Nothing Special   »   [go: up one dir, main page]

CN115306397A - Unloading balance construction method for newly-built rectangular pipe-jacking upward-penetrating existing subway tunnel - Google Patents

Unloading balance construction method for newly-built rectangular pipe-jacking upward-penetrating existing subway tunnel Download PDF

Info

Publication number
CN115306397A
CN115306397A CN202210774164.4A CN202210774164A CN115306397A CN 115306397 A CN115306397 A CN 115306397A CN 202210774164 A CN202210774164 A CN 202210774164A CN 115306397 A CN115306397 A CN 115306397A
Authority
CN
China
Prior art keywords
pipe
tunnel
pipe jacking
jacking
existing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202210774164.4A
Other languages
Chinese (zh)
Inventor
李忠超
张志伟
霍超
吴斌
谭冲
梁荣柱
黄超群
刘律
黄栋
李徐德
彭静
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China University of Geosciences
Wuhan Municipal Construction Group Co Ltd
Original Assignee
China University of Geosciences
Wuhan Municipal Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China University of Geosciences, Wuhan Municipal Construction Group Co Ltd filed Critical China University of Geosciences
Priority to CN202210774164.4A priority Critical patent/CN115306397A/en
Publication of CN115306397A publication Critical patent/CN115306397A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/001Improving soil or rock, e.g. by freezing; Injections
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/001Improving soil or rock, e.g. by freezing; Injections
    • E21D9/002Injection methods characterised by the chemical composition used
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/003Arrangement of measuring or indicating devices for use during driving of tunnels, e.g. for guiding machines
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/10Making by using boring or cutting machines
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F17/00Methods or devices for use in mines or tunnels, not covered elsewhere
    • E21F17/18Special adaptations of signalling or alarm devices
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Environmental & Geological Engineering (AREA)
  • Soil Sciences (AREA)
  • Chemical & Material Sciences (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • General Chemical & Material Sciences (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

An unloading balance construction method for a newly-built rectangular pipe jacking upward-penetrating existing subway tunnel comprises the following steps: arranging existing tunnel deformation monitoring points; calculating an excavation influence range; measuring and lofting, installing a push bench rack, a rear support device and a main jacking device, debugging equipment and entering a tunnel by the push bench; hoisting the cushion block and the pipe joint; jacking and measuring a jacking pipe; pressing and injecting soil consolidation slurry; monitoring the deformation of the existing tunnel; judging the maximum uplift value of the tunnel, and determining whether ballast measures are taken or not according to whether the vertical displacement value of the maximum vault of the existing tunnel is greater than or equal to a set early warning value or not; stacking and loading the weight; and (4) discharging the pipe jacking machine. According to the method, targeted deformation control measures are taken for the existing tunnel according to the calculated excavation influence range and the tunnel deformation dynamic monitoring result, so that the loss of manpower and material resources caused by blind control is avoided; according to an unloading balance method, the pile-loading pressure weight of the pipe sections is balanced to balance the unloading stress generated by the soil layer below, so that the aim of controlling the deformation of the existing tunnel can be effectively fulfilled; high construction efficiency and low cost.

Description

一种新建矩形顶管上穿既有地铁隧道卸荷平衡施工方法A construction method for unloading and balancing construction of a newly built rectangular pipe jacking through an existing subway tunnel

技术领域technical field

本发明属于地铁盾构隧道技术领域,具体涉及一种新建矩形顶管上穿既有地铁隧道卸荷平衡施工方法,尤其适用于软土地区需要严格控制既有隧道变形的矩形顶管上穿既有地铁隧道工程。The invention belongs to the technical field of subway shield tunnels, and in particular relates to a construction method for unloading balance of a new rectangular pipe jacking on an existing subway tunnel, and is especially suitable for a rectangular pipe jacking on top of an existing tunnel in soft soil areas where the deformation of the existing tunnel needs to be strictly controlled. There are subway tunnel projects.

背景技术Background technique

伴随着城市地下交通网络的不断完善,在有限的城市地下空间中将不可避免的遇到新建矩形顶管上穿既有地铁隧道的问题。顶管开挖由于其开挖的土体重量远大于安装的管节重量,会产生卸荷效应,从而引发下方既有地铁隧道出现整体或局部的隆起变形,进而导致下方盾构隧道结构产生诸如管片破损渗水、接头张开、纵向不均匀沉降等一系列病害,严重者将导致机车脱轨等重大安全事故。城市地下矩形顶管隧道穿越施工过程中,传统施工工法是提前对既有隧道周边地层的加固,这种加固方式在工程中成本非常高,因此如何在保证既有地铁隧道正常安全运营以及控制周围土体变形的基础上,开发与既有地铁隧道上方新建矩形顶管施工相适应的新型施工工艺,具有极高的社会经济效益。With the continuous improvement of the urban underground transportation network, in the limited urban underground space, it is inevitable to encounter the problem that the new rectangular jacking pipe will pass through the existing subway tunnel. Because the weight of the excavated soil is much greater than the weight of the installed pipe joints, the pipe jacking excavation will produce an unloading effect, which will cause the overall or local uplift deformation of the existing subway tunnel below, and then cause the shield tunnel structure below to produce such as A series of diseases such as segment damage and water seepage, joint opening, and longitudinal uneven settlement, etc., will lead to major safety accidents such as locomotive derailment in severe cases. During the construction process of urban underground rectangular pipe-jacking tunnels, the traditional construction method is to reinforce the surrounding strata of the existing tunnels in advance. This reinforcement method is very costly in the project. On the basis of soil deformation, the development of a new construction technology suitable for the construction of new rectangular pipe jacking above the existing subway tunnel has extremely high social and economic benefits.

发明内容Contents of the invention

本发明要解决的技术问题是,针对现有顶管隧道开挖存在的上述问题,提供一种新建矩形顶管上穿既有地铁隧道卸荷平衡施工方法,有效控制新建矩形顶管上穿施工下既有地铁隧道的变形,避免因盲目控制造成的人力、物力损耗;施工效率高,成本低。The technical problem to be solved by the present invention is to provide a new rectangular pipe jacking construction method for unloading and balancing construction of the existing subway tunnel, which can effectively control the construction of the newly built rectangular pipe jacking tunnel. The deformation of the existing subway tunnel can be avoided, and the loss of manpower and material resources caused by blind control can be avoided; the construction efficiency is high and the cost is low.

本发明为解决上述技术问题所采用的技术方案是:The technical scheme that the present invention adopts for solving the problems of the technologies described above is:

一种新建矩形顶管上穿既有地铁隧道卸荷平衡施工方法,包括以下步骤:A construction method for unloading balance of a new rectangular jacking pipe passing through an existing subway tunnel, comprising the following steps:

S1、布置既有隧道变形监测点;S1. Arrange deformation monitoring points of existing tunnels;

S2、计算开挖影响范围,将既有隧道视为搁置于Pasternak地基上的Timoshenko梁模型,得到既有隧道纵向变形受新建顶管隧道影响的主要范围;S2. Calculate the scope of impact of excavation, regard the existing tunnel as a Timoshenko beam model placed on the Pasternak foundation, and obtain the main scope of the longitudinal deformation of the existing tunnel affected by the new pipe-jacking tunnel;

S3、测量放样,安装顶管机机架、后靠、主顶装置,设备调试,顶管机进洞;S3. Measurement and setting out, installation of the pipe jacking machine frame, backrest, and main jacking device, equipment debugging, and the pipe jacking machine entering the hole;

S4、吊放垫块和管节;S4, hoisting pads and pipe joints;

S5、顶管顶进及测量;S5. Pipe jacking and measurement;

S6、压注土体固结浆液,顶管顶进时通过管壁注浆孔及时压注固结浆液,使浆液渗入顶管周围土层,在土层中硬化,从而加固土层;S6. Pressure injection of soil consolidation grout, during pipe jacking, pressure injection of consolidation grout through the pipe wall grouting hole in time, so that the grout penetrates into the soil layer around the pipe jacking and hardens in the soil layer, thereby strengthening the soil layer;

S7、既有隧道变形监测;S7. Deformation monitoring of existing tunnels;

S8、判断隧道最大隆起值,当开挖面在进入主要影响区前,若监测得到的既有隧道最大拱顶竖向位移值小于设定的预警值,则不对管节采取压载措施,后续根据顶管掘进过程中监测得到的既有隧道最大拱顶竖向位移值是否大于或等于设定的预警值决定是否采取压载措施;若不采取压载措施,则重复步骤S4~S7直至步骤S10顶管机出洞;S8. Judging the maximum uplift value of the tunnel. Before the excavation surface enters the main affected area, if the monitored maximum vertical displacement value of the existing tunnel vault is less than the set early warning value, no ballasting measures will be taken for the pipe joints. Follow-up According to whether the maximum vertical displacement value of the existing tunnel vault that is monitored during the pipe jacking process is greater than or equal to the set early warning value, it is decided whether to take ballast measures; if no ballast measures are taken, repeat steps S4 to S7 until step S10 pipe jacking machine out of the hole;

S9、堆载压重,当开挖面在进入主要影响区前或在后续掘进过程中,若监测得到的既有隧道最大拱顶竖向位移值大于或等于设定的预警值,则对管节采取压载措施;S9. Heap load and ballast. When the excavation face enters the main affected area or during the subsequent excavation process, if the monitored maximum vertical displacement value of the existing tunnel vault is greater than or equal to the set early warning value, the tunnel take ballast measures;

S10、当机头抵达接收井后,顶管机出洞。S10. When the machine head arrives at the receiving shaft, the pipe jacking machine goes out of the hole.

按上述方案,所述步骤S1具体为:在顶管正式施工前1~2个月对既有地铁隧道布置变形监测点,既有地铁隧道变形监测断面布置范围为距离新旧隧道平面交点左右侧60m范围,布置间距从顶管顶进轴线两侧按5m、10m、20m进行布置,各断面内共布置5处棱镜,其中,第一棱镜布置于断面中心最顶部,用于监测隧道拱顶竖向位移;第二、第三棱镜布置于断面的水平方向轴线两端部,用于监测隧道净空收敛;第四、第五棱镜分别布置于道床上,分别用于监测道床水平位移和道床竖向位移。According to the above plan, the step S1 specifically includes: arranging deformation monitoring points for existing subway tunnels 1 to 2 months before the official construction of pipe jacking, and the layout range of deformation monitoring sections of existing subway tunnels is 60m from the left and right sides of the plane intersection point of the old and new tunnels Scope, the layout distance is arranged according to 5m, 10m, 20m from both sides of the pipe jacking axis, and 5 prisms are arranged in each section, of which the first prism is arranged at the top of the center of the section to monitor the vertical Displacement; the second and third prisms are arranged at both ends of the horizontal axis of the section to monitor the convergence of the tunnel clearance; the fourth and fifth prisms are respectively arranged on the ballast bed to monitor the horizontal displacement and vertical displacement of the ballast bed respectively.

按上述方案,所述步骤S2具体为:采用Mindlin解和有限差分法计算既有隧道最大隆起值随开挖距离的变化图,将隆起值无显著变化的区间定为次要影响区,有显著变化的区间定为主要影响区,具体为:开挖面距离既有隧道轴线3倍新建顶管宽度范围内为主要影响区,3倍新建顶管宽度范围外为次要影响区。According to the above scheme, the step S2 is specifically: using the Mindlin solution and the finite difference method to calculate the change diagram of the maximum uplift value of the existing tunnel with the excavation distance, and define the interval where the uplift value has no significant change as the secondary influence area, which has significant The changed interval is defined as the main impact area, specifically: the excavation surface is within 3 times the width of the newly-built pipe jacking from the existing tunnel axis as the main impact area, and the area outside 3 times the width of the newly-built pipe jacking is the secondary impact area.

按上述方案,所述步骤S3中顶管机进洞具体为:待完成测量放样,安装顶管机机架、后靠、主顶装置,设备调试,破洞门工作后操作顶管机进洞;吊放垫块和管节具体为:在顶管千斤顶顶进一节管节后,及时吊放垫块和管节,并安装新的管节。According to the above scheme, the pipe jacking machine entering the hole in the step S3 is as follows: to complete the measurement and setting out, install the pipe jacking machine frame, backrest, and main jacking device, equipment debugging, and operate the pipe jacking machine to enter the hole after the hole is broken. ; Lifting pads and pipe joints are specifically as follows: After a pipe joint is pushed in by the pipe jacking jack, the pads and pipe joints are lifted in time, and a new pipe joint is installed.

按上述方案,所述步骤S5顶管顶进及测量具体为:According to the above scheme, the pipe jacking and measurement of the step S5 are specifically:

顶管顶进速度v在步骤二中计算得到的次要影响区内控制在3.5~4m/d,在主要影响区内控制在2~3m/d,顶推力F结合工程情况按照公式(1)计算,其余施工参数需不断根据地表及隧道变形反馈数据动态调整,以达到最佳状态:The pipe jacking speed v is controlled at 3.5-4m/d in the secondary influence area calculated in step 2, and is controlled at 2-3m/d in the main influence area. The jacking force F is combined with the engineering situation according to the formula (1) calculation, and the remaining construction parameters need to be dynamically adjusted according to the feedback data of the surface and tunnel deformation to achieve the best state:

F=F1+F2 (1)F=F 1 +F 2 (1)

式中:F为最小顶力,单位kN;F1为管道与土层的摩阻力,单位kN,F1=(a+b)×2Lf,L为顶管顶进长度,单位m;f为管道外壁与土的平均摩阻力,单位kN/m2,宜取7~12kN/m2;F2为顶管机的迎面阻力,单位kN,F2=a×bR1,R1为顶管机下部1/3处的被动土压力,单位kN;a为顶管机宽,单位m;b为顶管机高,单位m。In the formula: F is the minimum jacking force, the unit is kN; F 1 is the frictional resistance between the pipeline and the soil layer, the unit is kN, F 1 = (a+b)×2Lf, L is the pipe jacking length, the unit is m; f is The average frictional resistance between the outer wall of the pipeline and the soil, in kN/m 2 , should be 7~12kN/m 2 ; F 2 is the head-on resistance of the pipe jacking machine, in kN, F 2 =a×bR 1 , R 1 is the pipe jacking Passive earth pressure at the lower 1/3 of the machine, in kN; a is the width of the pipe jacking machine, in m; b is the height of the pipe jacking machine, in m.

按上述方案,所述步骤S6中压注土体固结浆液的压浆顺序具体为:地面拌浆→启动压浆泵→总管阀门打开→管节阀门打开→送浆→管节阀门关闭→总管阀门关闭→井内快速接头拆开→下管节→接2英寸总管→循环复始;注浆材料及配比:胶凝材料采用P042.5水泥,浆液配比控制在以下范围内:0.5:1~1:1。According to the above scheme, the grouting sequence of the pressure-injected soil consolidation grout in step S6 is specifically: ground grouting → start the grouting pump → open the main pipe valve → open the pipe joint valve → send slurry → close the pipe joint valve → main pipe Close the valve → disassemble the quick joint in the well → lower the pipe joint → connect the 2-inch main pipe → repeat the cycle; grouting material and proportion: the cementitious material is P042.5 cement, and the proportion of the slurry is controlled within the following range: 0.5:1 ~1:1.

按上述方案,所述步骤S7既有隧道变形监测具体为:在顶管顶进过程中,对既有盾构隧道的变形使用智能化全站仪进行监测;当顶管开挖面处于次要影响区时,监测频率为1~2次/天;当顶管开挖面处于主要影响区时,监测频率为3~4次/天。According to the above scheme, the deformation monitoring of the existing tunnel in the step S7 is specifically: during the pipe jacking process, the deformation of the existing shield tunnel is monitored using an intelligent total station; when the pipe jacking excavation surface is in the secondary In the affected area, the monitoring frequency is 1-2 times/day; when the pipe jacking excavation surface is in the main affected area, the monitoring frequency is 3-4 times/day.

按上述方案,所述步骤S8和步骤S9中预警值设定范围是3~5mm。According to the above solution, the setting range of the warning value in the steps S8 and S9 is 3-5 mm.

按上述方案,所述步骤S9中对管节采取压载措施的具体步骤为:According to the above scheme, the specific steps for taking ballast measures to the pipe joints in the step S9 are:

S91、若是在顶管开挖面进入主要影响区前实施堆载压重,则待顶管机每次对隧道前方土体开挖一个管节的容量后,及时计算出开挖土体与管节的重量差,采用同等重量差重量的预制C20素砼或铁块对主要影响区内的管节实施堆载压重;;待每一管节土体开挖至堆载压重完成后,方进行后续土体的开挖工作;当已压载的管节离开主要影响区时,将其用于压载的素砼或铁块搬离至后续进入主要影响区的管节上;S91. If stacking and ballasting is carried out before the excavation surface of the pipe jacking enters the main affected area, after the pipe jacking machine excavates the capacity of a pipe joint in the soil in front of the tunnel each time, the excavated soil and pipe joints will be calculated in time. If the weight difference of the joints is different, the prefabricated C20 plain concrete or iron blocks with the same weight difference shall be used to carry out heap ballasting on the pipe joints in the main influence area; after the excavation of the soil body of each pipe joint until the heap ballasting is completed, When the ballasted pipe joint leaves the main impact area, the plain concrete or iron block used for ballasting is moved to the subsequent pipe joint that enters the main impact area;

S92、若是在后续掘进过程中实施堆载,则立刻对主要影响区内的所有管节进行堆载压重,具体步骤与上述步骤S91一致。S92. If stacking is implemented in the subsequent excavation process, immediately perform stacking and ballasting on all pipe joints in the main influence area, and the specific steps are consistent with the above step S91.

按上述方案,所述步骤S10顶管机出洞具体包括两种情况:According to the above scheme, the step S10 of the pipe jacking machine exiting the hole specifically includes two situations:

S101、若顶管顶进全程并未采取压载措施,则对顶管机进行分解并吊出接收井,之后进行浆液置换,以及拆除管内设备、嵌缝、清理、接头处理;S101. If ballasting measures are not taken during the whole process of pipe jacking, the pipe jacking machine shall be disassembled and hoisted out of the receiving well, followed by grout replacement, removal of equipment in the pipe, caulking, cleaning, and joint treatment;

S102、若对顶管采取了压载措施,则在顶管全程贯通后通过管节注浆孔对主要影响区内的土层进行注浆加固;注浆加固后逐节搬离堆载物,并同步监测既有隧道变形,若每节堆载物搬离后,既有隧道变形稳定,则继续搬离下一节重物,直至全部搬离,如变形不稳定,则继续注浆或采取其他地层加固措施,直至搬离堆载物不影响隧道的后续变形;待隧道变形稳定后再进行顶管机分解并吊出接收井以及后续工作。S102. If ballasting measures are taken for the pipe jacking, the soil layer in the main affected area shall be grouted and reinforced through the grouting holes of the pipe joints after the pipe jacking is fully penetrated; Simultaneously monitor the deformation of the existing tunnel. If the deformation of the existing tunnel is stable after each section of load is removed, continue to remove the next section of heavy objects until all of them are removed. If the deformation is unstable, continue grouting or take measures. Other stratum reinforcement measures will not affect the subsequent deformation of the tunnel until the load is removed; after the deformation of the tunnel is stable, the pipe jacking machine will be disassembled and lifted out of the receiving shaft and follow-up work.

本发明的有益效果具体如下:The beneficial effects of the present invention are specifically as follows:

1、依据计算的开挖影响范围以及隧道变形动态监测结果对既有隧道采取有针对性的变形控制措施,能避免因盲目控制造成的人力、物力损耗;1. Take targeted deformation control measures for existing tunnels based on the calculated excavation impact range and tunnel deformation dynamic monitoring results, which can avoid the loss of manpower and material resources caused by blind control;

2、根据卸荷平衡法,对管节堆载压重以平衡下方土层产生的卸荷应力,能有效实现控制既有隧道变形的目的;2. According to the unloading balance method, the pipe joints are piled up to balance the unloading stress generated by the soil layer below, which can effectively achieve the purpose of controlling the deformation of the existing tunnel;

3、施工方法简单,操作简便,施工效率高,成本低。3. The construction method is simple, the operation is convenient, the construction efficiency is high, and the cost is low.

附图说明Description of drawings

图1是本发明实施例新建顶管上穿既有地铁隧道卸荷平衡施工方法流程图;Fig. 1 is the flow chart of the unloading and balancing construction method of the newly-built pipe jacking on the existing subway tunnel in the embodiment of the present invention;

图2是本发明实施例中既有盾构隧道断面变形监测点布置图;Fig. 2 is the arrangement diagram of the existing shield tunnel section deformation monitoring points in the embodiment of the present invention;

图3是本发明实施例中新建顶管开挖影响范围计算模型;Fig. 3 is the calculation model of the scope of influence of newly-built pipe jacking excavation in the embodiment of the present invention;

图4是本发明实施例中新建顶管开挖主要影响区。Fig. 4 is the main influence area of new pipe jacking excavation in the embodiment of the present invention.

具体实施方式Detailed ways

以下结合附图和实施例对本发明进行详细说明。The present invention will be described in detail below in conjunction with the accompanying drawings and embodiments.

本发明所述的一种新建顶管上穿既有地铁隧道卸荷平衡施工方法,包括布置既有隧道变形监测点,计算开挖影响范围,顶管机进洞,吊放垫块和管节,顶管顶进及测量,压注土体固结浆液,既有隧道变形监测,判断隧道最大隆起值,堆载压重,顶管机出洞。整个方法流程图如图1所示,具体包括以下步骤:The invention relates to a newly-built pipe jacking construction method for unloading balance of an existing subway tunnel, which includes arranging deformation monitoring points of the existing tunnel, calculating the influence range of excavation, entering the hole with a pipe jacking machine, and hoisting pads and pipe joints , pipe jacking and measurement, pressure injection of soil consolidation grout, existing tunnel deformation monitoring, judgment of maximum uplift value of tunnel, heap load pressure, pipe jacking machine out of the hole. The flow chart of the whole method is shown in Figure 1, which specifically includes the following steps:

步骤一、布置既有隧道变形监测点Step 1. Arranging deformation monitoring points for existing tunnels

在顶管正式施工前1~2个月对既有地铁隧道布置变形监测点,既有地铁隧道变形监测断面布置范围为距离新旧隧道平面交点左右侧60m范围,布置间距从顶管顶进轴线两侧按5m、10m、20m进行布置,各断面内共布置5处棱镜,棱镜A用于监测隧道拱顶竖向位移,棱镜B、C用于监测隧道净空收敛,棱镜D用于监测道床水平位移,棱镜E用于监测道床竖向位移,隧道断面变形监测点布置如图2所示。Arrange deformation monitoring points for existing subway tunnels 1 to 2 months before the official construction of pipe jacking. The sides are arranged according to 5m, 10m, and 20m, and 5 prisms are arranged in each section. Prism A is used to monitor the vertical displacement of the tunnel vault, prisms B and C are used to monitor the tunnel clearance convergence, and prism D is used to monitor the horizontal displacement of the ballast bed , the prism E is used to monitor the vertical displacement of the ballast bed, and the layout of the deformation monitoring points of the tunnel section is shown in Figure 2.

步骤二、计算开挖影响范围Step 2. Calculate the scope of excavation influence

矩形顶管施工对既有隧道的影响程度随开挖面的掘进距离动态变化,在顶管开挖前结合工程资料和理论方法计算开挖的影响范围,将既有隧道视为搁置于Pasternak地基上的Timoshenko梁模型,开挖影响范围计算模型如图3所示。采用Mindlin解和有限差分法计算既有隧道最大隆起值随开挖距离的变化图,将隆起值无显著变化的区间定为次要影响区,有显著变化的区间定为主要影响区,详细的计算过程可参考文献:Liang R,Kang C,Xiang L,Li Z,Lin C,Gao K,Guo Y,2021.Responses of in-service shield tunnel toovercrossing tunnelling in soft ground.Environmental Earth Sciences.80(5),1-15。理论及大量实测结果表明开挖面距离既有隧道轴线3倍新建顶管宽度范围内为主要影响区,3倍新建顶管宽度范围外为次要影响区,新建隧道开挖主要影响区如图4所示。The impact of rectangular pipe jacking construction on the existing tunnel changes dynamically with the excavation distance. Before the pipe jacking excavation, the influence range of the excavation is calculated by combining engineering data and theoretical methods, and the existing tunnel is regarded as resting on the Pasternak foundation. Based on the Timoshenko beam model above, the calculation model of the excavation influence range is shown in Figure 3. Using the Mindlin solution and the finite difference method to calculate the change diagram of the maximum uplift value of the existing tunnel with the excavation distance, the interval with no significant change in the uplift value is designated as the secondary impact area, and the interval with significant changes is designated as the main influence area. Detailed For the calculation process, please refer to the literature: Liang R, Kang C, Xiang L, Li Z, Lin C, Gao K, Guo Y, 2021. Responses of in-service shield tunnel toovercrossing tunneling in soft ground. Environmental Earth Sciences.80(5) ,1-15. Theoretical and a large number of actual measurement results show that the excavation surface is within 3 times the width of the newly-built pipe jacking from the existing tunnel axis as the main impact area, and outside the range of 3 times the width of the newly-built pipe jacking is the secondary impact area. The main impact area of the new tunnel excavation is shown in the figure 4.

步骤三、顶管机进洞Step 3, the pipe jacking machine enters the hole

待完成测量放样,安装顶管机机架、后靠、主顶装置,设备调试,破洞门等工作后操作顶管机进洞。After completing the measurement and setting out, installing the pipe jacking machine frame, backrest, main jacking device, equipment debugging, and breaking the hole door, operate the pipe jacking machine to enter the hole.

步骤四、吊放垫块和管节Step 4. Hanging pads and pipe joints

在顶管千斤顶顶进一节管节后,及时吊放垫块和管节,并安装新的管节。After a pipe joint is jacked in by the pipe jacking jack, the block and pipe joint shall be hoisted in time, and a new pipe joint shall be installed.

步骤五、顶管顶进及测量Step five, pipe jacking and measurement

顶管顶进速度v在步骤二中计算得到的次要影响区内控制在3.5~4m/d,在主要影响区内控制在2~3m/d,顶推力F结合工程情况按照公式(1)计算,其余施工参数需不断根据地表及隧道变形反馈数据动态调整,以达到最佳状态。The pipe jacking speed v is controlled at 3.5-4m/d in the secondary influence area calculated in step 2, and is controlled at 2-3m/d in the main influence area. The jacking force F is combined with the engineering situation according to the formula (1) The rest of the construction parameters need to be dynamically adjusted according to the feedback data of the surface and tunnel deformation to achieve the best state.

顶进过程中密切控制顶进轴线,在每节管节顶进结束后,进行机头的姿态测量,机头一旦出现微小转角,立即采取刀盘反转、加压铁等措施回纠。顶管机出土采用螺旋输送机+轨道土箱+卷扬机+履带吊的形式出土。在顶进过程中,尽量精确地统计出每节的出土量,力争使之与理论出土量保持一致,避免超挖或欠挖,确保正面土体的相对稳定,减少对地层的扰动。顶管顶进过程中通过始发井后方的全站仪密切监测顶管的顶进距离,将顶进距离纪录并与开挖影响范围进行对比,随着顶管继续开挖,逐步增加对顶进距离监测的频率,次要影响区内1天1~2测,主要影响区内1天3~4测,以便及时判断顶管开挖面所处的影响区。During the jacking process, the jacking axis is closely controlled. After the jacking of each pipe section, the attitude of the machine head is measured. Once the machine head has a small rotation angle, measures such as cutter head reversal and iron pressing are immediately corrected. The pipe jacking machine is unearthed in the form of screw conveyor + track soil box + hoist + crawler crane. During the jacking process, the unearthed volume of each section should be counted as accurately as possible to keep it consistent with the theoretical unearthed volume, avoid over-excavation or under-excavation, ensure the relative stability of the front soil, and reduce disturbance to the stratum. During the pipe jacking process, the total station behind the launch shaft closely monitors the jacking distance of the pipe jacking, records the jacking distance and compares it with the scope of influence of the excavation. As the pipe jacking continues to be excavated, the jacking distance is gradually increased. The frequency of distance monitoring is 1-2 measurements a day in the secondary impact area, and 3-4 measurements a day in the main impact area, so as to timely judge the impact area where the pipe jacking excavation face is located.

步骤六、压注土体固结浆液Step 6. Pressure injection of soil consolidation slurry

顶管顶进时通过管壁注浆孔及时压注固结浆液,使浆液渗入顶管周围土层,在土层中硬化,从而达到加固土层的效果。压浆顺序:地面拌浆→启动压浆泵→总管阀门打开→管节阀门打开→送浆→管节阀门关闭→总管阀门关闭→井内快速接头拆开→下管节→接2英寸总管→循环复始。注浆材料及配比:胶凝材料采用P042.5水泥,合适的浆液配比既能提高浆液的扩散加固范围又能控制浆液的胶凝时间,浆液配比要控制在以下范围内:0.5:1~1:1。During pipe jacking, the consolidation grout is injected in time through the grouting holes on the pipe wall, so that the grout penetrates into the soil layer around the pipe jacking and hardens in the soil layer, thereby achieving the effect of strengthening the soil layer. Squeeze of grouting: ground slurry mixing→start grouting pump→open main pipe valve→open pipe joint valve→slurry delivery→close pipe joint valve→main pipe valve close→disassemble quick joint in well→lower pipe joint→connect 2-inch main pipe→circulate start again. Grouting material and ratio: P042.5 cement is used as the cementitious material. A suitable grout ratio can not only improve the diffusion and reinforcement range of the grout, but also control the gelling time of the grout. The grout ratio should be controlled within the following range: 0.5: 1~1:1.

步骤七、既有隧道变形监测Step 7. Deformation monitoring of existing tunnels

在顶管顶进过程中,对既有盾构隧道的变形使用智能化全站仪进行监测;当顶管开挖面处于次要影响区时,监测频率为1~2次/天,当顶管开挖面处于主要影响区时,监测频率为3~4次/天。During the pipe jacking process, an intelligent total station is used to monitor the deformation of the existing shield tunnel; when the pipe jacking excavation surface is in the secondary impact area, the monitoring frequency is 1-2 times/day. When the pipe excavation surface is in the main affected area, the monitoring frequency is 3-4 times/day.

步骤八、判断隧道最大隆起值Step 8. Determine the maximum uplift value of the tunnel

当开挖面在进入主要影响区前,若监测得到的既有隧道最大拱顶竖向位移值小于设定的预警值,预警值设定范围为3~5mm(实施例中预警值设定为3mm),则无需对管节采取压载措施,后续根据顶管掘进过程中监测得到的既有隧道最大拱顶竖向位移值是否大于或等于设定的预警值来决定是否采取压载措施。若不需采取压载措施,则重复步骤四~七直至步骤十顶管机出洞。Before the excavation surface enters the main affected area, if the maximum vertical displacement value of the existing tunnel vault obtained by monitoring is less than the set early warning value, the setting range of the early warning value is 3-5 mm (in the embodiment, the early warning value is set to 3mm), there is no need to take ballasting measures for the pipe joints, and whether to take ballasting measures will be decided according to whether the maximum vertical displacement value of the existing tunnel vault that is monitored during the pipe jacking excavation process is greater than or equal to the set early warning value. If ballasting measures are not required, repeat steps 4 to 7 until the pipe jacking machine goes out of the hole in step 10.

步骤九、堆载压重Step 9. Heap load

当顶管开挖面在进入主要影响区前或在后续掘进过程中,若监测得到的既有隧道最大拱顶竖向位移值大于或等于设定的预警值,则需对管节采取压载措施。若是在顶管开挖面进入主要影响区前实施堆载,则待顶管机每次对隧道前方土体开挖一个管节的容量后,及时计算出开挖土体与管节的重量差,采用同等重量差重量的预制C20素砼或铁块对主要影响区内的管节实施堆载压重。为方便后期搬运,采用九夹板对素砼进行分层分块,每块尺寸为1m×4m×0.5m,后期配合滑轮车及吊车运出,素砼置于管节轨道内两侧,避免影响滑轮车通行。待每一管节土体开挖至堆载压重完成后,方可进行后续土体的开挖工作。当已压载的管节离开主要影响区时,应将其用于压载的素砼或铁块搬离至后续进入主要影响区的管节上。若是在后续掘进过程中实施堆载,则应立刻对主要影响区内的所有管节进行堆载,步骤与上述一致。When the pipe jacking excavation surface enters the main impact area or during the subsequent excavation process, if the monitored maximum vertical displacement value of the existing tunnel arch is greater than or equal to the set early warning value, the pipe joint needs to be ballasted measure. If stacking is carried out before the pipe jacking excavation surface enters the main impact area, the weight difference between the excavated soil and pipe joints will be calculated in time after the pipe jacking machine excavates the soil in front of the tunnel to the capacity of one pipe joint each time. , Use prefabricated C20 plain concrete or iron blocks with the same weight difference to carry out stacking and ballasting on the pipe joints in the main influence area. In order to facilitate later transportation, nine splints are used to divide the plain concrete into layers and blocks. Pulley traffic. Subsequent excavation of the soil can only be carried out after the excavation of the soil of each pipe joint until the heap load is completed. When the ballasted pipe joints leave the main influence area, the plain concrete or iron blocks used for ballasting shall be moved to the pipe joints that subsequently enter the main influence area. If stacking is implemented during subsequent excavation, all pipe joints in the main impact area should be stacked immediately, and the steps are the same as above.

步骤十、顶管机出洞Step 10, the pipe jacking machine exits the hole

若顶管顶进全程并未采取压载措施,则对顶管机进行分解并吊出接收井,之后进行浆液置换,以及拆除管内设备、嵌缝、清理、接头处理。If ballasting measures are not taken during the whole process of pipe jacking, the pipe jacking machine shall be disassembled and hoisted out of the receiving well, followed by grout replacement, removal of equipment in the pipe, caulking, cleaning, and joint treatment.

步骤十一、主要影响区土体加固Step 11. Soil reinforcement in the main affected area

若对顶管采取了压载措施,则在顶管全程贯通后通过管节注浆孔对主要影响区内的土层进行注浆加固。If ballasting measures are taken for the pipe jacking, the soil layer in the main affected area shall be grouted and reinforced through the grouting holes of the pipe joints after the pipe jacking is fully penetrated.

步骤十二、搬出堆载物Step 12. Remove the load

注浆加固后逐节搬离堆载物,并同步监测既有隧道变形,若每节堆载物搬离后,既有隧道变形稳定,则继续搬离下一节堆载物,直至全部搬离,如变形不稳定,则继续注浆或采取其他地层加固措施,直至搬离重物不会影响隧道的后续变形。待隧道变形稳定后再进行步骤十中顶管机吊出接收井后的后续工作。After grouting reinforcement, the loads are removed section by section, and the deformation of the existing tunnel is monitored synchronously. If the deformation of the existing tunnel is stable after each section of the load is removed, continue to remove the next section of the load until all the loads are removed. If the deformation is unstable, continue grouting or take other ground reinforcement measures until the removal of heavy objects will not affect the subsequent deformation of the tunnel. After the tunnel deformation is stable, proceed to the follow-up work after the pipe jacking machine is hoisted out of the receiving shaft in step ten.

以上所述仅是本发明的优选实施方式,本发明的保护范围并不仅局限于上述实施例,凡属于本发明思路下的技术方案均属于本发明的保护范围。应当指出,对于本技术领域的普通技术人员来说,在不脱离本发明原理前提下的若干改进和润饰,这些改进和润饰也应视为本发明的保护范围。The above descriptions are only preferred implementations of the present invention, and the protection scope of the present invention is not limited to the above-mentioned embodiments, and all technical solutions under the idea of the present invention belong to the protection scope of the present invention. It should be pointed out that for those skilled in the art, some improvements and modifications without departing from the principles of the present invention should also be regarded as the protection scope of the present invention.

Claims (10)

1.一种新建矩形顶管上穿既有地铁隧道卸荷平衡施工方法,其特征在于,包括以下步骤:1. a kind of newly-built rectangular pipe jacking wears existing subway tunnel unloading balance construction method, it is characterized in that, comprises the following steps: S1、布置既有隧道变形监测点;S1. Arrange deformation monitoring points of existing tunnels; S2、计算开挖影响范围,将既有隧道视为搁置于Pasternak地基上的Timoshenko梁模型,得到既有隧道纵向变形受新建顶管隧道影响的主要范围;S2. Calculate the scope of impact of excavation, regard the existing tunnel as a Timoshenko beam model placed on the Pasternak foundation, and obtain the main scope of the longitudinal deformation of the existing tunnel affected by the new pipe-jacking tunnel; S3、测量放样,安装顶管机机架、后靠、主顶装置,设备调试,顶管机进洞;S3. Measurement and setting out, installation of the pipe jacking machine frame, backrest, and main jacking device, equipment debugging, and the pipe jacking machine entering the hole; S4、吊放垫块和管节;S4, hoisting pads and pipe joints; S5、顶管顶进及测量;S5. Pipe jacking and measurement; S6、压注土体固结浆液,顶管顶进时通过管壁注浆孔及时压注固结浆液,使浆液渗入顶管周围土层,在土层中硬化,从而加固土层;S6. Pressure injection of soil consolidation grout, during pipe jacking, pressure injection of consolidation grout through the pipe wall grouting hole in time, so that the grout penetrates into the soil layer around the pipe jacking and hardens in the soil layer, thereby strengthening the soil layer; S7、既有隧道变形监测;S7. Deformation monitoring of existing tunnels; S8、判断隧道最大隆起值,当开挖面在进入主要影响区前,若监测得到的既有隧道最大拱顶竖向位移值小于设定的预警值,则不对管节采取压载措施,后续根据顶管掘进过程中监测得到的既有隧道最大拱顶竖向位移值是否大于或等于设定的预警值决定是否采取压载措施;若不采取压载措施,则重复步骤S4~S7直至步骤S10顶管机出洞;S8. Judging the maximum uplift value of the tunnel. Before the excavation surface enters the main affected area, if the monitored maximum vertical displacement value of the existing tunnel vault is less than the set early warning value, no ballasting measures will be taken for the pipe joints. Follow-up According to whether the maximum vertical displacement value of the existing tunnel vault that is monitored during the pipe jacking process is greater than or equal to the set early warning value, it is decided whether to take ballast measures; if no ballast measures are taken, repeat steps S4 to S7 until step S10 pipe jacking machine out of the hole; S9、堆载压重,当开挖面在进入主要影响区前或在后续掘进过程中,若监测得到的既有隧道最大拱顶竖向位移值大于或等于设定的预警值,则对管节采取压载措施;S9. Heap load and ballast. When the excavation face enters the main affected area or during the subsequent excavation process, if the monitored maximum vertical displacement value of the existing tunnel vault is greater than or equal to the set early warning value, the tunnel take ballast measures; S10、当机头抵达接收井后,顶管机出洞。S10. When the machine head arrives at the receiving shaft, the pipe jacking machine goes out of the hole. 2.根据权利要求1所述的新建矩形顶管上穿既有地铁隧道卸荷平衡施工方法,其特征在于,所述步骤S1具体为:在顶管正式施工前1~2个月对既有地铁隧道布置变形监测点,既有地铁隧道变形监测断面布置范围为距离新旧隧道平面交点左右侧60m范围,布置间距从顶管顶进轴线两侧按5m、10m、20m进行布置,各断面内共布置5处棱镜,其中,第一棱镜布置于断面中心最顶部,用于监测隧道拱顶竖向位移;第二、第三棱镜布置于断面的水平方向轴线两端部,用于监测隧道净空收敛;第四、第五棱镜分别布置于道床上,分别用于监测道床水平位移和道床竖向位移。2. The construction method according to claim 1, wherein the unloading and balancing construction method of the newly-built rectangular pipe jacking through the existing subway tunnel is characterized in that, the step S1 is specifically as follows: 1 to 2 months before the formal construction of the pipe jacking, the existing subway tunnel Deformation monitoring points are arranged in the subway tunnel. The layout range of the existing subway tunnel deformation monitoring section is 60m from the left and right sides of the plane intersection of the new and old tunnels. Five prisms are arranged, among which, the first prism is arranged at the top of the center of the section to monitor the vertical displacement of the tunnel vault; the second and third prisms are arranged at both ends of the horizontal axis of the section to monitor the convergence of the tunnel clearance; The fourth and fifth prisms are respectively arranged on the ballast bed to monitor the horizontal displacement and the vertical displacement of the ballast bed respectively. 3.根据权利要求1所述的新建矩形顶管上穿既有地铁隧道卸荷平衡施工方法,其特征在于,所述步骤S2具体为:采用Mindlin解和有限差分法计算既有隧道最大隆起值随开挖距离的变化图,将隆起值无显著变化的区间定为次要影响区,有显著变化的区间定为主要影响区,具体为:开挖面距离既有隧道轴线3倍新建顶管宽度范围内为主要影响区,3倍新建顶管宽度范围外为次要影响区。3. The newly-built rectangular pipe jacking method according to claim 1, wherein the unloading balance construction method of the existing subway tunnel is characterized in that, the step S2 is specifically: using the Mindlin solution and the finite difference method to calculate the maximum uplift value of the existing tunnel As shown in the diagram of changes with excavation distance, the interval with no significant change in uplift value is defined as the secondary impact area, and the interval with significant change is defined as the main impact area, specifically: the distance between the excavation face and the axis of the existing tunnel is 3 times the newly-built pipe jacking The main impact area is within the width range, and the secondary impact area is outside the range of 3 times the width of the newly-built pipe jacking. 4.根据权利要求1所述的新建矩形顶管上穿既有地铁隧道卸荷平衡施工方法,其特征在于,所述步骤S3中顶管机进洞具体为:待完成测量放样,安装顶管机机架、后靠、主顶装置,设备调试,破洞门工作后操作顶管机进洞;吊放垫块和管节具体为:在顶管千斤顶顶进一节管节后,及时吊放垫块和管节,并安装新的管节。4. The newly-built rectangular pipe jacking method according to claim 1, wherein the unloading and balancing construction method of the existing subway tunnel is characterized in that, in the step S3, the pipe jacking machine enters the hole specifically as follows: the measurement and lofting are to be completed, and the pipe jacking is installed Machine frame, backrest, main jacking device, equipment debugging, operating the pipe jacking machine to enter the hole after the broken hole door is working; hoisting pads and pipe joints are as follows: after a pipe jack is jacked into a pipe joint, hoist it in time Place spacers and joints, and install new joints. 5.根据权利要求1所述的新建矩形顶管上穿既有地铁隧道卸荷平衡施工方法,其特征在于,所述步骤S5顶管顶进及测量具体为:5. The newly-built rectangular pipe jacking method according to claim 1, wherein the unloading balance construction method of the existing subway tunnel is characterized in that, the jacking and measurement of the pipe jacking in the step S5 are specifically: 顶管顶进速度v在步骤二中计算得到的次要影响区内控制在3.5~4m/d,在主要影响区内控制在2~3m/d,顶推力F结合工程情况按照公式(1)计算,其余施工参数需不断根据地表及隧道变形反馈数据动态调整,以达到最佳状态:The pipe jacking speed v is controlled at 3.5-4m/d in the secondary influence area calculated in step 2, and is controlled at 2-3m/d in the main influence area. The jacking force F is combined with the engineering situation according to the formula (1) calculation, and the remaining construction parameters need to be dynamically adjusted according to the feedback data of the surface and tunnel deformation to achieve the best state: F=F1+F2 (1)F=F 1 +F 2 (1) 式中:F为最小顶力,单位kN;F1为管道与土层的摩阻力,单位kN,F1=(a+b)×2Lf,L为顶管顶进长度,单位m;f为管道外壁与土的平均摩阻力,单位kN/m2,宜取7~12kN/m2;F2为顶管机的迎面阻力,单位kN,F2=a×bR1,R1为顶管机下部1/3处的被动土压力,单位kN;a为顶管机宽,单位m;b为顶管机高,单位m。In the formula: F is the minimum jacking force, the unit is kN; F 1 is the frictional resistance between the pipeline and the soil layer, the unit is kN, F 1 = (a+b)×2Lf, L is the pipe jacking length, the unit is m; f is The average frictional resistance between the outer wall of the pipeline and the soil, in kN/m 2 , should be 7~12kN/m 2 ; F 2 is the head-on resistance of the pipe jacking machine, in kN, F 2 =a×bR 1 , R 1 is the pipe jacking Passive earth pressure at the lower 1/3 of the machine, in kN; a is the width of the pipe jacking machine, in m; b is the height of the pipe jacking machine, in m. 6.根据权利要求1所述的新建新建矩形顶管上穿既有地铁隧道卸荷平衡施工方法,其特征在于,所述步骤S6中压注土体固结浆液的压浆顺序具体为:地面拌浆→启动压浆泵→总管阀门打开→管节阀门打开→送浆→管节阀门关闭→总管阀门关闭→井内快速接头拆开→下管节→接2英寸总管→循环复始;注浆材料及配比:胶凝材料采用P042.5水泥,浆液配比控制在以下范围内:0.5:1~1:1。6. The newly-built rectangular pipe jacking method according to claim 1, wherein the unloading and balancing construction method of the existing subway tunnel is characterized in that the grouting sequence of the pressure-injected soil consolidation grout in the step S6 is specifically: the ground Slurry mixing→start grouting pump→open main pipe valve→open pipe joint valve→slurry delivery→close pipe joint valve→main pipe valve close→disassemble quick joint in well→lower pipe joint→connect 2-inch main pipe→cycle start again; grouting Materials and ratio: P042.5 cement is used as the cementitious material, and the ratio of slurry is controlled within the following range: 0.5:1~1:1. 7.根据权利要求1所述的新建矩形顶管上穿既有地铁隧道卸荷平衡施工方法,其特征在于,所述步骤S7既有隧道变形监测具体为:在顶管顶进过程中,对既有盾构隧道的变形使用智能化全站仪进行监测;当顶管开挖面处于次要影响区时,监测频率为1~2次/天;当顶管开挖面处于主要影响区时,监测频率为3~4次/天。7. The newly-built rectangular pipe jacking method according to claim 1, wherein the unloading and balancing construction method of the existing subway tunnel is characterized in that, the deformation monitoring of the existing tunnel in the step S7 is specifically: during the pipe jacking process, the The deformation of the existing shield tunnel is monitored with an intelligent total station; when the pipe jacking excavation surface is in the secondary influence area, the monitoring frequency is 1-2 times/day; when the pipe jacking excavation surface is in the main influence area , The monitoring frequency is 3-4 times/day. 8.根据权利要求1所述的新建矩形顶管上穿既有地铁隧道卸荷平衡施工方法,其特征在于,所述步骤S8和步骤S9中预警值设定范围是3~5mm。8. The construction method for unloading and balancing construction of a new rectangular pipe jacking on an existing subway tunnel according to claim 1, characterized in that the setting range of the warning value in the steps S8 and S9 is 3-5 mm. 9.根据权利要求1所述的新建矩形顶管上穿既有地铁隧道卸荷平衡施工方法,其特征在于,所述步骤S9中对管节采取压载措施的具体步骤为:9. The newly-built rectangular pipe jacking method according to claim 1, wherein the existing subway tunnel unloading balance construction method is characterized in that, in the step S9, the specific steps of taking ballast measures for the pipe joints are: S91、若是在顶管开挖面进入主要影响区前实施堆载压重,则待顶管机每次对隧道前方土体开挖一个管节的容量后,及时计算出开挖土体与管节的重量差,采用同等重量差重量的预制C20素砼或铁块对主要影响区内的管节实施堆载压重;;待每一管节土体开挖至堆载压重完成后,方进行后续土体的开挖工作;当已压载的管节离开主要影响区时,将其用于压载的素砼或铁块搬离至后续进入主要影响区的管节上;S91. If stacking and ballasting is carried out before the excavation surface of the pipe jacking enters the main affected area, after the pipe jacking machine excavates the capacity of a pipe joint in the soil in front of the tunnel each time, the excavated soil and pipe joints will be calculated in time. If the weight difference of the joints is different, the prefabricated C20 plain concrete or iron blocks with the same weight difference shall be used to carry out heap ballasting on the pipe joints in the main influence area; after the excavation of the soil body of each pipe joint until the heap ballasting is completed, When the ballasted pipe joint leaves the main impact area, the plain concrete or iron block used for ballasting is moved to the subsequent pipe joint that enters the main impact area; S92、若是在后续掘进过程中实施堆载,则立刻对主要影响区内的所有管节进行堆载压重,具体步骤与上述步骤S91一致。S92. If heaping is to be carried out during the subsequent excavation process, immediately perform heaping and ballasting on all pipe joints in the main influence area, and the specific steps are consistent with the above-mentioned step S91. 10.根据权利要求1所述的新建矩形顶管上穿既有地铁隧道卸荷平衡施工方法,其特征在于,所述步骤S10顶管机出洞具体包括两种情况:10. The newly-built rectangular pipe jacking method according to claim 1, wherein the unloading and balancing construction method of passing through an existing subway tunnel is characterized in that, the exiting hole of the pipe jacking machine in the step S10 specifically includes two situations: S101、若顶管顶进全程并未采取压载措施,则对顶管机进行分解并吊出接收井,之后进行浆液置换,以及拆除管内设备、嵌缝、清理、接头处理;S101. If ballasting measures are not taken during the whole process of pipe jacking, the pipe jacking machine shall be disassembled and hoisted out of the receiving well, followed by grout replacement, removal of equipment in the pipe, caulking, cleaning, and joint treatment; S102、若对顶管采取了压载措施,则在顶管全程贯通后通过管节注浆孔对主要影响区内的土层进行注浆加固;注浆加固后逐节搬离堆载物,并同步监测既有隧道变形,若每节堆载物搬离后,既有隧道变形稳定,则继续搬离下一节重物,直至全部搬离,如变形不稳定,则继续注浆或采取其他地层加固措施,直至搬离堆载物不影响隧道的后续变形;待隧道变形稳定后再进行顶管机分解并吊出接收井以及后续工作。S102. If ballasting measures are taken for the pipe jacking, after the pipe jacking is completely penetrated, the soil layer in the main affected area shall be grouted and reinforced through the grouting holes of the pipe joints; Simultaneously monitor the deformation of the existing tunnel. If the deformation of the existing tunnel is stable after each section of load is removed, continue to remove the next section of heavy objects until all are removed. If the deformation is unstable, continue grouting or take measures Other stratum reinforcement measures will not affect the subsequent deformation of the tunnel until the load is removed; after the deformation of the tunnel is stable, the pipe jacking machine will be disassembled and hoisted out of the receiving shaft and follow-up work.
CN202210774164.4A 2022-07-01 2022-07-01 Unloading balance construction method for newly-built rectangular pipe-jacking upward-penetrating existing subway tunnel Pending CN115306397A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210774164.4A CN115306397A (en) 2022-07-01 2022-07-01 Unloading balance construction method for newly-built rectangular pipe-jacking upward-penetrating existing subway tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210774164.4A CN115306397A (en) 2022-07-01 2022-07-01 Unloading balance construction method for newly-built rectangular pipe-jacking upward-penetrating existing subway tunnel

Publications (1)

Publication Number Publication Date
CN115306397A true CN115306397A (en) 2022-11-08

Family

ID=83855919

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210774164.4A Pending CN115306397A (en) 2022-07-01 2022-07-01 Unloading balance construction method for newly-built rectangular pipe-jacking upward-penetrating existing subway tunnel

Country Status (1)

Country Link
CN (1) CN115306397A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115507808A (en) * 2022-09-14 2022-12-23 中国地质大学(武汉) Test device and method for simulating stress deformation characteristic of existing tunnel under adjacent tunnel construction condition
CN116878577A (en) * 2023-07-19 2023-10-13 山东大学 Method and system for monitoring tunnel drilling and blasting in-situ reconstruction and expansion engineering

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104766129A (en) * 2014-12-31 2015-07-08 华中科技大学 Subway shield construction surface deformation warning method based on temporal and spatial information fusion
CN109682416A (en) * 2018-12-19 2019-04-26 中国地质大学(武汉) Measure the experimental provision and method of the distribution of tunnel Water And Earth Pressures and tunnel deformation rule
CN110147587A (en) * 2019-04-29 2019-08-20 浙江大学城市学院 Load causes the calculation method of existing tunnel displacement deformation in a kind of tunnel
CN111101540A (en) * 2019-12-20 2020-05-05 粤水电轨道交通建设有限公司 Construction method for passing existing electric power tunnel on open cut tunnel
CN112818510A (en) * 2021-01-04 2021-05-18 浙江省大成建设集团有限公司 Accurate method for predicting vertical displacement of foundation pit excavation to adjacent tunnel
CN113360985A (en) * 2021-06-10 2021-09-07 安徽省建筑科学研究设计院 High-precision prediction method for longitudinal deformation of existing shield tunnel caused by penetration of newly-built tunnel
US20210301660A1 (en) * 2020-03-25 2021-09-30 Bridge & Tunnel Engineering Company of the Third Engineering Group Co. Ltd. of China Railway Construction method for making water-rich sand layer shield over cross existing line and underneath cross sewage push pipe at close range

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104766129A (en) * 2014-12-31 2015-07-08 华中科技大学 Subway shield construction surface deformation warning method based on temporal and spatial information fusion
CN109682416A (en) * 2018-12-19 2019-04-26 中国地质大学(武汉) Measure the experimental provision and method of the distribution of tunnel Water And Earth Pressures and tunnel deformation rule
CN110147587A (en) * 2019-04-29 2019-08-20 浙江大学城市学院 Load causes the calculation method of existing tunnel displacement deformation in a kind of tunnel
CN111101540A (en) * 2019-12-20 2020-05-05 粤水电轨道交通建设有限公司 Construction method for passing existing electric power tunnel on open cut tunnel
US20210301660A1 (en) * 2020-03-25 2021-09-30 Bridge & Tunnel Engineering Company of the Third Engineering Group Co. Ltd. of China Railway Construction method for making water-rich sand layer shield over cross existing line and underneath cross sewage push pipe at close range
CN112818510A (en) * 2021-01-04 2021-05-18 浙江省大成建设集团有限公司 Accurate method for predicting vertical displacement of foundation pit excavation to adjacent tunnel
CN113360985A (en) * 2021-06-10 2021-09-07 安徽省建筑科学研究设计院 High-precision prediction method for longitudinal deformation of existing shield tunnel caused by penetration of newly-built tunnel

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
LIANG R ET AL.: "Responses of in-service shield tunnel to overcrossing tunnelling in soft ground", 《ENVIRONMENTAL EARTH SCIENCES》, 31 December 2021 (2021-12-31), pages 1 - 15 *
程康等: "既有隧道在上覆基坑卸荷下的形变响应简化算法", 《岩石力学与工程学报》, 30 June 2020 (2020-06-30), pages 637 - 648 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115507808A (en) * 2022-09-14 2022-12-23 中国地质大学(武汉) Test device and method for simulating stress deformation characteristic of existing tunnel under adjacent tunnel construction condition
CN115507808B (en) * 2022-09-14 2024-06-28 中国地质大学(武汉) Test device and method for simulating stress-deformation characteristics of existing tunnels under adjacent tunnel construction conditions
CN116878577A (en) * 2023-07-19 2023-10-13 山东大学 Method and system for monitoring tunnel drilling and blasting in-situ reconstruction and expansion engineering
CN116878577B (en) * 2023-07-19 2024-02-27 山东大学 Method and system for monitoring tunnel drilling and blasting in-situ reconstruction and expansion engineering

Similar Documents

Publication Publication Date Title
CN111396063B (en) Construction method for short-distance upward-crossing existing line downward-passing sewage jacking pipe of water-rich sand layer shield
CN105804758B (en) Across constructing metro tunnel method on the rectangular top pipe of the shallow small spacing of earthing big cross section
CN102587922B (en) A construction method for arc-guided roof lifting in oblique inclined shafts in soft and broken rock formations
CN102733816B (en) Deformation control method when shield traverse building within short distance
CN108316368B (en) Active underpinning method for bridge pile foundation of single-column single pile
CN115306397A (en) Unloading balance construction method for newly-built rectangular pipe-jacking upward-penetrating existing subway tunnel
CN105133856B (en) A kind of method that integral shift is carried out to building using assembled trailer
CN106968690A (en) The method for tunnel construction for soil property of caving in
CN111503368B (en) Pipe jacking construction method under sandy gravel geological condition
CN113062354A (en) Assembly method for prefabricated subway station of open-cut pile support system
CN106499399A (en) A kind of Shield Construction Method Used method of overlapping tunnel in rich water powder land floor
CN113756314B (en) Construction method suitable for excavation of deep large subway foundation pit of soft soil foundation in long triangular area
CN112576265A (en) Sedimentation control method for old villages penetrated by shield
CN103244143B (en) A kind of underground construction excavating construction method and underground station
CN108571330A (en) Method for treating leakage water of post-cast strip of subway bottom plate
CN105178355B (en) The stratum pre-reinforcement processing method of underground space construction
CN203891047U (en) Equipment equipped with steel platform for foundation construction of land bridge
CN115030222B (en) Deformation control method for large-angle upward crossing existing track traffic line of open-cut tunnel
CN115217474B (en) Top-facing layered filling mining method for long anchor cable pre-protecting layer of thick and large crushed ore body
CN112507424B (en) A construction method for shield tunneling under expansive soil strata to pass through railway tracks
CN113323722B (en) Special tunnel water burst treatment method
CN115354667A (en) Protection method for super-close distance implementation open excavation and overpass structure of subway shield in liquefied soil
CN113700503A (en) Uneven settlement reinforcement treatment method in expressway tunnel bottom plate construction process
CN110130397A (en) Hexagonal pipe gallery system combined with inclined support and main structure and its construction method
CN118499016B (en) An underwater cushion construction method matching U-shaped shield construction

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination