CN101435270B - Sectional butt joint operation method of high-rise columns - Google Patents
Sectional butt joint operation method of high-rise columns Download PDFInfo
- Publication number
- CN101435270B CN101435270B CN2007100481726A CN200710048172A CN101435270B CN 101435270 B CN101435270 B CN 101435270B CN 2007100481726 A CN2007100481726 A CN 2007100481726A CN 200710048172 A CN200710048172 A CN 200710048172A CN 101435270 B CN101435270 B CN 101435270B
- Authority
- CN
- China
- Prior art keywords
- pillar
- security platform
- platform
- safety
- pillars
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000000034 method Methods 0.000 title claims abstract description 16
- 210000001503 joint Anatomy 0.000 title claims abstract description 12
- 238000003466 welding Methods 0.000 claims abstract description 7
- 238000003032 molecular docking Methods 0.000 claims description 11
- 238000004364 calculation method Methods 0.000 claims 6
- 230000009977 dual effect Effects 0.000 claims 2
- 230000013011 mating Effects 0.000 claims 1
- 238000009428 plumbing Methods 0.000 claims 1
- 230000003014 reinforcing effect Effects 0.000 claims 1
- 230000009194 climbing Effects 0.000 abstract description 12
- 229910000831 Steel Inorganic materials 0.000 abstract description 4
- 239000010959 steel Substances 0.000 abstract description 4
- 238000010276 construction Methods 0.000 description 8
- 230000001681 protective effect Effects 0.000 description 4
- 238000009434 installation Methods 0.000 description 2
- 230000002093 peripheral effect Effects 0.000 description 2
- 230000011218 segmentation Effects 0.000 description 2
- 238000005097 cold rolling Methods 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
Images
Landscapes
- Ladders (AREA)
Abstract
Description
技术领域technical field
本发明涉及高工作业,尤其涉及一种高层柱子分段作业方法。The invention relates to high-rise work, in particular to a segmental work method for high-rise pillars.
背景技术Background technique
重型(高层)厂房结构中对超高超长、超宽、超重构件的吊装,所面临的施工安全技术困难是:①超长构件无法运输;②市政道路制约运输;③场地条件无法满足大型吊机站位要求造成的吊装能力制约;④构件外表不能设置过多辅助性临时设施;⑤高空作业使用频繁且拆除困难。对于以往安装此类型结构时很难满足安全可靠的技术要求。如对于某单位的冷轧厂房四管柱分段对接(长54.5米、宽4米、重113吨)的安装,采用常规的安全技术措施,考虑到因场地条件制约而导致大型吊机无法使用、市政道路运输制约等情况,只能分段安装,每段柱子需要对接焊接至设计高度,在高空焊接作业如何保证操作人员人身安全长久以来没有很好的解决办法,同时焊接设备在高空的放置也是个问题。In the hoisting of super-high, super-long, super-wide, and super-heavy components in heavy (high-rise) factory building structures, the construction safety technical difficulties faced are: ① super-long components cannot be transported; ② municipal roads restrict transportation; ③ site conditions cannot meet the needs of large cranes Restricted hoisting capacity caused by site requirements; ④ Too many auxiliary temporary facilities should not be installed on the surface of components; ⑤ High-altitude operations are frequently used and difficult to dismantle. It is difficult to meet the safe and reliable technical requirements when installing this type of structure in the past. For example, for the installation of the segmental butt joint of four pipe columns (54.5 meters in length, 4 meters in width, and 113 tons in weight) in a cold rolling plant of a certain unit, conventional safety technical measures are adopted, considering that large cranes cannot be used due to site conditions , Municipal road transportation constraints, etc., can only be installed in sections, and each column needs to be butt-welded to the design height. How to ensure the personal safety of operators in high-altitude welding operations has not been a good solution for a long time. At the same time, welding equipment is placed at high altitude. Also a problem.
发明内容Contents of the invention
本发明旨在解决上述问题,提供一种高层柱子分段对接作业方法。本发明的作业平台对于安全技术措施而言确实是一种可行性强的方案,不仅简单科学,而且实用、方便。高层构件必须分段对接而安全措施制定困难情况下实现施工人员从地面至高空对接操作点的安全通廊,灵活、可操作性强、安全快捷,以达到节约资源。The present invention aims to solve the above problems, and provides a segmented butt joint operation method for high-rise columns. The working platform of the present invention is indeed a highly feasible solution for safety technical measures, which is not only simple and scientific, but also practical and convenient. High-rise components must be docked in sections and safety measures are difficult to formulate to realize a safe corridor for construction personnel to connect from the ground to the high-altitude docking operation point, which is flexible, operable, safe and fast, so as to save resources.
本发明是这样实现的:一种高层柱子分段对接方法;它包括若干对带有吊耳的双管柱柱子,它包括下列步骤:The present invention is realized like this: a kind of high-rise column segmental docking method; It comprises several pairs of double-pipe column columns with lifting lugs, and it comprises the following steps:
步骤一,在若干柱子的表面,自下而上地沿长度方向通长设置钢筋直爬梯;Step 1, on the surfaces of several pillars, a steel bar straight climbing ladder is arranged along the length direction from bottom to top;
步骤二,在所述设置了直爬梯的柱子的双管的顶端设置安全平台;
步骤三,利用起吊设备,通过吊耳把设置了安全平台柱子直立设置,作业人员通过直爬梯登上安全平台;Step 3: Use the lifting equipment to set the safety platform pillars upright through the lifting lugs, and the operator boards the safety platform through the straight ladder;
步骤四,起吊未设安全平台的柱子,作业人员在安全平台台上将两段柱子对接焊接;Step 4: Lift the pillar without a safety platform, and the operator will butt weld the two sections of pillars on the safety platform;
步骤五,拆除安全平台,重复步骤二至四,完成所有高层柱子的对接工作。
所述的高层柱子分段对接方法,所述步骤一中,所述直爬梯设有相应的半圆罩状的护笼,所述护笼的两端固定连接直爬梯的两侧边,并和直爬梯共同形成一个从地面到所述安全平台间一个安全通道。In the segmented butt joint method of high-rise columns, in the first step, the straight climbing ladder is provided with a corresponding semicircular cover-shaped protective cage, and the two ends of the protective cage are fixedly connected to the two sides of the straight climbing ladder, and are connected with the straight climbing ladder. The ladders together form a safe passage from the ground to the safety platform.
所述的高层柱子分段对接方法,所述安全平台包括一平板,平板四周设有栏杆,平板中设有通孔以容纳高层柱子,平板下部靠近柱子位置设有卡板,所述步骤二中,在柱子周面上设置若干与所述卡板相应数量的卡扣,所述卡板插入卡扣从而使平台与柱子固定连接。In the segmented butt joint method of high-rise pillars, the safety platform includes a flat plate, railings are provided around the flat plate, through holes are provided in the flat plate to accommodate high-rise pillars, and clamping plates are provided at the lower part of the flat plate near the pillars. In the second step A number of buckles corresponding to the number of clamps are provided on the peripheral surface of the column, and the clamps are inserted into the buckles so that the platform and the column are fixedly connected.
所述的高空柱子分段对接方法,所述安全平台底部还设有三角支撑架,所述三角支撑架的垂杆固定在所述柱子上。In the segmented butt joint method of high-altitude pillars, a triangular support frame is provided at the bottom of the safety platform, and the vertical rods of the triangular support frame are fixed on the columns.
所述的高空柱子分段对接方法,所述步骤二中,所述安全平台下部还连接有安全网。In the segmented docking method of high-altitude pillars, in the second step, a safety net is connected to the lower part of the safety platform.
所述的高空柱子分段对接方法,所述步骤三中,在柱子孔口拉设生命绳,直接捆绑在双管柱柱子上;作业人员在摘钩、对接连接、焊接施工时均需要挂好安全带,安全带扣点在设置在人孔口处的生命绳上。In the segmented butt joint method of high-altitude columns, in the third step, a life rope is pulled at the hole of the column and directly tied to the double-pipe column; the operator needs to hang it well during unhooking, butt connection, and welding construction. Safety belt, the safety belt buckle point is arranged on the life rope at the manhole.
本发明采用的方法是采用专用临时平台,通过从设置在柱子上的护笼直爬梯,从地面开始一直到临时平台设置点,甚至到柱子顶部及吊车梁等安装频繁点,可以形成一条安全走廊。使用完成后,临时平台又可以方便拆除,便于二次利用,拆除时的方便快捷也意味着减少了安全隐患。安装和拆卸均很方便,且与柱子的通长钢筋直爬梯和护笼配套措施,形成一条快捷方便的安全走廊。在工程施工实际安全控制中,安装方便、操作灵活,降低了施工成本,起到显著效果,适用于同类型厂房高空作业频繁的吊装。The method adopted in the present invention is to use a special temporary platform, and a safety corridor can be formed by climbing the ladder directly from the protective cage set on the pillar, starting from the ground to the setting point of the temporary platform, and even to the top of the pillar and the crane beam. . After the use is completed, the temporary platform can be easily dismantled for secondary use, and the convenience and quickness of dismantling also means that potential safety hazards are reduced. It is very convenient to install and disassemble, and it forms a fast and convenient safety corridor with the supporting measures of the full-length steel bar straight climbing ladder and the protective cage of the column. In the actual safety control of engineering construction, the installation is convenient, the operation is flexible, and the construction cost is reduced.
附图说明Description of drawings
下面,结合附图对本发明作进一步的说明:Below, the present invention will be further described in conjunction with accompanying drawing:
图1为本发明的示意图;Fig. 1 is a schematic diagram of the present invention;
图2为图1中A-A剖视图。Fig. 2 is a sectional view of A-A in Fig. 1 .
具体实施方式Detailed ways
一种高层柱子分段对接方法;它包括若干对带有吊耳的双管柱柱子1,它包括下列步骤:A segmented butt joint method for high-rise columns; it includes several pairs of double-pipe column columns 1 with lifting lugs, and it includes the following steps:
步骤一,请参见图1,在若干柱子1自下而上地沿长度方向通长设置钢筋直爬梯3;所述直爬梯3设有相应的半圆罩状的护笼4,所述护笼4的两端固定连接直爬梯3的两侧边,并和直爬梯3共同形成一个从地面到柱子1顶部间一个安全通道;该通道是方便作业人员上下通行的安全防护通道。上段柱子的摘钩将通过此直爬梯来完成。Step 1, please refer to Fig. 1, in some pillars 1 from bottom to top along the length direction, the
步骤二,在所述设置了直爬梯3的柱子1的双管顶端设置安全平台2,平台的功能必须多样化,这是受柱子分段点处空间范围狭小、超高度施工作业任务多样、柱子外表不宜焊接过多功能结构等多重限制所决定的。请参见图1并结合图2,所述安全平台2包括一平板20,平板20四周设有栏杆21,平板20中设有通孔以容纳高层柱子1,平板20下部靠近柱子1位置设有三个卡板22,相应地,在柱子分段点下部周面上设置三个卡扣11,所述卡板22插入卡扣11从而与柱子1固定连接;为了保证安全平台2的稳固,所述安全平台2底部还设有三角支撑架23,所述三角支撑架23的垂杆固定在所述柱子1上;所述安全平台2下部还连接有安全网5以防止操作人员及施工设备的坠落。
步骤三,利用起吊设备通过吊耳把设置了安全平台2的柱子1直立设置,作业人员通过直爬梯3登上安全平台2;
步骤四,起吊未设安全平台的柱子1,作业人员在安全平台2上将两段柱子1对接焊接;为了保障安全,在柱子1孔口拉设生命绳,直接捆绑在双管柱柱子1上;作业人员在摘钩、对接连接、焊接施工时均需要挂好安全带,安全带扣点在设置在人孔口处的生命绳上;Step 4: Lift the column 1 without a safety platform, and the operator will butt-weld the two sections of column 1 on the
步骤五,拆除安全平台2,重复步骤二至四,完成所有柱子1的对接工作。
Claims (6)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2007100481726A CN101435270B (en) | 2007-11-13 | 2007-11-13 | Sectional butt joint operation method of high-rise columns |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2007100481726A CN101435270B (en) | 2007-11-13 | 2007-11-13 | Sectional butt joint operation method of high-rise columns |
Publications (2)
Publication Number | Publication Date |
---|---|
CN101435270A CN101435270A (en) | 2009-05-20 |
CN101435270B true CN101435270B (en) | 2012-04-04 |
Family
ID=40709890
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2007100481726A Expired - Fee Related CN101435270B (en) | 2007-11-13 | 2007-11-13 | Sectional butt joint operation method of high-rise columns |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN101435270B (en) |
Families Citing this family (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102912996B (en) * | 2012-11-19 | 2015-03-18 | 广州机施建设集团有限公司 | Steel tube concrete column high-altitude construction safety protection system |
CN104878917A (en) * | 2015-05-22 | 2015-09-02 | 中国十七冶集团有限公司 | Movable construction platform and application method thereof |
CN105971265A (en) * | 2016-05-26 | 2016-09-28 | 黄标城 | A mobile double-layer safety net device for construction scaffolding |
CN107542273B (en) * | 2016-06-24 | 2020-05-26 | 中国二十冶集团有限公司 | Core column type high-rise mast construction method |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1256344A (en) * | 1998-12-10 | 2000-06-14 | 日立工程设备建设株式会社 | Construction method for laying main beam and main beam centering adjusting device |
CN1261638A (en) * | 1999-12-30 | 2000-08-02 | 王康强 | Mounting method for high-rise building steel structure |
CN2695510Y (en) * | 2004-05-08 | 2005-04-27 | 刘志峰 | Building body assembling frame structure |
-
2007
- 2007-11-13 CN CN2007100481726A patent/CN101435270B/en not_active Expired - Fee Related
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1256344A (en) * | 1998-12-10 | 2000-06-14 | 日立工程设备建设株式会社 | Construction method for laying main beam and main beam centering adjusting device |
CN1261638A (en) * | 1999-12-30 | 2000-08-02 | 王康强 | Mounting method for high-rise building steel structure |
CN2695510Y (en) * | 2004-05-08 | 2005-04-27 | 刘志峰 | Building body assembling frame structure |
Non-Patent Citations (1)
Title |
---|
JP特开平9-112037A 1997.04.28 |
Also Published As
Publication number | Publication date |
---|---|
CN101435270A (en) | 2009-05-20 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US10329781B2 (en) | Safety barrier netting system | |
EP3147425B1 (en) | A hub | |
US9528285B2 (en) | Safety barrier netting system with rigid panel net supports and stopper mechanisms | |
CN104088397B (en) | A kind of prefabricated post and precast construction method thereof | |
AU2013212529B2 (en) | Automated formwork climbing system | |
CN104695752B (en) | Rapid rush-repair Tower System and its erection method | |
CN101435270B (en) | Sectional butt joint operation method of high-rise columns | |
CN206873307U (en) | Movable type bridge justifies pier stud work high above the ground operating platform | |
CN211689948U (en) | Suspension operation platform device for construction of suspension cable at tower part of cable-stayed bridge | |
CN106451271B (en) | A kind of cable passageway portal structure and its installation method | |
JP5152768B2 (en) | Roof structure for temporary scaffold and method for assembling structure using the same | |
CN112302320A (en) | Modular assembled scaffolding module, system and construction method for building column | |
CN206220534U (en) | The pump line support meanss of concrete pumping equipment | |
CN206283215U (en) | A kind of cable passageway portal structure | |
CN211815605U (en) | Construction device for pile column type pier tie beam and capping beam | |
CN209924407U (en) | Combined working platform for steel structure high-altitude installation | |
CN104195954B (en) | Overhead column erection without scaffolding platform and erection method thereof | |
CN110130629B (en) | A platform and method for removing rust and preventing corrosion on the inner wall of a flat-bottomed storage tank | |
CN210659342U (en) | Detachable stair face limit guard rail | |
CN201169922Y (en) | Safety device of high layer posts subsection butt-joint operation | |
CN110206298A (en) | A kind of optimization sliding-mode structure construction technology for the matrix side storehouse that misplaces | |
CN221919409U (en) | A multifunctional guide frame | |
CN216690358U (en) | Pier stud outer skeleton construction platform | |
CN217998886U (en) | Narrow space climbing platform | |
CN213171372U (en) | Light-duty assembled vertical transportation device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CP03 | Change of name, title or address |
Address after: 200941 Shanghai City, Baoshan District Road, No. four yuan, 168 Patentee after: SHANGHAI BAOYE GROUP Corp.,Ltd. Address before: 200941, four Yuan Road, Shanghai, No. 168 Patentee before: SHANGHAI BAOYE GROUP Corp.,Ltd. |
|
CP03 | Change of name, title or address | ||
CF01 | Termination of patent right due to non-payment of annual fee |