Nothing Special   »   [go: up one dir, main page]

CN110409244B - Composite bearing prefabricated road slab and prefabricated pavement construction method - Google Patents

Composite bearing prefabricated road slab and prefabricated pavement construction method Download PDF

Info

Publication number
CN110409244B
CN110409244B CN201910782599.1A CN201910782599A CN110409244B CN 110409244 B CN110409244 B CN 110409244B CN 201910782599 A CN201910782599 A CN 201910782599A CN 110409244 B CN110409244 B CN 110409244B
Authority
CN
China
Prior art keywords
pavement
prefabricated
slab
pile head
conical
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201910782599.1A
Other languages
Chinese (zh)
Other versions
CN110409244A (en
Inventor
朱利平
陈耀东
郭永成
张博楠
许占勇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Seventh Engineering Division Corp Ltd
Original Assignee
China Construction Seventh Engineering Division Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Seventh Engineering Division Corp Ltd filed Critical China Construction Seventh Engineering Division Corp Ltd
Priority to CN201910782599.1A priority Critical patent/CN110409244B/en
Publication of CN110409244A publication Critical patent/CN110409244A/en
Application granted granted Critical
Publication of CN110409244B publication Critical patent/CN110409244B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C19/00Machines, tools or auxiliary devices for preparing or distributing paving materials, for working the placed materials, or for forming, consolidating, or finishing the paving
    • E01C19/52Apparatus for laying individual preformed surfacing elements, e.g. kerbstones
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C5/00Pavings made of prefabricated single units
    • E01C5/06Pavings made of prefabricated single units made of units with cement or like binders
    • E01C5/08Reinforced units with steel frames

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Road Paving Structures (AREA)

Abstract

The invention provides a composite bearing prefabricated road slab and a prefabricated pavement construction method. Processing a composite bearing prefabricated road slab; rolling and tamping the original soil layer; paving a leveling layer on the original soil layer and tamping; hoisting the molded composite bearing prefabricated road panel to a construction road section and installing the composite bearing prefabricated road panel in place, fitting a primary static pressure with a leveling layer, and caulking the two adjacent composite bearing prefabricated road panels through waterproof mortar; drilling holes in the conical pile head holes in the composite bearing prefabricated road slab from top to bottom by using a small-sized drilling machine, and forming pillar pile pouring holes after soil is removed; and pouring concrete downwards through the upper part of the conical pile head hole until the concrete fills the inner cavities of the pillar pile pouring hole and the conical pile head hole, so as to form the pillar pile. The overall bearing capacity of the pavement slab is improved, and the adverse effect of the subsidence subgrade on the pavement is reduced; the integral connectivity of the prefabricated pavement and the base layer is enhanced, the lateral horizontal slippage of the prefabricated pavement is reduced, and the integral stability of the roadbed and the pavement is improved.

Description

Composite bearing prefabricated road slab and prefabricated pavement construction method
Technical Field
The invention relates to a composite bearing prefabricated road slab and a prefabricated pavement construction method.
Background
The prefabricated road surface is a road surface of which a surface layer is paved by cement concrete prefabricated blocks, and the prefabricated road mainly has two problems in the using process. Receive prefabricated road surface itself to assemble the shaping, wholly combine not well with the road bed, seal not tight, require high to the road matrix volume, later stage is along with road bed rainwater infiltration and inhomogeneous settlement scheduling problem, takes place the perk not smooth problem very easily. Resulting in cracking and breaking of the prefabricated pavement and the like. The requirement of the stability of the long-term load of the road cannot be met. Thereby causing difficulty in the popularization of the prefabricated road.
Disclosure of Invention
The invention aims to provide a composite bearing prefabricated road deck capable of bearing through a roadbed and a pillar pile in a composite mode, and the composite bearing prefabricated road deck is used for solving the technical problem that the load stability of the existing prefabricated road is influenced by the fact that a prefabricated road surface is tilted and cracked due to the fact that the roadbed is permeated by rainwater and unevenly settled; the invention also aims to provide a construction method of the prefabricated pavement using the composite bearing prefabricated pavement slab.
The technical scheme of the composite bearing prefabricated road slab is realized as follows: the composite bearing prefabricated road slab comprises a rectangular road surface body and a reinforcing steel bar frame positioned in the road surface body, wherein a plurality of pre-buried hook bolts are uniformly distributed on the upper part of the road surface body, the lower parts of the pre-buried hook bolts are fixedly welded with the reinforcing steel bar frame, a plurality of conical pile head holes which are small in size up and down are uniformly distributed on the road surface body so as to be matched with an axial top support and radial limiting matching of a reinforced concrete support pile poured in a roadbed, and a demolding layer which is convenient to separate from the reinforced concrete support pile when the demolding is carried out is arranged on the inner wall of each conical pile head hole.
On the basis of the scheme, the method is further improved in the following mode, wherein the demolding layer is a demolding agent layer which is brushed or a pre-buried PVC mold.
On the basis of the scheme, the diameter of the uppermost edge of the conical pile head hole is not less than 80mm, and the diameter of the lowermost edge of the conical pile head hole is 2-4 times of the diameter of the uppermost edge.
On the basis of the scheme, the thickness of the pavement body is further improved to be 20 mm.
On the basis of the scheme, the distance between any two adjacent conical pile head holes is 1 m.
The technical scheme of the construction method of the prefabricated pavement is realized as follows: the construction method of the prefabricated pavement comprises the following steps:
s1, processing the composite bearing prefabricated pavement slab, placing a steel bar frame in a mould, uniformly welding a plurality of pre-embedded hook bolts on the steel bar frame, arranging conical moulds with release agents coated on the outer surfaces in the mould at intervals, pouring concrete, condensing and then detaching the conical moulds;
s2, flattening the original soil layer of the construction road section, and then rolling and tamping;
s3, paving sand, lime soil and cement on the original soil layer to form a leveling layer, and tamping after leveling;
s4, hoisting the molded composite bearing prefabricated road panels to a construction road section and installing the composite bearing prefabricated road panels in place, fitting the composite bearing prefabricated road panels with a leveling layer by preliminary static pressure, and caulking the adjacent composite bearing prefabricated road panels by waterproof mortar;
s5, drilling holes in the conical pile head holes on the composite bearing prefabricated road slab from top to bottom by using a small-sized drilling machine, and forming pillar pile pouring holes after soil is removed;
and S6, pouring concrete downwards through the upper part of the conical pile head hole until the concrete fills the inner cavities of the pillar pile pouring hole and the conical pile head hole to form the pillar pile.
On the basis of the scheme, the method is further improved in that before S6, reinforcing steel bars are placed in the post pile pouring holes.
On the basis of the scheme, the method is further improved in the following way that when the composite bearing prefabricated road slab is dismantled, the composite bearing prefabricated road slab is lifted by embedding the hook bolts.
On the basis of the scheme, the method is further improved in that before S6, a release agent is coated on the inner wall of each conical pile head hole or a PVC mold is pre-buried.
By adopting the technical scheme, the invention has the beneficial effects that: according to the invention, the prefabricated road slab is provided with the plurality of conical pile head holes so as to be matched with the support piles penetrating into the roadbed through the conical surface, and the conical surface is utilized for accurate limiting. The prefabricated pavement slab adopts a roadbed and support piles combined bearing system, so that the overall bearing capacity of the pavement slab is improved, and the adverse effect of a settled roadbed on the pavement is reduced; the road deck adopts the cast-in-place support piles, so that the integral connectivity of the prefabricated road surface and the base layer is enhanced, and the lateral horizontal slippage of the prefabricated road surface is reduced; the prefabricated road deck construction system is simple to install and disassemble and convenient and fast to construct; the prefabricated road slab can be repeatedly circulated, so that the cost is saved, and the prefabricated road slab is green and environment-friendly; through the pillar pile hole, carry out the secondary slip casting to road deck board and road bed gap, improved the overall stability on road bed and road surface.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings used in the description of the embodiments or the prior art will be briefly described below, and it is obvious that the drawings in the following description are only some embodiments of the present invention, and for those skilled in the art, other drawings can be obtained according to these drawings without creative efforts.
FIG. 1 is a schematic structural view of a raw soil layer after flattening, rolling and tamping;
FIG. 2 is a schematic structural diagram of a leveling layer compacted on a raw soil layer;
FIG. 3 is a schematic view of the structure after the prefabricated pavement slab is installed on the leveling layer;
FIG. 4 is a schematic structural view of a small-sized drilling machine drilling and clearing a pillar pile pouring hole;
FIG. 5 is a schematic structural view of a post pile formed after pouring;
FIG. 6 is a schematic view of the prefabricated road deck being lifted and removed;
FIG. 7 is a schematic view of the internal structure of a prefabricated road deck;
wherein: 1-original soil layer, 2-leveling layer, 3-prefabricated road panel, 31-pavement body, 32-reinforcing steel bar frame, 33-embedded hook bolt, 34-conical pile head hole, 35-demoulding layer, 4-pillar pile pouring hole, 5-pillar pile, 51-reinforcing steel bar and 6-small drilling machine.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
The concrete embodiment of the construction method of the prefabricated pavement comprises the following steps:
s1, as shown in fig. 7, processing the composite load-bearing prefabricated pavement slab 3, placing the steel bar frames 32 in the mold, uniformly welding a plurality of pre-embedded hook bolts 33 on the steel bar frames 32, arranging conical molds with release agents coated on the outer surfaces in the mold at intervals, pouring concrete, condensing, and then detaching the conical molds; the composite bearing prefabricated pavement slab 3 comprises a rectangular pavement body 31 and a reinforcing steel bar frame 32 positioned in the pavement body 31, a plurality of embedded hook bolts 33 are uniformly distributed on the upper part of the pavement body 31, the lower parts of the embedded hook bolts 33 are fixedly welded with the reinforcing steel bar frame 32, a plurality of conical pile head holes 34 which are small at the upper part and big at the lower part are uniformly distributed on the pavement body 31 so as to be matched with the axial jacking and radial limiting of reinforced concrete support piles 5 poured in a roadbed, and a demoulding layer 35 which is convenient to separate from the reinforced concrete support piles 5 when being dismantled is arranged on the inner wall of each conical pile head hole 34. The demoulding layer 35 is a demoulding agent layer which is coated or a pre-buried PVC mould. The diameter of the uppermost edge of the conical pile head hole 34 is not less than 80mm, and the diameter of the lowermost edge of the conical pile head hole 34 is 2-4 times of the diameter of the uppermost edge. The thickness of the pavement body 31 is 20 mm. The distance between any two adjacent conical pile head holes 34 is 1 meter.
S2, as shown in figure 1, flattening the original soil layer 1 of the construction road section, and then rolling and tamping;
s3, paving sand, lime soil and cement on the original soil layer 1 to form a leveling layer 2, and tamping after leveling, as shown in figure 2;
s4, as shown in figure 3, hoisting the molded composite load-bearing prefabricated road panels 3 to a construction road section and installing the same in place, fitting the leveling layer 2 with preliminary static pressure, and caulking the two adjacent composite load-bearing prefabricated road panels 3 through waterproof mortar;
s5, as shown in figure 4, drilling each conical pile head hole 34 on the composite bearing prefabricated road panel 3 from top to bottom by using a small-sized drilling machine 6, and forming a post pile pouring hole 4 after soil removal;
s6, as shown in fig. 5, pouring concrete downwards through the upper part of the conical pile head hole 34 until the concrete fills the inner cavities of the post pile pouring hole 4 and the conical pile head hole 34, so as to form the post pile 5.
Before S6, the reinforcing bars 51 are placed in the post pile casting holes 4. As shown in fig. 6, when the composite load-bearing prefabricated road slab 3 is removed, the composite load-bearing prefabricated road slab is lifted by embedding the hook bolts 33. Before S6, a release agent or a pre-buried PVC mold is coated on the inner wall of each conical pile head hole 34.
Specifically, the concrete size of the prefabricated pavement slab 3 can be designed according to the width of the road, and the thickness and the reinforcing bars of the pavement slab can be designed according to the bearing requirements of the pavement. The thickness of the temporary road prefabricated pavement slab 3 on a general construction site is 20mm, the reinforcing bars are C12@200mm double-layer bidirectional, and the thickness of the protective layer is 25 mm. The lower part of the road slab is provided with conical molds with the distance of 1 meter. The spacing may be adjusted according to the actual application. And hoisting bolts are embedded at four corners of the pavement slab. After the road deck plate is poured and molded, the top circular hole is not less than 8 centimeters, the bottom circular diameter is not less than 2 times of the top and not more than 4 times, and the road deck plate is convenient to remove in the later period. The hole 4 is pour to the stake that prefabricated pavement slab 3 left, adopts mushroom circular cone shape hole design, and big end down, hole lateral wall scribble drawing of patterns isolating agent or pre-buried PVC membrane, had both satisfied the integral connection of pavement slab and fender pile. But also ensures the possibility of later hoisting and dismantling.
The specific embodiment of the composite load-bearing prefabricated road slab of the invention is the same as the specific embodiment of the prefabricated road slab in the specific embodiment of the prefabricated pavement construction method of the invention, and the detailed description is omitted.
The above description is only for the purpose of illustrating the preferred embodiments of the present invention and is not to be construed as limiting the invention, and any modifications, equivalents, improvements and the like that fall within the spirit and principle of the present invention are intended to be included therein.

Claims (9)

1. The composite bearing prefabricated pavement slab is characterized by comprising a rectangular pavement body and a reinforcing steel bar frame positioned in the pavement body, wherein a plurality of pre-embedded hook bolts are uniformly distributed on the upper part of the pavement body, the lower parts of the pre-embedded hook bolts are welded and fixed with the reinforcing steel bar frame, a plurality of conical pile head holes which are small in top and large in bottom are uniformly distributed on the pavement body so as to be matched with reinforced concrete support piles poured in a roadbed in an axial jacking manner and in a radial limiting manner, and a demolding layer which is convenient to be separated from the reinforced concrete support piles during dismantling is arranged on the inner wall of each conical pile head hole; the prefabricated road slab is provided with a plurality of conical pile head holes so as to be matched with the support piles punctured into the roadbed through the conical surfaces, and the conical surfaces are utilized for accurate limiting; the prefabricated pavement adopts a roadbed and pillar pile combined bearing system, so that the overall bearing capacity of the pavement slab is improved; the cast-in-place support column piles are adopted, the overall connectivity of the prefabricated pavement and the base course is enhanced, and the lateral horizontal slippage of the prefabricated pavement is reduced.
2. The composite load-bearing precast pavement slab of claim 1, wherein the release layer is a painted release layer or a pre-buried PVC mold.
3. The composite load-bearing precast road slab according to claim 1 or 2, wherein the diameter of the uppermost edge of the tapered pile head hole is not less than 80mm, and the diameter of the lowermost edge of the tapered pile head hole is 2-4 times the diameter of the uppermost edge.
4. The composite load-bearing precast pavement slab of claim 3, wherein the pavement body has a thickness of 20 mm.
5. The composite load-bearing precast road panel of claim 3, wherein the distance between any two adjacent conical pile head holes is 1 m.
6. The construction method of the prefabricated pavement is characterized by comprising the following steps of:
s1, processing the composite bearing prefabricated pavement slab, placing a steel bar frame in a mould, uniformly welding a plurality of pre-embedded hook bolts on the steel bar frame, arranging conical moulds with release agents coated on the outer surfaces in the mould at intervals, pouring concrete, condensing and then detaching the conical moulds;
the composite bearing prefabricated pavement slab comprises a rectangular pavement body and a reinforcing steel bar frame positioned in the pavement body, wherein a plurality of pre-embedded hook bolts are uniformly distributed on the upper part of the pavement body, the lower parts of the pre-embedded hook bolts are welded and fixed with the reinforcing steel bar frame, a plurality of conical pile head holes which are small in top and large in bottom are uniformly distributed on the pavement body so as to be matched with reinforced concrete support piles poured in a roadbed in an axial jacking and radial limiting manner, and a demoulding layer which is convenient to separate from the reinforced concrete support piles during dismantling is arranged on the inner wall of each conical pile head hole;
s2, flattening the original soil layer of the construction road section, and then rolling and tamping;
s3, paving sand, lime soil and cement on the original soil layer to form a leveling layer, and tamping after leveling;
s4, hoisting the molded composite bearing prefabricated road panels to a construction road section and installing the composite bearing prefabricated road panels in place, fitting the composite bearing prefabricated road panels with a leveling layer by preliminary static pressure, and caulking the adjacent composite bearing prefabricated road panels by waterproof mortar;
s5, drilling holes in the conical pile head holes on the composite bearing prefabricated road slab from top to bottom by using a small-sized drilling machine, and forming pillar pile pouring holes after soil is removed;
and S6, pouring concrete downwards through the upper part of the conical pile head hole until the concrete fills the inner cavities of the pillar pile pouring hole and the conical pile head hole to form the pillar pile.
7. The precast pavement construction method according to claim 6, wherein reinforcing bars are installed in the post pile casting holes before S6.
8. The precast pavement construction method according to claim 6 or 7, wherein the composite load-bearing precast pavement slab is lifted by embedding hook bolts when being removed.
9. The precast pavement construction method according to claim 6 or 7, wherein a release agent or a pre-buried PVC mold is coated on an inner wall of each tapered pile head hole before S6.
CN201910782599.1A 2019-08-23 2019-08-23 Composite bearing prefabricated road slab and prefabricated pavement construction method Active CN110409244B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910782599.1A CN110409244B (en) 2019-08-23 2019-08-23 Composite bearing prefabricated road slab and prefabricated pavement construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910782599.1A CN110409244B (en) 2019-08-23 2019-08-23 Composite bearing prefabricated road slab and prefabricated pavement construction method

Publications (2)

Publication Number Publication Date
CN110409244A CN110409244A (en) 2019-11-05
CN110409244B true CN110409244B (en) 2021-06-25

Family

ID=68368558

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910782599.1A Active CN110409244B (en) 2019-08-23 2019-08-23 Composite bearing prefabricated road slab and prefabricated pavement construction method

Country Status (1)

Country Link
CN (1) CN110409244B (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112227125B (en) * 2020-10-26 2022-05-17 温州展业建设工程有限公司 Roadbed construction method for reinforced concrete pavement of highway
CN112458818B (en) * 2020-12-08 2022-03-08 长沙理工大学 High-comfort assembly type cement concrete pavement repairing structure, construction method and pavement structure overturning device
CN113322740B (en) * 2021-06-25 2022-07-26 江苏广吴建设园林有限公司 Reinforced asphalt concrete road and construction method thereof
CN114922019B (en) * 2022-06-30 2023-04-28 重庆科技学院 Slope pavement construction method

Family Cites Families (22)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB570763A (en) * 1943-10-26 1945-07-20 Guest Keen & Nettlefolds Ltd Improvements relating to floors, paving or roads
JPS6059206A (en) * 1983-09-09 1985-04-05 三星産業株式会社 Crack repairing method of paved road
IT245362Y1 (en) * 1998-05-05 2002-03-20 Sai & Smi S N C Di Maran R Gar MODULAR MODULAR ELEMENTS FOR THE CONSTRUCTION OF NON PERMANENT FLOORS
DE19948003A1 (en) * 1999-10-06 2001-04-12 Boegl Max Bauunternehmung Gmbh Precast reinforced concrete slab
JP2004150181A (en) * 2002-10-31 2004-05-27 Keeper Co Ltd Work execution method for flexible plate
NL1031929C2 (en) * 2006-05-31 2007-12-03 Heijmans Infrastructuur & Mili Steel bridge improving method for road, involves covering upper side of steel cover plate with prefabricated concrete deck, and adjusting concrete deck in vertical direction with respect to plate
CN102242537A (en) * 2010-11-29 2011-11-16 有利华建材(惠州)有限公司 Cyclically used temporary pavement platen, and method for paving temporary pavement therewith
CN103103903A (en) * 2011-11-14 2013-05-15 江苏广卫建设有限公司 Pavement slab
CN103334361B (en) * 2013-06-26 2015-10-28 中国建筑股份有限公司 Prefabricated hollow steel bar concrete wear resistant road surface plate and pavement construction method
US9430943B2 (en) * 2013-07-23 2016-08-30 Newpark Mats & Integrated Services Llc Apparatus and methods for providing illuminated signals from a support surface
CN103422414B (en) * 2013-07-24 2016-01-06 福建士联建设有限公司 A kind of environmental-protection decorative permeable pavement structure and construction method thereof
CN103866670B (en) * 2014-02-28 2017-01-11 中国建筑股份有限公司 Fabricated vehicle bearing pavement and construction method thereof
CN205636397U (en) * 2016-03-24 2016-10-12 杭州江润科技有限公司 Assembled cement road surface structure
DE102017102821A1 (en) * 2017-02-13 2018-08-16 Kronimus Aktiengesellschaft Shock-proofing block and method for producing a sliding securing block
CN107022940B (en) * 2017-05-18 2019-09-20 百盛联合建设集团有限公司 Sidewalk structure and its construction method
CN206887667U (en) * 2017-07-05 2018-01-16 重庆科技学院 Roadbed based on prefabricated member collapses repair system
CN207812203U (en) * 2017-11-13 2018-09-04 福建乐动体育场材料有限公司 A kind of permeable terrace
CN207672354U (en) * 2017-12-14 2018-07-31 四川西南交大土木工程设计有限公司 Concrete pavement slab assembly connection structure
CN108385467B (en) * 2018-03-19 2019-02-26 陈长华 A kind of bridge road surface supporting pad plate
CN208762812U (en) * 2018-06-11 2019-04-19 中交一公局集团有限公司 Steel bearing plate connecting structure of assembled pavement
CN209162560U (en) * 2018-11-12 2019-07-26 福建省东方水泥制品有限公司 A kind of good water-permeable brick of blocking-proof result
CN109610263B (en) * 2018-12-27 2020-10-09 中铁十四局集团大盾构工程有限公司 Construction method of assembled construction access road

Also Published As

Publication number Publication date
CN110409244A (en) 2019-11-05

Similar Documents

Publication Publication Date Title
CN110409244B (en) Composite bearing prefabricated road slab and prefabricated pavement construction method
CN106854873B (en) Engineering method of prefabricated spliced open caisson type parking garage and parking garage
CN108560684B (en) Heavy-load traffic road inspection well ring and construction method thereof
CN107059667A (en) Door shape assembled armored concrete box culvert and its construction method
CN209555978U (en) A kind of cast-in-situ steel reinforced concrete manhole shaft shaping combined steel shuttering
CN110295627B (en) Construction method of road inspection well
CN111188355B (en) Super-gravity type anchorage shallow-buried foundation and construction method
CN206495233U (en) Door shape assembled armored concrete box culvert
CN104358275A (en) Construction method for deeper elevator well or water collecting well
CN108035379B (en) Comprehensive pipe gallery and construction method thereof
CN108978713B (en) Factory prefabricated elevator shaft pit and installation method thereof
CN103015328A (en) Continuous splicing construction method of pier column for jacking broken beam of bridge
KR101756965B1 (en) Height adjusting type maintanable rail track construction method and maintanance method using the same
CN101929245A (en) Thin webbed girder vertical construction method
CN108978699B (en) Land integral prefabricated bearing platform and production and installation method thereof
CN109811613B (en) Temporary ground facility and integrated construction method thereof
CN112112292A (en) Construction method for preventing concrete from permeating into two sides of post-cast strip of bottom plate of garage
CN217810304U (en) Multifunctional road construction prefabricated slab
CN206220537U (en) A kind of assembly type truss frame platform
CN214940226U (en) Take braced system work well
CN211498929U (en) Street lamp basis prefabricated construction
CN110306398B (en) Sectional beam-setting pretensioning staggered symmetrical tensioning prestressed tendon superposed assembly road and construction method thereof
WO2021258144A1 (en) Method for making a grated trench channel
CN105839824B (en) Shed deckhead construction method
CN101818501B (en) Construction method of reinforced concrete foundation on top of large-scale trenched pipe culvert

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information

Inventor after: Zhu Liping

Inventor after: Chen Yaodong

Inventor after: Guo Yongcheng

Inventor after: Zhang Bonan

Inventor after: Xu Zhanyong

Inventor before: Zhu Liping

Inventor before: Chen Yaodong

Inventor before: Guo Yongcheng

Inventor before: Zhang Bonan

Inventor before: Xu Zhanyong

CB03 Change of inventor or designer information
CB02 Change of applicant information

Address after: No.267, 15th Street, Jingkai, Zhengzhou, Henan Province, 450000

Applicant after: CHINA CONSTRUCTION SEVENTH ENGINEERING DIVISION Corp.,Ltd.

Address before: 450000 No. 116 Chengdong Road, Jinshui District, Henan, Zhengzhou

Applicant before: CHINA CONSTRUCTION SEVENTH ENGINEERING DIVISION Corp.,Ltd.

CB02 Change of applicant information
GR01 Patent grant
GR01 Patent grant