Nothing Special   »   [go: up one dir, main page]

CN101435270B - Sectional butt joint operation method of high-rise columns - Google Patents

Sectional butt joint operation method of high-rise columns Download PDF

Info

Publication number
CN101435270B
CN101435270B CN2007100481726A CN200710048172A CN101435270B CN 101435270 B CN101435270 B CN 101435270B CN 2007100481726 A CN2007100481726 A CN 2007100481726A CN 200710048172 A CN200710048172 A CN 200710048172A CN 101435270 B CN101435270 B CN 101435270B
Authority
CN
China
Prior art keywords
pillar
security platform
platform
safety
pillars
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2007100481726A
Other languages
Chinese (zh)
Other versions
CN101435270A (en
Inventor
周金国
龚卫星
钟龙发
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Baoye Group Corp Ltd
Original Assignee
Shanghai Baoye Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Baoye Group Corp Ltd filed Critical Shanghai Baoye Group Corp Ltd
Priority to CN2007100481726A priority Critical patent/CN101435270B/en
Publication of CN101435270A publication Critical patent/CN101435270A/en
Application granted granted Critical
Publication of CN101435270B publication Critical patent/CN101435270B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Ladders (AREA)

Abstract

The invention relates to high-rise operation, in particular to a high-rise column section operation method. A high-rise pillar segment butt joint method; the method comprises a plurality of pairs of double-column pillars with lifting lugs, and comprises the following steps: firstly, arranging a steel bar vertical ladder on the surfaces of a plurality of columns along the length direction from bottom to top; step two, arranging a safety platform at the top end of a double pipe of the column provided with the vertical ladder; thirdly, vertically arranging the columns provided with the safety platforms by using lifting equipment through lifting lugs, and climbing the safety platforms by operating personnel through a vertical ladder; hoisting other pillars without a safety platform, and butt-welding the two sections of pillars on the safety platform by an operator; and fifthly, detaching the safety platform, and repeating the second step to the fourth step to finish the butt joint work of all the pillars.

Description

高层柱子分段对接作业方法Sectional butt joint operation method of high-rise columns

技术领域technical field

本发明涉及高工作业,尤其涉及一种高层柱子分段作业方法。The invention relates to high-rise work, in particular to a segmental work method for high-rise pillars.

背景技术Background technique

重型(高层)厂房结构中对超高超长、超宽、超重构件的吊装,所面临的施工安全技术困难是:①超长构件无法运输;②市政道路制约运输;③场地条件无法满足大型吊机站位要求造成的吊装能力制约;④构件外表不能设置过多辅助性临时设施;⑤高空作业使用频繁且拆除困难。对于以往安装此类型结构时很难满足安全可靠的技术要求。如对于某单位的冷轧厂房四管柱分段对接(长54.5米、宽4米、重113吨)的安装,采用常规的安全技术措施,考虑到因场地条件制约而导致大型吊机无法使用、市政道路运输制约等情况,只能分段安装,每段柱子需要对接焊接至设计高度,在高空焊接作业如何保证操作人员人身安全长久以来没有很好的解决办法,同时焊接设备在高空的放置也是个问题。In the hoisting of super-high, super-long, super-wide, and super-heavy components in heavy (high-rise) factory building structures, the construction safety technical difficulties faced are: ① super-long components cannot be transported; ② municipal roads restrict transportation; ③ site conditions cannot meet the needs of large cranes Restricted hoisting capacity caused by site requirements; ④ Too many auxiliary temporary facilities should not be installed on the surface of components; ⑤ High-altitude operations are frequently used and difficult to dismantle. It is difficult to meet the safe and reliable technical requirements when installing this type of structure in the past. For example, for the installation of the segmental butt joint of four pipe columns (54.5 meters in length, 4 meters in width, and 113 tons in weight) in a cold rolling plant of a certain unit, conventional safety technical measures are adopted, considering that large cranes cannot be used due to site conditions , Municipal road transportation constraints, etc., can only be installed in sections, and each column needs to be butt-welded to the design height. How to ensure the personal safety of operators in high-altitude welding operations has not been a good solution for a long time. At the same time, welding equipment is placed at high altitude. Also a problem.

发明内容Contents of the invention

本发明旨在解决上述问题,提供一种高层柱子分段对接作业方法。本发明的作业平台对于安全技术措施而言确实是一种可行性强的方案,不仅简单科学,而且实用、方便。高层构件必须分段对接而安全措施制定困难情况下实现施工人员从地面至高空对接操作点的安全通廊,灵活、可操作性强、安全快捷,以达到节约资源。The present invention aims to solve the above problems, and provides a segmented butt joint operation method for high-rise columns. The working platform of the present invention is indeed a highly feasible solution for safety technical measures, which is not only simple and scientific, but also practical and convenient. High-rise components must be docked in sections and safety measures are difficult to formulate to realize a safe corridor for construction personnel to connect from the ground to the high-altitude docking operation point, which is flexible, operable, safe and fast, so as to save resources.

本发明是这样实现的:一种高层柱子分段对接方法;它包括若干对带有吊耳的双管柱柱子,它包括下列步骤:The present invention is realized like this: a kind of high-rise column segmental docking method; It comprises several pairs of double-pipe column columns with lifting lugs, and it comprises the following steps:

步骤一,在若干柱子的表面,自下而上地沿长度方向通长设置钢筋直爬梯;Step 1, on the surfaces of several pillars, a steel bar straight climbing ladder is arranged along the length direction from bottom to top;

步骤二,在所述设置了直爬梯的柱子的双管的顶端设置安全平台;Step 2, a safety platform is set at the top of the double pipe of the column of the straight climbing ladder;

步骤三,利用起吊设备,通过吊耳把设置了安全平台柱子直立设置,作业人员通过直爬梯登上安全平台;Step 3: Use the lifting equipment to set the safety platform pillars upright through the lifting lugs, and the operator boards the safety platform through the straight ladder;

步骤四,起吊未设安全平台的柱子,作业人员在安全平台台上将两段柱子对接焊接;Step 4: Lift the pillar without a safety platform, and the operator will butt weld the two sections of pillars on the safety platform;

步骤五,拆除安全平台,重复步骤二至四,完成所有高层柱子的对接工作。Step 5, remove the safety platform, repeat steps 2 to 4, and complete the docking work of all high-rise columns.

所述的高层柱子分段对接方法,所述步骤一中,所述直爬梯设有相应的半圆罩状的护笼,所述护笼的两端固定连接直爬梯的两侧边,并和直爬梯共同形成一个从地面到所述安全平台间一个安全通道。In the segmented butt joint method of high-rise columns, in the first step, the straight climbing ladder is provided with a corresponding semicircular cover-shaped protective cage, and the two ends of the protective cage are fixedly connected to the two sides of the straight climbing ladder, and are connected with the straight climbing ladder. The ladders together form a safe passage from the ground to the safety platform.

所述的高层柱子分段对接方法,所述安全平台包括一平板,平板四周设有栏杆,平板中设有通孔以容纳高层柱子,平板下部靠近柱子位置设有卡板,所述步骤二中,在柱子周面上设置若干与所述卡板相应数量的卡扣,所述卡板插入卡扣从而使平台与柱子固定连接。In the segmented butt joint method of high-rise pillars, the safety platform includes a flat plate, railings are provided around the flat plate, through holes are provided in the flat plate to accommodate high-rise pillars, and clamping plates are provided at the lower part of the flat plate near the pillars. In the second step A number of buckles corresponding to the number of clamps are provided on the peripheral surface of the column, and the clamps are inserted into the buckles so that the platform and the column are fixedly connected.

所述的高空柱子分段对接方法,所述安全平台底部还设有三角支撑架,所述三角支撑架的垂杆固定在所述柱子上。In the segmented butt joint method of high-altitude pillars, a triangular support frame is provided at the bottom of the safety platform, and the vertical rods of the triangular support frame are fixed on the columns.

所述的高空柱子分段对接方法,所述步骤二中,所述安全平台下部还连接有安全网。In the segmented docking method of high-altitude pillars, in the second step, a safety net is connected to the lower part of the safety platform.

所述的高空柱子分段对接方法,所述步骤三中,在柱子孔口拉设生命绳,直接捆绑在双管柱柱子上;作业人员在摘钩、对接连接、焊接施工时均需要挂好安全带,安全带扣点在设置在人孔口处的生命绳上。In the segmented butt joint method of high-altitude columns, in the third step, a life rope is pulled at the hole of the column and directly tied to the double-pipe column; the operator needs to hang it well during unhooking, butt connection, and welding construction. Safety belt, the safety belt buckle point is arranged on the life rope at the manhole.

本发明采用的方法是采用专用临时平台,通过从设置在柱子上的护笼直爬梯,从地面开始一直到临时平台设置点,甚至到柱子顶部及吊车梁等安装频繁点,可以形成一条安全走廊。使用完成后,临时平台又可以方便拆除,便于二次利用,拆除时的方便快捷也意味着减少了安全隐患。安装和拆卸均很方便,且与柱子的通长钢筋直爬梯和护笼配套措施,形成一条快捷方便的安全走廊。在工程施工实际安全控制中,安装方便、操作灵活,降低了施工成本,起到显著效果,适用于同类型厂房高空作业频繁的吊装。The method adopted in the present invention is to use a special temporary platform, and a safety corridor can be formed by climbing the ladder directly from the protective cage set on the pillar, starting from the ground to the setting point of the temporary platform, and even to the top of the pillar and the crane beam. . After the use is completed, the temporary platform can be easily dismantled for secondary use, and the convenience and quickness of dismantling also means that potential safety hazards are reduced. It is very convenient to install and disassemble, and it forms a fast and convenient safety corridor with the supporting measures of the full-length steel bar straight climbing ladder and the protective cage of the column. In the actual safety control of engineering construction, the installation is convenient, the operation is flexible, and the construction cost is reduced.

附图说明Description of drawings

下面,结合附图对本发明作进一步的说明:Below, the present invention will be further described in conjunction with accompanying drawing:

图1为本发明的示意图;Fig. 1 is a schematic diagram of the present invention;

图2为图1中A-A剖视图。Fig. 2 is a sectional view of A-A in Fig. 1 .

具体实施方式Detailed ways

一种高层柱子分段对接方法;它包括若干对带有吊耳的双管柱柱子1,它包括下列步骤:A segmented butt joint method for high-rise columns; it includes several pairs of double-pipe column columns 1 with lifting lugs, and it includes the following steps:

步骤一,请参见图1,在若干柱子1自下而上地沿长度方向通长设置钢筋直爬梯3;所述直爬梯3设有相应的半圆罩状的护笼4,所述护笼4的两端固定连接直爬梯3的两侧边,并和直爬梯3共同形成一个从地面到柱子1顶部间一个安全通道;该通道是方便作业人员上下通行的安全防护通道。上段柱子的摘钩将通过此直爬梯来完成。Step 1, please refer to Fig. 1, in some pillars 1 from bottom to top along the length direction, the straight climbing ladder 3 of steel bar is set; The two ends of the two ends are fixedly connected to the two sides of the straight climbing ladder 3, and together with the straight climbing ladder 3, a safe passage is formed from the ground to the top of the column 1; The unhooking of the upper column will be completed through this straight ladder.

步骤二,在所述设置了直爬梯3的柱子1的双管顶端设置安全平台2,平台的功能必须多样化,这是受柱子分段点处空间范围狭小、超高度施工作业任务多样、柱子外表不宜焊接过多功能结构等多重限制所决定的。请参见图1并结合图2,所述安全平台2包括一平板20,平板20四周设有栏杆21,平板20中设有通孔以容纳高层柱子1,平板20下部靠近柱子1位置设有三个卡板22,相应地,在柱子分段点下部周面上设置三个卡扣11,所述卡板22插入卡扣11从而与柱子1固定连接;为了保证安全平台2的稳固,所述安全平台2底部还设有三角支撑架23,所述三角支撑架23的垂杆固定在所述柱子1上;所述安全平台2下部还连接有安全网5以防止操作人员及施工设备的坠落。Step 2, a safety platform 2 is set at the top of the double pipes of the column 1 provided with the straight climbing ladder 3, and the functions of the platform must be diversified, which is due to the narrow space range at the column segmentation point, various super-height construction tasks, and the column The appearance should not be determined by multiple restrictions such as welding too many multifunctional structures. Please refer to Fig. 1 and in conjunction with Fig. 2, described safety platform 2 comprises a plate 20, is provided with railing 21 around plate 20, is provided with through hole in plate 20 to accommodate high-rise column 1, and plate 20 bottom is provided with three positions near column 1. Clamping plate 22, correspondingly, three buckles 11 are arranged on the lower peripheral surface of the column segmentation point, and the clamping plate 22 is inserted into the buckles 11 so as to be fixedly connected with the column 1; in order to ensure the stability of the safety platform 2, the safety The bottom of the platform 2 is also provided with a triangular support frame 23, and the vertical rod of the triangular support frame 23 is fixed on the column 1; the bottom of the safety platform 2 is also connected with a safety net 5 to prevent operators and construction equipment from falling.

步骤三,利用起吊设备通过吊耳把设置了安全平台2的柱子1直立设置,作业人员通过直爬梯3登上安全平台2;Step 3, using lifting equipment to set the pillar 1 on which the safety platform 2 is set upright through the lifting lugs, and the operator boards the safety platform 2 through the straight ladder 3;

步骤四,起吊未设安全平台的柱子1,作业人员在安全平台2上将两段柱子1对接焊接;为了保障安全,在柱子1孔口拉设生命绳,直接捆绑在双管柱柱子1上;作业人员在摘钩、对接连接、焊接施工时均需要挂好安全带,安全带扣点在设置在人孔口处的生命绳上;Step 4: Lift the column 1 without a safety platform, and the operator will butt-weld the two sections of column 1 on the safety platform 2; in order to ensure safety, a life rope is pulled at the hole of the column 1 and directly tied to the double-pipe column column 1 ;Operators need to hang up the safety belt when unhooking, butt jointing and welding construction, and the safety belt buckle point is on the life rope set at the manhole;

步骤五,拆除安全平台2,重复步骤二至四,完成所有柱子1的对接工作。Step 5, remove the safety platform 2, repeat steps 2 to 4, and complete the docking work of all columns 1.

Claims (6)

1. high layer post subsection docking calculation; It comprises some to having the dual string pillar of hanger, it is characterized in that it comprises the following steps:
Step 1 is at some pillars surface, the elongated along its length from bottom to up reinforcing bar catladder that is provided with;
Step 2 is provided with security platform on the two-tube top of the pillar that is provided with catladder;
Step 3 is utilized lifting appliance, uprightly is provided with being provided with the security platform pillar through hanger, and the operating personnel climbs up security platform through catladder;
Step 4 is lifted by crane the pillar that other does not establish security platform, and the operating personnel welds two sections pillar butt joints on the security platform platform;
Step 5 is removed security platform, and repeating step two to four is accomplished the mating operation of all pillars.
2. high layer post subsection docking calculation according to claim 1; It is characterized in that; In the said step 1; Said catladder is provided with the cage that protects of corresponding semicircle cover shape, and said right ends of protecting cage is fixedly connected the dual-side of catladder, and and catladder common form one from ground to escape way said security platform.
3. high layer post subsection docking calculation according to claim 1 is characterized in that, in the said step 2; Said security platform comprises a flat board; Be provided with railing around dull and stereotyped, be provided with through hole in the flat board to hold high-rise pillar, dull and stereotyped bottom is provided with clamp near the pillar position; The buckle of some and said clamp respective numbers is set on the pillar side face, said platform is fixedly connected with pillar thereby said clamp inserts buckle.
4. high layer post subsection docking calculation according to claim 3 is characterized in that, said security platform bottom also is provided with triangular support bracket, and the plumbing bar of said triangular support bracket is fixed on the said pillar.
5. high layer post subsection docking calculation according to claim 3 is characterized in that, in the said step 2, said security platform bottom also is connected with safety net.
6. high layer post subsection docking calculation according to claim 1 is characterized in that, in the said step 3; Draw in the pillar aperture and to establish the life rope, directly be bundled on the dual string pillar; The operating personnel all need hang up properly safety belt when decoupling device, butt joint connection, welding procedure, buckle of safety belt point is being arranged on the life rope at pillar man-hole opening place.
CN2007100481726A 2007-11-13 2007-11-13 Sectional butt joint operation method of high-rise columns Expired - Fee Related CN101435270B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2007100481726A CN101435270B (en) 2007-11-13 2007-11-13 Sectional butt joint operation method of high-rise columns

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2007100481726A CN101435270B (en) 2007-11-13 2007-11-13 Sectional butt joint operation method of high-rise columns

Publications (2)

Publication Number Publication Date
CN101435270A CN101435270A (en) 2009-05-20
CN101435270B true CN101435270B (en) 2012-04-04

Family

ID=40709890

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2007100481726A Expired - Fee Related CN101435270B (en) 2007-11-13 2007-11-13 Sectional butt joint operation method of high-rise columns

Country Status (1)

Country Link
CN (1) CN101435270B (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102912996B (en) * 2012-11-19 2015-03-18 广州机施建设集团有限公司 Steel tube concrete column high-altitude construction safety protection system
CN104878917A (en) * 2015-05-22 2015-09-02 中国十七冶集团有限公司 Movable construction platform and application method thereof
CN105971265A (en) * 2016-05-26 2016-09-28 黄标城 A mobile double-layer safety net device for construction scaffolding
CN107542273B (en) * 2016-06-24 2020-05-26 中国二十冶集团有限公司 Core column type high-rise mast construction method

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1256344A (en) * 1998-12-10 2000-06-14 日立工程设备建设株式会社 Construction method for laying main beam and main beam centering adjusting device
CN1261638A (en) * 1999-12-30 2000-08-02 王康强 Mounting method for high-rise building steel structure
CN2695510Y (en) * 2004-05-08 2005-04-27 刘志峰 Building body assembling frame structure

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1256344A (en) * 1998-12-10 2000-06-14 日立工程设备建设株式会社 Construction method for laying main beam and main beam centering adjusting device
CN1261638A (en) * 1999-12-30 2000-08-02 王康强 Mounting method for high-rise building steel structure
CN2695510Y (en) * 2004-05-08 2005-04-27 刘志峰 Building body assembling frame structure

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
JP特开平9-112037A 1997.04.28

Also Published As

Publication number Publication date
CN101435270A (en) 2009-05-20

Similar Documents

Publication Publication Date Title
US10329781B2 (en) Safety barrier netting system
EP3147425B1 (en) A hub
US9528285B2 (en) Safety barrier netting system with rigid panel net supports and stopper mechanisms
CN104088397B (en) A kind of prefabricated post and precast construction method thereof
AU2013212529B2 (en) Automated formwork climbing system
CN104695752B (en) Rapid rush-repair Tower System and its erection method
CN101435270B (en) Sectional butt joint operation method of high-rise columns
CN206873307U (en) Movable type bridge justifies pier stud work high above the ground operating platform
CN211689948U (en) Suspension operation platform device for construction of suspension cable at tower part of cable-stayed bridge
CN106451271B (en) A kind of cable passageway portal structure and its installation method
JP5152768B2 (en) Roof structure for temporary scaffold and method for assembling structure using the same
CN112302320A (en) Modular assembled scaffolding module, system and construction method for building column
CN206220534U (en) The pump line support meanss of concrete pumping equipment
CN206283215U (en) A kind of cable passageway portal structure
CN211815605U (en) Construction device for pile column type pier tie beam and capping beam
CN209924407U (en) Combined working platform for steel structure high-altitude installation
CN104195954B (en) Overhead column erection without scaffolding platform and erection method thereof
CN110130629B (en) A platform and method for removing rust and preventing corrosion on the inner wall of a flat-bottomed storage tank
CN210659342U (en) Detachable stair face limit guard rail
CN201169922Y (en) Safety device of high layer posts subsection butt-joint operation
CN110206298A (en) A kind of optimization sliding-mode structure construction technology for the matrix side storehouse that misplaces
CN221919409U (en) A multifunctional guide frame
CN216690358U (en) Pier stud outer skeleton construction platform
CN217998886U (en) Narrow space climbing platform
CN213171372U (en) Light-duty assembled vertical transportation device

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CP03 Change of name, title or address

Address after: 200941 Shanghai City, Baoshan District Road, No. four yuan, 168

Patentee after: SHANGHAI BAOYE GROUP Corp.,Ltd.

Address before: 200941, four Yuan Road, Shanghai, No. 168

Patentee before: SHANGHAI BAOYE GROUP Corp.,Ltd.

CP03 Change of name, title or address
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20120404

CF01 Termination of patent right due to non-payment of annual fee