Nothing Special   »   [go: up one dir, main page]

CN115821997A - Construction method for actively controlling deformation of building through multi-row grouting - Google Patents

Construction method for actively controlling deformation of building through multi-row grouting Download PDF

Info

Publication number
CN115821997A
CN115821997A CN202211191743.2A CN202211191743A CN115821997A CN 115821997 A CN115821997 A CN 115821997A CN 202211191743 A CN202211191743 A CN 202211191743A CN 115821997 A CN115821997 A CN 115821997A
Authority
CN
China
Prior art keywords
grouting
pipe
deformation
hole
row
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202211191743.2A
Other languages
Chinese (zh)
Inventor
王振飞
冀叶涛
夏曾银
赵岗领
韩圣章
祁可录
何占江
王雷
于全胜
孟灵波
刘颖
马小龙
杜坤鹏
邢锦朝
郭华军
李现军
梁安平
张坦
范占海
饶杨
王刚
程雪松
郑刚
糜同年
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Tianjin Rail Transit Investment And Construction Co ltd
Tianjin University
China Railway Tunnel Group Co Ltd CRTG
CRTG Road and Bridge Engineering Co Ltd
Beijing China Railway Tunnel Construction Co Ltd
China Railway Investment Group Co Ltd
Original Assignee
China Railway Tianjin Rail Transit Investment And Construction Co ltd
Tianjin University
China Railway Tunnel Group Co Ltd CRTG
CRTG Road and Bridge Engineering Co Ltd
Beijing China Railway Tunnel Construction Co Ltd
China Railway Investment Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Tianjin Rail Transit Investment And Construction Co ltd, Tianjin University, China Railway Tunnel Group Co Ltd CRTG, CRTG Road and Bridge Engineering Co Ltd, Beijing China Railway Tunnel Construction Co Ltd, China Railway Investment Group Co Ltd filed Critical China Railway Tianjin Rail Transit Investment And Construction Co ltd
Priority to CN202211191743.2A priority Critical patent/CN115821997A/en
Publication of CN115821997A publication Critical patent/CN115821997A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

The invention discloses a construction method for actively controlling deformation of a building by multi-row grouting, which comprises the following steps: obtaining the number and the positions of a plurality of rows of grouting holes between the building structure to be rectified and the foundation pit and the range of grouting expansion areas in the grouting holes through theoretical calculation or numerical simulation calculation; preparing grouting pipes, wherein each grouting pipe consists of a pipe A and a pipe B which are bound together, the axes of the pipe A and the pipe B are parallel, the top surfaces of the pipe A and the pipe B are flush, the length of the pipe B is greater than that of the pipe A, and the area between the bottom wall of the pipe B and the bottom wall of the pipe A is a grouting expansion area; drilling a grouting hole by using a drilling machine according to a preset position; digging a foundation pit on the inner side of the underground diaphragm wall, measuring the horizontal deformation of the building structure to be rectified by using an instrument in a segmented mode, and inserting a grouting pipe into a grouting hole in the position corresponding to the horizontal deformation for grouting according to the horizontal deformation measuring result of the building structure when the horizontal deformation exceeds the alarm value set before engineering construction. The method can effectively increase the effect of deformation regulation and control.

Description

一种多排注浆主动控制建构筑物变形的施工方法A Construction Method for Actively Controlling the Deformation of Building Structures by Multiple Rows of Grouting

技术领域technical field

本发明涉及地下工程施工方法,具体涉及施工过程中控制隧道和地铁车站等建构筑物的水平变形的实施方法。The invention relates to an underground engineering construction method, in particular to an implementation method for controlling the horizontal deformation of structures such as tunnels and subway stations during the construction process.

背景技术Background technique

为开发地下空间而进行的基坑施工不可避免地引起周边土体产生变形,从而引发土体中隧道和地铁车站等的建构筑物产生变形。这给地铁线路等的结构安全和运营安全带来威胁,也对基坑设计水平及施工技术带来新的挑战。为减小基坑施工对邻近既有隧道等建构筑物的影响,需要采取必要的控制措施。现有的保护措施可分为主动保护措施和被动保护措施。The foundation pit construction for the development of underground space will inevitably cause deformation of the surrounding soil, which will lead to deformation of buildings such as tunnels and subway stations in the soil. This poses a threat to the structural safety and operational safety of subway lines, and also brings new challenges to the design level and construction technology of foundation pits. In order to reduce the impact of foundation pit construction on adjacent existing tunnels and other structures, it is necessary to take necessary control measures. Existing protection measures can be divided into active protection measures and passive protection measures.

主动控制措施主要包括注浆和水平支撑轴力伺服控制技术。目前,有关注浆抬升既有建筑物或者隧道的研究较多,而有关注浆控制隧道等建构筑物水平变形的研究较少,尚缺乏控制其水平变形的系统注浆理论及策略。传统注浆补偿技术的控制能力存在一定局限性,粗放的注浆方法忽略了对注浆顺序的研究,难以有效提高拟纠偏对象的变形效果,且对周边工程的建设存在影响,不能够最大化变形控制的效果。Active control measures mainly include grouting and horizontal support axial force servo control technology. At present, there are many studies on grouting uplifting existing buildings or tunnels, but less research on grouting to control the horizontal deformation of tunnels and other structures, and there is still a lack of systematic grouting theory and strategies to control their horizontal deformation. The control ability of the traditional grouting compensation technology has certain limitations. The extensive grouting method ignores the research on the grouting sequence, and it is difficult to effectively improve the deformation effect of the object to be corrected. It also has an impact on the construction of surrounding projects and cannot be maximized. The effect of the deformation control.

发明内容Contents of the invention

本发明的目的在于克服已有技术的缺点,提供一种可以高效地恢复隧道等建构筑物变形,且对周围其他结构不会产生影响的多排注浆主动控制建构筑物变形的施工方法。The purpose of the present invention is to overcome the shortcomings of the prior art and provide a construction method for actively controlling the deformation of structures such as tunnels with multiple rows of grouting that can efficiently restore the deformation of structures such as tunnels without affecting other surrounding structures.

为解决上述技术问题,通过以下的技术方案予以实现。In order to solve the above-mentioned technical problems, it is realized through the following technical solutions.

本发明提出一种多排注浆主动控制建构筑物变形的施工方法,包括以下步骤:The invention proposes a construction method for actively controlling the deformation of buildings and structures by multi-row grouting, which includes the following steps:

步骤一、通过理论计算或数值模拟计算得到位于拟纠偏建构筑物和基坑之间的多排注浆孔的数量和位置以及注浆孔内注浆膨胀区域的范围,多排注浆孔根据理论计算或数值模拟结果布置成两排、三排或更多排;Step 1. Obtain the number and position of the multiple rows of grouting holes located between the structure to be corrected and the foundation pit and the range of the grouting expansion area in the grouting holes through theoretical calculation or numerical simulation calculation. The multiple rows of grouting holes are based on theoretical Calculation or numerical simulation results are arranged in two, three or more rows;

步骤二、准备注浆管,每根注浆管由绑扎在一起的A管和B管组成,A管和B管的轴线平行且顶面平齐,所述B管的长度大于A管的长度,所述B管的底壁与A管的底壁之间的区域为注浆膨胀区域;Step 2. Prepare the grouting pipes. Each grouting pipe is composed of A pipe and B pipe bound together. The axes of A pipe and B pipe are parallel and the top surfaces are flush. The length of the B pipe is greater than the length of the A pipe. , the area between the bottom wall of the B pipe and the bottom wall of the A pipe is the grouting expansion area;

步骤三、按照步骤一设定的位置采用钻孔机钻注浆孔,在钻注浆孔过程中采用泥浆护壁;Step 3. Use a drilling machine to drill the grouting hole according to the position set in step 1, and use mud to protect the wall during the drilling of the grouting hole;

步骤四、在地连墙内侧开挖基坑,使用仪器分段测量拟纠偏建构筑物的水平变形,当水平变形超过工程施工前设定的报警值时,根据建构筑物的水平变形测量结果,在与水平变形相对应位置处的注浆孔中插入注浆管,然后执行以下注浆过程:Step 4: Excavate the foundation pit on the inner side of the ground connection wall, and use the instrument to measure the horizontal deformation of the structure to be corrected in sections. When the horizontal deformation exceeds the alarm value set before the construction, according to the measurement results of the horizontal deformation of the building Insert the grouting pipe into the grouting hole at the position corresponding to the horizontal deformation, and then perform the following grouting process:

第一步,从距离拟纠偏建构筑物较远的一排注浆孔开始注浆,在向注浆孔中的注浆管内注浆时,均先通过注浆管的B管注入水泥浆,直至整个注浆孔填满水泥浆;The first step is to start grouting from a row of grouting holes that are far away from the structure to be corrected. When grouting into the grouting pipe in the grouting hole, the grout is first injected through the B pipe of the grouting pipe until The entire grouting hole is filled with cement slurry;

第二步,通过注浆管的A管注入水玻璃,使得注浆孔内地表以下A管长度范围内水泥浆与水玻璃混合,进行封孔;In the second step, the water glass is injected through the A pipe of the grouting pipe, so that the cement slurry is mixed with the water glass within the length of the A pipe below the ground surface in the grouting hole, and the hole is sealed;

第三步,通过注浆管的B管注入双液浆;所述双液浆为由水泥浆和水玻璃混合制成;In the third step, the double liquid slurry is injected through the B pipe of the grouting pipe; the double liquid slurry is made by mixing cement slurry and water glass;

第四步,在注浆过程中,继续测量拟纠偏建构筑物的水平变形恢复情况,反复重复第一步至第三步,按照离拟调控区域由远及近的注浆顺序向各排注浆孔内的注浆管内注浆,直至拟纠偏建构筑物的水平变形降低至报警值以下。In the fourth step, during the grouting process, continue to measure the horizontal deformation recovery of the structure to be corrected, repeat the first step to the third step repeatedly, and grout to each row according to the grouting sequence from far to near to the area to be controlled The grouting pipe in the hole is grouted until the horizontal deformation of the structure to be corrected decreases below the alarm value.

本发明的有益成果为:The beneficial results of the present invention are:

1、通过由远及近的注浆顺序,先行注浆区域的土体对后续注浆一侧土体变形具有反力效应,使得后续注浆对与注浆方向相同侧土体水平位移作用效果更大,有效增大变形调控的效果。1. Through the sequence of grouting from far to near, the soil in the area of grouting in advance has a counter force effect on the deformation of the soil on the side of the subsequent grouting, so that the effect of subsequent grouting on the horizontal displacement of the soil on the same side as the grouting direction Larger, effectively increasing the effect of deformation control.

2、先行注浆区域的土体对后续注浆另一侧的土体变形具有遮挡效应,与注浆方向相反侧土体水平位移减小,可降低对注浆顺序另一侧建构筑物的影响。2. The soil in the first grouting area has a blocking effect on the deformation of the soil on the other side of the subsequent grouting, and the horizontal displacement of the soil on the side opposite to the grouting direction is reduced, which can reduce the impact on the structures on the other side of the grouting sequence .

3、高效经济,适用范围广,纠偏对象可以为隧道、地铁车站或基坑围护结构等多种建构筑物。3. Efficient and economical, with a wide range of applications, the correction object can be various buildings such as tunnels, subway stations or foundation pit enclosure structures.

附图说明Description of drawings

图1为注浆膨胀区域剖面图;Figure 1 is a sectional view of the grouting expansion area;

图2为单孔注浆流程示意图;Figure 2 is a schematic diagram of a single hole grouting process;

图3为各排注浆孔注浆顺序示意图;Fig. 3 is a schematic diagram of the grouting sequence of each row of grouting holes;

图4为注浆完成后土体水平位移效果示意图。Figure 4 is a schematic diagram of the horizontal displacement effect of the soil after the grouting is completed.

具体实施方式Detailed ways

为了使本发明的目的、方案和优点更加清晰,下面结合附图和一个具体实施案例对本发明作进一步的描述。In order to make the purpose, solution and advantages of the present invention clearer, the present invention will be further described below in conjunction with the accompanying drawings and a specific implementation case.

本发明方法的原理是,利用先行注浆区域的土体对后续注浆另一侧的土体变形的遮挡效应,根据拟纠偏对象的变形情况和附近其他建构筑物的位置情况,结合理论计算和数值模拟的结果,确定注浆孔的位置和数量,以增大对拟纠偏对象的控制效果,同时减小对附近其他建构筑物的负面影响。The principle of the method of the present invention is to use the shielding effect of the soil mass in the preceding grouting area on the deformation of the soil mass on the other side of the subsequent grouting, and combine theoretical calculation and As a result of numerical simulation, the location and number of grouting holes are determined to increase the control effect on the object to be corrected and reduce the negative impact on other nearby structures.

如图1-3所示,本发明的一种多排注浆主动控制建构筑物变形的实施方法,包括以下步骤:As shown in Figures 1-3, a method for implementing multi-row grouting to actively control the deformation of buildings and structures of the present invention includes the following steps:

步骤一、因基坑开挖等原因导致隧道或地铁车站等建构筑物发生水平变形时,通过理论计算或数值模拟(例如可以通过PLAXIS或FLAC等软件)计算得到位于拟纠偏建构筑物2和基坑3之间的多排注浆孔的数量和位置以及注浆孔内注浆膨胀区域1的范围,优选的,每排注浆孔的中心的连线与拟纠偏建构筑物2的轴线方向平行;多排注浆孔根据理论计算或数值模拟结果布置成两排、三排或更多排。注浆孔的孔径可以为50~60mm。Step 1. When horizontal deformation of structures such as tunnels or subway stations occurs due to excavation of foundation pits, etc., through theoretical calculation or numerical simulation (for example, software such as PLAXIS or FLAC), it is calculated that the structure 2 and the foundation pit located in the proposed deviation correction The number and position of the multiple rows of grouting holes between 3 and the scope of the grouting expansion area 1 in the grouting holes, preferably, the line of the center of each row of grouting holes is parallel to the axial direction of the structure 2 to be corrected; Multiple rows of grouting holes are arranged in two, three or more rows according to theoretical calculation or numerical simulation results. The diameter of the grouting hole may be 50-60 mm.

步骤二、准备注浆管,每根注浆管由绑扎在一起的A管和B管组成,A管和B管的轴线平行且顶面平齐,所述B管的长度大于A管的长度,所述B管的底壁与A管的底壁之间的区域为注浆膨胀区域1。注浆管底部开孔,方便浆液流出。可以通过调整A管和B管的长度控制注浆膨胀区域的大小。Step 2. Prepare the grouting pipes. Each grouting pipe is composed of A pipe and B pipe bound together. The axes of A pipe and B pipe are parallel and the top surfaces are flush. The length of the B pipe is greater than the length of the A pipe. , the area between the bottom wall of the B pipe and the bottom wall of the A pipe is the grouting expansion area 1 . The bottom of the grouting pipe is perforated to facilitate the flow of grout. The size of the grouting expansion area can be controlled by adjusting the length of pipe A and pipe B.

步骤三、按照步骤一设定的位置采用钻孔机钻注浆孔,在钻注浆孔过程中采用泥浆护壁,以防止塌孔。注浆孔的底标高与理论计算或数值模拟结果保持一致。Step 3. Use a drilling machine to drill the grouting hole according to the position set in step 1. During the drilling of the grouting hole, use mud to protect the wall to prevent the hole from collapsing. The bottom elevation of the grouting hole is consistent with the theoretical calculation or numerical simulation results.

步骤四、在地连墙内侧开挖基坑3,使用多台水准仪或全站仪等仪器分段测量拟纠偏建构筑物2的水平变形,拟纠偏建构筑物的测点根据测量规范沿其长度方向布置,当水平变形超过工程施工前根据相关建构筑物变形规范制定的报警值时,根据建构筑物的水平变形测量结果,在与水平变形相对应位置处的注浆孔中插入注浆管,然后执行以下注浆过程:Step 4: Excavate the foundation pit 3 on the inner side of the ground connection wall, and use multiple levels or total stations to measure the horizontal deformation of the structure 2 to be corrected in sections. The measuring points of the structure to be corrected are along its length according to the measurement specifications Layout, when the horizontal deformation exceeds the alarm value established according to the relevant building deformation specifications before construction, according to the horizontal deformation measurement results of the building, insert the grouting pipe into the grouting hole at the position corresponding to the horizontal deformation, and then execute The following grouting process:

第一步,从距离拟纠偏建构筑物2较远的一排注浆孔开始注浆,如图3所示,在向注浆孔中的注浆管内注浆时,均先通过注浆管的B管注入水泥浆,直至整个注浆孔填满水泥浆;The first step is to start grouting from a row of grouting holes that are far away from the structure 2 to be corrected. As shown in Figure 3, when grouting into the grouting pipe in the grouting hole, first pass through the grouting pipe. Pipe B injects cement slurry until the entire grouting hole is filled with cement slurry;

第二步,通过注浆管的A管注入水玻璃,使得注浆孔内地表以下A管长度范围内水泥浆与水玻璃混合,进行封孔;水泥浆水灰比优选的为0.6~0.7。In the second step, the water glass is injected through the A pipe of the grouting pipe, so that the cement slurry is mixed with the water glass within the length of the A pipe below the ground surface in the grouting hole, and the hole is sealed; the water-cement ratio of the cement slurry is preferably 0.6-0.7.

第三步,通过注浆管的B管注入双液浆,以控制土体变形。所述双液浆为由水泥浆和水玻璃两者混合而成。双液浆中水泥浆与水玻璃的体积比为3:1。水泥浆和水玻璃的混合液能够在短时间内迅速凝固,形成强度。The third step is to inject double liquid grout through the B pipe of the grouting pipe to control the soil deformation. The double liquid slurry is formed by mixing cement slurry and water glass. The volume ratio of cement slurry to water glass in double liquid slurry is 3:1. The mixture of cement slurry and water glass can quickly solidify in a short time to form strength.

第四步,在注浆过程中,继续测量拟纠偏建构筑物的水平变形恢复情况,反复重复第一步至第三步,按照离拟调控区域由远及近的注浆顺序向各排注浆孔内的注浆管内注浆,直至拟纠偏建构筑物的水平变形降低至报警值以下。In the fourth step, during the grouting process, continue to measure the horizontal deformation recovery of the structure to be corrected, repeat the first step to the third step repeatedly, and grout to each row according to the grouting sequence from far to near to the area to be controlled The grouting pipe in the hole is grouted until the horizontal deformation of the structure to be corrected decreases below the alarm value.

本实施方法的纠偏对象适用于隧道、地铁车站、基坑围护结构等多种建构筑物,适用范围广,变形控制效果好,同时对基坑的反力作用小。The deviation correction object of the implementation method is applicable to various structures such as tunnels, subway stations, foundation pit enclosure structures, etc., and has a wide application range, good deformation control effect, and small reaction force to the foundation pit.

注浆完成时及最终水平位移效果如图4所示,按照上述注浆顺序注浆完成后,对基坑侧的结构位移影响较小(如注浆孔左侧曲线所示),对拟调控区域影响效果显著(如注浆孔右侧曲线所示),即由于已进行前排注浆,后排注浆使得与注浆方向相同侧土体水平位移更大,而与注浆方向相反侧的土体水平位移更小,已进行注浆的土体会对后续的注浆效果具有反力效应和遮挡效应。The completion of grouting and the final horizontal displacement effect are shown in Figure 4. After the grouting is completed according to the above grouting sequence, the impact on the structural displacement on the side of the foundation pit is small (as shown by the curve on the left side of the grouting hole). The regional influence effect is significant (as shown by the curve on the right side of the grouting hole), that is, because the front row of grouting has been performed, the rear row of grouting makes the horizontal displacement of the soil body larger on the same side as the grouting direction, while the side opposite to the grouting direction The horizontal displacement of the soil is smaller, and the grouted soil will have a reaction force effect and a shielding effect on the subsequent grouting effect.

尽管上面结合附图对本发明的优选实施例进行了描述,但是本发明并不局限于上述的具体实施方式,上述的具体实施方式仅仅是示意性的,并不是限制性的,本领域的普通技术人员在本发明的启示下,在不脱离本发明宗旨和权利要求所保护的范围的情况下,还可以做出很多形式,这些均属于本发明的保护范围之内。Although the preferred embodiments of the present invention have been described above in conjunction with the accompanying drawings, the present invention is not limited to the above-mentioned specific embodiments. The above-mentioned specific embodiments are only illustrative and not restrictive. Those of ordinary skill in the art Under the enlightenment of the present invention, people can also make many forms without departing from the purpose of the present invention and the scope of protection of the claims, and these all belong to the protection scope of the present invention.

Claims (4)

1.一种多排注浆主动控制建构筑物变形的实施方法,其特征在于包括以下步骤:1. An implementation method for actively controlling the deformation of a multi-row grouting structure, characterized in that it comprises the following steps: 步骤一、通过理论计算或数值模拟计算得到位于拟纠偏建构筑物和基坑之间的多排注浆孔的数量和位置以及注浆孔内注浆膨胀区域的范围,多排注浆孔根据理论计算或数值模拟结果布置成两排、三排或更多排;Step 1. Obtain the number and position of the multiple rows of grouting holes located between the structure to be corrected and the foundation pit and the range of the grouting expansion area in the grouting holes through theoretical calculation or numerical simulation calculation. The multiple rows of grouting holes are based on theoretical Calculation or numerical simulation results are arranged in two, three or more rows; 步骤二、准备注浆管,每根注浆管由绑扎在一起的A管和B管组成,A管和B管的轴线平行且顶面平齐,所述B管的长度大于A管的长度,所述B管的底壁与A管的底壁之间的区域为注浆膨胀区域;Step 2. Prepare the grouting pipes. Each grouting pipe is composed of A pipe and B pipe bound together. The axes of A pipe and B pipe are parallel and the top surfaces are flush. The length of the B pipe is greater than the length of the A pipe. , the area between the bottom wall of the B pipe and the bottom wall of the A pipe is the grouting expansion area; 步骤三、按照步骤一设定的位置采用钻孔机钻注浆孔,在钻注浆孔过程中采用泥浆护壁;Step 3. Use a drilling machine to drill the grouting hole according to the position set in step 1, and use mud to protect the wall during the drilling of the grouting hole; 步骤四、在地连墙内侧开挖基坑,使用仪器分段测量拟纠偏建构筑物的水平变形,当水平变形超过工程施工前设定的报警值时,根据建构筑物的水平变形测量结果,在与水平变形相对应位置处的注浆孔中插入注浆管,然后执行以下注浆过程:Step 4: Excavate the foundation pit on the inner side of the ground connection wall, and use the instrument to measure the horizontal deformation of the structure to be corrected in sections. When the horizontal deformation exceeds the alarm value set before the construction, according to the measurement results of the horizontal deformation of the building Insert the grouting pipe into the grouting hole at the position corresponding to the horizontal deformation, and then perform the following grouting process: 第一步,从距离拟纠偏建构筑物较远的一排注浆孔开始注浆,在向注浆孔中的注浆管内注浆时,均先通过注浆管的B管注入水泥浆,直至整个注浆孔填满水泥浆;The first step is to start grouting from a row of grouting holes that are far away from the structure to be corrected. When grouting into the grouting pipe in the grouting hole, the grout is first injected through the B pipe of the grouting pipe until The entire grouting hole is filled with cement slurry; 第二步,通过注浆管的A管注入水玻璃,使得注浆孔内地表以下A管长度范围内水泥浆与水玻璃混合,进行封孔;In the second step, the water glass is injected through the A pipe of the grouting pipe, so that the cement slurry is mixed with the water glass within the length of the A pipe below the ground surface in the grouting hole, and the hole is sealed; 第三步,通过注浆管的B管注入双液浆;所述双液浆为由水泥浆和水玻璃混合制成;In the third step, the double liquid slurry is injected through the B pipe of the grouting pipe; the double liquid slurry is made by mixing cement slurry and water glass; 第四步,在注浆过程中,继续测量拟纠偏建构筑物的水平变形恢复情况,反复重复第一步至第三步,按照离拟调控区域由远及近的注浆顺序向各排注浆孔内的注浆管内注浆,直至拟纠偏建构筑物的水平变形降低至报警值以下。In the fourth step, during the grouting process, continue to measure the horizontal deformation recovery of the structure to be corrected, repeat the first step to the third step repeatedly, and grout to each row according to the grouting sequence from far to near to the area to be controlled The grouting pipe in the hole is grouted until the horizontal deformation of the structure to be corrected decreases below the alarm value. 2.根据权利要求1所述的多排注浆主动控制建构筑物变形的实施方法,其特征在于:所述的水泥浆中水灰比为0.6~0.7。2. The implementation method of multi-row grouting for actively controlling deformation of buildings and structures according to claim 1, characterized in that: the water-cement ratio in the grout is 0.6-0.7. 3.根据权利要求1或者2所述的多排注浆主动控制建构筑物变形的实施方法,其特征在于:所述的双液浆中水泥浆与水玻璃的体积比为3:1。3. The implementation method for multi-row grouting to actively control the deformation of buildings and structures according to claim 1 or 2, characterized in that: the volume ratio of cement slurry to water glass in the double liquid slurry is 3:1. 4.根据权利要求3所述的多排注浆主动控制建构筑物变形的实施方法,其特征在于:每排注浆孔的中心的连线与拟纠偏建构筑物的轴线方向平行。4. The method for actively controlling the deformation of a building with multiple rows of grouting according to claim 3, wherein the line connecting the centers of each row of grouting holes is parallel to the axial direction of the structure to be corrected.
CN202211191743.2A 2022-09-28 2022-09-28 Construction method for actively controlling deformation of building through multi-row grouting Pending CN115821997A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202211191743.2A CN115821997A (en) 2022-09-28 2022-09-28 Construction method for actively controlling deformation of building through multi-row grouting

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202211191743.2A CN115821997A (en) 2022-09-28 2022-09-28 Construction method for actively controlling deformation of building through multi-row grouting

Publications (1)

Publication Number Publication Date
CN115821997A true CN115821997A (en) 2023-03-21

Family

ID=85524105

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202211191743.2A Pending CN115821997A (en) 2022-09-28 2022-09-28 Construction method for actively controlling deformation of building through multi-row grouting

Country Status (1)

Country Link
CN (1) CN115821997A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116641391A (en) * 2023-07-27 2023-08-25 中国建筑第六工程局有限公司 Double-row bag type grouting method for controlling deformation of foundation pit approaching tunnel
CN118498441A (en) * 2024-07-16 2024-08-16 中国电建集团西北勘测设计研究院有限公司 Adjustable stress compensation type tunnel deformation prevention combined system

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116641391A (en) * 2023-07-27 2023-08-25 中国建筑第六工程局有限公司 Double-row bag type grouting method for controlling deformation of foundation pit approaching tunnel
CN116641391B (en) * 2023-07-27 2023-10-10 中国建筑第六工程局有限公司 Double-row bag type grouting method for controlling deformation of foundation pit approaching tunnel
CN118498441A (en) * 2024-07-16 2024-08-16 中国电建集团西北勘测设计研究院有限公司 Adjustable stress compensation type tunnel deformation prevention combined system

Similar Documents

Publication Publication Date Title
CN103074898B (en) Multi-row pile foundation pit support structure and construction method thereof
CN104695963B (en) The construction method of subway tunnel crossing building in fragmentation rock stratum
CN115821997A (en) Construction method for actively controlling deformation of building through multi-row grouting
CN207892615U (en) A kind of three step Rapid Construction of Tunnels structure of big arch springing based on pre-timbering with tubular prop
CN109026020B (en) Water-rich tunnel karst cave treatment and excavation method
CN104389315B (en) Consolidation grouting drilled pile wall and construction method thereof
CN111677520A (en) Construction method of excavating station structure by tunnel first and then station pipe curtain hole pile method
CN106120710A (en) A kind of I shape composite steel plate pile
CN206034454U (en) Supporting construction
CN111172988B (en) A grouting pipe system for rock-embedded piles in rock-embedded sections of a pipe frame implanted with a pile-first method
CN206204967U (en) A kind of double perfusion pile cofferdam
CN106120791B (en) Nothing makees vertical supporting system underground structure covered back-digging construction method in advance
CN105178355B (en) The stratum pre-reinforcement processing method of underground space construction
CN115874604A (en) A Method for Controlling the Deformation of Building Structures by Combined Use of Grouting and Partition Wall
CN207829905U (en) A kind of drift-sand stratum bored tunnel three-dimensional supporting construction in advance
CN111022068A (en) A construction method for a pipe jacking tunnel passing through an existing building and its construction work surface
CN213869905U (en) Large-section tunnel base anti-sedimentation structure under loose rock stack stratum
CN108411934A (en) Floating pile pile, dykes and dams soil-baffling structure and its construction method
CN209722983U (en) Close on the irregular deep basal pit group comprehensive support structure of high-speed railway
CN106703063A (en) Pipe-jacking construction method for reinforcing pile foundation in soft soil stratum
CN209508979U (en) Slip-crack surface bracing means
CN219691533U (en) A segmented grouting pre-reinforcement structure for water-rich soft rock tunnels
CN221855535U (en) A grouting oblique force-bearing body suitable for foundation pit rescue
CN205154180U (en) Structure is handled to pre -reinforcing to massif tunnel construction level
CN206512722U (en) A kind of enhanced Larsen steel plate pile supporting system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination