CN112160570A - Green building supporting platform convenient to quick construction - Google Patents
Green building supporting platform convenient to quick construction Download PDFInfo
- Publication number
- CN112160570A CN112160570A CN202010977531.1A CN202010977531A CN112160570A CN 112160570 A CN112160570 A CN 112160570A CN 202010977531 A CN202010977531 A CN 202010977531A CN 112160570 A CN112160570 A CN 112160570A
- Authority
- CN
- China
- Prior art keywords
- frame
- platform
- escalator
- construction
- workers
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G1/00—Scaffolds primarily resting on the ground
- E04G1/15—Scaffolds primarily resting on the ground essentially comprising special means for supporting or forming platforms; Platforms
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G1/00—Scaffolds primarily resting on the ground
- E04G1/18—Scaffolds primarily resting on the ground adjustable in height
- E04G1/22—Scaffolds having a platform on an extensible substructure, e.g. of telescopic type or with lazy-tongs mechanism
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G1/00—Scaffolds primarily resting on the ground
- E04G1/24—Scaffolds primarily resting on the ground comprising essentially special base constructions; comprising essentially special ground-engaging parts, e.g. inclined struts, wheels
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G5/00—Component parts or accessories for scaffolds
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G5/00—Component parts or accessories for scaffolds
- E04G5/003—Devices for storing material on the scaffold
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G5/00—Component parts or accessories for scaffolds
- E04G5/10—Steps or ladders specially adapted for scaffolds
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G5/00—Component parts or accessories for scaffolds
- E04G5/12—Canopies
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G5/00—Component parts or accessories for scaffolds
- E04G5/14—Railings
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G5/00—Component parts or accessories for scaffolds
- E04G5/14—Railings
- E04G5/144—Railings specific for the lateral, i.e. short side of a scaffold
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Movable Scaffolding (AREA)
Abstract
The invention relates to the technical field of building construction, in particular to a green building supporting platform convenient for rapid construction, which comprises an underframe mechanism and a platform mechanism, wherein the platform mechanism is arranged above the underframe mechanism, the underframe mechanism is in contact with the ground, a shed roof is arranged for facilitating the use of workers, the construction experience of the workers is optimized under the condition of light rain or insolation, the construction speed is accelerated, the workers can be protected, the adverse effect of falling objects on the life safety of the workers is avoided, the construction safety is improved, the workers turn over a static escalator frame, a dynamic escalator side frame slides downwards under the action of gravity, the length of the whole escalator component is increased, simultaneously a left escalator frame and a right escalator frame are respectively turned over and are mutually spliced to form an escalator pedal structure, the workers only need to step on the escalator pedal structure, the structure is simple, the operation is convenient, the increase of the escalator component can be realized, and the construction requirements of, and the platform adaptability is improved.
Description
Technical Field
The invention relates to the technical field of building construction, in particular to a green building supporting platform convenient for rapid construction.
Background
The green building is a high-quality building which saves resources, protects the environment, reduces pollution, provides healthy, applicable and efficient use space for people and furthest realizes harmonious symbiosis between people and nature in the whole life cycle, various support platforms are required to be utilized in the construction process of the green building, so that workers can conveniently construct the building structure, the existing support platform for construction only provides a support function, no protective structure is arranged on the periphery, and the safety is not high.
The Chinese patent with the application number of CN202010484347.3 provides a green building supporting platform convenient for rapid construction, which improves and optimizes the structure of the building construction platform, so that the building construction platform can be conveniently moved according to the use requirement, and can change the size of the working table top according to the use requirement, thereby facilitating the change and the change of the size of the building construction platform according to the different use requirements of workers and tools, and the construction supporting platform has high use safety performance, can effectively reduce the probability of accidents, but in the patent, the top of the building construction platform is not provided with any protection device, can not comprehensively protect workers in the building construction process, and the solid waste materials generated in the building construction process need to be manually lifted off the platform, thereby wasting time and energy, and the generated liquid waste materials are easy to accumulate in the platform, the corrosion of the platform bottom plate is accelerated, the service life of the platform device is shortened, the length of the escalator is fixed when the height of the construction supporting platform is changed, and the escalator is inconvenient for workers to use.
Disclosure of Invention
The invention aims to provide a green building supporting platform convenient for quick construction, which has the advantages of optimizing the construction experience of workers, accelerating the construction speed, protecting the workers, avoiding the adverse effect of falling objects on the life safety of the workers, improving the construction safety, having simple structure and convenient operation, realizing the growth of escalator components, meeting the construction requirements of different heights and improving the adaptability of the platform, so as to solve the problems that no protective device is arranged at the top of the building construction platform provided in the background technology, the workers cannot be comprehensively protected in the building construction process, solid waste materials generated in the building construction process need to be manually lifted by the workers to be lifted up to the platform, time and labor are wasted, liquid waste materials are easily accumulated in the platform, the corrosion of the bottom plate of the platform is accelerated, the service life of the platform device is shortened, the length of the escalator is fixed while the height of the construction supporting platform is changed, is inconvenient for workers to use.
In order to achieve the purpose, the invention provides the following technical scheme: a green building supporting platform convenient for rapid construction comprises an underframe mechanism and a platform mechanism, wherein the platform mechanism is arranged above the underframe mechanism, the underframe mechanism is in contact with the ground, the underframe mechanism consists of a underframe plate, a material frame butt joint groove, outer bracket sleeves, an electric telescopic rod and a lap plate, the material frame butt joint groove is processed on the underframe plate, four groups of the outer bracket sleeves are fixedly arranged on the top surface of the underframe plate, the lap plate is welded on the outer wall of each outer bracket sleeve, the electric telescopic rod is fixedly arranged in each outer bracket sleeve, and the top of the electric telescopic rod is fixedly connected with the platform mechanism; the platform mechanism comprises a ceiling assembly, a supporting platform, an installation frame, a material conveying channel and a material frame, wherein the ceiling assembly is fixedly installed on the supporting platform, the installation frame is fixedly arranged on the side wall of the supporting platform and is communicated with one end of the material conveying channel, the other end of the material conveying channel extends into the material frame, and the material frame is clamped in a material frame butt joint groove.
Preferably, the ceiling assembly comprises a ceiling, an upper shaft sleeve, a lower shaft sleeve, a connecting shaft and a knob, the bottom surface of the ceiling is fixedly connected with the upper shaft sleeve, the connecting shaft is sleeved inside the upper shaft sleeve, the bottom of the connecting shaft is fixed inside the lower shaft sleeve, the lower shaft sleeve is fixed on the top surface of the supporting platform, the knob is movably mounted on the upper shaft sleeve, and a screw rod part of the knob extends into the inside of the upper shaft sleeve and is attached to the outer wall of the connecting shaft.
Preferably, supporting platform includes the outer frame of platform, the platform bottom plate, subtract the burden groove, the buckle, the trip, staircase subassembly and installation axle, the fixed mounting platform bottom plate of the inside bottom surface of the outer frame of platform, set up the burden groove in the left and right sides outer frame of platform, the burden groove and the installing frame fixed connection that subtract that set up on the left side outer frame of platform, the top and the lower axle sleeve fixed connection of the outer frame of platform, the front outer wall of the outer frame of platform sets up the export, the left side outer wall mounting buckle in the exit, the buckle meets with the trip, the trip passes through axle movable mounting on the staircase subassembly, the staircase subassembly cup joints with the outer frame activity of platform through the installation.
Preferably, the top surface processing multiunit of platform bottom plate permeates water the hole, permeates water the hole and communicates with hollow platform bottom plate's inner chamber, processes the delivery port on platform bottom plate's the lateral wall, and the size of platform bottom plate is the same with the planar structure's that four groups of frame boards formed size.
Preferably, the staircase subassembly includes static escalator frame, developments staircase frame, the accepting groove, the change, left ladder grillage and right ladder grillage, the top of static escalator frame and the installation axle fixed cup joint of fixing on the outer frame of platform, the both sides inner wall of static escalator frame all sets up to hollow structure, the equal movable suit dynamic staircase frame of both sides inner wall of static escalator frame, the inboard outer wall processing accepting groove of dynamic staircase frame, the inside fixed mounting change of accepting groove, the change of installation meets with left ladder grillage in the accepting groove of left side, the change of installation meets with right ladder grillage in the accepting groove of right side, the right-hand member face of left ladder grillage is inwards sunken, the left end face of right ladder grillage is outwards outstanding, form staircase footboard structure after left ladder grillage and the concatenation of right ladder grillage.
Preferably, the material conveying channel is a corrugated square pipe component made of plastic, and the material conveying channel is accommodated in the mounting frame in a shrinkage shape in an unused state.
The invention provides a green building supporting platform convenient for rapid construction, which has the beneficial effects that:
1. this green building supporting platform convenient to quick construction sets up the shed roof and makes things convenient for the workman to use, under little rain or insolate environment, optimizes workman construction and experiences for construction speed also can protect the workman, avoids falling object from the high altitude to the harmful effects that workman life safety caused, improves construction safety nature.
2. This green building supporting platform convenient to quick construction, workman's static escalator frame of upset, developments staircase side frame lapse under the effect of gravity, the length that makes whole staircase subassembly increases, the accepting groove exposes simultaneously, it prescribes the back to left ladder grillage and right ladder grillage position to remove static escalator frame, left ladder grillage and right ladder grillage take place the upset around the change respectively, until left ladder grillage and right ladder grillage splice each other and form staircase footboard structure, the workman trample the staircase footboard structure can, moreover, the steam generator is simple in structure, and convenient for operation can realize the increase of staircase subassembly, satisfy the not construction demand of co-altitude, improve platform suitability.
Drawings
FIG. 1 is a schematic view of the overall structure of a green building support platform for facilitating rapid construction according to the present invention;
FIG. 2 is a schematic structural diagram of an underframe mechanism of a green building supporting platform convenient for rapid construction according to the invention;
FIG. 3 is a schematic structural diagram of a platform mechanism of a green building supporting platform for facilitating rapid construction according to the present invention;
FIG. 4 is a schematic view of an overall structure of a green building supporting platform convenient for rapid construction according to the present invention in a use state;
FIG. 5 is a schematic view of the staircase assembly structure of a green building support platform for facilitating rapid construction according to the present invention;
fig. 6 is a schematic structural view of a platform bottom plate of a green building supporting platform convenient for rapid construction according to the present invention.
In the figure: 1. an undercarriage mechanism; 11. a chassis plate; 12. a material frame butt joint groove; 13. an outer stent sleeve; 14. an electric telescopic rod; 15. a scaffold plate; 2. a platform mechanism; 21. a ceiling assembly; 211. a shed roof; 212. an upper shaft sleeve; 213. a lower shaft sleeve; 214. a connecting shaft; 215. a knob; 22. a support platform; 221. a platform outer frame; 222. a platform floor; 2221. water permeable holes; 2222. a water outlet; 223. a load reduction groove; 224. buckling; 225. a hook is clamped; 226. an escalator component; 2261. a static ladder rack; 2262. a dynamic staircase side frame; 2263. an accommodating groove; 2264. rotating the ring; 2265. a left ladder frame; 2266. a right ladder rack; 227. installing a shaft; 23. installing a frame; 24. a material conveying channel; 25. and (7) material frame.
Detailed Description
The technical scheme in the embodiment of the invention will be made clear below by combining the attached drawings in the embodiment of the invention; fully described, it is to be understood that the described embodiments are merely exemplary of some, but not all, embodiments of the invention and that all other embodiments, which can be derived by one of ordinary skill in the art based on the described embodiments without inventive faculty, are within the scope of the invention.
Referring to fig. 1, a green building supporting platform convenient for rapid construction includes an underframe mechanism 1 and a platform mechanism 2, the platform mechanism 2 is installed above the underframe mechanism 1, the underframe mechanism 1 contacts with the ground, a worker uses the platform mechanism 2 to construct a building, and the underframe mechanism 1 supports the platform mechanism 2.
Referring to fig. 2, the chassis mechanism 1 is composed of a chassis plate 11, a material frame butt joint groove 12, an outer support sleeve 13, an electric telescopic rod 14 and a support frame lapping plate 15, the material frame butt joint groove 12 is processed on the chassis plate 11, four groups of outer support sleeves 13 are fixedly installed on the top surface of the chassis plate 11, the outer wall of each outer support sleeve 13 is welded with the support frame lapping plate 15, the electric telescopic rod 14 is fixedly installed inside the outer support sleeve 13, the top of the electric telescopic rod 14 is fixedly connected with the platform mechanism 2, when the platform mechanism 2 is used, the four groups of electric telescopic rods 14 are driven to integrally lift through lifting of the electric telescopic rod 14, height adjustment of the platform mechanism 2 is achieved, the four groups of electric telescopic rods 14 are connected in series and lift synchronously, the lifting process of the platform mechanism 2 is more stable, and position stability.
Referring to fig. 3-4, the platform mechanism 2 includes a ceiling assembly 21, a supporting platform 22, a mounting frame 23, a material conveying channel 24 and a material frame 25, the ceiling assembly 21 is fixedly mounted on the supporting platform 22, the side wall of the supporting platform 22 is fixedly provided with the mounting frame 23, the mounting frame 23 is communicated with one end of the material conveying channel 24, the material conveying channel 24 is received in the mounting frame 23 in a shrinking manner in a non-use state, the other end of the material conveying channel 24 extends into the material frame 25, the material frame 25 is clamped in the material frame butt-joint groove 12, the ceiling assembly 21 is composed of a ceiling 211, an upper shaft sleeve 212, a lower shaft sleeve 213, a connecting shaft 214 and a knob 215, the bottom surface of the ceiling 211 is fixedly connected with the upper shaft sleeve 212, the connecting shaft 214 is sleeved inside the upper shaft sleeve 212, the bottom of the connecting shaft 214 is fixed inside the lower shaft sleeve 213, the lower shaft sleeve 213 is fixed on the top surface of the supporting platform 22, the knob 215 is movably mounted, the screw part of the knob 215 extends into the upper shaft sleeve 212 and is attached to the outer wall of the connecting shaft 214, the shed roof 211 is lifted upwards to enable the upper shaft sleeve 212 to move upwards along the connecting shaft 214, after the shed roof 211 is adjusted to a proper height, the knob 215 is rotated by manpower to enable the screw part of the knob 215 to be closely attached to the connecting shaft 214, the position limitation of the shed roof 211 is realized through the friction force between the screw part and the connecting shaft, the shed roof 211 is arranged to be convenient for workers to use, the construction experience of the workers is optimized under the condition of light rain or insolation, the construction speed is accelerated, the workers can be protected, the adverse effect of falling objects on the life safety of the workers is avoided, the construction safety is improved, the supporting platform 22 comprises a platform outer frame 221, a platform bottom plate 222, a load reduction groove 223, a buckle 224, a clamping hook 225, an escalator component 226 and an installation shaft 227, the platform bottom plate 222 is fixed, the left and right side platform outer frames 221 are internally provided with relief grooves 223, the relief grooves 223 arranged on the left side platform outer frame 221 are fixedly connected with the mounting frame 23, the top of the platform outer frame 221 is fixedly connected with the lower shaft sleeve 213, the outer wall of the front side of the platform outer frame 221 is provided with an outlet, a buckle 224 is arranged on the outer wall of the left side at the outlet, the buckle 224 is connected with a buckle 225, the buckle 225 is movably arranged on the staircase component 226 through a shaft, the staircase component 226 is movably sleeved with the platform outer frame 221 through a mounting shaft 227, the self weight of the platform outer frame 221 is reduced through the arrangement of the relief grooves 223, a worker stands inside the platform bottom plate 222 for construction, construction waste is conveyed into the material frame 25 through the material conveying channel 24, the construction waste is not required to be conveyed downwards manually, time and labor are saved, the material conveying channel 24 is arranged to be a corrugated square pipe component made of plastics and is contracted into, the workman uses staircase subassembly 226 to enter into the inside back of platform outer frame 221, makes trip 225 and buckle 224 block through rotating trip 225, realizes the fixed of staircase subassembly 226 position, and the exit of platform outer frame 221 is blockked by staircase subassembly 226, avoids the platform export of open type to the hidden danger that workman construction safety caused, avoids workman or construction apparatus to drop from the platform exit accident, improves the platform practicality.
Referring to fig. 5, the staircase assembly 226 includes a static staircase frame 2261, a dynamic staircase frame 2262, a receiving groove 2263, a rotary ring 2264, a left staircase frame 2265 and a right staircase frame 2266, wherein the top of the static staircase frame 2261 is fixedly sleeved with a mounting shaft 227 fixed on the platform outer frame 221, inner walls of two sides of the static staircase frame 2261 are both provided with hollow structures, inner walls of two sides of the static staircase frame 2261 are movably sleeved with the dynamic staircase frame 2262, the receiving groove 2263 is processed on the outer wall of the inner side of the dynamic staircase frame 2262, the rotary ring 2264 is fixedly mounted inside the receiving groove 2263, the rotary ring 2264 mounted in the left receiving groove 2263 is connected with the left staircase frame 2265, the rotary ring 2264 mounted in the right receiving groove 2263 is connected with the right staircase frame 2266, the right end of the left staircase frame 2265 is recessed inwards, the left end of the right staircase frame 2266 protrudes outwards, the left staircase frame 2265 and the right staircase frame 2266 form a staircase pedal structure, and the staircase frame 2261 is turned downwards when in a vertical state, one end of the static escalator frame 2261 rotates around the mounting shaft 227, the other end of the static escalator frame 2261 rotates downwards, the dynamic escalator side frame 2262 sleeved inside the static escalator frame 2261 slides downwards under the action of gravity, so that the length of the whole escalator assembly 226 is increased, meanwhile, the accommodating groove 2263 is exposed, after the position of the static escalator frame 2261 on the left escalator frame 2265 and the position of the right escalator frame 2266 are limited, the left escalator frame 2265 and the right escalator frame 2266 are respectively turned around the rotating ring 2264 until the left escalator frame 2265 and the right escalator frame 2266 are mutually spliced to form an escalator pedal structure, and a worker steps on the escalator pedal structure.
Referring to fig. 6, a plurality of sets of water permeable holes 2221 are formed in the top surface of the platform bottom plate 222, the water permeable holes 2221 are communicated with the inner cavity of the hollow platform bottom plate 222, a water outlet 2222 is formed in the side wall of the platform bottom plate 222, the size of the platform bottom plate 222 is the same as that of the planar structure formed by the four sets of mounting plates 15, liquid waste generated during construction falls into the inner cavity of the platform bottom plate 222 along the water permeable holes 2221 and then flows out of the platform bottom plate 222 from the water outlet 2222, so that the liquid waste is prevented from being accumulated in the platform bottom plate 222 and being rusted on the platform bottom plate 222, the water outlet direction of the water outlet 2222 is fixed, rainwater or the liquid waste is guided, and the rainwater or.
The working principle is as follows: a worker uses the platform mechanism 2 to construct a building, the underframe mechanism 1 supports the platform mechanism 2, when in use, the electric telescopic rod 14 is lifted to drive the platform mechanism 2 to integrally lift, so as to realize the height adjustment of the platform mechanism 2, the shed roof 211 is lifted upwards to enable the upper shaft sleeve 212 to move upwards along the connecting shaft 214, after the shed roof 211 is adjusted to a proper height, the knob 215 is rotated by manpower, the screw part of the knob 215 is tightly attached to the connecting shaft 214, the position limitation of the shed roof 211 is realized by the friction force between the screw part and the connecting shaft, the shed roof 211 is arranged to be convenient for the worker to use, the self weight of the platform outer frame 221 is reduced by the arrangement of the load reducing groove 223, the worker stands in the platform bottom plate 222 for construction, construction waste is conveyed into the material frame 25 through the material conveying channel 24, the material conveying channel 24 is arranged to be a corrugated square pipe component made of plastics and is contracted into the mounting frame, after a worker enters the inside of the platform outer frame 221 by using the staircase component 226, the hook 225 is engaged with the buckle 224 by rotating the hook 225, so as to fix the position of the staircase component 226, the exit of the platform outer frame 221 is blocked by the staircase component 226, when the escalator is used, the static staircase frame 2261 in a vertical state is turned downwards, one end of the static staircase frame 2261 rotates around the mounting shaft 227, the other end of the static staircase frame 2261 rotates downwards, the dynamic staircase frame 2262 sleeved inside the static staircase frame 2261 slides downwards under the action of gravity, so that the length of the whole staircase component 226 is increased, meanwhile, the accommodating groove 2263 is exposed, after the position limitation of the static staircase frame 2261 on the left staircase frame 2265 and the right staircase frame 2266 is released, the left staircase frame 2265 and the right staircase frame 2266 are respectively turned around the rotating ring 2264 until the left staircase frame 2265 and the right staircase frame 2266 are mutually spliced to form a step structure, the worker steps on the escalator step structure, liquid waste generated during construction falls into the inner cavity of the platform bottom plate 222 along the water permeable holes 2221 and then flows out of the platform bottom plate 222 from the water outlet 2222, the water outlet direction of the water outlet 2222 is fixed, and the guiding effect on rainwater or liquid waste is achieved.
In summary, according to the green building supporting platform convenient for rapid construction, a worker uses the platform mechanism 2 to construct a building, the underframe mechanism 1 supports the platform mechanism 2, when in use, the electric telescopic rods 14 lift up and down to drive the platform mechanism 2 to lift up and down integrally, so as to realize height adjustment of the platform mechanism 2, the four groups of electric telescopic rods 14 are connected in series and lift up and down synchronously, so that the lifting process of the platform mechanism 2 is more stable, the position stability of the platform mechanism 2 in the lifting process is ensured, the upper shaft sleeve 212 moves upwards along the connecting shaft 214 by lifting up the shed roof 211, after the shed roof 211 is adjusted to a proper height, the screw part of the knob 215 is tightly attached to the connecting shaft 214 by rotating the knob 215 by manpower, the position limitation of the shed roof 211 is realized by friction force between the screw part and the connecting shaft 214, the shed roof 211 is convenient for the worker to use, and under the environment of, the construction experience of workers is optimized, the construction speed is accelerated, workers can be protected, adverse effects of falling objects from high altitude on the life safety of the workers are avoided, the construction safety is improved, the dead weight of the platform outer frame 221 is reduced through the arrangement of the burden reduction groove 223, the workers stand inside the platform bottom plate 222 for construction, construction waste is conveyed into the material frame 25 through the conveying channel 24, the construction waste is not required to be conveyed downwards manually, time and labor are saved, the conveying channel 24 is a corrugated square pipe component made of plastics and is contracted in the mounting frame 23 when not in use, the occupied space is small, after the workers enter the inside of the platform outer frame 221 through the escalator component 226, the clamping hook 225 is clamped with the buckle 224 through rotating the clamping hook 225, the position of the escalator component 226 is fixed, the outlet of the platform outer frame 221 is blocked by the escalator component 226, and hidden dangers of the open type platform outlet on the construction safety of the workers are avoided, the escalator has the advantages that workers or construction tools are prevented from accidentally falling from the platform outlet, the platform practicability is improved, when the escalator is used, the static escalator frame 2261 in a vertical state is turned downwards, one end of the static escalator frame 2261 rotates around the installation shaft 227, the other end of the static escalator frame 2261 rotates downwards, the dynamic escalator side frame 2262 sleeved in the static escalator frame 2261 slides downwards under the action of gravity, the length of the whole escalator component 226 is increased, the accommodating groove 2263 is exposed at the same time, after the position limitation of the static escalator frame 2261 on the left escalator frame 2265 and the right escalator frame 2266 is relieved, the left escalator frame 2265 and the right escalator frame 2266 are respectively turned around the rotating ring 2264 until the left escalator frame 2265 and the right escalator frame 2266 are mutually spliced to form an escalator pedal structure, the escalator is simple in structure and convenient to operate, the escalator component 226 can be increased, and construction requirements of different heights are met, the platform adaptability is improved, liquid waste generated during construction falls into the inner cavity of the platform bottom plate 222 along the water permeable holes 2221 and then flows out of the platform bottom plate 222 from the water outlet 2222, so that the liquid waste is prevented from accumulating in the platform bottom plate 222 and being rusted on the platform bottom plate 222, the water outlet direction of the water outlet 2222 is fixed, rainwater or the liquid waste is guided, and the rainwater or the liquid waste is prevented from flowing in a scattered manner.
The above description is only for the preferred embodiment of the present invention, but the scope of the present invention is not limited thereto, and any person skilled in the art should be able to cover the technical solutions and the inventive concepts of the present invention within the technical scope of the present invention.
Claims (6)
1. A green building supporting platform convenient for rapid construction comprises an underframe mechanism (1) and a platform mechanism (2), wherein the platform mechanism (2) is installed above the underframe mechanism (1), and the underframe mechanism (1) is in contact with the ground, and is characterized in that the underframe mechanism (1) consists of an underframe plate (11), a material frame butt joint groove (12), an outer support sleeve (13), an electric telescopic rod (14) and a support plate (15), the material frame butt joint groove (12) is processed on the underframe plate (11), four groups of outer support sleeves (13) are fixedly installed on the top surface of the underframe plate (11), the support plate (15) is welded on the outer wall of the outer support sleeve (13), the electric telescopic rod (14) is fixedly installed inside the outer support sleeve (13), and the top of the electric telescopic rod (14) is fixedly connected with the platform mechanism (2); platform mechanism (2) include ceiling subassembly (21), supporting platform (22), installing frame (23), defeated material passageway (24) and material frame (25), ceiling subassembly (21) fixed mounting is on supporting platform (22), and the lateral wall of supporting platform (22) is fixed to set up installing frame (23), installing frame (23) and the one end intercommunication of defeated material passageway (24), and the other end of defeated material passageway (24) stretches into in material frame (25), and material frame (25) clamp is in material frame butt-joint groove (12).
2. A green building support platform facilitating rapid construction according to claim 1, wherein: ceiling subassembly (21) is by shed roof (211), upper shaft cover (212), lower shaft sleeve (213), even axle (214) and knob (215) are constituteed, the bottom surface and upper shaft sleeve (212) fixed connection of shed roof (211), the inside suit of upper shaft sleeve (212) is even axle (214), the bottom of even axle (214) is fixed in the inside of lower shaft sleeve (213), lower shaft sleeve (213) are fixed on the top surface of supporting platform (22), movable mounting knob (215) on upper shaft sleeve (212), the screw rod part of knob (215) stretches into the inside of upper shaft sleeve (212) and the outer wall laminating of even axle (214).
3. A green building support platform facilitating rapid construction according to claim 1, wherein: the supporting platform (22) comprises a platform outer frame (221), a platform bottom plate (222), a load reduction groove (223), a buckle (224), a hook (225), an escalator component (226) and a mounting shaft (227), the inside bottom surface fixed mounting platform bottom plate (222) of platform outer frame (221), set up in the platform outer frame (221) of left and right sides and subtract burden groove (223), the subtract burden groove (223) and installing frame (23) fixed connection that set up on the platform outer frame (221) of left side, the top and the lower axle sleeve (213) fixed connection of platform outer frame (221), the front outer wall of platform outer frame (221) sets up the export, the left side outer wall mounting buckle (224) in exit, buckle (224) meet with trip (225), trip (225) are through axle movable mounting on staircase subassembly (226), staircase subassembly (226) are through installation axle (227) and platform outer frame (221) movable sleeve joint.
4. A green building support platform facilitating rapid construction according to claim 3, wherein: the top surface of the platform bottom plate (222) is provided with a plurality of groups of water permeable holes (2221), the water permeable holes (2221) are communicated with the inner cavity of the hollow platform bottom plate (222), the side wall of the platform bottom plate (222) is provided with a water outlet (2222), and the size of the platform bottom plate (222) is the same as that of a plane structure formed by four groups of frame plates (15).
5. A green building support platform facilitating rapid construction according to claim 3, wherein: the escalator component (226) comprises a static escalator frame (2261), a dynamic escalator side frame (2262), a containing groove (2263), a rotating ring (2264), a left escalator frame (2265) and a right escalator frame (2266), the top of the static escalator frame (2261) is fixedly sleeved with a mounting shaft (227) fixed on a platform outer frame (221), the inner walls of two sides of the static escalator frame (2261) are both set to be hollow structures, the inner walls of two sides of the static escalator frame (2261) are movably sleeved with the dynamic escalator side frame (2262), the inner outer wall of the inner side of the dynamic escalator side frame (2262) is processed into the containing groove (2263), the rotating ring (2264) is fixedly mounted in the containing groove (2263) on the inner side and connected with the left escalator frame (2265), the rotating ring (2264) mounted in the containing groove (2263) on the right side is connected with the right escalator frame (2266), and the inner concave grillage at the right end of the left escalator frame (2265), the left end face of the right ladder board frame (2266) protrudes outwards, and the left ladder board frame (2265) and the right ladder board frame (2266) are spliced to form a ladder pedal structure.
6. A green building support platform facilitating rapid construction according to claim 1, wherein: the material conveying channel (24) is a corrugated square pipe component made of plastics, and the material conveying channel (24) is accommodated in the mounting frame (23) in a shrinkage shape in an unused state.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202010977531.1A CN112160570A (en) | 2020-09-16 | 2020-09-16 | Green building supporting platform convenient to quick construction |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202010977531.1A CN112160570A (en) | 2020-09-16 | 2020-09-16 | Green building supporting platform convenient to quick construction |
Publications (1)
Publication Number | Publication Date |
---|---|
CN112160570A true CN112160570A (en) | 2021-01-01 |
Family
ID=73858165
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202010977531.1A Pending CN112160570A (en) | 2020-09-16 | 2020-09-16 | Green building supporting platform convenient to quick construction |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN112160570A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN115977363A (en) * | 2022-12-15 | 2023-04-18 | 中国十九冶集团有限公司 | Operation rack for repairing water-cooled furnace cover of refining furnace |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101884626B1 (en) * | 2017-09-28 | 2018-08-02 | 유남호 | Scaffold connected by the rack method |
CN208168295U (en) * | 2018-04-04 | 2018-11-30 | 浙江峰邦机械科技有限公司 | A kind of construction scaffold convenient for storage |
CN109113315A (en) * | 2018-09-12 | 2019-01-01 | 孙勇军 | A kind of multi-functional construction platform |
CN210263827U (en) * | 2019-05-29 | 2020-04-07 | 浙江中闳建设有限公司 | Scaffold for building construction |
CN210369825U (en) * | 2019-07-12 | 2020-04-21 | 陈招妹 | But carrying frame is built in height-adjusting formula room |
CN210530292U (en) * | 2019-08-17 | 2020-05-15 | 广东振晟建设工程有限公司 | Scaffold for building |
CN210738049U (en) * | 2019-09-11 | 2020-06-12 | 陕西能源职业技术学院 | Can sun-proof rain-proof building engineering scaffold frame |
-
2020
- 2020-09-16 CN CN202010977531.1A patent/CN112160570A/en active Pending
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101884626B1 (en) * | 2017-09-28 | 2018-08-02 | 유남호 | Scaffold connected by the rack method |
CN208168295U (en) * | 2018-04-04 | 2018-11-30 | 浙江峰邦机械科技有限公司 | A kind of construction scaffold convenient for storage |
CN109113315A (en) * | 2018-09-12 | 2019-01-01 | 孙勇军 | A kind of multi-functional construction platform |
CN210263827U (en) * | 2019-05-29 | 2020-04-07 | 浙江中闳建设有限公司 | Scaffold for building construction |
CN210369825U (en) * | 2019-07-12 | 2020-04-21 | 陈招妹 | But carrying frame is built in height-adjusting formula room |
CN210530292U (en) * | 2019-08-17 | 2020-05-15 | 广东振晟建设工程有限公司 | Scaffold for building |
CN210738049U (en) * | 2019-09-11 | 2020-06-12 | 陕西能源职业技术学院 | Can sun-proof rain-proof building engineering scaffold frame |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN115977363A (en) * | 2022-12-15 | 2023-04-18 | 中国十九冶集团有限公司 | Operation rack for repairing water-cooled furnace cover of refining furnace |
CN115977363B (en) * | 2022-12-15 | 2024-04-02 | 中国十九冶集团有限公司 | Operating bench for repairing water-cooled furnace cover of refining furnace |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN112160570A (en) | Green building supporting platform convenient to quick construction | |
CN219326994U (en) | Movable hanging basket device | |
CN216516769U (en) | Construction lifting platform for erecting steel pipe frame | |
CN218487567U (en) | Scaffold welding equipment | |
CN211548666U (en) | Scaffold with protective device for plastering wall top | |
CN211007574U (en) | Concrete pouring operation rack for building floor slab | |
CN210177931U (en) | Scaffold for building construction | |
CN205023638U (en) | Protection device in gap between construction elevator well and floor | |
CN114735154A (en) | Method for building film type LNG (liquefied Natural gas) cabin bottom floor stairs | |
CN219261698U (en) | Stable integral climbing steel platform die carrier | |
CN221321725U (en) | Scaffold protection device for building construction | |
CN210482963U (en) | Height-adjustable movable construction platform for steel structure | |
CN221917352U (en) | Multifunctional ascending ladder | |
CN217128893U (en) | Scaffold | |
CN221524177U (en) | Adjustable platform for high-rise outer wall construction | |
CN218145445U (en) | Load pushing tool and device | |
CN218843675U (en) | Scaffold | |
CN211622697U (en) | Anti-falling device for building construction | |
CN220267171U (en) | Building scaffold with detachable structure | |
CN215798218U (en) | Portable compact brake lifter for wind driven generator | |
CN215167790U (en) | A carrier frame for municipal works and room are built | |
CN221778298U (en) | Portable dolly convenient to bridge side crane span structure construction | |
CN212562387U (en) | Steel construction operation frame | |
CN220395117U (en) | Building safety construction platform | |
CN210975576U (en) | Anti-falling device for bridge construction |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20210101 |
|
RJ01 | Rejection of invention patent application after publication |