CN102220808A - 框架结构降梁施工方法 - Google Patents
框架结构降梁施工方法 Download PDFInfo
- Publication number
- CN102220808A CN102220808A CN 201110102125 CN201110102125A CN102220808A CN 102220808 A CN102220808 A CN 102220808A CN 201110102125 CN201110102125 CN 201110102125 CN 201110102125 A CN201110102125 A CN 201110102125A CN 102220808 A CN102220808 A CN 102220808A
- Authority
- CN
- China
- Prior art keywords
- construction
- reinforcing steel
- girder
- main beam
- main
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Landscapes
- On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
Abstract
一种框架结构降梁施工方法,它是在有主梁和次梁相交的框架结构施工中,降低主梁底的标高,使主梁底的实际标高H为主梁底设计标高h减去次梁上部主钢筋直径d1与楼板钢筋直径d2之和,然后,按以上标高支模,绑扎钢筋,次梁上部主钢筋和楼板钢筋得以相应降低,再进行框架结构现场浇灌施工。它根据主梁、次梁、楼板钢筋的直径尺寸,确定主梁底需要降低的高度;通过降低主梁的高度保证混凝土工程的质量;方法操作简便,通过简单的降低主梁底标高即可实行,简单有效;它适用范围广,存在主次梁或是其它高低梁交叉的框架结构均可使用。
Description
技术领域
本发明涉及建筑施工方法,具体是指框架结构降梁施工方法。
背景技术
传统的建筑施工方法是按照设计图纸的设计标高,由下至上支模、绑扎钢筋。因此在建筑工程框架结构中主次梁等交叉节点处,在保证主梁按设计标高支模、绑扎钢筋后,导致次梁、板钢筋的实际高度超出设计标高(参见图1),从而导致框架结构混凝土施工中经常存在楼板混凝土超厚、梁柱节点处露筋、楼板不平整等问题。
发明内容
本发明要解决的技术问题是,针对现有技术存在的缺陷,提出一种框架结构降梁施工方法,通过适当降低主梁(或是相对高的梁)高度而克服在框架结构混凝土施工中经常存在楼板混凝土超厚、梁柱节点处露筋、楼板不平整等问题;梁板柱节点施工质量可得到明显提高,同时可大大减少因板超厚带来的资源浪费及成本增加。
本发明的技术方案是,所述框架结构降梁施工方法为,在有主梁与次梁及板钢筋相交的框架结构施工中,降低主梁底的标高,使主梁底的实际标高H为主梁底设计标高h减去次梁上部主钢筋直径d1与楼板钢筋直径d2之和,即:
H = h -(d1 + d2)
然后,按以上标高支模,绑扎钢筋,次梁上部主钢筋和楼板钢筋得以相应降低,再进行框架结构现场浇灌施工。
以下对本发明做出进一步说明。
本发明方法(施工工法)主要应用于主、次梁或是其它高、低梁交叉的框架现浇结构。本申请人针对传统施工工艺存在的问题,经过研究发现主梁与次梁交叉节点处楼板超厚值恰好等于次梁钢筋直径与楼板钢筋直径之和,为此研究出采取主梁支模时梁底模板下降的施工方法,降低主梁底标高(根据楼层净高的概念,降低梁底标高并不影响楼层净高值),也就降低了主梁负筋的标高,从而给交叉节点处次梁负筋和楼板负筋预留了空间。理论分析和实践结果证明,降低主梁梁底标高30mm左右,对结构无影响。本发明解决了困扰施工单位在混凝土施工时有主次梁交叉叠合梁部位的楼板超厚、钢筋保护层达不到规范和楼层净高减小的问题。
由以上可知,本发明为一种框架结构降梁施工方法,它根据主梁、次梁、楼板钢筋的直径尺寸,确定主梁底需要降低的高度;通过降低主梁的高度保证钢筋混凝土工程的质量;方法操作简便,通过简单的降低主梁底标高即可实行,简单有效;它适用范围广,存在主次梁或是其它高低梁交叉的框架结构均可使用。
附图说明
图1是传统施工方法剖面示意图;
图2是本发明施工方法剖面示意图;
图3是本发明施工方法工艺流程图。
在图中:
1—楼板钢筋, 2—主梁, 3—次梁。
具体实施方式
参见图2,本发明框架结构降梁施工方法为,在有主梁和次梁相交的框架结构施工中,降低主梁底的标高,使主梁底的实际标高H为主梁底设计标高h减去次梁上部主钢筋直径d1与楼板钢筋直径d2之和,即:
H = h -(d1 + d2)
然后,按以上标高支模,绑扎钢筋,次梁上部主钢筋和楼板钢筋得以相应降低,再进行框架结构现场浇灌施工。
.施工工艺流程及操作要点
1.1操作要点
1.1.1 计算
通过图纸根据主、次梁及板的钢筋计算出主梁下降高度,按照计算出的高度交底给钢筋和木工班组。
1.1.2模板支撑体系施工
钢筋绑扎前全面检查模板支撑体系的稳定性,主次梁模板的标高标高和板面的平整度,以及模板拼装缝隙。只有在模板分项工程验收后方可进行楼板钢筋的绑扎。
1.1.3绑扎钢筋
1.1.3.1. 钢筋绑扎前,应先对柱筋进行调直、校正;
1.1.3.2. 按计算出主梁下降高度依次对进主梁、次梁、楼板钢筋进行绑扎,钢筋绑扎严格按规范要求进行。
1.1.4 浇筑混凝土
混凝土浇筑时注意施工缝的留置规范和振捣密实。
1.1.5 混凝土成品养护
在混凝土终凝前进行第二次抹平、收光,以保证施工质量和外观效果。及时浇水养护。
2.效益分析
本发明方法与传统的方法相比,避免了因传统施工带来的楼面超高,直接减少了楼板混凝土的用量,经计算节约了5%—10%的板混凝土用量,以总施工面积150万平方米粗略估算:150*0.12*5%*280=252万元(板厚取0.12米,混凝土单价200元/m3,混凝土节约量5%),即可间接为业主节约了252万元,经济效益显著。同时也提高了混凝土楼面的施工质量。
本方法在施工全过程处于安全、稳定、快速、优质的可控状态。实践表明,该方法应用成熟,操作简便合理,保证施工质量,经济效益和社会效益显著,具有很好的推广价值。
Claims (1)
1.一种框架结构降梁施工方法,其特征是,该方法为,在有主梁和次梁相交的框架结构施工中,降低主梁底的标高,使主梁底的实际标高H为主梁底设计标高h减去次梁上部主钢筋直径d1与楼板钢筋直径d2之和,即:
H = h —(d1 + d2)
然后,按以上标高支模,绑扎钢筋,次梁上部主钢筋和楼板钢筋得以相应降低,再进行框架结构现场浇灌施工。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201110102125 CN102220808A (zh) | 2011-04-22 | 2011-04-22 | 框架结构降梁施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201110102125 CN102220808A (zh) | 2011-04-22 | 2011-04-22 | 框架结构降梁施工方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN102220808A true CN102220808A (zh) | 2011-10-19 |
Family
ID=44777495
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN 201110102125 Pending CN102220808A (zh) | 2011-04-22 | 2011-04-22 | 框架结构降梁施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102220808A (zh) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102995910A (zh) * | 2012-12-13 | 2013-03-27 | 北京创高铁研科技发展有限公司 | 一种框架结构轴线标高控制方法 |
CN104652839A (zh) * | 2015-01-30 | 2015-05-27 | 中国矿业大学 | 一种降低钢筋混凝土框架结构高度的方法 |
CN114961276A (zh) * | 2022-06-28 | 2022-08-30 | 中国二十二冶集团有限公司 | 框架结构有梁楼板双向上层钢筋无马凳施工方法 |
-
2011
- 2011-04-22 CN CN 201110102125 patent/CN102220808A/zh active Pending
Non-Patent Citations (1)
Title |
---|
《筑龙论坛》 20100925 caiqianfu 欢迎大家讨论所谓的"降梁"问题 , * |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102995910A (zh) * | 2012-12-13 | 2013-03-27 | 北京创高铁研科技发展有限公司 | 一种框架结构轴线标高控制方法 |
CN102995910B (zh) * | 2012-12-13 | 2015-02-18 | 北京创高铁研科技发展有限公司 | 一种框架结构轴线标高控制方法 |
CN104652839A (zh) * | 2015-01-30 | 2015-05-27 | 中国矿业大学 | 一种降低钢筋混凝土框架结构高度的方法 |
CN114961276A (zh) * | 2022-06-28 | 2022-08-30 | 中国二十二冶集团有限公司 | 框架结构有梁楼板双向上层钢筋无马凳施工方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
Kannan et al. | Constructability assessment of climbing formwork systems using building information modeling | |
CN204343459U (zh) | 叠合板式混凝土剪力墙体系的女儿墙节点结构 | |
CN103470040A (zh) | 一种叠合楼板与梁的拼接方法 | |
CN206428968U (zh) | 一种钢筋桁架式无支撑模板体系 | |
CN103276893A (zh) | 新型刚性建筑模板支撑组合结构及施工方法 | |
CN204920210U (zh) | 一种异形柱木模板加固结构 | |
CN106400982A (zh) | 一种箍筋加密的装配式钢筋混凝土柱与柱拼接节点 | |
CN102966113A (zh) | 一种浅埋式钢柱脚及施工方法 | |
CN103088842A (zh) | 毛石挡土墙加固单面模板支撑系统及施工方法 | |
CN104294920B (zh) | 一种u形钢混凝土组合梁与异形钢管混凝土柱的节点组件及制备方法 | |
CN102493647B (zh) | 高层混凝土结构施工方法 | |
CN107327019A (zh) | 一种免模板现浇钢筋混凝土圈梁结构及其施工方法 | |
CN106088640A (zh) | 对既有框架结构进行抽柱改造的方法 | |
CN102220808A (zh) | 框架结构降梁施工方法 | |
CN104727446A (zh) | 一种运用在铝合金模板体系中沉降缝处大模板施工方法 | |
CN105625573A (zh) | 梁底中强度预应力筋与普通钢筋套筒连接的梁柱节点 | |
CN106088579B (zh) | 钢筋混凝土墙体模板的搭设方法 | |
CN105804426B (zh) | 砌体结构改造方法及用于砌体结构改造的托换结构 | |
CN206752693U (zh) | 一种箍筋加密的装配式钢筋混凝土柱与柱拼接节点 | |
CN108978478A (zh) | 桥梁现浇箱梁反吊支架系统及其施工方法 | |
CN204475896U (zh) | 一种新型全装配钢结构住宅 | |
CN104563496A (zh) | 一种圆柱模的施工结构 | |
CN204081090U (zh) | 一种u形钢混凝土组合梁与异形钢管混凝土柱的节点组件 | |
CN206769153U (zh) | 装配现浇组合式叠合箱网梁楼盖连接结构 | |
CN205776898U (zh) | 整体装配式钢筋混凝土剪力墙结构体系 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C12 | Rejection of a patent application after its publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20111019 |