CN112529446A - Engineering project cost risk management system - Google Patents
Engineering project cost risk management system Download PDFInfo
- Publication number
- CN112529446A CN112529446A CN202011511109.3A CN202011511109A CN112529446A CN 112529446 A CN112529446 A CN 112529446A CN 202011511109 A CN202011511109 A CN 202011511109A CN 112529446 A CN112529446 A CN 112529446A
- Authority
- CN
- China
- Prior art keywords
- module
- project
- cost
- risk
- information table
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000007726 management method Methods 0.000 claims abstract description 144
- 238000010276 construction Methods 0.000 claims abstract description 82
- 238000012502 risk assessment Methods 0.000 claims abstract description 53
- 238000007728 cost analysis Methods 0.000 claims abstract description 12
- 238000011156 evaluation Methods 0.000 claims description 22
- 238000004891 communication Methods 0.000 claims description 12
- 238000000034 method Methods 0.000 claims description 11
- 230000002159 abnormal effect Effects 0.000 claims description 10
- 238000012545 processing Methods 0.000 abstract description 3
- 238000004519 manufacturing process Methods 0.000 abstract 1
- 238000007689 inspection Methods 0.000 description 4
- 238000005070 sampling Methods 0.000 description 2
- 238000013459 approach Methods 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000010835 comparative analysis Methods 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000012954 risk control Methods 0.000 description 1
- 238000005728 strengthening Methods 0.000 description 1
- 238000012546 transfer Methods 0.000 description 1
Images
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0631—Resource planning, allocation, distributing or scheduling for enterprises or organisations
- G06Q10/06311—Scheduling, planning or task assignment for a person or group
- G06Q10/063114—Status monitoring or status determination for a person or group
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0635—Risk analysis of enterprise or organisation activities
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/10—Office automation; Time management
Landscapes
- Business, Economics & Management (AREA)
- Human Resources & Organizations (AREA)
- Engineering & Computer Science (AREA)
- Entrepreneurship & Innovation (AREA)
- Strategic Management (AREA)
- Economics (AREA)
- Tourism & Hospitality (AREA)
- Marketing (AREA)
- Operations Research (AREA)
- Quality & Reliability (AREA)
- Physics & Mathematics (AREA)
- General Business, Economics & Management (AREA)
- General Physics & Mathematics (AREA)
- Theoretical Computer Science (AREA)
- Game Theory and Decision Science (AREA)
- Development Economics (AREA)
- Educational Administration (AREA)
- Data Mining & Analysis (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The invention relates to a construction project cost risk management system, which comprises a management server, a project management terminal and a cost management terminal, wherein the project management terminal comprises a project management server and a project management server; the project management terminal comprises a budget loading module and an early warning loading module; the cost management terminal comprises a cost loading module, a material loading module and a personnel loading module; the management server comprises a cost analysis module, a material distribution module, a personnel distribution module, a cost budget module, a risk assessment module and a risk early warning module. The invention can carry out real-time risk assessment on the manufacturing cost, and when the engineering project has risks, the risk early warning module sends alarm information so as to carry out processing in time.
Description
Technical Field
The invention relates to the technical field of construction cost, in particular to a construction project cost risk management system.
Background
The construction cost refers to the construction price of a project, and refers to the total sum of all costs expected or actually required to complete the construction of a project. The data of the construction cost is huge, in addition, the components of the engineering project are various, the loss of the engineering construction is large, and the deviation between the budget cost and the actual cost often exists, so that the strengthening of the management of the construction cost is the key point of the risk control of the project management.
The existing engineering cost management is influenced by various factors such as materials, personnel, funds, environment, management and the like, the construction progress can not be completed according to a plan, in addition, the factors influencing the construction progress are various, the construction progress is difficult to find and analyze in time when the construction progress is abnormal, the engineering cost can not be dynamically managed, and the engineering project management risk is difficult to effectively control.
Disclosure of Invention
Aiming at the defects in the prior art, the invention aims to provide a project cost risk management system, which can dynamically manage project cost progress and carry out risk early warning when the project cost has risks so as to process in time.
The above object of the present invention is achieved by the following technical solutions:
a project cost risk management system comprises a management server, a project management terminal and a cost management terminal; the project management terminal and the cost management terminal are respectively in communication connection with the management server;
the project management terminal comprises a budget loading module and an early warning loading module; the budget loading module is used for receiving budget data and transmitting the budget data to a management server; the early warning loading module is used for receiving early warning data and transmitting the early warning data to the management server;
the cost management terminal comprises a cost loading module, a material loading module and a personnel loading module;
the cost loading module is used for receiving cost data and transmitting the cost data to the management server; the material loading module is used for receiving material data and transmitting the material data to the management server; the personnel loading module is used for receiving personnel data and transmitting the personnel data to the management server;
the management server comprises a construction cost analysis module, a material distribution module, a personnel distribution module, a cost budget module, a risk assessment module and a risk early warning module;
the construction cost analysis module receives the data sent by the construction cost loading module and generates a project construction cost information table;
the material distribution module receives the data sent by the material loading module and generates a material distribution information table;
the personnel loading module receives the data sent by the personnel loading module and generates a personnel distribution information table;
the cost budget module receives the data sent by the budget loading module and generates an engineering budget information table;
the construction cost analysis module, the material distribution module, the cost budget module and the personnel distribution module are respectively in communication connection with a risk assessment module, and the risk assessment module calls the engineering construction cost information table, the material distribution information table, the personnel distribution information table and the engineering budget information table, analyzes and processes the information to generate a risk assessment information table;
the early warning loading module is in communication connection with the risk early warning module, receives the loaded alarm threshold and sends the alarm threshold to the risk early warning module;
the management server further comprises a risk early warning adjusting module, and the risk early warning adjusting module calls a risk assessment information table to adjust the threshold value.
By adopting the scheme, the construction cost management terminal and the project management terminal establish the risk assessment information table through the management server, the system carries out real-time risk assessment on the project, when the data of the risk assessment information table exceeds the alarm threshold value, the risk assessment module sends the early warning instruction to the risk early warning module, the risk early warning module carries out early warning, the system is ensured to supervise the construction cost risk of the project in real time, corresponding data of abnormal risk assessment are found in time, the corresponding scheme is adjusted in time, and the management of the project is optimized.
The invention is further configured to: the management server further comprises a risk early warning adjusting module, the risk early warning adjusting module is in communication connection with the risk assessment module, and calls a risk assessment information table to adjust the early warning value.
By adopting the technical scheme, the risk early warning adjusting module calls the risk assessment information table to adjust the early warning value, the risk assessment information table can be dynamically monitored, the early warning value can be adjusted in time, and the management of engineering projects is optimized.
The invention is further configured to: the construction cost management terminal is further provided with a project progress loading module, the project management terminal is provided with a project progress query module, the management server is provided with a project progress analysis module, the project progress analysis module receives project progress data sent by the project progress loading module and generates a project progress information table, and the project progress query module is used for querying information of the project progress information table.
By adopting the technical scheme, the project progress data is input by the project progress loading module, the project progress information table is generated by the project progress analysis module, the project progress query module can query the project progress information table information, the progress condition of the project is known in real time, and data support is provided for the project completion of the project according to the plan.
The invention is further configured to: the management server is further provided with a notification module, the project management terminal is further provided with a project progress setting module, the project progress setting module transmits project progress preset value data and address book data of a constructor responsible person to the project progress analysis module, the notification module calls a project progress information table in real time to compare and evaluate the project progress, and when the project progress is lower than a preset value, the notification module sends a progress notification to the address book of the constructor responsible person.
By adopting the technical scheme, the project progress setting module sets project progress preset value data and the address book contact mode of the construction party responsible person, when the project progress is lower than the preset value, the notification module can send progress notification to the address book of the construction party responsible person, prompts the construction party responsible person to find the reason that the project progress does not reach the standard, and timely adjusts the project progress.
The invention is further configured to: the construction cost management terminal also comprises a construction cost information module, wherein the construction cost information module comprises construction cost names, contact ways and processed engineering project names.
By adopting the technical scheme, the relevant information of the construction workers is marked in the loading process of the project name of the engineering project, the construction cost data, the material data and the personnel data, so that the quality of the engineering project can be conveniently traced, and the management of the engineering project is standardized.
The invention is further configured to: the project management terminal also comprises a project changing module, and the project changing module is used for modifying and/or deleting the pre-stored data by loading a changing instruction.
By adopting the technical scheme, when the project progress is abnormal or the risk evaluation module sends out early warning information, the project management terminal with the change authority can add, modify or delete the pre-stored data through the project change module, so that the project can be smoothly carried out, and the dynamic management of the project can be realized.
The invention is further configured to: the project management terminal also comprises a project progress query module, and the project progress query module calls the project progress analysis module to perform information query.
By adopting the technical scheme, the project management responsible person can inquire the construction cost, materials and personnel data of the project through fuzzy inquiry, keyword inquiry or multi-condition inquiry in the inquiry authority, thereby facilitating project management, knowing the data change of the project in real time and improving the level of project management.
The invention is further configured to: the project management terminal further comprises a spot check module, the spot check module receives spot check information input from the outside and calls a risk evaluation information table of the risk evaluation module to generate a spot check result, and the spot check result is marked on the risk evaluation information table.
By adopting the technical scheme, the selective examination module calls the risk assessment information table, so that the construction cost and budget of the engineering project and the cost of materials and personnel can be subjected to selective examination, and the management level of the engineering project is improved.
To sum up, the beneficial technical effect of this application:
1. the construction cost management terminal and the project management terminal establish an analysis evaluation information table through a risk evaluation module of a management server, when data of the risk evaluation information table exceed an alarm threshold value, the risk evaluation module sends an early warning instruction to a risk early warning module, the risk early warning module carries out early warning, the system is ensured to supervise construction cost risks of project projects in real time, corresponding data of abnormal risk evaluation are found in time, corresponding schemes are adjusted in time, and management of the project is optimized.
2. According to the method and the device, the early warning value is adjusted through the early warning adjusting module, the risk early warning adjusting module calls the risk assessment information table to adjust the early warning value, the risk assessment information table can be dynamically monitored, the early warning value is adjusted in time, and management of engineering projects can be optimized.
3. The project management terminal can access the management server through the project progress query module to perform project progress query, can acquire the whole project progress in real time, is convenient for management personnel to correspondingly adjust and manage projects, and ensures the quality of project projects.
Drawings
Fig. 1 is a block diagram of the system in this embodiment.
Detailed Description
The present invention will be described in further detail with reference to the accompanying drawings.
Referring to fig. 1, an embodiment of the present application: a project cost risk management system comprises a management server, a project management terminal and a cost management terminal; the project management terminal and the cost management terminal are respectively in communication connection with the management server, and the project management terminal and the cost management terminal can be mobile equipment, such as a mobile phone, a tablet and a computer.
The project management terminal comprises a budget loading module and an early warning loading module; the budget loading module is used for receiving budget data and transmitting the budget data to the management server, wherein the budget data comprises material budget amount, material budget unit price, artificial budget amount, unit time artificial budget unit price, mechanical equipment budget amount and unit time mechanical equipment budget unit price obtained according to the project book; the early warning loading module is used for receiving early warning data and transmitting the early warning data to the management server, and the early warning data is used for judging the preset value of the risk level of each construction step.
The cost management terminal comprises a cost loading module, a material loading module and a personnel loading module.
The cost loading module is used for receiving the cost data and transmitting the cost data to the management server, and a cost person inputs a project name, a project type and a project stage through the cost loading module. The material loading module is used for receiving material data and transmitting the material data to the management server; the construction worker inputs the material code, the material quantity and the material unit price according to the number of the engineering items through the material loading module; the cost worker inputs the personnel category and the personnel number through the personnel loading module according to the project book, and transmits the received personnel data to the management server.
The management server comprises a cost analysis module, a material distribution module, a personnel distribution module, a cost budget module, a risk assessment module and a risk early warning module.
And the construction cost analysis module receives the data sent by the construction cost loading module and generates a project construction cost information table.
The constructor inputs the temporarily estimated amount, the material type and the quantity through the material loading module, and transmits the data to the material distribution module, and the material distribution module generates a material distribution information table. And the material distribution module generates a material distribution information table according to the input total material price and amount information.
The personnel category and the personnel number input by the personnel loading module are transmitted to the personnel distribution module by the costing personnel, and the personnel distribution module processes the data to generate a personnel distribution information table. The personnel allocation information table comprises the personnel category number and the personnel number list of each project stage.
And the cost budgeting module receives the data sent by the budget loading module and generates an engineering budget information table. The project management side sends the estimated material type, the material quantity, the material unit price, the personnel type, the personnel quantity and the personnel cost in unit time to the cost budget module through the budget loading module according to the project book, and the cost budget module produces a cost budget information sheet according to the data. The cost budget information table comprises the total quantity of materials, the total cost of materials, the total quantity of personnel and a total personnel cost list of the project stage.
The construction cost analysis module, the material distribution module, the cost budget module and the personnel distribution module are respectively in communication connection with the risk assessment module, and the risk assessment module calls the engineering construction cost information table, the material distribution information table, the personnel distribution information table and the engineering budget information table, analyzes and processes the information to generate a risk assessment information table.
The risk assessment information table comprises project names, project categories and difference values of total actual material cost and total budget material cost and total actual personnel cost and total budget personnel cost in project stages. The above-mentioned difference is used to rate the risk.
In the risk evaluation information table, when the construction cost is lower than the predicted construction cost, the construction has no risk, when the actual construction cost is higher than the predicted construction cost, the construction has risk, and the difference value of the actual construction cost and the predicted construction cost is taken as risk grade evaluation;
the early warning loading module is in communication connection with the risk early warning module, receives the loaded warning threshold value and sends the warning threshold value to the risk early warning module. The alarm threshold is used for judging the preset value of the risk level of each construction step, the alarm threshold comprises a plurality of alarm thresholds,
and the risk early warning module calls the risk assessment information table, and when the data of the risk assessment information table is abnormal and exceeds the corresponding alarm threshold value, the risk early warning module outputs an early warning signal. If the risk level is 1, the alarm threshold is set to be 10, and when the difference value between the actual total material cost and the estimated total material cost is larger than 10, the risk alarm module outputs an early warning signal to prompt the risk level, and relevant personnel carry out corresponding plan processing.
The construction cost management terminal and the project management terminal establish a risk assessment information table through the management server, the system carries out real-time risk assessment on the project, when data of the risk assessment information table exceed an alarm threshold value, the risk assessment module sends an early warning instruction to the risk early warning module, the risk early warning module carries out early warning, the system is ensured to supervise construction cost risks of the project in real time, corresponding data of abnormal risk assessment are found in time, corresponding schemes are adjusted in time, and management of the project is optimized.
The management server in this embodiment further includes a risk early warning adjustment module, and the risk early warning adjustment module calls the risk assessment information table to adjust the early warning value, so that the risk assessment information table can be dynamically monitored, the early warning value can be adjusted in time, and management of engineering projects is optimized. And the risk early warning adjusting module is in communication connection with the risk assessment module.
In this embodiment, the management server further includes a risk early warning adjustment module, and the risk early warning adjustment module calls the risk assessment information table to adjust the early warning threshold. Specifically, the risk early warning adjustment module calls data of the risk assessment information table and approaches the early warning threshold value to the risk assessment information table according to the data of the risk assessment information table.
The construction cost management terminal of this embodiment still is equipped with project progress loading module, and the project management terminal is equipped with project progress query module, and the management server is equipped with project progress analysis module, and project progress analysis module receives the project progress data that project progress loading module sent and generates the project progress information table, and project progress query module is used for inquiring project progress information table information, knows the progress condition of engineering project in real time, accomplishes according to the plan for the engineering project and provides data support.
The cost management terminal also comprises a cost information module, wherein the cost information module comprises a cost name, a contact mode and a processed project name; the relevant information of the construction workers is marked in the loading process of the project name, the construction cost data, the material data and the personnel data, so that the quality of the project can be conveniently traced, and the project management is standardized.
The management server of this embodiment still is equipped with the notice module, project management terminal still is equipped with project progress setting module, project progress setting module gives project progress preset value data and constructor address book data transfer to project progress analysis module, the notice module calls project progress information table in real time and carries out comparative evaluation to the project progress, when the project progress is less than the preset value, the notice module sends the progress notice to constructor person of charge address book, the suggestion constructor person of charge seeks the reason that the project progress is not up to standard, and in time adjust.
In this embodiment, the item management terminal further includes an item change module, where the item change module uses a load change instruction to modify and/or delete pre-stored data; and when the project progress is abnormal or the risk evaluation module sends out early warning information, the constructor manager with the change authority can add, modify or delete the pre-stored data through the project change module, so that the smooth proceeding of the engineering project is ensured, and the dynamic management of the engineering project is realized.
In this embodiment, the project management terminal further includes a project progress query module, and the project progress query module calls the project progress analysis module to perform information query. The project management responsible person can inquire the cost, materials and personnel data of the project through fuzzy inquiry, keyword inquiry or multi-condition inquiry within the inquiry authority, the project inquiry module is used for receiving the inquiry condition loaded by the project management terminal to inquire information, the project management can be facilitated, the data change of the project can be known in real time, and the project management level can be improved.
In this embodiment, the project management terminal further includes a selective examination module, the selective examination module receives selective examination information input from the outside, and the selective examination information may be engineering cost information, material information, worker information, and the like, and the selective examination module calls a risk assessment information table of the risk assessment module, and performs selective examination on the progress, material cost, and number of personnel of the engineering project to generate a selective examination result. The project progress is greater than or equal to the preset project progress, the material settlement cost is less than or equal to the material budget cost, the actual number of the personnel is less than or equal to the personnel budget number, the personnel budget number is qualified through the selective inspection, and otherwise, the selective inspection is unqualified; the sampling inspection result is marked on the risk assessment information table, and a construction cost manager can inquire the sampling inspection result by calling the risk assessment module through the construction cost management terminal, so that the engineering project management level is improved.
The method comprises the steps of analyzing and processing a project cost information table, a material distribution information table, a personnel distribution information table and a project budget information table to generate a risk assessment information table;
the working process of the application is as follows: the construction cost manager inputs the project name, the category and the project plan completion time to the construction cost analysis module through the construction cost loading module of the construction cost management terminal, and the construction cost analysis module generates a project construction cost information table.
The constructor inputs the material type and quantity through the material loading module, measures the unit and the market unit price to the material distribution module, and the material distribution module generates a material distribution information table.
The construction staff inputs constructor information and manager information to the staff distribution module through the staff loading module, the staff distribution module is in communication connection with the staff loading module, and the staff loading module receives data sent by the staff loading module and generates a staff distribution information table.
The construction party inputs budget data to the cost budget module through a budget loading module of the project management terminal, and the cost budget module generates a project budget information table.
And the risk evaluation module calls the project cost information table, the material distribution information table, the personnel distribution information table and the project budget information table, and analyzes and processes the project cost information table, the material distribution information table, the personnel distribution information table and the project budget information table to generate a risk evaluation information table. Specifically, the generation is based on the construction cost and the construction budget
The construction method comprises the steps that a constructor inputs an alarm threshold value to a risk assessment module through an early warning loading module, when data of a risk assessment information table are abnormal and exceed the corresponding alarm threshold value, the risk assessment module sends an early warning instruction to the risk early warning module, and the risk early warning module starts early warning.
The construction cost management terminal and the project management terminal establish an analysis evaluation information table through a risk evaluation module of a management server, when data of the risk evaluation information table exceed an alarm threshold value, the risk evaluation module sends an early warning instruction to a risk early warning module, the risk early warning module carries out early warning prompt, the system is ensured to supervise construction cost risks of project projects in real time, corresponding data of abnormal risk evaluation are found in time, corresponding schemes are adjusted in time, and management of the project is optimized.
The embodiments of the present invention are preferred embodiments of the present invention, and the scope of the present invention is not limited by these embodiments, so: all equivalent changes made according to the structure, shape and principle of the invention are covered by the protection scope of the invention.
Claims (8)
1. A project cost risk management system, its characterized in that: the system comprises a management server, a project management terminal and a cost management terminal; the project management terminal and the cost management terminal are respectively in communication connection with the management server;
the project management terminal comprises a budget loading module and an early warning loading module; the budget loading module is used for receiving budget data and transmitting the budget data to a management server; the early warning loading module is used for receiving early warning data and transmitting the early warning data to the management server;
the cost management terminal comprises a cost loading module, a material loading module and a personnel loading module;
the cost loading module is used for receiving cost data and transmitting the cost data to the management server; the material loading module is used for receiving material data and transmitting the material data to the management server; the personnel loading module is used for receiving personnel data and transmitting the personnel data to the management server;
the management server comprises a construction cost analysis module, a material distribution module, a personnel distribution module, a cost budget module, a risk assessment module and a risk early warning module;
the construction cost analysis module receives the data sent by the construction cost loading module and generates a project construction cost information table;
the material distribution module receives the data sent by the material loading module and generates a material distribution information table;
the personnel loading module receives the data sent by the personnel loading module and generates a personnel distribution information table;
the cost budget module receives the data sent by the budget loading module and generates an engineering budget information table;
the construction cost analysis module, the material distribution module, the cost budget module and the personnel distribution module are respectively in communication connection with a risk assessment module, and the risk assessment module calls the engineering construction cost information table, the material distribution information table, the personnel distribution information table and the engineering budget information table, analyzes and processes the information to generate a risk assessment information table;
the early warning loading module is in communication connection with the risk early warning module, receives the loaded alarm threshold and sends the alarm threshold to the risk early warning module;
and the risk early warning module calls the risk assessment information table, and when the data of the risk assessment information table is abnormal and exceeds the corresponding alarm threshold value, the risk early warning module outputs an early warning signal.
2. The project cost risk management system of claim 1, wherein: the management server further comprises a risk early warning adjusting module, and the risk early warning adjusting module calls a risk assessment information table to adjust the threshold value.
3. The project cost risk management system of claim 1, wherein: the construction cost management terminal is further provided with a project progress loading module, the project management terminal is provided with a project progress query module, the management server is provided with a project progress analysis module, the project progress analysis module receives project progress data sent by the project progress loading module and generates a project progress information table, and the project progress query module is used for querying information of the project progress information table.
4. The project cost risk management system of claim 3, wherein: the management server is further provided with a notification module, the project management terminal is further provided with a project progress setting module, the project progress setting module transmits project progress preset value data and project responsible person address book data to the project progress analysis module, the notification module calls a project progress information table in real time to compare and evaluate the project progress, and when the project progress is lower than a preset value, the notification module sends a progress notification to the project responsible person address book.
5. The project cost risk management system of claim 4, wherein: the construction cost management terminal also comprises a construction cost information module, and the construction cost information base comprises construction cost names, contact ways and processed engineering project names.
6. The project cost risk management system of claim 1, wherein: the project management terminal also comprises a project changing module, and the project changing module is used for modifying and/or deleting the pre-stored data by loading a changing instruction.
7. The project cost risk management system of claim 3, wherein: the project management terminal also comprises a project progress query module, and the project progress query module calls the project progress analysis module to perform information query.
8. The project cost risk management system of claim 1, wherein: the project management terminal further comprises a spot check module, the spot check module receives spot check information input from the outside and calls a risk evaluation information table of the risk evaluation module to generate a spot check result, and the spot check result is marked on the risk evaluation information table.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202011511109.3A CN112529446A (en) | 2020-12-18 | 2020-12-18 | Engineering project cost risk management system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202011511109.3A CN112529446A (en) | 2020-12-18 | 2020-12-18 | Engineering project cost risk management system |
Publications (1)
Publication Number | Publication Date |
---|---|
CN112529446A true CN112529446A (en) | 2021-03-19 |
Family
ID=75001719
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202011511109.3A Pending CN112529446A (en) | 2020-12-18 | 2020-12-18 | Engineering project cost risk management system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN112529446A (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114548685A (en) * | 2022-01-21 | 2022-05-27 | 四川省交通建设集团股份有限公司 | Building construction project progress management method, system, electronic device and storage medium |
CN117114427A (en) * | 2023-10-25 | 2023-11-24 | 深圳市睿拓新科技有限公司 | BIM-based whole-process engineering pricing management method and system |
CN117273456A (en) * | 2023-09-27 | 2023-12-22 | 深圳叮当科技技术有限公司 | Project cost intelligent management system based on big data technology |
CN118014376A (en) * | 2024-04-09 | 2024-05-10 | 中交二公局东萌工程有限公司 | Engineering construction project risk tracking and early warning method |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109377172A (en) * | 2018-10-13 | 2019-02-22 | 广州名都建设项目管理有限公司 | Project cost progress control system |
CN110991990A (en) * | 2019-11-25 | 2020-04-10 | 四川华通建设工程造价管理有限责任公司 | Engineering project cost management system |
CN111476425A (en) * | 2020-04-15 | 2020-07-31 | 中道明华建设工程项目咨询有限责任公司 | Engineering project cost progress supervision system and method |
CN111784278A (en) * | 2020-05-22 | 2020-10-16 | 河南建达工程项目管理有限公司 | Project cost project progress management system |
CN111815015A (en) * | 2020-05-22 | 2020-10-23 | 北京合力信工程投资咨询有限公司 | Engineering management optimization method and system |
-
2020
- 2020-12-18 CN CN202011511109.3A patent/CN112529446A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109377172A (en) * | 2018-10-13 | 2019-02-22 | 广州名都建设项目管理有限公司 | Project cost progress control system |
CN110991990A (en) * | 2019-11-25 | 2020-04-10 | 四川华通建设工程造价管理有限责任公司 | Engineering project cost management system |
CN111476425A (en) * | 2020-04-15 | 2020-07-31 | 中道明华建设工程项目咨询有限责任公司 | Engineering project cost progress supervision system and method |
CN111784278A (en) * | 2020-05-22 | 2020-10-16 | 河南建达工程项目管理有限公司 | Project cost project progress management system |
CN111815015A (en) * | 2020-05-22 | 2020-10-23 | 北京合力信工程投资咨询有限公司 | Engineering management optimization method and system |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114548685A (en) * | 2022-01-21 | 2022-05-27 | 四川省交通建设集团股份有限公司 | Building construction project progress management method, system, electronic device and storage medium |
CN117273456A (en) * | 2023-09-27 | 2023-12-22 | 深圳叮当科技技术有限公司 | Project cost intelligent management system based on big data technology |
CN117114427A (en) * | 2023-10-25 | 2023-11-24 | 深圳市睿拓新科技有限公司 | BIM-based whole-process engineering pricing management method and system |
CN117114427B (en) * | 2023-10-25 | 2024-02-09 | 深圳市睿拓新科技有限公司 | BIM-based whole-process engineering pricing management method and system |
CN118014376A (en) * | 2024-04-09 | 2024-05-10 | 中交二公局东萌工程有限公司 | Engineering construction project risk tracking and early warning method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN112529446A (en) | Engineering project cost risk management system | |
CN109672663B (en) | Closed-loop network security supervision method and system for security threat event | |
CN106447284B (en) | Nuclear power station DCS configuration change informatization platform management system and method | |
CN110133706B (en) | Method, device, equipment and medium for monitoring environment radiation of million-kilowatt nuclear power station | |
CN112560046B (en) | Assessment method and device for business data security index | |
CN111915143B (en) | Complex product assembly management and control system based on intelligent contract | |
CN114639183A (en) | Intelligent inspection method, system, computer equipment and medium based on element | |
CN101655936A (en) | Network monitoring method for maintaining telecommunication equipment | |
CN118132577B (en) | Consistency verification method and device | |
US6807416B2 (en) | Troubleshooting method and apparatus | |
CN111815015A (en) | Engineering management optimization method and system | |
CN111582754B (en) | Risk investigation method, apparatus, device and computer readable storage medium | |
CN107835218A (en) | Combustion gas based on compound Internet of Things uses planing method and Internet of things system | |
CN114647645A (en) | Operation and maintenance system of industrial mobile robot | |
CN108881517B (en) | Domain name pool automatic management method and system | |
CN114049100A (en) | Wisdom government affairs integration platform based on letter creates environment | |
CN113625673A (en) | Dynamic scheduling method, device and system for power safety inspection personnel and storage device | |
CN111428890A (en) | Cabinet maintenance management method, system and device | |
CN106294411B (en) | Software category identification method and system | |
CN114115003B (en) | Remote start-stop control platform | |
CN116108097A (en) | Intelligent supervision system and method for enterprise management | |
CN113050579B (en) | Furniture spraying energy consumption management system and method and computer readable storage medium | |
CN116795064B (en) | DCS-based alarm management method, electronic equipment and storage medium | |
CN112597229B (en) | Equipment data access method, device and system and readable storage medium | |
CN118836048A (en) | Shield tunnel construction monitoring data supervision method and related equipment |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |