CN204300679U - LNG mono-pump two-shipper filling station control system - Google Patents

LNG mono-pump two-shipper filling station control system Download PDF

Info

Publication number
CN204300679U
CN204300679U CN201420631094.8U CN201420631094U CN204300679U CN 204300679 U CN204300679 U CN 204300679U CN 201420631094 U CN201420631094 U CN 201420631094U CN 204300679 U CN204300679 U CN 204300679U
Authority
CN
China
Prior art keywords
lng
pneumatic valve
pump
valve
shipper
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN201420631094.8U
Other languages
Chinese (zh)
Inventor
张绍军
赵会杰
袁现化
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhengzhou Langrun Intelligent Equipment Co ltd
Original Assignee
Zhengzhou Lang Run Oil Equipment Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhengzhou Lang Run Oil Equipment Co Ltd filed Critical Zhengzhou Lang Run Oil Equipment Co Ltd
Priority to CN201420631094.8U priority Critical patent/CN204300679U/en
Application granted granted Critical
Publication of CN204300679U publication Critical patent/CN204300679U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Filling Or Discharging Of Gas Storage Vessels (AREA)

Abstract

A kind of LNG mono-pump two-shipper filling station control system, comprises the pneumatic valve being arranged on each line connection, switch, LNG filling device, upper-position unit and acoustic-optic alarm that the limit switch be arranged on pneumatic valve, the pressure transducer be arranged in LNG storage tank, the controller detecting the concurrent number of delivering letters, the frequency variator of control LNG immersed pump pressure, LNG annotate.The utility model utilizes PLC and ForceControl configuration software to combine, overcome the problem that the mono-pump two-shipper of LNG can not be annotated when unloading simultaneously, pneumatic valve is because machinery or valve is freezing etc. that valve that reason causes is failure to actuate causes system to occur accident, because the operator that complex process causes are difficult to grasp operating method.Therefore, the utility model improves manufacturing efficiency, and operator can be helped to understand rapidly system process operation, understands in time and processes the fault of valve, having extraordinary economic value and use value.

Description

LNG mono-pump two-shipper filling station control system
Technical field
The utility model relates to LNG filling station filing provision, is specifically related to a kind of LNG mono-pump two-shipper filling station control system.
Background technique
The technological operation of LNG filling station comprises safe standby state, self pressurized vaporizer is annotated simultaneously, and immersed pump unloads liquid and annotates simultaneously, and immersed pump is only annotated, tank car gas phase and station inner storage tank gaseous pressure balance, tank car, manually from supercharging, stands inner storage tank manually from supercharging, and supercharging forced by tank car, inner storage tank of standing forces supercharging, the BOG of middle storage tank of unloading reclaims, and inner storage tank of stand falls liquid, the BOG recovery of storage tank in filling.LNG filling station control system utilizes controller by integrated various instrument valve equipment, achieves the object of LNG filling station monitoring.But, the problem that the mono-pump two-shipper of existing LNG mono-pump two-shipper filling station control system LNG can not be annotated when unloading simultaneously, pneumatic valve is because machinery or valve is freezing etc. that valve that reason causes is failure to actuate causes system to occur accident, because the operator that complex process causes are difficult to grasp operating method.
Model utility content
The technical problems to be solved in the utility model is to provide a kind of LNG mono-pump two-shipper filling station control system, realizes can annotating while unloading, automatically can detect the fault that pneumatic valve switch puts in place, and simple to operate.
The technical solution of the utility model is: a kind of LNG mono-pump two-shipper filling station control system, comprises the pneumatic valve being arranged on each line connection, the limit switch be arranged on pneumatic valve, the pressure transducer be arranged in LNG storage tank, the controller detecting the concurrent number of delivering letters, the frequency variator of control LNG immersed pump outlet pressure, the switch of LNG filling, LNG filling device, upper-position unit and acoustic-optic alarm.
Described pneumatic valve comprises the feed flow pneumatic valve of the enterprising hydraulic pneumatic valve of LNG storage tank and lower feed liquor pneumatic valve, LNG filling device.
Described pneumatic valve front end is provided with pilot valve, and pilot valve is two-bit triplet pneumatic valve.
Described controller is PLC.
The utility model utilizes PLC and ForceControl configuration software to combine, overcome the problem that the mono-pump two-shipper of LNG can not be annotated when unloading simultaneously, pneumatic valve is because machinery or valve is freezing etc. that valve that reason causes is failure to actuate causes system to occur accident, because the operator that complex process causes are difficult to grasp operating method.Therefore, the utility model improves manufacturing efficiency, and operator can be helped to understand rapidly system process operation, understands in time and processes the fault of valve, having extraordinary economic value and use value.
Accompanying drawing explanation
Fig. 1 is theory diagram of the present utility model.
Fig. 2 is LNG of the present utility model mono-pump two-shipper filling station structural representation.
Embodiment
In order to be illustrated more clearly in the technological scheme of the utility model embodiment, introduce in detail below in conjunction with accompanying drawing.
A kind of LNG mono-pump two-shipper filling station control system, as shown in Figure 1, the pneumatic valve being arranged on each line connection, the limit switch be arranged on pneumatic valve, the pressure transducer be arranged in LNG storage tank, the controller detecting the concurrent number of delivering letters, the frequency variator of control LNG immersed pump pressure, upper-position unit and acoustic-optic alarm is comprised.Controller is PLC.
LNG mono-pump two-shipper filling station comprises LNG tank car 1, LNG storage tank 2, LNG immersed pump 3, a LNG filling device 4, the 2nd LNG filling device 5, vaporizer 6, heater 7 and flame trap 8.LNG tank car 1 is provided with liquid phase mouth, gas phase mouth and boost port.LNG tank car 1 is provided with liquid phase mouth, and liquid phase mouth is connected with the first liquid phase pipeline 13, and first liquid phase pipeline 13 the other end is connected with the liquid entering hole of LNG immersed pump 3.Motor in LNG immersed pump 3 can by LNG Liquid transfer to LNG storage tank 2, a LNG filling device 4 or the 2nd LNG filling device 5.LNG storage tank 2 is provided with liquid entering hole 202 and lower liquid entering hole 201.When unloading liquid, LNG liquid can be sent into the lower liquid entering hole 201 of LNG storage tank 2 by the motor in LNG immersed pump 3 by lower water influent pipeline 15, sent into the upper liquid entering hole 202 of LNG storage tank 2 by upper water influent pipeline 14.Lower water influent pipeline 15 is provided with lower feed liquor pneumatic valve 9, and upper water influent pipeline 14 is provided with enterprising hydraulic pneumatic valve 10.LNG liquid can be sent into a LNG filling device 4 by the first charging line 16 by the motor in LNG immersed pump 3, sends into the 2nd LNG filling device 5 by the second charging line 17.First charging line 16 is provided with feed flow pneumatic valve 11, second charging line 17 and is provided with feed flow pneumatic valve 12.LNG liquid in LNG storage tank 2 can enter the liquid entering hole of LNG immersed pump 3 through second liquid phase pipeline 18 from lower liquid entering hole 203.
The utility model can realize when unloading liquid to LNG storage tank 2, and when there being LNG filling automobile to need filling, this system stops unloading liquid to LNG storage tank 2, and is switched to LNG filling automobile liquid feeding; When not having LNG filling automobile to need filling, system switches back more again unloads liquid status to LNG storage tank 2.
Concrete electrically realization flow is: when LNG immersed pump 3 unloads liquid to LNG storage tank 2, PLC opens lower feed liquor pneumatic valve 9; Close the feed flow pneumatic valve 11 of a LNG filling device 4 and the feed flow pneumatic valve 12 of the 2nd LNG filling device 5, time delay 2s; The exit pressure levels that frequency variator arranges LNG immersed pump 3 is 1.2Mpa, and start LNG immersed pump 3, then LNG liquid flows to LNG storage tank 2 from LNG tank car 1 through the first liquid phase pipeline 13, LNG immersed pump 3, upper water influent pipeline 14 and lower water influent pipeline 15, starts to unload liquid; Control storage tank gaseous pressure unloading in liquid process, PLC is by gathering the signal of the pressure transmitter be arranged in LNG storage tank 2 gas phase, as pressure >0.6Mpa in LNG storage tank 2, PLC opens enterprising hydraulic pneumatic valve 10, spray step-down; As pressure < 0.4Mpa in LNG storage tank 2, PLC opens lower feed liquor pneumatic valve 9, and storage tank boosts.
When there being automobile to need filling, the filling switch of the one LNG filling device 4 or the 2nd LNG filling device 5 cuts out, PLC receives the filling switch shutdown signal of a LNG filling device 4 or the 2nd LNG filling device 5, opens the feed flow pneumatic valve of corresponding LNG filling device, time delay 2s; Close enterprising hydraulic pneumatic valve 10 and lower feed liquor pneumatic valve 9, PLC gives a LNG filling device 4 or the 2nd LNG filling device 5 feedback signal; The exit pressure levels that frequency variator arranges LNG immersed pump 3 is 2.0Mpa, then LNG liquid flows to a LNG filling device 4 or the 2nd LNG filling device 5 from LNG tank car 1 through the first liquid phase pipeline 13, LNG immersed pump 3, first charging line 16 or the second charging line 17.After filling completes, the filling switch opens of the one LNG filling device 4 or the 2nd LNG filling device 5, according to the force value that pressure transmitter will detect, open enterprising hydraulic pneumatic valve 10 and lower feed liquor pneumatic valve 9, close the feed flow pneumatic valve 11 of a LNG filling device 4 and the feed flow pneumatic valve 12 of the 2nd LNG filling device 5, time delay 2s; The exit pressure levels that frequency variator arranges LNG immersed pump 3 is 1.2Mpa, then LNG liquid flows to LNG storage tank 2 from LNG tank car 1 through the first liquid phase pipeline 13, LNG immersed pump 3, upper water influent pipeline 14 and lower water influent pipeline 15.So move in circles until unload liquid and complete.
The utility model can realize checking whether pneumatic valve normally opens closedown, prevent pneumatic valve because machinery or valve is freezing etc. that valve that reason causes is failure to actuate causes system to occur accident, when there is pneumatic valve valve and being failure to actuate, alert notice operator trouble shooting pneumatic valve.Concrete electrically realization flow is: pneumatic valve front end is provided with pilot valve, and pilot valve is two-bit triplet pneumatic valve.Pilot valve is controlled by PLC output point.Pilot valve coil obtains electric, and pneumatic valve is opened, pilot valve dead electricity, and pneumatic valve cuts out.When pneumatic valve is in closed condition, PLC is to pneumatic valve opening signal, and what in 4s, PLC did not receive limit switch reaches a signal, then the valve of pneumatic valve opens fault; When pneumatic valve is in open mode, PLC is to pneumatic valve shutdown signal, the reaching a signal and should disappear of limit switch of this pneumatic valve in 2s under normal circumstances, but what after having crossed 2s, PLC did not receive limit switch reaches a disappearance of signal, then the valve of pneumatic valve closes fault.After breaking down, signal is conveyed into upper-position unit by PLC, and upper-position unit reminds operator to break down by power control monitoring software, and makes acoustic-optic alarm send acoustooptic alarm, and operator understand and process failsafe valve.
Be provided with ForceControl configuration software in upper-position unit, ForceControl configuration software can show the flow chart circuit of LNG mono-pump two-shipper filling station.Circuit in flow chart does not have mobility under normal circumstances, can the mobility of configuration line in ForceControl configuration software.When the curve in corresponding flow chart after the corresponding flow process button in push picture will become mobility, program opens the valve on mobility curve automatically according to logic, makes master control technique picture more lively like this, be more convenient for operator's study and operation.
The above; be only the utility model preferably embodiment; but protection domain of the present utility model is not limited thereto; anyly be familiar with those skilled in the art in the technical scope that the utility model discloses; the change that can expect easily or replacement, all should be encompassed within protection domain of the present utility model.Therefore, protection domain of the present utility model should be as the criterion with the protection domain of claims.

Claims (4)

1. LNG mono-pump two-shipper filling station control system, is characterized in that: comprise the pneumatic valve being arranged on each line connection, the limit switch be arranged on pneumatic valve, the pressure transducer be arranged in LNG storage tank, the controller detecting the concurrent number of delivering letters, the frequency variator of control LNG immersed pump outlet pressure, the switch of LNG filling, LNG filling device, upper-position unit and acoustic-optic alarm.
2. LNG according to claim 1 mono-pump two-shipper filling station control system, is characterized in that, described pneumatic valve comprises the feed flow pneumatic valve of the enterprising hydraulic pneumatic valve of LNG storage tank and lower feed liquor pneumatic valve, LNG filling device.
3. LNG according to claim 1 mono-pump two-shipper filling station control system, is characterized in that, described pneumatic valve front end is provided with pilot valve, and pilot valve is two-bit triplet pneumatic valve.
4. LNG according to claim 1 mono-pump two-shipper filling station control system, is characterized in that, described controller is PLC.
CN201420631094.8U 2014-10-29 2014-10-29 LNG mono-pump two-shipper filling station control system Expired - Lifetime CN204300679U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420631094.8U CN204300679U (en) 2014-10-29 2014-10-29 LNG mono-pump two-shipper filling station control system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420631094.8U CN204300679U (en) 2014-10-29 2014-10-29 LNG mono-pump two-shipper filling station control system

Publications (1)

Publication Number Publication Date
CN204300679U true CN204300679U (en) 2015-04-29

Family

ID=53106217

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420631094.8U Expired - Lifetime CN204300679U (en) 2014-10-29 2014-10-29 LNG mono-pump two-shipper filling station control system

Country Status (1)

Country Link
CN (1) CN204300679U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108147356A (en) * 2017-12-18 2018-06-12 安徽省锐凌计量器制造有限公司 Portable liquid filling machine's trouble self-checking device
CN110425418A (en) * 2019-07-31 2019-11-08 郑州朗润智能装备股份有限公司 Box LNG aerating skid-mounted device process system and its working method

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108147356A (en) * 2017-12-18 2018-06-12 安徽省锐凌计量器制造有限公司 Portable liquid filling machine's trouble self-checking device
CN110425418A (en) * 2019-07-31 2019-11-08 郑州朗润智能装备股份有限公司 Box LNG aerating skid-mounted device process system and its working method
CN110425418B (en) * 2019-07-31 2021-06-04 郑州朗润智能装备股份有限公司 Box type LNG (liquefied Natural gas) filling skid-mounted device process system and working method thereof

Similar Documents

Publication Publication Date Title
WO2011137853A1 (en) System and method for supplying hydrogen and hydrogen fuel cell system
CN204300679U (en) LNG mono-pump two-shipper filling station control system
CN206903849U (en) Automatic pump pressurizer
CN213235288U (en) Oil pressure maintaining system of low-pressure oil way of diesel engine
CN102591314B (en) Centralized oxygen supply system and control method
CN207527295U (en) A kind of compressed air double loop automatic switching control equipment for tobacco shred production line
CN201513215U (en) Safe starting control device for underground transport truck
CN202533791U (en) Centralized oxygen supply system
CN203655589U (en) Control device for TRT auxiliary system pumping set
CN210950806U (en) Liquid tank field automatic feeding system based on DCS control
CN204875936U (en) Water supply system provides for oneself from opening emergency apparatus control system
CN103758350A (en) Air and electricity linkage device of full-automatic high-speed concrete spraying machine
CN201558430U (en) Flow balance self-controlling type foam proportioning device
CN206339442U (en) Hydraulic pressure intelligently loads detection means
CN110577201A (en) Intelligent phosphine generator system
CN206293967U (en) System architecture with two segments of direct-current power buses mutually in hot backup
CN210795774U (en) Intelligent phosphine generator system
CN202403875U (en) Automatic interlocking device for pressure control in pressure-resistant test for pressure container
CN202091167U (en) Electrical control safety system of sludge pump
CN202208120U (en) Horizontal ultrahigh pressure cold isostatic pressing system
CN203834575U (en) Gas top pressure fire-fighting water supply device
CN201807114U (en) Alternate foam storage and proportioning device
CN104563212A (en) Variable-frequency constant-pressure make-up water control system on basis of PI (Proportional-Integral) regulation
CN203384020U (en) Control device for mining water pumps
CN105288912A (en) Water injection device and water injection method used for fire fighting truck

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee
CP01 Change in the name or title of a patent holder

Address after: 450000, No. 12, building 1, No. 1, block 11, block 1, Gaoxin Road, hi tech, Henan, Zhengzhou

Patentee after: ZHENGZHOU LANGRUN INTELLIGENT EQUIPMENT CO.,LTD.

Address before: 450000, No. 12, building 1, No. 1, block 11, block 1, Gaoxin Road, hi tech, Henan, Zhengzhou

Patentee before: Zhengzhou Langrun Petroleum Equipment Co.,Ltd.

CX01 Expiry of patent term

Granted publication date: 20150429