CN206844815U - A kind of transformer station's Assembled enclosing wall - Google Patents

A kind of transformer station's Assembled enclosing wall Download PDF

Info

Publication number
CN206844815U
CN206844815U CN201720099421.3U CN201720099421U CN206844815U CN 206844815 U CN206844815 U CN 206844815U CN 201720099421 U CN201720099421 U CN 201720099421U CN 206844815 U CN206844815 U CN 206844815U
Authority
CN
China
Prior art keywords
column
wallboard
transformer station
basis
enclosing wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720099421.3U
Other languages
Chinese (zh)
Inventor
桂晓刚
韩斌
安金霞
刘洁
陈铿
高旭浩
汪海江
蔡蕾
王林
钟阳颂
胡彬
徐升阳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
The Ningxia Hui Autonomous Region Electric Power Design Institute Co., Ltd.
Hebei Electric Power Design and Research Institute
Original Assignee
NINGXIA HUI AUTONOMOUS REGION ELECTRIC POWER DESIGN INSTITUTE
Hebei Electric Power Design and Research Institute
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NINGXIA HUI AUTONOMOUS REGION ELECTRIC POWER DESIGN INSTITUTE, Hebei Electric Power Design and Research Institute filed Critical NINGXIA HUI AUTONOMOUS REGION ELECTRIC POWER DESIGN INSTITUTE
Priority to CN201720099421.3U priority Critical patent/CN206844815U/en
Application granted granted Critical
Publication of CN206844815U publication Critical patent/CN206844815U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Fencing (AREA)

Abstract

The utility model belongs to building walling technical field, more particularly to a kind of transformer station's Assembled enclosing wall, to solve the technical problem that transformer station's enclosure wall building construction cycle is long in the prior art and cost of labor is high.Including:Basis, grade beam, column, wallboard, wallboard are beared down on one and cap etc.;Wherein, basis is stand alone type;Column bottom is fixedly connected with basis;Column cylinder set neck, grade beam both ends set tenon and by tenon be inserted into column neck and freely-supported on the basis of;Wallboard both ends are plugged in column neck, and bottom is supported on grade beam;It is high to wall is designed to stack the wallboard of respective numbers, flat mouth alignment connection or concave convex button connection between adjacent wall board;Wallboard bears down on one is installed on panel tops by the groove set thereon;Cap is installed at the top of column by the groove set thereon.Compared with prior art, the utility model can shorten construction period, improve efficiency of construction, reduce construction cost.

Description

A kind of transformer station's Assembled enclosing wall
Technical field
The utility model belongs to building walling technical field, more particularly to a kind of transformer station's Assembled enclosing wall.
Background technology
Traditional transformer station's enclosure wall uses the technique of clear water enclosure wall more, and clear water enclosure wall refers to not carry out any decoration to metope, Only make enclosure wall facing with the Natural color of base material in itself, whole metope need not other decorations and rendering.Clear water enclosure wall is divided into clear water Brick wall and dry concrete wall.It is higher to the technical requirements of building worker by laying bricks or stones but clear water enclosure wall is built by laying bricks or stones, and because wet trade compared with It is more, the problem of construction period is longer, and cost of labor is higher be present, therefore, need a kind of new change that can solve the problem that above mentioned problem badly Power station enclosure wall technique.
The content of the invention
To solve the technical problem that transformer station's enclosure wall building construction cycle is long, cost of labor is high in the prior art, this practicality New a kind of transformer station's Assembled enclosing wall of offer, to improve efficiency of construction, reduce cost.
In order to solve the above technical problems, transformer station's Assembled enclosing wall provided by the utility model, including:Basis, grade beam, Column, wallboard, wallboard bear down on one and cap;Wherein, basis is stand alone type;Column bottom is fixedly connected with basis;Column cylinder is set Neck is put, grade beam both ends set tenon, and grade beam is inserted into by the tenon set thereon in column neck and freely-supported is on the basis of; Wallboard both ends are plugged in column neck, and bottom is supported on grade beam;It is high to design wall to stack the wallboard of respective numbers, adjacent wall Flat mouth alignment connection or concave convex button connection between plate;Wallboard bottom of bearing down on one sets the groove that is matched with wallboard, and wallboard, which bears down on one, to be passed through Groove is installed on panel tops;Cap bottom sets the groove matched with column, and cap is installed at the top of column by groove.
It is preferred that the column is connected with basis using plug-in type, or the column is connected with base solder.
It is preferred that the column includes standard column and corner upright;The standard column both sides setting neck, described turn The adjacent two sides of corner post set neck.
It is preferred that spilled water hole is set in the grade beam beam body.
It is preferred that the wallboard bears down on one, top is curved surface, and top tilts to both sides from the central position.
It is preferred that being curved surface at the top of the cap, top tilts to surrounding from the central position.
It is preferred that the wallboard bears down on one, bottom sets drip along both sides.
It is preferred that the circumferentially arranged drip in cap bottom.
It is preferred that the cap and wallboard bear down on one, top sets mounting hole, sets fence thereon.
The utility model beneficial effect includes:
Compared with prior art, Assembled enclosing wall provided by the utility model, the wet trade of job site is reduced, can Shorten construction period, improve efficiency of construction, reduce construction cost.
Brief description of the drawings
Fig. 1 is structural representation of the present utility model.
Description of reference numerals:1 basis;2 grade beams;20 spilled water holes;30 standard columns;31 corner uprights;4 wallboards;5 wallboard pressures Top;6 caps.
Embodiment
Below in conjunction with the accompanying drawings, the utility model is described in detail with specific embodiment.
As shown in fig.1, transformer station's Assembled enclosing wall of the utility model embodiment, including:Basis 1, grade beam 2, stand Post, wallboard 4, wallboard bear down on one 5 and cap 6;Wherein, basis 1 is stand alone type;Column bottom is fixedly connected with basis 1;Column cylinder Neck is set, and the both ends of grade beam 2 set tenon, and grade beam 2 is inserted into by the tenon set thereon in column neck and freely-supported is in base On plinth 1;The both ends of wallboard 4 are plugged in column neck, and bottom is supported on grade beam 2;The wallboards 4 of respective numbers is stacked to design wall Height, flat mouth alignment connection or concave convex button connection between adjacent wall board 4;The bottom of bearing down on one of wallboard 4 sets the groove that is matched with wallboard 4, Wallboard 4 bears down on one is installed on the top of wallboard 4 by groove;The bottom of cap 6 sets the groove matched with column, and cap 6 passes through groove It is installed at the top of column.Basis 1 and grade beam 2 can use concrete cast-in-situ formula, or concrete prefabricated formula according to field condition;Base C15 the concrete cushions thick bottom surface of plinth 1 laying 100mm;Column, wallboard 4, wallboard bear down on one 5 and cap 6 use prefabricated;Peace Fill it is ready after, joint filling is handled using dedicated mortar or silicone weatherproof sealant.
It is preferred that as shown in fig.1, basis 1 is independent rim of a cup formula, column is inserted on basis 1;Or the top of basis 1 Pre-embedded steel slab, column bottom pre-embedded steel slab, column are welded to connect with basis 1.
It is preferred that as shown in fig.1, column includes standard column 30 and corner upright 31;The both sides of standard column 30 are set Neck, the adjacent two sides of corner upright 31 set neck.
It is preferred that as shown in fig.1, spilled water hole 20 is set in the beam body of grade beam 2.
It is preferred that 5 tops are curved surface as shown in fig.1, wallboard bears down on one, top tilts to both sides from the central position, more Body, top is the conical surface, prevents ponding.
It is preferred that as shown in fig.1, the top of cap 6 is curved surface, top tilts to surrounding from the central position, more specifically, Top is domatic, prevents ponding.
It is preferred that 5 bottoms set drip along both sides as shown in fig.1, wallboard bears down on one, prevent water from bearing down on one 5 bottoms along wallboard Wallboard 4 is penetrated into face, corrodes wallboard 4.
It is preferred that as shown in fig.1, the circumferentially arranged drip in the bottom of cap 6, it is vertical to prevent that water from penetrating into along cap bottom surface Post, corrode column
It is preferred that 5 tops set mounting hole as shown in fig.1, cap 6 and wallboard bear down on one, fence is set thereon.
In summary, compared with prior art, Assembled enclosing wall provided by the utility model, the wet of job site is reduced Operation, construction period can be shortened, improve efficiency of construction, reduce construction cost.
Obviously, those skilled in the art can carry out various changes and modification without departing from this practicality to the utility model New spirit and scope.So, if these modifications and variations of the present utility model belong to the utility model claims and Within the scope of its equivalent technologies, then the utility model is also intended to comprising including these changes and modification.

Claims (9)

  1. A kind of 1. transformer station's Assembled enclosing wall, it is characterised in that including:Basis, grade beam, column, wallboard, wallboard bears down on one and post Cap;Wherein, basis is stand alone type;Column bottom is fixedly connected with basis;Column cylinder sets neck, and grade beam both ends set convex Tenon, grade beam is inserted into by the tenon set thereon in column neck and freely-supported is on the basis of;Wallboard both ends are plugged in column card In groove, bottom is supported on grade beam;It is high to wall is designed to stack the wallboards of respective numbers, between adjacent wall board flat mouth alignment connection or Concave convex button connects;Wallboard bottom of bearing down on one sets the groove that is matched with wallboard, and wallboard bears down on one is installed on panel tops by groove;Post Cap bottom sets the groove matched with column, and cap is installed at the top of column by groove.
  2. 2. transformer station's Assembled enclosing wall as claimed in claim 1, it is characterised in that the column uses plug-in type with basis Connection, or the column are used with basis and are welded to connect.
  3. 3. transformer station's Assembled enclosing wall as claimed in claim 1, it is characterised in that the column includes standard column and turned Corner post;The standard column both sides set neck, and the adjacent two sides of the corner upright set neck.
  4. 4. transformer station's Assembled enclosing wall as claimed in claim 1, it is characterised in that set and sluice in the grade beam beam body Hole.
  5. 5. transformer station's Assembled enclosing wall as claimed in claim 1, it is characterised in that the wallboard bear down on one top be curved surface, Top tilts to both sides from the central position.
  6. 6. transformer station's Assembled enclosing wall as claimed in claim 1, it is characterised in that it is curved surface at the top of the cap, top Tilted from the central position to surrounding.
  7. 7. transformer station's Assembled enclosing wall as claimed in claim 1, it is characterised in that wallboard bottom of bearing down on one is set along both sides Put drip.
  8. 8. transformer station's Assembled enclosing wall as claimed in claim 1, it is characterised in that the circumferentially arranged drop in cap bottom Waterline.
  9. 9. transformer station's Assembled enclosing wall as described in claim 1-8 is any, it is characterised in that the cap and wallboard bear down on one Top sets mounting hole, sets fence thereon.
CN201720099421.3U 2017-01-23 2017-01-23 A kind of transformer station's Assembled enclosing wall Active CN206844815U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720099421.3U CN206844815U (en) 2017-01-23 2017-01-23 A kind of transformer station's Assembled enclosing wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720099421.3U CN206844815U (en) 2017-01-23 2017-01-23 A kind of transformer station's Assembled enclosing wall

Publications (1)

Publication Number Publication Date
CN206844815U true CN206844815U (en) 2018-01-05

Family

ID=60790176

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720099421.3U Active CN206844815U (en) 2017-01-23 2017-01-23 A kind of transformer station's Assembled enclosing wall

Country Status (1)

Country Link
CN (1) CN206844815U (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109236033A (en) * 2018-09-14 2019-01-18 拓暄建设科技有限公司 A kind of building prefabrication Assembled enclosing wall and its production technology
CN109869044A (en) * 2019-03-28 2019-06-11 中国建筑西北设计研究院有限公司 A kind of modularization dismounting enclosure wall
CN109989413A (en) * 2019-04-18 2019-07-09 中国建筑西北设计研究院有限公司 The spliced basis of power station equipment
CN110159065A (en) * 2019-05-31 2019-08-23 中国三冶集团有限公司 A kind of assembled environment protection architecture enclosure wall
CN110306869A (en) * 2019-06-29 2019-10-08 中国二十二冶集团有限公司 Multi-functional hedgerow enclosing and preparation method thereof
CN113958191A (en) * 2021-10-26 2022-01-21 国家电网有限公司 Assembled enclosure wall structure
CN116044245A (en) * 2022-12-02 2023-05-02 国网江苏省电力有限公司连云港供电分公司 Prefabricated enclosing wall capping and construction method for power substation

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109236033A (en) * 2018-09-14 2019-01-18 拓暄建设科技有限公司 A kind of building prefabrication Assembled enclosing wall and its production technology
CN109869044A (en) * 2019-03-28 2019-06-11 中国建筑西北设计研究院有限公司 A kind of modularization dismounting enclosure wall
CN109989413A (en) * 2019-04-18 2019-07-09 中国建筑西北设计研究院有限公司 The spliced basis of power station equipment
CN110159065A (en) * 2019-05-31 2019-08-23 中国三冶集团有限公司 A kind of assembled environment protection architecture enclosure wall
CN110159065B (en) * 2019-05-31 2024-09-10 中国三冶集团有限公司 Assembled environmental protection building enclosure
CN110306869A (en) * 2019-06-29 2019-10-08 中国二十二冶集团有限公司 Multi-functional hedgerow enclosing and preparation method thereof
CN113958191A (en) * 2021-10-26 2022-01-21 国家电网有限公司 Assembled enclosure wall structure
CN116044245A (en) * 2022-12-02 2023-05-02 国网江苏省电力有限公司连云港供电分公司 Prefabricated enclosing wall capping and construction method for power substation
CN116044245B (en) * 2022-12-02 2024-01-05 国网江苏省电力有限公司连云港供电分公司 Prefabricated enclosing wall capping and construction method for power substation

Similar Documents

Publication Publication Date Title
CN206844815U (en) A kind of transformer station's Assembled enclosing wall
CN201137234Y (en) Building block brick and its splicing structure
PH12014501858A1 (en) Preformed formwork for forming concrete floor slab for a height adjustable shipping container building structure
CN201172916Y (en) Reinforcement trough split head of concrete products for reinforced concrete slab
CN203701387U (en) Floor slab structure with embedded heat preservation cavities
CN209760787U (en) post-cast strip supporting structure capable of being used in turnover mode
CN203129162U (en) Split powder storing tank foundation
CN203530998U (en) Precast independent foundation
CN203669091U (en) Novel installation structure of building and house with same used
CN103498512B (en) A kind of assembled architecture wall beam stablizes syndeton
CN203729492U (en) Light thermal-insulation net rack board
CN202559656U (en) Stamping steel board brick for paving industrial terrace
CN204456559U (en) Laminated tile curtain wall structure unit based on full cylindrical tile
CN201817916U (en) Stone-carving tenon structure
CN206220116U (en) Factory building upright post basic
CN102002980B (en) Stone carving tenon structure and method for installing antiqued Hui-style dolmen applying tenon structure
CN221031051U (en) Waterproof foundation structure of cooling tower
CN206046267U (en) A kind of wet electrical dust precipitator anode module support
CN204626964U (en) Concreting leak-proof device
CN203846405U (en) Bridge construction cast-in-place template
CN211499323U (en) Landscape wall structure
CN211775108U (en) Prefabricated building site gate stand
CN202248774U (en) Fixing device for waterstone dividing strip
CN215594706U (en) Regional intergral template fixed establishment of eminence structure link plate disappearance
CN106639069A (en) EPS module frame connecting bridge

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder

Address after: No. 3120, Dalian Road, Jinfeng District, Yinchuan, the Ningxia Hui Autonomous Region

Co-patentee after: Hebei Province Power Surveying Design & Research Institute

Patentee after: The Ningxia Hui Autonomous Region Electric Power Design Institute Co., Ltd.

Address before: No. 3120, Dalian Road, Jinfeng District, Yinchuan, the Ningxia Hui Autonomous Region

Co-patentee before: Hebei Province Power Surveying Design & Research Institute

Patentee before: Ningxia Hui Autonomous Region Electric Power Design Institute

CP01 Change in the name or title of a patent holder