CN103866979A - 一种转换层卸荷式支模体系施工工法 - Google Patents
一种转换层卸荷式支模体系施工工法 Download PDFInfo
- Publication number
- CN103866979A CN103866979A CN201410069504.9A CN201410069504A CN103866979A CN 103866979 A CN103866979 A CN 103866979A CN 201410069504 A CN201410069504 A CN 201410069504A CN 103866979 A CN103866979 A CN 103866979A
- Authority
- CN
- China
- Prior art keywords
- support body
- conversion layer
- step square
- vertical rod
- formwork
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
Abstract
本发明公开了一种转换层卸荷式支模体系施工工法,包括转换层大截面混凝土梁支模架体搭设的步骤,支模架体由立杆和水平杆的钢管通过钢管扣件搭设而成,立杆、水平杆的端部均与四周的框架柱、框架梁、剪力墙顶紧顶牢,水平杆与邻近柱抱箍。本发明采用采用普通的钢管、扣件、顶托等材料进行支模架搭设从而完成转换层的支模架施工,通过周边已成型梁、板、柱对整个支模架进行加固和卸载,从而科学合理地完成转换层支模架施工。
Description
技术领域
本发明涉及超重梁支模技术。
背景技术
为了上下结构的变换要求,在高层建筑中往往会设计有从框架结构到剪力墙筒体结构的转换层。转换层又多以大截面混凝土梁来达到传力的目的。根据建质[87]号文,搭设高度超过8m,施工总荷载15KN/m2及以上,集中荷载20KN/m及以上为超高、超重梁。由于超高、超重梁有其特殊性,若以一般的支模方式或者混凝土浇筑方式无法满足施工的正常进行。
发明内容
本发明所要解决的技术问题就是提供了一种转换层卸荷式支模体系施工工法,解决超高、超重梁施工困难的技术问题。
为解决上述技术问题,本发明采用如下技术方案:一种转换层卸荷式支模体系施工工法,包括转换层大截面混凝土梁支模架体搭设的步骤,支模架体由立杆和水平杆的钢管通过钢管扣件搭设而成,立杆、水平杆的端部均与四周的框架柱、框架梁、剪力墙顶紧顶牢,水平杆与邻近柱抱箍。
优选的,支模架体的主要技术参数为:
1)每延米1.5吨以下的梁立杆沿梁跨方向间距450mm,梁底增加一根立杆,梁两侧立杆间距为梁宽+400~500mm,步矩≤1500mm;
2)每延米1.5吨-3吨的梁立杆沿梁跨方向间距450mm,梁底增加两根立杆,梁两侧立杆间距为梁宽+400~500mm,步矩≤1500mm,架体搭设高20m以下的梁最上两步矩750mm;
3)每延米3-5吨的梁立杆沿梁跨方向间距450mm,梁底增加三根立杆,步矩750mm,架体搭设高20m以下的梁最上两步矩750mm;
4)每延米大于5吨的梁立杆沿梁跨方向间距300mm,梁底增加三根立杆,步矩750mm,架体搭设高20m以下的梁最上两步矩750mm;
5)架体搭设高20m以下的梁最上两步矩750mm,架体搭设高20m以上的最上四步的步矩750mm。
本发明采用采用普通的钢管、扣件、顶托等材料进行支模架搭设从而完成转换层的支模架施工,通过周边已成型梁、板、柱对整个支模架进行加固和卸载,从而科学合理地完成转换层支模架施工。
具体实施方式
本发明工法适用于下部大空间,上部部分竖向构件不能直接连续贯通落地,而通过水平转换结构与下部竖向构件连接的高层建筑转换层施工中。
一种转换层卸荷式支模体系施工工法,包括转换层大截面混凝土梁支模架体搭设的步骤,支模架体由立杆和水平杆的钢管通过钢管扣件搭设而成,立杆、水平杆的端部均与四周的框架柱、框架梁、剪力墙顶紧顶牢,水平杆与邻近柱抱箍。
支模架体的主要技术参数为:
1)每延米1.5吨以下的梁立杆沿梁跨方向间距450mm,梁底增加一根立杆,梁两侧立杆间距为梁宽+400~500mm,步矩≤1500mm;
2)每延米1.5吨-3吨的梁立杆沿梁跨方向间距450mm,梁底增加两根立杆,梁两侧立杆间距为梁宽+400~500mm,步矩≤1500mm,架体搭设高20m以下的梁最上两步矩750mm;
3)每延米3-5吨的梁立杆沿梁跨方向间距450mm,梁底增加三根立杆,步矩750mm,架体搭设高20m以下的梁最上两步矩750mm;
4)每延米大于5吨的梁立杆沿梁跨方向间距300mm,梁底增加三根立杆,步矩750mm,架体搭设高20m以下的梁最上两步矩750mm。
5)架体搭设高20m以下的梁最上两步矩750mm,架体搭设高20m以上的最上四步的步矩750mm。
本发明工法优点为:
1、该工法操作简便,所用材料均为一般的支模材料,节约成本。
2、通过与周边已成型柱抱牢,水平杆顶紧周边梁柱,加强架体的整体性。
3、通过在转换层周边已成型梁上预埋钢管或拉环,反拉钢丝绳对架体进行卸荷,从而减小支撑架体对基础的荷载,有效保证梁施工安全和质量。
4、通过合理设计转换层支撑架体纵横水平杆位置,将纵横水平杆架于周边各层梁板上,从而达到进一步卸荷的目的。
Claims (2)
1.一种转换层卸荷式支模体系施工工法,包括转换层大截面混凝土梁支模架体搭设的步骤,其特征在于:支模架体由立杆和水平杆的钢管通过钢管扣件搭设而成,立杆、水平杆的端部均与四周的框架柱、框架梁、剪力墙顶紧顶牢,水平杆与邻近柱抱箍。
2.根据权利要求1所述的转换层卸荷式支模体系施工工法,其特征在于支模架体的主要技术参数为:
1)每延米1.5吨以下的梁立杆沿梁跨方向间距450mm,梁底增加一根立杆,梁两侧立杆间距为梁宽+400~500mm,步矩≤1500mm;
2)每延米1.5吨-3吨的梁立杆沿梁跨方向间距450mm,梁底增加两根立杆,梁两侧立杆间距为梁宽+400~500mm,步矩≤1500mm,架体搭设高20m以下的梁最上两步矩750mm;
3)每延米3-5吨的梁立杆沿梁跨方向间距450mm,梁底增加三根立杆,步矩750mm,架体搭设高20m以下的梁最上两步矩750mm;
4)每延米大于5吨的梁立杆沿梁跨方向间距300mm,梁底增加三根立杆,步矩750mm,架体搭设高20m以下的梁最上两步矩750mm;
5)架体搭设高20m以下的梁最上两步矩750mm,架体搭设高20m以上的最上四步的步矩750mm。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410069504.9A CN103866979A (zh) | 2014-02-27 | 2014-02-27 | 一种转换层卸荷式支模体系施工工法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410069504.9A CN103866979A (zh) | 2014-02-27 | 2014-02-27 | 一种转换层卸荷式支模体系施工工法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN103866979A true CN103866979A (zh) | 2014-06-18 |
Family
ID=50905958
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410069504.9A Pending CN103866979A (zh) | 2014-02-27 | 2014-02-27 | 一种转换层卸荷式支模体系施工工法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103866979A (zh) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105298125A (zh) * | 2015-10-16 | 2016-02-03 | 中建三局集团有限公司 | 一种下承上挂结构体系及其施工方法 |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101761231A (zh) * | 2009-12-31 | 2010-06-30 | 青建集团股份公司 | 梁式转换层模板支撑构造及下部结构加固方法 |
CN102619331A (zh) * | 2011-03-08 | 2012-08-01 | 青光绪 | 高层建筑梁式转换层钢管支撑叠合浇筑一次成型施工方法 |
CN103046746A (zh) * | 2012-12-03 | 2013-04-17 | 成军 | 高层建筑结构转换梁钢筋施工方法 |
KR20130075136A (ko) * | 2011-12-27 | 2013-07-05 | 주식회사 에스더블유비앤씨 | 무지주용 슬래브 거푸집 |
-
2014
- 2014-02-27 CN CN201410069504.9A patent/CN103866979A/zh active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101761231A (zh) * | 2009-12-31 | 2010-06-30 | 青建集团股份公司 | 梁式转换层模板支撑构造及下部结构加固方法 |
CN102619331A (zh) * | 2011-03-08 | 2012-08-01 | 青光绪 | 高层建筑梁式转换层钢管支撑叠合浇筑一次成型施工方法 |
KR20130075136A (ko) * | 2011-12-27 | 2013-07-05 | 주식회사 에스더블유비앤씨 | 무지주용 슬래브 거푸집 |
CN103046746A (zh) * | 2012-12-03 | 2013-04-17 | 成军 | 高层建筑结构转换梁钢筋施工方法 |
Non-Patent Citations (3)
Title |
---|
何盛熙: ""某工程转换层支模体系施工与安全控制"", 《施工技术》, vol. 39, no. 4, 30 April 2010 (2010-04-30) * |
江建玲: ""高层住宅结构转换层的施工技术"", 《中国新技术新产品》, no. 8, 25 April 2012 (2012-04-25) * |
陆锦峰: ""高层住宅结构转换层的施工技术"", 《建筑施工》, vol. 33, no. 9, 25 September 2011 (2011-09-25) * |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105298125A (zh) * | 2015-10-16 | 2016-02-03 | 中建三局集团有限公司 | 一种下承上挂结构体系及其施工方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101575911B (zh) | 逆作降模模板系统及施工方法 | |
CN101824800B (zh) | 一种桥位现浇预应力混凝土连续梁的施工方法 | |
CN104746422A (zh) | 一种桥梁预制空心墩柱后浇连接结构及施工方法 | |
WO2012057510A3 (ko) | 철골/철근 콘크리트 구조를 갖는 고층 건축구조물 시공구조 | |
CN103452311A (zh) | 一种型钢悬挑结构支撑架的搭设方法 | |
CN212200750U (zh) | 一种装配式建筑框架结构组合支撑系统 | |
CN109914244B (zh) | 一种适用于高塔钢混结合横梁钢结构安装及底、顶板混凝土浇筑的弱支架系统及其操作方法 | |
CN102277835A (zh) | 单柱盖梁采用抱箍与三角支架组合体系施工方法 | |
CN103046645A (zh) | 一种大跨度预制整浇结构及施工方法 | |
WO2014126544A1 (en) | Horizontal and vertical reinforcement used on columns and structural walls in buildings | |
CN103966947B (zh) | 一种基于桥梁梁体减震的防落梁装置 | |
CN103883052A (zh) | 上翻梁与现浇板整体浇筑施工方法 | |
CN103194982B (zh) | 桥梁边跨现浇段短悬臂支架施工方法 | |
CN203834926U (zh) | 清水混凝土地下室外墙模板支模结构 | |
CN204097864U (zh) | 一种桥梁预制空心墩柱后浇连接结构 | |
CN111535628B (zh) | 一种c型料场上部结构的施工方法 | |
CN103866979A (zh) | 一种转换层卸荷式支模体系施工工法 | |
CN104234418A (zh) | 钢筋混凝土梁拱型早拆模板及其施工方法 | |
CN202596161U (zh) | 一种hr重型门架与钢筋混凝土临时结构柱联合支模装置 | |
CN102828616A (zh) | 一种屋盖高支模体系 | |
CN105781159A (zh) | 一种电厂主厂房钢筋混凝土煤漏斗施工工艺 | |
CN102409845A (zh) | 一种梁模板支撑架 | |
CN102505859B (zh) | 转换层梁上型钢混凝土柱纵向钢筋并焊方法 | |
CN105442737A (zh) | 一种新型复合保温楼面板及其施工方法 | |
CN103485524A (zh) | 牛腿式悬挑脚手架及其搭设时的施工工法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C12 | Rejection of a patent application after its publication | ||
RJ01 | Rejection of invention patent application after publication |