Nothing Special   »   [go: up one dir, main page]

CN205576940U - Compound retaining structure of friction pile that pile bolck is connected entirely - Google Patents

Compound retaining structure of friction pile that pile bolck is connected entirely Download PDF

Info

Publication number
CN205576940U
CN205576940U CN201620278187.6U CN201620278187U CN205576940U CN 205576940 U CN205576940 U CN 205576940U CN 201620278187 U CN201620278187 U CN 201620278187U CN 205576940 U CN205576940 U CN 205576940U
Authority
CN
China
Prior art keywords
pile
friction
row
friction pile
landslide
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620278187.6U
Other languages
Chinese (zh)
Inventor
胡春林
刘竞宇
吴彪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuhan University of Technology WUT
Original Assignee
Wuhan University of Technology WUT
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuhan University of Technology WUT filed Critical Wuhan University of Technology WUT
Priority to CN201620278187.6U priority Critical patent/CN205576940U/en
Application granted granted Critical
Publication of CN205576940U publication Critical patent/CN205576940U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Abstract

The utility model relates to a compound retaining structure of friction pile that pile bolck is connected entirely, including setting up 4 rows of friction piles on the landslide, the 4 rows of friction piles are taken the extending direction interval and are laid along the landslide is smooth, first, two rows of friction piles are the slim hole bored concrete pile, and third, four rows of friction piles just are total length formula friction pile for major diameter drilling bored concrete pile, the first row of friction pile and second row friction pile pass through reinforced concrete cover connection, the third is arranged the friction pile and is arranged the friction pile and pass through the connection of second guan liang through first guanliang connection, fourth, and first guanliang and second guanliang form pile bolck connection structure entirely through even roof beam connection. The utility model discloses bear landslide thrust ability reinforce, the specially adapted has had the great type landslide of local obvious sliding deformation, can in time stablize the dangerous situation to satisfy the requirement of consolidating the landslide.

Description

A kind of the full friction pile connected in top is combined retaining structure
Technical field
This utility model belongs to landslide control engineering field, is specifically related to a kind of the full friction pile connected in top and is combined retaining structure.
Background technology
Through engineering practice for many years and theoretical research, the various aspects at landslide control all achieve great success both at home and abroad, its In gear antiskid structure development and application the rapidest.Lose when measures such as cutting slope, off-load, slip casting, draining is not enough to solve side slope During steady problem, using friction pile retaining structure is the relatively effective engineering measure generally acknowledged both at home and abroad.Engineering practice shows, antiskid Stake can solve some more difficult engineering problems rapidly, safely, economically, and therefore development is very fast.At China's landslide control engineering In, using is at most most widely single antiskid post, but, for relatively large landslide engineering, Single row pillars is in stress It is unable to reach engine request.Therefore, in order to improve the anti-slide performance of friction pile, generally use double friction pile.Double friction pile Retaining structure, compared with other retaining structures, has the advantages such as rigidity is big, the friendship of good stability, bearing capacity is high, stress condition is good. But the relatively large landslide of sliding deformation obvious to existing local, double friction pile undertakes the ability of Thrust of Landslide, can not meet Reinforcement criteria, it is impossible to stablize dangerous situation.
Utility model content
Technical problem to be solved in the utility model is to provide a kind of the full friction pile connected in top and is combined retaining structure, this gear It is strong that structure undertakes Thrust of Landslide ability, is particularly well-suited to the relatively large landslide of the obvious sliding deformation in existing local, can stablize in time Dangerous situation, can meet again the reinforcement criteria on landslide.
This utility model be the technical scheme is that a kind of the full friction pile connected in top is combined retaining structure, including being arranged on 4 row's friction piles on landslide, 4 row's friction piles are laid along landslide-slip zone bearing of trend interval;First and second row's friction pile be little directly Footpath cast-in-situ bored pile, third and fourth row's friction pile is large diameter bored pile, and is total length formula friction pile;
First and second row's friction pile is connected by reinforced concrete cover plate, and the 3rd row's friction pile is connected by the first Guan Liang, the 4th row Friction pile is connected by the second Guan Liang, and the first Guan Liang and the second Guan Liang is connected by coupling beam, forms the full attachment structure in stake top.
Further scheme is, the diameter of described large diameter bored pile is more than 600mm, the coagulation of its pile body longitudinal reinforcement Protective soil layer thickness is not less than 50mm, and the diameter of described pile body longitudinal reinforcement is more than 16mm;In same large diameter bored pile Distance between pile body longitudinal reinforcement and pile body longitudinal reinforcement is between 120~250mm;The stirrup of described large diameter bored pile Diameter is more than 8mm, is smaller than 200mm in same large diameter bored pile between stirrup and stirrup.
Further scheme is, the array pitch between the 3rd row's friction pile and the 4th row's friction pile is 2d~5d, and wherein d is big straight The diameter of footpath cast-in-situ bored pile.
Further scheme is, described large diameter bored pile socket length is long not less than 1/4~1/3.
Further scheme is, in the 3rd row's friction pile, the spacing of the centrage of adjacent large diameter bored pile is 5-10m.
Further scheme is, in the 4th row's friction pile, the spacing of the centrage of adjacent large diameter bored pile is 5-10m.
Further scheme is, described reinforced concrete cover plate, the first Guan Liang, coupling beam, the second Guan Liang top concordant.
Further scheme is, the main muscle of coupling beam and the 3rd row's friction pile, the pile body longitudinal reinforcement welding of the 4th row's friction pile.
Local being had to the relatively large landslide of obvious sliding deformation, early stage, in order to stablize dangerous situation in time, first lays two row's minor diameters Two row hole drilling bored concrete pile drawknots are anchored by cast-in-situ bored pile by reinforced concrete cover plate;Later stage is steady for the safety ensureing landslide Fixed, lay two row's large diameter bored piles along slide strips bearing of trend interval, and often row's large diameter bored pile is passed through Guan Liang Connect, then by coupling beam, 2 rows are preced with the anchoring of beam drawknot;4 row's friction piles are compounded to form an organic whole, and shared comes down Thrust.4 row's friction piles are laid in the middle front part of antiskid section.
The beneficial effects of the utility model are:
Use twice double-row pile retaining structure, form a compound organic whole, improve entirety and undertake the ability of Thrust of Landslide, Meet the reinforcement criteria on landslide, can be suitably used for the relatively large landslide of the obvious sliding deformation in existing local, stablize dangerous situation, it is ensured that life Property safety.
Accompanying drawing explanation
Fig. 1 is the structural representation that the friction pile that this utility model stake top connects entirely is combined retaining structure;
Fig. 2 is the attachment structure schematic diagram of first row friction pile and second row friction pile;
Fig. 3 is the attachment structure schematic diagram of first row friction pile;
Fig. 4 is the attachment structure schematic diagram of second row friction pile;
Fig. 5 is the 3rd row's friction pile and the attachment structure schematic diagram of the 4th row's friction pile;
Fig. 6 is the attachment structure schematic diagram of the 3rd row's friction pile;
Fig. 7 is the attachment structure schematic diagram of the 4th row's friction pile.
In figure: 1, first row friction pile, 2, second row friction pile, the 3, the 3rd row's friction pile, the 4, the 4th row's friction pile, 5, First Guan Liang, the 6, second Guan Liang, 7, coupling beam, 8, reinforced concrete cover plate, 9, slide surface, 10, civil construction, 11, Landslide Deformation body.
Detailed description of the invention
Further illustrate embodiment of the present utility model below in conjunction with the accompanying drawings.
Seeing Fig. 1, landslide includes slide surface 9 and Landslide Deformation body 11, sometimes also has resident on Landslide Deformation body 11 and build Build 10.
Seeing Fig. 1-Fig. 7, a kind of the full friction pile connected in top is combined retaining structure, including the 4 row's antiskids being arranged on landslide Stake (first row friction pile 1, second row friction pile the 2, the 3rd row's friction pile the 3, the 4th row's friction pile 4), 4 row's friction piles are along sliding Hill wash band bearing of trend interval is laid;First row friction pile 1 and second row friction pile 2 are small-diameter cast-in-place bored pile, the 3rd row Friction pile 3 and the 4th row's friction pile 4 are large diameter bored pile, and all total length formula friction piles;
First row friction pile 1 and second row friction pile 2 are connected by reinforced concrete cover plate 8, and the 3rd row's friction pile 3 is by the One hat beam 5 connects, and the 4th row's friction pile 4 is connected by the second hat beam 6, and the first hat beam 5 and the second hat beam 6 are by coupling beam 7 Connecting, it is concordant that reinforced concrete cover plate 8, first is preced with beam 5, coupling beam 7, second is preced with the top of beam 6, and the first hat beam 5, even Beam 7, second is preced with beam 6 and is formed the full attachment structure in stake top.
In order to improve the intensity undertaking Thrust of Landslide ability and large diameter bored pile, the 3rd row's friction pile 3 and the 4th can be made The diameter of row's friction pile 4 is more than 600mm so that it is the thickness of concrete cover of pile body longitudinal reinforcement is not less than 50mm (i.e. pile body Distance outside longitudinal reinforcement and large diameter bored pile is not less than 50mm) so that it is the diameter of pile body longitudinal reinforcement is more than 16mm; Distance between same large diameter bored pile pile longitudinal reinforcement and pile body longitudinal reinforcement is between 120~250mm;Greatly The stirrup diameter of diameter bores bored concrete pile is more than 8mm, and in same large diameter bored pile, the spacing between stirrup and stirrup is little In 200mm.
In order to reach good anti-slippery effect, improve and undertake Thrust of Landslide ability, make the 3rd row's friction pile 3 and the 4th row's friction pile Spacing between 4 is 2d~5d, and wherein d is the diameter of large diameter bored pile.Make the embedding rock of large diameter bored pile the least In 1/4~1/3 long (should be long not less than 1/3 for soil layer or soft rock stratum, for completely, harder middle weathered rock formation Should be long not less than 1/4);The 3rd row's friction pile 3 is made to neutralize the center of adjacent large diameter bored pile in the 4th row's friction pile 4 The spacing of line is 5-10m;Make the main muscle of coupling beam 7 and the pile body longitudinal reinforcement welding of the 3rd row's friction pile the 3, the 4th row's friction pile 4.
The pile concrete of 4 row's friction piles can use normal concrete, and its intensity preferably uses C25 or C30;Large diameter borehole irrigates Stake longitudinal reinforcement should use the Ribbed Bar of more than I grade;Small-diameter cast-in-place bored pile with the common shaped steel of hot rolling as principal rod, Consolidation grouting between two row's small-diameter cast-in-place bored pile stakes.
During construction, it is necessary to ensure that friction pile stake is long not less than designing pile length;Campshed takes to be spaced the sequence of construction of pile, concrete Can construct after being poured 24 hours adjacent stake;For guaranteeing the quality of underwater concrete, advise during conductive pipe concrete perfusion Use concrete pump conveying or use other effective measures;The groundwater increment of concrete should be grasped by the designed elevation on stake top during construction, It is allowed to both ensure to cut concrete quality after the laitance layer of stake top, is unlikely to again chisel and goes too many and cause waste, surpassing of stake top concrete Filling height is 1 times of stake footpath;During Guan Liang construction, stake top laitance, weak concrete and broken segment should be removed;Monitoring should Synchronization carry out with construction, when dangerous situation occurs in landslide, and jeopardize workmen safe time, should notify that personnel withdraw in time.
In this utility model, a diameter of 100-300mm of described small-diameter cast-in-place bored pile.
Twice employing double friction pile retaining structure before and after this utility model, the ability making entirety undertake Thrust of Landslide obtains carrying the most greatly Height, it is thus possible to the deformation on effective suppression landslide, and can effectively solve the hypodynamic problem of Single row pillars antiskid.

Claims (8)

1. the friction pile that a stake top connects entirely is combined retaining structure, it is characterised in that: include the 4 row's antiskids being arranged on landslide Stake, 4 row's friction piles are laid along landslide-slip zone bearing of trend interval;First and second row's friction pile is small-diameter cast-in-place bored pile, the Three, four row's friction piles are large diameter bored pile, and are total length formula friction pile;
First and second row's friction pile is connected by reinforced concrete cover plate;3rd row's friction pile is connected by the first Guan Liang, the 4th row Friction pile is connected by the second Guan Liang, and the first Guan Liang and the second Guan Liang is connected by coupling beam, forms the full attachment structure in stake top.
The friction pile that stake top the most according to claim 1 connects entirely is combined retaining structure, it is characterised in that: described major diameter The diameter of cast-in-situ bored pile is more than 600mm, and the thickness of concrete cover of its pile body longitudinal reinforcement is not less than 50mm, described pile body The diameter of longitudinal reinforcement is more than 16mm;Between same large diameter bored pile pile longitudinal reinforcement and pile body longitudinal reinforcement Distance is between 120~250mm;The stirrup diameter of described large diameter bored pile is more than 8mm, and same large diameter borehole fills Note stake is smaller than 200mm between stirrup and stirrup.
The friction pile that stake top the most according to claim 1 and 2 connects entirely is combined retaining structure, it is characterised in that: the 3rd row Spacing between friction pile and the 4th row's friction pile is 2d~5d, and wherein d is the diameter of large diameter bored pile.
The friction pile that stake top the most according to claim 3 connects entirely is combined retaining structure, it is characterised in that: described major diameter The socket length of cast-in-situ bored pile is long not less than 1/4~1/3.
The friction pile that stake top the most according to claim 3 connects entirely is combined retaining structure, it is characterised in that: the 3rd row's antiskid In Zhuan, the spacing of the centrage of two adjacent studs is 5-10m.
The friction pile that stake top the most according to claim 3 connects entirely is combined retaining structure, it is characterised in that: the 4th row's antiskid In Zhuan, the spacing of the centrage of two adjacent studs is 5-10m.
The friction pile that stake top the most according to claim 1 connects entirely is combined retaining structure, it is characterised in that: described reinforcing bar mixes Solidifying earth mulch plate, the first Guan Liang, coupling beam, the second Guan Liang top concordant.
The friction pile that stake top the most according to claim 1 connects entirely is combined retaining structure, it is characterised in that: the main muscle of coupling beam Weld with the 3rd row's friction pile, the pile body longitudinal reinforcement of the 4th row's friction pile.
CN201620278187.6U 2016-04-06 2016-04-06 Compound retaining structure of friction pile that pile bolck is connected entirely Expired - Fee Related CN205576940U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620278187.6U CN205576940U (en) 2016-04-06 2016-04-06 Compound retaining structure of friction pile that pile bolck is connected entirely

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620278187.6U CN205576940U (en) 2016-04-06 2016-04-06 Compound retaining structure of friction pile that pile bolck is connected entirely

Publications (1)

Publication Number Publication Date
CN205576940U true CN205576940U (en) 2016-09-14

Family

ID=56865188

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620278187.6U Expired - Fee Related CN205576940U (en) 2016-04-06 2016-04-06 Compound retaining structure of friction pile that pile bolck is connected entirely

Country Status (1)

Country Link
CN (1) CN205576940U (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107191198A (en) * 2017-04-05 2017-09-22 中铁二十二局哈尔滨铁路建设集团有限责任公司 The retaining structure and method of a kind of horizontal creep of suppression tunnel light and shade hole intersection slopes
CN107288126A (en) * 2017-08-12 2017-10-24 湖南科技大学 A kind of drill-pouring combination anti-slid pile and its construction method
CN107988894A (en) * 2017-08-31 2018-05-04 中铁二院工程集团有限责任公司 The concrete buttress structure for preventing high gradient slope bridge pier from deviating
CN108265732A (en) * 2018-03-21 2018-07-10 中铁第四勘察设计院集团有限公司 Antiskid built pile retaining structure and its construction method
CN109653221A (en) * 2019-02-21 2019-04-19 中水北方勘测设计研究有限责任公司 For high slope, the retaining structure in narrow location
CN110055981A (en) * 2019-04-18 2019-07-26 中铁第四勘察设计院集团有限公司 Supporting and retaining system unit, retaining structure and the construction method on landslide
CN111206604A (en) * 2020-03-25 2020-05-29 贵州星隆迪岩土工程有限公司 Circular parallel anti-slide pile and construction method

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107191198A (en) * 2017-04-05 2017-09-22 中铁二十二局哈尔滨铁路建设集团有限责任公司 The retaining structure and method of a kind of horizontal creep of suppression tunnel light and shade hole intersection slopes
CN107288126A (en) * 2017-08-12 2017-10-24 湖南科技大学 A kind of drill-pouring combination anti-slid pile and its construction method
CN107988894A (en) * 2017-08-31 2018-05-04 中铁二院工程集团有限责任公司 The concrete buttress structure for preventing high gradient slope bridge pier from deviating
CN107988894B (en) * 2017-08-31 2023-07-18 中铁二院工程集团有限责任公司 Concrete buttress structure for preventing high-steep slope pier from shifting
CN108265732A (en) * 2018-03-21 2018-07-10 中铁第四勘察设计院集团有限公司 Antiskid built pile retaining structure and its construction method
CN109653221A (en) * 2019-02-21 2019-04-19 中水北方勘测设计研究有限责任公司 For high slope, the retaining structure in narrow location
CN110055981A (en) * 2019-04-18 2019-07-26 中铁第四勘察设计院集团有限公司 Supporting and retaining system unit, retaining structure and the construction method on landslide
CN111206604A (en) * 2020-03-25 2020-05-29 贵州星隆迪岩土工程有限公司 Circular parallel anti-slide pile and construction method

Similar Documents

Publication Publication Date Title
CN205576940U (en) Compound retaining structure of friction pile that pile bolck is connected entirely
CN104775428B (en) Compound-type pre-stvessed anchor cable structure and construction method thereof
CN104533446B (en) Construction method and its structure that a kind of big cross section Support System in Soft Rock Tunnels bilayer pre- Geological disaster prevention of preliminary bracing occurs
CN102518135B (en) Horizontal jet grouting soil anchor and castinplace pile Composite Foundation Pit supporting construction engineering method
CN105696427B (en) The construction method and its road structure of a kind of consolidation process newly built railway karst foundation
CN105350584B (en) A kind of construction method of anti-float anchor rod
CN107503257B (en) One kind being close to mountain high-filled subgrade stabilization and Deformation control structure and construction method
CN103410161B (en) Oblique control slip casting steel anchor tube framework and construction method thereof
CN103321244B (en) Sand foundation existing building sets up the construction method of basement
CN105041325A (en) Construction method of high-tension water-rich extra-large-section weak breccia tunnel
CN204703160U (en) Two anchoring section prestressed anchor Cable Structure
CN104790393A (en) Double-anchoring-section prestress anchor cable structure and constructing method thereof
CN103147442A (en) Ultra-deep foundation pit press-grouting pile and prestressed anchor combined supporting construction method
CN204401385U (en) A kind of road structure processing Deep Thick Soft Ground karst foundation
CN207109475U (en) It is close to mountain high-filled subgrade stabilization and Deformation control structure
CN105298516A (en) Combined supporting structure of steel pipe pile steel-bar-embedded tunnel composite lining used for soft foundation
CN105696602A (en) Composite pile-anchor supporting method and structure for deepening excavation
CN104499479A (en) Dig-hole pile construction method based on penetration of sand gravel backfilling layer
CN203334300U (en) Root pile supporting structure
CN106869969A (en) A kind of excavation supporting construction method of soft rock large section tunnel
CN109183809A (en) A kind of construction method of Muddy Bottoms clay deep-foundation pit engineering composite support support replacement
CN104532714B (en) Roadbed structure for treating deep soft soil karst foundation
CN201538975U (en) Seepage-proofing joint of underground continuous wall
CN101575859B (en) Anti-seepage joint of underground continuous walls and construction method thereof
CN205225280U (en) A combined supporting structure that is used for steel -pipe pile bar planting tunnel composite lining of soft base

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160914

Termination date: 20180406

CF01 Termination of patent right due to non-payment of annual fee