder (6) for each piping lane door frame (2) outfit, and four cheek board oil cylinders (6) point are in pairs, In the two sides of piping lane door frame (2) between the upper and lower every setting, cheek board oil cylinder (6) pushes inner side template (2c) in pulley (10) and guiding It is stretched out outward under the common guiding role of slot (11) or to contract;Two piping lane door frames (2) share four it is in rectangular layout The bracket (2d) welded on jacking cylinder (5), the piston rod of jacking cylinder (5) and corresponding piping lane door frame (2) front-rear side walls is connected.
4. the double cabin pipe galleries of underground single layer described in accordance with the claim 3 are hydraulic from walking formwork jumbo, it is characterised in that: when The top template (2b) rises in place, and inner side template (2c) is stretched out outward when connecting with the end of top template (2b), top template Four inside locks for pouring chamber that (2b) and inner side template (2c), inner side template (2c) and bottom plate (1) surround have chamfering (2e)。
5. the double cabin pipe galleries of underground single layer described in accordance with the claim 3 are hydraulic from walking formwork jumbo, it is characterised in that: institute The gradient for stating bottom plate (1) is 1%.
6. the double cabin pipe galleries of underground single layer described in accordance with the claim 1 are hydraulic from walking formwork jumbo, it is characterised in that: two A piping lane door frame (2) is contour, but width differs.
CN201821308189.0U 2018-08-14 2018-08-14 Single layer double cabin pipe galleries in underground are hydraulic from walking formwork jumbo Active CN208594572U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821308189.0U CN208594572U (en) 2018-08-14 2018-08-14 Single layer double cabin pipe galleries in underground are hydraulic from walking formwork jumbo

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821308189.0U CN208594572U (en) 2018-08-14 2018-08-14 Single layer double cabin pipe galleries in underground are hydraulic from walking formwork jumbo

Publications (1)

Publication Number Publication Date
CN208594572U true CN208594572U (en) 2019-03-12

Family

ID=65604926

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821308189.0U Active CN208594572U (en) 2018-08-14 2018-08-14 Single layer double cabin pipe galleries in underground are hydraulic from walking formwork jumbo

Country Status (1)

Country Link
CN (1) CN208594572U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112878362A (en) * 2021-01-07 2021-06-01 中国二十冶集团有限公司 Comprehensive pipe gallery slip form device and construction method
CN113463683A (en) * 2021-05-21 2021-10-01 重庆川九建设有限责任公司 Double-pipe gallery slip form trolley and double-pipe gallery construction method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112878362A (en) * 2021-01-07 2021-06-01 中国二十冶集团有限公司 Comprehensive pipe gallery slip form device and construction method
CN113463683A (en) * 2021-05-21 2021-10-01 重庆川九建设有限责任公司 Double-pipe gallery slip form trolley and double-pipe gallery construction method

Similar Documents

Publication Publication Date Title
CN204640450U (en) A kind of assembling-type precast box girder integral moving die plate
CN204626960U (en) Large-section stiffened steel rib column steel truss template
CN208594572U (en) Single layer double cabin pipe galleries in underground are hydraulic from walking formwork jumbo
CN103074871B (en) Arc-shaped slope concrete sliding and lifting template
CN107237270A (en) A kind of construction method of girder construction
CN209408814U (en) A kind of PC track beam form system
CN104453951B (en) Combined type subway station lining template trolley for baffle
CN105041339B (en) Disengaging type formwork jumbo, chassis component and underpass concrete construction method
CN210969361U (en) Production line for precast concrete hollow anti-seismic wallboard
CN107386246B (en) A kind of lock chamber wall Construction Through Form on Traveler method
CN103669872B (en) A kind of walling method and walling equipment
CN107443547A (en) The production equipment and production method of a kind of precast beam
CN108265981A (en) A kind of design method of building element production technology layout
CN212399901U (en) Gypsum slat production host computer
CN212774321U (en) Disconnect-type concrete form platform truck
CN103225394B (en) Big wood template construction method of indoor constructional engineering shear wall
CN102322138A (en) The modular sliding formwork
CN107398985A (en) The production equipment and production method of a kind of precast beam
CN112482317A (en) Door slot second-stage concrete self-climbing slip form pouring system and construction method
CN110344334A (en) Steel reinforced concrete combined bridge construction method is done using two bridgings of dorsal funciculus formula Bridge Erector
CN214573768U (en) Self-climbing sliding formwork pouring system for second-stage concrete pouring of gate slot
CN205591932U (en) Full -automatic highway, railway ditch cable duct lining cutting platform truck
CN208933913U (en) Whole revetment wall form mobile device
CN203684687U (en) Walling device
CN111823366A (en) Gypsum batten production host and production method

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant