CN101565997A - Construction method for large-area irregular floor tile - Google Patents

Construction method for large-area irregular floor tile Download PDF

Info

Publication number
CN101565997A
CN101565997A CNA2009100156979A CN200910015697A CN101565997A CN 101565997 A CN101565997 A CN 101565997A CN A2009100156979 A CNA2009100156979 A CN A2009100156979A CN 200910015697 A CN200910015697 A CN 200910015697A CN 101565997 A CN101565997 A CN 101565997A
Authority
CN
China
Prior art keywords
paving
brick
floor tile
mortar
line
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CNA2009100156979A
Other languages
Chinese (zh)
Inventor
吕强
尹晓丽
彭振宇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Qingdao Hengshengyuan Group Construction Co Ltd
Original Assignee
Qingdao Hengshengyuan Group Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Qingdao Hengshengyuan Group Construction Co Ltd filed Critical Qingdao Hengshengyuan Group Construction Co Ltd
Priority to CNA2009100156979A priority Critical patent/CN101565997A/en
Publication of CN101565997A publication Critical patent/CN101565997A/en
Pending legal-status Critical Current

Links

Landscapes

  • Road Paving Structures (AREA)

Abstract

The invention relates to a construction method for a large-area irregular floor tile. The method is characterized by comprising the following processes of base layer treatment, paving and curing, and finished product protection, wherein the base layer treatment process comprises surface layer treatment of a base layer, cake pasting and rib marking; a process for paving a combined layer comprises paving of the combined layer of a surface layer, elastic control of wires, brick arrangement for test paving, paving of a surface block material, pointing, curing and mopboard embedment; and the finished product protection process comprises cleaning and finished product protection. The method solves the problems of long construction period, high management cost, more rework, more floor tile waste, high later maintenance cost and the like in the prior construction method for the large-area irregular floor tile, and is applicable to the construction for the large-area irregular floor tile.

Description

Construction method for large-area irregular floor tile
Technical field
The present invention relates to builing industry technology construction field, a kind of specifically construction method for large-area irregular floor tile.
Background technology
At present, common large-area irregular floor tile inorganization flowing water job practices has very big deficiency, construction period is long, overhead cost are high, it is many to do over again in the work progress, the floor tile waste is many, problem such as more than the maintenance cost in the future, has both wasted resource, brings environment pollution again.
Summary of the invention
The present invention is for solving the deficiency that exists in the present construction method for large-area irregular floor tile, long as the construction period, overhead cost are high, it is many to do over again in the work progress, the floor tile waste is many, maintenance cost is many in the future, both wasted resource, bring problems such as environment pollution again, invent a kind of job practices of in large-area irregular floor tile, using.
The present invention is for solving the problems of the technologies described above; the technical scheme of being taked is; a kind of construction method for large-area irregular floor tile; its special character is to comprise base treatment, paving maintenance, finished product protection; the base treatment activities comprises basic unit's aspect processing, pastes cake and mark muscle; smear shop setting course activities comprise smear paving layer setting course, play control line, row's brick examination shop, the paving of face piece material, jointing, maintenance, edge subsides baseboard, the finished product protection activities comprises cleaning, finished product protection.
1, base treatment
(1) basic unit's aspect is handled
Earlier the floating ash in the basic unit, land ash, foreign material etc. and weed out with chisel, with wire brush, broom that the surface dust cleaning is clean again, the various holes of flooring slit should be in advance to irritate packing with pea gravel concreten real, and leakproof phenomenon on inspection.The compressive strength of cement class basic unit is not less than 1.2Mpa.
(2) paste cake and mark muscle
According to the metope bullet good+the 500mm reference line, eject above ground structure absolute altitude line and skirting top curve, do ash cake around then in the room.The thickness of the low institute's paving brick of ash cake surface ratio surface structures absolute altitude line is pressed ash cake mark muscle again.Between bathe in the lavatory, kitchen and balcony ceramic tile floor tile brick face be than the low 20mm of floor ground building absolute altitude line, and does radial mark muscle from floor drain and drain hole direction, the gradient adheres to specification.Stair step, bullet be substep tooth angle line well, carries out step level kickplate and pedal ash cake.
2, smear the shop setting course
(1) smears paving layer setting course
Basic unit waters moistening before the setting course mortar of shop, the lean concrete grout that to brush water/binder ratio be 0.4-0.5, with brushing: the dry mortar of rough sand=1: 3 (volume ratio) (consistency of mortar must be controlled at about 30mm) with laying cement, according to mark muscle absolute altitude, mortar is made real strickling with floating rule, scrape one time with long floating rule is logical, wood float is rubbed with the hands flat again.Detect planeness and backguy then and measure absolute altitude and flashing, after adhering to specification, be twisted into hair side with wood float.Floating (pedal) in facade (kickplate) back smeared in stair step earlier.As because of adjusting the step level, it is plastered when thicker, and pressure is smeared in layering, must not once survive.The skirting bottom is smeared cement mortar.
(2) play control line
Contrast center line (cross hairs) stitches size according to staying of row brick figure and floor tile, ejects control line and frame bar on basic unit ground.By design the pattern requirement is arranged, eject the pattern position line, carry out mark, and check, with error protection through preliminary examination.
(3) row's brick examination shop
Row is during brick, perpendicular to the floor tile symmetric arrays of doorway direction, when examination row is last when non-full sized brick occurring, non-full sized brick and a full sized brick size sum divided equally cuts into two big bats, and symmetry comes both sides.The direction parallel with the doorway, when the doorway was full sized brick, a most inboard brick, was divided equally the most inboard non-full sized brick and doorway full sized brick size addition on doorway and the most inboard in the time can not satisfying greater than bat (or greater than 200mm).During the close joint paving, stitch the wide 1mm that is not more than.Try the shop according to the construction drawing, after the examination shop meets the requirements, carry out formal paving.Take the logical row of whole layer, local whole row, row's brick mode that computer composition and actual examination row combine.
(4) face piece material paving
Soak brick.After the fragment of brick that apolegamy is good cleans up, put into clear water and soak after 2-3 hour, taking-up is dried standby.Tile work.The order of tile work is as follows: spread positioning belt in length and breadth earlier by line, the positioning belt 15-20 piece brick of being separated by is spread the face brick in the positioning belt then, from the doorway, to the both sides paving, also can outwards move back from the lining by vertical control line and spread.Skirting is finished the back paving on ground, stair and the step first paving kickplate of marking time, back paving pedal, pedal elder generation paving reeding, the fringing part is the shop fringing earlier, during tile work, smear lean concrete grout, and press the paving of face brick control line, and no matter take which kind of paving order, several capable bricks of all first paving are done standard, to guarantee the paving quality, and use 2M guiding ruler and spirit level inspection at any time, and guarantee that the brick face is smooth, the seam lattice are straight.
(5) jointing
(general about 36 hours of summer when the mortar strength of tile work surface layer reaches 1.2MPa, after general 60 hours of winter) carry out jointing, with with the same kind of paving brick surface layer, carry out jointing with the cement of strength grade or the cement cream or the cement mortar of white cement and mineral pigment furnishing designing requirement color, jointing clear, straight, smooth smooth, the depth is consistent, and with linen-cotton the surface is wiped clean and not to be stayed residual ash for extremely.
(6) maintenance
The intact 24 hours planted agents of brick surface layer paving carry out maintenance, and when summer temperature was higher, in paving maintenance and covering after intact 12 hours, curing time was no less than 7 days.
(7) edge pastes baseboard
The piece material of employing and the same kind of ground bulk, same specification, the preceding elder generation of edge subsides soaks plate moistening, and it is drenched that basic unit is watered, even brushing plain-water slurry, limit welt brush.Earlier each edge pastes a baseboard at the wall two ends, and open height should be in same horizon it on, and outstanding metope thickness should be consistent, draws logical line along stupefied on two baseboards then, inlays subsides with 1: 2 cement mortar block-by-block.The specification of baseboard should be consistent with earth material, and seam should connect with ground between plate, checks the smooth-going and vertical of baseboard when edge pastes at any time, wipes the same ground of seam way.
3, finished product protection
Should handle with care when (1) product is carried, forbid to fall and throw away, rainproof measure is taked in outdoor stacking;
(2) in the construction, floor drain, the mouth of pipe, interim sealing is in case material falls in the pipe blocking pipe;
(3) materials handling must not break doorframe or metope.In ground, stair, the step construction, interim sealing, inaccurate upward people;
(4) forbid on the ground of having completed mix mortar or stack material.Forbid in the Ground Operation to adopt " the pulp sweeping cementation of fissures ", in order to avoid pollute the floor;
Use backing plate when (5) cutting face brick, forbid cutting on the floor file face;
(6) rationally arrange sequence of construction, water power, ventilation, equipment installation etc. are fulfiled ahead of schedule, prevent to damage face brick;
(7) take and note not breaking ground when tearing shelf open, the frame leg should wrap up and the underlay flitch.
Technique effect of the present invention is to adopt above-mentioned technical scheme:
One, ground construction duration weak point, the overhead cost of minimizing personnel, plant equipment reduce construction costs;
Two, easy construction by shifting to an earlier date pre-control, has reduced and has done over again;
Three, adopt advanced computer composition technology and actual examination to arrange the technology that combines, avoided the wasting phenomenon of irregular place floor tile effectively, obtained favorable economic benefit;
Four, for the floor tile construction provides sufficient quality assurance, reduced maintenance work in the future.
The specific embodiment
Below in conjunction with the example of library, Chinese Marine University Laoshan school district engineering, the present invention is further described.
This invention is as follows in the implementation process of library, Chinese Marine University Laoshan school district engineering:
1, base treatment
(1) basic unit's aspect is handled
Earlier the floating ash in the basic unit, land ash, foreign material etc. and weed out with chisel, with wire brush, broom that the surface dust cleaning is clean again, the various holes of flooring slit should be in advance to irritate packing with pea gravel concreten real, and leakproof phenomenon on inspection.
(2) paste cake and mark muscle
According to the metope bullet good+the 500mm reference line, eject above ground structure absolute altitude line and skirting top curve, do ash cake around then in the room.Ash cake mark muscle should be pressed again than the thickness of the low institute's paving brick of surface structures absolute altitude line in the ash cake surface.Should build the low 20mm of absolute altitude line than floor ground with balcony ceramic tile floor tile brick face between bathe in the lavatory, and do radial mark muscle from floor drain and drain hole direction, the gradient should adhere to specification.Stair step, bullet be substep tooth angle line well, carries out step level kickplate and pedal ash cake.
2, smear the shop setting course
(1) smears paving layer setting course
Basic unit should water moistening before the setting course mortar of shop, the lean concrete grout that to brush water/binder ratio be 0.4-0.5, with brushing: the dry mortar of rough sand=1: 3 (volume ratio) (consistency of mortar must be controlled at about 30mm) with laying cement, according to mark muscle absolute altitude, mortar is made real strickling with floating rule, scrape one time with long floating rule is logical, wood float is rubbed with the hands flat again.Detect planeness and backguy then and measure absolute altitude and flashing, after adhering to specification, be twisted into hair side with wood float.Floating (pedal) in facade (kickplate) back smeared in stair step earlier.The skirting bottom is smeared cement mortar.
(2) play control line
Contrast center line (cross hairs) stitches size according to staying of row brick figure and floor tile, ejects control line and frame bar on basic unit ground.According to design the pattern requirement is arranged, eject the pattern position line, carry out mark, and check, with error protection through preliminary examination.
(3) row's brick examination shop
Row is during brick, perpendicular to the floor tile symmetric arrays of doorway direction, when examination row is last when non-full sized brick occurring, non-full sized brick and a full sized brick size sum should be divided equally and cuts into two big bats, and symmetry comes both sides.The direction parallel with the doorway, when the doorway was full sized brick, a most inboard brick should in the time can not satisfying, be divided equally the most inboard non-full sized brick and doorway full sized brick size addition on doorway and the most inboard greater than bat (or greater than 200mm).During the close joint paving, stitch the wide 1mm that is not more than.Try the shop according to the construction drawing, after the examination shop meets the requirements, carry out formal paving.Take the logical row of whole layer, local whole row, row's brick mode that computer composition and actual examination row combine.
(4) face piece material paving
Soak brick.After the fragment of brick that apolegamy is good cleans up, after putting into clear water and soaking 2-3h, take out dry standby.Tile work.The order of tile work is as follows: spread positioning belt in length and breadth earlier by line, the positioning belt 15-20 piece brick of being separated by is spread the face brick in the positioning belt, then from the doorway, to the both sides paving.Skirting is finished the back paving on ground, stair and the step first paving kickplate of marking time, back paving pedal, pedal elder generation paving reeding, the fringing part is the shop fringing earlier, during tile work, should smear lean concrete grout, and press the paving of face brick control line, and no matter take which kind of paving order, several capable bricks of all first paving are done standard, to guarantee the paving quality, and use 2M guiding ruler and spirit level inspection at any time, and guarantee that the brick face is smooth, the seam lattice are straight.
(5) jointing
Jointing: (general about 36 hours of summer when the mortar strength of tile work surface layer reaches 1.2MPa, after general 60 hours of winter) carry out jointing, with with the same kind of paving brick surface layer, carry out jointing with the cement of strength grade or the cement cream or the cement mortar of white cement and mineral pigment furnishing designing requirement color, jointing clear, straight, smooth smooth, the depth is consistent, and with linen-cotton the surface is wiped clean and not to be stayed residual ash for extremely.
(6) maintenance
Maintenance: the intact 24 hours planted agents of brick surface layer paving carry out maintenance, when summer temperature is higher, should be in paving maintenance and covering after intact 12 hours, and curing time is no less than 7 days.
(7) edge pastes baseboard
The piece material of employing and the same kind of ground bulk, same specification, the preceding elder generation of edge subsides soaks plate moistening, and it is drenched that basic unit is watered, even brushing plain-water slurry, limit welt brush.Earlier each edge pastes a baseboard at the wall two ends, and open height is in same horizon it on, and outstanding metope consistency of thickness draws logical line along stupefied on two baseboards then, inlays subsides with 1: 2 cement mortar block-by-block.The specification of baseboard is consistent with earth material, and seam and ground connect between plate, checks the smooth-going and vertical of baseboard when edge pastes at any time, wipes the same ground of seam way.
3, finished product protection
Handle with care when (1) product is carried, forbid to fall and throw away, rainproof measure is taked in outdoor stacking;
(2) in the construction, floor drain, the mouth of pipe, interim sealing is in case material falls in the pipe blocking pipe;
(3) materials handling must not break doorframe or metope.In ground, stair, the step construction, interim sealing, inaccurate upward people;
(4) forbid on the ground of having completed mix mortar or stack material.Forbid in the Ground Operation to adopt " the pulp sweeping cementation of fissures ", in order to avoid pollute the floor;
Use backing plate when (5) cutting face brick, forbid cutting on the floor file face;
(6) rationally arrange sequence of construction, water power, ventilation, equipment installation etc. are fulfiled ahead of schedule, prevent to damage face brick;
(7) take and note not breaking ground when tearing shelf open, the frame leg should wrap up and the underlay flitch.

Claims (1)

1, a kind of construction method for large-area irregular floor tile is characterized in that comprising base treatment, paving maintenance, finished product protection;
The base treatment activities comprises basic unit's aspect processing, pastes cake and mark muscle;
Smear shop setting course activities comprise smear paving layer setting course, play control line, row's brick examination shop, the paving of face piece material, jointing, maintenance, edge subsides baseboard;
The finished product protection activities comprises cleaning, finished product protection;
The base treatment activities:
Basic unit's aspect is handled:
Earlier the floating ash in the basic unit, land ash, foreign material etc. and weed out with chisel, with wire brush, broom that the surface dust cleaning is clean again, the various holes of flooring slit should be in advance to irritate packing with pea gravel concreten real, and leakproof phenomenon on inspection;
Paste cake and mark muscle:
According to the metope bullet good+the 500mm reference line, eject above ground structure absolute altitude line and skirting top curve, do ash cake around then in the room; The thickness of the low institute's paving brick of ash cake surface ratio surface structures absolute altitude line is pressed ash cake mark muscle again; Hang down 20mm with balcony ceramic tile floor tile brick face than floor ground building absolute altitude line between bathe in the lavatory, and do radial mark muscle from floor drain and drain hole direction, the gradient adheres to specification;
Smear shop setting course activities:
Smear paving layer setting course:
Basic unit waters moistening before the setting course mortar of shop, brush one time lean concrete grout, with brushing: the dry mortar of rough sand=1: 3 (volume ratio) (consistency of mortar must be controlled at about 30mm) with laying cement, according to mark muscle absolute altitude, mortar is made real strickling with floating rule, scrape one time with long floating rule is logical, wood float is rubbed with the hands flat again; Detect planeness and backguy then and measure absolute altitude and flashing, after adhering to specification, be twisted into hair side with wood float;
Play control line:
Contrast center line (cross hairs) stitches size according to staying of row brick figure and floor tile, ejects control line and frame bar on basic unit ground;
Row's brick examination shop:
Row is during brick, perpendicular to the floor tile symmetric arrays of doorway direction, when examination row is last when non-full sized brick occurring, non-full sized brick and a full sized brick size sum divided equally cuts into two big bats, and symmetry comes both sides.The direction parallel with the doorway, when the doorway was full sized brick, a most inboard brick, was divided equally the most inboard non-full sized brick and doorway full sized brick size addition on doorway and the most inboard in the time can not satisfying greater than bat (or greater than 200mm);
The paving of face piece material:
After the fragment of brick that apolegamy is good cleans up, putting into clear water soaked after 2-3 hour, taking-up is dried standby, and the order of tile work is as follows: spread positioning belt in length and breadth earlier by line, the positioning belt 15-20 piece brick of being separated by, spread the face brick in the positioning belt then, from the doorway,, also can outwards move back from the lining and spread by vertical control line to the both sides paving, skirting is finished the back paving on ground, stair and the step first paving kickplate of marking time, back paving pedal, pedal elder generation paving reeding, the fringing part is the shop fringing earlier, during tile work, smear lean concrete grout, and press the paving of face brick control line, no matter take which kind of paving order, several capable bricks of all first paving are done standard, with assurance paving quality, and use 2M guiding ruler and spirit level inspection at any time, guarantee that the brick face is smooth, the seam lattice are straight;
Jointing:
(general about 36 hours of summer when the mortar strength of tile work surface layer reaches 1.2MPa, after general 60 hours of winter) carry out jointing, with with the same kind of paving brick surface layer, carry out jointing with the cement of strength grade or the cement cream or the cement mortar of white cement and mineral pigment furnishing designing requirement color, jointing clear, straight, smooth smooth, the depth is consistent, and with linen-cotton the surface is wiped clean and not to be stayed residual ash for extremely;
Maintenance:
The intact 24 hours planted agents of brick surface layer paving carry out maintenance, and curing time is no less than 7 days;
Edge pastes baseboard:
It is moistening earlier plate to be soaked before edge pastes, and it is drenched that basic unit is watered, evenly the brushing plain-water slurry, limit welt brush, each edge pastes a baseboard earlier at the wall two ends, and open height should be in same horizon on it, and outstanding metope thickness should be consistent, draw logical line along stupefied on two baseboards then, paste with 1: 2 cement mortar block-by-block edge, the specification of baseboard should be consistent with earth material, and seam should connect with ground between plate, at any time check the smooth-going and vertical of baseboard when edge pastes, wipe the same ground of seam way.
CNA2009100156979A 2009-05-25 2009-05-25 Construction method for large-area irregular floor tile Pending CN101565997A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNA2009100156979A CN101565997A (en) 2009-05-25 2009-05-25 Construction method for large-area irregular floor tile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNA2009100156979A CN101565997A (en) 2009-05-25 2009-05-25 Construction method for large-area irregular floor tile

Publications (1)

Publication Number Publication Date
CN101565997A true CN101565997A (en) 2009-10-28

Family

ID=41282344

Family Applications (1)

Application Number Title Priority Date Filing Date
CNA2009100156979A Pending CN101565997A (en) 2009-05-25 2009-05-25 Construction method for large-area irregular floor tile

Country Status (1)

Country Link
CN (1) CN101565997A (en)

Cited By (24)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102371622A (en) * 2010-08-19 2012-03-14 上海住总工程材料有限公司 Process method for combining prefabricated member by paving ceramic tiles in advance
CN102505831A (en) * 2011-12-22 2012-06-20 深圳市深装总装饰工程工业有限公司 Construction method for paving plasters on ground and manmade stone
CN102140836B (en) * 2010-01-29 2012-10-17 华煜建设集团有限公司 Construction method of large-size floor tile
CN104404857A (en) * 2014-12-04 2015-03-11 中冶天工集团有限公司 Permeable brick paving ground and construction method
CN105926886A (en) * 2016-04-20 2016-09-07 安徽老石人石业有限公司 Marble laying technological process in building
CN106150020A (en) * 2016-07-07 2016-11-23 东莞市清爽节能材料有限公司 A kind of construction technology utilizing flowing mortar adhesively face brick
CN106284917A (en) * 2016-08-04 2017-01-04 东莞市清爽节能材料有限公司 A kind of construction technology utilizing flowable mortar adhesively face brick
CN106284953A (en) * 2016-08-15 2017-01-04 东莞市清爽节能材料有限公司 A kind of construction technology utilizing flowable mortar adhesively face brick
CN106381980A (en) * 2016-08-31 2017-02-08 刘林沂 Floor tile paving process
CN106988533A (en) * 2017-05-12 2017-07-28 中国十七冶集团有限公司 A kind of construction method of concrete staircase tiling dual side-edge wall not lattice side's centering
CN107254954A (en) * 2017-06-09 2017-10-17 北京家装云网络科技有限公司 Ground paving ceramic tile construction technology
CN107288296A (en) * 2017-07-05 2017-10-24 广州橙加科技有限公司 A kind of screed-coat based on dry mixing cement mortar and levelling technique
CN107489256A (en) * 2016-06-13 2017-12-19 宜兴市周铁镇生力钻探机械厂 A kind of large scale floor tile construction method
CN108265946A (en) * 2017-12-15 2018-07-10 夹江县盛世东方陶瓷有限公司 A kind of ceramics painting and calligraphy brick patch block method
CN108385905A (en) * 2018-02-12 2018-08-10 福建闽华防水材料工程有限公司 A kind of foam concrete roofing gets the construction method for looking for slope ready
CN109488004A (en) * 2018-11-08 2019-03-19 广东省第建筑工程有限公司 A kind of smooth concrete surface ceramic tile ungauged regions sticking construction method
CN109736518A (en) * 2018-12-30 2019-05-10 中铁十四局集团有限公司 Interior decoration construction method
CN109736534A (en) * 2018-12-30 2019-05-10 中铁十四局集团有限公司 Flooring construction method
CN109838065A (en) * 2019-03-16 2019-06-04 北京金碧合力建筑设计工程有限公司 A kind of ground brick flooring paving construction method
CN110130642A (en) * 2019-05-27 2019-08-16 西安市鑫龙建筑装饰工程(集团)有限公司 A kind of stone floor construction technology
CN110306404A (en) * 2019-07-10 2019-10-08 上海建为历保科技股份有限公司 A kind of colored street floor file construction method
CN110424204A (en) * 2019-08-08 2019-11-08 江苏山水环境建设集团股份有限公司 Large Square pavement construction method based on BIM technology
CN111335604A (en) * 2020-03-10 2020-06-26 广东博智林机器人有限公司 Working device of leveling robot and leveling robot
CN113833232A (en) * 2021-09-18 2021-12-24 广东贝林建筑设计有限公司 Marble ground construction process

Cited By (27)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102140836B (en) * 2010-01-29 2012-10-17 华煜建设集团有限公司 Construction method of large-size floor tile
CN102371622A (en) * 2010-08-19 2012-03-14 上海住总工程材料有限公司 Process method for combining prefabricated member by paving ceramic tiles in advance
CN102505831A (en) * 2011-12-22 2012-06-20 深圳市深装总装饰工程工业有限公司 Construction method for paving plasters on ground and manmade stone
CN102505831B (en) * 2011-12-22 2014-01-08 深圳市深装总装饰工程工业有限公司 Construction method for paving plasters on ground and manmade stone
CN104404857A (en) * 2014-12-04 2015-03-11 中冶天工集团有限公司 Permeable brick paving ground and construction method
CN104404857B (en) * 2014-12-04 2016-08-31 中冶天工集团有限公司 A kind of permeable tile work ground and construction method
CN105926886A (en) * 2016-04-20 2016-09-07 安徽老石人石业有限公司 Marble laying technological process in building
CN107489256A (en) * 2016-06-13 2017-12-19 宜兴市周铁镇生力钻探机械厂 A kind of large scale floor tile construction method
CN106150020A (en) * 2016-07-07 2016-11-23 东莞市清爽节能材料有限公司 A kind of construction technology utilizing flowing mortar adhesively face brick
CN106284917A (en) * 2016-08-04 2017-01-04 东莞市清爽节能材料有限公司 A kind of construction technology utilizing flowable mortar adhesively face brick
CN106284953A (en) * 2016-08-15 2017-01-04 东莞市清爽节能材料有限公司 A kind of construction technology utilizing flowable mortar adhesively face brick
CN106381980A (en) * 2016-08-31 2017-02-08 刘林沂 Floor tile paving process
CN106381980B (en) * 2016-08-31 2019-02-26 刘林沂 A kind of ground tile paving technique
CN106988533A (en) * 2017-05-12 2017-07-28 中国十七冶集团有限公司 A kind of construction method of concrete staircase tiling dual side-edge wall not lattice side's centering
CN107254954A (en) * 2017-06-09 2017-10-17 北京家装云网络科技有限公司 Ground paving ceramic tile construction technology
CN107288296A (en) * 2017-07-05 2017-10-24 广州橙加科技有限公司 A kind of screed-coat based on dry mixing cement mortar and levelling technique
CN108265946A (en) * 2017-12-15 2018-07-10 夹江县盛世东方陶瓷有限公司 A kind of ceramics painting and calligraphy brick patch block method
CN108385905A (en) * 2018-02-12 2018-08-10 福建闽华防水材料工程有限公司 A kind of foam concrete roofing gets the construction method for looking for slope ready
CN109488004A (en) * 2018-11-08 2019-03-19 广东省第建筑工程有限公司 A kind of smooth concrete surface ceramic tile ungauged regions sticking construction method
CN109736518A (en) * 2018-12-30 2019-05-10 中铁十四局集团有限公司 Interior decoration construction method
CN109736534A (en) * 2018-12-30 2019-05-10 中铁十四局集团有限公司 Flooring construction method
CN109838065A (en) * 2019-03-16 2019-06-04 北京金碧合力建筑设计工程有限公司 A kind of ground brick flooring paving construction method
CN110130642A (en) * 2019-05-27 2019-08-16 西安市鑫龙建筑装饰工程(集团)有限公司 A kind of stone floor construction technology
CN110306404A (en) * 2019-07-10 2019-10-08 上海建为历保科技股份有限公司 A kind of colored street floor file construction method
CN110424204A (en) * 2019-08-08 2019-11-08 江苏山水环境建设集团股份有限公司 Large Square pavement construction method based on BIM technology
CN111335604A (en) * 2020-03-10 2020-06-26 广东博智林机器人有限公司 Working device of leveling robot and leveling robot
CN113833232A (en) * 2021-09-18 2021-12-24 广东贝林建筑设计有限公司 Marble ground construction process

Similar Documents

Publication Publication Date Title
CN101565997A (en) Construction method for large-area irregular floor tile
CN103321442A (en) Self-compensating repair structure and process for internal stress cracking of inner wall heat insulating wall surface
CN107254954A (en) Ground paving ceramic tile construction technology
Chew Maintainability of Facilities: Green FM for Building Professionals Second Edition
CN105399389A (en) Building inner wall whitewashing gypsum and process flow thereof
CN102400525B (en) Thin-layer plastering method for autoclaved aerated concrete block wall bodies
CN104120855A (en) Construction method for paving ground tile floor
CN106284998A (en) Plastering on inner walls completely spreads fiberglass gridding cloth construction method
CN112267628A (en) Construction method of plastering-free system for interior wall decoration of constructional engineering
CN112681643A (en) Construction method for washing stone on outer wall surface
CN103195218B (en) Wall ceramic sand mortar external plastering construction method
CN101545269B (en) Method for rigid waterproof construction of beam and slab type basement
CN112575979A (en) Construction method of plastering waterproof mortar for building exterior wall
CN104120860A (en) Construction method for cement mortar ground leveling
CN105625650B (en) A kind of parapet of roofing flashing protective layer construction method
CN108130992A (en) Rubble plate, styrofoam and porous brick compound thermal-insulating decorative external wall construction engineering method
CN102344278B (en) Permeable crystallization type cement-based waterproof mucilage
CN102888959A (en) Method for constructing external wall by using premixed dry mortar
CN109853888A (en) A kind of historical building plucking wall surface construction technology
CN207194343U (en) The tapestry brick paving structure of autoclave aerated concrete building block exterior wall
CN103291024A (en) Novel cement-based plastering mortar construction method
CN103774696A (en) Construction process of cement-based permeable-crystallization type waterproof material
CN101586367B (en) Method for preventing decorative surfaces of ceramic tiles in shower room from leaking water
CN102094494A (en) Construction process for paving S-shaped tiles on roof with slope of more than 60 degrees
CN112408851A (en) Anti-radiation semi-permanent nano-penetration crystallization sealing compacting agent and use method thereof

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20091028