Nothing Special   »   [go: up one dir, main page]

CN103048616B - SF 6the charged calibration equipment of density monitor - Google Patents

SF 6the charged calibration equipment of density monitor Download PDF

Info

Publication number
CN103048616B
CN103048616B CN201210576677.0A CN201210576677A CN103048616B CN 103048616 B CN103048616 B CN 103048616B CN 201210576677 A CN201210576677 A CN 201210576677A CN 103048616 B CN103048616 B CN 103048616B
Authority
CN
China
Prior art keywords
valve
air outlet
density monitor
calibration equipment
gas admittance
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201210576677.0A
Other languages
Chinese (zh)
Other versions
CN103048616A (en
Inventor
吴哲
孙鹏
崔天宝
高鹏
王涛
王世儒
王晔
崔汉斌
盖恒民
马彬
徐斌
孙宏
何慧君
姜会玲
郑元华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Zibo Power Supply Co of State Grid Shandong Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
Zibo Power Supply Co of State Grid Shandong Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Zibo Power Supply Co of State Grid Shandong Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201210576677.0A priority Critical patent/CN103048616B/en
Publication of CN103048616A publication Critical patent/CN103048616A/en
Application granted granted Critical
Publication of CN103048616B publication Critical patent/CN103048616B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • Gas-Insulated Switchgears (AREA)

Abstract

The present invention relates to a kind of SF 6the charged calibration equipment of density monitor.Described SF 6the charged calibration equipment of density monitor, comprises gas admittance valve, variable valve, standard scale and air outlet valve, and gas admittance valve, variable valve, standard scale and air outlet valve are linked in sequence by loading line.The present invention is rational in infrastructure, easy to use, is easy to carry, and can not dismantle SF 6on the basis of density monitor, its accuracy is detected.

Description

SF6密度继电器带电校验装置SF6 Density Relay Live Calibration Device

技术领域 technical field

本发明涉及一种SF6密度继电器带电校验装置。 The invention relates to a SF 6 density relay electrification verification device.

背景技术 Background technique

SF6气体密度继电器是指示SF6电气设备内部压力的检测设备,并具有气体压力检查报警及闭锁接点动作的保护性功能,其测量及动作的准确性直接关系到SF6电气设备的安全运行,因此必须到达有关标准的规定,使SF6电气一次设备长期保持良好的运行工况。 SF 6 gas density relay is a detection device that indicates the internal pressure of SF 6 electrical equipment, and has the protective function of gas pressure inspection alarm and blocking contact action. The accuracy of its measurement and action is directly related to the safe operation of SF 6 electrical equipment. Therefore, it is necessary to meet the requirements of the relevant standards, so that the SF 6 electrical primary equipment can maintain good operating conditions for a long time.

SF6密度继电器校验工作是指校验SF6密度继电器在0.6Mpa额定压力指示值、0.52Mpa报警压力指示值、0.5Mpa闭锁压力指示值,与模拟标准压力值进行比较,以观察指示值是否正确,来判断SF6密度继电器指示准确及接点动作的好坏。 The verification work of SF 6 density relay refers to the verification of SF 6 density relay at 0.6Mpa rated pressure indication value, 0.52Mpa alarm pressure indication value, 0.5Mpa blocking pressure indication value, and comparing with the analog standard pressure value to observe whether the indication value Correct, to judge the accuracy of the SF 6 density relay indication and the quality of the contact action.

国家电网公司2012年352文《国家电网公司十八项电网重大反事故措施》明确规定:SF6密度继电器与开关设备本体之间的连接方式应满足不拆卸校验密度继电器的要求。 State Grid Corporation’s 2012 article 352 “State Grid Corporation’s Eighteen Major Power Grid Anti-Accident Measures” clearly stipulates that the connection method between the SF 6 density relay and the switchgear body should meet the requirements of not disassembling the density relay.

同时由于校验SF6密度继电器工作量较大,研制一种不用拆卸即可带电校验SF6密度继电器的专用装置,对缩短工作时间,提高工作效率,及时发现存在异常故障的SF6密度继电器具有重要意义。 At the same time, due to the large workload of verifying SF 6 density relays, a special device for live verification of SF 6 density relays without disassembly is developed, which can shorten working time, improve work efficiency, and timely detect SF 6 density relays with abnormal faults is of great significance.

发明内容 Contents of the invention

根据以上现有技术中的不足,本发明要解决的技术问题是:提供一种能够不用拆卸SF6密度继电器即可带电对SF6密度继电器进行比对校验的SF6密度继电器带电校验装置。 According to the deficiencies in the prior art above, the technical problem to be solved in the present invention is: provide a kind of SF 6 density relay electrification verification device that can compare and verify the SF 6 density relay without dismantling the SF 6 density relay .

本发明所提供的SF6密度继电器带电校验装置,包括进气阀、调节阀、标准表和出气阀,进气阀、调节阀、标准表和出气阀通过充气管路顺序连接。 The SF 6 density relay electrification verification device provided by the present invention includes an inlet valve, a regulating valve, a standard gauge and an outlet valve, and the inlet valve, the regulating valve, the standard gauge and the outlet valve are sequentially connected through an inflation pipeline.

所述的进气阀、调节阀、标准表和出气阀依次连接后设置在装配箱内,进气阀的进口、出气阀的出口、标准表的显示面与调节阀的调节口,均设置在装配箱的同一平面上。便于携带,接口均在同一平面上使用时更方便、快捷。 The inlet valve, regulating valve, standard meter and outlet valve are arranged in the assembly box after being connected in sequence, and the inlet of the inlet valve, the outlet of the outlet valve, the display surface of the standard meter and the regulating port of the regulating valve are all arranged in the on the same plane as the box. It is easy to carry, and it is more convenient and fast to use when the interfaces are all on the same plane.

所述的进气阀的进口和出气阀的出口处均安装有快速自封接头。插接方便,密封性好,保证气体不会泄露。 Both the inlet of the inlet valve and the outlet of the outlet valve are equipped with quick self-sealing joints. It is easy to connect and connect, and has good sealing performance to ensure that the gas will not leak.

所述的标准表为0.25级准确度标准表,满足比被校验的SF6密度继电器准确度等级1.5级高两级的标准要求;调节阀可采用节流阀的工作原理,具有流量自主调节,控制气体压力变化功能;充气管路材料为聚四氟乙烯材料,重量轻、耐腐蚀、耐氧化、抗高电压、不吸水等优点。 The standard table is a 0.25-level accuracy standard table, which meets the standard requirements of two levels higher than the 1.5-level accuracy level of the verified SF 6 density relay; the regulating valve can adopt the working principle of a throttle valve, and has self-regulating flow , Control gas pressure change function; Inflatable pipeline material is polytetrafluoroethylene material, light weight, corrosion resistance, oxidation resistance, high voltage resistance, non-absorbent and other advantages.

本发明所提供的SF6密度继电器带电校验装置,结构合理,使用方便,便于携带,可在不拆卸SF6密度继电器的基础上,对其准确性进行检测。 The SF 6 density relay electrification verification device provided by the present invention has a reasonable structure, is convenient to use and is portable, and can detect the accuracy of the SF 6 density relay without disassembling it.

附图说明 Description of drawings

图1是本发明结构示意图; Fig. 1 is a structural representation of the present invention;

图中:1、进气阀;2、充气管路;3、调节阀;4、标准表;5、出气阀。 In the figure: 1. Inlet valve; 2. Inflatable pipeline; 3. Regulating valve; 4. Standard gauge; 5. Outlet valve.

具体实施方式 Detailed ways

下面结合附图对本发明的实施例做进一步描述: Embodiments of the present invention are further described below in conjunction with accompanying drawings:

如图1所示的SF6密度继电器带电校验装置,包括进气阀1、调节阀3、标准表4和出气阀5,进气阀1、调节阀3、标准表4和出气阀5通过充气管路2顺序连接。进气阀1、调节阀3、标准表4和出气阀5依次连接后设置在装配箱内,进气阀1的进口、出气阀5的出口、标准表4的显示面与调节阀3的调节口,均设置在装配箱的同一平面上。进气阀1的进口和出气阀5的出口处均安装有快速自封接头。标准表4为0.25级准确度标准表。 The SF 6 density relay electrification verification device shown in Figure 1 includes an inlet valve 1, a regulating valve 3, a standard meter 4 and an outlet valve 5, and the inlet valve 1, regulating valve 3, standard meter 4 and outlet valve 5 pass through The inflation pipelines 2 are connected sequentially. Intake valve 1, regulating valve 3, standard meter 4 and outlet valve 5 are connected in sequence and arranged in the assembly box, the inlet of inlet valve 1, the outlet of outlet valve 5, the display surface of standard meter 4 and the adjustment of regulating valve 3 The openings are all set on the same plane of the assembly box. A quick self-sealing joint is installed at the inlet of the air inlet valve 1 and the outlet of the air outlet valve 5 . Standard Table 4 is the standard table for 0.25 level accuracy.

校验流程为:关闭变电一次设备本体的控制阀门,切断SF6密度继电器与设备本体相连;将该带电校验装置与SF6密度继电器相连,用自带的SF6气瓶对其进行预充气至额定压力,用标准表4对SF6密度继电器进行校验,检查额定压力指示是否准确;脱离SF6气瓶,从进气阀1进行放气,逐渐降低SF6气体压力,待标准表4压力分别指示报警压力、闭锁压力时,观察SF6密度继电器在这两个刻度读数是否准确,是否超出数值偏差,并用万用表测量SF6密度继电器报警、闭锁接点动作的可靠性;逐渐放气至零表压,校验工作结束。 The verification process is as follows: close the control valve of the substation primary equipment body, cut off the connection between the SF 6 density relay and the equipment body ; Inflate to the rated pressure, check the SF 6 density relay with standard table 4, and check whether the rated pressure indication is accurate; detach from the SF 6 gas cylinder, deflate from the intake valve 1, gradually reduce the SF 6 gas pressure, wait for the standard table 4 When the pressure respectively indicates the alarm pressure and the blocking pressure, observe whether the readings of the SF 6 density relay on these two scales are accurate and whether the value deviation is exceeded, and use a multimeter to measure the reliability of the SF 6 density relay alarm and blocking contact action; gradually deflate to Zero gauge pressure, the calibration work is over.

Claims (2)

1. a SF 6the charged calibration equipment of density monitor, is characterized in that, comprises gas admittance valve, variable valve, standard scale and air outlet valve, and gas admittance valve, variable valve, standard scale and air outlet valve are linked in sequence by loading line;
Be arranged in assembling case after described gas admittance valve, variable valve, standard scale are connected successively with air outlet valve, the display surface of the import of gas admittance valve, the outlet of air outlet valve, standard scale and the adjustment mouth of variable valve, be all arranged on the same plane of assembling case; The import of described gas admittance valve and the exit of air outlet valve are all provided with Quick self-sealing joint.
2. SF according to claim 1 6the charged calibration equipment of density monitor, is characterized in that, described standard scale is 0.25 grade of standard of accruacy table.
CN201210576677.0A 2012-12-26 2012-12-26 SF 6the charged calibration equipment of density monitor Active CN103048616B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210576677.0A CN103048616B (en) 2012-12-26 2012-12-26 SF 6the charged calibration equipment of density monitor

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210576677.0A CN103048616B (en) 2012-12-26 2012-12-26 SF 6the charged calibration equipment of density monitor

Publications (2)

Publication Number Publication Date
CN103048616A CN103048616A (en) 2013-04-17
CN103048616B true CN103048616B (en) 2015-11-18

Family

ID=48061324

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210576677.0A Active CN103048616B (en) 2012-12-26 2012-12-26 SF 6the charged calibration equipment of density monitor

Country Status (1)

Country Link
CN (1) CN103048616B (en)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106680143A (en) * 2016-11-22 2017-05-17 中国南方电网有限责任公司超高压输电公司曲靖局 Verifying device of SF6 gas density sensor
CN108535641B (en) * 2018-06-12 2024-03-08 广东电网有限责任公司 SF6 density relay calibration device
CN110187265A (en) * 2019-05-29 2019-08-30 知为力(成都)科技有限公司 A kind of density monitor calibration equipment
CN111637258B (en) * 2020-06-01 2021-12-14 中国南方电网有限责任公司超高压输电公司大理局 Portable needle type exhaust joint and sulfur hexafluoride density relay checking method
CN112269125A (en) * 2020-10-21 2021-01-26 中广核核电运营有限公司 Pressure switch on-line checking method
CN112665782B (en) * 2020-12-16 2023-04-14 国网冀北电力有限公司检修分公司 A gas pressure online monitoring system and online monitoring method

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN203117384U (en) * 2012-12-26 2013-08-07 山东电力集团公司淄博供电公司 SF6 Density Relay Live Calibration Device

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0074498B1 (en) * 1981-09-04 1985-12-04 F. HOFFMANN-LA ROCHE & CO. Aktiengesellschaft Method and apparatus for the calibration of sensors
CN201004041Y (en) * 2007-01-08 2008-01-09 苏丽芳 SF6 air density relay calibrator for automatic rated value test
CN202133757U (en) * 2011-06-27 2012-02-01 常州爱特科技有限公司 Automatic check meter for SF6 density relay

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN203117384U (en) * 2012-12-26 2013-08-07 山东电力集团公司淄博供电公司 SF6 Density Relay Live Calibration Device

Also Published As

Publication number Publication date
CN103048616A (en) 2013-04-17

Similar Documents

Publication Publication Date Title
CN103048616B (en) SF 6the charged calibration equipment of density monitor
CN103306968B (en) transformer oil pump test device and test method thereof
CN105021356A (en) Test method for detecting leakage of hydrogen system of hydrogen-cooled generator
CN201803832U (en) Test device for detecting valve leakage by acoustic emission signal
CN203241325U (en) Portable device for water-pressure test in situ
CN103196800B (en) Structural plane transmission coefficient defining method and test unit
CN105736953B (en) A kind of the liquefied ammonia pipeline leakage checking system with clad and its method based on pressure sensitive
CN203335372U (en) Transformer oil pump testing device
CN205642764U (en) Movable makes up device that leaks hunting
CN207991654U (en) A kind of portable gas table calibrating installation
CN106124135A (en) A kind of device and method sealing tiny leakage for detecting high-power transformer cannula tip
CN206002261U (en) A kind of device for detecting high-power transformer cannula tip sealing tiny leakage
CN203117384U (en) SF6 Density Relay Live Calibration Device
CN203069372U (en) Valve testing device in vacuum environment
CN201732085U (en) Detection device for hydrogen sulfide in natural gas pipeline
CN204649491U (en) A kind of New type of S F 6multi-purpose gas way adapter
CN201876391U (en) Test bench for testing water pressure strength of cylinder
CN203688152U (en) Novel gas pressure reducer verifying device
CN203981382U (en) Large flow pneumatic accessories testing table
CN202994400U (en) Box gas leakage detector
CN205879454U (en) Special detection instrument of insulating gloves
CN204301761U (en) A kind of instrument calibration device for pure water cooling system
CN205262697U (en) Gas solenoid valve auto -action performance and leakage test machine
CN204788789U (en) On --spot detection device of cold pressure sensor of system of valve
CN209928602U (en) Gas alarm calibrating device

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C53 Correction of patent for invention or patent application
CB02 Change of applicant information

Address after: 255000, 100 meters north of Beijing road and Unicom Road, Zibo, Shandong

Applicant after: Zibo Power Supply Company of State Grid Shandong Province Electric Power Company

Applicant after: State Grid Corporation of China

Address before: 255000, 100 meters north of Beijing road and Unicom Road, Zibo, Shandong

Applicant before: Zibo Power Supply Company of Shandong Electric Power Corporation

Applicant before: State Grid Corporation of China

COR Change of bibliographic data

Free format text: CORRECT: APPLICANT; FROM: ZIBO POWER SUPPLY COMPANY OF SHANDONG ELECTRIC POWER CORPORATION TO: STATE GRID SHANDONG ELECTRIC POWER CORPORATION ZIBO POWER COMPANY

C14 Grant of patent or utility model
GR01 Patent grant