CN110528703A - Building built-in part and positioning precast floor slab - Google Patents

Building built-in part and positioning precast floor slab Download PDF

Info

Publication number
CN110528703A
CN110528703A CN201910830101.4A CN201910830101A CN110528703A CN 110528703 A CN110528703 A CN 110528703A CN 201910830101 A CN201910830101 A CN 201910830101A CN 110528703 A CN110528703 A CN 110528703A
Authority
CN
China
Prior art keywords
connector sleeve
connecting hole
building built
main body
floor
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910830101.4A
Other languages
Chinese (zh)
Inventor
不公告发明人
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Tianlin High Tech Co Ltd
Original Assignee
Guangdong Mountain Public Building Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Mountain Public Building Technology Co Ltd filed Critical Guangdong Mountain Public Building Technology Co Ltd
Priority to CN201910830101.4A priority Critical patent/CN110528703A/en
Publication of CN110528703A publication Critical patent/CN110528703A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/38Connections for building structures in general
    • E04B1/41Connecting devices specially adapted for embedding in concrete or masonry
    • E04B1/4114Elements with sockets
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B5/00Floors; Floor construction with regard to insulation; Connections specially adapted therefor
    • E04B5/02Load-carrying floor structures formed substantially of prefabricated units
    • E04B5/023Separate connecting devices for prefabricated floor-slabs
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B5/00Floors; Floor construction with regard to insulation; Connections specially adapted therefor
    • E04B5/02Load-carrying floor structures formed substantially of prefabricated units
    • E04B5/04Load-carrying floor structures formed substantially of prefabricated units with beams or slabs of concrete or other stone-like material, e.g. asbestos cement
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/38Connections for building structures in general
    • E04B1/41Connecting devices specially adapted for embedding in concrete or masonry
    • E04B2001/4192Connecting devices specially adapted for embedding in concrete or masonry attached to concrete reinforcing elements, e.g. rods or wires

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Joining Of Building Structures In Genera (AREA)

Abstract

The present invention discloses a kind of building built-in part, including fixed part (21), and the first side of the fixed part (21) is fixedly provided with the first connector sleeve (211);It is opposite with first side to second side of the fixed part (21) be fixedly provided with the second connector sleeve (212).Building built-in part of the present invention can punch floor to avoid in construction, improve the convenience of construction.In addition, invention additionally discloses one kind to avoid the punching in construction, the convenience of construction is improved, while enhancing surface aesthetics and with can be by the positioning precast floor slab of machine recognition positioning function.

Description

Building built-in part and positioning precast floor slab
Technical field
The present invention relates to a kind of floor more particularly to a kind of building built-in part and positioning precast floor slabs.
Background technique
In the construction process of the low floor building such as civilian self-built housing, wall and floor are usually used and first build mould Plate pours the mode of cementitious material again to form, and wall can be completed in form removal after pouring into the concrete setting in die cavity Basic forming.And after wall molding, it is also necessary to which the smallpox of wall face and floor to wall carries out decoration construction, to be set Metope texture and perception needed for meter.When constructing to wall body decoration using equipment, generally require to position equipment, such as When using robot to wall surface spraying, it is necessary first to using the location hole of slab surfaces, be positioned at the positioning mechanism of robot In location hole, and then robot is fixed on construction location, is then just able to achieve automated construction.In addition, in the day to floor During flower face is decorated, it is also desirable to so that decoration is fixedly connected on soffit using connecting hole.
However, since existing concrete floor is after pouring molding, surface and bottom surface are all not no location holes, because This needs the table first to floor before robot is to wall construction operation and before ornament is installed in the smallpox face to floor Face and bottom surface drilling, could further construct.Not only increase difficulty of construction in this way, constructs and inconvenient;Moreover, in drilling, Often the concrete surface layer of surrounding brill is split or bores bad, influences the structure of floor, in addition, these drillings after the completion of construction such as Fruit can seriously affect the aesthetics of floor without repairing, and repair the workload that will increase construction, reduce the convenient of construction Property.
Summary of the invention
It avoids punching floor in construction the purpose of the present invention is to provide one kind, improves the building of the convenience of construction Built-in fitting.
Another object of the present invention is to provide one kind to avoid the punching in construction, improves the convenience of construction, increases simultaneously The positioning precast floor slab of strong surface aesthetics.
To achieve the goals above, building built-in part provided by the invention includes fixed part, the first side of the fixed part It is fixedly provided with the first connector sleeve;It is opposite with first side to second side of the fixed part be fixedly provided with the second connection Set.
Compared with prior art, the first connector sleeve and the are arranged by the opposite sides in the fixed part due to the present invention Two connector sleeves, when building built-in part of the present invention is embedded in floor in advance, the opposite sides of floor expose first connector sleeve and Therefore second connector sleeve when the first side of floor carries out construction operation, can use the first connector sleeve and carry out to construction equipment Connection positioning, so that construction equipment connection is stronger reliable, assembly and disassembly are more convenient, to improve the convenience of construction.Also, When second side of floor carries out construction operation, directly ornament can be connect with the second connector sleeve, make ornament connection more Add fast and easy and stable and firm.In addition, since building built-in part has preset the first connector sleeve and the second connector sleeve is determined Position, therefore, in construction can to avoid to floor the first side and the second side perforating, the step of not only simplifying construction improve The convenience of construction, and avoid boring and split floor, keep the surface of floor more beautiful.In addition, the machine constructed on floor can To readily identify first connector sleeve and the second connector sleeve, to reach the function of quickly positioning, construction efficiency is improved.
Preferably, first connector sleeve is equipped with the first connecting hole, second connector sleeve is equipped with the second connecting hole.
Preferably, the fixed part is in flat structure.
Preferably, the center overlapping of axles of first connecting hole and the second connecting hole.
Preferably, the inner wall of the first connecting hole inner wall and/or second connecting hole is equipped with screw thread.The spiral shell is set Line can be such that construction equipment or ornament is directly connected thereto, and not only stable connection is secured, and convenient and fast connection, and raising is applied Work efficiency rate.
Preferably, the side of the fixed part, the lateral surface of first connector sleeve and/or second connector sleeve it is outer Side is set as that the rough surface of frictional force or adhesive force can be enhanced.The rough surface can guarantee to fix stronger reliable.
Preferably, the diameter of the fixed part be greater than first connector sleeve outer diameter and second connector sleeve it is outer Diameter.
Preferably, the aperture of first connecting hole is greater than the aperture of second connecting hole.
Preferably, the fixed part and first connector sleeve and the second connector sleeve are in integrated formed structure.
Preferably, the quantity of second connecting hole is multiple.
A kind of positioning precast floor slab, including floor main body and the building built-in part, the building built-in part are set to In the floor main body, and first connecting hole exposes to the first side of the floor main body, and second connecting hole is exposed In second side of the floor main body.
Preferably, the outer end face of first connector sleeve is lower than or flushes in the first side surface of the floor main body, institute The outer end face for stating the second connector sleeve is lower than or flushes in the second side surface of the floor main body.
Preferably, multiple building built-in parts are arranged, so that multiple first connecting holes and multiple described The lateral and/or vertical arrangement of each self-forming of two connecting holes, for navigating or positioning.
Preferably, being equipped with reinforcing rib in the floor main body, the reinforcing rib extends the edge of the floor main body, with Convenient for being connect with other components.
Detailed description of the invention
Fig. 1 is the cross-sectional view of present invention positioning precast floor slab.
Fig. 2 is the structural schematic diagram of building built-in part of the present invention.
Fig. 3 is the cross-sectional view of building built-in part of the present invention.
Fig. 4 is the cross-sectional view of second of structure of building built-in part of the present invention.
Fig. 5 is the cross-sectional view of the third structure of building built-in part of the present invention.
Fig. 6 is the cross-sectional view of 4th kind of structure of building built-in part of the present invention.
Fig. 7 is the structural schematic diagram on present invention positioning precast floor slab surface.
Specific embodiment
For the technology contents that the present invention will be described in detail, construction feature, the effect realized, below in conjunction with embodiment and match Attached drawing is closed to be explained in detail.
As shown in Figure 1 to Figure 3, positioning precast floor slab 100 of the invention includes floor main body 1 and the building built-in part 2, the building built-in part 2 is set in the floor main body 1;Reinforcing rib 3, the reinforcing rib 3 are equipped in the floor main body 1 Extend the edge of the floor main body 1, in order to connect with other components.The building built-in part 2 includes fixed part 21, institute Fixed part 21 is stated in flat structure.First side 21a of the fixed part 21 is fixedly provided with the first connector sleeve 211, and described One connector sleeve 211 is equipped with the first connecting hole 213;It is opposite with the first side 21a to the fixed part 21 second side 21b it is solid Surely it is equipped with the second connector sleeve 212, second connector sleeve 212 is equipped with the second connecting hole 214.First connector sleeve 211 Outer end face is lower than or flushes in the first side surface 1a of the floor main body 1, the outer end face of second connector sleeve 212 be lower than or Flush in the surface second side 1b of the floor main body 1.In the present embodiment, the outer end face of first connector sleeve 211 with it is described First side 1a flush of floor main body 1, second side of the outer end face of second connector sleeve 212 and the floor main body 1 1b flush.First connecting hole 213 exposes to the first side 1a of the floor main body 1, outside second connecting hole 214 It is exposed to second side 1b of the floor main body 1.
Again referring to Fig. 3, the center overlapping of axles of first connecting hole 213 and the second connecting hole 214, first connection The central axis of hole 213 and the second connecting hole 214 is vertical with the surface of the fixed part 21.First connecting hole described in the present embodiment 213 aperture be greater than second connecting hole 214 aperture, certainly, the aperture of second connecting hole 214 can also be greater than or Equal to the aperture of first connecting hole 213.The inner wall of first connecting hole, 213 inner wall and second connecting hole 214 is equal Equipped with screw thread 21c.The screw thread 21c, which is arranged, in first connecting hole 213 can be such that construction equipment or ornament directly connects with it It connects, not only stable connection is secured, and convenient and fast connection, improves construction efficiency.In addition, the fixed part 21 and described first Connector sleeve 211 and the second connector sleeve 212 are in integrated formed structure, and the composite materials such as plastic cement, first connector sleeve can be used 211 and second connector sleeve 212 or solid, or it is hollow, such as in Fig. 3 the present embodiment the second connecting hole 214 threaded hollow shapes;Fig. 4 is the not threaded hollow shape of the second connecting hole;Fig. 5 is that the second connector sleeve 212 is solid shape; Fig. 6 is that 214 inner wall of the second connecting hole of the second connector sleeve 212 is in honeycomb structure;Certain second connecting hole 214 can also be with It is multiple and in being arranged in array.It, can be with by the way that second connector sleeve 212 and the second connecting hole 214 are arranged to more specifications It avoids that the secondary aperture of floor is caused in construction to destroy floor, and the construction stage is avoided to generate noise, influence the people of surrounding.
Again referring to Fig. 3, the surface of second side 21b of the first side 21a and fixed part 21 of the fixed part 21 is set For the rough surface 21d that can enhance frictional force or adhesive force.In addition, the lateral surface of first connector sleeve 211 and described second connects The lateral surface of female connector 212 also can be set to rough surface.The rough surface 21d can make the fixed part 21 fix stronger Reliably.Rough lines can be set on the rough surface 21d, to enhance its combination between the floor main body 1 Power improves the stability of connection.The diameter of the fixed part 21 connects greater than the outer diameter of first connector sleeve 211 and described second The outer diameter of female connector 212.
It in addition as shown in fig. 7, can be with pre-buried multiple building built-in parts 2, institute on positioning precast floor slab 100 of the invention Building built-in part 2 is stated in being arranged, can be transversely arranged or vertical array, or is vertically arranged laterally and simultaneously, it is adjacent Spacing between two building built-in parts 2 is 20 to 30 centimetres, so that multiple first connecting holes 213 form transverse direction Arrangement 101 and/or vertical array 102 and multiple second connecting holes 214 form transversely arranged and/or vertical array, when When using construction robot, these arrangements 101,102 form leading line and navigate to construction robot, and to building machine Device people positions, and keeps the construction location of construction robot more accurate.
In conjunction with shown in Fig. 1, the positioning precast floor slab 100 of the invention is formed by concreting, mixed pouring Before solidifying soil, a die cavity is barricaded as first with template, then the building built-in part 2 is positioned in die cavity, makes the fixed part 21 The first side surface 21a towards the floor main body 1 the first side surface 1a and with the first side surface 1a of the floor main body 1 In parallel, the surface second side 21b of the fixation towards the floor main body 1 the surface second side 1b and with the floor main body 1 The surface second side 1b it is parallel, into die cavity, casting concrete forms floor main body 1 again later, and then building built-in part 2 is buried In in the floor main body 1, into keeping first connecting hole 213 and the second connecting hole 214 exposed.Form removal after solidification, institute The the first side surface 1a for stating floor main body 1 forms the ground of a floor, and first connecting hole 213 is then used for and for example constructs The automation equipments such as robot connection, to position these equipment in these equipment constructions.Second side of the floor main body 1 The surface 1b then forms the ceiling of next floor, and second connecting hole 214 is then used to connect with ornaments such as such as pendent lamps, with It installs and slings these ornaments.
Compared with prior art, the first connector sleeve is arranged by the opposite sides in the fixed part 21 due to the present invention 211 and second connector sleeve 212, and be arranged on first connector sleeve 211 and the second connector sleeve 212 first connecting hole 213 and Second connecting hole 214, when the building built-in part 2 is embedded in advance in floor main body 1, the opposite sides of floor main body 1 exposes institute The first connecting hole 213 and the second connecting hole 214 are stated, it therefore, can be with when the first side 1a of floor main body 1 carries out construction operation Positioning is attached to construction equipment using the first connecting hole 213, so that construction equipment connection is stronger reliable, assembly and disassembly are more It is convenient, to improve the convenience of construction.Also, second side 1b of floor main body 1 carry out construction operation when, can directly by Ornament is connect with the second connecting hole 214, keeps ornament connection more convenient quick and stable and firm.In addition, due to building Built-in fitting 2 has preset the first connecting hole 213 and the second connecting hole 214, therefore, can be to avoid to floor main body 1 in construction The step of first side 1a and second side 1b is punched, and not only simplifies construction, improves the convenience of construction, and avoid the building Zuan Lie Plate keeps the surface of floor more beautiful.Connect in addition, the machine constructed in floor main body 1 can readily identify described first Female connector 211 and the second connector sleeve 212 improve construction efficiency to reach the function of quickly positioning.
The above disclosure is only a preferred example of the present invention, cannot limit the right model of the present invention with this certainly It encloses, therefore according to equivalent variations made by scope of the present invention patent, still falls within the range that the present invention is covered.

Claims (14)

1. a kind of building built-in part, it is characterised in that: including fixed part (21), the first side of the fixed part (21) is fixedly set Have the first connector sleeve (211), it is opposite with first side to second side of the fixed part (21) be fixedly provided with the second company Female connector (212).
2. building built-in part as described in claim 1, it is characterised in that: first connector sleeve (211) is equipped with the first connection Hole (213);Second connector sleeve (212) is equipped with the second connecting hole (214).
3. building built-in part as described in claim 1, it is characterised in that: the fixed part (21) is in flat structure.
4. building built-in part as described in claim 1, it is characterised in that: first connecting hole (213) and the second connecting hole (214) center overlapping of axles.
5. building built-in part as described in claim 1, it is characterised in that: the first connecting hole (213) inner wall and/or described The inner wall of second connecting hole (214) is equipped with screw thread.
6. building built-in part as described in claim 1, it is characterised in that: the side of the fixed part (21), described first connect The lateral surface of the lateral surface of female connector (211) and/or second connector sleeve (212) is set as can enhancing the thick of frictional force or adhesive force Matte (21d).
7. building built-in part as described in claim 1, it is characterised in that: the diameter of the fixed part (21) is greater than described first The outer diameter of the outer diameter of connector sleeve (211) and second connector sleeve (212).
8. building built-in part as described in claim 1, it is characterised in that: the aperture of first connecting hole (213) is greater than institute State the aperture of the second connecting hole (214).
9. building built-in part as described in claim 1, it is characterised in that: the fixed part (21) and first connector sleeve (211) and the second connector sleeve (212) is in integrated formed structure.
10. building built-in part as described in claim 1, it is characterised in that: the quantity of second connecting hole (214) is more It is a.
11. a kind of positioning precast floor slab, it is characterised in that: including described in floor main body (1) and any one of claims 1 to 10 Several building built-in parts (2), the building built-in part (2) is set in the floor main body (1), and first connecting hole (213) the first side (1a) of the floor main body (1) is exposed to, second connecting hole (214) exposes to the floor main body (1) second side (1b).
12. positioning precast floor slab as claimed in claim 11, it is characterised in that: the outer end face of first connector sleeve (211) Be lower than or flush in surface the first side (1a) of the floor main body (1), the outer end face of second connector sleeve (212) be lower than or Flush in surface second side (1b) of the floor main body (1).
13. positioning precast floor slab as claimed in claim 11, it is characterised in that: multiple building built-in part (2) arrangements are set It sets, so that multiple first connecting holes (213) and each self-forming of multiple second connecting holes (214) are laterally and/or vertical Arrangement, with for navigating or position.
14. positioning precast floor slab as claimed in claim 11, it is characterised in that: be equipped with reinforcing rib in the floor main body (1) (3), the reinforcing rib (3) extends the edge of the floor main body (1), in order to connect with other components.
CN201910830101.4A 2019-09-03 2019-09-03 Building built-in part and positioning precast floor slab Pending CN110528703A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910830101.4A CN110528703A (en) 2019-09-03 2019-09-03 Building built-in part and positioning precast floor slab

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910830101.4A CN110528703A (en) 2019-09-03 2019-09-03 Building built-in part and positioning precast floor slab

Publications (1)

Publication Number Publication Date
CN110528703A true CN110528703A (en) 2019-12-03

Family

ID=68666549

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910830101.4A Pending CN110528703A (en) 2019-09-03 2019-09-03 Building built-in part and positioning precast floor slab

Country Status (1)

Country Link
CN (1) CN110528703A (en)

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201739406U (en) * 2010-09-01 2011-02-09 鞍山重型矿山机器股份有限公司 Rubber spring of sieve plate
KR20120063638A (en) * 2010-12-08 2012-06-18 (주)한도공영 Multi connector for a simple -prefabricated structure
CN204919996U (en) * 2015-07-23 2015-12-30 中国新兴保信建设总公司 Pre -buried connection structure of secondary structure reinforcing bar sleeve
CN205063040U (en) * 2015-10-26 2016-03-02 河南省第二建设集团有限公司 Built -in fitting of building gallows
CN107246076A (en) * 2017-08-11 2017-10-13 中建安装工程有限公司 Recyclable magnetic thread embedded parts for assembled architecture
CN206591640U (en) * 2017-03-10 2017-10-27 天津力达科创金属制品有限公司 A kind of two-sided pass building built-in part
CN108625555A (en) * 2018-06-20 2018-10-09 长葛市长润钢结构有限公司 A kind of stair built-in fitting of perforation type
CN208219909U (en) * 2018-05-16 2018-12-11 江苏建筑职业技术学院 A kind of construction wall with built-in fitting
CN211312865U (en) * 2019-09-03 2020-08-21 广东山众建筑科技有限公司 Building embedded part and positioning prefabricated floor slab

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201739406U (en) * 2010-09-01 2011-02-09 鞍山重型矿山机器股份有限公司 Rubber spring of sieve plate
KR20120063638A (en) * 2010-12-08 2012-06-18 (주)한도공영 Multi connector for a simple -prefabricated structure
CN204919996U (en) * 2015-07-23 2015-12-30 中国新兴保信建设总公司 Pre -buried connection structure of secondary structure reinforcing bar sleeve
CN205063040U (en) * 2015-10-26 2016-03-02 河南省第二建设集团有限公司 Built -in fitting of building gallows
CN206591640U (en) * 2017-03-10 2017-10-27 天津力达科创金属制品有限公司 A kind of two-sided pass building built-in part
CN107246076A (en) * 2017-08-11 2017-10-13 中建安装工程有限公司 Recyclable magnetic thread embedded parts for assembled architecture
CN208219909U (en) * 2018-05-16 2018-12-11 江苏建筑职业技术学院 A kind of construction wall with built-in fitting
CN108625555A (en) * 2018-06-20 2018-10-09 长葛市长润钢结构有限公司 A kind of stair built-in fitting of perforation type
CN211312865U (en) * 2019-09-03 2020-08-21 广东山众建筑科技有限公司 Building embedded part and positioning prefabricated floor slab

Similar Documents

Publication Publication Date Title
CN106013530A (en) Reinforcement structure of concrete shear wall based on 3D printing
CN103993691B (en) A kind of integrated form flooring module and assembling method thereof
CN104532983A (en) Steel pipe concrete composite system of building and masonry construction method thereof
CN206495501U (en) A kind of cast-in-place concrete floor reserving hole template
CN204139377U (en) A kind of industrialization Light trabs and assembly connection external member thereof
CN106639261B (en) One kind is based on BIM and aluminum alloy mould plate correct embedment terminal box and construction method
CN110528703A (en) Building built-in part and positioning precast floor slab
CN211312865U (en) Building embedded part and positioning prefabricated floor slab
CN210888078U (en) Embedded box for hyperboloid structural veneer and hyperboloid veneer construction structure
CN208136933U (en) A kind of preformed bricks fetal membrane standard component
CN205791363U (en) A kind of electrical engineering positioning installation apparatus
CN105697885A (en) Conduit fixing device, prefabricated component mold, prefabricated component and installing structure
CN203066493U (en) Positioning die for precise construction of main reinforcement of pillar
CN206982952U (en) Fabricated shear wall embeds window frame finishing die
CN206784422U (en) Beam and foundation structure of building
CN206542144U (en) A kind of prefabricated integrated line box building element
CN207110066U (en) A kind of wall body built-in fitting
CN210116012U (en) Special-shaped boss gasket tool
CN203064953U (en) Steel member insertion type structure of elevator shaft
CN215802632U (en) Prefabricated component interface direct shear reinforced vertical hole and prefabricated component with vertical hole
CN203347136U (en) Hanging patterned decorating plate prefabricated member
CN220768524U (en) Disassembling-free template fixing device
CN207829570U (en) A kind of prefabricated assembled H profile steel buckling-restrained bracing member
CN109838023B (en) Method for marking installation direction of prefabricated laminated slab and special concrete column
CN221143555U (en) Prefabricated component of I-steel wall penetrating piece opening without dismantling form

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right

Effective date of registration: 20240320

Address after: 518109 Building 12, 12th Floor, Block A, Baoneng Science and Technology Park, Qinghu Community, Longhua Street, Longhua District, Shenzhen City, Guangdong Province

Applicant after: Guangdong Tianlin High Tech Co.,Ltd.

Country or region after: China

Address before: 510000 Room 405, building 4, No. 3, Hua'an Middle Road, Huadu District, Guangzhou City, Guangdong Province

Applicant before: GUANGDONG SHANZHONG ARCHITECTURAL TECHNOLOGY Co.,Ltd.

Country or region before: China

TA01 Transfer of patent application right