The method of 500kV charged for replacement synthetic insulator
Technical field
The present invention relates to a kind of method of 500kV charged for replacement synthetic insulator.
Background technology
Leading screw due to the insulated tension pole top of charged for replacement 500kV synthetic insulator lifting lead wire used promotes and pine falls apart from limited, the operation of changing synthetic insulator of traditional 500kV electric transmission line hot-line in case of different model, length and original synthetic insulator differ greatly or too much when most adopt to have a power failure process.
Summary of the invention
The technical problem to be solved in the present invention is to provide a kind of method of 500kV charged for replacement synthetic insulator, and the method can realize charged for replacement different model, length and original synthetic insulator and differ greatly or too much synthetic insulator.
In order to solve prior art Problems existing, the technical solution used in the present invention is:
The method of 500kV charged for replacement synthetic insulator, comprises the following steps:
1. second protection device is installed: equipotential electrician enters highfield along insulated flexible ladder, is hung over by the hook of clamp buckle type secondary protector on steel tower cross-arm, and the device that will go offline is buckled on conductors on quad bundled;
2. adjustable line hanging hook is installed: tower head leading screw is arranged on steel tower cross-arm head, after adjusting insulation arm-tie and adjustable line hanging hook are assembled, adjusting insulation arm-tie is reliably connected with tower head leading screw, then is buckled on conductors on quad bundled by the equipotential electrician device that will go offline;
3. change insulator: screw or unscrew tower head leading screw to correct position, make adjustable line hanging hook bear the gravity vertically downward of conductors on quad bundled, old insulator is taken off, then leading screw is screwed or unscrews to correct position.
4. second adjustable line hanging hook is installed, tower head leading screw is adjusted to the most loose or the tightest, then the length of adjusting insulation arm-tie is regulated, make second tower head leading screw identical with the length of first adjusting insulation arm-tie with the length summation of second insulation pulling plate, and then screw or unscrew the second rhizoid thick stick, bear the gravity of conductors on quad bundled with second line hanging hook, be repeatedly used alternatingly two tower head leading screws stressed, until identical with new synthetic insulator length, i.e. installation.
The advantage that the present invention has and effect are:
The method of 500kV charged for replacement synthetic insulator of the present invention, not by tower restriction, the restriction not being subject to insulator length, can realize charged for replacement different model, length and original synthetic insulator and differ greatly or too much synthetic insulator.Multiple insulator model, multiple insulation combination form can be adapted to, two rhizoid thick sticks are without the need to simultaneously stressed, and a rhizoid thick stick is stressed, joint changed by a rhizoid thick stick, another rhizoid thick stick adjustment joint while the leading screw changing joint is again stressed, until changed, increase work efficiency.
Accompanying drawing explanation
The instrument used in the method for Fig. 1 500kV charged for replacement of the present invention synthetic insulator.
In figure: clamp buckle type secondary protector 1; Hook 11; Steel tower cross-arm 2; Go offline device 12; Conductors on quad bundled 3; Tower head leading screw 4; Adjusting insulation arm-tie 5; Adjustable line hanging hook 6; Go offline device 61; Synthetic insulator 7.
Embodiment
Below in conjunction with accompanying drawing, the invention will be further described:
As shown in Figure 1, the method for 500kV charged for replacement synthetic insulator of the present invention comprises the following steps:
1. second protection device is installed: equipotential electrician enters highfield along insulated flexible ladder, hangs on steel tower cross-arm 2 by the hook 11 of clamp buckle type secondary protector 1, and the device 12 that will go offline is buckled on conductors on quad bundled 3;
2. adjustable line hanging hook is installed: tower head leading screw 4 is arranged on steel tower cross-arm head, after adjusting insulation arm-tie 5 and adjustable line hanging hook 6 are assembled, adjusting insulation arm-tie 5 is reliably connected with tower head leading screw 4, then is buckled on conductors on quad bundled 3 by the equipotential electrician device 61 that will go offline;
3. insulator is changed: according to the length of the insulator that will change, screw or unscrew tower head leading screw to correct position, make adjustable line hanging hook bear the gravity vertically downward of conductors on quad bundled, old insulator is taken off, then leading screw is screwed or unscrews to correct position.
4. second adjustable line hanging hook is installed, tower head leading screw 4 is adjusted to the most loose or the tightest, then the length of adjusting insulation arm-tie 5 is regulated, make second tower head leading screw identical with the length of first adjusting insulation arm-tie 5 with the length summation of second insulation pulling plate, and then screw or unscrew the second rhizoid thick stick, bear the gravity of conductors on quad bundled 3 with second line hanging hook, be repeatedly used alternatingly two tower head leading screws stressed, until identical with new synthetic insulator 7 length, i.e. installation.
When short for the new insulator that will change below:
1. second protection device is installed: equipotential electrician enters highfield along insulated flexible ladder, hangs on steel tower cross-arm 2 by the hook 11 of clamp buckle type secondary protector 1, and the device 12 that will go offline is buckled on conductors on quad bundled 3, prevents wire accidental in operation.
2. adjustable line hanging hook is installed: tower head leading screw 4 is arranged on steel tower cross-arm head, after adjusting insulation arm-tie 5 and adjustable line hanging hook 6 are assembled, adjusting insulation arm-tie 5 is reliably connected with tower head leading screw 4, then is buckled on conductors on quad bundled 3 by the equipotential electrician device 61 that will go offline;
3. change insulator: screw tower head leading screw 4 to correct position, make adjustable line hanging hook 6 bear the gravity vertically downward of conductors on quad bundled 3, old insulator is taken off, then tower head leading screw 4 is threaded to the tightest.
4. second adjustable line hanging hook is installed, tower head leading screw 4 is adjusted to the most loose, then the length of adjusting insulation arm-tie 5 is regulated, make second tower head leading screw identical with the length of first adjusting insulation arm-tie with the length summation of second insulation pulling plate, and then screw second tower head leading screw, bear the gravity of conductors on quad bundled with second line hanging hook, be repeatedly used alternatingly two rhizoid thick sticks stressed, until identical with new synthetic insulator length, i.e. installation.