CN103029980B - A kind of material basket hangs uninstalling system automatically - Google Patents

A kind of material basket hangs uninstalling system automatically Download PDF

Info

Publication number
CN103029980B
CN103029980B CN201210585376.4A CN201210585376A CN103029980B CN 103029980 B CN103029980 B CN 103029980B CN 201210585376 A CN201210585376 A CN 201210585376A CN 103029980 B CN103029980 B CN 103029980B
Authority
CN
China
Prior art keywords
material basket
suspension
delivery area
hanging
basket
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201210585376.4A
Other languages
Chinese (zh)
Other versions
CN103029980A (en
Inventor
潘满
王子戡
荣显庭
黄启荣
叶金鹏
王丽红
黎焯雄
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Packaging & Food Machinery Co., Ltd.
Original Assignee
CHINA NATIONAL PACKAGING AND FOOD MACHINERY CORP
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CHINA NATIONAL PACKAGING AND FOOD MACHINERY CORP filed Critical CHINA NATIONAL PACKAGING AND FOOD MACHINERY CORP
Priority to CN201210585376.4A priority Critical patent/CN103029980B/en
Publication of CN103029980A publication Critical patent/CN103029980A/en
Application granted granted Critical
Publication of CN103029980B publication Critical patent/CN103029980B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Chain Conveyers (AREA)

Abstract

The invention discloses a kind of material basket and automatically hang uninstalling system, comprise suspension conveying line, material basket suspension rod, material basket and de-bar of putting into gear, the upper end of material basket suspension rod is connected with suspension conveying line, its lower end realizes lifting by suspension hook and the suspension ring on material basket, suspension conveying line is provided with material basket de-extension delivery area, de-bar of putting into gear is arranged at the below of suspension conveying line, and take off the suspension conveying line throughput direction hung in delivery area form a horizontal sextant angle with material basket, material basket takes off the below hanging delivery area and is provided with material basket feedway, material basket feedway takes off with material basket the suspension conveying line hung in delivery area and be arranged in parallel, and the two synchronous transport, be delivered to and expect that basket takes off the material basket hung in delivery area and contacts with material basket feedway, suspension hook and suspension ring take off to be hung, and suspension hook is positioned at suspension ring Dai Gua district, and material basket dependence material basket feedway drives to be carried, when material basket suspension rod is delivered to de-bar end of putting into gear, suspension hook shifts out suspension ring Dai Gua district, the unloading of material basket.Present invention achieves the steady unloading of material basket, improve degree of automation.

Description

A kind of material basket hangs uninstalling system automatically
Technical field
The present invention relates to butchering fowl equipment technical field, particularly one material basket hangs uninstalling system automatically.
Background technology
On current suspension conveying line, Self-tipping or erecting by overhang are divided into two classes.One class be unloading suspension conveying line hook or material basket on material, a class be unloading suspension conveying line on hook or material basket.For unloading hook or this kind of device of expecting basket, when mainly being run by suspension conveying line, collide the block on its service direction, the hook that suspension conveying line is hung or material basket are unloaded.This discharging gear is violently shaken in the uninstall process of hook or material basket, and thus hook or material basket are steady when coming off, and when linking up with or material basket is heavier, also more difficultly it to be unloaded from suspension conveying line.Meanwhile, because the position of block is fixed, so hook or material basket can be deposited in together after coming off, this is unfavorable for that subsequent handling uses, and reduces the degree of automation of manufacturing line.
Summary of the invention
In order to improve the automation unloading degree of suspension conveying line material loading basket, increasing the stationarity of material basket in Self-tipping process, the invention provides a kind of material basket and automatically hanging uninstalling system.
Described technical scheme is as follows:
A kind of material basket hangs uninstalling system automatically, comprise suspension conveying line, material basket suspension rod, material basket and de-bar of putting into gear, the upper end of described material basket suspension rod is connected with described suspension conveying line, its lower end realizes lifting by the suspension ring on suspension hook and described material basket, described suspension conveying line is provided with material basket de-extension delivery area, described de-bar of putting into gear is arranged at the below of described suspension conveying line, and take off with described material basket the suspension conveying line throughput direction hung in delivery area and form a horizontal sextant angle, described material basket takes off the below hanging delivery area and is provided with material basket feedway, described material basket feedway and described material basket take off the suspension conveying line hung in delivery area and be arranged in parallel, and the two synchronous transport, be delivered to described material basket to take off the described material basket hung in delivery area and drop down onto on described material basket feedway, described suspension hook is hung with described suspension ring are de-, and described suspension hook is positioned at the Dai Gua district of described suspension ring, expects that basket is fed forward by described material basket feedway driving, when described material basket suspension rod is delivered to the end of described de-bar of putting into gear along described de-bar of putting into gear, described suspension hook shifts out the Dai Gua district of described suspension ring, described material basket unloading.
Described material basket takes off the conveying end hanging delivery area and is provided with upward slope delivery area, described de-bar of putting into gear takes off near described material basket the conveying end hanging delivery area and arranges, the material basket suspension rod being delivered to described upward slope delivery area is driven by described suspension conveying line upwards to be carried, and described material basket is driven by described material basket feedway and is fed forward.
Described suspension conveying line is also provided with material basket hanging delivery area, hanging pin is provided with in described material basket hanging delivery area, described hanging pin is arranged at below the suspension conveying line in described material basket hanging delivery area, for the suspension hook of described material basket suspension rod lower end is offset its vertical plane, described material basket to be positioned on described material basket feedway and to be positioned at immediately below described material basket suspension rod; The material basket suspension rod be delivered in described material basket hanging delivery area is carried along described hanging pin, and make described suspension hook depart from the Dai Gua district of described suspension ring, when described material basket suspension rod is delivered to the end of described hanging pin, described suspension hook falls into the Dai Gua district of described suspension ring, realizes the hanging of described material basket.
Described hanging pin is circular arc or fold-line-shaped, it is fixedly connected with the support on described suspension conveying line, the two ends of described hanging pin are crossing with the vertical plane that multiple described material basket suspension rod is formed, the material basket suspension rod entered in described material basket hanging delivery area is carried along described hanging pin, realizes the de-extension between described suspension hook and described suspension ring and hanging successively.
The conveying end of described material basket hanging delivery area is provided with conveying upward slope district, described hanging pin is arranged near the conveying top of described material basket hanging delivery area, the material basket being delivered to described conveying upward slope district is driven by described suspension conveying line upwards to be carried, and described material basket and described material basket feedway are separated.
Described material basket takes off the conveying initiating terminal hanging delivery area and is connected with descending delivery area, the conveying initiating terminal of described material basket hanging delivery area is connected with conveying descending district, and the material basket be delivered in described descending delivery area drives conveying downwards with the material basket be delivered in described conveying descending district respectively by described suspension conveying line.
The bottom of described material basket suspension rod is provided with a link plate, and described link plate is provided with suspension hook described at least one; During described material basket hanging, described suspension hook and the clamping of described suspension hook phase; When described material basket takes off and hangs, described suspension hook is positioned at the Dai Gua district of described suspension ring.
Described suspension hook arranges three, it is arranged at the same side of described link plate, suspension hook described in one of them is positioned at the top of described link plate, and another two described suspension hooks are positioned at the bottom of described link plate, bottom two described in suspension hook be symmetricly set in the both sides of the described suspension hook on top; During described material basket hanging, three described suspension hooks and the clamping simultaneously of described suspension ring; When described material basket takes off and hangs, three described suspension hooks are positioned at the Dai Gua district of described suspension ring.
Described suspension ring comprise suspension rod and pole, and the two ends of described suspension rod are fixedly connected with respectively by the base of described pole with described material basket, the curved or taper of described suspension rod; During described material basket hanging, multiple described suspension hook and the clamping simultaneously of described suspension rod; When described material basket takes off and hangs, multiple described suspension hook is all placed in the Dai Gua district of described suspension ring.
The beneficial effect that technical scheme provided by the present invention is brought is:
A the present invention is provided with material basket de-extension delivery area on suspension conveying line, material basket take off hang delivery area suspension conveying line below be provided with material basket feedway, material basket feedway and suspension conveying line speed sync are carried in the same way, entering the material basket material basket taken off in extension delivery area drops down onto on material basket feedway, and rely on material basket feedway to realize conveying, when material basket drops down onto on feedway, the suspension ring of material basket upper end are hung with the suspension hook of material basket suspension rod lower end is de-mutually, the suspension hook of material basket falls in the Dai Gua district of suspension ring, material basket with expect that basket suspension rod synchronously continues in the process be fed forward, vertical plane is departed from the effect blanking basket suspension rod of de-bar of putting into gear, the de-extension that suspension hook and suspension ring realize truly is separated, when this structure is heavier for material basket, be also easy to it to unload from suspension conveying line, expect after basket unloads it is carry in turn on material basket feedway 6 due to front and back, the rear accumulation of expecting basket of unloading before and after can not causing.
B is in order to realize the steady hanging of expecting basket, the present invention is also provided with material basket hanging delivery area on suspension conveying line, first artificial being positioned over by material basket is expected on basket feedway, the position of material basket should be positioned over immediately below material basket suspension rod, before material basket suspension rod touches material basket, suspension hook offsets by material basket suspension rod under the effect of hanging pin, makes it be separated with suspension ring; When continuing to run along hanging pin, suspension hook returns to original vertical position gradually, suspension hook is now positioned at the Dai Gua district of suspension ring, then expect basket suspension rod by up upward slope delivery area or directly with expect that basket feedway is separated, material basket is engaged mutually with suspension hook under its effect of conducting oneself with dignity, thus realizes pulsation-free hanging.
C the present invention is provided with multiple suspension hook on the link plate of material basket suspension rod lower end, preferred employing 3 suspension hooks, 3 suspension hooks are that equicrural triangle is distributed on link plate, and are provided with the suspension rod of taper or circular arc on the top of suspension ring, and the two ends of suspension rod are fixedly connected with the base of material basket respectively by pole; During the hanging of material basket, the suspension hook of topmost and the top clamping of suspension rod, other two with the inclined-plane of suspension rod or cambered surface clamping, form a card access surface when three suspension hooks on link plate and suspension rod clamping, more steady when making material basket hang like this.
D the present invention takes off at material basket the two ends hanging delivery area and material basket hanging delivery area and is provided with upward slope delivery area and descending delivery area respectively, make to expect the hanging of basket and uninstall process more steady, smooth and easy.
Accompanying drawing explanation
In order to be illustrated more clearly in the technical scheme in the embodiment of the present invention, below the accompanying drawing used required in describing embodiment is briefly described, apparently, accompanying drawing in the following describes is only some embodiments of the present invention, for those of ordinary skill in the art, under the prerequisite not paying creative work, other accompanying drawing can also be obtained according to these accompanying drawings.
Fig. 1 is material basket uninstall process constructional drawing provided by the present invention;
Fig. 2-1 is the schematic diagram before material basket corresponding in Fig. 1 is in unloading;
Fig. 2-2 is material basket corresponding in Fig. 1 and suspension rod schematic diagrams when taking off extension;
Fig. 2-3 is material basket corresponding in Fig. 1 schematic diagrams when being separated with suspension rod;
Fig. 2-4 is the schematic diagrams after material basket unloading corresponding in Fig. 1;
Fig. 3 is material basket hoisting process constructional drawing provided by the present invention;
Fig. 4-1 is the schematic diagram before material basket hanging corresponding in Fig. 3;
Fig. 4-2 is that material basket corresponding in Fig. 3 takes off with suspension rod and hangs schematic diagram;
Fig. 4-3 is that material basket corresponding in Fig. 3 is engaged schematic diagram with suspension rod;
Fig. 4-4 is the schematic diagrams after material basket hanging corresponding in Fig. 3;
Fig. 5 is the constructional drawing of material basket suspension rod;
Fig. 6 is de-put into gear bar and suspension conveying line location diagram;
Fig. 7 is hanging pin and suspension conveying line location diagram.
In figure:
1-suspension conveying line; 2-expects basket suspension rod, 21-link plate; 3-expects basket, 31-suspension ring, 311-suspension rod, 312-pole;
32-base; The de-bar of putting into gear of 4-; 5-suspension hook, 6-expects basket feedway, and 7-hangs pin; 8-support;
1A-expects that basket is de-and hangs delivery area, 2A-upward slope delivery area, 3A-descending delivery area;
1B-expects basket hanging delivery area, and 2B-carries upward slope district, and 3B-carries descending district.
Detailed description of the invention
For making the object, technical solutions and advantages of the present invention clearly, below in conjunction with accompanying drawing, embodiment of the present invention is described further in detail.
Embodiment 1
By Fig. 1, this enforcement is described, the automatic load-release system of material basket comprises suspension conveying line 1, material basket suspension rod 2, material basket 3 and de-bar 4 of putting into gear, the upper end of material basket suspension rod 2 is connected with suspension conveying line 1, its lower end realizes lifting by suspension hook 5 and the suspension ring 31 on material basket 3, and material basket suspension rod 2 can do low-angle swing along the coupling end on its top perpendicular on its throughput direction.Suspension conveying line 1 is provided with material basket de-extension delivery area 1A, de-bar 4 of putting into gear is arranged at the below of suspension conveying line 1 by support 8, its location diagram as shown in Figure 6, and take off suspension conveying line 1 throughput direction hung in the 1A of delivery area form a horizontal sextant angle with material basket, material basket takes off the below hanging delivery area 1A and is provided with material basket feedway 6, for material conveying basket 3, material basket feedway 6 takes off with material basket the suspension conveying line 1 hung in the 1A of delivery area and be arranged in parallel, and the two is carried in the same way with same delivery speed; As shown in Figure 1, being delivered to the material basket material basket taken off in extension delivery area 1A drops down onto on material basket feedway 6, the suspension hook 5 of suspension rod 2 lower end falls in the Dai Gua district of suspension ring, and suspension hook 5 is hung with the suspension ring 31 on material basket 3 are first de-, and material basket 3 is driven by material basket feedway 6 and continues to be fed forward; When expect basket suspension rod 2 touch de-put into gear bar 4 time, because de-bar 4 of putting into gear has angle with throughput direction shape, suspension hook 5 can move towards the direction deviating from suspension ring 31 gradually, when being delivered to its end along de-bar 4 of putting into gear, suspension hook 5 shifts out the Dai Gua district of described suspension ring 31 completely, realize described material basket 3 to unload, material basket after unloading is by changing its throughput direction, material basket is carried along separate routes with material basket suspension rod, thus realize the separation of its real meaning, expect after basket unloads it is carry in turn on material basket feedway 6 due to front and back, the rear accumulation of expecting basket of unloading before and after can not causing.
The present invention connects a upward slope delivery area 2A by taking off at material basket the conveying end hanging delivery area 1A, de-bar of putting into gear wherein takes off near material basket the conveying end hanging delivery area and arranges, the material basket suspension rod 2 being delivered to upward slope delivery area 2A is driven by suspension conveying line 1 upwards to be carried, as Fig. 2-4, material basket 3 is driven by material basket feedway 6 and is fed forward, and so just achieves the travel line that is draped rapidly of the material basket suspension rod 2 after unloading and takes away.
As shown in Figure 5, the lower end of material basket suspension rod 2 of the present invention is provided with a link plate 21, the same side of link plate 21 is provided with three suspension hooks 5, one of them suspension hook is positioned at the top of link plate 21, another two suspension hooks are positioned at the bottom of link plate 21, and two suspension hooks of bottom are symmetricly set in the both sides of the suspension hook on top; When material basket 3 is hung, three suspension hooks 5 and suspension ring 31 clamping simultaneously; During material basket 3 de-extension, three suspension hooks 5 are positioned at the Dai Gua district of suspension ring 31.Suspension hook on link plate 21 of the present invention is not limited to three, also can be one or more.
Suspension ring 31 wherein comprise suspension rod 311 and pole 312, and the two ends of suspension rod 311 are fixedly connected with respectively by the base 32 of pole 312 with material basket 3, the curved or taper of suspension rod 311.The tapered structure of suspension rod 311 shown in figure.
Embodiment 2
The difference of the present embodiment and embodiment 1 is: on suspension conveying line 1, be also provided with descending delivery area 3A, and it takes off with material basket the conveying top hanging delivery area 1A and is connected, and the material basket 3 be delivered in the 3A of descending delivery area drives downward conveying by suspension conveying line 1.The setting of descending delivery area 3A can make material basket steadily enter in the de-delivery area 1A of extension of material basket to carry out de-extension.
During unloading, as shown in Figure 1, Figure 2 shown in-1 to Fig. 2-4, the material basket suspension rod 2 being hung with material basket 3 drops to certain altitude with suspension conveying line 1, when expecting that the material basket of basket suspension rod 2 lower end takes off the initiating terminal hanging delivery area 1A, material basket drops down onto on material basket feedway, now expect that the suspension hook 5 of basket suspension rod 2 lower end is hung with suspension ring 31 are de-, and be placed in the Dai Gua district of suspension ring.Then expect that basket suspension rod 2 keeps this status level to move forward with material basket 3; When putting into gear bar 4 through taking off, de-bar 4 of putting into gear will be expected that basket suspension rod 2 and vertical plane offset and be formed angle, make suspension hook 5 depart from material basket 3 completely; Finally, material basket 3 continues horizontal forward movement, and material basket suspension rod 2 upwards climbs with suspension conveying line 1, completes unloading.
Embodiment 3
On the basis of embodiment 2, as shown in Figure 3, the present invention is also provided with material basket hanging delivery area 1B on suspension conveying line 1, is provided with hanging pin 7 in material basket hanging delivery area 1B, and hanging pin 7 is arranged at below the suspension conveying line 1 in material basket hanging delivery area 1B.Material basket 3 is positioned over expects on basket feedway 6 and is positioned at immediately below material basket suspension rod 2; The material basket suspension rod 2 be delivered in material basket hanging delivery area 1B contacts with hanging pin 7, material basket suspension rod 2 is made to offset its vertical plane, as shown in Fig. 4-2 structure, material basket suspension rod now 2 be placed on the material basket of expecting on basket feedway and be separated, along with the continuation of suspension conveying line 1 is carried, material basket suspension rod 2 continues to be fed forward along hanging pin 7, when expecting that basket suspension rod 2 is delivered to its end along hanging pin 7, suspension hook 5 returns to its vertical plane, as shown in Fig. 4-3, now suspension hook 5 moves into the Dai Gua district of suspension ring 31, realizes material basket 3 and hangs.
Hanging pin 7 in above-mentioned is in circular arc or fold-line-shaped, as shown in Figure 7, it is fixedly connected with the support 8 on suspension conveying line 1, the two ends of hanging pin 7 are crossing with the vertical plane that multiple material basket suspension rod 2 is formed, the material basket suspension rod 2 entered in material basket hanging delivery area 1B is carried along hanging pin 7, realize the de-extension of suspension hook 5 and suspension ring 31 successively, hanging, namely the material basket suspension rod carried is first by its offset vertical plane, as Fig. 4-2, along with material basket suspension rod 2 is along the conveying of hanging pin 7, suspension hook 5 is gradually near suspension ring, when being delivered to the end of hanging pin 7, suspension hook 5 and suspension ring 31 are positioned at same vertical plane, suspension hook 5 is positioned at the Dai Gua district of suspension ring 31, then by changing the distance between suspension conveying line and material basket feedway 6, material basket 3 is hung up by material basket suspension rod 2.
The present invention is by connecting a conveying upward slope district 2B at the conveying end of material basket hanging delivery area 1B, hanging pin 7 is wherein arranged near the conveying top of material basket hanging delivery area 1B, the material basket suspension rod 2 being delivered to conveying upward slope district 2B drives up by suspension conveying line 1, material basket is made progressively to depart from material basket feedway, the material basket suspension rod 2 that material basket 3 after hanging is draped rapidly on travel line 1 is mentioned, realize the rapid hanging of material basket, as shown in Fig. 3 and Fig. 4-4.
Embodiment 4
On the basis of embodiment 3, the present invention is also provided with conveying descending district 3B on suspension conveying line 1, and its conveying initiating terminal hanging delivery area 1B with material basket is connected, and the material basket suspension rod 2 be delivered in conveying descending district 3B drives downward conveying by suspension conveying line 1.Carry the setting of descending district 3B that material basket suspension rod 2 can be made steadily to enter in material basket hanging delivery area 1B to hang, as shown in Fig. 3 and Fig. 4-1.
During hanging, as shown in Fig. 3, Fig. 4-1 to Fig. 4-4, the putting position of material basket 3 on material basket feedway 6 need be corresponding with material basket suspension rod 2; Material basket suspension rod 2 drops to certain altitude with suspension conveying line, and falls in material basket hanging delivery area 1B, now expects that basket suspension rod 2 offsets with vertical plane under suspension rod pin 7 acts on and forms angle; Move with the synchronous forward horizontal of material basket 3 after forming angle, after leaving hanging pin 7, material basket suspension rod 2 returns in the vertical plane identical with expecting basket 3; Finally, expect that basket suspension rod 2 upwards climbs material basket 3 mentioned.
Suspension conveying line 1 is in unloading or wait that hanging region needs suitable descending delivery area 3A, conveying descending district 3B and upward slope delivery area 2A, conveying upward slope district 2B.The height of descending delivery area 3A, conveying descending district 3B and upward slope delivery area 2A, conveying upward slope district 2B needs the height of comprehensive material basket feedway 6, material basket 3 height and material basket suspension rod 2 Design of length.
Material basket suspension rod 2 is arranged on the nylon hanger of suspension conveying line 1, with suspension conveying line shifted forward or rising, decline.
The invention described above embodiment sequence number, just to describing, does not represent the quality of embodiment.
The foregoing is only preferred embodiment of the present invention, not in order to limit the present invention, within the spirit and principles in the present invention all, any amendment done, equivalent replacement, improvement etc., all should be included within protection scope of the present invention.

Claims (8)

1. a material basket hangs uninstalling system automatically, comprise suspension conveying line (1), material basket suspension rod (2), material basket (3) and de-bar (4) of putting into gear, the upper end of described material basket suspension rod (2) is connected with described suspension conveying line (1), its lower end realizes lifting by suspension hook (5) and the suspension ring (31) on described material basket (3), described suspension conveying line (1) is provided with material basket de-extension delivery area (1A), described de-bar (4) of putting into gear is arranged at the below of described suspension conveying line (1), and form a horizontal sextant angle with de-suspension conveying line (1) throughput direction hung in delivery area (1A) of described material basket, it is characterized in that:
The de-below hanging delivery area (1A) of described material basket is provided with material basket feedway (6), described material basket feedway (6) be arranged in parallel with the de-suspension conveying line (1) hung in delivery area (1A) of described material basket, and the two synchronous transport; Being delivered to the de-described material basket hung in delivery area (1A) of described material basket drops down onto on described material basket feedway (6), described suspension hook (5) is hung with described suspension ring (31) are de-, described suspension hook (5) is positioned at the Dai Gua district of described suspension ring (31), and material basket (3) is fed forward by the driving of described material basket feedway (6); When described material basket suspension rod (2) is delivered to the end of described de-bar (4) of putting into gear along described de-bar (4) of putting into gear, described suspension hook (5) shifts out the Dai Gua district of described suspension ring (31), described material basket (3) unloading;
The de-conveying end hanging delivery area (1A) of described material basket is provided with upward slope delivery area (2A), described de-bar (4) of putting into gear is arranged near the de-conveying end hanging delivery area (1A) of described material basket, the material basket suspension rod (2) being delivered to described upward slope delivery area (2A) is driven by described suspension conveying line (1) upwards to be carried, and described material basket (3) is fed forward by the driving of described material basket feedway (6).
2. material basket according to claim 1 hangs uninstalling system automatically, it is characterized in that:
Described suspension conveying line (1) is also provided with material basket hanging delivery area (1B), hanging pin (7) is provided with in described material basket hanging delivery area (1B), described hanging pin (7) is arranged at suspension conveying line (1) below in described material basket hanging delivery area (1B), for the suspension hook (5) of described material basket suspension rod (2) lower end is offset its vertical plane, described material basket (3) is positioned over described material basket feedway (6) and goes up and be positioned at immediately below described material basket suspension rod (2); The material basket suspension rod (2) be delivered in described material basket hanging delivery area (1B) is carried along described hanging pin (7), and make described suspension hook (5) depart from the Dai Gua district of described suspension ring (31), when described material basket suspension rod (2) is delivered to the end of described hanging pin (7), described suspension hook (5) falls into the Dai Gua district of described suspension ring (31), realizes the hanging of described material basket (3).
3. material basket according to claim 2 hangs uninstalling system automatically, it is characterized in that:
Described hanging pin (7) is in circular arc or fold-line-shaped, it is fixedly connected with the support on described suspension conveying line (1), the two ends of described hanging pin (7) are crossing with the vertical plane that multiple described material basket suspension rod (2) is formed, the material basket suspension rod (2) entered in described material basket hanging delivery area (1B) is carried along described hanging pin (7), realizes the de-extension between described suspension hook (5) and described suspension ring (31) and hanging successively.
4. material basket according to claim 3 hangs uninstalling system automatically, it is characterized in that:
The conveying end of described material basket hanging delivery area (1B) is provided with conveying upward slope district (2B), described hanging pin (7) is arranged near the conveying top of described material basket hanging delivery area (1B), the material basket (3) being delivered to described conveying upward slope district (2B) is driven by described suspension conveying line (1) upwards to be carried, and described material basket (3) and described material basket feedway (6) are separated.
5. material basket according to claim 4 hangs uninstalling system automatically, it is characterized in that:
The de-conveying initiating terminal hanging delivery area (1A) of described material basket is connected with descending delivery area (3A), the conveying initiating terminal of described material basket hanging delivery area (1B) is connected with conveying descending district (3B), is delivered to the material basket (3) in described descending delivery area (3A) and the material basket be delivered in described conveying descending district (3B) is carried respectively by described suspension conveying line (1) driving downwards.
6. material basket according to claim 5 hangs uninstalling system automatically, it is characterized in that:
The bottom of described material basket suspension rod (2) is provided with a link plate (21), and described link plate (21) is provided with suspension hook described at least one (5); During described material basket (3) hanging, described suspension hook (5) and described suspension hook (5) phase clamping; When described material basket (3) taking off is hung, described suspension hook (5) is positioned at the Dai Gua district of described suspension ring (31).
7. material basket according to claim 6 hangs uninstalling system automatically, it is characterized in that:
Described suspension hook (5) arranges three, it is arranged at the same side of described link plate (21), suspension hook described in one of them is positioned at the top of described link plate (21), another two described suspension hooks are positioned at the bottom of described link plate (21), bottom two described in suspension hook be symmetricly set in the both sides of the described suspension hook on top; During described material basket (3) hanging, three described suspension hooks (5) and described suspension ring (31) clamping simultaneously; When described material basket (3) taking off is hung, three described suspension hooks (5) are positioned at the Dai Gua district of described suspension ring (31).
8. material basket according to claim 7 hangs uninstalling system automatically, it is characterized in that:
Described suspension ring (31) comprise suspension rod (311) and pole (312), the two ends of described suspension rod (311) are fixedly connected with respectively by the base (32) of described pole (312) with described material basket (3), the curved or taper of described suspension rod (311); During described material basket (3) hanging, multiple described suspension hook (5) and described suspension rod (311) clamping simultaneously; When described material basket (3) taking off is hung, multiple described suspension hook (5) is all placed in the Dai Gua district of described suspension ring (31).
CN201210585376.4A 2012-12-28 2012-12-28 A kind of material basket hangs uninstalling system automatically Expired - Fee Related CN103029980B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210585376.4A CN103029980B (en) 2012-12-28 2012-12-28 A kind of material basket hangs uninstalling system automatically

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210585376.4A CN103029980B (en) 2012-12-28 2012-12-28 A kind of material basket hangs uninstalling system automatically

Publications (2)

Publication Number Publication Date
CN103029980A CN103029980A (en) 2013-04-10
CN103029980B true CN103029980B (en) 2015-09-02

Family

ID=48017470

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210585376.4A Expired - Fee Related CN103029980B (en) 2012-12-28 2012-12-28 A kind of material basket hangs uninstalling system automatically

Country Status (1)

Country Link
CN (1) CN103029980B (en)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CH713551A1 (en) * 2017-03-07 2018-09-14 Ferag Ag Method for picking goods and picking plant for carrying out the method.
CN108945974B (en) * 2018-07-18 2020-08-04 安徽美芝制冷设备有限公司 Hanger assembly and compressor suspension system having the same
CN110623052B (en) * 2019-10-28 2022-03-18 株洲云为智能科技有限公司 Method and device for hanging poultry up and down during slaughtering
CN110841849B (en) * 2019-12-03 2020-09-01 姜勇华 Automatic spraying system for fire extinguisher bottle body
CN112173733A (en) * 2020-09-23 2021-01-05 杨杰 Rice continuous type is carried and is broken up production line
CN112551075B (en) * 2020-12-10 2022-07-22 千科(苏州)医疗科技有限公司 Flywheel casing conveying device

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB887560A (en) * 1959-07-29 1962-01-17 Stewart Gill & Company Ltd Improvements in or relating to conveyors
US4228635A (en) * 1979-01-10 1980-10-21 W. F. Altenpohl, Inc. Poultry bagging system
NL1007745C2 (en) * 1997-12-09 1999-06-10 Systemate Bv Overhead conveyor system for transporting poultry in slaughterhouse
CN201128621Y (en) * 2007-11-26 2008-10-08 天津华杰机电科技有限公司 Automatic feeding mechanism of underslung conveyor
CN202116024U (en) * 2011-05-12 2012-01-18 福建森宝食品集团股份有限公司 Butchered poultry unhooking device
CN202282995U (en) * 2011-09-29 2012-06-27 安徽华卫集团禽业有限公司 Falling device
CN203359497U (en) * 2012-12-28 2013-12-25 中国包装和食品机械总公司 Automatic material basket suspending/unloading system

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US8151973B2 (en) * 2002-11-01 2012-04-10 Kraft Foods Global Brands Llc Suspension device for linked products

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB887560A (en) * 1959-07-29 1962-01-17 Stewart Gill & Company Ltd Improvements in or relating to conveyors
US4228635A (en) * 1979-01-10 1980-10-21 W. F. Altenpohl, Inc. Poultry bagging system
NL1007745C2 (en) * 1997-12-09 1999-06-10 Systemate Bv Overhead conveyor system for transporting poultry in slaughterhouse
CN201128621Y (en) * 2007-11-26 2008-10-08 天津华杰机电科技有限公司 Automatic feeding mechanism of underslung conveyor
CN202116024U (en) * 2011-05-12 2012-01-18 福建森宝食品集团股份有限公司 Butchered poultry unhooking device
CN202282995U (en) * 2011-09-29 2012-06-27 安徽华卫集团禽业有限公司 Falling device
CN203359497U (en) * 2012-12-28 2013-12-25 中国包装和食品机械总公司 Automatic material basket suspending/unloading system

Also Published As

Publication number Publication date
CN103029980A (en) 2013-04-10

Similar Documents

Publication Publication Date Title
CN103029980B (en) A kind of material basket hangs uninstalling system automatically
CN108422164B (en) Assembling mechanism and assembling method for heat exchanger
CN103121164B (en) Automatic assembling machine of photovoltaic junction box wire bracket
CN106185150A (en) Medicated clothing storage streamline
CN206013606U (en) Medicated clothing storage streamline
CN109366118A (en) A kind of c-type card automatic setup system
CN106185149A (en) Intelligence medicated clothing storage streamline
CN109250417A (en) A kind of automatically upper apparatus of laundry
CN116853779B (en) Junction box feeding system and feeding method
CN203359497U (en) Automatic material basket suspending/unloading system
CN204917190U (en) Automatic material machine is grabbed to three -dimensional frock delivery track line
CN116967140B (en) Suspension conveying sorting device
CN219043487U (en) Wisdom commodity circulation sorting device that can sort fast for commodity circulation
CN209424859U (en) A kind of c-type card automatic setup system
CN205397987U (en) Elevator
CN109834052A (en) A kind of logistics Classification Management device
EP3003115A1 (en) Device for washing up trays
CN219384480U (en) Automatic get lifting hook of hanging system and hang and unload ware
CN210883812U (en) Coffee bean conveying trough
CN203125122U (en) Automatic assembling machine for wire bracket of photovoltaic junction box
CN209306454U (en) A kind of packed line acquisition rejecting box separation device
CN209582905U (en) Continuous discharge device
CN209740105U (en) Automatic conveying sliding line for balance ring of washing machine
CN110759027A (en) Overturning type station entering device in clothing hanging system
CN109720827A (en) A kind of fiber serialization device for discharging

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee
CP01 Change in the name or title of a patent holder

Address after: 100083 Beijing city Chaoyang District Deshengmen North Beach No. 1

Patentee after: China Packaging & Food Machinery Co., Ltd.

Address before: 100083 Beijing city Chaoyang District Deshengmen North Beach No. 1

Patentee before: China National Packaging and Food Machinery Corporation

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150902

Termination date: 20171228