Nothing Special   »   [go: up one dir, main page]

CN111597690B - Method for establishing electric vehicle charging equipment demand coefficient calculation model - Google Patents

Method for establishing electric vehicle charging equipment demand coefficient calculation model Download PDF

Info

Publication number
CN111597690B
CN111597690B CN202010337480.6A CN202010337480A CN111597690B CN 111597690 B CN111597690 B CN 111597690B CN 202010337480 A CN202010337480 A CN 202010337480A CN 111597690 B CN111597690 B CN 111597690B
Authority
CN
China
Prior art keywords
charging
access
probability
time
electric vehicle
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202010337480.6A
Other languages
Chinese (zh)
Other versions
CN111597690A (en
Inventor
孟焕平
吴斌
龙海珊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hunan Architectural Design Institute Group Co ltd
Original Assignee
Hunan Architectural Design Institute Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hunan Architectural Design Institute Ltd filed Critical Hunan Architectural Design Institute Ltd
Priority to CN202010337480.6A priority Critical patent/CN111597690B/en
Publication of CN111597690A publication Critical patent/CN111597690A/en
Application granted granted Critical
Publication of CN111597690B publication Critical patent/CN111597690B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/20Design optimisation, verification or simulation

Landscapes

  • Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Computer Hardware Design (AREA)
  • Evolutionary Computation (AREA)
  • Geometry (AREA)
  • General Engineering & Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • Charge And Discharge Circuits For Batteries Or The Like (AREA)

Abstract

The invention relates to a method for establishing a coefficient calculation model required by electric vehicle charging equipment, which comprises the following steps of: step one, data processing; secondly, setting model input and output parameters; fitting out probability distribution curves of access time and charging duration according to the access event data set; step four, defining a charging matrix; and (5) obtaining a required coefficient. The value of the adjusted required coefficient Kx is more targeted and closer to the actual use condition, the calculation result is more in line with the actual condition, the capacity selection of the transformer of the power distribution system designed according to the algorithm is much smaller than that of the traditional rough algorithm, the requirements of the corresponding switch breaking capacity and the short-circuit tolerance capacity of the power distribution cabinet are reduced, and the manufacturing cost is saved.

Description

Method for establishing electric vehicle charging equipment demand coefficient calculation model
Technical Field
The invention relates to the field of electric vehicle charging technology design, in particular to a method for establishing a coefficient calculation model required by electric vehicle charging equipment.
Background
At present, the existing charging pile power distribution load calculation generally adopts the following formula:
Figure BDA0002467889670000011
in the calculation mode, the input power of all charging equipment in a place is directly accumulated, and then multiplied by a uniform required coefficient Kx value to obtain the calculation power of the charging equipment.
The charging piles of different types are different in use conditions, the probability of large-area simultaneous use of a large number of 7kW alternating-current charging piles is very low, and the demand coefficient is also very low; the possibility of using a small amount of high-power direct-current charging piles at the same time is very high.
In most cases, the value of this coefficient is suggested to be 0.8, but there is no proper theory or practical measure for this value.
For parking lots with different properties, the charging rules are different, and it is not reasonable to determine the Kx value as a uniform value.
Disclosure of Invention
Aiming at the defects of the prior art, the invention provides the method for establishing the calculation model of the required coefficient of the electric vehicle charging equipment, which has more pertinence in the value of the required coefficient and is closer to the actual use condition.
The technical scheme adopted by the invention for solving the technical problems is as follows: the method for establishing the coefficient calculation model required by the electric vehicle charging equipment comprises the following steps:
step 1, data processing: converting the access time and the charging time in the original access event data set into minutes;
step 2, setting model input and output parameters, wherein:
model input parameters: the access time interval is: a is 1 (ii) a The charging time interval is: a is a 2 (ii) a The access time segmentation points are: b is a mixture of 1 ,b 2 ,b 3 (ii) a The number n of charging piles;
the model output is: the required coefficients corresponding to the n charging piles;
step 3, fitting out a probability distribution curve of access time and charging duration according to the access event data set, wherein:
the access time probability distribution curve fitting step is as follows:
step 311: to b is paired with 1 :00~b 2 :00,b 2 :00~b 3 :00,b 3 :00~b 1 00 the access event frequencies of the three interval time periods are fitted according to unimodal lognormal distribution to obtain three function relations: f. of 1 ,f 2 ,f 3
f 1 ,f 2 ,f 3 Each represents b 1 :00~b 2 :00,b 2 :00~b 3 :00,b 3 :00~b 1 00 an access event frequency fitting function of the interval;
step 312: obtaining the i-th interval i.a of the vehicle 1 ~(i+1)·a 1 Access probability function f (i);
the charging time length probability distribution curve fitting step is as follows:
step 321: the charging time of all charging events is fitted according to the single-peak Gauss to obtain the charging timeRelation of fitting function f 4
Step 322: the charging time length is obtained to belong to the jth category, namely: j.a 2 ~(j+1)·a 2 A probability function g (j);
step 4, defining a charging matrix: the method comprises the following steps:
step 41, the access probability of each time slot obtained in step 312 is:
Figure BDA0002467889670000021
step 42, ranking the access probability of each time slot in step 41 to obtain:
Figure BDA0002467889670000031
in the above ordering, the following are satisfied:
Figure BDA0002467889670000032
p represents an access probability value of a certain access time period; t represents a corresponding certain access time period;
step 43, calculating coefficients of the n charging piles: the ordered access probability is normalized and corrected to obtain the corrected access probability
Figure BDA0002467889670000033
Figure BDA0002467889670000034
The charging matrix of the n charging piles is recorded as M:
Figure BDA0002467889670000035
in the above formula, M is n x 1440 dimension charging matrix j An n x 1440 dimensional charging matrix corresponding to the j charging mode;
step 5, obtaining a required coefficient: let line vector e = (1, \8230;, 1) 1×n If the row vector y = e · M is the sum of each column of the matrix M, and k = max { y } is the estimation coefficient of n piles;
e is an n-dimensional row vector of all 1 s, y = e · M is a 1440-dimensional row vector, and the elements are the sum of each column of the matrix M.
In a preferred embodiment of the method for establishing the model of calculating the required coefficient of the electric vehicle charging device, in step 312, the access time fitting function is specifically:
Figure BDA0002467889670000036
in a preferred embodiment of the method for establishing a model of calculating a required coefficient of an electric vehicle charging device, in step 322, the charging duration correction probability specifically includes:
Figure BDA0002467889670000041
in the above formula: jmax represents the total number of charging modes,
Figure BDA0002467889670000042
dmax represents the maximum charge duration in the data set.
In a preferred embodiment of the method for establishing the model for calculating the required coefficient of the electric vehicle charging equipment, in step 1, the event frequency is obtained by segmentation to obtain sample points, and then the probability distribution curve of the access time and the charging duration is fitted by performing gaussian fitting according to the sample points.
In a preferred embodiment of the method for establishing the model of calculating the demand factor of the electric vehicle charging equipment, in step 322, the charging duration x of the jth charging mode j Can be set to the maximum value: x is the number of j =(j+1)·a 2
In the electricity provided by the inventionIn a preferred embodiment of the method for establishing the coefficient calculation model required by the electric vehicle charging equipment, in step 43, m is set rc Is a matrix M j Row r and column c, wherein: r ∈ {0,1,2, \8230;, n }, c ∈ {0,1,2, … 1439}, defined as follows:
when r.a 1 +x j <At 1440:
Figure BDA0002467889670000043
when r.a 1 +x j At more than or equal to 1440:
Figure BDA0002467889670000051
compared with the prior art, the method for establishing the coefficient calculation model required by the electric vehicle charging equipment has the beneficial effects that: the value of the adjusted required coefficient Kx is more targeted and closer to the actual use condition, the calculation result is more in line with the actual condition, the capacity of the transformer of the power distribution system designed according to the algorithm is more selected than that of the traditional rough algorithm, the corresponding requirements on the switch breaking capacity and the short-circuit tolerance capacity of the power distribution cabinet are reduced, and the manufacturing cost is saved.
Drawings
In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the drawings used in the description of the embodiments will be briefly introduced below.
Fig. 1 is a value curve diagram of required coefficient Kx obtained by using the calculation model of the present invention for the actual data of a parking lot provided by the present invention.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
The method for establishing the coefficient calculation model required by the electric vehicle charging equipment comprises the following steps:
step 1, data processing: converting the Access time and the charging time length in the original Access event data set into minutes, and simultaneously respectively modifying the list into 'Access' and 'Duration' to be used as identification marks of software;
step 2, setting model input and output parameters, wherein:
model input parameters: the access time interval is: a is 1 (ii) a The charging time interval is: a is 2 (ii) a The access time segmentation points are: b 1 ,b 2 ,b 3 (ii) a The number n of charging piles;
the model output is: the required coefficients corresponding to the n charging piles;
and 3, fitting an access time and charging duration probability distribution curve according to the access event data set, wherein:
the fitting method of the embodiment comprises the following steps: firstly, the event frequency is calculated in a segmented manner to obtain a sample point, and then Gaussian fitting is carried out according to the sample point, wherein the charging time is specifically taken as an example:
calculating frequency freq of the charging time length according to the charging time length interval, such as: 0 to a 2 Interval frequency of freq 0 Then the 0 th sample point is (0,freq) 0 );
Accordingly, the ith sample point represents the ith interval number and the ith interval i · a 1 ~(i+1)·a 1 Frequency of (d): (i, freq) i ) (ii) a For these sample points { (i, freq) i ) And fitting unimodal normal distribution.
The access time probability distribution curve fitting step is as follows:
step 311: to b is paired with 1 :00~b 2 :00,b 2 :00~b 3 :00,b 3 :00~b 1 00 the access event frequency of the time periods of the three intervals is fitted according to unimodal lognormal distribution to obtain three functional relations: f. of 1 ,f 2 ,f 3
f 1 ,f 2 ,f 3 Each represents b 1 :00~b 2 :00,b 2 :00~b 3 :00,b 3 :00~b 1 00 access event frequency fitting function of interval section;
step 312: obtaining the i-th interval i.a of the vehicle 1 ~(i+1)·a 1 The access probability function f (i) of (a) is:
Figure BDA0002467889670000071
the charging time length probability distribution curve fitting step is as follows:
step 321: fitting the charging time lengths of all charging events according to a single-peak Gaussian to obtain a charging time length fitting function relation f 4
Step 322: the charging time period is obtained to belong to the jth category, namely: j.a 2 ~(j+1)·a 2 The probability function g (j) of (c) is (it is required that the sum of the probabilities is 1):
Figure BDA0002467889670000072
in the above formula: jmax represents the total number of charging modes,
Figure BDA0002467889670000073
dmax represents the maximum charge duration in the dataset;
the charging time length x of the jth charging mode can be simply determined j Set to the maximum value: x is the number of j =(j+1)·a 2 The unimodal Gaussian distribution is normal distribution.
Step 4, defining a charging matrix: the charging model mathematical matrix is manufactured according to the embodiment, and the specific idea is as follows:
assuming that the charging pile is a charging pile, namely selecting the highest point on a probability curve of an access time point as the access time point, wherein the matrix has only one row at the moment, redistributing the probability of the access time point, calculating the matrix for P times (P is the total number of charging modes), multiplying each time by the probability distribution of corresponding access time length, and then summing to obtain a final coefficient;
assuming that two charging piles are adopted, namely, the highest point and the next highest point on the probability curve of the access time point are selected as the access time points, the matrix has only two rows at the moment, the probability of the access time points is redistributed, P times (P is the total number of charging modes) are calculated for the matrix, and the probability distribution of each time multiplied by the corresponding access time duration is summed to obtain a final coefficient;
and the rest are repeated.
The defining a charging matrix comprises the steps of:
step 41, the access probability of each time slot obtained in step 312 is:
Figure BDA0002467889670000081
step 42, sequencing the access probability of each time period in step 41 to obtain:
Figure BDA0002467889670000082
in the above ordering, the following are satisfied:
Figure BDA0002467889670000083
p represents the access probability value of accessing a certain access time period; t represents a corresponding certain access time period;
step 43, calculating coefficients of the n charging piles: the ordered access probability is normalized and corrected to obtain the corrected access probability
Figure BDA0002467889670000084
Figure BDA0002467889670000085
Recording the charging matrix of the n charging piles as M:
Figure BDA0002467889670000086
in the above formula, M is n x 1440 dimension charging matrix j An n × 1440 charging matrix corresponding to the j charging mode;
let m rc Is a matrix M j Row r, column c elements of (a); wherein:
r ∈ {0,1,2, \8230;, n }, c ∈ {0,1,2, \8230, 1439}, defined as follows:
when r.a 1 +x j <At 1440:
Figure BDA0002467889670000087
when r.a 1 +x j At more than or equal to 1440:
Figure BDA0002467889670000091
step 4, obtaining a required coefficient: let line vector e = (1, \8230;, 1) 1×n If the row vector y = e · M is the sum of each column of the matrix M, then k = max { y } is the estimation coefficient of n piles;
e is an n-dimensional row vector of all 1 s, y = e · M is a 1440-dimensional row vector, and the elements are the sum of each column of the matrix M.
According to the method, two probability distribution curves of an access time point and a charging time length are fitted through a mathematical model according to an existing access event data set (the more the data is, the better the data is), and then a series of required coefficient values are obtained through calculation. This conclusion is unique for a particular sample library and is very targeted, i.e. for charging events of a certain type of parking lot (when the number of samples is sufficient, the same type of parking lot can be considered to obey the same probability distribution), if the charging event sample data set of another type of parking lot is replaced, conclusions for other types of parking lots can also be drawn.
Specifically, according to the actual data of a certain parking lot, the required coefficient Kx obtained by using the calculation model of the present invention takes the following values:
Figure BDA0002467889670000092
Figure BDA0002467889670000101
fitting was performed according to the data in the table above and the curve is shown in figure 1.
The comparison between the traditional required coefficient value and the required coefficient value of the invention is as follows:
A. taking values according to the demand coefficient before modification, the final calculation load of a parking lot provided with 200 7kW alternating-current charging piles is 1120kW (assuming that the efficiency = 1). The calculation process is as follows:
total Kx =0.8
Then Pjs =0.8, 200, 7, 1120kW
The required distribution equipment parameters are as follows
A transformer: 1600kVA
Bus bar: 3150A
Breaking capacity of the circuit breaker: 40kA
Setting value of the incoming line breaker: 3200A
B. According to the modified value of the demand coefficient, the final calculation load of a parking lot provided with 200 7kW alternating-current charging piles is 280kW (assuming that the efficiency = 1). The calculation process is as follows:
Kx=0.2
then Pjs =0.2, 200, 7=280kW
The required distribution equipment parameters are as follows
A transformer: 400kVA
Bus bar: 800A
Breaking capacity of the circuit breaker: 15kA
Setting value of the incoming line breaker: 800A
The value of the adjusted required coefficient Kx is more targeted and closer to the use condition, the calculation result is more practical, the capacity of the transformer of the power distribution system designed according to the algorithm is much smaller than that of the transformer in the prior art, the corresponding requirements on the switch breaking capacity and the short-circuit tolerance capacity of the power distribution cabinet are reduced, and the manufacturing cost is saved.
The above description is only an embodiment of the present invention, and not intended to limit the scope of the present invention, and all modifications of equivalent structures and equivalent processes, which are made by the present specification, or directly or indirectly applied to other related technical fields, are included in the scope of the present invention.

Claims (6)

1. A method for establishing a model for calculating a coefficient required by electric vehicle charging equipment is characterized by comprising the following steps of: the method comprises the following steps:
step 1, data processing: converting the access time and the charging time in the original access event data set into minutes;
step 2, setting model input and output parameters, wherein:
model input parameters: the access time interval is: a is 1 (ii) a The charging time interval is: a is 2 (ii) a The access time segmentation points are: b 1 ,b 2 ,b 3 (ii) a The number n of charging piles;
the model output is: the required coefficients corresponding to the n charging piles;
and 3, fitting an access time and charging duration probability distribution curve according to the access event data set, wherein:
the access time probability distribution curve fitting step is as follows:
step 311: to b is 1 :00~b 2 :00,b 2 :00~b 3 :00,b 3 :00~b 1 00 the frequency of the access events in the three interval time periods is fitted according to unimodal lognormal distribution to obtain three functional relations: f. of 1 ,f 2 ,f 3
f 1 ,f 2 ,f 3 Each represents b 1 :00~b 2 :00,b 2 :00~b 3 :00,b 3 :00~b 1 00 an access event frequency fitting function of the interval;
step 312: obtaining the i-th section i.a of the vehicle 1 ~(i+1)·a 1 Access probability function f (i);
the charging time length probability distribution curve fitting step is as follows:
step 321: fitting the charging time lengths of all charging events according to a single-peak Gaussian to obtain a charging time length fitting function relation f 4
Step 322: the charging time period is obtained to belong to the jth category, namely: j.a 2 ~(j+1)·a 2 A probability function g (j);
step 4, defining a charging matrix: the method comprises the following steps:
step 41, the access probability of each time slot obtained in step 312 is:
Figure FDA0002467889660000021
step 42, ranking the access probability of each time slot in step 41 to obtain:
Figure FDA0002467889660000022
in the above ordering, the following are satisfied:
Figure FDA0002467889660000023
p represents an access probability value of a certain access time period; t represents a corresponding certain access time period;
step 43, calculating coefficients of the n charging piles: the access probability after sequencing is normalized and corrected to obtain the corrected access probability
Figure FDA0002467889660000024
Figure FDA0002467889660000025
The charging matrix of the n charging piles is recorded as M:
Figure FDA0002467889660000026
in the above formula, M is n x 1440 dimension charging matrix j An n x 1440 dimensional charging matrix corresponding to the j charging mode;
step 5, obtaining a required coefficient: let a row vector e = (1, \8230;, 1) 1×n If the row vector y = e · M is the sum of each column of the matrix M, then k = max { y } is the estimation coefficient of n piles;
e is an n-dimensional row vector of all 1 s, y = e · M is a 1440-dimensional row vector, and the elements are the sum of each column of the matrix M.
2. The electric vehicle charging equipment demand coefficient calculation model according to claim 1, characterized in that: in step 312, the access time fitting function specifically includes:
Figure FDA0002467889660000031
3. the electric vehicle charging equipment demand coefficient calculation model according to claim 1, characterized in that: in step 322, the charging duration correction probability specifically includes:
Figure FDA0002467889660000032
in the above formula: jmax represents the total number of charging modes,
Figure FDA0002467889660000033
dmax represents the maximum charge duration in the data set.
4. The electric vehicle charging equipment demand coefficient calculation model of claim 1, characterized in that: in the step 1, the event frequency is calculated in a segmented manner to obtain sample points, and then the probability distribution curves of the access time and the charging duration are fitted by a Gaussian fitting method according to the sample points.
5. The electric vehicle charging equipment demand coefficient calculation model of claim 1, characterized in that: in the step 322, the charging duration x of the jth charging mode j Can be set to the maximum value: x is the number of j =(j+1)·a 2
6. The electric vehicle charging equipment demand coefficient calculation model of claim 1, characterized in that: in the step 43, let m rc Is a matrix M j Row r and column c, wherein: r ∈ {0,1,2, \8230;, n }, c ∈ {0,1,2, … 1439}, defined as follows:
when r.a 1 +x j <At 1440:
Figure FDA0002467889660000034
when r.a 1 +x j When the mass is more than or equal to 1440:
Figure FDA0002467889660000041
CN202010337480.6A 2020-04-26 2020-04-26 Method for establishing electric vehicle charging equipment demand coefficient calculation model Active CN111597690B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010337480.6A CN111597690B (en) 2020-04-26 2020-04-26 Method for establishing electric vehicle charging equipment demand coefficient calculation model

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010337480.6A CN111597690B (en) 2020-04-26 2020-04-26 Method for establishing electric vehicle charging equipment demand coefficient calculation model

Publications (2)

Publication Number Publication Date
CN111597690A CN111597690A (en) 2020-08-28
CN111597690B true CN111597690B (en) 2023-04-07

Family

ID=72183585

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010337480.6A Active CN111597690B (en) 2020-04-26 2020-04-26 Method for establishing electric vehicle charging equipment demand coefficient calculation model

Country Status (1)

Country Link
CN (1) CN111597690B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112487665B (en) * 2020-12-18 2022-09-09 天津博迈科海洋工程有限公司 Method for calculating actual demand coefficient of ocean engineering electrical equipment based on probability statistics

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108376985A (en) * 2018-02-02 2018-08-07 国家电网公司 A kind of electric vehicle charging load model is established and node voltage computational methods
WO2018157691A1 (en) * 2017-02-28 2018-09-07 国网江苏省电力公司常州供电公司 Active distribution network safety quantifying method
CN108944531A (en) * 2018-07-24 2018-12-07 河海大学常州校区 A kind of orderly charge control method of electric car
CN109359389A (en) * 2018-10-18 2019-02-19 东北大学 City electric car charging decision method based on typical load dynamic game
CN109460853A (en) * 2018-09-29 2019-03-12 中国电力科学研究院有限公司 A kind of electric car charging workload demand determines method and system
CN110020505A (en) * 2019-04-28 2019-07-16 三峡大学 Extensive charging pile plan model modeling method based on small data

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2018157691A1 (en) * 2017-02-28 2018-09-07 国网江苏省电力公司常州供电公司 Active distribution network safety quantifying method
CN108376985A (en) * 2018-02-02 2018-08-07 国家电网公司 A kind of electric vehicle charging load model is established and node voltage computational methods
CN108944531A (en) * 2018-07-24 2018-12-07 河海大学常州校区 A kind of orderly charge control method of electric car
CN109460853A (en) * 2018-09-29 2019-03-12 中国电力科学研究院有限公司 A kind of electric car charging workload demand determines method and system
CN109359389A (en) * 2018-10-18 2019-02-19 东北大学 City electric car charging decision method based on typical load dynamic game
CN110020505A (en) * 2019-04-28 2019-07-16 三峡大学 Extensive charging pile plan model modeling method based on small data

Also Published As

Publication number Publication date
CN111597690A (en) 2020-08-28

Similar Documents

Publication Publication Date Title
CN111327377B (en) Method, device, equipment and storage medium for field intensity prediction
CN106549396B (en) Multi-objective probability reactive power optimization method for power distribution network
CN110380444B (en) Capacity planning method for distributed wind power orderly access to power grid under multiple scenes based on variable structure Copula
CN113837444A (en) Trading clearing optimization method for virtual power plant participating in multiple markets
US11264799B2 (en) Submodular load clustering with robust principal component analysis
CN111597690B (en) Method for establishing electric vehicle charging equipment demand coefficient calculation model
CN105469316B (en) Method and system for calculating theoretical line loss between any two points of power distribution network
Taylor et al. Optimal operation of grid-tied energy storage systems considering detailed device-level battery models
CN114580251A (en) Method and device for analyzing charging load of electric vehicle in power distribution area
CN112595906B (en) Method for judging abnormal operation of transformer area
Jain et al. Control F-policy for Markovian retrial queue with server breakdowns
CN114862229A (en) Power quality evaluation method and device, computer equipment and storage medium
CN112365164B (en) Energy characteristic portrait method for medium and large energy users based on improved density peak value rapid search clustering algorithm
Li et al. Impact of PHEV in active distribution network under gas station network attack
CN114865673B (en) Micro-grid load storage collaborative optimization method, device, equipment and storage medium
CN114757548B (en) Wind power energy storage equipment regulation performance evaluation method constructed by adopting scene
CN114611869B (en) Low-voltage station area station household identification method
CN115327418A (en) Lithium battery internal resistance identification method, storage medium and electronic device
CN115061046A (en) Battery working condition identification method and device, automobile and electronic equipment
CN115310647A (en) Multi-stage random planning energy scheduling method and system considering non-predictability
CN110912162A (en) Method and device for determining scheme of energy storage device
EP3460732B1 (en) Dispatching method and system based on multiple levels of steady state production rate in working benches
CN114742285B (en) Construction method and application of resident power consumption mode prediction model
CN118693883A (en) Optimal control method of distributed energy storage system based on multi-time sequence cloud edge cooperation
JP2002074360A (en) Method for indexing in feature vector data space

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: 410208 No. 65, Fuxiang Road, Yuelu District, Changsha City, Hunan Province

Patentee after: Hunan Architectural Design Institute Group Co.,Ltd.

Address before: 410012 middle section of Pingtang Avenue, Yuelu District, Changsha City, Hunan Province

Patentee before: HUNAN ARCHITECTURAL DESIGN INSTITUTE LTD.